Test Procedure of Transformer Testing at Site
1 Measurement of Winding Resistance.
2 Measurement of voltage ratio and check of voltage vector
relationship.
3 Measurement of Short Circuit impedance and load loss.
4 Measurement of No-load loss and current.
5 Measurement of Insulation Resistance.
6 Temperature Rise Test.
7 Measurement of capacitance and loss factor.
8 Measurement of zero-sequence impedance (s) on three-phase
transformer.
9 Measurement of Air Pressure Test.
10 Measurement of Unbalance current.
11 Magnetic balance test on three phase transformer.
12 Vaccum test.

Transformer Site test

  • 1.
    connect2vinay.wordpress.com Test Procedure ofTransformer Testing at Site 1 Measurement of Winding Resistance. 2 Measurement of voltage ratio and check of voltage vector relationship. 3 Measurement of Short Circuit impedance and load loss. 4 Measurement of No-load loss and current. 5 Measurement of Insulation Resistance. 6 Temperature Rise Test. 7 Measurement of capacitance and loss factor. 8 Measurement of zero-sequence impedance (s) on three-phase transformer. 9 Measurement of Air Pressure Test. 10 Measurement of Unbalance current. 11 Magnetic balance test on three phase transformer. 12 Vaccum test.