SlideShare a Scribd company logo
[1]
A
Seminar Report
on
KALI SINDH THERMAL POWER PROJECT, JHALAWAR
Submitted to:
GLOBAL TECHNICAL CAMPUS, JAIPUR
2015-16
Submitted To: . Guided by Submitted By:
Ms. EKTA SHARMA Mr. O.P. KUMAVAT & NEERAJ PATIDAR
(H.O.D.) Mr. MANISH SHRIVASTVA 4th Yr.EE
Dept.OfElectrical Engg Asst. professor EE Dept Roll No.-12EGJEE733
.
DEPARTMENT OF ELECTRICAL ENGINEERING
GLOBAL INSTITUTE OF TECHNOLOGY
JAIPUR –302022
[2]
ACKNOWLEDGEMENT
It gives me an immense pleasure to complete the training report of KALISINDH
THERMAL POWER PROJECT. I would like to express my gratitude towards the
team of KaTPP. The experience and knowledge that I have gained from KaTPP will
always be motivating and guiding factor in my career to grow as a good professional
engineer.
I would sincerely like to thank my training report guide, Mr. MANISH
SHRIVASTVA and Mr. O.P.KUMAWAT for providing me the valuable
knowledge and giving their constructive feedback.
I would also like to thank Mrs. EKTA SHARMA (HOD, Dept. of EE) for the
encouragement and their support.
NEERAJ PATIDAR
4th
Year EE
12EGJEE733
[3]
ACKNOWLEDGEMENT
It gives me an immense pleasure to complete the training report of KALISINDH
THERMAL POWER PROJECT. I would like to express my gratitude towards the team
of KaTPP. The experience and knowledge that I have gained from KaTPP will always be
motivating and guiding factor in my career to grow as a good professional engineer.
I would sincerely like to thank my training report guide, Mr. MANISH
SHRIVASTVA and Mr. O.P.KUMAWAT for providing me the valuable knowledge
and giving their constructive feedback.
I would also like to thank Mrs. EKTA SHARMA (HOD, Dept. of EE) for the
encouragement and their support.
NEERAJ PATIDAR
4th Year EE
12EGJEE733
[4]
PREFACE
In today’s world, electricity has an important role. Today Electricity contributes the
largest share to a country’s economic growth. It is the most powerful resource and has
brought industrial revolution worldwide. It has resulted in social changes too and raised
the standard of living. In India, several organizations like NHPC, NTPC, POWER GRID,
and other state electricity boards etc. are engaged in electricity generation. RRVUNL is
one of the largest among these with an honorable Contribution.
The rise in civilization is closely related to improvements in transportation and
requirement of energy that is not readily available in large quantities but is also readily
transportable. There are several source of energy in world in which thermal power plant
is also a source of energy. It give electrical energy. A very peculiar fact about electrical
energy is that neither it is directly available in nature nor it is directly used finally in this
form, yet it is so widely produced and is the most popular high grade energy.
The purpose behind training is to understand the difficult concepts in a better
way with gain of knowledge. Report starts with a brief introduction of KaTPP.
While writing the report and while i was on my training i was wondering that
Science and technology are as ever expanding field and the engineers working hard day
and night and make the life a gift for us.
NEERAJ PATIDAR
4th Year EE
12EGJEE733
[5]
CONTENTS
S.NO. TITLE PAGE NO.
 FRONT PAGE ....
 CIRTIFICATE FROM ORGANIZATION ....
1. CHAPTER 1: INTRODUCATION………...…………………………… 01-08
1. INTRODUCATION..........................................................................…...01
1.1. INTRODUCATION OVERVIEW OF KaTPP…………….......….…...03
1.2. ENERGY GENERATED IN KaTPP………...…….….……......…….. 05
1.3. PLANT OVERVIEW……………………………….…..…..…....…… 06
1.4. PRINCIPLE OF OPERATION…………….......................................... 06
1.5. THERMAL PLANT OPERATION PROCEDURE……….……....…..06
1.6. PULVERSIZED COAL FUELED POWER PLANT….………………08
2. CHAPTER 2 : COAL HANDLING PLANT (CHP)…………………… 10-11
2.1. INTODUCATION………….………………..…………………..……. 10
2.2. STAGES OF COAL HANDLING PLANT…………….…….............. 11
3. CHAPTER 3 : IMPORTANT PARTS OF THERMAL POWER
PLANT.............................................................................................................15-23
3.1. BOILER……………………………………………………..……….... 15
3.2. TURBINE………………………………….…………….……….….....16
3.3. GENERATOR………………………….……………….…………...... 19
3.4. CONDENSER…………………………..…………………………..… 21
3.5. COOLING TOWER………………………….……………………….. 21
 COLLEGE CERTIFICATE .....
 ACKNOWLEDGMENT ….
 ABSTRACT .....
 PREFACE ….
 TABLE OF CONTENTS .....
 LIST OF FIGURES ......
 LIST OF TABLES ......
[6]
3.6. WATER TREATMENT PLANT……………………...…………...…. 23
4. CHAPTER 4 : ESP AND AHP SYSTEM………………………………… 26-30
4.1. ELECTROSTATIC PRECIPITATOR (ESP)……………………….... 26
4.2. ASH HANDLING PLANT (AHP)……….…………………………....30
5. CHAPTER 5 : CONTOLLING AND TRANSMISSION SYSTEM……. 32-39
5.1. CONTOL AND INSTRUMENTATION SYSTEM………..….….….. 32
5.2. CONTROL ROOM…………………………………………………… 36
5.3. AUXILLARY SUPPLY ……………………………………………… 37
5.4. SWITCHYARD ………………………………………………...…….39
6. CHAPTER 6: EFFICIENCY AND CONCLUSION…………………………46
6.1. EFFICIENCY…………………………………………………….….... 46
CONCLUSION……………………….………………………………………….… 47
REFRENCE…………………….………………………………………………….. 48
[7]
LIST OF FIGURE
FIG.NO. FIG.NAME PAGE NO.
1. General layout : Thermal power plant 1
1.1 Percentage of electricity produced by different sectors 2
1.2 Overview of KaTPP 3
1.3 Operation principal 6
1.4 Pulverized coal fueled power plant 8
2.1 Coal handling plant 14
3.1 Boiler 15
3.2 Turbine 17
3.3 Generator 19
3..5 Cooling Tower 22
4.1 Electrostatic Precipitation Unit 30
4.2 Fly ash system 31
5.3 Switching and transmission 38
5.4 Overview of switchyard 45
LIST OF TABLE
S.NO. TITTLE PAGE NO.
1.3 Plant overview 5
2.1 Coal handling detail 11
[8]
2.2 Crusher /ring granulator Specification 12
3.2 Turbine Specification 18
3.3 Generator specification for unit i and ii 20
3.4 Diesel generator 20
ABSTRACT
A steam-electric power station is a power station in which the electric generator
is steam driven. Water is heated, turns into steam and spins a steam turbine. After it
passes through the turbine, the steam is condensed in a condenser. The greatest variation
in the design of steam-electric power plants is due to the different fuel sources.
The site of Kalisindh Thermal Power Project is located in Nimoda, Undal, Motipura,
Singhania and Devri villages of Tehsil Jhalarapatan, Distt. Jhalawar. The proposed
capacity of coal based Thermal Power Project is 1200 MW. The project site is about 12
km from Jhalawar (Distt. Head quarter ) and NH-12 .It is 2km from state highway No.19
and 8 km from proposed Ramganj Mandi - Bhopal broad gauge rail line. The site
selection committee of Central Electricity Authority has visited the Nimodha and its
adjoining villages of Jhalawar Distt. And site was found techno-economical feasible for
setting up of a Power Project. The Govt. of Raj. have included that project in 11 th five
year plan. The estimated revised cost of the project is Rs.7723 Crores. M/s. TCE
Banglore has been appointed as the technical consultant for the project. The state
irrigation department has alloted 1200 mcft water for the project from proposed
Kalisindh dam. The existing Dam is located at Bhawarasa village, primarily for P.H.E.D.
purpose is being uplifted for providing a storase of 1200mcft water for this power
project. The GOR has alloted 842 bigha Government land and aquired 1388 bigha private
khatedari land for the thermal project .Phase-1 will be constructed on 1400 bigha land
only.EPC contract has been awarded to M/s. BGR Energy System Chennai on
[9]
dt.09/07/08, through ICB route at cost Rs.4900 Crores. Ministry of coal, Govt. of India
has alloted ‘Paras east and Kanta basin ‘ coal blocks to RVUN in Chhatisgarh state. The
RVUN has formed new company under joined venture with M/s. Adani Enterprises for
mining of coal blocks and new company started the work. Annual coal requirement for
the project is 56 LacsTPA. GOR also decided to setup two new units of 2x660 MW in
next few years
[10]
CHAPTER - 1
INTRODUCATION
Everybody must be having a thought that a thermal power plant is a place where
electricity is produced. But do you know how it is produced? How the chemical energy
stored in fuel is converted into heat energy which forms the input of power plant i.e.
steam and electrical energy produced by generator? Power is the single most important
necessity for common people and industrial development of nation. In a conventional
power plant the energy is first converted to a mechanical work and then is converted to
electrical energy .Thus the energy conversions involved are:
The first energy conversion takes place in Boiler or Steam Generator, second in
Turbine and the last conversion takes place in the Generator.
A thermal power station is a power plant in which the prime mover is steam
driven. Water is heated, turns into steam and rotates the turbine which drives an electrical
generator after that steam pass through in a condenser where it condensed and recycled to
again in boiler; this whole cycle is known as RANKINE CYCLE.
Fig-1: General Layout: Thermal Power Plant
[11]
CONTRIBUTATION OF THERMAL POWER PLANT IN INDIA
In India, Thermal Power Plant contribute about 60% of the total electricity produced.
Pie chart shows the electricity production percentage by different sectors-
Power Installed Capacity = 253.390 GW
As of 31st
August 2014
Thermal
176,118.6
MW
Hydro
40,798.8
MW
Nuclear
4,780
MW
Renewable
32,307.71
MW
Total
254,005.1 MW
Fig 1.1-Percentage of Electricity Produced by Different Sectors
[12]
1.1 INTRODUCATION OVERVIEW OF KaTPP
Fig 1.2 -Overview of KaTPP
[13]
Kalisindh Thermal Power Project is located in Jhalawar. The project site is about 12 km
from Jhalawar (Distt.-Head quarter) and NH-12. Site is comprising of 5 villages viz.
Nimoda, Undal, Motipura, Singharia and Devri. It is 2km from state highway No.19 and
8 km from RamganjMandi - Bhopal broad gauge rail line
The site selection committee of Central Electricity Authority has visited the
Nimodha and its adjoining villages of Jhalawar Distt. And site was found techno-
economical feasible for setting up of a Power Project. The Govt. of Raj.have included
that project in 11thfive year plan. The estimated revised cost of the project is Rs.7723
Crores. M/s. TCE Banglore has been appointed as the technical consultant for the project.
The state irrigation department has allotted 1200 mcft water for the project from
proposed Kalisindh dam. The origin of the Kalisindh river is from northern slop of
Vindya Mountains. The river enters from MP to Rajasthan near village Binda. After
flowing 145 km in Rajasthan, the Kalisindh river merges in Chambal river near Nanera
village of Distt. Kota.Its catchment area is about 7944 sq.km in Jhalawar & Kota Distt.
The existing Dam is located at Bhawarasa village, primarily for P.H.E.D. purpose is
being uplifted for providing a storage of 1200mcft water for this power project.
The GOR has allotted 842 bigha Government land and acquired 1388 bigha private
khatedari land for the thermal project .Phase-1 will be constructed on 1400 bigha land
only.EPC contract has been awarded to M/s. BGR Energy System Chennai on
dt.09/07/08,through ICB route at cost Rs.4900Crores. Ministry of coal, Govt. of India has
allotted Paras east and Kanta basin coal blocks to RVUN in Chhattisgarh state. The
RVUN has formed new company under joined venture with M/s. Adani Enterprises for
mining of coal blocks and new company started the work. Annual coal requirement for
the project is 56 LacsTPA.GOR also decided to setup two new units of 2x660MW in
next few years.
2*600 KALISINDH THERMAL POWERP ROJECT- JHALAWAR
o OWNER -RVUNL
o OWNER’S CONSULTANT - TATA CONSULTING ENERGY LTD.
MUMBAI
o EPC - BGR ENERGY SYSTEM LTD.
o CONTRACTOR - CHENNAI
[14]
1.2 ENERGY GENERATED IN KaTPP
 Number of units=2
 Electricity generated by one unit=600 MW
 Total electricity negated by plant=2x600=1200 MW
TABLE - 1.3:PLANT OVERVIEW
Project Kalisindh Super Thermal Power Project Jhalawar
Capacity 1200MW(2x600 MW)
Project Site Village-Undel, Motipura, Nimoda, Singhania & Deveri of Tehsil
Jhalarapatan, Distt-Jhalawar
Project Location The project site is about 12 km from NH-12, 2km from state
highway and 8 km from proposed Ramganj Mandi-Bhopal broad
gauge rail line.
Land Area 2230 Bigha/564 Hq.(1400 bigha/350 Hq. in I stage)
Water Source and
quantity
Dam on Kalisindh river and 3400CuM/Hrs.
Fuel Source Main Fuel-Coal from captive coal blocks(Paras east and kanta
Basin in Chhatisgarh state) Secondary Fuel-FO/HSD
Quantity of fuel(at
80% PLF)
Coal-56 Lacs TPA FO/HSD-13000-14000 KL/A
ElectroStatic
Precipator
99.9 % Capacity
Stack Height 275 Mtr
Estimated revised
cost
Rs.7723 Crores
[15]
1.3 PRINCIPLEOF OPERATION
For each process in a vapour power cycle, it is possible to assume a hypothetical or ideal
process which represents the basis intended operation and do not produce any extraneous
effect like heat loss.
 For steam boiler, this would be a reversible constant pressure heating process of
water to form steam.
 For turbine,the ideal process would be a reversible adiabatic expansion of steam.
 For condenser, it would be a reversible a constant pressure heat rejection as the
steam condenser till it becomes saturated liquid.
 For pump, the ideal process would be the reversible adiabatic compression of
liquid ending at the initial pressure.
When all the above four cycles are combined, the cycle achieved is called RANKINE
CYCLE. Hence the working of a thermal power plant is based upon Rankine Cycle with
some modification.
Fig 1.3 – Operation principal
1.4 THERMAL PLANT OPERATION PROCEDURE
The basic understanding of the modern thermal power station in terms of major systems
involved can be done under three basic heads viz. generating steam from coal, conversion
of thermal energy to mechanical power and generation & load dispatch of electric power.
 COAL TO STEAM- The coal is burnt at the rate upto 200 tonnes per hour. From
coal stores, the fuel is carried on convey or belts to bunkers through coal tipper. It
then falls in to coal pulverizing mill, where it is grounded into powder as fine as
flour. Air is drawn into the boiler house by drought fan and passed through
[16]
Preheaters. Some air is passed directly to bunker and rest, through primary air
fan, to pulverizing mill where it is mixed with powdered coal. The mixture is then
carried to bunker of furnace where it mixes with rest of the air and burns to great
heat. This heats circulating water and produces steam, which passes to steam
drum at very high pressure. The steam is then heated further in the Superheater
and fed to high pressure cylinder of steam turbine. . The spent steam is sent to
condenser, where it turns back to water called condensate. Condensate is sent
tolower part of steam drum through feed heater and economizer. The flue gases
leaving boiler are used for heating purpose in feed heater, economizer, and air
Preheater. The flue gases are then passed to electro-static precipitator and then,
through draught fan, to chimney.
 STEAM TO MECHANICAL POWER- Steam first enters the high pressure
cylinder of turbine where it passes over a ring of stationary/fixed blades which
acts as nozzle and directs steam onto a ring of moving blades. Steam passes to the
other cylinders through reheater and the process is repeated again and again. This
rotates the turbine shaft upto 3000rpm. At each stage, steam expands, pressure
decreases and velocity increases.
 MECHANICAL POWER TO ELECTRICAL POWER- To obtained the
electrical power from mechanical power we connect the shaft to an alternator’s
armature. When the armature is rotated and electric current is produced in the
stator’s windings. The generated electricity is of order 25,000 volts.
 SWITCHING AND TRANSMISSION-The produced electricity is can’t to
transmitted as this state so It is passed to a series of three switches called an
isolator, a circuit-breaker, and another isolator. From circuit-breaker, current is
taken to bus bars and then to another circuit-breaker with it’s associated isolator
before being fed to the main Grid. Each generator has its own switching and
transmission arrangement. Three-phase system is used for power transmission.
[17]
 CONTROL AND INSTRUMENTATION- Control and Instrumentation (C & I)
systems are provided to enable the power station to be operated in a safe and
efficient manner while responding to the demands of the national grid system.
These demands have to be met without violating the safety or operational
constraints of the plants. For example, metallurgical limitations are important as
they set limits on the maximum permissible boiler metal temperature and the
chemical constituents of the Feed water. The control and Instrumentation system
provides the means of the manual and automatic control of plant operating
conditions to maintain an adequate margin from the safety and operational
constraints.
1.5 PULVERIZED COAL FUELED POWER PLANT
A typical pulverized coal fueled power plant is based on Rankine Thermodynamic cycle.
“A Rankine cycle is a vapour cycle Furnace that relies on the isentropic expansion of
high pressure gas to produce work”.Let us see a super heat Rankine cycle:
Fig1.4- Pulverized Coal Fueled Power Plant
This facility first produces steam in a boiler (steam generator). This steam is used to
rotate turbine which is connected to a shaft of generator. Hence electricity is produced
here. The used steam is then condensed in a condenser, and the condensed liquid is used
again in the steam generator. This is a simple phenomenon, understood by everybody.
For all this we need a fuel. As the name suggest here coal is used as fuel. Coal is one of
the cheapest and most preferred fossil fuel used as a key to most of the power
[18]
plants.Usually delivered by train from Mines to the Coal Handing Plant (CHP). The CHP
unloads this it become more economical to unload the coal. Then the coal stacked,
reclaimed, crushed, and conveyed it to the storage silos near the steam generator. Then it
is fed through the Feeder to the Pulverizer. Feeder is mainly used to weight the amount of
coal going to the Pulverizer per hour. From the Feeder the coal is fed to the Pulverizer
which powders it and then it is carried to the steam generator using pressurized air.
Within the steam generator the coal is atomized and burned and the heat energy produced
is used for producing steam. Here two types of steam namely superheated & reheated
steam are produced in a cycle. The steam turbine generator converts the thermal energy
of superheated and reheated steam to electrical energy. The first energy conversion is
carried in Boiler or steam generator; the second is carried out in Turbine and the last one
carried out in the Generator.
Cooling water for the condenser is supplied by the circulating water system, which takes
the heat removed from the condenser and rejects it to the cooling towers or other heat
sink. This all working is controlled from a single place called control room. It enables the
operator to direct the plant operation for reliable and efficient production of electrical
energy. This is achieved by the control system installed by the C & I group. These are
DAS (Data Acquisition System), ACS (Analog Control System), FSSS (Furnace
Safeguard Supervisory System), and other relays governing numerous activities. Last but
not the least is the switching and transmission methods used here. The generated power
cannot be transmitted as such. It is stepped up to 132 KVA or 400 KVA then passed
through a series of three switches an isolator, a circuit breaker and an isolator. Three
phase system is used for the power transmission.Each generator has its own switchyard
and transmission arrangement.
[19]
CHAPTER-2
COAL HANDLING PLANT (C.H.P.)
2.1 INTRODUCTION:
Every thermal power plant is based on steam produced on the expanse of heat energy
produced on combustion of fuel. Coal is categorized as follows depending upon fixed
carbon, volatile matter and moisture content:
 Anthracite having 86% fixed carbon
 Bituminous having 46 to 86% fixed carbon
 Lignite having 30% fixed carbon and
 Peat having 5 to 10% fixed carbon
Coal from mines is transported to CHP in railway wagons. It is unloaded in track
hoppers. Each project requires transportation of large quantity of coal mines to the power
station site. Each project is established near coal mine which meets the coal requirements
for the span of its entire operational life. For the purpose each plant has Merry Go-Round
(MGR) rail transportation system. The loading operation of the coal rake takes place
while it is moving under the silo at a present speed of 0.8 Km/hr. the loading time for
each wagon is one minute. For unloading of coal from the wagons an underground track
hopper is provided at the power station.
The term coal handling plant means to store and to handle the coal which is
transported by the train and convey to the bunkers with the help of belt conveyers.
Through the bunkers coal is transferred to the coal mill and drifted to the furnace. The
coal handling plant includes wagon tippler, conveyer belt, crusher house, stacker &
reclaimer, bunkers & coal mill.
COAL SUPPLY IN KaTPP-Ministry of coal, Govt. of India has allotted Paras east and
Kanta basin coal blocks to RVUN in Chhattisgarh state.
[20]
2.2 STAGES OF COAL HANDLING PLANT
 WAGON TIPPLER-The term Wagon Tippler contains two words WAGON &
TIPPLER .Wagon means the compartment of train which is just like a container
which is used to carry the coal from mines to generating stations & the word
Tippler means a machine, which is used to unload the wagon into the hopper.
Hopper is just like a vessel which is made of concrete & it is covered with a thick
iron net on its top. Here big size coal pieces are hammered by the labors to
dispose it into the hopper.
TABLE – 2.1:Coal handling detail
Capacity 90 tonnes
Types of Tipplers 1.Weighing type,2.Non weighing type
Angle of Tip 30 ‘to35’
Wire Ropes 1.Hoisting Ropes, 2.Counter Weight Ropes
Drive unit Motor 37.3 KW
Operating Cycle 10 wagons/Hour on 1 wagon Tippler
Time consume for one cycle 6 minutes
 FEEDER- It is used to control the supply of crushed coal to the mill depending
upon load condition.It is installed under wagon tippler and hopper.In KaTPP there
are 4 unbalanced Motor Vibrating Feeder installed in unit 1st.
 CHRUSHER/RING GRANULATOR-In ring granulator the material is fed in to
the crushing chamber and is crushed by the rind hammers with impact and rolling
action across the feed, with concentrated pressure.This cracks the coal producing
a granulator product with a minimum of fines up to 20 mm square.
[21]
TABLE – 2.2:Chrusher /ring capacity
Capacity 500 Tonnes/hr
Machine Weight 30 Tonnes(approx.)
Max Feed Rate 500 Tonnes/hr
Rotor Speed 720 r.p.m
Motor 550 H.P
Volts 606 KV
Phase 3 Phase motor
 CONVEYORS-Conveyor belt is used to sent the coal from coal storage yard and
also used to sent crushed coal from store to mill bunkers.The carrying capacity of
conveyors belt is 750 tonnes/hrs that are installed in KaTPP.
Conveyor belt used in coal handling plant(CHP) are of 2 types
1. 5 ply x1000 mm width with 5 mm rubber top side and 5 mm rubber bottom side.
Total thickness of belt:-17 to 18 mm
Power:-1000KN/m2
2. 4 Ply x1000 mm width with 5mm rubber top side and 5 mm rubber bottom side.
Total thickness of belt:-17mm
Power:-800KN/m2
Cold joint are used in joining the conveyor,conveyor belts run with the help of
electric motor ,gear box,fluid coupling geared coupling are installed at head of
allconveyors.
 PARTS OF CONVEYORS:
1) Flap Gate-it provide under coal transfer chutes for replacements of
crusher/conveyors.
[22]
2) Deflector Plate-Deflector plates are installed in the chutes coming on
conveyors to keep the coal direction in the centre of the conveyors.
3) Skirt board and Skirt rubber-These are provided on tail end chutes to avoid
spillages of coal from Conveyors.
4) Stone picker-Stone picker pick the stonesfrom the running belt manually.
5) Metal Detactor-Electromagnets are provide on conveyors to avoid and to
save crusher parts and entry of iron pieces in crusher.It also stop the entry of
iron pieces in coal bunker to save damage of coal mills.
6) Guide Idlers-These idlers help to train/guide the conveyors.
7) Return Idlers-These idlers carries the conveyors belts in return side.
8) R.T.I (Return Training Idler)-These idlers are provided on return side to
guide the conveyors.
9) Impact Idler-These Rubber idlers are provided under chutes through which
coal falls on conveyors.
10) Carrying Idlers-These are installed to run the conveyor.
 BUNKERS-Bunckers are fabricated to store the coal before sending to coal
mills.Coal is fed in the bunkers with the help of tripper trolleys installed at 37 m
height for unit 1st and 2nd.These are 20 bunkers for unit 1st and 2nd.
Capacity of a bunker=500 tonne/bunker.
 COAL BUNKERS-These are in process storage used for storing crushed coal
from the handling system.Generally these are made up of the welded steel plates
with vibrating arrangement of the outlet to avoid chocking of coal, normally there
are six bunker supply coal to the corresponding mills.These are located on the top
of mills so as to add gravity feeding of coal.
[23]
 RECLAIM YARD-After filing the coal bunkers extra coal is taken to reclaim
yard after crushing of coal to storage.
 COAL CIRCULATION-Coal is transported from the coal mine with the help of
train.Train wagons are emptied with the help of wagon tipplers and sent to the
crusher for crushing.From coal crusher it goes to the bunker through conveyor
belt and from coal bunker it move to R.C feeder feeds coal to the coal mill,where
the coal is ground in to powder from.
Fig2.2-coal handling plant
[24]
CHAPTER-3
IMPORTANT PARTS OF THERMALPOWER PLANT
3.1 BOILER
Boiler can simply defined as the device where any liquid is boiled or Boiler may be
defined as a device that is used to transfer heat energy being produced by burning of fuel
to liquid, generally water, contended in it to cause its vaporization. Boiler, in simple
terms, can be called “Steam Generator”.
In simple way, boiler is a device used for producing steam. There are two types of boiler
(depending upon tube content):
a) Fire tube boiler
b) Water tube boiler
Here, boiler used is of water type. In the boiler, heat energy transfer takes place through
tube walls and drum. The gases lose their heat to water in the boiler or superheated. The
escape heat is used to heat the water through economizer.
ID and FD fans are used to produce artificial draught. The fuel oil is used to ignite the
boiler and pulverized coal is lifted from the coal mills by PA fans.
Various motors use in boiler are different rating and parameters 32KW,15KW ,11KW &
3.3KW.
Fig 3.1-Boiler
[25]
BOILER AUXILIARIES-Efficiency of a system is of most concerned. Thus it is very
important to maintain a system as efficient as possible. So Boiler auxiliaries help in
improving boiler’s efficiency. Following are the important auxiliaries used
 ECONOMISER: Its purpose is to preheat feed water before it is introduced
into boiler drum by recovering heat from flue gases leaving the furnace.
 SUPER HEATER: It increase the temperature of steam to super heated
region.
 REHEATER: It is used for heat addition and increase the temperature of
steam coming from high pressure turbine to 540 deg.
 DRAFT FANS: They handle the supply of air and the pressure of furnace.
BOILER MOUNTINGS-These are used for the safe operation of boiler. Some example
of mountings used are water level indicator in drum, furnace temperature probe, reheat
release valve, pressure gauges indicating steam pressure etc.
3.2 TURBINE
Turbine is an m/c in which a shaft is rotated steadily by the impact of reaction of steam
of working substance upon blades of a wheel. It converts the potential energy or heat
energy of the working substance into mechanical energy. When working substance is
steam it is called ‘Steam Turbine’
In the steam turbine the pressure of the steam is utilized to overcome external resistance
and the dynamic action of the steam is negligibly small.
 PRINCIPLE-Working of the steam turbine depends wholly upon the dynamic
action of steam. The steam is caused to fall with pressure in a passage of nozzle,
due to this fall in pressure, a whole amount of heat energy is converted into
mechanical energy & steam is set moving with the reactor velocity. The rapidly
moving particle of steam enter the moving part of turbine and here suffers a
change in the direction of motion which givesrise to change of momentum and
therefore to a force. This constitutes a driving force to a turbine.
[26]
The passage of them/through the moving part of the turbine commonly called the blade,
may take place in such a manner that the pressure at the outlet sides of the blade is equal
to that of the inlet side. Such a turbine is broadly termed as outlet turbine or Impulse
type.
On the other hand, the pressure of the steam at outlet from the moving blade may be less
than that at type inlet side of the blade. The drop of pressure suffered by the steam during
its flow through the moving blades causes a further generation of kinetic energy within
the blades and adds to the propelling force which is applied to the turbine rotor, such a
turbine is broadly termed as Reaction Turbine. Here in Kalisindh Thermal Power
Project N600-16.7/587/537,Re-Het,Three Casing, Four Exhaust, Tandem Compound
Condenser Type Turbine Used.
The turbine is of tandem compound design with separate High
Pressure(HP),Indermediate Pressure(IP) and Low Pressure(LP) cylinders. The HP turbine
is of Single Flow type while IP and LP turbines are of Double Flow type .
The readily designed HP,IP and LP turbines are combined and sized to required
power output,steam parameters and cycle configuration to give most economical turbine
set.The design and constructional feature have proved their reliability in service and
ensure trouble free operation over long operating periods and at the same time ensuring
high thermal efficiencies.
Fig 3.2-Turbine
[27]
TABLE – 3.2: TURBINE SPECIFICATION-
Rated output with extraction flow 600 MW
Speed 3000 r.p.m
Main steam throttle flow at HP Inlet 1848.5 TPH
Main steam pressure to HP turbine inlet 167 kg/sq.cm
Main steam temp. to HP turbine inlet 538 deg.cel
Re-heater steam flow at IP inlet 1587.942 TPH
Re-heater steam temp. at IP inlet 538 deg.cel
Steam pressure at LP inlet 35.12 kg/sq.cm
Steam flow at LP inlet 1353.7 TPH
Rotation Direction(view from turbine) anticlock wise
Number of stages 42
High pressure turbine-
a) Intermediate pressure
b) Low pressure turbine
c) Governing system
1 governing and 8 pressure
5 pressure stage
28 pressure stage
DEH(digital electro hydraulic)
Inlet steam flow governing type Nozzle+throttle
Rated exhaust pressure 0.09 kg/sq.cm
Type of bearing turbine 6 journal +1 thrust
Turbine allowable frequency 47.5 to 51.5 Hz
Turning gear rotation speed 1.5 r.p.m
Ist critical speed of HP & LP rotor 1722 r.p.m
Ist critical speed of LP-A rotor 1839 r.p.m
Ist critical speed of LP-b rotor 1903 r.p.m
Heat regenerative extraction system 3HP htr+1 deaerator+4 LP htr
Final feed water temperature 274.9 deg.cel
Maximum bearing vibration 0.076 m
Maximum allowable exhaust temp. 80 deg.cel.
Coolling water design flow at condenser 70200 TPH
[28]
3.3 GENERATOR
Generator is the important part of thermal power plant.It is device which convert the
mechanical energy into electrical energy.Generator is driven by coupled steam turbine at
a speed of 3000 r.p.m.Due to rotation at high speed it get heat.So there is cooling
construction enclosing the winding core of the genetator.So that during the operation is
being in normal temperature.
In KaTPP , Each of the 2 units have been provided with 3-phase turbo generator
rated output 706MVA, 18.525KA, 22KV, 0.85 lagging p.f., 984 rpm and 50 cycles/sec
.The generator has closed loop of hydrogen gas system for cooling of the stator and rotor
at a pressure of 4.5kg/sq-cm(g).
Fig 3.3 – Generator
[29]
GENERATOR SPECIFICATION FOR UNIT I AND II:-
TABLE – 3.3:Generator Specification
Make CQ GEARBOX China
Type QFSN
Apparent output 706 MVA
Active output 600 MW
Power factor 0.85 lagging
Rated voltage 22 KV
Rated current 18525 Amp
Rated speed 3000 r.p.m
Frequency 50 Hz
Phase connections Double gen.star
Cooling mode H20-H2-H2
Rated H2 pressure 4.5 Kg/sq-cm
Terminal in generator 6
DIESEL GENERATOR SET
It is used to emergency porpuse to supply auxillary system of power plant.3 Set Diesel
generator are use in which one is standby. parameters of generator are as
Table-3.3:Diesel Generator Specification
Make BY STAMFOARD MAHARASTRA INDIA
Rating 1900 KVA
Speed 1500 R.P.M
Rated Current 2643.37 A
Rated Temp 40 Degcel
AMPS 3.6 A
[30]
3.4 CONDENSER
In condenser, the water passes through various tubes and steam passes through a chamber
containing a large number of water tubes (about 20000).
The steam gets converted into water droplets,when steam comes in contact with
water tubes. The condensate is used again in boiler as it is dematerialized water and 5-6
heats the water, which was in tubes, during the process of condensation. This water is
sent to cooling tower.
Condenser is installed below the LP exhaust. The condenser is of surface type
made of fabricated construction in single shell. The tube is of divided type double pass
arrangement, having two independent cooling water inlet, outlet and reverse and water
boxes. This arrangement facilitates the operation of one half of condenser when the other
half is under maintenance. The condenser is provided with integral air-cooling zone at
the centre from where air and non-condensable gases are continuously drawn out with the
help of mechanical vacuum pump.
 Area of condenser = 9655 sq m
 Cooling water flow rate = 2400 cubic m/Hr.
3.5 COOLING TOWER
It is used to reject heat into the atmosphere. There are two types of the cooling tower.
(1) Natural draft.
(2) Forced draft.
Natural draft - tower used vary large concrete chimney to introduce air through the
media. They are generally used for water flow rate about 45000 m3 /hour. It is used in
utility power station. Here hight of cooling tower is 202M.
Forced draft- tower utilize large fans to force or suck air through circulating water. The
water falls downward over fills surface which helps in increase the contact time between
the water and air. This held maximize heat transfer between two media. Cooling rates
depend upon fan diameter and speed. This type of tower much wider used.
[31]
In KaTPP two natural draught cooling towers (2 NDCT) is present with height 202 m
each for each unit.
It is a structure of height 202 m (tallest in the world) designed to cool the water(coming
from condenser) by natural draught. The cross sectional area is less at the centre just to
create low pressure so that ate air can lift up due to natural draught and can carry heat
from spherical drops. The upper portion is also diverging for increasing the efficiency of
cooling tower. Hence it is named as natural draught cooling tower.
This structure is constructed in r.c.c. shell poud floor and its derified water channel
c.w. For bay. The entire structure is supported combined circular rafting constructed in
different segments with slanted colomn fotting to support 17 m hight circular sectional
reckarcolmns. This r.c.c. shell of 150 m dia. And 205 m height . It is made of m 50 grade
r.c.c. Which was also done at sight. There will be 200 colomnspoud floors that will
generate cascading effect for cooling. The cooling tower shell be capable of cooling the
rated quality of water
Fig 3.5-Cooling Tower
[32]
3.6 WATER TREATMENT PLANT
As everyone know that the cost of any thermal power plant is cores of rupees.So major
problem of any thermal power plant is that how to prevent the corrosion. The water
available can’t be used in boilers as such. The objective of water treatment plant is to
produce the boiler feed water so that there shall be.
 No scale formation ·
 No corrosion ·
 No priming or forming problems
Water used in thermal power plant is called ‘Dematerialized Water’ or DM Water.
The treated water is called ‘Dematerialized Water’. The treatment process can be divided
in two sections:
1. Pre-treatment section.
2. Demineralization section
PRE-TREATMENT SECTION:- Pre-treatment plant removes suspended solids
like clay, salt, plants, micro-organisms etc form raw water to give clarified water.
Suspended solids can be separable or non-separable. Separable solids are heavier & large
and can easily be removed by an aerator. Non-separable solids have finer size and take
long to settle down. Hence they are required to be flocculated. In this, water is first dozed
with lime and alum. This forces finer particles to coagulate increasing their weight and
size. Non-separable solids can now be separated in clariflocculator. The clarified water is
then stored in clarified water storage tanks.
DEMINERALISATION SECTION The clarified water now goes to FCA
(activated carbon filter) where it de-chlorinated. Water then passes through cation
exchanger where weak and strong acidic cations are removed on adding resin.
Water Treatment Stage:-
River (raw water) → Clarification → Filtration → Demineralization
[33]
CLARIFICATION AND FILTERATION OF WATER:-
River water contains different impurities i.e.
 Suspended impurities
 Biological impurities
 Soluble impurities
 Colloidal impurities
WORKING:- The raw water enters through valve and than chemicals is added. Chlorine
and alum are added. Chlorine is added to remove bacteria etc. Alums are added to make
the impurities heavier, once the impurities become heavier than a no. of flocs are formed.
By mixing the alums, heavy impurities are settle down due to gravity and later removed.
The time required for the formation of floc is called retention time which is generally 3
hours but this can’t be achieved as it require large tank. In order to cope up the limitation
CLARRIFOCCULATION TANK is used.
This flocculation tank is consist of
1. Clarification zone
2. Flocculationzon
Clarrifocculation tank has a central pillar which has four windows at 90 degree.
The outer circle is half of windows so that level of water is arise then it flows down
through these windows into overflow channel. After mixing from flash mixer, the water
passes on to central pillar and follows the path as shown in fig. i.e. it moves to max. Floc
area and comes out from window at 3.5 m height. The downward flow is through
perforated wall which sinks the raw water. Due to the long path a retention time of 4 hour
is easily available.
The capacity of water in this plant is 1000*1000 lt./hr.In flocculation zone max.floc is
formed and after removing it, the clear water moves into clarifier. Some impurities are
weightless and do not settle down so they are passed through filter beds. There are two
types of filter beds.
1. Gravity filter bed.
2. Forced filter bed.
[34]
In FORCED FILTER BEDS raisins are added to settle down the impurities. In
GRAVITY FILTER BEDS graded gravels are arranged. At bottom gravels of big size are
there and above other gravels are arranged according to size. Above it grit and most of
the above is sand. The clarified water enters into sump. Sump is fully closed leaving one
window to see the level. Since it is fully closed hence no foreign matter can enter into it.
3.2 DEMINERALIZING PLANT
Water is mainly used for cooling purpose of different parts like bearing winding etc. in
KaTPP. For this water should be Demineralized (D.M. water).
In this plant process water is freed from all dissolved salts. Equipments for
demineralization plant is supplied and erected by GE INDUSTRIAL (India) Ltd.This
plant consists of two streams, each stream with activated carbon filter, weak acid, carbon
exchanger and mixed bed exchanger. The filter water goes to DM water plant through
250 dia header from where a header top off has been taken off to softening plant. Two
filtered water booster pumps are provided on filtered water line for meeting the pressure
requirement in DM plant.
When pressure drop across filter exceeds a prescribed limit from the activated
carbon filter enter works acid carbon unit. The dilation water enter the weak base anion
exchanger unit water then enters degassifier unit where free CO2 is scrubbed out of water
by upward counter flow of low pressure air flow through degassifier lower and degassed
water is pumped to strong base exchanger(anion–exchanger).
PH VALUE OF WATER:- This is recommended to feed the water in the boiler at 25
degree centigrade and pH value is 8.2 to 9.2 up to 28 days and the pressure is 59 Kg
cm2.
[35]
CHAPTER 4
ESP AND AHP SYSTEM
4.1 ELECTROSTATIC PRECIPITATOR (ESP):
Electrostatic Precipitator (ESP) is equipment, which utilizes an intense electric force to
separate the suspended particle from the gases. In India coal is widely used to generate
power. The exhaust gases are emitted directly into the atmosphere, it will cause great
environmental problems. So it is necessary to extract this dust and smoke before emitted
the exhaust gases into atmosphere. There are various methods of extracting dust but
electrostatic precipitator is the most widely used. It involves electric changing of
suspended particle, collection of charge particles and removal of charge particles from
collecting electrode. Its various other advantages are as follows:
 It has high efficiency i.e. about 99%
 Ability to treat large volume of gases at high temperature
 Ability to cope with the corrosive atmosphere.
 It offers low resistance to the flow of gases.
 It requires less maintenance.
WORKING PRINCIPLE- The electrostatic precipitator utilizes electrostatic forces to
separate dust particles from the gases to be cleaned. The gas is passed through a chamber,
which contains steel plates (vertical) curtains. Theses steel curtains divide the chamber
into number of parallel paths. The framework is held in place by four insulators, which
insulate it electrically from all parts , which are grounded. A high voltage direct current is
connected between the framework and the ground, thereby creating strong electric field
between the wires in the framework curtains.
Strong electric field develops near the surface of the wire creates Corona
Discharge along the wire.Thus ionized gas produces +ve and –ve ions. In the chamber
plates are positively charged whereas the wire is negatively charged. Positive ions are
attracted towards the wire whereas the negative ions are attracted towards the plates. On
their way towards the curtains negative ions strike the dust particle and make them
negatively charged. Thus is collected on the steel curtains.
[36]
The whole process is divided into the following parts:
 Corona Generation
 Particle Charging
 Particle Collection
 Particle Removal
Details of the following are given below-
 Corona Generation- Corona is a gas discharge phenomenon associated with the
ionization of gas molecules by electron collision in regions of high electric field
strength. This process requires non-uniform electric field, which is obtained by
the use of small diameter wire as one electrode and a plate or cylinder as the other
electrode. The corona process is initiated by the presence of electron in strong
electric field near the wire. In this region of corona discharge, there are free
electrons and positive ions . Both positive and negative coronas are used in
industrial gas cleaning.
In case of negative corona, positive ions generated are attracted towards the
negative electrode or wire electrons towards collecting plates. On impact of
negative and serve as principle means of charging dust.
 Particle Charging- These are two physical mechanisms by which gas ions
impact charge to dust particles in the ESP. Particles in an electric fields causes
localized distortion in an electric filed so that electric field lines intersect with the
particles of maximum voltage gradient, which is along electric field lines. Thus
ions will be intercepted by the dust particles resulting in a net charge flow to the
dust particles. The ions will be held to the dust particles by an induced image
charge force between the ion and dust particle and become charged to a value
sufficient to divert the electric field lines from particles such that they do not
intercept.
 Particle Collection- The forces acting on the charged particles are Gravitational,
Inertial, Electrostatic and Aerodynamically. The flow of gas stream is turbulent
flow because it causes the particles to flow in random path through ESP. Particles
will be collected at boundary layers of collector pates. But if flow is laminar,
[37]
charge will act on particles in the direction of collecting electrode. This force is
opposite to viscous drag force and thus in the short time, particle would achieve
Terminal (Migration) velocity at which electrical; and viscous forces are equal.
Thus the flow of the charged particle is decided by the vector sum of these forces
i.e. Turbulent.
 Particle Removal- In dry removal of dust collected on plates, Rapping
Mechanism is used. It consider of a geared motor, Which moves along shaft
paced near the support collector electrode and is provided with cylindrical
hammer. On rotating of shaft these hammers strikes the supports causes plate to
vibrates and dust is removed from plates. Removed dust is collected in the
Hoppers below the precipitator. At the time of starting of precipitation of dust
from flue gases, the hoppers are at normal temperature but the ash collected is
very hot. So there is a chance of ash deposit at the exit of the hopper thus causing
problem of removing the ash. To avoid this , heater are provide which increase
the temperature at the exit point o the hopper thus avoiding any undue
accumulation of ash at starting . In other method, the water is allowed to flow
down the collector electrode and hence dust is collected in hoppers below.
GENERAL DESCRIPTION-
The whole ESP is divided into two parts-
 Mechanical System
 Electrical System
Here we will discuss only Mechanical System (i.e. Precipitator Casing, Emitting and
Collecting System and Hopper).
 Precipitator Casing-Precipitator Casing is made of 6mm mild steel plates with
required stiffness. The precipitator casing is all welded construction comprising
of pre-fabricated walls and proof-panels. The roof carries the precipitator
internals, insulator housing, transformer etc. Both emitting and collecting systems
are hung from the top of the casing.
[38]
 Emitting and Collecting System- Emitting System is the most important part of
ESP. Emitting system consists of rigid emitting frame suspended from four points
on the top of rigid emitting electrodes in the form of open spiral. The four
suspension points are supported on support insulators to give electrical insulation
to the emitting frame. The frame is designed to take up the retention forces of the
emitting electrode. The emitting electrode consists of hard drawn spiral wires and
are fastened with hooks to the discharge frame.
Collecting system mainly consists of collecting suspension frame, collection
electrodes and shock bars. Collecting electrode are made of 1.6 mm thick Mild
Steel sheets formed in ‘G’ Profile of 400mm width. Hook and guide are welded
on one end and shock iron on the dipped in rust preventive oil tank. Collecting
electrodes bundles are properly bundled in order to avoid any damage to
electrode.
 Hoppers- Hoppers are seized to hold the ash for 8-hour collection and is provided
under the casing of ESP. It is of Pyramidal Shape and is 56 in number. It is
preferred to evacuate the hoppers at the earliest as long storage of dust in hopper
leads to clogging of hopper. Also at the bottom of hopper electrical heating is
provided to avoid any condensation, which could also lead to clogging of hopper.
Baffle plates are provided in each hopper to avoid gas leakage.
RAPPING MECAHISM FOR COLLECTING SYSTEM- During electrostatic
precipitation a fraction of dust will be collected on the discharge on the discharge
electrodes and the corona will be suppressed as the dust layer grows. So rapping is done
in order to remove this dust by hammering the electrodes. As the shaft rotates the
hammer tumbles on to the shock bar that transmits the blow to the electrode. The whole
rapping mechanism is mounted on a single shaft, which is collection of ash on the
collecting electrode.
[39]
Fig 4.1 -Electrostatic Precipitation Unit
4.2 ASH HANDLING PLANT (AHP)
The ash produced on the combustion of coal is collected by ESP. This ash is now
required to disposed off. This purpose of ash disposal is solved by Ash Handling Plant
(AHP). There are basically two types of ash handling process undertaken by AHP.
 Dry Ash System
 Ash Slurry System
DRY ASH SYSTEM- Dry ash is required in cement factories as it can be directly added
to cement. Hence the dry ash collected in the ESP hopper is directly disposed to silos
using pressure pumps. The dry ash from these silos is transported to the required
destination.
ASH SLURRY SYSTEM- Ash from boiler is transported to ash dump areas by means
of sluicing type hydraulic system which consists of two types of system-
 Bottom Ash System
 Ash Water System
[40]
BOTTOM ASH SYSTEM- In this system, the ash slag discharged from the furnace is
collected in water impounded scraper installed below bottom ash hopper. The ash
collected is transported to clinkers by chain conveyors. The clinker grinders churn ash
which is then mixed with water to form slurry.
ASH WATER SYSTEM-In this system, the ash collected in ESP hopper is passed to
flushing system. Here low pressure water is applied through nozzle directing tangentially
to the section of pipe to create turbulence and proper mixing of ash with water to form
slurry. Slurry formed in above processes is transported to ash slurry sump. Here extra
water is added to slurry if required and then is pumped to the dump area.
FLY ASH SYSTEM-Even though ESP is very efficient, there is still some ash, about
0.2%,left in flue gases. It is disposed to the atmosphere along with flue gases through
chimney.
Fig 4.2 –fly ash system
[41]
CHAPTER-5
CONTROLLING, SWITCHINGAND TRANSMISSION
5.1 CONTROL AND INSTRUMENTATION SYSTEM
5.1.1 SWITCHGEAR
The apparatus used for switching, controlling and protecting the electrical circuits and
equipment is known as switchgear.
A switch gear is one which makes or breaks electric circuit. Numerous problems
arise in erection, testing and commissioning of switch gear and various precautions are to
be made in operating and maintenance of switch gear.
Essential Features of Switch Gear:-
 Complete Reliability
 Absolutely certain discrimination
 Quick operation
 Provision for manual control
 provision for instruments
The main components of indoor switchgear are given below:-
1) Bus-Bars
2) Isolating Switches
3) Current Transformers
4) Potential Transformers
5) Circuit Breaker
6) Earthing arrangement
7) Relays
8) Inter-Locking arrangements
(i) BUS-BARS:-
Bus bars are defined as the conductors to which several incoming and outgoing lines
are connected. They are essential component of Switchgear. They are made up of Cu.
and Al. The type and designers of Switchgear depends upon rated normal current and
[42]
short circuit capacity. The Bus bars are enclosed in bus bar chamber. In KaTPP there
are two types of indoor switch gear: 11 KV &3.3KV or High tension3.415V or Low
tension.
(ii) ISOLATING SWITCHING:-
1. They are capable of-Interrupting the Transformer Magnetizing Current-Interrupting
line charging Current.Interrupting load Transformer Switching.
2. The main application is in connection with feed or bank Transformer feeders & there
units make it possible to switch out one Transformer while the other is still on load.
(iii) CIRCUIT BREAKER:-
They are capable of breaking the circuit on faults. It is heavy duty equipment mainly
utilized for protection of various circuit and separation of loads. The Circuit Breaker uses
on a relay or by manual signal. The Circuit Breakers which are used in Switchgear are
VCB type.
(iv) EARTHED SWITCHES:-
Earthed switch is connected between line conductor and earth. Normally it is open when
line is disconnected. The Earthing switched is closed so as to discharge the voltage
trapped on line for high voltage and so the capacitor between line and earth is charged to
high voltage. For maintenance work their voltage are discharged to earth by closing the
earth switch.
(vi) INTER-LOCKING:-
The following type of inter- locking are provided The Circuit Breaker must be in open
position before it is lowered in this position. The Circuit Breaker can be closed only
raising the final plug in position. The Circuit Breaker can be closed before raising plug in
position. Inter-locking between isolators, Earthing switches and Circuit Breakers are
provided.
(vii) RELAYS:-
A Protective Relay is a device that detects the fault and initiates the operation of the
circuit breaker to isolate the defective element from the rest of the system.
[43]
5.1.2 PROTECTION
The fault, which may occur in stator winding are-
a. Phase to phase fault.
b. Phase to ground fault.
c. Line to line fault.
d. Overheating.
These faults are due to-
1. Over voltage is because of system transients, lightening switching surges or sudden
loss of load.
2. Insulation deterioration due to any matter, moisture, corona discharge, Hardening of
solid and vibration.
It is very necessary to minimize the tripping time during any fault so that the lamination
is not damaged. The repairing being affected by replacing the faulty stator bar.A delayed
clearance may damage the lamination, so fire may be caused and partial re- insulation of
core may be necessary.
GENERATOR PROTECTION:-
The Generator is required to be tripped or isolated on following types of fault:-
1. Failure of generating insulation.
2. Failure of prime mover turbine or boiler.
3. Failure of generating auxiliaries such as hydrogen gas system,seal oil system, cooling
system, and cooling water system.
4. Failure of grid.
The tripping command to the GT breaker is given by master trip relay 866, 86GT, and
86GB. To make it feasible the master trip relay is connected to a common bus. All the
protection relays are connected in between the position of 220V.
D.C. PROTECTION AND THE COMMON BUS:-
Protection device are that detect abnormal condition in electrical circuit by measuring the
electrical quantity which are different under normal and fault condition. The basic
electrical quantities are voltage, current, phase angle and frequency.
[44]
The relay doesn’t operate for normal voltage, normal current, normal phase angle and
normal frequency.
Different type of protection can be listed as:.
1. Current operated protection.
2. Different protection.
3. Voltage operated protection.
4. Impedance type protection.
5. Frequency type protection.
1. CURRENT OPERATED PROTECTION:-
a. Generator differential protection.
b. Generator negative sequence protection.
c. Generator output current protection.
d. Generator stator earth fault protection.
e. Generator REF protection.
f. Generator standby earth fault protection.
g. UAT o/c protection. h. Generator o/c and short circuit protection.
i. L.B.B. protection.
2. DIFFERENTIAL PROTECTION:-
a. Generator overall differential protection.
b. UAT differential protection.
3. VOLTAGE OPERATED PROTECTION:-
a. Generator over voltage protection.
b. Generator stator E/F protection.
c. GT over voltage protection.
d. PT’s voltage supervision protection.
e. Generator inter-turn fault protection.
[45]
4. IMPEDANCE TYPE PROTECTION:-
a. Generator back up impedance protection.
b. Generator loss of exact protection.
c. Generator pole slip protection.
5. FREQUENCY TYPE PROTECTION:-
a. Generator under protection Frequency.
REQUIREMENT OF PROTECTIVE DEVICES:
 Selectivity: Only that part of the installation containing fault should is
disconnected. Safety against faulty tripping: There should be no trip when there is
no fault.
 Reliability: The device must act within the required time.
 Sensitivity: Lowest signal input value at which the device must act.
 Tripping time: There should be a clear a distinction between the tripping time of
the device, considering the circumstances such as current and total tripping time
for the fault.
5.2 CONTROL ROOM
Various measurements can be taken at the control room simultaneously. The second
important part of the control room is relay part. Various relays are provided here BY
AREVA LTD.
CONTROL ROOM PANELS:-
FAN CONTROL DESK: -
1. ID Fan (Induced draft fan, 2nos.) at full load.
2. FD Fan (Forced draft fan, 2nos.)at full load.
3. PA Fan (Primary air fan, 2 nos.) at full load.
[46]
PRESSURE CONTROL DESK: -
1. Furnace pressure (5-10mmwcl.).
2. Primary air header pressure (750-800mmwcl).
FUEL CONTROL DESK:-Coal oil flow. Oil pressure. Temperature of mill (inlet or
outlet) Flow of air. Drum level control, flow of steam water Pressure of steam and water.
Temperature of steam and water.
TURBINE DESK:- Pressure control, load mode control. Speed control. Ejector, control
valves, stops valves and deviators.
GENERATOR CONTROL PANEL:-Voltage, current, MVAR. Stator, rotor
temperature. For stator cooling.
5.3AUXILIARY SUPPLY
Electrical supply system is the most important part of the thermal power station. The
failure of even comparatively small equipment could result in the losing of load or being
put out of commission.
SOURCE OF SUPPLY: -
1. URGENT AUXILLARY: - Those are associated with running of units whose loss
would cause an immediate reduction unit output.
2. SERVICE AUXILLARY: - These are common auxiliaries associated with one or
more units. There loss would not affect the output of the unit after considerable time of
interval.
[47]
ELECTRICAL AUXILLARY SYSTEM: -
The KaTPP auxiliaries are operated at two voltages that are 6.6 KV and 415V. In respect
of 6.6KV system, auto change over facility is provided for change over of source of
supply from unit station in the case of unit trip out.
The station is having the following auxiliary system: -
a) More then 1500KW connected on 11KV.
b) More then 200KW less then 1500KW connected on 3.3KV.
c) Less then 200KW on 415V.
220V D.C. underground system for use in control and protection system.
3.3 KV SYSTEM: -
For the running unit, the unit auxiliaries are normally fed from gen’r itself through 11/3.3
KV, 15 MVA unit auxiliary transformers, which is, connected to the unit switchgear viz.
USA and USB. Power to station auxiliaries and by unit auxiliary is fed from 220/3.3KV,
50 MVA station transformers through two switchgear viz.
415 KV SYSTEMS: -
For driving ten 100W motors and other accessories, we need 415V supply. For this
purpose various transformer are used to step down 3.3 KV to 415V at various places. Oil
circuit breaker is provided between 3.3 KV bus and primary winding of transformer.
Fig 5.3- Switching and transmission
[48]
5.4 SWITCH YARD
Switchyard is considered as the HEART of the Power Plant. Power generated can be
worthful only if it is successfully transmitted and received by its consumers. Switchyard
plays a very important role as a buffer between the generation and transmission. It is a
junction, which carries the generated power to its destination (i.e. consumers).
Switchyard is basically a yard or an open area where many different kinds of equipments
are located (isolator, circuit breaker etc…), responsible for connecting & disconnecting
the transmission line as per requirement (e.g. any fault condition). Power transmission is
done at a higher voltage. (Higher transmission voltage reduces transmission losses).
Both units is 22KV in KaTPP. stepped-up to 400KV by the Generating transformer &
then transmitted to switchyard. Switchyards can be of 400KV, & 200KVIn SSTPS there
are two interconnected switchyards:-
(i) 400KV SWITCHYARD
(ii) 220KV SWITCHYARD
The 400KV & 220KV switch yard have conventional two buses arrangement with a
bus coupled breaker. Both the generator transformer and line feeder taking off from
switch yard can be taken to any of the two buses, similarly two station transformer
can be fed from any two buses. Each of these line feeders has been provided with by
pass isolators connected across line isolators and breaker isolators to facilitate the
maintenance of line breaker. Each 400KV & 220KV lines have provision of local
break up protection. In event of breaker which corresponding to bus bar differential
protection scheme and trips out all the breakers and connected zone bus bars
differential protection scheme for bus I & II. All the breaker of the connected zone
and bus coupler, breaker will trip in event of fault in that zone. Here in KaTPP 4 out
going line are as below:-
1) 400KV TO BTAWDA
2) 400KV TO BTAWDA
3) 220KV TO JHALAWAR
4) 220KV TO JHALAWAR
[49]
Each of the two bus bars has one P.T. one for each phase connected to it. Potential
Transformer are make in CROMPTON LTD. Each time line feeders has two nos. Core
for each phase capacitor voltage Transformer. for metering and protection are multicored
single phase, oil filled, nitrogen sealed and are provided at rate of one per phase.
400KV SWITCHYARD: There are on total 21 bays in this switchyard.
(A bay is basically a way for the incoming power from generator as well as outgoing
power for distribution).
3 for unit Generating Transformer.
2 for various distribution lines such as:
BTAWDA LINE
 2 for Bus coupler.
 2 for TBC.
 2 for ICT.
 1 for the Bus Section.
There are on total 2 buses in 400KV switchyard.
 Bus-1
 Bus-2
There are two transfer buses:
 Transfer bus-1
 Transfer bus-2
Transfer buses are kept spare and remain idle and are used only for emergency purposes.
BUS COUPLER-1 interconnects Bus-1 & Bus-2, respectively. Bus couplers are very
beneficial as they help in load sharing between the different buses.
TBC (TRANSFER BUS COUPLER): TBC is a bus coupler, which uses transfer bus
when there is any defect in the equipments used (circuit breakers & isolators) in any of
the bay. Thus, it offers a closed path through transfer bus for the flow of power in the
respective bus.
[50]
A described of electrical equipment at 400KV & 220KV system are as follows: -
 Circuit Breaker(VCB& SF6)
 Isolators
 Current Transformers(C.T.)
 Potential Transformers(P.T.)
 Lighting Arresters
 Earthing Arresters
 Capacitor Voltage Transformers(C.V.T.)
 Inter connected transformer (ICT)
CIRCUIT BREAKER:-
It is an automatic controlling switch used in power house, substation & workshop as well
as in power transmission during any unwanted condition (any fault condition-earth fault,
over-current, flashover, single phasing,). During such condition it cuts down the supply
automatically by electromagnetic action or thermal action. It can be used in off-load as
well as on-load condition. When a circuit breaker is operated by sending an
impulsethrough relay, C.B.contact is made or broken accordingly.During this making and
breaking, an arc is produced which has to be quenched; this is done by air, oil, SF6 gas
etc.
Depending on the medium being used C.B.s can be categorized into various
types.PLANT for 400 KV/220 KV switchyard only 4 main types are being used:-
ABCB (Air operated circuit breaker):- operated as well as arc quenched through air.
Air operated SF6 circuit breaker:-operated through air but arc quenching done through
SF6 gas.
MOCB (Minimum oil circuit breaker):-operated through spring action but arc
quenching done through oil (Aerosol fluid oil). Hydraulic operated SF6 circuit breaker:-
operated through hydraulic oil and arc quenching done through SF6 gas. Hydraulic
operated SF6 circuit breaker is the most efficient due to following reasons:-
1. Less maintenance.
2. Arc quenching capability of SF6 gas is more effective than air.
3. Heat transfer capacity is better in this C.B.
[51]
Here we use SF6 provided for each stage are SIEMENS made and rated for
420KV/245KV, 3150A Each pole has three interrupters which are oil filled with SF6 gas
at 7.5 Kg/sq. cm.Here in KaTPP 3AP1FI/3AP2FI type CB are used for 400KV &220KV
Switchyard.
Interlock Scheme of Circuit Breaker: -
 Generator Breaker
 Station Transformer Breaker
 Line Feeder Breaker
 Bus Coupler Breaker.
ISOLATERS:-
An isolator is also a switching device used to disconnect the line. As the name suggests it
isolate the line from the supply. It is always used in OFF-LOAD condition. Whenever
any fault occurs in the equipments present in the line, in order to remove the fault or
replace the device first of all supply is disconnected. But even after the disconnection of
the supply, the line remains in charged mode so before working on the device (to remove
fault) isolator should be made open.
Depending on the structure there are mainly two types of isolators:-
 Pentagraph isolator.
 Centre-break isolator (also known as Sequential isolator).
Pentagraph is generally used in buses whereas Centre-break (Sequential) is used in line.
Isolators may be operated in air (pneumatic), electrically or even manually.
LIGHTENING ARRESTER:-
It is a protective device, which protects the costly equipments such as overhead lines,
poles or towers, transformer etc. against lightening. As the name suggests it arrests the
lightening of very high voltage (crores of KV) and dump it into the ground. It works on
the principle of easy path for the flow of current. L.A. is connected in parallel with the
line with its lower end connected and the upper end projected above the pole of tower.
[52]
LIGHTENING MOST:
It is present at the highest point, at the topmost tower of the switchyard and is connected
together by wires forming a web. The reason for its presence at the topmost point is to
grasp the lightening before it can come, fall and damage the costly equipments present in
the switchyard.
EARTHING ISOLATORS:-
The term ‘Earthing’ means connecting of the non-current carrying parts of the electrical
equipment or the neutral point of the supply system to the general mass of earth in such a
manner that all times an immediate discharge of electrical energy takes place without
danger. An Earthing isolator is a large value of capacitance. This can be charged up to
line voltage. Earthing isolator is used to discharge the line capacitance and work on it.
WAVE TRAPER:-
It is an equipment used to trap the high carrier frequency of 500 KHz and above and
allow the flow of power frequency (50 Hz). High frequencies also get generated due to
capacitance to earth in long transmission lines. The basic principle of wave trap is that it
has low inductance (2 Henry) & negligible resistance, thus it offers high impedance to
carrier frequency whereas very low impedance to power frequency hence allowing it to
flow in the station.
CURRENT TRANSFORMER:-
This Transformer is used for basically two major functions: -
 Metering which means current measurement.
 Protection such as over current protection, overload earth fault protection, Bus-
bar protection, Bus differential protection.
NOTE: - Secondary of the C.T should be kept shorted because (when secondary is kept
open) even the presence of a very small voltage in the primary of C.T will prove to be
harmful as it will start working as a step-up Transformer & will increase the voltage to
such a high value that primary would not be able to bear it & will get burned. CT used
current ratio 1000:1 and range is 1A-5A.CT connected in series while PT in parallel.
[53]
PIPRI LINE:-
In the case of emergency, e.g. total grid failure we take the power from Pipri line for the
initial starting of the station (Main Plant).
CAPACITOR VOLTAGE TRANSFORMER(CVT):-
This Transformer performs mainly two major functions:-
 Used for voltage measurement. The high voltage of 400 KV is impossible to
measure directly. Hence a C.V.T is used, (connected in parallel with the line)
which step-downs the voltage of 400 KV to 110 KV, comparatively easy to
measure.
 The other most important function of C.V.T is that it blocks power frequency of
50Hz and allows the flow of carrier frequency for communication.Each of the
four line feeders provided with three capacitor volt transformer for metering and
synchronizing.
P.T (POTENTIAL TRANSFORMER):-
This Transformer is connected in parallel with the line with one end earthed. It is only
used for voltage measurement by stepping-down the voltage to the required measurable
value.
INTER CONNECTED TRANSFORMER (ICT):-
Purpose of ICT is simply interconnection between 400KV and 220KV Switchyard.
3xM1802-300/D-10.19.300MA2 Type autotransformer is used. manufacture by
CROMPTON GEARVES TRANSFORMER DIVISION BHOPAL
SURGE ARRESTER
The electricity is usually produced in the stator winding of the large modern generators at
about 25,000 volts and is fed through terminal connections to one side of a generator
transformer that steps up the voltage 132000, 220000 or 400000 volts. From here
conductors carry it to a series of three switches comprising an isolator, a circuit breaker
and another isolator.
[54]
The circuit breaker, which is a heavy-duty switch capable of operating in a fraction of a
second, is used to switch off the current flowing to the transmission lines. Once the
current has been interrupted the isolators can be opened. These isolate the circuit breaker
from all outside electrical sources.
Fig-5.4 : Overview of switchyard
From the circuit breaker the current is taken to the bus bars-conductors, which run the
length of the switching compound and then to another circuit breaker with its associated
isolates before feeding to the grid.
Three wires are used in a ‘three=phase’ system for large power transmission. The
centre of the power station is the control room. Here engineers monitor the output of
electricity, supervising and controlling the operation of the generation plant and high
voltage switch gear and directing power to the grid system as required.
[55]
CHAPTER-6
EFFICIENCY
6.1 EFFICIENCY
In KaTPP we convert potential energy or chemical energy of the fuel into heat by the
process of combustion. The heat is given to the water and it converts its form into steam.
The pressure of steam rotates the turbine, which is now in the form of kinetic energy.
Generator producing electrical energy, which is sand to different localities for utilization,
consumes this kinetic energy.
Efficiency in the case of electrical generator process can be expressed as the amount of
heat energy librated in the boiler compared with the amount of electrical energy
generated with it.
Efficiency is defined as the ratio of output to input. Efficiency of any thermal power
plant can be divided into four parts-
1) Cycle Efficiency
2) Boiler Efficiency
3) Generator Efficiency
4) Turbine Efficiency
Efficiency of thermal power plant is defined as in the term of overall efficiency
i.e. overall efficiency = cycle x boiler x generator x turbine efficiency
CYCLE EFFICIENCY- Cycle efficiency is defined as the ration of energy available for
conversion in work to the heat supplied to the boiler.
BOILER EFFICIENCY- Efficiency of boiler depends upon the following factors:
a) Dry flue gas loss: Increase by excess air in boiler.
b) Wet flue gas loss: Moisture in coal.
c) Moisture in combustion loss: Hydrogen loss.
GENERATOR EFFICIENCY- Efficiency of generator is about 98% also its efficiency
depends upon Copper iron loss and Windage losses
TURBINE EFFICIENCY- It means the efficiency of steam turbine in converting the
heat energy made available in the cycle into actual mechanical work.
[56]
CONCLUSION
Electricity is one of the most vital infrastructure inputs for economic development of a
country. The demand of electricity in India is enormous and is growing steadily. The vast
Indian electricity market, today offers one of the highest growth opportunities for private
developers
This is my first practical training in which I learned lot of things and seen lot of huge
machine like Turbine, Boiler, Generator, cooling tower and many other things.
The architecture of the power plant, the way various units are linked and the way
working of whole plant is controlled make the student realize that engineering is not just
learning the structure description and working of various machine but the great part is of
planning proper and management.
I think training has essential for any student. It has allowed an opportunity to get
an exposure of the practical implementation to theoretical fundamentals.
[57]
APPENDIX
a) R.V.U.N.L –Rajasthan Vidyut Uttpadan Nigam Limited.
b) C.H.P.- Coal Handling Plant.
c) A.H.P.- Ash Handling Plant.
d) D.G.- Diesel Generator
e) B.A.H.-Bottom ash hopper
f) L.P.T.- Low pressure turbine
g) H.P.T.- High pressure turbine
h) I.P.T.- Intermediate pressure steam turbine
i) F.D.F.-Forced draught fan
j) I.D.F.-Induced draught fan
k) F.W.H. -Feedwater heater
[58]
REFERENCE
[1]http://www.steelguru.com/indian_news/First_unit_of_coal_based_Kalisindh_th
ermal_power_plant_has_commenced_generation/335431.h
[2] http://www.rvunl.com/Kalisindh%20Thermal%20Power%20Project.php
[3 ] www.energyindia.com
[4] www.thermalpower.com
[5] www.scibe.com
[6] Fundamentals of electrical engineering/power plant/tpp/655 ,Ashfaq Husain
Dhanpat Rai&Co.
[7] Generation of electrical power/thermal station, B R Gupta ,S.CHAND
PUBLICATION.
[8] EPC Book Volume-V,TCE 5248.A-H-500-001.
[9] Annual Report o f TCE Ltd.
[10] Single Line Diagram GID-118-EL-XJ-2012,BGR REPORT ON KaTPP.
[11] Single line diagram KaTPP Plan GID-2012,BGR ENERGY SYSTEM.
[12] PPT On Thermal Plant/TCE/M Shreenivashan/104840/.
[13] Generation of electrical power By B. R. Gupta, S CHAND PUBLICATION
[14] Steam and Gas Turbine By R. Yadav , CPH
[15] Engineering Thermodynamics By P. K. Nag, TMH.
[16] http://rvunl.com/Kalisindh%20Thermal%20Power%20Project.php
[17] http://www.business-standard.com/article/pti-stories/kalisindh-thermal-
power-plant-starts-power-generation-114032200454_1.html.

More Related Content

What's hot

ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
Aditya Narain
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANT
Subarna Poddar
 
Project report of kota super thermal power plant
Project report of kota super thermal power plantProject report of kota super thermal power plant
Project report of kota super thermal power plant
Hîmãńshu Mêęńä
 
Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
DS Group (Dharampal Satyapal Limited)
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
Anubhav Ghosh
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
haxxo24
 
Vikas ntpc report complete
Vikas ntpc report completeVikas ntpc report complete
Vikas ntpc report complete
Vikas Singh
 
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan) 2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
Ministry of New & Renewable Energy, Govt of India
 
NTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORTNTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORT
Anil Jadon
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
Dilip kumar
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
pratikguptateddy
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training ppt
aryan5808
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
Aditya Narain
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
Sachin Verma
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
sanjeevps12345
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
Ankur Pal
 
Kalisindh thermal power project jhalawar (keshav)
Kalisindh thermal power project jhalawar (keshav)Kalisindh thermal power project jhalawar (keshav)
Kalisindh thermal power project jhalawar (keshav)
Keshav Meena
 
Industrial training report of thermal power plant
Industrial training report of thermal power plantIndustrial training report of thermal power plant
Industrial training report of thermal power plant
Ravinder Jangid
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
abdul mohammad
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
Rajan Kumar Choudhary
 

What's hot (20)

ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANT
 
Project report of kota super thermal power plant
Project report of kota super thermal power plantProject report of kota super thermal power plant
Project report of kota super thermal power plant
 
Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Vikas ntpc report complete
Vikas ntpc report completeVikas ntpc report complete
Vikas ntpc report complete
 
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan) 2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
 
NTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORTNTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORT
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training ppt
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
 
Kalisindh thermal power project jhalawar (keshav)
Kalisindh thermal power project jhalawar (keshav)Kalisindh thermal power project jhalawar (keshav)
Kalisindh thermal power project jhalawar (keshav)
 
Industrial training report of thermal power plant
Industrial training report of thermal power plantIndustrial training report of thermal power plant
Industrial training report of thermal power plant
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 

Similar to KALISINDH THARMAL POWER PLANT report by Neeraj Patidar

Training reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishorTraining reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishor
NAVAL KISHOR
 
NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015
LekhraJ Meena
 
Report ntpc
Report ntpcReport ntpc
Report ntpc
Lakshay Bhambri
 
Report ntpc auraiya
Report ntpc auraiyaReport ntpc auraiya
Report ntpc auraiya
Gopesh Kushwaha
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
ADITYA ARYAN
 
A summer training report on NTPC
A summer training report on NTPCA summer training report on NTPC
A summer training report on NTPC
Ranjeet1501
 
A summer traning report on ntpc
A summer traning report on ntpcA summer traning report on ntpc
A summer traning report on ntpc
Ranjeet1501
 
rajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportrajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-report
Raj Sharma
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
Shivam Singh
 
Ntpc tranning report
Ntpc tranning report Ntpc tranning report
Ntpc tranning report
Study Hub
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
94600banti
 
NTPC Training Report
NTPC Training ReportNTPC Training Report
NTPC Training Report
Pratik Gupta
 
DADRI GAS POWER PLANT report
DADRI GAS POWER PLANT reportDADRI GAS POWER PLANT report
DADRI GAS POWER PLANT report
94600banti
 
Ntpc report
Ntpc reportNtpc report
Ntpc report
Alok Tiwari
 
Ntpc 131113070238-phpapp02
Ntpc 131113070238-phpapp02Ntpc 131113070238-phpapp02
Ntpc 131113070238-phpapp02
k,l polytechnic roorkee
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
Milind Punj
 
Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauli
Devanshu Yadav
 
Vikas
VikasVikas
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plant
Raj Kumar Parihar
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
Nikhil Singh
 

Similar to KALISINDH THARMAL POWER PLANT report by Neeraj Patidar (20)

Training reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishorTraining reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishor
 
NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015
 
Report ntpc
Report ntpcReport ntpc
Report ntpc
 
Report ntpc auraiya
Report ntpc auraiyaReport ntpc auraiya
Report ntpc auraiya
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
A summer training report on NTPC
A summer training report on NTPCA summer training report on NTPC
A summer training report on NTPC
 
A summer traning report on ntpc
A summer traning report on ntpcA summer traning report on ntpc
A summer traning report on ntpc
 
rajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportrajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-report
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
 
Ntpc tranning report
Ntpc tranning report Ntpc tranning report
Ntpc tranning report
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
 
NTPC Training Report
NTPC Training ReportNTPC Training Report
NTPC Training Report
 
DADRI GAS POWER PLANT report
DADRI GAS POWER PLANT reportDADRI GAS POWER PLANT report
DADRI GAS POWER PLANT report
 
Ntpc report
Ntpc reportNtpc report
Ntpc report
 
Ntpc 131113070238-phpapp02
Ntpc 131113070238-phpapp02Ntpc 131113070238-phpapp02
Ntpc 131113070238-phpapp02
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
 
Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauli
 
Vikas
VikasVikas
Vikas
 
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plant
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
 

Recently uploaded

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 

Recently uploaded (20)

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 

KALISINDH THARMAL POWER PLANT report by Neeraj Patidar

  • 1. [1] A Seminar Report on KALI SINDH THERMAL POWER PROJECT, JHALAWAR Submitted to: GLOBAL TECHNICAL CAMPUS, JAIPUR 2015-16 Submitted To: . Guided by Submitted By: Ms. EKTA SHARMA Mr. O.P. KUMAVAT & NEERAJ PATIDAR (H.O.D.) Mr. MANISH SHRIVASTVA 4th Yr.EE Dept.OfElectrical Engg Asst. professor EE Dept Roll No.-12EGJEE733 . DEPARTMENT OF ELECTRICAL ENGINEERING GLOBAL INSTITUTE OF TECHNOLOGY JAIPUR –302022
  • 2. [2] ACKNOWLEDGEMENT It gives me an immense pleasure to complete the training report of KALISINDH THERMAL POWER PROJECT. I would like to express my gratitude towards the team of KaTPP. The experience and knowledge that I have gained from KaTPP will always be motivating and guiding factor in my career to grow as a good professional engineer. I would sincerely like to thank my training report guide, Mr. MANISH SHRIVASTVA and Mr. O.P.KUMAWAT for providing me the valuable knowledge and giving their constructive feedback. I would also like to thank Mrs. EKTA SHARMA (HOD, Dept. of EE) for the encouragement and their support. NEERAJ PATIDAR 4th Year EE 12EGJEE733
  • 3. [3] ACKNOWLEDGEMENT It gives me an immense pleasure to complete the training report of KALISINDH THERMAL POWER PROJECT. I would like to express my gratitude towards the team of KaTPP. The experience and knowledge that I have gained from KaTPP will always be motivating and guiding factor in my career to grow as a good professional engineer. I would sincerely like to thank my training report guide, Mr. MANISH SHRIVASTVA and Mr. O.P.KUMAWAT for providing me the valuable knowledge and giving their constructive feedback. I would also like to thank Mrs. EKTA SHARMA (HOD, Dept. of EE) for the encouragement and their support. NEERAJ PATIDAR 4th Year EE 12EGJEE733
  • 4. [4] PREFACE In today’s world, electricity has an important role. Today Electricity contributes the largest share to a country’s economic growth. It is the most powerful resource and has brought industrial revolution worldwide. It has resulted in social changes too and raised the standard of living. In India, several organizations like NHPC, NTPC, POWER GRID, and other state electricity boards etc. are engaged in electricity generation. RRVUNL is one of the largest among these with an honorable Contribution. The rise in civilization is closely related to improvements in transportation and requirement of energy that is not readily available in large quantities but is also readily transportable. There are several source of energy in world in which thermal power plant is also a source of energy. It give electrical energy. A very peculiar fact about electrical energy is that neither it is directly available in nature nor it is directly used finally in this form, yet it is so widely produced and is the most popular high grade energy. The purpose behind training is to understand the difficult concepts in a better way with gain of knowledge. Report starts with a brief introduction of KaTPP. While writing the report and while i was on my training i was wondering that Science and technology are as ever expanding field and the engineers working hard day and night and make the life a gift for us. NEERAJ PATIDAR 4th Year EE 12EGJEE733
  • 5. [5] CONTENTS S.NO. TITLE PAGE NO.  FRONT PAGE ....  CIRTIFICATE FROM ORGANIZATION .... 1. CHAPTER 1: INTRODUCATION………...…………………………… 01-08 1. INTRODUCATION..........................................................................…...01 1.1. INTRODUCATION OVERVIEW OF KaTPP…………….......….…...03 1.2. ENERGY GENERATED IN KaTPP………...…….….……......…….. 05 1.3. PLANT OVERVIEW……………………………….…..…..…....…… 06 1.4. PRINCIPLE OF OPERATION…………….......................................... 06 1.5. THERMAL PLANT OPERATION PROCEDURE……….……....…..06 1.6. PULVERSIZED COAL FUELED POWER PLANT….………………08 2. CHAPTER 2 : COAL HANDLING PLANT (CHP)…………………… 10-11 2.1. INTODUCATION………….………………..…………………..……. 10 2.2. STAGES OF COAL HANDLING PLANT…………….…….............. 11 3. CHAPTER 3 : IMPORTANT PARTS OF THERMAL POWER PLANT.............................................................................................................15-23 3.1. BOILER……………………………………………………..……….... 15 3.2. TURBINE………………………………….…………….……….….....16 3.3. GENERATOR………………………….……………….…………...... 19 3.4. CONDENSER…………………………..…………………………..… 21 3.5. COOLING TOWER………………………….……………………….. 21  COLLEGE CERTIFICATE .....  ACKNOWLEDGMENT ….  ABSTRACT .....  PREFACE ….  TABLE OF CONTENTS .....  LIST OF FIGURES ......  LIST OF TABLES ......
  • 6. [6] 3.6. WATER TREATMENT PLANT……………………...…………...…. 23 4. CHAPTER 4 : ESP AND AHP SYSTEM………………………………… 26-30 4.1. ELECTROSTATIC PRECIPITATOR (ESP)……………………….... 26 4.2. ASH HANDLING PLANT (AHP)……….…………………………....30 5. CHAPTER 5 : CONTOLLING AND TRANSMISSION SYSTEM……. 32-39 5.1. CONTOL AND INSTRUMENTATION SYSTEM………..….….….. 32 5.2. CONTROL ROOM…………………………………………………… 36 5.3. AUXILLARY SUPPLY ……………………………………………… 37 5.4. SWITCHYARD ………………………………………………...…….39 6. CHAPTER 6: EFFICIENCY AND CONCLUSION…………………………46 6.1. EFFICIENCY…………………………………………………….….... 46 CONCLUSION……………………….………………………………………….… 47 REFRENCE…………………….………………………………………………….. 48
  • 7. [7] LIST OF FIGURE FIG.NO. FIG.NAME PAGE NO. 1. General layout : Thermal power plant 1 1.1 Percentage of electricity produced by different sectors 2 1.2 Overview of KaTPP 3 1.3 Operation principal 6 1.4 Pulverized coal fueled power plant 8 2.1 Coal handling plant 14 3.1 Boiler 15 3.2 Turbine 17 3.3 Generator 19 3..5 Cooling Tower 22 4.1 Electrostatic Precipitation Unit 30 4.2 Fly ash system 31 5.3 Switching and transmission 38 5.4 Overview of switchyard 45 LIST OF TABLE S.NO. TITTLE PAGE NO. 1.3 Plant overview 5 2.1 Coal handling detail 11
  • 8. [8] 2.2 Crusher /ring granulator Specification 12 3.2 Turbine Specification 18 3.3 Generator specification for unit i and ii 20 3.4 Diesel generator 20 ABSTRACT A steam-electric power station is a power station in which the electric generator is steam driven. Water is heated, turns into steam and spins a steam turbine. After it passes through the turbine, the steam is condensed in a condenser. The greatest variation in the design of steam-electric power plants is due to the different fuel sources. The site of Kalisindh Thermal Power Project is located in Nimoda, Undal, Motipura, Singhania and Devri villages of Tehsil Jhalarapatan, Distt. Jhalawar. The proposed capacity of coal based Thermal Power Project is 1200 MW. The project site is about 12 km from Jhalawar (Distt. Head quarter ) and NH-12 .It is 2km from state highway No.19 and 8 km from proposed Ramganj Mandi - Bhopal broad gauge rail line. The site selection committee of Central Electricity Authority has visited the Nimodha and its adjoining villages of Jhalawar Distt. And site was found techno-economical feasible for setting up of a Power Project. The Govt. of Raj. have included that project in 11 th five year plan. The estimated revised cost of the project is Rs.7723 Crores. M/s. TCE Banglore has been appointed as the technical consultant for the project. The state irrigation department has alloted 1200 mcft water for the project from proposed Kalisindh dam. The existing Dam is located at Bhawarasa village, primarily for P.H.E.D. purpose is being uplifted for providing a storase of 1200mcft water for this power project. The GOR has alloted 842 bigha Government land and aquired 1388 bigha private khatedari land for the thermal project .Phase-1 will be constructed on 1400 bigha land only.EPC contract has been awarded to M/s. BGR Energy System Chennai on
  • 9. [9] dt.09/07/08, through ICB route at cost Rs.4900 Crores. Ministry of coal, Govt. of India has alloted ‘Paras east and Kanta basin ‘ coal blocks to RVUN in Chhatisgarh state. The RVUN has formed new company under joined venture with M/s. Adani Enterprises for mining of coal blocks and new company started the work. Annual coal requirement for the project is 56 LacsTPA. GOR also decided to setup two new units of 2x660 MW in next few years
  • 10. [10] CHAPTER - 1 INTRODUCATION Everybody must be having a thought that a thermal power plant is a place where electricity is produced. But do you know how it is produced? How the chemical energy stored in fuel is converted into heat energy which forms the input of power plant i.e. steam and electrical energy produced by generator? Power is the single most important necessity for common people and industrial development of nation. In a conventional power plant the energy is first converted to a mechanical work and then is converted to electrical energy .Thus the energy conversions involved are: The first energy conversion takes place in Boiler or Steam Generator, second in Turbine and the last conversion takes place in the Generator. A thermal power station is a power plant in which the prime mover is steam driven. Water is heated, turns into steam and rotates the turbine which drives an electrical generator after that steam pass through in a condenser where it condensed and recycled to again in boiler; this whole cycle is known as RANKINE CYCLE. Fig-1: General Layout: Thermal Power Plant
  • 11. [11] CONTRIBUTATION OF THERMAL POWER PLANT IN INDIA In India, Thermal Power Plant contribute about 60% of the total electricity produced. Pie chart shows the electricity production percentage by different sectors- Power Installed Capacity = 253.390 GW As of 31st August 2014 Thermal 176,118.6 MW Hydro 40,798.8 MW Nuclear 4,780 MW Renewable 32,307.71 MW Total 254,005.1 MW Fig 1.1-Percentage of Electricity Produced by Different Sectors
  • 12. [12] 1.1 INTRODUCATION OVERVIEW OF KaTPP Fig 1.2 -Overview of KaTPP
  • 13. [13] Kalisindh Thermal Power Project is located in Jhalawar. The project site is about 12 km from Jhalawar (Distt.-Head quarter) and NH-12. Site is comprising of 5 villages viz. Nimoda, Undal, Motipura, Singharia and Devri. It is 2km from state highway No.19 and 8 km from RamganjMandi - Bhopal broad gauge rail line The site selection committee of Central Electricity Authority has visited the Nimodha and its adjoining villages of Jhalawar Distt. And site was found techno- economical feasible for setting up of a Power Project. The Govt. of Raj.have included that project in 11thfive year plan. The estimated revised cost of the project is Rs.7723 Crores. M/s. TCE Banglore has been appointed as the technical consultant for the project. The state irrigation department has allotted 1200 mcft water for the project from proposed Kalisindh dam. The origin of the Kalisindh river is from northern slop of Vindya Mountains. The river enters from MP to Rajasthan near village Binda. After flowing 145 km in Rajasthan, the Kalisindh river merges in Chambal river near Nanera village of Distt. Kota.Its catchment area is about 7944 sq.km in Jhalawar & Kota Distt. The existing Dam is located at Bhawarasa village, primarily for P.H.E.D. purpose is being uplifted for providing a storage of 1200mcft water for this power project. The GOR has allotted 842 bigha Government land and acquired 1388 bigha private khatedari land for the thermal project .Phase-1 will be constructed on 1400 bigha land only.EPC contract has been awarded to M/s. BGR Energy System Chennai on dt.09/07/08,through ICB route at cost Rs.4900Crores. Ministry of coal, Govt. of India has allotted Paras east and Kanta basin coal blocks to RVUN in Chhattisgarh state. The RVUN has formed new company under joined venture with M/s. Adani Enterprises for mining of coal blocks and new company started the work. Annual coal requirement for the project is 56 LacsTPA.GOR also decided to setup two new units of 2x660MW in next few years. 2*600 KALISINDH THERMAL POWERP ROJECT- JHALAWAR o OWNER -RVUNL o OWNER’S CONSULTANT - TATA CONSULTING ENERGY LTD. MUMBAI o EPC - BGR ENERGY SYSTEM LTD. o CONTRACTOR - CHENNAI
  • 14. [14] 1.2 ENERGY GENERATED IN KaTPP  Number of units=2  Electricity generated by one unit=600 MW  Total electricity negated by plant=2x600=1200 MW TABLE - 1.3:PLANT OVERVIEW Project Kalisindh Super Thermal Power Project Jhalawar Capacity 1200MW(2x600 MW) Project Site Village-Undel, Motipura, Nimoda, Singhania & Deveri of Tehsil Jhalarapatan, Distt-Jhalawar Project Location The project site is about 12 km from NH-12, 2km from state highway and 8 km from proposed Ramganj Mandi-Bhopal broad gauge rail line. Land Area 2230 Bigha/564 Hq.(1400 bigha/350 Hq. in I stage) Water Source and quantity Dam on Kalisindh river and 3400CuM/Hrs. Fuel Source Main Fuel-Coal from captive coal blocks(Paras east and kanta Basin in Chhatisgarh state) Secondary Fuel-FO/HSD Quantity of fuel(at 80% PLF) Coal-56 Lacs TPA FO/HSD-13000-14000 KL/A ElectroStatic Precipator 99.9 % Capacity Stack Height 275 Mtr Estimated revised cost Rs.7723 Crores
  • 15. [15] 1.3 PRINCIPLEOF OPERATION For each process in a vapour power cycle, it is possible to assume a hypothetical or ideal process which represents the basis intended operation and do not produce any extraneous effect like heat loss.  For steam boiler, this would be a reversible constant pressure heating process of water to form steam.  For turbine,the ideal process would be a reversible adiabatic expansion of steam.  For condenser, it would be a reversible a constant pressure heat rejection as the steam condenser till it becomes saturated liquid.  For pump, the ideal process would be the reversible adiabatic compression of liquid ending at the initial pressure. When all the above four cycles are combined, the cycle achieved is called RANKINE CYCLE. Hence the working of a thermal power plant is based upon Rankine Cycle with some modification. Fig 1.3 – Operation principal 1.4 THERMAL PLANT OPERATION PROCEDURE The basic understanding of the modern thermal power station in terms of major systems involved can be done under three basic heads viz. generating steam from coal, conversion of thermal energy to mechanical power and generation & load dispatch of electric power.  COAL TO STEAM- The coal is burnt at the rate upto 200 tonnes per hour. From coal stores, the fuel is carried on convey or belts to bunkers through coal tipper. It then falls in to coal pulverizing mill, where it is grounded into powder as fine as flour. Air is drawn into the boiler house by drought fan and passed through
  • 16. [16] Preheaters. Some air is passed directly to bunker and rest, through primary air fan, to pulverizing mill where it is mixed with powdered coal. The mixture is then carried to bunker of furnace where it mixes with rest of the air and burns to great heat. This heats circulating water and produces steam, which passes to steam drum at very high pressure. The steam is then heated further in the Superheater and fed to high pressure cylinder of steam turbine. . The spent steam is sent to condenser, where it turns back to water called condensate. Condensate is sent tolower part of steam drum through feed heater and economizer. The flue gases leaving boiler are used for heating purpose in feed heater, economizer, and air Preheater. The flue gases are then passed to electro-static precipitator and then, through draught fan, to chimney.  STEAM TO MECHANICAL POWER- Steam first enters the high pressure cylinder of turbine where it passes over a ring of stationary/fixed blades which acts as nozzle and directs steam onto a ring of moving blades. Steam passes to the other cylinders through reheater and the process is repeated again and again. This rotates the turbine shaft upto 3000rpm. At each stage, steam expands, pressure decreases and velocity increases.  MECHANICAL POWER TO ELECTRICAL POWER- To obtained the electrical power from mechanical power we connect the shaft to an alternator’s armature. When the armature is rotated and electric current is produced in the stator’s windings. The generated electricity is of order 25,000 volts.  SWITCHING AND TRANSMISSION-The produced electricity is can’t to transmitted as this state so It is passed to a series of three switches called an isolator, a circuit-breaker, and another isolator. From circuit-breaker, current is taken to bus bars and then to another circuit-breaker with it’s associated isolator before being fed to the main Grid. Each generator has its own switching and transmission arrangement. Three-phase system is used for power transmission.
  • 17. [17]  CONTROL AND INSTRUMENTATION- Control and Instrumentation (C & I) systems are provided to enable the power station to be operated in a safe and efficient manner while responding to the demands of the national grid system. These demands have to be met without violating the safety or operational constraints of the plants. For example, metallurgical limitations are important as they set limits on the maximum permissible boiler metal temperature and the chemical constituents of the Feed water. The control and Instrumentation system provides the means of the manual and automatic control of plant operating conditions to maintain an adequate margin from the safety and operational constraints. 1.5 PULVERIZED COAL FUELED POWER PLANT A typical pulverized coal fueled power plant is based on Rankine Thermodynamic cycle. “A Rankine cycle is a vapour cycle Furnace that relies on the isentropic expansion of high pressure gas to produce work”.Let us see a super heat Rankine cycle: Fig1.4- Pulverized Coal Fueled Power Plant This facility first produces steam in a boiler (steam generator). This steam is used to rotate turbine which is connected to a shaft of generator. Hence electricity is produced here. The used steam is then condensed in a condenser, and the condensed liquid is used again in the steam generator. This is a simple phenomenon, understood by everybody. For all this we need a fuel. As the name suggest here coal is used as fuel. Coal is one of the cheapest and most preferred fossil fuel used as a key to most of the power
  • 18. [18] plants.Usually delivered by train from Mines to the Coal Handing Plant (CHP). The CHP unloads this it become more economical to unload the coal. Then the coal stacked, reclaimed, crushed, and conveyed it to the storage silos near the steam generator. Then it is fed through the Feeder to the Pulverizer. Feeder is mainly used to weight the amount of coal going to the Pulverizer per hour. From the Feeder the coal is fed to the Pulverizer which powders it and then it is carried to the steam generator using pressurized air. Within the steam generator the coal is atomized and burned and the heat energy produced is used for producing steam. Here two types of steam namely superheated & reheated steam are produced in a cycle. The steam turbine generator converts the thermal energy of superheated and reheated steam to electrical energy. The first energy conversion is carried in Boiler or steam generator; the second is carried out in Turbine and the last one carried out in the Generator. Cooling water for the condenser is supplied by the circulating water system, which takes the heat removed from the condenser and rejects it to the cooling towers or other heat sink. This all working is controlled from a single place called control room. It enables the operator to direct the plant operation for reliable and efficient production of electrical energy. This is achieved by the control system installed by the C & I group. These are DAS (Data Acquisition System), ACS (Analog Control System), FSSS (Furnace Safeguard Supervisory System), and other relays governing numerous activities. Last but not the least is the switching and transmission methods used here. The generated power cannot be transmitted as such. It is stepped up to 132 KVA or 400 KVA then passed through a series of three switches an isolator, a circuit breaker and an isolator. Three phase system is used for the power transmission.Each generator has its own switchyard and transmission arrangement.
  • 19. [19] CHAPTER-2 COAL HANDLING PLANT (C.H.P.) 2.1 INTRODUCTION: Every thermal power plant is based on steam produced on the expanse of heat energy produced on combustion of fuel. Coal is categorized as follows depending upon fixed carbon, volatile matter and moisture content:  Anthracite having 86% fixed carbon  Bituminous having 46 to 86% fixed carbon  Lignite having 30% fixed carbon and  Peat having 5 to 10% fixed carbon Coal from mines is transported to CHP in railway wagons. It is unloaded in track hoppers. Each project requires transportation of large quantity of coal mines to the power station site. Each project is established near coal mine which meets the coal requirements for the span of its entire operational life. For the purpose each plant has Merry Go-Round (MGR) rail transportation system. The loading operation of the coal rake takes place while it is moving under the silo at a present speed of 0.8 Km/hr. the loading time for each wagon is one minute. For unloading of coal from the wagons an underground track hopper is provided at the power station. The term coal handling plant means to store and to handle the coal which is transported by the train and convey to the bunkers with the help of belt conveyers. Through the bunkers coal is transferred to the coal mill and drifted to the furnace. The coal handling plant includes wagon tippler, conveyer belt, crusher house, stacker & reclaimer, bunkers & coal mill. COAL SUPPLY IN KaTPP-Ministry of coal, Govt. of India has allotted Paras east and Kanta basin coal blocks to RVUN in Chhattisgarh state.
  • 20. [20] 2.2 STAGES OF COAL HANDLING PLANT  WAGON TIPPLER-The term Wagon Tippler contains two words WAGON & TIPPLER .Wagon means the compartment of train which is just like a container which is used to carry the coal from mines to generating stations & the word Tippler means a machine, which is used to unload the wagon into the hopper. Hopper is just like a vessel which is made of concrete & it is covered with a thick iron net on its top. Here big size coal pieces are hammered by the labors to dispose it into the hopper. TABLE – 2.1:Coal handling detail Capacity 90 tonnes Types of Tipplers 1.Weighing type,2.Non weighing type Angle of Tip 30 ‘to35’ Wire Ropes 1.Hoisting Ropes, 2.Counter Weight Ropes Drive unit Motor 37.3 KW Operating Cycle 10 wagons/Hour on 1 wagon Tippler Time consume for one cycle 6 minutes  FEEDER- It is used to control the supply of crushed coal to the mill depending upon load condition.It is installed under wagon tippler and hopper.In KaTPP there are 4 unbalanced Motor Vibrating Feeder installed in unit 1st.  CHRUSHER/RING GRANULATOR-In ring granulator the material is fed in to the crushing chamber and is crushed by the rind hammers with impact and rolling action across the feed, with concentrated pressure.This cracks the coal producing a granulator product with a minimum of fines up to 20 mm square.
  • 21. [21] TABLE – 2.2:Chrusher /ring capacity Capacity 500 Tonnes/hr Machine Weight 30 Tonnes(approx.) Max Feed Rate 500 Tonnes/hr Rotor Speed 720 r.p.m Motor 550 H.P Volts 606 KV Phase 3 Phase motor  CONVEYORS-Conveyor belt is used to sent the coal from coal storage yard and also used to sent crushed coal from store to mill bunkers.The carrying capacity of conveyors belt is 750 tonnes/hrs that are installed in KaTPP. Conveyor belt used in coal handling plant(CHP) are of 2 types 1. 5 ply x1000 mm width with 5 mm rubber top side and 5 mm rubber bottom side. Total thickness of belt:-17 to 18 mm Power:-1000KN/m2 2. 4 Ply x1000 mm width with 5mm rubber top side and 5 mm rubber bottom side. Total thickness of belt:-17mm Power:-800KN/m2 Cold joint are used in joining the conveyor,conveyor belts run with the help of electric motor ,gear box,fluid coupling geared coupling are installed at head of allconveyors.  PARTS OF CONVEYORS: 1) Flap Gate-it provide under coal transfer chutes for replacements of crusher/conveyors.
  • 22. [22] 2) Deflector Plate-Deflector plates are installed in the chutes coming on conveyors to keep the coal direction in the centre of the conveyors. 3) Skirt board and Skirt rubber-These are provided on tail end chutes to avoid spillages of coal from Conveyors. 4) Stone picker-Stone picker pick the stonesfrom the running belt manually. 5) Metal Detactor-Electromagnets are provide on conveyors to avoid and to save crusher parts and entry of iron pieces in crusher.It also stop the entry of iron pieces in coal bunker to save damage of coal mills. 6) Guide Idlers-These idlers help to train/guide the conveyors. 7) Return Idlers-These idlers carries the conveyors belts in return side. 8) R.T.I (Return Training Idler)-These idlers are provided on return side to guide the conveyors. 9) Impact Idler-These Rubber idlers are provided under chutes through which coal falls on conveyors. 10) Carrying Idlers-These are installed to run the conveyor.  BUNKERS-Bunckers are fabricated to store the coal before sending to coal mills.Coal is fed in the bunkers with the help of tripper trolleys installed at 37 m height for unit 1st and 2nd.These are 20 bunkers for unit 1st and 2nd. Capacity of a bunker=500 tonne/bunker.  COAL BUNKERS-These are in process storage used for storing crushed coal from the handling system.Generally these are made up of the welded steel plates with vibrating arrangement of the outlet to avoid chocking of coal, normally there are six bunker supply coal to the corresponding mills.These are located on the top of mills so as to add gravity feeding of coal.
  • 23. [23]  RECLAIM YARD-After filing the coal bunkers extra coal is taken to reclaim yard after crushing of coal to storage.  COAL CIRCULATION-Coal is transported from the coal mine with the help of train.Train wagons are emptied with the help of wagon tipplers and sent to the crusher for crushing.From coal crusher it goes to the bunker through conveyor belt and from coal bunker it move to R.C feeder feeds coal to the coal mill,where the coal is ground in to powder from. Fig2.2-coal handling plant
  • 24. [24] CHAPTER-3 IMPORTANT PARTS OF THERMALPOWER PLANT 3.1 BOILER Boiler can simply defined as the device where any liquid is boiled or Boiler may be defined as a device that is used to transfer heat energy being produced by burning of fuel to liquid, generally water, contended in it to cause its vaporization. Boiler, in simple terms, can be called “Steam Generator”. In simple way, boiler is a device used for producing steam. There are two types of boiler (depending upon tube content): a) Fire tube boiler b) Water tube boiler Here, boiler used is of water type. In the boiler, heat energy transfer takes place through tube walls and drum. The gases lose their heat to water in the boiler or superheated. The escape heat is used to heat the water through economizer. ID and FD fans are used to produce artificial draught. The fuel oil is used to ignite the boiler and pulverized coal is lifted from the coal mills by PA fans. Various motors use in boiler are different rating and parameters 32KW,15KW ,11KW & 3.3KW. Fig 3.1-Boiler
  • 25. [25] BOILER AUXILIARIES-Efficiency of a system is of most concerned. Thus it is very important to maintain a system as efficient as possible. So Boiler auxiliaries help in improving boiler’s efficiency. Following are the important auxiliaries used  ECONOMISER: Its purpose is to preheat feed water before it is introduced into boiler drum by recovering heat from flue gases leaving the furnace.  SUPER HEATER: It increase the temperature of steam to super heated region.  REHEATER: It is used for heat addition and increase the temperature of steam coming from high pressure turbine to 540 deg.  DRAFT FANS: They handle the supply of air and the pressure of furnace. BOILER MOUNTINGS-These are used for the safe operation of boiler. Some example of mountings used are water level indicator in drum, furnace temperature probe, reheat release valve, pressure gauges indicating steam pressure etc. 3.2 TURBINE Turbine is an m/c in which a shaft is rotated steadily by the impact of reaction of steam of working substance upon blades of a wheel. It converts the potential energy or heat energy of the working substance into mechanical energy. When working substance is steam it is called ‘Steam Turbine’ In the steam turbine the pressure of the steam is utilized to overcome external resistance and the dynamic action of the steam is negligibly small.  PRINCIPLE-Working of the steam turbine depends wholly upon the dynamic action of steam. The steam is caused to fall with pressure in a passage of nozzle, due to this fall in pressure, a whole amount of heat energy is converted into mechanical energy & steam is set moving with the reactor velocity. The rapidly moving particle of steam enter the moving part of turbine and here suffers a change in the direction of motion which givesrise to change of momentum and therefore to a force. This constitutes a driving force to a turbine.
  • 26. [26] The passage of them/through the moving part of the turbine commonly called the blade, may take place in such a manner that the pressure at the outlet sides of the blade is equal to that of the inlet side. Such a turbine is broadly termed as outlet turbine or Impulse type. On the other hand, the pressure of the steam at outlet from the moving blade may be less than that at type inlet side of the blade. The drop of pressure suffered by the steam during its flow through the moving blades causes a further generation of kinetic energy within the blades and adds to the propelling force which is applied to the turbine rotor, such a turbine is broadly termed as Reaction Turbine. Here in Kalisindh Thermal Power Project N600-16.7/587/537,Re-Het,Three Casing, Four Exhaust, Tandem Compound Condenser Type Turbine Used. The turbine is of tandem compound design with separate High Pressure(HP),Indermediate Pressure(IP) and Low Pressure(LP) cylinders. The HP turbine is of Single Flow type while IP and LP turbines are of Double Flow type . The readily designed HP,IP and LP turbines are combined and sized to required power output,steam parameters and cycle configuration to give most economical turbine set.The design and constructional feature have proved their reliability in service and ensure trouble free operation over long operating periods and at the same time ensuring high thermal efficiencies. Fig 3.2-Turbine
  • 27. [27] TABLE – 3.2: TURBINE SPECIFICATION- Rated output with extraction flow 600 MW Speed 3000 r.p.m Main steam throttle flow at HP Inlet 1848.5 TPH Main steam pressure to HP turbine inlet 167 kg/sq.cm Main steam temp. to HP turbine inlet 538 deg.cel Re-heater steam flow at IP inlet 1587.942 TPH Re-heater steam temp. at IP inlet 538 deg.cel Steam pressure at LP inlet 35.12 kg/sq.cm Steam flow at LP inlet 1353.7 TPH Rotation Direction(view from turbine) anticlock wise Number of stages 42 High pressure turbine- a) Intermediate pressure b) Low pressure turbine c) Governing system 1 governing and 8 pressure 5 pressure stage 28 pressure stage DEH(digital electro hydraulic) Inlet steam flow governing type Nozzle+throttle Rated exhaust pressure 0.09 kg/sq.cm Type of bearing turbine 6 journal +1 thrust Turbine allowable frequency 47.5 to 51.5 Hz Turning gear rotation speed 1.5 r.p.m Ist critical speed of HP & LP rotor 1722 r.p.m Ist critical speed of LP-A rotor 1839 r.p.m Ist critical speed of LP-b rotor 1903 r.p.m Heat regenerative extraction system 3HP htr+1 deaerator+4 LP htr Final feed water temperature 274.9 deg.cel Maximum bearing vibration 0.076 m Maximum allowable exhaust temp. 80 deg.cel. Coolling water design flow at condenser 70200 TPH
  • 28. [28] 3.3 GENERATOR Generator is the important part of thermal power plant.It is device which convert the mechanical energy into electrical energy.Generator is driven by coupled steam turbine at a speed of 3000 r.p.m.Due to rotation at high speed it get heat.So there is cooling construction enclosing the winding core of the genetator.So that during the operation is being in normal temperature. In KaTPP , Each of the 2 units have been provided with 3-phase turbo generator rated output 706MVA, 18.525KA, 22KV, 0.85 lagging p.f., 984 rpm and 50 cycles/sec .The generator has closed loop of hydrogen gas system for cooling of the stator and rotor at a pressure of 4.5kg/sq-cm(g). Fig 3.3 – Generator
  • 29. [29] GENERATOR SPECIFICATION FOR UNIT I AND II:- TABLE – 3.3:Generator Specification Make CQ GEARBOX China Type QFSN Apparent output 706 MVA Active output 600 MW Power factor 0.85 lagging Rated voltage 22 KV Rated current 18525 Amp Rated speed 3000 r.p.m Frequency 50 Hz Phase connections Double gen.star Cooling mode H20-H2-H2 Rated H2 pressure 4.5 Kg/sq-cm Terminal in generator 6 DIESEL GENERATOR SET It is used to emergency porpuse to supply auxillary system of power plant.3 Set Diesel generator are use in which one is standby. parameters of generator are as Table-3.3:Diesel Generator Specification Make BY STAMFOARD MAHARASTRA INDIA Rating 1900 KVA Speed 1500 R.P.M Rated Current 2643.37 A Rated Temp 40 Degcel AMPS 3.6 A
  • 30. [30] 3.4 CONDENSER In condenser, the water passes through various tubes and steam passes through a chamber containing a large number of water tubes (about 20000). The steam gets converted into water droplets,when steam comes in contact with water tubes. The condensate is used again in boiler as it is dematerialized water and 5-6 heats the water, which was in tubes, during the process of condensation. This water is sent to cooling tower. Condenser is installed below the LP exhaust. The condenser is of surface type made of fabricated construction in single shell. The tube is of divided type double pass arrangement, having two independent cooling water inlet, outlet and reverse and water boxes. This arrangement facilitates the operation of one half of condenser when the other half is under maintenance. The condenser is provided with integral air-cooling zone at the centre from where air and non-condensable gases are continuously drawn out with the help of mechanical vacuum pump.  Area of condenser = 9655 sq m  Cooling water flow rate = 2400 cubic m/Hr. 3.5 COOLING TOWER It is used to reject heat into the atmosphere. There are two types of the cooling tower. (1) Natural draft. (2) Forced draft. Natural draft - tower used vary large concrete chimney to introduce air through the media. They are generally used for water flow rate about 45000 m3 /hour. It is used in utility power station. Here hight of cooling tower is 202M. Forced draft- tower utilize large fans to force or suck air through circulating water. The water falls downward over fills surface which helps in increase the contact time between the water and air. This held maximize heat transfer between two media. Cooling rates depend upon fan diameter and speed. This type of tower much wider used.
  • 31. [31] In KaTPP two natural draught cooling towers (2 NDCT) is present with height 202 m each for each unit. It is a structure of height 202 m (tallest in the world) designed to cool the water(coming from condenser) by natural draught. The cross sectional area is less at the centre just to create low pressure so that ate air can lift up due to natural draught and can carry heat from spherical drops. The upper portion is also diverging for increasing the efficiency of cooling tower. Hence it is named as natural draught cooling tower. This structure is constructed in r.c.c. shell poud floor and its derified water channel c.w. For bay. The entire structure is supported combined circular rafting constructed in different segments with slanted colomn fotting to support 17 m hight circular sectional reckarcolmns. This r.c.c. shell of 150 m dia. And 205 m height . It is made of m 50 grade r.c.c. Which was also done at sight. There will be 200 colomnspoud floors that will generate cascading effect for cooling. The cooling tower shell be capable of cooling the rated quality of water Fig 3.5-Cooling Tower
  • 32. [32] 3.6 WATER TREATMENT PLANT As everyone know that the cost of any thermal power plant is cores of rupees.So major problem of any thermal power plant is that how to prevent the corrosion. The water available can’t be used in boilers as such. The objective of water treatment plant is to produce the boiler feed water so that there shall be.  No scale formation ·  No corrosion ·  No priming or forming problems Water used in thermal power plant is called ‘Dematerialized Water’ or DM Water. The treated water is called ‘Dematerialized Water’. The treatment process can be divided in two sections: 1. Pre-treatment section. 2. Demineralization section PRE-TREATMENT SECTION:- Pre-treatment plant removes suspended solids like clay, salt, plants, micro-organisms etc form raw water to give clarified water. Suspended solids can be separable or non-separable. Separable solids are heavier & large and can easily be removed by an aerator. Non-separable solids have finer size and take long to settle down. Hence they are required to be flocculated. In this, water is first dozed with lime and alum. This forces finer particles to coagulate increasing their weight and size. Non-separable solids can now be separated in clariflocculator. The clarified water is then stored in clarified water storage tanks. DEMINERALISATION SECTION The clarified water now goes to FCA (activated carbon filter) where it de-chlorinated. Water then passes through cation exchanger where weak and strong acidic cations are removed on adding resin. Water Treatment Stage:- River (raw water) → Clarification → Filtration → Demineralization
  • 33. [33] CLARIFICATION AND FILTERATION OF WATER:- River water contains different impurities i.e.  Suspended impurities  Biological impurities  Soluble impurities  Colloidal impurities WORKING:- The raw water enters through valve and than chemicals is added. Chlorine and alum are added. Chlorine is added to remove bacteria etc. Alums are added to make the impurities heavier, once the impurities become heavier than a no. of flocs are formed. By mixing the alums, heavy impurities are settle down due to gravity and later removed. The time required for the formation of floc is called retention time which is generally 3 hours but this can’t be achieved as it require large tank. In order to cope up the limitation CLARRIFOCCULATION TANK is used. This flocculation tank is consist of 1. Clarification zone 2. Flocculationzon Clarrifocculation tank has a central pillar which has four windows at 90 degree. The outer circle is half of windows so that level of water is arise then it flows down through these windows into overflow channel. After mixing from flash mixer, the water passes on to central pillar and follows the path as shown in fig. i.e. it moves to max. Floc area and comes out from window at 3.5 m height. The downward flow is through perforated wall which sinks the raw water. Due to the long path a retention time of 4 hour is easily available. The capacity of water in this plant is 1000*1000 lt./hr.In flocculation zone max.floc is formed and after removing it, the clear water moves into clarifier. Some impurities are weightless and do not settle down so they are passed through filter beds. There are two types of filter beds. 1. Gravity filter bed. 2. Forced filter bed.
  • 34. [34] In FORCED FILTER BEDS raisins are added to settle down the impurities. In GRAVITY FILTER BEDS graded gravels are arranged. At bottom gravels of big size are there and above other gravels are arranged according to size. Above it grit and most of the above is sand. The clarified water enters into sump. Sump is fully closed leaving one window to see the level. Since it is fully closed hence no foreign matter can enter into it. 3.2 DEMINERALIZING PLANT Water is mainly used for cooling purpose of different parts like bearing winding etc. in KaTPP. For this water should be Demineralized (D.M. water). In this plant process water is freed from all dissolved salts. Equipments for demineralization plant is supplied and erected by GE INDUSTRIAL (India) Ltd.This plant consists of two streams, each stream with activated carbon filter, weak acid, carbon exchanger and mixed bed exchanger. The filter water goes to DM water plant through 250 dia header from where a header top off has been taken off to softening plant. Two filtered water booster pumps are provided on filtered water line for meeting the pressure requirement in DM plant. When pressure drop across filter exceeds a prescribed limit from the activated carbon filter enter works acid carbon unit. The dilation water enter the weak base anion exchanger unit water then enters degassifier unit where free CO2 is scrubbed out of water by upward counter flow of low pressure air flow through degassifier lower and degassed water is pumped to strong base exchanger(anion–exchanger). PH VALUE OF WATER:- This is recommended to feed the water in the boiler at 25 degree centigrade and pH value is 8.2 to 9.2 up to 28 days and the pressure is 59 Kg cm2.
  • 35. [35] CHAPTER 4 ESP AND AHP SYSTEM 4.1 ELECTROSTATIC PRECIPITATOR (ESP): Electrostatic Precipitator (ESP) is equipment, which utilizes an intense electric force to separate the suspended particle from the gases. In India coal is widely used to generate power. The exhaust gases are emitted directly into the atmosphere, it will cause great environmental problems. So it is necessary to extract this dust and smoke before emitted the exhaust gases into atmosphere. There are various methods of extracting dust but electrostatic precipitator is the most widely used. It involves electric changing of suspended particle, collection of charge particles and removal of charge particles from collecting electrode. Its various other advantages are as follows:  It has high efficiency i.e. about 99%  Ability to treat large volume of gases at high temperature  Ability to cope with the corrosive atmosphere.  It offers low resistance to the flow of gases.  It requires less maintenance. WORKING PRINCIPLE- The electrostatic precipitator utilizes electrostatic forces to separate dust particles from the gases to be cleaned. The gas is passed through a chamber, which contains steel plates (vertical) curtains. Theses steel curtains divide the chamber into number of parallel paths. The framework is held in place by four insulators, which insulate it electrically from all parts , which are grounded. A high voltage direct current is connected between the framework and the ground, thereby creating strong electric field between the wires in the framework curtains. Strong electric field develops near the surface of the wire creates Corona Discharge along the wire.Thus ionized gas produces +ve and –ve ions. In the chamber plates are positively charged whereas the wire is negatively charged. Positive ions are attracted towards the wire whereas the negative ions are attracted towards the plates. On their way towards the curtains negative ions strike the dust particle and make them negatively charged. Thus is collected on the steel curtains.
  • 36. [36] The whole process is divided into the following parts:  Corona Generation  Particle Charging  Particle Collection  Particle Removal Details of the following are given below-  Corona Generation- Corona is a gas discharge phenomenon associated with the ionization of gas molecules by electron collision in regions of high electric field strength. This process requires non-uniform electric field, which is obtained by the use of small diameter wire as one electrode and a plate or cylinder as the other electrode. The corona process is initiated by the presence of electron in strong electric field near the wire. In this region of corona discharge, there are free electrons and positive ions . Both positive and negative coronas are used in industrial gas cleaning. In case of negative corona, positive ions generated are attracted towards the negative electrode or wire electrons towards collecting plates. On impact of negative and serve as principle means of charging dust.  Particle Charging- These are two physical mechanisms by which gas ions impact charge to dust particles in the ESP. Particles in an electric fields causes localized distortion in an electric filed so that electric field lines intersect with the particles of maximum voltage gradient, which is along electric field lines. Thus ions will be intercepted by the dust particles resulting in a net charge flow to the dust particles. The ions will be held to the dust particles by an induced image charge force between the ion and dust particle and become charged to a value sufficient to divert the electric field lines from particles such that they do not intercept.  Particle Collection- The forces acting on the charged particles are Gravitational, Inertial, Electrostatic and Aerodynamically. The flow of gas stream is turbulent flow because it causes the particles to flow in random path through ESP. Particles will be collected at boundary layers of collector pates. But if flow is laminar,
  • 37. [37] charge will act on particles in the direction of collecting electrode. This force is opposite to viscous drag force and thus in the short time, particle would achieve Terminal (Migration) velocity at which electrical; and viscous forces are equal. Thus the flow of the charged particle is decided by the vector sum of these forces i.e. Turbulent.  Particle Removal- In dry removal of dust collected on plates, Rapping Mechanism is used. It consider of a geared motor, Which moves along shaft paced near the support collector electrode and is provided with cylindrical hammer. On rotating of shaft these hammers strikes the supports causes plate to vibrates and dust is removed from plates. Removed dust is collected in the Hoppers below the precipitator. At the time of starting of precipitation of dust from flue gases, the hoppers are at normal temperature but the ash collected is very hot. So there is a chance of ash deposit at the exit of the hopper thus causing problem of removing the ash. To avoid this , heater are provide which increase the temperature at the exit point o the hopper thus avoiding any undue accumulation of ash at starting . In other method, the water is allowed to flow down the collector electrode and hence dust is collected in hoppers below. GENERAL DESCRIPTION- The whole ESP is divided into two parts-  Mechanical System  Electrical System Here we will discuss only Mechanical System (i.e. Precipitator Casing, Emitting and Collecting System and Hopper).  Precipitator Casing-Precipitator Casing is made of 6mm mild steel plates with required stiffness. The precipitator casing is all welded construction comprising of pre-fabricated walls and proof-panels. The roof carries the precipitator internals, insulator housing, transformer etc. Both emitting and collecting systems are hung from the top of the casing.
  • 38. [38]  Emitting and Collecting System- Emitting System is the most important part of ESP. Emitting system consists of rigid emitting frame suspended from four points on the top of rigid emitting electrodes in the form of open spiral. The four suspension points are supported on support insulators to give electrical insulation to the emitting frame. The frame is designed to take up the retention forces of the emitting electrode. The emitting electrode consists of hard drawn spiral wires and are fastened with hooks to the discharge frame. Collecting system mainly consists of collecting suspension frame, collection electrodes and shock bars. Collecting electrode are made of 1.6 mm thick Mild Steel sheets formed in ‘G’ Profile of 400mm width. Hook and guide are welded on one end and shock iron on the dipped in rust preventive oil tank. Collecting electrodes bundles are properly bundled in order to avoid any damage to electrode.  Hoppers- Hoppers are seized to hold the ash for 8-hour collection and is provided under the casing of ESP. It is of Pyramidal Shape and is 56 in number. It is preferred to evacuate the hoppers at the earliest as long storage of dust in hopper leads to clogging of hopper. Also at the bottom of hopper electrical heating is provided to avoid any condensation, which could also lead to clogging of hopper. Baffle plates are provided in each hopper to avoid gas leakage. RAPPING MECAHISM FOR COLLECTING SYSTEM- During electrostatic precipitation a fraction of dust will be collected on the discharge on the discharge electrodes and the corona will be suppressed as the dust layer grows. So rapping is done in order to remove this dust by hammering the electrodes. As the shaft rotates the hammer tumbles on to the shock bar that transmits the blow to the electrode. The whole rapping mechanism is mounted on a single shaft, which is collection of ash on the collecting electrode.
  • 39. [39] Fig 4.1 -Electrostatic Precipitation Unit 4.2 ASH HANDLING PLANT (AHP) The ash produced on the combustion of coal is collected by ESP. This ash is now required to disposed off. This purpose of ash disposal is solved by Ash Handling Plant (AHP). There are basically two types of ash handling process undertaken by AHP.  Dry Ash System  Ash Slurry System DRY ASH SYSTEM- Dry ash is required in cement factories as it can be directly added to cement. Hence the dry ash collected in the ESP hopper is directly disposed to silos using pressure pumps. The dry ash from these silos is transported to the required destination. ASH SLURRY SYSTEM- Ash from boiler is transported to ash dump areas by means of sluicing type hydraulic system which consists of two types of system-  Bottom Ash System  Ash Water System
  • 40. [40] BOTTOM ASH SYSTEM- In this system, the ash slag discharged from the furnace is collected in water impounded scraper installed below bottom ash hopper. The ash collected is transported to clinkers by chain conveyors. The clinker grinders churn ash which is then mixed with water to form slurry. ASH WATER SYSTEM-In this system, the ash collected in ESP hopper is passed to flushing system. Here low pressure water is applied through nozzle directing tangentially to the section of pipe to create turbulence and proper mixing of ash with water to form slurry. Slurry formed in above processes is transported to ash slurry sump. Here extra water is added to slurry if required and then is pumped to the dump area. FLY ASH SYSTEM-Even though ESP is very efficient, there is still some ash, about 0.2%,left in flue gases. It is disposed to the atmosphere along with flue gases through chimney. Fig 4.2 –fly ash system
  • 41. [41] CHAPTER-5 CONTROLLING, SWITCHINGAND TRANSMISSION 5.1 CONTROL AND INSTRUMENTATION SYSTEM 5.1.1 SWITCHGEAR The apparatus used for switching, controlling and protecting the electrical circuits and equipment is known as switchgear. A switch gear is one which makes or breaks electric circuit. Numerous problems arise in erection, testing and commissioning of switch gear and various precautions are to be made in operating and maintenance of switch gear. Essential Features of Switch Gear:-  Complete Reliability  Absolutely certain discrimination  Quick operation  Provision for manual control  provision for instruments The main components of indoor switchgear are given below:- 1) Bus-Bars 2) Isolating Switches 3) Current Transformers 4) Potential Transformers 5) Circuit Breaker 6) Earthing arrangement 7) Relays 8) Inter-Locking arrangements (i) BUS-BARS:- Bus bars are defined as the conductors to which several incoming and outgoing lines are connected. They are essential component of Switchgear. They are made up of Cu. and Al. The type and designers of Switchgear depends upon rated normal current and
  • 42. [42] short circuit capacity. The Bus bars are enclosed in bus bar chamber. In KaTPP there are two types of indoor switch gear: 11 KV &3.3KV or High tension3.415V or Low tension. (ii) ISOLATING SWITCHING:- 1. They are capable of-Interrupting the Transformer Magnetizing Current-Interrupting line charging Current.Interrupting load Transformer Switching. 2. The main application is in connection with feed or bank Transformer feeders & there units make it possible to switch out one Transformer while the other is still on load. (iii) CIRCUIT BREAKER:- They are capable of breaking the circuit on faults. It is heavy duty equipment mainly utilized for protection of various circuit and separation of loads. The Circuit Breaker uses on a relay or by manual signal. The Circuit Breakers which are used in Switchgear are VCB type. (iv) EARTHED SWITCHES:- Earthed switch is connected between line conductor and earth. Normally it is open when line is disconnected. The Earthing switched is closed so as to discharge the voltage trapped on line for high voltage and so the capacitor between line and earth is charged to high voltage. For maintenance work their voltage are discharged to earth by closing the earth switch. (vi) INTER-LOCKING:- The following type of inter- locking are provided The Circuit Breaker must be in open position before it is lowered in this position. The Circuit Breaker can be closed only raising the final plug in position. The Circuit Breaker can be closed before raising plug in position. Inter-locking between isolators, Earthing switches and Circuit Breakers are provided. (vii) RELAYS:- A Protective Relay is a device that detects the fault and initiates the operation of the circuit breaker to isolate the defective element from the rest of the system.
  • 43. [43] 5.1.2 PROTECTION The fault, which may occur in stator winding are- a. Phase to phase fault. b. Phase to ground fault. c. Line to line fault. d. Overheating. These faults are due to- 1. Over voltage is because of system transients, lightening switching surges or sudden loss of load. 2. Insulation deterioration due to any matter, moisture, corona discharge, Hardening of solid and vibration. It is very necessary to minimize the tripping time during any fault so that the lamination is not damaged. The repairing being affected by replacing the faulty stator bar.A delayed clearance may damage the lamination, so fire may be caused and partial re- insulation of core may be necessary. GENERATOR PROTECTION:- The Generator is required to be tripped or isolated on following types of fault:- 1. Failure of generating insulation. 2. Failure of prime mover turbine or boiler. 3. Failure of generating auxiliaries such as hydrogen gas system,seal oil system, cooling system, and cooling water system. 4. Failure of grid. The tripping command to the GT breaker is given by master trip relay 866, 86GT, and 86GB. To make it feasible the master trip relay is connected to a common bus. All the protection relays are connected in between the position of 220V. D.C. PROTECTION AND THE COMMON BUS:- Protection device are that detect abnormal condition in electrical circuit by measuring the electrical quantity which are different under normal and fault condition. The basic electrical quantities are voltage, current, phase angle and frequency.
  • 44. [44] The relay doesn’t operate for normal voltage, normal current, normal phase angle and normal frequency. Different type of protection can be listed as:. 1. Current operated protection. 2. Different protection. 3. Voltage operated protection. 4. Impedance type protection. 5. Frequency type protection. 1. CURRENT OPERATED PROTECTION:- a. Generator differential protection. b. Generator negative sequence protection. c. Generator output current protection. d. Generator stator earth fault protection. e. Generator REF protection. f. Generator standby earth fault protection. g. UAT o/c protection. h. Generator o/c and short circuit protection. i. L.B.B. protection. 2. DIFFERENTIAL PROTECTION:- a. Generator overall differential protection. b. UAT differential protection. 3. VOLTAGE OPERATED PROTECTION:- a. Generator over voltage protection. b. Generator stator E/F protection. c. GT over voltage protection. d. PT’s voltage supervision protection. e. Generator inter-turn fault protection.
  • 45. [45] 4. IMPEDANCE TYPE PROTECTION:- a. Generator back up impedance protection. b. Generator loss of exact protection. c. Generator pole slip protection. 5. FREQUENCY TYPE PROTECTION:- a. Generator under protection Frequency. REQUIREMENT OF PROTECTIVE DEVICES:  Selectivity: Only that part of the installation containing fault should is disconnected. Safety against faulty tripping: There should be no trip when there is no fault.  Reliability: The device must act within the required time.  Sensitivity: Lowest signal input value at which the device must act.  Tripping time: There should be a clear a distinction between the tripping time of the device, considering the circumstances such as current and total tripping time for the fault. 5.2 CONTROL ROOM Various measurements can be taken at the control room simultaneously. The second important part of the control room is relay part. Various relays are provided here BY AREVA LTD. CONTROL ROOM PANELS:- FAN CONTROL DESK: - 1. ID Fan (Induced draft fan, 2nos.) at full load. 2. FD Fan (Forced draft fan, 2nos.)at full load. 3. PA Fan (Primary air fan, 2 nos.) at full load.
  • 46. [46] PRESSURE CONTROL DESK: - 1. Furnace pressure (5-10mmwcl.). 2. Primary air header pressure (750-800mmwcl). FUEL CONTROL DESK:-Coal oil flow. Oil pressure. Temperature of mill (inlet or outlet) Flow of air. Drum level control, flow of steam water Pressure of steam and water. Temperature of steam and water. TURBINE DESK:- Pressure control, load mode control. Speed control. Ejector, control valves, stops valves and deviators. GENERATOR CONTROL PANEL:-Voltage, current, MVAR. Stator, rotor temperature. For stator cooling. 5.3AUXILIARY SUPPLY Electrical supply system is the most important part of the thermal power station. The failure of even comparatively small equipment could result in the losing of load or being put out of commission. SOURCE OF SUPPLY: - 1. URGENT AUXILLARY: - Those are associated with running of units whose loss would cause an immediate reduction unit output. 2. SERVICE AUXILLARY: - These are common auxiliaries associated with one or more units. There loss would not affect the output of the unit after considerable time of interval.
  • 47. [47] ELECTRICAL AUXILLARY SYSTEM: - The KaTPP auxiliaries are operated at two voltages that are 6.6 KV and 415V. In respect of 6.6KV system, auto change over facility is provided for change over of source of supply from unit station in the case of unit trip out. The station is having the following auxiliary system: - a) More then 1500KW connected on 11KV. b) More then 200KW less then 1500KW connected on 3.3KV. c) Less then 200KW on 415V. 220V D.C. underground system for use in control and protection system. 3.3 KV SYSTEM: - For the running unit, the unit auxiliaries are normally fed from gen’r itself through 11/3.3 KV, 15 MVA unit auxiliary transformers, which is, connected to the unit switchgear viz. USA and USB. Power to station auxiliaries and by unit auxiliary is fed from 220/3.3KV, 50 MVA station transformers through two switchgear viz. 415 KV SYSTEMS: - For driving ten 100W motors and other accessories, we need 415V supply. For this purpose various transformer are used to step down 3.3 KV to 415V at various places. Oil circuit breaker is provided between 3.3 KV bus and primary winding of transformer. Fig 5.3- Switching and transmission
  • 48. [48] 5.4 SWITCH YARD Switchyard is considered as the HEART of the Power Plant. Power generated can be worthful only if it is successfully transmitted and received by its consumers. Switchyard plays a very important role as a buffer between the generation and transmission. It is a junction, which carries the generated power to its destination (i.e. consumers). Switchyard is basically a yard or an open area where many different kinds of equipments are located (isolator, circuit breaker etc…), responsible for connecting & disconnecting the transmission line as per requirement (e.g. any fault condition). Power transmission is done at a higher voltage. (Higher transmission voltage reduces transmission losses). Both units is 22KV in KaTPP. stepped-up to 400KV by the Generating transformer & then transmitted to switchyard. Switchyards can be of 400KV, & 200KVIn SSTPS there are two interconnected switchyards:- (i) 400KV SWITCHYARD (ii) 220KV SWITCHYARD The 400KV & 220KV switch yard have conventional two buses arrangement with a bus coupled breaker. Both the generator transformer and line feeder taking off from switch yard can be taken to any of the two buses, similarly two station transformer can be fed from any two buses. Each of these line feeders has been provided with by pass isolators connected across line isolators and breaker isolators to facilitate the maintenance of line breaker. Each 400KV & 220KV lines have provision of local break up protection. In event of breaker which corresponding to bus bar differential protection scheme and trips out all the breakers and connected zone bus bars differential protection scheme for bus I & II. All the breaker of the connected zone and bus coupler, breaker will trip in event of fault in that zone. Here in KaTPP 4 out going line are as below:- 1) 400KV TO BTAWDA 2) 400KV TO BTAWDA 3) 220KV TO JHALAWAR 4) 220KV TO JHALAWAR
  • 49. [49] Each of the two bus bars has one P.T. one for each phase connected to it. Potential Transformer are make in CROMPTON LTD. Each time line feeders has two nos. Core for each phase capacitor voltage Transformer. for metering and protection are multicored single phase, oil filled, nitrogen sealed and are provided at rate of one per phase. 400KV SWITCHYARD: There are on total 21 bays in this switchyard. (A bay is basically a way for the incoming power from generator as well as outgoing power for distribution). 3 for unit Generating Transformer. 2 for various distribution lines such as: BTAWDA LINE  2 for Bus coupler.  2 for TBC.  2 for ICT.  1 for the Bus Section. There are on total 2 buses in 400KV switchyard.  Bus-1  Bus-2 There are two transfer buses:  Transfer bus-1  Transfer bus-2 Transfer buses are kept spare and remain idle and are used only for emergency purposes. BUS COUPLER-1 interconnects Bus-1 & Bus-2, respectively. Bus couplers are very beneficial as they help in load sharing between the different buses. TBC (TRANSFER BUS COUPLER): TBC is a bus coupler, which uses transfer bus when there is any defect in the equipments used (circuit breakers & isolators) in any of the bay. Thus, it offers a closed path through transfer bus for the flow of power in the respective bus.
  • 50. [50] A described of electrical equipment at 400KV & 220KV system are as follows: -  Circuit Breaker(VCB& SF6)  Isolators  Current Transformers(C.T.)  Potential Transformers(P.T.)  Lighting Arresters  Earthing Arresters  Capacitor Voltage Transformers(C.V.T.)  Inter connected transformer (ICT) CIRCUIT BREAKER:- It is an automatic controlling switch used in power house, substation & workshop as well as in power transmission during any unwanted condition (any fault condition-earth fault, over-current, flashover, single phasing,). During such condition it cuts down the supply automatically by electromagnetic action or thermal action. It can be used in off-load as well as on-load condition. When a circuit breaker is operated by sending an impulsethrough relay, C.B.contact is made or broken accordingly.During this making and breaking, an arc is produced which has to be quenched; this is done by air, oil, SF6 gas etc. Depending on the medium being used C.B.s can be categorized into various types.PLANT for 400 KV/220 KV switchyard only 4 main types are being used:- ABCB (Air operated circuit breaker):- operated as well as arc quenched through air. Air operated SF6 circuit breaker:-operated through air but arc quenching done through SF6 gas. MOCB (Minimum oil circuit breaker):-operated through spring action but arc quenching done through oil (Aerosol fluid oil). Hydraulic operated SF6 circuit breaker:- operated through hydraulic oil and arc quenching done through SF6 gas. Hydraulic operated SF6 circuit breaker is the most efficient due to following reasons:- 1. Less maintenance. 2. Arc quenching capability of SF6 gas is more effective than air. 3. Heat transfer capacity is better in this C.B.
  • 51. [51] Here we use SF6 provided for each stage are SIEMENS made and rated for 420KV/245KV, 3150A Each pole has three interrupters which are oil filled with SF6 gas at 7.5 Kg/sq. cm.Here in KaTPP 3AP1FI/3AP2FI type CB are used for 400KV &220KV Switchyard. Interlock Scheme of Circuit Breaker: -  Generator Breaker  Station Transformer Breaker  Line Feeder Breaker  Bus Coupler Breaker. ISOLATERS:- An isolator is also a switching device used to disconnect the line. As the name suggests it isolate the line from the supply. It is always used in OFF-LOAD condition. Whenever any fault occurs in the equipments present in the line, in order to remove the fault or replace the device first of all supply is disconnected. But even after the disconnection of the supply, the line remains in charged mode so before working on the device (to remove fault) isolator should be made open. Depending on the structure there are mainly two types of isolators:-  Pentagraph isolator.  Centre-break isolator (also known as Sequential isolator). Pentagraph is generally used in buses whereas Centre-break (Sequential) is used in line. Isolators may be operated in air (pneumatic), electrically or even manually. LIGHTENING ARRESTER:- It is a protective device, which protects the costly equipments such as overhead lines, poles or towers, transformer etc. against lightening. As the name suggests it arrests the lightening of very high voltage (crores of KV) and dump it into the ground. It works on the principle of easy path for the flow of current. L.A. is connected in parallel with the line with its lower end connected and the upper end projected above the pole of tower.
  • 52. [52] LIGHTENING MOST: It is present at the highest point, at the topmost tower of the switchyard and is connected together by wires forming a web. The reason for its presence at the topmost point is to grasp the lightening before it can come, fall and damage the costly equipments present in the switchyard. EARTHING ISOLATORS:- The term ‘Earthing’ means connecting of the non-current carrying parts of the electrical equipment or the neutral point of the supply system to the general mass of earth in such a manner that all times an immediate discharge of electrical energy takes place without danger. An Earthing isolator is a large value of capacitance. This can be charged up to line voltage. Earthing isolator is used to discharge the line capacitance and work on it. WAVE TRAPER:- It is an equipment used to trap the high carrier frequency of 500 KHz and above and allow the flow of power frequency (50 Hz). High frequencies also get generated due to capacitance to earth in long transmission lines. The basic principle of wave trap is that it has low inductance (2 Henry) & negligible resistance, thus it offers high impedance to carrier frequency whereas very low impedance to power frequency hence allowing it to flow in the station. CURRENT TRANSFORMER:- This Transformer is used for basically two major functions: -  Metering which means current measurement.  Protection such as over current protection, overload earth fault protection, Bus- bar protection, Bus differential protection. NOTE: - Secondary of the C.T should be kept shorted because (when secondary is kept open) even the presence of a very small voltage in the primary of C.T will prove to be harmful as it will start working as a step-up Transformer & will increase the voltage to such a high value that primary would not be able to bear it & will get burned. CT used current ratio 1000:1 and range is 1A-5A.CT connected in series while PT in parallel.
  • 53. [53] PIPRI LINE:- In the case of emergency, e.g. total grid failure we take the power from Pipri line for the initial starting of the station (Main Plant). CAPACITOR VOLTAGE TRANSFORMER(CVT):- This Transformer performs mainly two major functions:-  Used for voltage measurement. The high voltage of 400 KV is impossible to measure directly. Hence a C.V.T is used, (connected in parallel with the line) which step-downs the voltage of 400 KV to 110 KV, comparatively easy to measure.  The other most important function of C.V.T is that it blocks power frequency of 50Hz and allows the flow of carrier frequency for communication.Each of the four line feeders provided with three capacitor volt transformer for metering and synchronizing. P.T (POTENTIAL TRANSFORMER):- This Transformer is connected in parallel with the line with one end earthed. It is only used for voltage measurement by stepping-down the voltage to the required measurable value. INTER CONNECTED TRANSFORMER (ICT):- Purpose of ICT is simply interconnection between 400KV and 220KV Switchyard. 3xM1802-300/D-10.19.300MA2 Type autotransformer is used. manufacture by CROMPTON GEARVES TRANSFORMER DIVISION BHOPAL SURGE ARRESTER The electricity is usually produced in the stator winding of the large modern generators at about 25,000 volts and is fed through terminal connections to one side of a generator transformer that steps up the voltage 132000, 220000 or 400000 volts. From here conductors carry it to a series of three switches comprising an isolator, a circuit breaker and another isolator.
  • 54. [54] The circuit breaker, which is a heavy-duty switch capable of operating in a fraction of a second, is used to switch off the current flowing to the transmission lines. Once the current has been interrupted the isolators can be opened. These isolate the circuit breaker from all outside electrical sources. Fig-5.4 : Overview of switchyard From the circuit breaker the current is taken to the bus bars-conductors, which run the length of the switching compound and then to another circuit breaker with its associated isolates before feeding to the grid. Three wires are used in a ‘three=phase’ system for large power transmission. The centre of the power station is the control room. Here engineers monitor the output of electricity, supervising and controlling the operation of the generation plant and high voltage switch gear and directing power to the grid system as required.
  • 55. [55] CHAPTER-6 EFFICIENCY 6.1 EFFICIENCY In KaTPP we convert potential energy or chemical energy of the fuel into heat by the process of combustion. The heat is given to the water and it converts its form into steam. The pressure of steam rotates the turbine, which is now in the form of kinetic energy. Generator producing electrical energy, which is sand to different localities for utilization, consumes this kinetic energy. Efficiency in the case of electrical generator process can be expressed as the amount of heat energy librated in the boiler compared with the amount of electrical energy generated with it. Efficiency is defined as the ratio of output to input. Efficiency of any thermal power plant can be divided into four parts- 1) Cycle Efficiency 2) Boiler Efficiency 3) Generator Efficiency 4) Turbine Efficiency Efficiency of thermal power plant is defined as in the term of overall efficiency i.e. overall efficiency = cycle x boiler x generator x turbine efficiency CYCLE EFFICIENCY- Cycle efficiency is defined as the ration of energy available for conversion in work to the heat supplied to the boiler. BOILER EFFICIENCY- Efficiency of boiler depends upon the following factors: a) Dry flue gas loss: Increase by excess air in boiler. b) Wet flue gas loss: Moisture in coal. c) Moisture in combustion loss: Hydrogen loss. GENERATOR EFFICIENCY- Efficiency of generator is about 98% also its efficiency depends upon Copper iron loss and Windage losses TURBINE EFFICIENCY- It means the efficiency of steam turbine in converting the heat energy made available in the cycle into actual mechanical work.
  • 56. [56] CONCLUSION Electricity is one of the most vital infrastructure inputs for economic development of a country. The demand of electricity in India is enormous and is growing steadily. The vast Indian electricity market, today offers one of the highest growth opportunities for private developers This is my first practical training in which I learned lot of things and seen lot of huge machine like Turbine, Boiler, Generator, cooling tower and many other things. The architecture of the power plant, the way various units are linked and the way working of whole plant is controlled make the student realize that engineering is not just learning the structure description and working of various machine but the great part is of planning proper and management. I think training has essential for any student. It has allowed an opportunity to get an exposure of the practical implementation to theoretical fundamentals.
  • 57. [57] APPENDIX a) R.V.U.N.L –Rajasthan Vidyut Uttpadan Nigam Limited. b) C.H.P.- Coal Handling Plant. c) A.H.P.- Ash Handling Plant. d) D.G.- Diesel Generator e) B.A.H.-Bottom ash hopper f) L.P.T.- Low pressure turbine g) H.P.T.- High pressure turbine h) I.P.T.- Intermediate pressure steam turbine i) F.D.F.-Forced draught fan j) I.D.F.-Induced draught fan k) F.W.H. -Feedwater heater
  • 58. [58] REFERENCE [1]http://www.steelguru.com/indian_news/First_unit_of_coal_based_Kalisindh_th ermal_power_plant_has_commenced_generation/335431.h [2] http://www.rvunl.com/Kalisindh%20Thermal%20Power%20Project.php [3 ] www.energyindia.com [4] www.thermalpower.com [5] www.scibe.com [6] Fundamentals of electrical engineering/power plant/tpp/655 ,Ashfaq Husain Dhanpat Rai&Co. [7] Generation of electrical power/thermal station, B R Gupta ,S.CHAND PUBLICATION. [8] EPC Book Volume-V,TCE 5248.A-H-500-001. [9] Annual Report o f TCE Ltd. [10] Single Line Diagram GID-118-EL-XJ-2012,BGR REPORT ON KaTPP. [11] Single line diagram KaTPP Plan GID-2012,BGR ENERGY SYSTEM. [12] PPT On Thermal Plant/TCE/M Shreenivashan/104840/. [13] Generation of electrical power By B. R. Gupta, S CHAND PUBLICATION [14] Steam and Gas Turbine By R. Yadav , CPH [15] Engineering Thermodynamics By P. K. Nag, TMH. [16] http://rvunl.com/Kalisindh%20Thermal%20Power%20Project.php [17] http://www.business-standard.com/article/pti-stories/kalisindh-thermal- power-plant-starts-power-generation-114032200454_1.html.