SlideShare a Scribd company logo
1
Term Project Paper on Design of Shallow and Deep Foundation for
a cement plant in Columbia
Submitted by
J M RAKIBUL HASAN (250821180)
24th April 2015 Graduate Program: Foundation Engineering
Professor M. Hesham El Naggar
The School of Civil and Environmental Engineering
The University of Western Ontario
London, Ontario, Canada
An Assignment submitted in partial fulfillment of the requirements
for the degree of Master of Engineering in Civil and Environmental
Engineering
2
Content
1. Project Background………………………………………………………………………….1
2. Project Description…………………………………………………………………………..1
3. Soil profile of Cement Plant…………………………………………………………………1
4. Design Conditions……………………………………………………………………………1
5. Design Expectations………………………………………………………………………….2
6. Scope of work………………………………………………………………………………...2
7. Design Criteria……………………………………………………………………………….2
Shallow Design 1………………………………………………………………………..3
Capacity Calculation…………………………………………………………...4
Settlement Calculation…………………………………………………………5
Plaxis Analysis…………………………………………………………………..7
Shallow design 2………………………………………………………………………...7
Capacity Calculation……………………………………………………………7
Settlement Calculation………………………………………………………….10
Plaxis Analysis…………………………………………………………………..11
Deep Design……………………………………………………………………………..13
Capacity Calculation and Pile parameters…………………………………....13
Single Pile Settlement Calculation……………………………………………..14
Group Pile Settlement Calculation…………………………………………….15
Lateral Capacity Calculation…………………………………………………..16
Lateral Deflection Calculation…………………………………………………17
8. Results of All Design Criteria……………………………………………………………….18
9. Recommended Design for Client…………………………………………………………....19
10. Appendix…………………………………………………………………………………….21
11. References…………………………………………………………………………………...27
3
1. Project Background
My given Project work is to design shallow and deep foundation for a Cement Plant. A cement
plant is a structure for grinding, mixing and processing Cement of various kinds for
constructional purpose. From a foundation engineering point of view the loading pattern of a
cement plant on existing foundation is not constant because after grinding and processing the
cement materials are taken away from plant and the amounts are not always the same. So the live
load on existing ground level may change rapidly but I have to design a foundation for the
maximum live load from a cement plan.
2. Project Description
My Project structure is Situated in Columbia, a country situated in the northwest of South
America, The soil between depths of 8 and 25 inches, (20 to 64 cm) is moist in some or all parts
from late October to late May or June and is dry in all parts the remainder of the year, unless
irrigated. The 10 to 40 inches, (25 to 102 cm) particle-size control section is stratified fine sandy
loam, very fine sandy loam, silt loam, loam, loamy sand, loamy fine sand, fine sand or sand and
averages 10 to 18 percent clay, when mixed, and has greater than 15 percent fine sand or coarser.
Up to 35 percent gravel may occur below a depth of 40 inches, (102 cm). Redoximorphic
features occur between 10 and 48 inches, (25 to 122 cm). Content of organic matter decreases
irregularly with depth.
3. Soil profile of Cement Plant
A geotechnical investigation was conducted to determine the soil parameters required for the
design, which 5 boreholes, BH‐5 to BH9 that extended to 60.0 m below ground surface. The site
generally consists of around 1.5 m of fill, followed by natural (native) cohesive (sandy silt clay,
sandy clay, lean clay, fat clay, silty clay, and clayey silt). Undisturbed soil samples were
retrieved using thin walled Shelby tubes and were used to determine the undrained shear strength
and deformation characteristics. In addition, geophysical study was conducted to determine the
dynamic soil properties of the site soils. The results from the field and laboratory tests are
provided in Tables 1‐4 of Appendix.
4. Design Conditions
It is required to design a foundation system to support a cement mill. The total static (dead) load
of the mill and associated equipment is 8,820 kN and the total operating load (dead + live loads)
is 25,100 kN. The top of concrete of the proposed foundation will be at the existing ground
elevation and the thickness of the foundation will be 5.0 m. To accommodate the mill and the
associated equipment, the foundation (or pile cap) has to be square with minimum side length of
4
20.0 m. The maximum (total) settlement allowed is 30 mm. The plant is located in a seismic
zone characterized by peak ground acceleration of 0.2 g.
5. Design Expectations
Different foundation options are considered for supporting the proposed mill, including:
1. Shallow Foundation
1) Shallow foundation resting on the native soil at depth 5.0 m below existing grade. In this
option, the design soil parameters that should be used in the design are based on the measured
properties presented in Tables 1‐4 and Figures 1‐4;
2) Shallow foundation option resting on improved soil (using the soil mixing technique) between
depths5.0 and 25.0 m below grade. In this option, the cement‐soil mixing technique with result in
minimum undrained shear strength of the improved soil, Su = 100 kPa. The soil improvement
technique will also reduce the compression ratio by at least 50%, i.e., CR improved soil = CR
native soil/2;
2. Deep foundation
1) The preferred deep foundation option is drilled cast in place piles. The available equipment
allows the construction of piles 0.60, 0.90, 1.20 and 1.50m diameter.
6. Scope of work
This is a practical problem for given loads and conditions. So different foundation system can be
compared to find the best foundation option for a client. Engineering Recommendation and
discussions on designed length, width, depth and other parameters of concrete foundation can
really pave the way of an economical solution
7. Design Criteria
Shallow
Deep
5
Shallow Design 1
1) Shallow foundation resting on the native soil at depth 5.0 m below existing grade. In this
option, the design soil parameters that should be used in the design are based on the measured
properties presented in Tables 1‐4 and Figures 1‐4;
Given Data
Depth eO CR RR m Mr j OCR Pc
5.55 0.404 0.078 0.014 29 164 0 5 343
9.9 0.896 0.132 0.037 17 62 0 2 215
BH 5 20.9 1.889 0.252 0.02 9 115 0 2.7 239
23.8 0.603 0.081 0.012 28 191 0 1 215
28.15 1.356 0.212 0.025 11 92 0 0.8 216
52 0.733 0.115 0.011 20 209 0 0.8 392
BH 6 3.25 0.75 0.108 0.017 21 135 0 5.2 225
26.95 0.598 0.1 0.012 23 192 0 1.1 284
4.75 0.893 0.137 0.042 17 55 0 4.2 225
BH 7 22.25 1.168 0.156 0.036 15 64 0 1.7 343
26.75 2.235 0.247 0.021 9 109 0 1.3 353
5.35 1.278 0.162 0.03 14 77 0 2.7 176
8.75 0.521 0.078 0.013 29 177 0 2.3 216
BH 8 20.75 1.46 0.227 0.032 10 72 0 1.8 363
25.15 0.085 0.105 0.016 22 144 0 0.9 206
29.15 0.645 0.079 0.024 29 96 0 0.8 206
4.7 0.658 0.108 0.036 22 64 0 5 274
10.75 0.62 0.08 0.024 29 96 0 2 216
BH 9 20.25 1.523 0.186 0.07 12 32 0 1 186
28.75 0.665 0.102 0.024 23 96 0 0.9 235
43.45 0.7 0.082 0.023 28 100 0 0.5 196
6
Data Extracted from Graphs (attached in Appendix)
Depth eo CR RR Cu OCR Gmax ϒ
5 0.8 0.12 0.03 55 4.3 52.946 18.2
10 0.7 0.095 0.035 70 2.9 162.464 19
15 1 0.14 0.02 90 2.9 193.4 19
20 1.6 0.2 0.03 50 1.2 159.626 17.8
25 0.6 0.1 0.025 100 2.5 142.79 17.4
30 0.7 0.09 0.024 150 2.5 208.258 19.5
35 0.7 0.085 0.024 175 2.5 242.66 19.5
40 0.6 0.08 0.022 175 1.3 249.226 19.5
45 0.7 0.08 0.023 175 1.3 166.786 19.5
50 0.7 0.11 0.011 175 1.3 261.78 19.5
55 0.6 0.12 0.01 175 1.3 263.668 19.5
Capacity Calculation
DL 8820
LL 16280
V(DL+LL) 25100
V(concrete) 138720
V(given+Conc) 163820
H(.2x(Foundation load x
DL))
11364
M 56820
e 0.346844
D 5
B 34
L 34
B' 33.30631
L' 33.30631
x 1
m 1.5
7
ϒ 19
D 5
sq 1
dq 1.294118
iq 1
bq 1
gq 1
Nq 1
Nc 5.14
q(ult) for
DL+LL
597.53 FOS 3 q(allow) 199.18 q(max)
Given
Vertical
load
141.71 q(allow)>q(max)
q(ult) for
seismic
578.09 FOS2.
5
q(allow) 231.24 q(max)
Given
Seismic
lateral Load
66.847 q(allow)>q(max)
Result
For Shallow Design 1 My design Satisfies Given Load for a Foundation of 34m X 34m X 5
square footing
Settlement Calculation
B 34
L 34
cu 73
sc 1.194553
dc 1.058824
ic 0.959047
bc 1
gc 1
8
V 25100
H 11364
cs 0.95
q 21.71280277
B 34
v 0.5
Eu 52794.2
Si 0.009963076
Sc 0.01983263
Settlement 0.029795706
29 mm
Plaxis Analysis
D E eo CR RR OCR Cr Cc ϒ ϒ' h B+Δz σ'vo Δσ' σ'p log((σ'vo+Δσ')/σ'vo) Sc
5 15.04 0.8 0.120 0.030 4.3 0.054 0.216 18.2 8.4 5 36.5 21 18.84 90.3 0.2781 0.0232
10 45.49 0.7 0.095 0.035 2.9 0.060 0.162 19 9.2 5 41.5 65 14.57 188.5 0.0879 0.0090
15 54.15 1 0.140 0.020 2.9 0.040 0.280 19 9.2 5 46.5 111 11.61 321.9 0.0432 0.0022
20 44.54 1.6 0.200 0.030 1.2 0.078 0.520 17.8 8 5 51.5 154 9.46 184.8 0.0259 0.0015
25 39.70 0.6 0.100 0.025 2.5 0.040 0.160 17.4 7.6 5 56.5 193 7.86 482.5 0.0173 0.0014
30 57.90 0.7 0.090 0.024 2.5 0.041 0.153 19.5 9.7 5 61.5 236.25 6.64 590.6 0.0120 0.0008
35 66.97 0.7 0.085 0.024 2.5 0.041 0.145 19.5 9.7 5 66.5 284.75 5.68 711.9 0.0086 0.0006
40 69.39 0.6 0.080 0.022 1.3 0.035 0.128 19.5 9.7 5 71.5 333.25 4.91 433.2 0.0064 0.0004
45 45.70 0.7 0.080 0.023 1.3 0.039 0.136 19.5 9.7 5 76.5 381.75 4.29 496.3 0.0049 0.0003
50 70.68 0.7 0.110 0.011 1.3 0.019 0.187 19.5 9.7 5 81.5 430.25 3.78 559.3 0.0038 0.0001
55 71.19 0.6 0.120 0.010 1.3 0.016 0.192 19.5 9.7 5 86.5 478.75 3.35 622.4 0.0030 9E-05
Total Sc 0.0198
9
Data Used in Plaxis
Depth ϒ Cu E
5 18.2 55 15.037
10 19 70 45.4894
15 19 90 54.1518
20 17.8 50 44.5374
25 17.4 100 39.6958
30 19.5 150 57.8954
35 19.5 175 66.973
40 19.5 175 69.3864
45 19.5 175 45.6996
50 19.5 175 70.6802
55 19.5 175 71.1902
10
Result
For Shallow Design 1 My design of 34 X 34 X 5 m footing settles for 29 mm and from Plaxis the
value is 29.1 mm
Shallow design 2
Shallow foundation option resting on improved soil (using the soil mixing technique) between
depths5.0 and 25.0 m below grade. In this option, the cement‐soil mixing technique with result in
minimum undrained shear strength of the improved soil, Su = 100 kPa. The soil improvement
technique will also reduce the compression ratio by at least 50%, i.e., CR improved soil = CR
native soil/2
Capacity Calculation
11
D 5
B 24
L 24
B' 22.34557
L' 22.34557
x 1
m 1.5
Nq 1
Nc 5.14
DL 8820
LL 16280
V(DL+LL) 25100
V(concrete) 69120
V(given+Conc) 94220
H 15588
M 77940
e 0.827213
ϒ 19
D 5
sq 1
dq 1.416667
iq 1
bq 1
gq 1
cu 100
sc 1.194553
dc 1.083333
ic 0.908896
bc 1
gc 1
12
q(ult)
for
DL+LL
799.75 FOS 3 q(allow) 266.5833 q(max)Give
n Vertical
load
163.5764 q(allow)
>q(max)
q(ult)
for
seismic
739.1509 FOS2.5 q(allow) 295.6604 q(max)Give
n Seismic
lateral Load
129.9 q(allow)
>q(max)
Settlement Calculation
cs 0.95
q 43.57639
B 24
v 0.5
Eu 52794.2
Si 0.014114
Sc 0.015416
Settlement 0.02953
29 mm
Depth E eo CR RR OCR Cr Cc ϒ ϒ' h B+Δz σ'vo Δσ' σ'p log((σ'vo+Δσ')/σ'vo) Sc
5 15.037 0.8 0.06 0.015 4.3 0.027 0.108 18.2 8.4 5 26.5 21 35.74225703 90.3 0.431687312 0.017986971
10 45.4894 0.7 0.0475 0.0175 2.9 0.02975 0.08075 19 9.2 5 31.5 65 25.29604434 188.5 0.142755369 0.007347703
15 54.1518 1 0.07 0.01 2.9 0.02 0.14 19 9.2 5 36.5 111 18.84030775 321.9 0.068086557 0.001702164
20 44.5374 1.6 0.1 0.015 1.2 0.039 0.26 17.8 8 5 41.5 154 14.57395848 184.8 0.039269764 0.001132782
25 39.6958 0.6 0.05 0.0125 2.5 0.02 0.08 17.4 7.6 5 46.5 193 11.60827841 482.5 0.025365892 0.000990855
30 57.8954 0.7 0.045 0.012 2.5 0.0204 0.0765 19.5 9.7 5 51.5 236.25 9.463662928 590.625 0.017057489 0.000602029
35 66.973 0.7 0.0425 0.012 2.5 0.0204 0.07225 19.5 9.7 5 56.5 284.75 7.862792701 711.875 0.011829576 0.000417514
40 69.3864 0.6 0.04 0.011 1.3 0.0176 0.064 19.5 9.7 5 61.5 333.25 6.636261485 433.225 0.008563452 0.000294369
45 45.6996 0.7 0.04 0.0115 1.3 0.01955 0.068 19.5 9.7 5 66.5 381.75 5.675843745 496.275 0.006409542 0.000216793
50 70.6802 0.7 0.055 0.0055 1.3 0.00935 0.0935 19.5 9.7 5 71.5 430.25 4.909775539 559.325 0.004927865 7.97155E-05
55 71.1902 0.6 0.06 0.005 1.3 0.008 0.096 19.5 9.7 5 76.5 478.75 4.288948695 622.375 0.003873363 6.05213E-05
Total Sc 0.015415709
13
Plaxis Analysis
Data Used
Depth ϒ Cu E
5 18.2 100 15.037
10 19 100 45.4894
15 19 100 54.1518
20 17.8 100 44.5374
25 17.4 100 39.6958
30 19.5 150 57.8954
35 19.5 175 66.973
40 19.5 175 69.3864
45 19.5 175 45.6996
50 19.5 175 70.6802
55 19.5 175 71.1902
14
Result
For Shallow Design 1 My design of 24 X 24 X 5 m footing settles for 29 mm and from Plaxis the
value is 28 mm
15
Deep Design
Capacity Calculation and Pile parameters
Depth Cu Δz α Qs
2 15 2 1 141.372
7 55 5 0.9 1166.319
12 70 5 0.3 494.802
16 90 4 0.9 1526.818
21 50 5 0.25 294.525
27 100 6 0.25 706.86
32 150 5 0.25 883.575
40 175 8 0.3 1979.208
45 175 5 0.3 1237.005
50 175 5 0.3 1237.005
55 175 5 0.3 1237.005
V 25100
FS 3
Qu group 75300
G 0.7
n 23.90295
25 pcs
Qgroup
(design)
26252
Qu (design) 78755.99
L 25
d 0.6
Le 25
Ab 0.282744
Nc 6
Cub 100
Circumfurence 4.7124
Qb 169.6464
Qs 4330.696
Qult 4500.342
Qsingle 1500.114
16
Result
For Given Calculation my Engineering calculation and recommends to have 25 pieces of 25
meter concretes bored piles of .6m diameter
Single Pile Settlement Calculation
L 25
d 0.6
Cs 0.058884
Cb 0.03
fb 2119
Qb 296.8812
Qs 4330.696
FOS 3
cub 175
Nc 9
σvb 544
Qba 98.9604
Qsa 1443.565
αs 0.67
Ap 0.282744
Ep 30000000
17
Sss 0.001605
Ssb 0.001335
Sp 0.003142
Ssingle 0.006082
6 mm
Group Pile Settlement Calculation
dc 4.4
L 25
n 25
Ap 0.2827
Ep 30000000
b' 9
l' 9
Es 198911.4
Qa 1004
Eeq 3319196
S 0.0300295
30 mm
18
n 25
w 0.5
Rs 5
SG 0.03041
30 mm
Lateral Capacity Calculation
Solving this two equation we get a quadric equation and from there I got my Pile capacity of
451.39 Kpa for single Pile and 11284.7kpa for group Pile. My Myeild was greater than Mmax so
I used Long pile fixed head formula, though I have a short pile .
I 0.00636
S 0.021
fy 30000
fr 0.6
M yield 378
19
P 293.112 x f
f 1.54
P 451.39
PG 11284.75
Lateral Deflection Calculation
yg = HfyF
H 11364
L 25
d 0.6
fy 30000000
Ep 24647515.09
Es 1989114
K 12.39120286
fyh 6.92424E-07
fθH 9.89827E-07
fθM 3.40959E-06
fyF 4.0507E-07
yg 0.004603
4.6 mm
20
8. Results of All Design Criteria
1. Shallow Foundation Type 1
Design 34m X 34m X 5m concrete square footing.
Capacity vertical load
q allowable =199.1757 kpa
q max =141.71 kpa
Capacity for seismic load
q allowable = 217.4114224 kpa
q max = 173.5764706 kpa
Settlement
29 mm
2. Shallow Foundation Type 2
Design 24m X 24m X 5m concrete square footing.
Capacity for vertical load
q allowable = 266.5833333 kpa
q max = 163.5763889 kpa
Capacity for seismic load
q allowable = 295.660371 kpa
q max = 129.9 kpa
Settlement
29mm
21
3. Deep Foundation Type 1
Design: 25 meter deep, 0.6 meter diameter 25 pcs of concrete pile bored in a distance of 1.8
meter
Capacity
q single = 1542.5256 kpa
q Group = 26994.198 kpa
Settlement
Ssingle =6 mm
Sgroup =30 mm
Lateral Capacity
q single = 451.39 kpa
q group = 11284.75 kpa
Lateral Deflection
4.6 mm
9. Recommended Design for Client
The transfer of loads from deep foundations to the soil is different from that of shallow
foundations. Shallow foundations primarily transfer the load to the soil via bearing pressure.
Deep foundations also transfer the load via friction along the length (or depth) of the foundation,
called skin friction. The force that remains at the bottom of the deep foundation is transferred to
the soil by bearing pressure.
Shallow foundations, often called footings, are usually embedded about few meters into soil ( in
this case 5 meters) One common type is the spread footing which consists of strips or pads of
concrete (or other materials) which extend below the frost line and transfer the weight from walls
and columns to the soil or bedrock. Another common type of shallow foundation is the slab-on-
grade foundation where the weight of the building is transferred to the soil through a concrete
slab placed at the surface. Slab-on-grade foundations can be reinforced mat slabs, which range
from 30 cm to several meters thick, depending on the size of the building, or post-tensioned
slabs, which are typically at least 20 cm for houses, and thicker for heavier structures. A deep
foundation is used to transfer the load of a structure down through the upper weak layer of
22
topsoil to the stronger layer of subsoil below. There are different types of deep footings including
impact driven piles, drilled shafts, caissons, helical piles, geo-piers and earth stabilized columns.
The naming conventions for different types of footings vary between different engineers.
Historically, piles were wood, later steel, reinforced concrete, and pre-tensioned concrete.
In this case my engineering recommendation is Deep foundation Type 1.If I have a chance to
install shallow foundation over a deep foundation I would definitely go for that always because
deep foundations are complicated to install and it is expensive than shallow foundation. In my
design I have 25 piles means I have to make 25 bore hole and I have to bore those until 25
meters of depth with 1.8 meters of spacing, so for avoiding complicated design and cost I would
prefer Shallow foundation
Now I have 2 options for shallow foundation. One is in improved soil and my designed footing is
24 X 24 X 5 which is much lesser than the designed footing of 34 X 34 X 5 in natural soil. So
volume of concrete is more in shallow foundation design 1 but I would still go for design 1
because improving soil up to 25 meters would be so costly and the installation procedure would
take much time because I have to excavate soil up to a fair amount of depth of 25 meters. So
counting time and money as well design complicacy I would recommend my client to go for
Shallow foundation design type 1.
23
10. Appendix
Tables
Table 1
24
Table 2
Table 3
25
Table 4
26
Table 5
27
Table 6
Graphs
Graph 1
28
Graph 2
Graph 3
29
Graph 4
11. References
1. Lecture Notes of M. Hesham El Naggar, Ph.D., P. Eng., MASCE, FEIC,Professor and
Research Director,Geotechnical Research Centre
2. soilseries.sc.egov.usda.gov/OSD_Docs/C/COLUMBIA.html
30
3. http://en.wikipedia.org/wiki/Deep_foundation
4. Simplified Design of Building Foundations, 2nd Edition by James Ambrose (Author)
5. Building Foundations of Scientific Understanding: A Science Curriculum for K-2 by
Bernard J. Nebel (Author)
6. Foundation Engineering P. C. VARGHESE
7. Foundation Engineering Handbook by Robert Day McGraw Hill Professional, Dec 12,
2005

More Related Content

What's hot

Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
 
Settlement of soil/foundation
Settlement of soil/foundationSettlement of soil/foundation
Settlement of soil/foundation
Jam Shoaib Ahmed veeha
 
Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing
Pirpasha Ujede
 
Lateral Earth Pressure
Lateral Earth PressureLateral Earth Pressure
Lateral Earth Pressure
Fast-NU Lahore
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniques
AHMED NADIM JILANI
 
Effect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionEffect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its prevention
Sailish Cephas
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
VARANASI RAMA RAO
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
Infocengrs63
 
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981) OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
5006
 
Foundation
FoundationFoundation
Foundation
Parth Malhotra
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
HERITAGE INFRASPACE INDIA PRIVATE LIMITED
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
tirath prajapati
 
Soil exploration
Soil explorationSoil exploration
Soil exploration
Rajput Satyam Lodhi
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Make Mannan
 
Methods Of Improving Soil Bearing Capacity
Methods Of Improving Soil Bearing CapacityMethods Of Improving Soil Bearing Capacity
Methods Of Improving Soil Bearing Capacity
Vibhanshu Singh
 
Earth retaining 2
Earth retaining 2Earth retaining 2
Earth retaining 2
MarlizaAshiqin
 
_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)
sharda university
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
Mohit Goyal
 

What's hot (20)

Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 
Settlement of soil/foundation
Settlement of soil/foundationSettlement of soil/foundation
Settlement of soil/foundation
 
Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing
 
Lateral Earth Pressure
Lateral Earth PressureLateral Earth Pressure
Lateral Earth Pressure
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniques
 
Effect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionEffect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its prevention
 
Foundation 1
Foundation 1Foundation 1
Foundation 1
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
 
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981) OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
 
Foundation
FoundationFoundation
Foundation
 
Section 300
Section 300Section 300
Section 300
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
 
Soil exploration
Soil explorationSoil exploration
Soil exploration
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Methods Of Improving Soil Bearing Capacity
Methods Of Improving Soil Bearing CapacityMethods Of Improving Soil Bearing Capacity
Methods Of Improving Soil Bearing Capacity
 
Earth retaining 2
Earth retaining 2Earth retaining 2
Earth retaining 2
 
_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
 

Viewers also liked

Shallow Foundations
Shallow FoundationsShallow Foundations
Shallow FoundationsJames Smith
 
الاساسات
الاساساتالاساسات
الاساسات
Mohamed Ahmed
 
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...
Make Mannan
 
Shallow foundation(by indrajit mitra)01
Shallow   foundation(by indrajit mitra)01Shallow   foundation(by indrajit mitra)01
Shallow foundation(by indrajit mitra)01
Indrajit Ind
 
Shallow Foundation
Shallow FoundationShallow Foundation
Shallow Foundation
Md. Shahadat Hossain
 
Construction material lime
Construction material limeConstruction material lime
Construction material lime
Manish Jain Luhadia
 
اسلینگ چیست؟
اسلینگ چیست؟اسلینگ چیست؟
اسلینگ چیست؟
Dr Sanaat
 
Cardox Technology for the Steel Industry
Cardox Technology for the Steel IndustryCardox Technology for the Steel Industry
Cardox Technology for the Steel Industry
ATD-Pressure Gas System
 
Foundation types
Foundation typesFoundation types
Foundation types
ProBest Pest Management
 
Foundation
FoundationFoundation
Foundation
er_kamal
 
Ch6 mfg pro.sel. & design
Ch6 mfg pro.sel. & designCh6 mfg pro.sel. & design
Ch6 mfg pro.sel. & designvideoaakash15
 
Lime
LimeLime
Cardox Technology for the Lime Industry
Cardox Technology for the Lime IndustryCardox Technology for the Lime Industry
Cardox Technology for the Lime Industry
ATD-Pressure Gas System
 
Bussines Plan for Car Manufacturing
Bussines Plan for Car ManufacturingBussines Plan for Car Manufacturing
Bussines Plan for Car Manufacturing
Rupal Lala
 
3. lime
3. lime3. lime
3. lime
htictan
 
lime and its uses in engineering.
lime and its uses in engineering.lime and its uses in engineering.
lime and its uses in engineering.
archixet
 
Limestone presentation by ruchika
Limestone presentation by ruchikaLimestone presentation by ruchika
Limestone presentation by ruchika
DaveRuchika
 
Steel 1 - Layout , Design of Sections - تصميم المنشآت المعدنية
Steel 1 - Layout , Design of Sections - تصميم المنشآت المعدنيةSteel 1 - Layout , Design of Sections - تصميم المنشآت المعدنية
Steel 1 - Layout , Design of Sections - تصميم المنشآت المعدنية
Karim Gaber
 
Cement testing
Cement testingCement testing
Cement testing
Narendra Kanchkar
 

Viewers also liked (20)

Shallow Foundations
Shallow FoundationsShallow Foundations
Shallow Foundations
 
الاساسات
الاساساتالاساسات
الاساسات
 
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...Numerical Problem and solution on Bearing Capacity  ( Terzaghi and Meyerhof T...
Numerical Problem and solution on Bearing Capacity ( Terzaghi and Meyerhof T...
 
Shallow foundation(by indrajit mitra)01
Shallow   foundation(by indrajit mitra)01Shallow   foundation(by indrajit mitra)01
Shallow foundation(by indrajit mitra)01
 
Shallow Foundation
Shallow FoundationShallow Foundation
Shallow Foundation
 
Construction material lime
Construction material limeConstruction material lime
Construction material lime
 
اسلینگ چیست؟
اسلینگ چیست؟اسلینگ چیست؟
اسلینگ چیست؟
 
Cardox Technology for the Steel Industry
Cardox Technology for the Steel IndustryCardox Technology for the Steel Industry
Cardox Technology for the Steel Industry
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Foundation
FoundationFoundation
Foundation
 
Ch6 mfg pro.sel. & design
Ch6 mfg pro.sel. & designCh6 mfg pro.sel. & design
Ch6 mfg pro.sel. & design
 
Lime
LimeLime
Lime
 
Cardox Technology for the Lime Industry
Cardox Technology for the Lime IndustryCardox Technology for the Lime Industry
Cardox Technology for the Lime Industry
 
Bussines Plan for Car Manufacturing
Bussines Plan for Car ManufacturingBussines Plan for Car Manufacturing
Bussines Plan for Car Manufacturing
 
3. lime
3. lime3. lime
3. lime
 
lime and its uses in engineering.
lime and its uses in engineering.lime and its uses in engineering.
lime and its uses in engineering.
 
Limestone presentation by ruchika
Limestone presentation by ruchikaLimestone presentation by ruchika
Limestone presentation by ruchika
 
Limestone
LimestoneLimestone
Limestone
 
Steel 1 - Layout , Design of Sections - تصميم المنشآت المعدنية
Steel 1 - Layout , Design of Sections - تصميم المنشآت المعدنيةSteel 1 - Layout , Design of Sections - تصميم المنشآت المعدنية
Steel 1 - Layout , Design of Sections - تصميم المنشآت المعدنية
 
Cement testing
Cement testingCement testing
Cement testing
 

Similar to Term Project Paper on Design of Shallow and Deep Foundation for a cement plant in Columbia

QS.pdf
QS.pdfQS.pdf
QS.pdf
ErTipuSultan
 
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET Journal
 
CIVE 416 report(final)
CIVE 416 report(final)CIVE 416 report(final)
CIVE 416 report(final)Monique F M
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
MUHAMMAD NOMAN KHAN
 
Draft report
Draft reportDraft report
Draft report
abdullahmohideen
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportJoshua Yu
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
ashleyyeap
 
Waste Foundry Sand as Partial Replacement of Fine aggregate in Concrete
Waste Foundry Sand as Partial Replacement of Fine aggregate in ConcreteWaste Foundry Sand as Partial Replacement of Fine aggregate in Concrete
Waste Foundry Sand as Partial Replacement of Fine aggregate in Concrete
IRJET Journal
 
Construction Management Project
Construction Management ProjectConstruction Management Project
Construction Management Project
Muhammad Umar Hayat
 
Project of construction management
Project of construction managementProject of construction management
Project of construction management
Muhammad Umar Hayat
 
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Carlo Gabriele Borri MACostE AMICE
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary ReportNatalie Reid
 
Frother type Impact over size by size Cu recovery
Frother type Impact over size by size Cu recoveryFrother type Impact over size by size Cu recovery
Frother type Impact over size by size Cu recovery
Juan J. Anes B.Sc, M.Sc, P.Eng
 
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Lovneesh Modi
 
mort.250.2013.pdf
mort.250.2013.pdfmort.250.2013.pdf
mort.250.2013.pdf
lokeshnandina
 

Similar to Term Project Paper on Design of Shallow and Deep Foundation for a cement plant in Columbia (20)

GP Report
GP ReportGP Report
GP Report
 
QS.pdf
QS.pdfQS.pdf
QS.pdf
 
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
 
CIVE 416 report(final)
CIVE 416 report(final)CIVE 416 report(final)
CIVE 416 report(final)
 
Group 3 Presentation
Group 3 PresentationGroup 3 Presentation
Group 3 Presentation
 
Training PPT
Training PPTTraining PPT
Training PPT
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
 
Draft report
Draft reportDraft report
Draft report
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering Report
 
NNH
NNHNNH
NNH
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 
Waste Foundry Sand as Partial Replacement of Fine aggregate in Concrete
Waste Foundry Sand as Partial Replacement of Fine aggregate in ConcreteWaste Foundry Sand as Partial Replacement of Fine aggregate in Concrete
Waste Foundry Sand as Partial Replacement of Fine aggregate in Concrete
 
Construction Management Project
Construction Management ProjectConstruction Management Project
Construction Management Project
 
Project of construction management
Project of construction managementProject of construction management
Project of construction management
 
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
 
FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary Report
 
Frother type Impact over size by size Cu recovery
Frother type Impact over size by size Cu recoveryFrother type Impact over size by size Cu recovery
Frother type Impact over size by size Cu recovery
 
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
 
mort.250.2013.pdf
mort.250.2013.pdfmort.250.2013.pdf
mort.250.2013.pdf
 

More from Rakibul Hasan,MEng,EIT

Effectiveness of SODIS in Rural and Urban Areas of Bangladesh
Effectiveness of SODIS in Rural and Urban Areas of BangladeshEffectiveness of SODIS in Rural and Urban Areas of Bangladesh
Effectiveness of SODIS in Rural and Urban Areas of Bangladesh
Rakibul Hasan,MEng,EIT
 
Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...
Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...
Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...
Rakibul Hasan,MEng,EIT
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, France
Rakibul Hasan,MEng,EIT
 
Survey on Frazer River Sand in Richmond, British Columbia, Canada
Survey on Frazer River Sand in Richmond, British Columbia, CanadaSurvey on Frazer River Sand in Richmond, British Columbia, Canada
Survey on Frazer River Sand in Richmond, British Columbia, Canada
Rakibul Hasan,MEng,EIT
 
Design of a Cold Storage Warehouse Using Building Information Modeling
Design of a Cold Storage Warehouse Using Building Information ModelingDesign of a Cold Storage Warehouse Using Building Information Modeling
Design of a Cold Storage Warehouse Using Building Information Modeling
Rakibul Hasan,MEng,EIT
 
Design of Wind Generated Structural Response of a Tall Building Situated in T...
Design of Wind Generated Structural Response of a Tall Building Situated in T...Design of Wind Generated Structural Response of a Tall Building Situated in T...
Design of Wind Generated Structural Response of a Tall Building Situated in T...
Rakibul Hasan,MEng,EIT
 
Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...
Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...
Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...
Rakibul Hasan,MEng,EIT
 
Sustainable Building Strategies for Toronto
Sustainable Building Strategies for TorontoSustainable Building Strategies for Toronto
Sustainable Building Strategies for Toronto
Rakibul Hasan,MEng,EIT
 

More from Rakibul Hasan,MEng,EIT (8)

Effectiveness of SODIS in Rural and Urban Areas of Bangladesh
Effectiveness of SODIS in Rural and Urban Areas of BangladeshEffectiveness of SODIS in Rural and Urban Areas of Bangladesh
Effectiveness of SODIS in Rural and Urban Areas of Bangladesh
 
Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...
Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...
Assessment and Remediation of Dominant Contaminants of Picatinny Arsenal, New...
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, France
 
Survey on Frazer River Sand in Richmond, British Columbia, Canada
Survey on Frazer River Sand in Richmond, British Columbia, CanadaSurvey on Frazer River Sand in Richmond, British Columbia, Canada
Survey on Frazer River Sand in Richmond, British Columbia, Canada
 
Design of a Cold Storage Warehouse Using Building Information Modeling
Design of a Cold Storage Warehouse Using Building Information ModelingDesign of a Cold Storage Warehouse Using Building Information Modeling
Design of a Cold Storage Warehouse Using Building Information Modeling
 
Design of Wind Generated Structural Response of a Tall Building Situated in T...
Design of Wind Generated Structural Response of a Tall Building Situated in T...Design of Wind Generated Structural Response of a Tall Building Situated in T...
Design of Wind Generated Structural Response of a Tall Building Situated in T...
 
Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...
Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...
Design of a Minor Storm Water Management System Using XPSWMM for London, Onta...
 
Sustainable Building Strategies for Toronto
Sustainable Building Strategies for TorontoSustainable Building Strategies for Toronto
Sustainable Building Strategies for Toronto
 

Recently uploaded

Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Term Project Paper on Design of Shallow and Deep Foundation for a cement plant in Columbia

  • 1. 1 Term Project Paper on Design of Shallow and Deep Foundation for a cement plant in Columbia Submitted by J M RAKIBUL HASAN (250821180) 24th April 2015 Graduate Program: Foundation Engineering Professor M. Hesham El Naggar The School of Civil and Environmental Engineering The University of Western Ontario London, Ontario, Canada An Assignment submitted in partial fulfillment of the requirements for the degree of Master of Engineering in Civil and Environmental Engineering
  • 2. 2 Content 1. Project Background………………………………………………………………………….1 2. Project Description…………………………………………………………………………..1 3. Soil profile of Cement Plant…………………………………………………………………1 4. Design Conditions……………………………………………………………………………1 5. Design Expectations………………………………………………………………………….2 6. Scope of work………………………………………………………………………………...2 7. Design Criteria……………………………………………………………………………….2 Shallow Design 1………………………………………………………………………..3 Capacity Calculation…………………………………………………………...4 Settlement Calculation…………………………………………………………5 Plaxis Analysis…………………………………………………………………..7 Shallow design 2………………………………………………………………………...7 Capacity Calculation……………………………………………………………7 Settlement Calculation………………………………………………………….10 Plaxis Analysis…………………………………………………………………..11 Deep Design……………………………………………………………………………..13 Capacity Calculation and Pile parameters…………………………………....13 Single Pile Settlement Calculation……………………………………………..14 Group Pile Settlement Calculation…………………………………………….15 Lateral Capacity Calculation…………………………………………………..16 Lateral Deflection Calculation…………………………………………………17 8. Results of All Design Criteria……………………………………………………………….18 9. Recommended Design for Client…………………………………………………………....19 10. Appendix…………………………………………………………………………………….21 11. References…………………………………………………………………………………...27
  • 3. 3 1. Project Background My given Project work is to design shallow and deep foundation for a Cement Plant. A cement plant is a structure for grinding, mixing and processing Cement of various kinds for constructional purpose. From a foundation engineering point of view the loading pattern of a cement plant on existing foundation is not constant because after grinding and processing the cement materials are taken away from plant and the amounts are not always the same. So the live load on existing ground level may change rapidly but I have to design a foundation for the maximum live load from a cement plan. 2. Project Description My Project structure is Situated in Columbia, a country situated in the northwest of South America, The soil between depths of 8 and 25 inches, (20 to 64 cm) is moist in some or all parts from late October to late May or June and is dry in all parts the remainder of the year, unless irrigated. The 10 to 40 inches, (25 to 102 cm) particle-size control section is stratified fine sandy loam, very fine sandy loam, silt loam, loam, loamy sand, loamy fine sand, fine sand or sand and averages 10 to 18 percent clay, when mixed, and has greater than 15 percent fine sand or coarser. Up to 35 percent gravel may occur below a depth of 40 inches, (102 cm). Redoximorphic features occur between 10 and 48 inches, (25 to 122 cm). Content of organic matter decreases irregularly with depth. 3. Soil profile of Cement Plant A geotechnical investigation was conducted to determine the soil parameters required for the design, which 5 boreholes, BH‐5 to BH9 that extended to 60.0 m below ground surface. The site generally consists of around 1.5 m of fill, followed by natural (native) cohesive (sandy silt clay, sandy clay, lean clay, fat clay, silty clay, and clayey silt). Undisturbed soil samples were retrieved using thin walled Shelby tubes and were used to determine the undrained shear strength and deformation characteristics. In addition, geophysical study was conducted to determine the dynamic soil properties of the site soils. The results from the field and laboratory tests are provided in Tables 1‐4 of Appendix. 4. Design Conditions It is required to design a foundation system to support a cement mill. The total static (dead) load of the mill and associated equipment is 8,820 kN and the total operating load (dead + live loads) is 25,100 kN. The top of concrete of the proposed foundation will be at the existing ground elevation and the thickness of the foundation will be 5.0 m. To accommodate the mill and the associated equipment, the foundation (or pile cap) has to be square with minimum side length of
  • 4. 4 20.0 m. The maximum (total) settlement allowed is 30 mm. The plant is located in a seismic zone characterized by peak ground acceleration of 0.2 g. 5. Design Expectations Different foundation options are considered for supporting the proposed mill, including: 1. Shallow Foundation 1) Shallow foundation resting on the native soil at depth 5.0 m below existing grade. In this option, the design soil parameters that should be used in the design are based on the measured properties presented in Tables 1‐4 and Figures 1‐4; 2) Shallow foundation option resting on improved soil (using the soil mixing technique) between depths5.0 and 25.0 m below grade. In this option, the cement‐soil mixing technique with result in minimum undrained shear strength of the improved soil, Su = 100 kPa. The soil improvement technique will also reduce the compression ratio by at least 50%, i.e., CR improved soil = CR native soil/2; 2. Deep foundation 1) The preferred deep foundation option is drilled cast in place piles. The available equipment allows the construction of piles 0.60, 0.90, 1.20 and 1.50m diameter. 6. Scope of work This is a practical problem for given loads and conditions. So different foundation system can be compared to find the best foundation option for a client. Engineering Recommendation and discussions on designed length, width, depth and other parameters of concrete foundation can really pave the way of an economical solution 7. Design Criteria Shallow Deep
  • 5. 5 Shallow Design 1 1) Shallow foundation resting on the native soil at depth 5.0 m below existing grade. In this option, the design soil parameters that should be used in the design are based on the measured properties presented in Tables 1‐4 and Figures 1‐4; Given Data Depth eO CR RR m Mr j OCR Pc 5.55 0.404 0.078 0.014 29 164 0 5 343 9.9 0.896 0.132 0.037 17 62 0 2 215 BH 5 20.9 1.889 0.252 0.02 9 115 0 2.7 239 23.8 0.603 0.081 0.012 28 191 0 1 215 28.15 1.356 0.212 0.025 11 92 0 0.8 216 52 0.733 0.115 0.011 20 209 0 0.8 392 BH 6 3.25 0.75 0.108 0.017 21 135 0 5.2 225 26.95 0.598 0.1 0.012 23 192 0 1.1 284 4.75 0.893 0.137 0.042 17 55 0 4.2 225 BH 7 22.25 1.168 0.156 0.036 15 64 0 1.7 343 26.75 2.235 0.247 0.021 9 109 0 1.3 353 5.35 1.278 0.162 0.03 14 77 0 2.7 176 8.75 0.521 0.078 0.013 29 177 0 2.3 216 BH 8 20.75 1.46 0.227 0.032 10 72 0 1.8 363 25.15 0.085 0.105 0.016 22 144 0 0.9 206 29.15 0.645 0.079 0.024 29 96 0 0.8 206 4.7 0.658 0.108 0.036 22 64 0 5 274 10.75 0.62 0.08 0.024 29 96 0 2 216 BH 9 20.25 1.523 0.186 0.07 12 32 0 1 186 28.75 0.665 0.102 0.024 23 96 0 0.9 235 43.45 0.7 0.082 0.023 28 100 0 0.5 196
  • 6. 6 Data Extracted from Graphs (attached in Appendix) Depth eo CR RR Cu OCR Gmax ϒ 5 0.8 0.12 0.03 55 4.3 52.946 18.2 10 0.7 0.095 0.035 70 2.9 162.464 19 15 1 0.14 0.02 90 2.9 193.4 19 20 1.6 0.2 0.03 50 1.2 159.626 17.8 25 0.6 0.1 0.025 100 2.5 142.79 17.4 30 0.7 0.09 0.024 150 2.5 208.258 19.5 35 0.7 0.085 0.024 175 2.5 242.66 19.5 40 0.6 0.08 0.022 175 1.3 249.226 19.5 45 0.7 0.08 0.023 175 1.3 166.786 19.5 50 0.7 0.11 0.011 175 1.3 261.78 19.5 55 0.6 0.12 0.01 175 1.3 263.668 19.5 Capacity Calculation DL 8820 LL 16280 V(DL+LL) 25100 V(concrete) 138720 V(given+Conc) 163820 H(.2x(Foundation load x DL)) 11364 M 56820 e 0.346844 D 5 B 34 L 34 B' 33.30631 L' 33.30631 x 1 m 1.5
  • 7. 7 ϒ 19 D 5 sq 1 dq 1.294118 iq 1 bq 1 gq 1 Nq 1 Nc 5.14 q(ult) for DL+LL 597.53 FOS 3 q(allow) 199.18 q(max) Given Vertical load 141.71 q(allow)>q(max) q(ult) for seismic 578.09 FOS2. 5 q(allow) 231.24 q(max) Given Seismic lateral Load 66.847 q(allow)>q(max) Result For Shallow Design 1 My design Satisfies Given Load for a Foundation of 34m X 34m X 5 square footing Settlement Calculation B 34 L 34 cu 73 sc 1.194553 dc 1.058824 ic 0.959047 bc 1 gc 1
  • 8. 8 V 25100 H 11364 cs 0.95 q 21.71280277 B 34 v 0.5 Eu 52794.2 Si 0.009963076 Sc 0.01983263 Settlement 0.029795706 29 mm Plaxis Analysis D E eo CR RR OCR Cr Cc ϒ ϒ' h B+Δz σ'vo Δσ' σ'p log((σ'vo+Δσ')/σ'vo) Sc 5 15.04 0.8 0.120 0.030 4.3 0.054 0.216 18.2 8.4 5 36.5 21 18.84 90.3 0.2781 0.0232 10 45.49 0.7 0.095 0.035 2.9 0.060 0.162 19 9.2 5 41.5 65 14.57 188.5 0.0879 0.0090 15 54.15 1 0.140 0.020 2.9 0.040 0.280 19 9.2 5 46.5 111 11.61 321.9 0.0432 0.0022 20 44.54 1.6 0.200 0.030 1.2 0.078 0.520 17.8 8 5 51.5 154 9.46 184.8 0.0259 0.0015 25 39.70 0.6 0.100 0.025 2.5 0.040 0.160 17.4 7.6 5 56.5 193 7.86 482.5 0.0173 0.0014 30 57.90 0.7 0.090 0.024 2.5 0.041 0.153 19.5 9.7 5 61.5 236.25 6.64 590.6 0.0120 0.0008 35 66.97 0.7 0.085 0.024 2.5 0.041 0.145 19.5 9.7 5 66.5 284.75 5.68 711.9 0.0086 0.0006 40 69.39 0.6 0.080 0.022 1.3 0.035 0.128 19.5 9.7 5 71.5 333.25 4.91 433.2 0.0064 0.0004 45 45.70 0.7 0.080 0.023 1.3 0.039 0.136 19.5 9.7 5 76.5 381.75 4.29 496.3 0.0049 0.0003 50 70.68 0.7 0.110 0.011 1.3 0.019 0.187 19.5 9.7 5 81.5 430.25 3.78 559.3 0.0038 0.0001 55 71.19 0.6 0.120 0.010 1.3 0.016 0.192 19.5 9.7 5 86.5 478.75 3.35 622.4 0.0030 9E-05 Total Sc 0.0198
  • 9. 9 Data Used in Plaxis Depth ϒ Cu E 5 18.2 55 15.037 10 19 70 45.4894 15 19 90 54.1518 20 17.8 50 44.5374 25 17.4 100 39.6958 30 19.5 150 57.8954 35 19.5 175 66.973 40 19.5 175 69.3864 45 19.5 175 45.6996 50 19.5 175 70.6802 55 19.5 175 71.1902
  • 10. 10 Result For Shallow Design 1 My design of 34 X 34 X 5 m footing settles for 29 mm and from Plaxis the value is 29.1 mm Shallow design 2 Shallow foundation option resting on improved soil (using the soil mixing technique) between depths5.0 and 25.0 m below grade. In this option, the cement‐soil mixing technique with result in minimum undrained shear strength of the improved soil, Su = 100 kPa. The soil improvement technique will also reduce the compression ratio by at least 50%, i.e., CR improved soil = CR native soil/2 Capacity Calculation
  • 11. 11 D 5 B 24 L 24 B' 22.34557 L' 22.34557 x 1 m 1.5 Nq 1 Nc 5.14 DL 8820 LL 16280 V(DL+LL) 25100 V(concrete) 69120 V(given+Conc) 94220 H 15588 M 77940 e 0.827213 ϒ 19 D 5 sq 1 dq 1.416667 iq 1 bq 1 gq 1 cu 100 sc 1.194553 dc 1.083333 ic 0.908896 bc 1 gc 1
  • 12. 12 q(ult) for DL+LL 799.75 FOS 3 q(allow) 266.5833 q(max)Give n Vertical load 163.5764 q(allow) >q(max) q(ult) for seismic 739.1509 FOS2.5 q(allow) 295.6604 q(max)Give n Seismic lateral Load 129.9 q(allow) >q(max) Settlement Calculation cs 0.95 q 43.57639 B 24 v 0.5 Eu 52794.2 Si 0.014114 Sc 0.015416 Settlement 0.02953 29 mm Depth E eo CR RR OCR Cr Cc ϒ ϒ' h B+Δz σ'vo Δσ' σ'p log((σ'vo+Δσ')/σ'vo) Sc 5 15.037 0.8 0.06 0.015 4.3 0.027 0.108 18.2 8.4 5 26.5 21 35.74225703 90.3 0.431687312 0.017986971 10 45.4894 0.7 0.0475 0.0175 2.9 0.02975 0.08075 19 9.2 5 31.5 65 25.29604434 188.5 0.142755369 0.007347703 15 54.1518 1 0.07 0.01 2.9 0.02 0.14 19 9.2 5 36.5 111 18.84030775 321.9 0.068086557 0.001702164 20 44.5374 1.6 0.1 0.015 1.2 0.039 0.26 17.8 8 5 41.5 154 14.57395848 184.8 0.039269764 0.001132782 25 39.6958 0.6 0.05 0.0125 2.5 0.02 0.08 17.4 7.6 5 46.5 193 11.60827841 482.5 0.025365892 0.000990855 30 57.8954 0.7 0.045 0.012 2.5 0.0204 0.0765 19.5 9.7 5 51.5 236.25 9.463662928 590.625 0.017057489 0.000602029 35 66.973 0.7 0.0425 0.012 2.5 0.0204 0.07225 19.5 9.7 5 56.5 284.75 7.862792701 711.875 0.011829576 0.000417514 40 69.3864 0.6 0.04 0.011 1.3 0.0176 0.064 19.5 9.7 5 61.5 333.25 6.636261485 433.225 0.008563452 0.000294369 45 45.6996 0.7 0.04 0.0115 1.3 0.01955 0.068 19.5 9.7 5 66.5 381.75 5.675843745 496.275 0.006409542 0.000216793 50 70.6802 0.7 0.055 0.0055 1.3 0.00935 0.0935 19.5 9.7 5 71.5 430.25 4.909775539 559.325 0.004927865 7.97155E-05 55 71.1902 0.6 0.06 0.005 1.3 0.008 0.096 19.5 9.7 5 76.5 478.75 4.288948695 622.375 0.003873363 6.05213E-05 Total Sc 0.015415709
  • 13. 13 Plaxis Analysis Data Used Depth ϒ Cu E 5 18.2 100 15.037 10 19 100 45.4894 15 19 100 54.1518 20 17.8 100 44.5374 25 17.4 100 39.6958 30 19.5 150 57.8954 35 19.5 175 66.973 40 19.5 175 69.3864 45 19.5 175 45.6996 50 19.5 175 70.6802 55 19.5 175 71.1902
  • 14. 14 Result For Shallow Design 1 My design of 24 X 24 X 5 m footing settles for 29 mm and from Plaxis the value is 28 mm
  • 15. 15 Deep Design Capacity Calculation and Pile parameters Depth Cu Δz α Qs 2 15 2 1 141.372 7 55 5 0.9 1166.319 12 70 5 0.3 494.802 16 90 4 0.9 1526.818 21 50 5 0.25 294.525 27 100 6 0.25 706.86 32 150 5 0.25 883.575 40 175 8 0.3 1979.208 45 175 5 0.3 1237.005 50 175 5 0.3 1237.005 55 175 5 0.3 1237.005 V 25100 FS 3 Qu group 75300 G 0.7 n 23.90295 25 pcs Qgroup (design) 26252 Qu (design) 78755.99 L 25 d 0.6 Le 25 Ab 0.282744 Nc 6 Cub 100 Circumfurence 4.7124 Qb 169.6464 Qs 4330.696 Qult 4500.342 Qsingle 1500.114
  • 16. 16 Result For Given Calculation my Engineering calculation and recommends to have 25 pieces of 25 meter concretes bored piles of .6m diameter Single Pile Settlement Calculation L 25 d 0.6 Cs 0.058884 Cb 0.03 fb 2119 Qb 296.8812 Qs 4330.696 FOS 3 cub 175 Nc 9 σvb 544 Qba 98.9604 Qsa 1443.565 αs 0.67 Ap 0.282744 Ep 30000000
  • 17. 17 Sss 0.001605 Ssb 0.001335 Sp 0.003142 Ssingle 0.006082 6 mm Group Pile Settlement Calculation dc 4.4 L 25 n 25 Ap 0.2827 Ep 30000000 b' 9 l' 9 Es 198911.4 Qa 1004 Eeq 3319196 S 0.0300295 30 mm
  • 18. 18 n 25 w 0.5 Rs 5 SG 0.03041 30 mm Lateral Capacity Calculation Solving this two equation we get a quadric equation and from there I got my Pile capacity of 451.39 Kpa for single Pile and 11284.7kpa for group Pile. My Myeild was greater than Mmax so I used Long pile fixed head formula, though I have a short pile . I 0.00636 S 0.021 fy 30000 fr 0.6 M yield 378
  • 19. 19 P 293.112 x f f 1.54 P 451.39 PG 11284.75 Lateral Deflection Calculation yg = HfyF H 11364 L 25 d 0.6 fy 30000000 Ep 24647515.09 Es 1989114 K 12.39120286 fyh 6.92424E-07 fθH 9.89827E-07 fθM 3.40959E-06 fyF 4.0507E-07 yg 0.004603 4.6 mm
  • 20. 20 8. Results of All Design Criteria 1. Shallow Foundation Type 1 Design 34m X 34m X 5m concrete square footing. Capacity vertical load q allowable =199.1757 kpa q max =141.71 kpa Capacity for seismic load q allowable = 217.4114224 kpa q max = 173.5764706 kpa Settlement 29 mm 2. Shallow Foundation Type 2 Design 24m X 24m X 5m concrete square footing. Capacity for vertical load q allowable = 266.5833333 kpa q max = 163.5763889 kpa Capacity for seismic load q allowable = 295.660371 kpa q max = 129.9 kpa Settlement 29mm
  • 21. 21 3. Deep Foundation Type 1 Design: 25 meter deep, 0.6 meter diameter 25 pcs of concrete pile bored in a distance of 1.8 meter Capacity q single = 1542.5256 kpa q Group = 26994.198 kpa Settlement Ssingle =6 mm Sgroup =30 mm Lateral Capacity q single = 451.39 kpa q group = 11284.75 kpa Lateral Deflection 4.6 mm 9. Recommended Design for Client The transfer of loads from deep foundations to the soil is different from that of shallow foundations. Shallow foundations primarily transfer the load to the soil via bearing pressure. Deep foundations also transfer the load via friction along the length (or depth) of the foundation, called skin friction. The force that remains at the bottom of the deep foundation is transferred to the soil by bearing pressure. Shallow foundations, often called footings, are usually embedded about few meters into soil ( in this case 5 meters) One common type is the spread footing which consists of strips or pads of concrete (or other materials) which extend below the frost line and transfer the weight from walls and columns to the soil or bedrock. Another common type of shallow foundation is the slab-on- grade foundation where the weight of the building is transferred to the soil through a concrete slab placed at the surface. Slab-on-grade foundations can be reinforced mat slabs, which range from 30 cm to several meters thick, depending on the size of the building, or post-tensioned slabs, which are typically at least 20 cm for houses, and thicker for heavier structures. A deep foundation is used to transfer the load of a structure down through the upper weak layer of
  • 22. 22 topsoil to the stronger layer of subsoil below. There are different types of deep footings including impact driven piles, drilled shafts, caissons, helical piles, geo-piers and earth stabilized columns. The naming conventions for different types of footings vary between different engineers. Historically, piles were wood, later steel, reinforced concrete, and pre-tensioned concrete. In this case my engineering recommendation is Deep foundation Type 1.If I have a chance to install shallow foundation over a deep foundation I would definitely go for that always because deep foundations are complicated to install and it is expensive than shallow foundation. In my design I have 25 piles means I have to make 25 bore hole and I have to bore those until 25 meters of depth with 1.8 meters of spacing, so for avoiding complicated design and cost I would prefer Shallow foundation Now I have 2 options for shallow foundation. One is in improved soil and my designed footing is 24 X 24 X 5 which is much lesser than the designed footing of 34 X 34 X 5 in natural soil. So volume of concrete is more in shallow foundation design 1 but I would still go for design 1 because improving soil up to 25 meters would be so costly and the installation procedure would take much time because I have to excavate soil up to a fair amount of depth of 25 meters. So counting time and money as well design complicacy I would recommend my client to go for Shallow foundation design type 1.
  • 29. 29 Graph 4 11. References 1. Lecture Notes of M. Hesham El Naggar, Ph.D., P. Eng., MASCE, FEIC,Professor and Research Director,Geotechnical Research Centre 2. soilseries.sc.egov.usda.gov/OSD_Docs/C/COLUMBIA.html
  • 30. 30 3. http://en.wikipedia.org/wiki/Deep_foundation 4. Simplified Design of Building Foundations, 2nd Edition by James Ambrose (Author) 5. Building Foundations of Scientific Understanding: A Science Curriculum for K-2 by Bernard J. Nebel (Author) 6. Foundation Engineering P. C. VARGHESE 7. Foundation Engineering Handbook by Robert Day McGraw Hill Professional, Dec 12, 2005