SlideShare a Scribd company logo
LAKE MEAD WATER INTAKE NO. 3
Constructing the highest pressure tunnel in the world
to preserve drinking water supply for two million people
 Drought in the Colorado River basin
 Colorado River supplies 90% of Las Vegas’ water
1983 2013
The Situation
3
Lake Mead dropped
150 feet between
2000 and 2015
HIGH AND LOW LAKE LEVEL ELEVATIONS
Intake No. 1 Out of ServiceIntake No. 2 Out of Service
Saddle
Island
Elevation 860’
Spillway
gates
Elevation 1,000’
Hoover
Dam
Dead Pool - Elevation 897’
Spillway Gate - Elevation 1,224’
Elevation 1,050’
INTAKE NO. 3
INTAKE NO. 2
INTAKE NO. 1
Drought Impacts
 If the lake level falls below 1,050 feet:
 Intake No. 1 will be out of service
 Pumping capacity will be reduced
A new intake system is needed
to preserve existing capacity and water
quality if lake levels continue to decline.
Lake Mead Water Level Impacts
Lake Mead Intake No. 3
 Approved by SNWA Board of Directors May 2005
 Six contracts (originally), $817 Million total (est)…
Deferred Pumping Station - three major contracts
$650M estimated construction value
 Completion 2015 (2020 with Pumping Station)
Challenges
 Variable Geology:
 Hard, fractured
 Weak sedimentary
 Volcanic rock
 High tunneling pressures – 17 bar (250 psi)
 Intake Structure installed in 350 feet of water
 Intake Structure/TBM docking within a 1-ft
tolerance after 3 miles of tunneling
 Connection to existing operating intakes
Project Location
Lake Mead
Las Vegas
Exist Water
Treatment
Facility
L3P3 PUMPING STATION
Intake 3
INTAKE No. 2
CONNECTOR TUNNEL
Lake Mead Intake No. 3 Contracts
Exist Intake 1
Exist Intake 2
INTAKE No. 2 CONNECTION
& MODIFICATIONS
Lake Mead
Saddle Island
Exist Water
Treatment
Facility
Intake 3
INTAKE No. 2
CONNECTION
Exist Intake 1
Exist Intake 2
INTAKE No. 2 CONNECTION
& MODIFICATIONS
Lake Mead
Saddle Island
Vegas Tunnel Constructors (Design-Build) ~ $450M
Access Shaft
• ~ 600’ deep
• 30’ finished interior diameter
Tunnel
• Launch Chamber ~ 202’ long, 47’ W x 35’ H
• Starter Tunnel ~ 450’ long, 27’ W x 25’ H
• TBM tunnel
– 20’ finished internal diameter
– ~ 14,904’ long
– 14” concrete segmental lining
Intake Structure (elev 860)
• 96’ high
• 16’ diameter riser
• Radial inlet
Shafts & Tunnel
13
Top-Down Shaft Construction Sequence
1) Drill
2) Blast
3) Excavate
4) Map the rock face
5) Initial Support
6) Lower Form
7) Cast Concrete
Repeat…
Shaft Excavation
Completed
January 2010
TBM Assembly Chamber
TBM Chamber Excavating Top Heading – Nov 2009
TBM Assembly Chamber
Beginning of inflow in Starter Tunnel - June 28, 2010
Incursion of Unstable Ground
Tunnel Flooding
Flooding Event
June 28th – July 1st, 2010
Area of Tunnel
Inflows
Tunnel
Realignment
New Alignment
January 2011
20 Realigned Starter Tunnel viewed from Cavern – 03/29/11
Starter Tunnel
Completed
June 2011
Drilling Jumbo Truck - Hoover Dam Diversion Tunnels
http://www.usbr.gov/history/photos/dams007.jpg
Back then…
23
Tunnel Boring Machine
• 24ft Outside Diameter
• 600ft Long Trailing Gear
• Total Weight 1500 Metric Tons
• TBM was designed to be driven
in rock with water head up to
17 bar (250 psi)
• Capable of grouting and soil
improvement ahead of the face
• Machine designed and
fabricated specifically for this
project with strict cooperation
between SNWA, Design-Builder,
and Supplier (Herrenknecht)
Contract 01
TBM TRAILING / SUPPORT GEAR - 585’ long, 1500 tons
TBM
Strand Jacks Used to Handle Weight and Depth
Lowering TBM Down Shaft
27 TBM Lowering September 2011
TBM Positioned At Tunnel Face
December 27, 2011
Local Mfg. of Precast Segments
5 Segments + I keystone = Ring
30 Tunnel Segments delivered to Site
31
Segment Transport
Took a Toll on the Machine
2013 Mar 29
2013/2014 TBM Repairs
3 Repair Stops
4 foot deep niche
excavated in front of
cutterhead
36
Soft eye
41 Stainless Steel Riser Assembly
42 Stainless Steel Intake Screen
Intake Riser - Excavation
Spring 2010
44
Preparations for Excavation at lake bottom
• Additional ground investigation
• Bathymetry Survey
• Excavation and Blasting done from crane
barge
• Clam and airlift “Overburden”-15,000 CY
• Overburden was 6 ft of desert soil; very
small silt layer about 6 inch on top.
Shaped Charges
 Placed on rock surface
 7.5 kg / charge
 Placement structure
 30 ft x 30 ft
 Small blasts at surface –
Fish Scare
23,000
charges
46 Rendering of final excavation at lake bottom
Total Tremie
Concrete =
11,300 cy
February and
March 2012
Assembled Intake Structure
Conveyed to Intake Site
15 Feb 2012
Concrete Batch Plant
Concrete Transport Barge
10-ft.
ROV Intake Inspection
Cleaning Seal with ROV
Lowering Bulkhead
Piece of soft eye during hole through
59
Breakthrough on December 10, 2014
60
TBM Removal
TBM Removal
TBM Removal - Completed Apr 27, 2015
Tunnel Steam Cleaner
Remaining Milestones
Intake No. 3 Shafts & Tunnel
 Operational October 2015
 Final Completion January 2016
600
800
700
900
1100
1000
1200
1300
Intake3
Intake1
RMWTF
AMSWTF
BROF
IPS-1 IPS-2
IPS-2 Pump
Operation Limit
El. 1000
IPS-1 Pump
Operation Limit
El. 1050
Lake
Elev.
(feet
above
MSL)
Intake2
IsolationGate
L3PS
68
Low Lake Level Pumping Station
L3PS was approved by
the SNWA on
December 10, 2014
L3PS CONTRACT PACKAGES
 Mass Excavation - Design-Bid-Build
 Pumping Station - CMAR
 Underground
 Mechanical and Electrical
 Discharge Pipelines – Design-Bid-Build
 Electrical Feed & Substation – Design-Bid-Build
(by CRC)
Questions?Questions ?

More Related Content

What's hot

Dams PPT
Dams PPTDams PPT
Dams PPT
Seminar Links
 
Dams and spillways
Dams and spillwaysDams and spillways
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
Jimit Shah
 
Dam construction
Dam constructionDam construction
Dam constructionalizay41
 
Latest technology used for underwater lining of canal
Latest technology used for underwater lining of canalLatest technology used for underwater lining of canal
Latest technology used for underwater lining of canal
Shivam Mittal
 
Ailments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri LankaAilments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri Lanka
Nihal Vitharana
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
SAGAR RAUT
 
Concrete dam lecture 1
Concrete dam lecture 1Concrete dam lecture 1
Concrete dam lecture 1
Vidhi Khokhani
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
Divya Vishnoi
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
Association for Project Management
 
Vanmeerten ea XVI-ECSMGE-Paper-Final version
Vanmeerten ea XVI-ECSMGE-Paper-Final versionVanmeerten ea XVI-ECSMGE-Paper-Final version
Vanmeerten ea XVI-ECSMGE-Paper-Final versionHans van Meerten
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
Vidhi Khokhani
 
Storage head works
Storage head worksStorage head works
Storage head works
Anirudhan K M
 
Grouting
Grouting Grouting
Grouting
Chaitanya Raval
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementADFIAP
 
Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminar
Prashant Ojha
 

What's hot (20)

Ballinalack
BallinalackBallinalack
Ballinalack
 
Dams PPT
Dams PPTDams PPT
Dams PPT
 
Irrigation
IrrigationIrrigation
Irrigation
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Dam construction
Dam constructionDam construction
Dam construction
 
Latest technology used for underwater lining of canal
Latest technology used for underwater lining of canalLatest technology used for underwater lining of canal
Latest technology used for underwater lining of canal
 
Ground Treatment
Ground TreatmentGround Treatment
Ground Treatment
 
Ailments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri LankaAilments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri Lanka
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Concrete dam lecture 1
Concrete dam lecture 1Concrete dam lecture 1
Concrete dam lecture 1
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
 
Vanmeerten ea XVI-ECSMGE-Paper-Final version
Vanmeerten ea XVI-ECSMGE-Paper-Final versionVanmeerten ea XVI-ECSMGE-Paper-Final version
Vanmeerten ea XVI-ECSMGE-Paper-Final version
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
 
Storage head works
Storage head worksStorage head works
Storage head works
 
Grouting
Grouting Grouting
Grouting
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground Improvement
 
Reservoir Dam Safety
Reservoir Dam SafetyReservoir Dam Safety
Reservoir Dam Safety
 
Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminar
 

Similar to Tri State Presentation - 9-24-15

1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015
John Newquist
 
Ranjitha.S.H
Ranjitha.S.HRanjitha.S.H
Ranjitha.S.H
Ranjitha Shiravalalu
 
Schoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudySchoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case Study
Things Simplified
 
Intern PPT Presentation
Intern PPT PresentationIntern PPT Presentation
Intern PPT PresentationGilson Hogan
 
Dams and Hydraulic Structures
Dams and Hydraulic StructuresDams and Hydraulic Structures
Dams and Hydraulic Structures
MANJUNATH BORAKANAVAR
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Ishant Gautam.
 
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
riseagrant
 
2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2Ismael Vazquez, LSIT
 
Presentation1mining
Presentation1miningPresentation1mining
Presentation1mining
khaledabdelghafar
 
06 bridge
06 bridge06 bridge
06 bridge
Cida Feitosa
 
2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Control2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Controlshiqiang Ye
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
Vishweshwar Rao Narla
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
Angelo Indelicato
 
Chapter 7 dams and reservoirs
Chapter 7 dams and reservoirsChapter 7 dams and reservoirs
Chapter 7 dams and reservoirsMohammed Salahat
 
Reservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.pptReservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.ppt
muk7971
 
Dam
DamDam
CTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdfCTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdf
PramodLimbore
 

Similar to Tri State Presentation - 9-24-15 (20)

1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015
 
Ranjitha.S.H
Ranjitha.S.HRanjitha.S.H
Ranjitha.S.H
 
Schoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudySchoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case Study
 
Intern PPT Presentation
Intern PPT PresentationIntern PPT Presentation
Intern PPT Presentation
 
Dams and Hydraulic Structures
Dams and Hydraulic StructuresDams and Hydraulic Structures
Dams and Hydraulic Structures
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
 
2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2
 
Presentation1mining
Presentation1miningPresentation1mining
Presentation1mining
 
06 bridge
06 bridge06 bridge
06 bridge
 
2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Control2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Control
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
Hoover dam
Hoover damHoover dam
Hoover dam
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
Chapter 7 dams and reservoirs
Chapter 7 dams and reservoirsChapter 7 dams and reservoirs
Chapter 7 dams and reservoirs
 
coalpreppic
coalpreppiccoalpreppic
coalpreppic
 
Reservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.pptReservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.ppt
 
Dam
DamDam
Dam
 
Dams 1
Dams 1Dams 1
Dams 1
 
CTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdfCTM_tutorial3 (1).pdf
CTM_tutorial3 (1).pdf
 

Tri State Presentation - 9-24-15