Transbay Transit Center                                                                         1




 Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
Transbay Transit Center                                 2




                 Presented by:


       Maritza Acosta, P.E.
 Vice President, Northern California Regional Manager


                    July 30, 2012




            Cordoba Corporation
           500 12th Street, Suite 330
             Oakland, CA 94607
Content                                                                          3




• A Little History
• Project Highlights
• Cost and Funding Sources
• Milestones Timeline
• Transbay Joint Powers Authority
• CMO Project Team
• Cordoba’s Role
• 2012 Construction Activities
• 2017: Grand Central Station of the West
                     Photo Courtesy of the San Francisco History Center, San Francisco Public Library
A Little History                                                                      4




Transbay Terminal
   1939 - 1958




                      Photos Courtesy of the San Francisco History Center, San Francisco Public Library
Project Highlights                                                                          5




 Largest public
transportation
project in the
Western US
 LEED® Gold
certification
 11 transit
systems
 45 million
passengers/year
 Over 125,000
jobs
 High Speed
Train terminal



                   Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
Cost and Funding Sources                                                                              6




 Project Cost:

     $4.2 billion


 Funding Sources:

    oLocal

    oRegional

    oState

    oFederal




                     Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
Milestones   7




 2001: TJPA Created
 2002: Senate Bill 1856
 2004: Final EIS/EIR Certified
 2005: Preliminary Engineering
 2007: Architecture
 2008: Begin Construction
 2012: CHSR Bill Signed
 2017: Phase 1
 2018: Phase 2
Cordoba’s Role                                                            8




 Subcontractor to
Turner Construction
since October 2010
 Services provided:
document control,
field engineering and
administrative
support
 Team Cordoba:
Ethan Lu and Chris
Jones




                     Photograph and data courtesy of Chris Jones, Turner Construction and the TJPA
2012 Construction Activities                                                         9




    Photographs and data courtesy of Chris Jones, Turner Construction and the TJPA
2017: Grand Central Station of the West 10




          Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
Thank you                   11




    Special Thanks to:

        Ethan Lu
       Chris Jones
      Erik Yesayan
Anna Senatore and her team

Transbay Transit Center

  • 1.
    Transbay Transit Center 1 Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
  • 2.
    Transbay Transit Center 2 Presented by: Maritza Acosta, P.E. Vice President, Northern California Regional Manager July 30, 2012 Cordoba Corporation 500 12th Street, Suite 330 Oakland, CA 94607
  • 3.
    Content 3 • A Little History • Project Highlights • Cost and Funding Sources • Milestones Timeline • Transbay Joint Powers Authority • CMO Project Team • Cordoba’s Role • 2012 Construction Activities • 2017: Grand Central Station of the West Photo Courtesy of the San Francisco History Center, San Francisco Public Library
  • 4.
    A Little History 4 Transbay Terminal 1939 - 1958 Photos Courtesy of the San Francisco History Center, San Francisco Public Library
  • 5.
    Project Highlights 5  Largest public transportation project in the Western US  LEED® Gold certification  11 transit systems  45 million passengers/year  Over 125,000 jobs  High Speed Train terminal Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
  • 6.
    Cost and FundingSources 6  Project Cost: $4.2 billion  Funding Sources: oLocal oRegional oState oFederal Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
  • 7.
    Milestones 7  2001: TJPA Created  2002: Senate Bill 1856  2004: Final EIS/EIR Certified  2005: Preliminary Engineering  2007: Architecture  2008: Begin Construction  2012: CHSR Bill Signed  2017: Phase 1  2018: Phase 2
  • 8.
    Cordoba’s Role 8  Subcontractor to Turner Construction since October 2010  Services provided: document control, field engineering and administrative support  Team Cordoba: Ethan Lu and Chris Jones Photograph and data courtesy of Chris Jones, Turner Construction and the TJPA
  • 9.
    2012 Construction Activities 9 Photographs and data courtesy of Chris Jones, Turner Construction and the TJPA
  • 10.
    2017: Grand CentralStation of the West 10 Images and Renderings Courtesy of the Transbay Joint Powers Authority www.transbaycenter.org
  • 11.
    Thank you 11 Special Thanks to: Ethan Lu Chris Jones Erik Yesayan Anna Senatore and her team