SlideShare a Scribd company logo
Accident 19th November 2013 – Lessons Learned
Page 1 of 8
Accident description & “Lessons Learned”
Subject:
Accident
19th November 2013
Total Refinery Antwerp, Belgium
Date:
April 1, 2014
On November 19, 2013 a steam explosion occurred at the Total Refinery Antwerp in Belgium causing the
death of two TEAM technicians. The technicians were working on a leaking 16” bonnet-valve body flange
connection when the stud bolt (20 x 1 ½” ASTM A193 B7) securing the bonnet, suddenly failed causing
the bonnet-motor assembly to separate from the valve body with great force. The sudden release of the
boiler water resulted in the steam explosion.
The product was Boiler water, pressure 70 bar (1015 psi), temperature 290°C (554F). The valve was 16”,
# 900 gate valve with a ring type joint (octagonal RTJ) bonnet – body assembly. The valve was in open
position.
At the time of the incident, the technicians were performing a re-injection into a leak sealing clamp
installed around the joint in March 2011. Almost immediately after the start of their work the accident
happened.
Identical bonnet – motor configuration Identical bonnet – body clamp around
adjacent vaIve
Accident 19th November 2013 – Lessons Learned
Page 2 of 8
Valve after bonnet separated Separated bonnet
Cause leading the bonnet to separate from the valve body
The cause of the bonnet separation was the sudden failure of the stud bolts securing the bonnet. 14 Out of
the 20 stud bolts were severely degraded due to (caustic) Stress Corrosion Cracking (SCC) (see also page
5). After examination, the stud bolts showed degradation percentages between 70% and 87%. 6 Stud bolts
(no. 11 thru 16) had no signs of SCC and showed “normal” fracture. The bolt failure occurred during the
re-injection process through one injection port (between studno.1 & no.2).
SCC fracture “Normal” fracture
Accident 19th November 2013 – Lessons Learned
Page 3 of 8
From the investigation the following scenario was developed leading to the failure of the stud bolts.
1. The valve has an original design or construction flaw. The diameter of the RTJ groove in the bonnet is 5
mm. too small (acceptable ASME tolerance is 0,13 mm). Because of this design or construction flaw,
the standard RTJ ring does not fit in the groove as required. This flaw was not known.
RTJ ring in an exact copy of the bonnet flange. On the right photo the RTJ ring is out of the
groove. On the left photo the ring is in the groove.
2. This design- or construction flaw resulted in a non-parallel bonnet – body flange connection (with
standard assembly of the bonnet and stud bolt stress (310 N/mm2
)). In order to create parallel flanges,
several stud bolts have to be tightened with stresses close to the minimum yield. Laser measurements
established that the original bonnet flange has taken on the shape of an umbrella. This is another
indicator of the high forces in the stud bolts.
3. After the 2009 turnaround, there were fluctuations in the quality of the boiler water. Because of this
fluctuation, several leaks occurred in the system requiring the installation of several clamps. These
boiler water quality fluctuations explain the cause of the leaks but alone are not a cause of the accident.
4. In March 2011, the leak sealing clamp was installed around the bonnet – body joint creating a leak free
joint. It was not known at this time that several of the stud bolts in the joint had stresses close to the
minimum yield (approx. 600 N/mm2
bij 300°C). See also point 2 above.
Accident 19th November 2013 – Lessons Learned
Page 4 of 8
5. After installation of the clamp, the line was out of service for 5 months between April and November
2011 and again in 2012 for about 6 weeks. Once during this period a visible leak occurred and 1 re-
injection was performed. The valve remained under pressure, but at low temperatures (dead end). In
this cold condition, a minor leak re-occurred inside the flange – clamp assembly creating a wet
corrosive environment in which several stud bolts were subjected to general corrosion. Because of this
corrosion, the pressure layer (rolled stud bolts) on the outside of the thread that creates resistance
against SCC corroded away.
Possibly there were also initial micro cracks present due to galling (hardness of nut and stud bolt are
almost the same) when the bolts were tightened.
6. After the line came back into service at the end of 2011 the connection leaked several times and
injections were performed. During this period an accelerated SCC process started affecting the stud
bolts. The boiler water that has leaked evaporates leaving a corrosive residue behind on the degraded
stud bolts..
Stud bolt with “old” SCC crack and rest fracture SCC crack under a microscope
General corrosion affected screw thread of the
stud bolts. Light grey is the stud bolt. Purple line
is the shape of thread acc. to the standard.
SCC crack at bottom of the screw thread
Accident 19th November 2013 – Lessons Learned
Page 5 of 8
7. On 19th November 2013, the technicians are performing a re-injection on the bonnet – valve body
connection with the severely degraded stud bolts. The additional stress on the severely degraded stud
bolts occurring during the re-injection process is enough to let one (or more) stud bolts fail. The
Fracture of one (or more) bolt results creates an increase in stress on the weakened surrounding bolts,
leading to overload and fracture, resulting in a chain reaction and separation of the bonnet from the
valve body causing the explosion.
What is Stress Corrosion Cracking?
A crack inducing form of corrosion under the simultaneous influence of a corrosive product and (high)
tensile stresses. Without the tensile stresses, the metal would not or would hardly be affected by the
corrosive product. Also, without the corrosive product, much higher stresses would be necessary to let the
material fail.
Causes of the caustic SCC
 Corrosive product (caustic/electrolyte → boiler water)
 Susceptible material (general corrosion affected B7 stud bolts)
 High tensile stresses (tightening of the stud bolts close to the yield to create parallel flanges).
 Temperature > 60-70 °C (process temperature is 290 °C)
Remark; De degraded stud bolts all broke at the flange – nut face, which is the location of the highest
stresses.
Location of the re-injection at the position of
the weakened stud bolts. The missing
injection valve was found connected to the
injection pump hose.
Accident 19th November 2013 – Lessons Learned
Page 6 of 8
Additional research of identical flange – clamp connections.
 All flange stud bolts (>200 pcs) from the other flange – clamp connections in the unit were inspected
(NDE). None of these stud bolts showed any signs of general corrosion or stress corrosion. All of these
joints were within the same system and had identical process conditions.
 All clamps were installed in approximatley the same period. All clamps had multiple re-injections.
 Same sealants were used for all re-injections.
 This section of the system had not been out of of service/ been cold.
Clamp was not designed to take the extra axial load due to failure of the stud bolts.
A strong back device to take the extra axial load on the flange bolts was not a standard design for boiler
water at high pressure for Total or TEAM. This was determined on a case by case basis based upon the
outcome of the flange bolt calculations. These calculations are based upon (1) stud bolts being in good
condition and (2) an evenly spread load.
Summary
 Due to a design- or construction flaw, the RTJ ring does not fit in the groove of the bonnet correctly. In
order to create a parallel flange connection, the stud bolts are heavily tightened, resulting in high stress
in the stud bolts.
 Fluctuations in the quality of the boiler water caused leaks resulting in the installation of several leak
sealing clamps.
 As a result of 5 months out of service (cold condition) the stud bolts have been affected by general
corrosion making then susceptible to SCC.
 When the line was placed back in service, all ingredients (high stress, caustic environment, susceptible
material and high enough temperature (> 70°C / 158°F) were present for a rapid degradation by SCC.
 During the re-injection process additional forces occurred on the weakened bolts causing them to fail.
 There was no strong back device foreseen.
Accident 19th November 2013 – Lessons Learned
Page 7 of 8
Lessons learned
 Visual inspection is not conclusive regarding the condition of stud bolts or other relevant parts.
 SCC can progress very fast. Stud bolts that are in good condition can, under the right circumstances,
degrade rapidly due to SCC.
 In case of a re-injection, as part of the risk evaluation, the condition of the stud bolts should evaluated.
The additional forces on stud bolts due to (re) injections do not cause a problem when the stud bolts
are in good condition and have a normal stress. Attention is required when the condition of the stud
bolts and stress is unknown. Additional attention is also required when there are re-occurring leaks.
When boiler water evaporates, caustic residue can stay behind on the stud bolts.
 Extra attention is required when there are white deposites visible on bolts and /or flanges.
 SCC needs (high) tensile stresses AND a corrosive product. Additional attention is therefore required
when working on systems containing corrosive products like, but not limited to;
- Boiler water
- Boiler feed water
- Caustic
Accident 19th November 2013 – Lessons Learned
Page 8 of 8
Lessons Learned (Cont.)
 Regarding stud bolts stresses;
History of a (leaking) joint must be recorded and special attention paid. The history must capture what
has been done with the bolts and the joint assembly. Un-controlled tightening of the bolts (often the first
repair attempt when a joint is leaking) should be avoided. The use of manual or hydraulic torque
wrenches is highly recommended when tightening the bolts.
 Extra attention should be paid for possible combinations of conducive factors like stress environment,
corrosive environment, installation operating outside normal operating conditions, the systems
temporary taken out of service, additional stresses due to activities, etc.
 Different standards allow different calculation stresses. This results in a different outcome in identical
situations. Therefore in high risk environments with many unknowns, no matter the result of the
calculations, strong backs should be considered.
 In most cases, on-line leak sealing does not rectify the cause of the leak (erosion, corrosion, fatigue,
defective material, etc…). Therefore leak sealing clamps and enclosures must be considered to be a
temporary repair method and do not replace general maintenance or permanent repairs. It is
recommended that, when there is a safe opportunity (for example a scheduled turn around) clamps and
enclosures are replaced by a permanent repair.
Additional attention points (not directly related to the accident).
 Risk of Hydrogen Embrittlement should be considered. Products that require attention are, but not
limited to;
- Hydrogen Fluoride (HF)
- Hydrogen Sulfide (H2S)
 Some greases that are used for lubrication of stud bolts are known for their potential to cause SCC.
Example is Molybdeen Sulfides containing grease.
 There is only limited information sharing between industries when near misses or accidents occur. The
more we share our knowledge about these incidents, the less accidents will occur benefitting
everybody.

More Related Content

What's hot

ASME B31.3 Training Course
ASME B31.3 Training CourseASME B31.3 Training Course
ASME B31.3 Training Course
Meena Rezkallah
 
16 wis5 consumable
16 wis5 consumable16 wis5 consumable
16 wis5 consumable
Tori Tom
 
PIPE SUPPORT
PIPE SUPPORTPIPE SUPPORT
PIPE SUPPORT
Shweyee Win
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
Praj Industries Ltd.
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
Mohamed Gaafar
 
How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1
Tiago Pereira
 
Gaskets.pptx
Gaskets.pptxGaskets.pptx
Gaskets.pptx
AliJaved963319
 
Nb 23 2011 part 3 repairs
Nb 23 2011 part 3 repairsNb 23 2011 part 3 repairs
Nb 23 2011 part 3 repairs
JoseAdrianHernandezH
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
Mohamed Farouk
 
Electrode selection
Electrode selection  Electrode selection
Electrode selection
Prasanth Kumar
 
Asme b31.3 process_piping
Asme b31.3 process_pipingAsme b31.3 process_piping
Asme b31.3 process_piping
dinusim
 
Pipe Support Field Inspection, Installation & Maintenance
Pipe Support Field Inspection, Installation & MaintenancePipe Support Field Inspection, Installation & Maintenance
Pipe Support Field Inspection, Installation & Maintenance
Piping Technology & Products, Inc.
 
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdf
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdfMain_book_CSWIP_3_1_Welding_Inspector_WI.pdf
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdf
University of Sarajevo, Manufacturing Technology:
 
Design by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vesselDesign by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vessel
AnalyzeForSafety
 
Process piping b31.3 detailed
Process piping b31.3 detailedProcess piping b31.3 detailed
Process piping b31.3 detailed
Adeel Mazhar
 
Gasket hand book 2012
Gasket hand book 2012Gasket hand book 2012
Gasket hand book 2012
Mouli Edla
 
Stress analysis of storage tank piping - Jeba Anand
Stress analysis of storage tank  piping - Jeba AnandStress analysis of storage tank  piping - Jeba Anand
Stress analysis of storage tank piping - Jeba Anand
Jeba Anand Nadar
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
AshifuddinAli
 
Wis5 stress and distortion 15
Wis5 stress and distortion 15Wis5 stress and distortion 15
Wis5 stress and distortion 15
Thang Do Minh
 
Pressure vessel
Pressure vesselPressure vessel
Pressure vessel
Ayman Hasprapo
 

What's hot (20)

ASME B31.3 Training Course
ASME B31.3 Training CourseASME B31.3 Training Course
ASME B31.3 Training Course
 
16 wis5 consumable
16 wis5 consumable16 wis5 consumable
16 wis5 consumable
 
PIPE SUPPORT
PIPE SUPPORTPIPE SUPPORT
PIPE SUPPORT
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
 
How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1
 
Gaskets.pptx
Gaskets.pptxGaskets.pptx
Gaskets.pptx
 
Nb 23 2011 part 3 repairs
Nb 23 2011 part 3 repairsNb 23 2011 part 3 repairs
Nb 23 2011 part 3 repairs
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
 
Electrode selection
Electrode selection  Electrode selection
Electrode selection
 
Asme b31.3 process_piping
Asme b31.3 process_pipingAsme b31.3 process_piping
Asme b31.3 process_piping
 
Pipe Support Field Inspection, Installation & Maintenance
Pipe Support Field Inspection, Installation & MaintenancePipe Support Field Inspection, Installation & Maintenance
Pipe Support Field Inspection, Installation & Maintenance
 
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdf
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdfMain_book_CSWIP_3_1_Welding_Inspector_WI.pdf
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdf
 
Design by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vesselDesign by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vessel
 
Process piping b31.3 detailed
Process piping b31.3 detailedProcess piping b31.3 detailed
Process piping b31.3 detailed
 
Gasket hand book 2012
Gasket hand book 2012Gasket hand book 2012
Gasket hand book 2012
 
Stress analysis of storage tank piping - Jeba Anand
Stress analysis of storage tank  piping - Jeba AnandStress analysis of storage tank  piping - Jeba Anand
Stress analysis of storage tank piping - Jeba Anand
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
 
Wis5 stress and distortion 15
Wis5 stress and distortion 15Wis5 stress and distortion 15
Wis5 stress and distortion 15
 
Pressure vessel
Pressure vesselPressure vessel
Pressure vessel
 

Similar to Total Refinery Accident Description and Study- GASKET FAILURE

Solids conveying consistency
Solids conveying consistencySolids conveying consistency
Solids conveying consistency
R&B Plastics Machinery
 
Giuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdfGiuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdf
Giuseppe Tommasone
 
Est group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 englishEst group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 english
Jim Novak (吉因龙)
 
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET Journal
 
Extruder Screw Cooling
Extruder Screw CoolingExtruder Screw Cooling
Extruder Screw Cooling
R&B Plastics Machinery
 
Failure of SVs.pdf
Failure of SVs.pdfFailure of SVs.pdf
Failure of SVs.pdf
MomenAdel11
 
Branch connections
Branch connectionsBranch connections
Branch connections
Nazar Abdul Kareem Hussein
 
Organizing an Effective Maintenance Program for Plasticating Components
Organizing an Effective Maintenance Program for Plasticating ComponentsOrganizing an Effective Maintenance Program for Plasticating Components
Organizing an Effective Maintenance Program for Plasticating Components
Glycon Corp.
 
Sugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdfSugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdf
Udhayakumar Venkataraman
 
Goel Scientific General information and introduction
Goel Scientific General information and introductionGoel Scientific General information and introduction
Goel Scientific General information and introduction
Goel Scientific
 
Equipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger CostanziEquipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger Costanzi
NSW Environment and Planning
 
How to prevent weld failure
How to prevent weld failure How to prevent weld failure
How to prevent weld failure
أحمد دعبس
 
Critical Equipment Identification and Preventative Action Plan
Critical Equipment Identification and Preventative Action PlanCritical Equipment Identification and Preventative Action Plan
Critical Equipment Identification and Preventative Action Plan
Nathan Schaefer
 
Paper id 24201467
Paper id 24201467Paper id 24201467
Paper id 24201467
IJRAT
 
Review paper on study and implementation of steam traps
Review paper on study and implementation of steam trapsReview paper on study and implementation of steam traps
Review paper on study and implementation of steam traps
IRJET Journal
 
Failure Analysis of Expansion Joints (Bellows)
Failure Analysis of Expansion Joints (Bellows)Failure Analysis of Expansion Joints (Bellows)
Failure Analysis of Expansion Joints (Bellows)
IRJET Journal
 
Anchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_ukAnchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_uk
Mandeep Singh
 
Ethylene oxide reactor failure pvp 2011 paper china
Ethylene oxide reactor failure pvp 2011 paper chinaEthylene oxide reactor failure pvp 2011 paper china
Ethylene oxide reactor failure pvp 2011 paper china
AbdelhakAbdouKermad
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech Article
Scott Chambers
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech Article
Scott Chambers
 

Similar to Total Refinery Accident Description and Study- GASKET FAILURE (20)

Solids conveying consistency
Solids conveying consistencySolids conveying consistency
Solids conveying consistency
 
Giuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdfGiuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdf
 
Est group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 englishEst group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 english
 
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
 
Extruder Screw Cooling
Extruder Screw CoolingExtruder Screw Cooling
Extruder Screw Cooling
 
Failure of SVs.pdf
Failure of SVs.pdfFailure of SVs.pdf
Failure of SVs.pdf
 
Branch connections
Branch connectionsBranch connections
Branch connections
 
Organizing an Effective Maintenance Program for Plasticating Components
Organizing an Effective Maintenance Program for Plasticating ComponentsOrganizing an Effective Maintenance Program for Plasticating Components
Organizing an Effective Maintenance Program for Plasticating Components
 
Sugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdfSugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdf
 
Goel Scientific General information and introduction
Goel Scientific General information and introductionGoel Scientific General information and introduction
Goel Scientific General information and introduction
 
Equipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger CostanziEquipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger Costanzi
 
How to prevent weld failure
How to prevent weld failure How to prevent weld failure
How to prevent weld failure
 
Critical Equipment Identification and Preventative Action Plan
Critical Equipment Identification and Preventative Action PlanCritical Equipment Identification and Preventative Action Plan
Critical Equipment Identification and Preventative Action Plan
 
Paper id 24201467
Paper id 24201467Paper id 24201467
Paper id 24201467
 
Review paper on study and implementation of steam traps
Review paper on study and implementation of steam trapsReview paper on study and implementation of steam traps
Review paper on study and implementation of steam traps
 
Failure Analysis of Expansion Joints (Bellows)
Failure Analysis of Expansion Joints (Bellows)Failure Analysis of Expansion Joints (Bellows)
Failure Analysis of Expansion Joints (Bellows)
 
Anchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_ukAnchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_uk
 
Ethylene oxide reactor failure pvp 2011 paper china
Ethylene oxide reactor failure pvp 2011 paper chinaEthylene oxide reactor failure pvp 2011 paper china
Ethylene oxide reactor failure pvp 2011 paper china
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech Article
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech Article
 

More from PGE India - PILOT Gaskets

Guidelines for Pressure Boundary Bolted Flange Joint Assembly
Guidelines for Pressure Boundary Bolted Flange Joint AssemblyGuidelines for Pressure Boundary Bolted Flange Joint Assembly
Guidelines for Pressure Boundary Bolted Flange Joint Assembly
PGE India - PILOT Gaskets
 
EIL Vendor Registration for PILOT Gaskets
EIL Vendor Registration for PILOT GasketsEIL Vendor Registration for PILOT Gaskets
EIL Vendor Registration for PILOT Gaskets
PGE India - PILOT Gaskets
 
Indigenization by PILOT Gaskets
Indigenization by PILOT GasketsIndigenization by PILOT Gaskets
Indigenization by PILOT Gaskets
PGE India - PILOT Gaskets
 
Indigenisation projects by PILOT Gaskets and Engineers
Indigenisation projects by PILOT Gaskets and EngineersIndigenisation projects by PILOT Gaskets and Engineers
Indigenisation projects by PILOT Gaskets and Engineers
PGE India - PILOT Gaskets
 
ISO 9001 Quality Manual Policy
ISO 9001 Quality Manual PolicyISO 9001 Quality Manual Policy
ISO 9001 Quality Manual Policy
PGE India - PILOT Gaskets
 
Making India AsbestosFREE
Making India AsbestosFREEMaking India AsbestosFREE
Making India AsbestosFREE
PGE India - PILOT Gaskets
 
COCHIN SHIPYARD Asbestos Problem
COCHIN SHIPYARD Asbestos ProblemCOCHIN SHIPYARD Asbestos Problem
COCHIN SHIPYARD Asbestos Problem
PGE India - PILOT Gaskets
 
Case Studies of Asbestos Victims
Case Studies of Asbestos Victims Case Studies of Asbestos Victims
Case Studies of Asbestos Victims
PGE India - PILOT Gaskets
 
Asbestos case order
Asbestos case orderAsbestos case order
Asbestos case order
PGE India - PILOT Gaskets
 
API 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive EmissionsAPI 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive Emissions
PGE India - PILOT Gaskets
 
IS 11451: Health Exposure to Asbestos
IS 11451: Health Exposure to AsbestosIS 11451: Health Exposure to Asbestos
IS 11451: Health Exposure to Asbestos
PGE India - PILOT Gaskets
 
National Asbestos Profile of India
National Asbestos Profile of IndiaNational Asbestos Profile of India
National Asbestos Profile of India
PGE India - PILOT Gaskets
 
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
PGE India - PILOT Gaskets
 
GENTOO Coatings and the US Defence
GENTOO Coatings and the US DefenceGENTOO Coatings and the US Defence
GENTOO Coatings and the US Defence
PGE India - PILOT Gaskets
 
Asbestos Gasket usage causing mesothelioma
Asbestos Gasket usage causing mesothelioma Asbestos Gasket usage causing mesothelioma
Asbestos Gasket usage causing mesothelioma
PGE India - PILOT Gaskets
 
ARIA Database Gasket Failures
ARIA Database Gasket FailuresARIA Database Gasket Failures
ARIA Database Gasket Failures
PGE India - PILOT Gaskets
 
IS 2712 Indian Standard for Compressed Asbestos Fiber
IS 2712  Indian Standard for Compressed Asbestos Fiber IS 2712  Indian Standard for Compressed Asbestos Fiber
IS 2712 Indian Standard for Compressed Asbestos Fiber
PGE India - PILOT Gaskets
 
List of Asbestos Manufacturers and Dealers in India
List of Asbestos Manufacturers and Dealers in IndiaList of Asbestos Manufacturers and Dealers in India
List of Asbestos Manufacturers and Dealers in India
PGE India - PILOT Gaskets
 
IS 11768 Waste Disposal for Asbestos Containing Products
IS 11768 Waste Disposal for Asbestos Containing ProductsIS 11768 Waste Disposal for Asbestos Containing Products
IS 11768 Waste Disposal for Asbestos Containing Products
PGE India - PILOT Gaskets
 
The National Asbestos Profile of India
The National Asbestos Profile of IndiaThe National Asbestos Profile of India
The National Asbestos Profile of India
PGE India - PILOT Gaskets
 

More from PGE India - PILOT Gaskets (20)

Guidelines for Pressure Boundary Bolted Flange Joint Assembly
Guidelines for Pressure Boundary Bolted Flange Joint AssemblyGuidelines for Pressure Boundary Bolted Flange Joint Assembly
Guidelines for Pressure Boundary Bolted Flange Joint Assembly
 
EIL Vendor Registration for PILOT Gaskets
EIL Vendor Registration for PILOT GasketsEIL Vendor Registration for PILOT Gaskets
EIL Vendor Registration for PILOT Gaskets
 
Indigenization by PILOT Gaskets
Indigenization by PILOT GasketsIndigenization by PILOT Gaskets
Indigenization by PILOT Gaskets
 
Indigenisation projects by PILOT Gaskets and Engineers
Indigenisation projects by PILOT Gaskets and EngineersIndigenisation projects by PILOT Gaskets and Engineers
Indigenisation projects by PILOT Gaskets and Engineers
 
ISO 9001 Quality Manual Policy
ISO 9001 Quality Manual PolicyISO 9001 Quality Manual Policy
ISO 9001 Quality Manual Policy
 
Making India AsbestosFREE
Making India AsbestosFREEMaking India AsbestosFREE
Making India AsbestosFREE
 
COCHIN SHIPYARD Asbestos Problem
COCHIN SHIPYARD Asbestos ProblemCOCHIN SHIPYARD Asbestos Problem
COCHIN SHIPYARD Asbestos Problem
 
Case Studies of Asbestos Victims
Case Studies of Asbestos Victims Case Studies of Asbestos Victims
Case Studies of Asbestos Victims
 
Asbestos case order
Asbestos case orderAsbestos case order
Asbestos case order
 
API 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive EmissionsAPI 622, API 624 and API 641 for Fugitive Emissions
API 622, API 624 and API 641 for Fugitive Emissions
 
IS 11451: Health Exposure to Asbestos
IS 11451: Health Exposure to AsbestosIS 11451: Health Exposure to Asbestos
IS 11451: Health Exposure to Asbestos
 
National Asbestos Profile of India
National Asbestos Profile of IndiaNational Asbestos Profile of India
National Asbestos Profile of India
 
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
 
GENTOO Coatings and the US Defence
GENTOO Coatings and the US DefenceGENTOO Coatings and the US Defence
GENTOO Coatings and the US Defence
 
Asbestos Gasket usage causing mesothelioma
Asbestos Gasket usage causing mesothelioma Asbestos Gasket usage causing mesothelioma
Asbestos Gasket usage causing mesothelioma
 
ARIA Database Gasket Failures
ARIA Database Gasket FailuresARIA Database Gasket Failures
ARIA Database Gasket Failures
 
IS 2712 Indian Standard for Compressed Asbestos Fiber
IS 2712  Indian Standard for Compressed Asbestos Fiber IS 2712  Indian Standard for Compressed Asbestos Fiber
IS 2712 Indian Standard for Compressed Asbestos Fiber
 
List of Asbestos Manufacturers and Dealers in India
List of Asbestos Manufacturers and Dealers in IndiaList of Asbestos Manufacturers and Dealers in India
List of Asbestos Manufacturers and Dealers in India
 
IS 11768 Waste Disposal for Asbestos Containing Products
IS 11768 Waste Disposal for Asbestos Containing ProductsIS 11768 Waste Disposal for Asbestos Containing Products
IS 11768 Waste Disposal for Asbestos Containing Products
 
The National Asbestos Profile of India
The National Asbestos Profile of IndiaThe National Asbestos Profile of India
The National Asbestos Profile of India
 

Recently uploaded

Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...
um7474492
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
snaprevwdev
 
FULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back EndFULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back End
PreethaV16
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
b0754201
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
Bituminous road construction project based learning report
Bituminous road construction project based learning reportBituminous road construction project based learning report
Bituminous road construction project based learning report
CE19KaushlendraKumar
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
MuhammadJazib15
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
Ericsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.pptEricsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.ppt
wafawafa52
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...
pvpriya2
 

Recently uploaded (20)

Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...smart pill dispenser is designed to improve medication adherence and safety f...
smart pill dispenser is designed to improve medication adherence and safety f...
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
 
FULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back EndFULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back End
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
Bituminous road construction project based learning report
Bituminous road construction project based learning reportBituminous road construction project based learning report
Bituminous road construction project based learning report
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
Ericsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.pptEricsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.ppt
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...Determination of Equivalent Circuit parameters and performance characteristic...
Determination of Equivalent Circuit parameters and performance characteristic...
 

Total Refinery Accident Description and Study- GASKET FAILURE

  • 1. Accident 19th November 2013 – Lessons Learned Page 1 of 8 Accident description & “Lessons Learned” Subject: Accident 19th November 2013 Total Refinery Antwerp, Belgium Date: April 1, 2014 On November 19, 2013 a steam explosion occurred at the Total Refinery Antwerp in Belgium causing the death of two TEAM technicians. The technicians were working on a leaking 16” bonnet-valve body flange connection when the stud bolt (20 x 1 ½” ASTM A193 B7) securing the bonnet, suddenly failed causing the bonnet-motor assembly to separate from the valve body with great force. The sudden release of the boiler water resulted in the steam explosion. The product was Boiler water, pressure 70 bar (1015 psi), temperature 290°C (554F). The valve was 16”, # 900 gate valve with a ring type joint (octagonal RTJ) bonnet – body assembly. The valve was in open position. At the time of the incident, the technicians were performing a re-injection into a leak sealing clamp installed around the joint in March 2011. Almost immediately after the start of their work the accident happened. Identical bonnet – motor configuration Identical bonnet – body clamp around adjacent vaIve
  • 2. Accident 19th November 2013 – Lessons Learned Page 2 of 8 Valve after bonnet separated Separated bonnet Cause leading the bonnet to separate from the valve body The cause of the bonnet separation was the sudden failure of the stud bolts securing the bonnet. 14 Out of the 20 stud bolts were severely degraded due to (caustic) Stress Corrosion Cracking (SCC) (see also page 5). After examination, the stud bolts showed degradation percentages between 70% and 87%. 6 Stud bolts (no. 11 thru 16) had no signs of SCC and showed “normal” fracture. The bolt failure occurred during the re-injection process through one injection port (between studno.1 & no.2). SCC fracture “Normal” fracture
  • 3. Accident 19th November 2013 – Lessons Learned Page 3 of 8 From the investigation the following scenario was developed leading to the failure of the stud bolts. 1. The valve has an original design or construction flaw. The diameter of the RTJ groove in the bonnet is 5 mm. too small (acceptable ASME tolerance is 0,13 mm). Because of this design or construction flaw, the standard RTJ ring does not fit in the groove as required. This flaw was not known. RTJ ring in an exact copy of the bonnet flange. On the right photo the RTJ ring is out of the groove. On the left photo the ring is in the groove. 2. This design- or construction flaw resulted in a non-parallel bonnet – body flange connection (with standard assembly of the bonnet and stud bolt stress (310 N/mm2 )). In order to create parallel flanges, several stud bolts have to be tightened with stresses close to the minimum yield. Laser measurements established that the original bonnet flange has taken on the shape of an umbrella. This is another indicator of the high forces in the stud bolts. 3. After the 2009 turnaround, there were fluctuations in the quality of the boiler water. Because of this fluctuation, several leaks occurred in the system requiring the installation of several clamps. These boiler water quality fluctuations explain the cause of the leaks but alone are not a cause of the accident. 4. In March 2011, the leak sealing clamp was installed around the bonnet – body joint creating a leak free joint. It was not known at this time that several of the stud bolts in the joint had stresses close to the minimum yield (approx. 600 N/mm2 bij 300°C). See also point 2 above.
  • 4. Accident 19th November 2013 – Lessons Learned Page 4 of 8 5. After installation of the clamp, the line was out of service for 5 months between April and November 2011 and again in 2012 for about 6 weeks. Once during this period a visible leak occurred and 1 re- injection was performed. The valve remained under pressure, but at low temperatures (dead end). In this cold condition, a minor leak re-occurred inside the flange – clamp assembly creating a wet corrosive environment in which several stud bolts were subjected to general corrosion. Because of this corrosion, the pressure layer (rolled stud bolts) on the outside of the thread that creates resistance against SCC corroded away. Possibly there were also initial micro cracks present due to galling (hardness of nut and stud bolt are almost the same) when the bolts were tightened. 6. After the line came back into service at the end of 2011 the connection leaked several times and injections were performed. During this period an accelerated SCC process started affecting the stud bolts. The boiler water that has leaked evaporates leaving a corrosive residue behind on the degraded stud bolts.. Stud bolt with “old” SCC crack and rest fracture SCC crack under a microscope General corrosion affected screw thread of the stud bolts. Light grey is the stud bolt. Purple line is the shape of thread acc. to the standard. SCC crack at bottom of the screw thread
  • 5. Accident 19th November 2013 – Lessons Learned Page 5 of 8 7. On 19th November 2013, the technicians are performing a re-injection on the bonnet – valve body connection with the severely degraded stud bolts. The additional stress on the severely degraded stud bolts occurring during the re-injection process is enough to let one (or more) stud bolts fail. The Fracture of one (or more) bolt results creates an increase in stress on the weakened surrounding bolts, leading to overload and fracture, resulting in a chain reaction and separation of the bonnet from the valve body causing the explosion. What is Stress Corrosion Cracking? A crack inducing form of corrosion under the simultaneous influence of a corrosive product and (high) tensile stresses. Without the tensile stresses, the metal would not or would hardly be affected by the corrosive product. Also, without the corrosive product, much higher stresses would be necessary to let the material fail. Causes of the caustic SCC  Corrosive product (caustic/electrolyte → boiler water)  Susceptible material (general corrosion affected B7 stud bolts)  High tensile stresses (tightening of the stud bolts close to the yield to create parallel flanges).  Temperature > 60-70 °C (process temperature is 290 °C) Remark; De degraded stud bolts all broke at the flange – nut face, which is the location of the highest stresses. Location of the re-injection at the position of the weakened stud bolts. The missing injection valve was found connected to the injection pump hose.
  • 6. Accident 19th November 2013 – Lessons Learned Page 6 of 8 Additional research of identical flange – clamp connections.  All flange stud bolts (>200 pcs) from the other flange – clamp connections in the unit were inspected (NDE). None of these stud bolts showed any signs of general corrosion or stress corrosion. All of these joints were within the same system and had identical process conditions.  All clamps were installed in approximatley the same period. All clamps had multiple re-injections.  Same sealants were used for all re-injections.  This section of the system had not been out of of service/ been cold. Clamp was not designed to take the extra axial load due to failure of the stud bolts. A strong back device to take the extra axial load on the flange bolts was not a standard design for boiler water at high pressure for Total or TEAM. This was determined on a case by case basis based upon the outcome of the flange bolt calculations. These calculations are based upon (1) stud bolts being in good condition and (2) an evenly spread load. Summary  Due to a design- or construction flaw, the RTJ ring does not fit in the groove of the bonnet correctly. In order to create a parallel flange connection, the stud bolts are heavily tightened, resulting in high stress in the stud bolts.  Fluctuations in the quality of the boiler water caused leaks resulting in the installation of several leak sealing clamps.  As a result of 5 months out of service (cold condition) the stud bolts have been affected by general corrosion making then susceptible to SCC.  When the line was placed back in service, all ingredients (high stress, caustic environment, susceptible material and high enough temperature (> 70°C / 158°F) were present for a rapid degradation by SCC.  During the re-injection process additional forces occurred on the weakened bolts causing them to fail.  There was no strong back device foreseen.
  • 7. Accident 19th November 2013 – Lessons Learned Page 7 of 8 Lessons learned  Visual inspection is not conclusive regarding the condition of stud bolts or other relevant parts.  SCC can progress very fast. Stud bolts that are in good condition can, under the right circumstances, degrade rapidly due to SCC.  In case of a re-injection, as part of the risk evaluation, the condition of the stud bolts should evaluated. The additional forces on stud bolts due to (re) injections do not cause a problem when the stud bolts are in good condition and have a normal stress. Attention is required when the condition of the stud bolts and stress is unknown. Additional attention is also required when there are re-occurring leaks. When boiler water evaporates, caustic residue can stay behind on the stud bolts.  Extra attention is required when there are white deposites visible on bolts and /or flanges.  SCC needs (high) tensile stresses AND a corrosive product. Additional attention is therefore required when working on systems containing corrosive products like, but not limited to; - Boiler water - Boiler feed water - Caustic
  • 8. Accident 19th November 2013 – Lessons Learned Page 8 of 8 Lessons Learned (Cont.)  Regarding stud bolts stresses; History of a (leaking) joint must be recorded and special attention paid. The history must capture what has been done with the bolts and the joint assembly. Un-controlled tightening of the bolts (often the first repair attempt when a joint is leaking) should be avoided. The use of manual or hydraulic torque wrenches is highly recommended when tightening the bolts.  Extra attention should be paid for possible combinations of conducive factors like stress environment, corrosive environment, installation operating outside normal operating conditions, the systems temporary taken out of service, additional stresses due to activities, etc.  Different standards allow different calculation stresses. This results in a different outcome in identical situations. Therefore in high risk environments with many unknowns, no matter the result of the calculations, strong backs should be considered.  In most cases, on-line leak sealing does not rectify the cause of the leak (erosion, corrosion, fatigue, defective material, etc…). Therefore leak sealing clamps and enclosures must be considered to be a temporary repair method and do not replace general maintenance or permanent repairs. It is recommended that, when there is a safe opportunity (for example a scheduled turn around) clamps and enclosures are replaced by a permanent repair. Additional attention points (not directly related to the accident).  Risk of Hydrogen Embrittlement should be considered. Products that require attention are, but not limited to; - Hydrogen Fluoride (HF) - Hydrogen Sulfide (H2S)  Some greases that are used for lubrication of stud bolts are known for their potential to cause SCC. Example is Molybdeen Sulfides containing grease.  There is only limited information sharing between industries when near misses or accidents occur. The more we share our knowledge about these incidents, the less accidents will occur benefitting everybody.