SlideShare a Scribd company logo
PROJECT SAFETY MANAGEMENT
GROUP : 08
SECTION : 02
PEM : 16
WHAT IS PROJECT SAFETY MANAGEMENT ?
• Generally known as HSE or Health, Safety and EnvironmentManagement.Other forms are SHE and EHS.
Depends on priority. Most commonly use form is HSE.
• Ensures that the health (physicalor mental) of workforce is maintained,that they work in safe work
environmentand there is no environmentalimpact.
• HSE Policy, better known as Safety Policy, becomes more and more importantwith increase in
Complexity of the Project.
• The more number of stakeholdersand more is the importance of the Project, leads to the requirement
of more stringent and carefullywritten safety policy
• However, irrespective of size (cost and scope), safety is of utmost importance. Increases quality of work,
productivityand helps saving cost.
CASE STUDY – REHABILITATION OF EXISTING
40 YEARS OLD 200 MLD STP
• LOCATION: Doha, Qatar
• CLIENT: Public Works Authority (ASHGAL), Qatar
• CONSULTANT: Parsons InternationalLimited, Qatar
• CONTRACTOR : VA Tech Wabag Limited, India
• SUB-CONTRACTORS :
M/s Medgulf Construction Company WLL
M/s Emcon Trading and Contracting LLC
M/s Elite InternationalTrading & Maintainance
M/s Voltech Group, India
• PLANT OPERATORS :
M/s Veolia Water
M/s Metito Overseas Qatar
WHAT MAKES THIS PROJECT COMPLEX?
• Live or running or active plant – riskier than any other new project.
• Multiplestakeholderslike client, consultant,contractor, multiplesub-contractors.
• Change of Plant Operationresponsibilitiesfrom one company to another, while execution.
• Strict local laws and regulationsfor health and safety.
• FIFA World Cup – 2022 critical Project. Aims to reduce foul smell in the area during football matches
(plant is barely 100 mtrs from a FIFA stadium).
SAFETY POLICY – ON SITE
• Anywork, prior to start, shall have approvedmethod statement with Risk
Assessment.
• Anywork, shall not be started without signed permit from contractor,
plant operator, consultant and client
• Individualattendance registers outside confinedspace areas– workforce
made responsible for themselves and their buddyalloted
• For all confined space work, buddysystem should be regulated
• Anyoff time work shall not be executed without availabilityofsite
emergency vehicle, first aider, HSE officer
• Special works like liftingactivities, to be carried out in supervision of
certified liftingsupervisor.Same for height works, confined space works
etc.
• PPE made mandatory.Violators are punished.Goodpractices are
rewarded
• SafetyWalk through every week. MOM is circulated and actions decided
sought within same week
CONTROL OVER HSE DEPARTMENT
• Project Management team’scontrol over HSE team is very important.Although, HSE shall always
function independent.However, the Project Manager is the head of safety committee, hence the
control.
• Quarterly Audits(External and Inter-Company) ensured to check all documentation arein place
• Monthlysafety progress report. Root Cause analysisof all accidentsor incidents.Preventive actions
proposed by HSE manager and approvedby Project Manager
PROJECT SAFETY MANAGEMENT – STAGE WISE
THE CHANNEL TUNNEL (CHUNNEL) PROJECT
CONTRACTOR : TRANSMANCHE LINK (TML)
INCEPTION PHASE
• Maximum of the risks considered in this phase
were purely technical.Process and approval
risks were not envisaged.
• Not much records of any safety risk considered
during this phase.
• The Project was considered simple initially and
slowly turned complex with works adding.
Probably addingto the risk list.
• Scope of works were not clear. Even bidding was
done without clearing the scope of works. This
makes risk assessment prior to call for bid
document extremely difficult.
• Although the IGC had a Safety Authority –
Independent– still it was of no particular use in
pre-bidding stage.
DEVELOPMENT PHASE
• This phase was very importantand significant
for TML management to decide the HSE
structure in Organisation
• TML made line management responsible for
ensuring safety
• Line management was under single, unified
management, making HSE as well, responsibility
of top management and line management.
• CEO was also, Chief Safety Officer.
• Traced safety responsibilityfrom Lead Hand to
CEO
• Example : One contractorchosen, about to work
at the heart of the project, when asked to follow
a safety measure told TML that they need
approvalfrom their HSE team.
• Moral : The respective personnel from Sub-
Contractordid not have the authority to chose
between right and wrong for his team.
IMPLEMENTATION PHASE
• Project Managerswere asked to set up Safety
meeting, monthly, chaired by Line managers
(juniormost) and CEO (senior most). Attended
by Lead Handsas well.
• Any accident or incidentto be investigatedby
Lead Hand (party leader). Then reviewed by
his/her supervisor, then line manager and so on
until CEO.
• Category of accidentsor incidentswere formed
by line manager, insteadof instruction from top
tier management.
• Analysisof accidents or incidentsshowed that
95% of accidents or incidentshappeneddue to
Human Behaviorsand not due to the extreme
conditionslike undergroundworks
• Example : Back Strain was common work place
accident. Upon analysisand investigation,it was
found that the method of pullingpoint levers
was wrong. Same was rectified – increased
productivityand reduced health risk.
• TML had sensors to record temperature and gas
levelsin the tunnel – permanent recording –
direct data to controllers
CLOSE OUT PHASE
• The initialchange in safety organization,to
include line managers and make them
responsible, was the most complexchange in
organization
• Due to this change TML faced problems for the
phased hand-over of the project to the client,
ET. The principalcause for rejecting the
proposed organizationhasbeen the failure to
identify satisfactorilythe safety chain from the
operativeto the chief executive.
• The Project was closed in 1994 and entered the
Operationand Maintenancephase with a very
good safety review, throughout the four (4)
stages of the project
PROJECT SAFETY MANAGEMENT – RATING
THE CHANNEL TUNNEL (CHUNNEL) PROJECT
CONTRACTOR : TRANSMANCHE LINK (TML)
RATINGS BASED ON CASE STUDY
Phases
• INITIATION PHASE
• DEVELOPMENTPHASE
• IMPLIMENTATIONPHASE
• CLOSE OUT PHASE
Rate (1-5)
• 2
• 4
• 4
• 3
PROJECT SAFETY MANAGEMENT – LESSONS
LEARNED
THE CHANNEL TUNNEL (CHUNNEL) PROJECT
CONTRACTOR : TRANSMANCHE LINK (TML)
WHAT DID WE LEARN ?
• Safety of workforce shall alwaysbe on top priority. No project is bigger than a life.
• Continuousevaluationof HSE policies required.
• Ignorance is not bliss – in this case. Every worker deserves to go back to his/her family, safely.
• Proper structuring of HSE organizationfor a project is very important.
• Making Line Managersresponsible for their team’s safety and healthincreases productivityand quality
in work.
• FollowingHSE norms saves cost – like cost incurred due to accidents, fatalities,insuranceclaimed by
workforce, statutory fine etc.
”
“
WHO HELPED US – THOU WILL BE REMEBERED, ALWAYS
• The Bombardier Story (by Larry MacDonald)
• Megaproject Management (by Virginia A Greiman)
• Safety in Underground Construction and Operation of the Explanatory Studies Facility at Yucca
Mountain (by US National Committee on Tunneling Technology and National Research Council)

More Related Content

What's hot

Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
VIDYA VIKAS INSTITUTE OF ENGINEERING AND TECHNOLOGY
 
Quality plan
Quality planQuality plan
Hidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) ConstructionHidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) Construction
GAURAV. H .TANDON
 
Quality management
Quality managementQuality management
Quality management
charliesleopanadan
 
Lead Regulatory Engineer
Lead Regulatory EngineerLead Regulatory Engineer
Lead Regulatory Engineerstephen ferris
 
Tennelli_Cost of Quality
Tennelli_Cost of QualityTennelli_Cost of Quality
Tennelli_Cost of Quality
Tennelli Industries (Pty) Ltd
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on Site
IRJET Journal
 
MillsAddendum-QualityManagerResponsibilitiesatMetoKote.docx
MillsAddendum-QualityManagerResponsibilitiesatMetoKote.docxMillsAddendum-QualityManagerResponsibilitiesatMetoKote.docx
MillsAddendum-QualityManagerResponsibilitiesatMetoKote.docxWilliam Mills
 
Construction quality control site inspection training (2) pages-deleted
Construction quality control  site inspection training (2) pages-deletedConstruction quality control  site inspection training (2) pages-deleted
Construction quality control site inspection training (2) pages-deleted
Sanjana Khound
 
Qaqc in civil construction
Qaqc in civil constructionQaqc in civil construction
Qaqc in civil construction
kaladharan pillai
 
Quality management templates
Quality management templatesQuality management templates
Quality management templatesselinasimpson371
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
IAEME Publication
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
SANJEEV Wazir
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
GiO Friginal
 
Qc
QcQc
17 1st review
17 1st review17 1st review
17 1st review
Vishnuvardhan s
 

What's hot (20)

Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
 
Quality plan
Quality planQuality plan
Quality plan
 
Hidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) ConstructionHidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) Construction
 
Quality management
Quality managementQuality management
Quality management
 
Lead Regulatory Engineer
Lead Regulatory EngineerLead Regulatory Engineer
Lead Regulatory Engineer
 
Tennelli_Cost of Quality
Tennelli_Cost of QualityTennelli_Cost of Quality
Tennelli_Cost of Quality
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on Site
 
MillsAddendum-QualityManagerResponsibilitiesatMetoKote.docx
MillsAddendum-QualityManagerResponsibilitiesatMetoKote.docxMillsAddendum-QualityManagerResponsibilitiesatMetoKote.docx
MillsAddendum-QualityManagerResponsibilitiesatMetoKote.docx
 
Construction quality control site inspection training (2) pages-deleted
Construction quality control  site inspection training (2) pages-deletedConstruction quality control  site inspection training (2) pages-deleted
Construction quality control site inspection training (2) pages-deleted
 
Qaqc in civil construction
Qaqc in civil constructionQaqc in civil construction
Qaqc in civil construction
 
Quality management templates
Quality management templatesQuality management templates
Quality management templates
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
 
Quality management forms
Quality management formsQuality management forms
Quality management forms
 
CV Michael Geer1
CV Michael Geer1CV Michael Geer1
CV Michael Geer1
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
The chunnel project
The chunnel projectThe chunnel project
The chunnel project
 
Qc
QcQc
Qc
 
Qa qc
Qa qcQa qc
Qa qc
 
17 1st review
17 1st review17 1st review
17 1st review
 

Similar to The channel tunnel - Safety Management

Resume Craig Edwards 042016
Resume  Craig Edwards 042016Resume  Craig Edwards 042016
Resume Craig Edwards 042016Craig Edwards
 
constructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptxconstructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptx
Sudas Duddey
 
constructionsafetymanagement-EAA.pdf
constructionsafetymanagement-EAA.pdfconstructionsafetymanagement-EAA.pdf
constructionsafetymanagement-EAA.pdf
ssuser2c065e
 
Construction Safety Management
Construction Safety ManagementConstruction Safety Management
Construction Safety Management
GAURAV. H .TANDON
 
Contractor Safe: Contractor Management & OHS Liability
  Contractor Safe: Contractor Management & OHS Liability  Contractor Safe: Contractor Management & OHS Liability
Contractor Safe: Contractor Management & OHS Liability
Australian Institute of Health & Safety
 
MFC )UPNEWS & INFORMATIONFind more productsupplier info.docx
MFC )UPNEWS & INFORMATIONFind more productsupplier info.docxMFC )UPNEWS & INFORMATIONFind more productsupplier info.docx
MFC )UPNEWS & INFORMATIONFind more productsupplier info.docx
ARIV4
 
UFR Hse supervision Resume
UFR Hse supervision ResumeUFR Hse supervision Resume
UFR Hse supervision Resume
olorunyomi wale
 
Construction Quality & Safety Management
Construction Quality & Safety ManagementConstruction Quality & Safety Management
Construction Quality & Safety Management
Yahaya Hassan Labaran
 
Update CV 01.08.15
Update CV 01.08.15Update CV 01.08.15
Update CV 01.08.15Edmar Reso
 
Employee Engagement
Employee Engagement Employee Engagement
Employee Engagement
John Newquist
 
Not Just Average
Not Just AverageNot Just Average
Not Just Average
Phil La Duke
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Kayode Aremu
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptx
malikshanii458
 
Alan Stewart(AJ) CV 2
Alan Stewart(AJ) CV 2Alan Stewart(AJ) CV 2
Alan Stewart(AJ) CV 2Alan Stewart
 

Similar to The channel tunnel - Safety Management (20)

Resume Craig Edwards 042016
Resume  Craig Edwards 042016Resume  Craig Edwards 042016
Resume Craig Edwards 042016
 
constructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptxconstructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptx
 
constructionsafetymanagement-EAA.pdf
constructionsafetymanagement-EAA.pdfconstructionsafetymanagement-EAA.pdf
constructionsafetymanagement-EAA.pdf
 
Construction Safety Management
Construction Safety ManagementConstruction Safety Management
Construction Safety Management
 
Contractor Safe: Contractor Management & OHS Liability
  Contractor Safe: Contractor Management & OHS Liability  Contractor Safe: Contractor Management & OHS Liability
Contractor Safe: Contractor Management & OHS Liability
 
Robert Wilson - CV 2015 A
Robert Wilson -  CV 2015 ARobert Wilson -  CV 2015 A
Robert Wilson - CV 2015 A
 
MFC )UPNEWS & INFORMATIONFind more productsupplier info.docx
MFC )UPNEWS & INFORMATIONFind more productsupplier info.docxMFC )UPNEWS & INFORMATIONFind more productsupplier info.docx
MFC )UPNEWS & INFORMATIONFind more productsupplier info.docx
 
TCI PRESENTATION
TCI PRESENTATIONTCI PRESENTATION
TCI PRESENTATION
 
UFR Hse supervision Resume
UFR Hse supervision ResumeUFR Hse supervision Resume
UFR Hse supervision Resume
 
Construction Quality & Safety Management
Construction Quality & Safety ManagementConstruction Quality & Safety Management
Construction Quality & Safety Management
 
Update CV 01.08.15
Update CV 01.08.15Update CV 01.08.15
Update CV 01.08.15
 
Employee Engagement
Employee Engagement Employee Engagement
Employee Engagement
 
Not Just Average
Not Just AverageNot Just Average
Not Just Average
 
TJCResume
TJCResumeTJCResume
TJCResume
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptx
 
AKEEM CV
AKEEM CVAKEEM CV
AKEEM CV
 
AKEEM CV
AKEEM CVAKEEM CV
AKEEM CV
 
Alan Stewart(AJ) CV 2
Alan Stewart(AJ) CV 2Alan Stewart(AJ) CV 2
Alan Stewart(AJ) CV 2
 

Recently uploaded

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 

Recently uploaded (20)

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 

The channel tunnel - Safety Management

  • 1. PROJECT SAFETY MANAGEMENT GROUP : 08 SECTION : 02 PEM : 16
  • 2. WHAT IS PROJECT SAFETY MANAGEMENT ? • Generally known as HSE or Health, Safety and EnvironmentManagement.Other forms are SHE and EHS. Depends on priority. Most commonly use form is HSE. • Ensures that the health (physicalor mental) of workforce is maintained,that they work in safe work environmentand there is no environmentalimpact. • HSE Policy, better known as Safety Policy, becomes more and more importantwith increase in Complexity of the Project. • The more number of stakeholdersand more is the importance of the Project, leads to the requirement of more stringent and carefullywritten safety policy • However, irrespective of size (cost and scope), safety is of utmost importance. Increases quality of work, productivityand helps saving cost.
  • 3. CASE STUDY – REHABILITATION OF EXISTING 40 YEARS OLD 200 MLD STP • LOCATION: Doha, Qatar • CLIENT: Public Works Authority (ASHGAL), Qatar • CONSULTANT: Parsons InternationalLimited, Qatar • CONTRACTOR : VA Tech Wabag Limited, India • SUB-CONTRACTORS : M/s Medgulf Construction Company WLL M/s Emcon Trading and Contracting LLC M/s Elite InternationalTrading & Maintainance M/s Voltech Group, India • PLANT OPERATORS : M/s Veolia Water M/s Metito Overseas Qatar
  • 4. WHAT MAKES THIS PROJECT COMPLEX? • Live or running or active plant – riskier than any other new project. • Multiplestakeholderslike client, consultant,contractor, multiplesub-contractors. • Change of Plant Operationresponsibilitiesfrom one company to another, while execution. • Strict local laws and regulationsfor health and safety. • FIFA World Cup – 2022 critical Project. Aims to reduce foul smell in the area during football matches (plant is barely 100 mtrs from a FIFA stadium).
  • 5. SAFETY POLICY – ON SITE • Anywork, prior to start, shall have approvedmethod statement with Risk Assessment. • Anywork, shall not be started without signed permit from contractor, plant operator, consultant and client • Individualattendance registers outside confinedspace areas– workforce made responsible for themselves and their buddyalloted • For all confined space work, buddysystem should be regulated • Anyoff time work shall not be executed without availabilityofsite emergency vehicle, first aider, HSE officer • Special works like liftingactivities, to be carried out in supervision of certified liftingsupervisor.Same for height works, confined space works etc. • PPE made mandatory.Violators are punished.Goodpractices are rewarded • SafetyWalk through every week. MOM is circulated and actions decided sought within same week
  • 6. CONTROL OVER HSE DEPARTMENT • Project Management team’scontrol over HSE team is very important.Although, HSE shall always function independent.However, the Project Manager is the head of safety committee, hence the control. • Quarterly Audits(External and Inter-Company) ensured to check all documentation arein place • Monthlysafety progress report. Root Cause analysisof all accidentsor incidents.Preventive actions proposed by HSE manager and approvedby Project Manager
  • 7. PROJECT SAFETY MANAGEMENT – STAGE WISE THE CHANNEL TUNNEL (CHUNNEL) PROJECT CONTRACTOR : TRANSMANCHE LINK (TML)
  • 8. INCEPTION PHASE • Maximum of the risks considered in this phase were purely technical.Process and approval risks were not envisaged. • Not much records of any safety risk considered during this phase. • The Project was considered simple initially and slowly turned complex with works adding. Probably addingto the risk list. • Scope of works were not clear. Even bidding was done without clearing the scope of works. This makes risk assessment prior to call for bid document extremely difficult. • Although the IGC had a Safety Authority – Independent– still it was of no particular use in pre-bidding stage.
  • 9. DEVELOPMENT PHASE • This phase was very importantand significant for TML management to decide the HSE structure in Organisation • TML made line management responsible for ensuring safety • Line management was under single, unified management, making HSE as well, responsibility of top management and line management. • CEO was also, Chief Safety Officer. • Traced safety responsibilityfrom Lead Hand to CEO • Example : One contractorchosen, about to work at the heart of the project, when asked to follow a safety measure told TML that they need approvalfrom their HSE team. • Moral : The respective personnel from Sub- Contractordid not have the authority to chose between right and wrong for his team.
  • 10. IMPLEMENTATION PHASE • Project Managerswere asked to set up Safety meeting, monthly, chaired by Line managers (juniormost) and CEO (senior most). Attended by Lead Handsas well. • Any accident or incidentto be investigatedby Lead Hand (party leader). Then reviewed by his/her supervisor, then line manager and so on until CEO. • Category of accidentsor incidentswere formed by line manager, insteadof instruction from top tier management. • Analysisof accidents or incidentsshowed that 95% of accidents or incidentshappeneddue to Human Behaviorsand not due to the extreme conditionslike undergroundworks • Example : Back Strain was common work place accident. Upon analysisand investigation,it was found that the method of pullingpoint levers was wrong. Same was rectified – increased productivityand reduced health risk. • TML had sensors to record temperature and gas levelsin the tunnel – permanent recording – direct data to controllers
  • 11. CLOSE OUT PHASE • The initialchange in safety organization,to include line managers and make them responsible, was the most complexchange in organization • Due to this change TML faced problems for the phased hand-over of the project to the client, ET. The principalcause for rejecting the proposed organizationhasbeen the failure to identify satisfactorilythe safety chain from the operativeto the chief executive. • The Project was closed in 1994 and entered the Operationand Maintenancephase with a very good safety review, throughout the four (4) stages of the project
  • 12. PROJECT SAFETY MANAGEMENT – RATING THE CHANNEL TUNNEL (CHUNNEL) PROJECT CONTRACTOR : TRANSMANCHE LINK (TML)
  • 13. RATINGS BASED ON CASE STUDY Phases • INITIATION PHASE • DEVELOPMENTPHASE • IMPLIMENTATIONPHASE • CLOSE OUT PHASE Rate (1-5) • 2 • 4 • 4 • 3
  • 14. PROJECT SAFETY MANAGEMENT – LESSONS LEARNED THE CHANNEL TUNNEL (CHUNNEL) PROJECT CONTRACTOR : TRANSMANCHE LINK (TML)
  • 15. WHAT DID WE LEARN ? • Safety of workforce shall alwaysbe on top priority. No project is bigger than a life. • Continuousevaluationof HSE policies required. • Ignorance is not bliss – in this case. Every worker deserves to go back to his/her family, safely. • Proper structuring of HSE organizationfor a project is very important. • Making Line Managersresponsible for their team’s safety and healthincreases productivityand quality in work. • FollowingHSE norms saves cost – like cost incurred due to accidents, fatalities,insuranceclaimed by workforce, statutory fine etc.
  • 16. ” “ WHO HELPED US – THOU WILL BE REMEBERED, ALWAYS • The Bombardier Story (by Larry MacDonald) • Megaproject Management (by Virginia A Greiman) • Safety in Underground Construction and Operation of the Explanatory Studies Facility at Yucca Mountain (by US National Committee on Tunneling Technology and National Research Council)