STANDARD TOR FOR
BUILDING AND
CONSTRUCTION PROJECT
LAND ENVIROMENT
• Land use examination as per master plan
• Land use within around 10 km radius of the project site
• Satellite imagery shall be used for the study
• Check on flood plain of any river
• Details of Environmentally Sensitive Places, Land Acquisition Status,
Rahabilitation
LAND ENVIRONMENT
• Contour Plan with Slope
• Drainage pattern of the site and surrounding area
• Any obstruction by the proposed project on the above
• Present land use and permission required for any conversion such as forest or
agricultural land
BASELINE MONITORING
• Land
• Ground Water
• Surface Water
• Air
• Biodiversity
• Noise and Vibration
• Socio Economic and Health
BIODIVERSITY
• Details of the existing number of trees in the core area
• Type of trees in the buffer area
• Number of trees will be felled for the project
CORPORATE ENVIRONMENTAL
RESPONSIBILITY
• Role and responsibility of the developer
• Environmental
• Social
WATER ENVIRONMENT
• Source of Water
• Water Requirement
• Wastewater Treatment and Reuse
• Water Balance for the project
• Rain Water Harvesting
• Soil Characteristic and depth of ground water for Harvesting
SOLID WASTE MANAGMENT
• Quantification of Solid Waste
• Source of Generation
• Method of Treatment and Disposal of Solid Waste
ENERGY CONSERVATION
• Use of solar energy or alternate source of energy
• Other energy conservation measures as ECBC guidelines
AIR ENVIRONMENT
• Emission monitoring from DG Set during construction and operation phase
TRAFFIC
• Road rail connectivity to the project
• Impact on present traffic due to this project
• Detailed traffic and transportation study for existing and project scenario
• Transport of material for construction
ENVIRONMENTAL MANAGEMENT AND
MONITORING PLAN FOR CONSTRUCTION AND
OPERATION PHASE
• Details of EMP implementation and activity
DISASTER MANAGEMENT PLAN
• Disaster Management Plan and emergency evacuation during
• Natural
• Man made
DETAILS OF LITIGATION PENDING AGAINST
THE PROJECT
• Direction or order of the court.
EMP COST OF THE PROJECT
• Capital
• Recurring

Standard TOR for Building and Construction Project.pptx

  • 1.
    STANDARD TOR FOR BUILDINGAND CONSTRUCTION PROJECT
  • 2.
    LAND ENVIROMENT • Landuse examination as per master plan • Land use within around 10 km radius of the project site • Satellite imagery shall be used for the study • Check on flood plain of any river • Details of Environmentally Sensitive Places, Land Acquisition Status, Rahabilitation
  • 3.
    LAND ENVIRONMENT • ContourPlan with Slope • Drainage pattern of the site and surrounding area • Any obstruction by the proposed project on the above • Present land use and permission required for any conversion such as forest or agricultural land
  • 4.
    BASELINE MONITORING • Land •Ground Water • Surface Water • Air • Biodiversity • Noise and Vibration • Socio Economic and Health
  • 5.
    BIODIVERSITY • Details ofthe existing number of trees in the core area • Type of trees in the buffer area • Number of trees will be felled for the project
  • 6.
    CORPORATE ENVIRONMENTAL RESPONSIBILITY • Roleand responsibility of the developer • Environmental • Social
  • 7.
    WATER ENVIRONMENT • Sourceof Water • Water Requirement • Wastewater Treatment and Reuse • Water Balance for the project • Rain Water Harvesting • Soil Characteristic and depth of ground water for Harvesting
  • 8.
    SOLID WASTE MANAGMENT •Quantification of Solid Waste • Source of Generation • Method of Treatment and Disposal of Solid Waste
  • 9.
    ENERGY CONSERVATION • Useof solar energy or alternate source of energy • Other energy conservation measures as ECBC guidelines
  • 10.
    AIR ENVIRONMENT • Emissionmonitoring from DG Set during construction and operation phase
  • 11.
    TRAFFIC • Road railconnectivity to the project • Impact on present traffic due to this project • Detailed traffic and transportation study for existing and project scenario • Transport of material for construction
  • 12.
    ENVIRONMENTAL MANAGEMENT AND MONITORINGPLAN FOR CONSTRUCTION AND OPERATION PHASE • Details of EMP implementation and activity
  • 13.
    DISASTER MANAGEMENT PLAN •Disaster Management Plan and emergency evacuation during • Natural • Man made
  • 14.
    DETAILS OF LITIGATIONPENDING AGAINST THE PROJECT • Direction or order of the court.
  • 15.
    EMP COST OFTHE PROJECT • Capital • Recurring