Solving Power Crisis of Bangladesh by Utilizing Renewable
Energy
1,
Afshana Morshed, 2,
Farzad Hossain, 3,
Rifat Sultana Setu
1,2,3
Department of Mechanical Engineering, Military Institute of Science and Technology, Dhaka, Bangladesh
-------------------------------------------------ABSTRACT---------------------------------------------------------
Bangladesh is a developing country and crisis of power is one of the acute quandaries in any developing
country like Bangladesh. Power is the most paramount factor and the demand of power is incrementing rapidly
in the country. There are several reasons behind the power failure like lack of commitment of ascendancy,
system loss, circumscription of resources, high demand, corruption in potency, low generation capacity etc. To
overcome the problem of power crisis, renewable energy can be a great source. Bangladesh has huge untapped
renewable energy resources which can be utilized to solve and aid the power crisis. In this paper we described
about different forms of renewable energy that can be acclimated to meet the power demand by proper
utilization at low cost and less risk. We also discussed about several sectors of renewable energy sources such
as solar energy, wind energy, tidal energy, bio energy, hydro power, geothermal, ocean wave energy and
energy from Bay-of-Bengal. Skilled manpower and new technology are required for taking initiative steps for
power sectors utilizing renewable energy.
KEYWORDS: Power crisis, Paramount factor, Lack of commitment, Renewable energy, Implementation.
---------------------------------------------------------------------------------------------------------------------------------------
Date of Submission: Date, 06 June 2018 Date of Publication: 11 June 2018
---------------------------------------------------------------------------------------------------------------------------------------
I. INTRODUCTION
Power is the key and main requisite for running different sectors like agricultural, industrial, conveyance and
the sectors which we face in our circadian activities. Electricity is the main source of energy. In the modern age,
the world’s whole development and most of the economical activities depend on the electric power. People of
the whole world cannot cerebrate a moment without electric power. Day by day the authoritative ordinance of
electric power and energy is incremented but the engenderment and source of electric power are circumscribed.
The main reason of this lack of electric power is due to the energy crisis throughout the world. The term energy
crisis is any significant bottleneck in the supply of energy resources to an economy [1]. However, it often refers
to one of the energy sources utilized at a particular time and place that can supply national electricity grid. Like
other developing countries, Bangladesh is also an energy hungry country. The energy crisis is one of the major
quandaries for people and economical activities of this country. Power infrastructure of Bangladesh remains
same but the demand is rapidly incrementing. The per capita power consumption in Bangladesh is about
407KWH [2], which is one of the lowest in the world but for huge population density our power section is
under enormous pressure.
In Bangladesh at 2016, the total number of consumers connected to the grid is 21.8 million of the population [3]
and the access to electricity is 76% of total population until June, 2016 [3]. So, 24% of the population still does
not have direct access to electricity and those who get the electricity are additionally suffering astronomically
immense for load shedding. In order to achieve the growth rate; availability of a reasonably priced and reliable
source of electricity is a prerequisite [3]. The present condition of electricity cannot meet consumers growing
demand. So, it is not possible to fulfill constant supply of electric power to all consumers throughout the
country. Gradually the demand for electric power is increasing rapidly, so it is compulsory to take salutary steps
to solve this power crisis. It is necessary to increase production of electricity and we need to concentrate on
utilizing renewable energy like solar, wind, geothermal, tidal energy etc to produce adequate amount of
electricity. The International Renewable Energy Agency (IRENA) ranked Bangladesh as the sixth largest
renewable energy related work force in the world with 114,000 jobs in 2013 [4]. So, Bangladesh has enough
possibility to utilize this renewable energy satisfactorily for installing sufficient electric power and setting
power stations.
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 21
II. PRESENT SITUATION OF POWER SECTOR IN BANGLADESH
To solve the power crisis at first, it is necessary to focus on the present situation of Bangladesh power sector
and production capacity. Bangladesh government electric sectors management control structure at a glance [3]:
Figure 1: Present Structure of Power Sector
Table 1 shows the manufacturing condition of Bangladesh at 2016 and 2017 [5].
Table 1: Manufacturing condition of Bangladesh at 2016 and 2017
Subject Unit 2016 2017
Production capability MW 14,565 15,755
Grid Sub-station Power MVA 26,690 30,993
Number of village with
electricity
Number 58,500 66,900
Production from renewable
sources
MW 202 216
Allotment for annual
development program
Crore 16,217 22,885
System loss Percentage 13.10% 12.19%
From table 1, it is clear that with the increasing of manufacturing, system loss has been decreased to 12.19% in
the year 2017. Moreover, within a year, we can see increment in the production capability, grid sub-station
power, production from renewable sources, number of village with electricity, and allotment for annual
development program.
Table 2 and 3 shows present installed generation capacity (MW) in public and private sectors respectively as on
January 5, 2018 [6]
Table 2: Present Installed Generation Capacity (MW) in public sectors as on June 5, 2018
Public Sector Installed Generation Capacity (MW)
BPDB 5266
APSCL 1444
EGCB 839
NWPGCL 1070
RPCL 77
BPDB-RPCL JV 149
Subtotal 8845 (57%)
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 22
Table 3: Present Installed Generation Capacity (MW) in private sectors as on June 5, 2018
Private Sector Installed Generation Capacity (MW)
IPPs 3953
SIPPs (BPDB) 99
SIPPs (REB) 251
15 YR. Rental 169
3/5 YR. Rental 1576
Power Import 660
Subtotal 6708 (43%)
From the table 2 and 3, it is seen that total amount of 15,553 has been generated from the public and private
sectors as on June 5, 2018.
If we include captive power then the power installed capacity becomes (15,553 + 2800 = 18,353 MW).
Installed Capacity as on May, 2018 (By Plant Type) is shown in the pie chart (Fig. 2) and installed capacity as
on May, 2018 (By Fuel Type) is shown in another pie chart (Fig. 3).
Figure 2: Installed Capacity as on May, 2018
(By Plant Type)
Figure 3: Installed Capacity as on May, 2018
(By Fuel Type)
37%
33%
9%
15%
2% 4%
Installed Capacity as on May, 2018
(By Plant Type)
Combined Cycle
Reciprocating Engine
Gas Turbine
Steam Turbine
Hydro
Others
62%
21%
8%
3% 2% 4%
Installed Capacity as on May, 2018
(By Fuel Type)
Natural Gas
Furnace Oil
Diesel
Coal
Hydro
Others
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 23
The figures 2 and 3 show the total installed generation capacity of Bangladesh on May, 2018. The percentage of
Natural gas, Furnace oil, Coal, Diesel, Hydro, Steam turbine, Gas turbine, Combined cycle, Reciprocating
engine of the year 2018 is represented in the pie charts.
Different type of power stations can be seen in Bangladesh. Maximum power stations of Bangladesh use natural
gas as their fuel. They are summarized below in a tabular form [7].
Table 4: Types of Power Station in Bangladesh
Type of Power Station Power Station Capacity Fuel Type
Coal fired Barapukuria 250 Coal
Oil and Gas fired Thermal Ashuganj 638 Oil & natural gas
Oil and Gas fired Thermal Ghorashal 950 Oil & natural gas
Oil and Gas fired Thermal Siddhirganj 260 Natural gas
Oil and Gas fired Thermal Shikalbaha 60 Natural gas
Gas turbines Haripur 360 Natural gas
Gas turbines Ashuganj 146 Natural gas
Gas turbines Raozan 240 Natural gas
Gas turbines Gopalganj 100 Natural gas
Gas turbines Meghnaghat 450 Natural gas
Gas turbines Golpara Barge 56 Natural gas
Gas engines Gazipur 53 Natural gas
Gas engines Siddhirganj 240 Natural gas
Gas engines Mymensingh 216 Natural gas
Gas engines Maona 35 Natural gas
Gas engines Fenchuganj 51 Natural gas
Gas engines Dhaka 7 Natural gas
Gas engines Ghorasal Regent 108 Natural gas
Gas engines Baghabari 50 Natural gas
Hydroelectric Karnafuli 230 Hydroelectricity
III. RENEWABLE ENERGY AND ITS TYPES
Renewable energy is a kind of energy which can be obtained from innate processes and can be replenished
constantly. Solar, wind, wave, hydro-power, geothermal, biomass etc. are considered renewable sources of
energy which are environmentally safe and naturally replenished.
Solar Energy: The amount of solar energy which is incident on the earth every year is identically equivalent to
160 times the energy stores in the world’s proven reserves of fossil fuels and equipollent to more than 15000
times the world’s annual utilization of fossil & nuclear fuels and hydro power [8]. However, among the total
solar incoming radiation: 30% is reflected back to space, 47% is utilized to warm the earth’s surface and 23% is
absorbed by evaporation of water [8]. Moreover, relatively small portions are habituated to drive the winds &
waves and are absorbed by plants in photosynthesis [8].
Wind Energy: Wind energy has the facility to engender adequate amount of electricity without engendering
any environmental quandaries. Sundry amounts of wind turbines are utilized all over the world for electricity
engendering and water pumping purposes. Since the wind will perpetuate to be utilized for this purport, it is the
utilization of wind energy as a pollution-free designates of engendering electricity on a potentially paramount
scale that has the ability to magnetize most current interest.
Wave Energy: A variety of designs for contrivances for extracting energy from waves has been proposed [9].
Experimental versions of several have already been tried, but the technology has not yet reached the
commercial stage [9]. Several countries, including the UK have a paramount potential for utilizing wave energy
[9].
Hydro-power: Hydro electricity is well established as one of the principle energy engendering technologies
around the world providing 20 percent of the world’s electricity and in the developing countries, the proportion
rises to around forty percent [9]. However, the capacity of the large hydroelectric schemes can be several times
that of a usual power station and they are highly reliable, efficient and durable [9]. Moreover, the dams and
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 24
lakes of large schemes also have environmental and gregarious impacts. There are additionally numerous
devices for extracting energy from small and medium sized rivers and streams, with and without dams.
Geothermal Energy: The interior of the earth is very much warmer than its surface, with estimated
temperatures of several thousand degrees Celsius [9]. There are various places where the hot rock is very near
or genuinely on the earth’s surface and heats water in underground aquifers [9]. However, hot water or steam
has been provided by such places for centuries [9]. Moreover, many countries are utilizing geothermal steam
because of electricity engendering and water heating purposes.
Biomass: Biomass plant is one of the major world fuel resources especially in the third world where it provides
forty percent of requisites [9]. It is also important in some of the forest-rich parts of the industrial nations (14%
in Canada, 8% in Sweden) [9]. Though wood is the essential fuel, but animal dung and straw are widely
utilized. Wood fuel can be called a renewable resource if its consuming rate is no more dominant than renewing
rate. Moreover, Gas and liquid fuels can additionally be found from biological sources.
IV. SOLVING POWER CRISIS USING RENEWABLE ENERGY
Solar Energy: The most important renewable energy is solar energy. Utilizing solar energy can solve most of
the power crisis by producing electricity. Already solar energy is being used in different places of Bangladesh.
But the usage is not widely done in Bangladesh. Most of the countries in the world utilize solar energy to solve
their power demand. By following and applying their technologies and processes, Bangladesh can also utilize
renewable energy to solve power crisis problem through different power plants for producing electricity. There
are some methods of converting photons into electricity.
Solar Dynamic (SD) Technology: Solar dynamic utilizes a heat engine to drive a turbine or a piston which
connects to a generator [10].
Photovoltaic (PV) Technology: Photovoltaic uses semiconductor cells to directly convert sunlight photons into
voltage via a quantum mechanical mechanism [10]. They are not subjected to the thermodynamic
circumscriptions of thermal engines such as those utilized in 50 accumulation system. Already Bangladesh is
utilizing this technology in rural areas and Saint Martin Island. It is additionally utilized on road to run the road
lights. However, if we utilize it in all road lights of Bangladesh, we can preserve some power for household and
industrial needs.
Concentrating Photovoltaic Technology: It is possible to utilize the concentrating photovoltaic system. It is
like solar dynamic which is a form of subsisting terrestrial concentrating. Solar energy approaches which
converts concentrated light into electricity by photovoltaic. To solve power crisis in sea side like Saint Martin
island or Cox’s bazaar, Bangladesh can follow the solar oases produce renewable energy by utilizing alternative
energy sources and desalinated brine for supplying the population in arid regions with aliment, energy, water
and to establish fundamentals for development.
Biomass: Another paramount and subsidiary renewable energy is biomass. The biomass utilized for electricity
engenderment ranges by region forest by products, such as wood residues are popular in the United States [11].
Agriculture waste is prevalent in Southeast Asia (rice husks) and Mauritius (sugar cane residue) [11]. Animal
husbandry residues such as, poultry litter is popular in the UK [11]. In Brazil, sugar or ethanol plants engender
electricity in need from and residuals from sugar cane are left over by the milling process and it sells the surplus
electricity to the public grid [12].The sucrose accounts for minor more than 30% is the chemical energy stored
in the matured plant, 35% is in the leaves and stem tips, which are left in the fields during harvest, and 35% are
in the fibrous material left over from pressing [13].The production process of sugar and ethanol in Brazil
thoroughly capitalizes on the energy stored in sugar cane and they engender 600 MW of current for self-use and
100 MW for sale [14]. In Bangladesh, there is one sugar mill present. If government wants, a sugar and ethanol
power plant can be placed as like Brazil, to engender electricity by utilizing the sugar cane residue to solve the
power crisis around the mill.
Wind Energy: Wind power is a great source of renewable energy which can convert the kinetic energy of wind
to engender electricity or mechanical power. This is done by utilizing a huge wind turbine usually consisting of
propellers which is connected to an engenderer to produce electricity. Though it is not widely utilized in
Bangladesh, many countries have already utilized it in a large scale. Many developed countries have already
installed a lot of large and small wind turbines and can be able to solve their power crisis. Small wind turbines
are concretely agreed for self-sufficient power generation or local electricity producing in off-grid areas [15].
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 25
Moreover, small wind turbines require a maximum rotor area of 200 m², which is equal to a maximum nominal
power of 50 kW for an electrical voltage of below 1500 V DC or 1000 V AC [15]. Onshore wind turbines are
also utilized in the developing countries which require low investment cost. Moreover, electricity engenderment
can be possible with less investment and less transmission losses. On the other hand, offshore wind turbines are
utilized in the developed countries in order to replace conventional power stations in the long term due to higher
wind speeds at sea and can be possible to utilize 100% of the energy. However, wind energy can be one of the
effective solutions to solve power crisis of Bangladesh. Small Wind Turbine (SWT) is considered the most
opportune option for Bangladesh to solve power crisis which can be conveyed and installed with minimum land
and infrastructure requisite. Moreover, wind turbines may be established in the coastal and higher altitude areas
which can be very much subsidiary for engendering of electricity in the coastal region of Bangladesh. So,
Bangladesh Government and other private organizations must be conscientious of establishing more wind
power plants in order to solve the power crisis.
Hydro-electricity: Engendering electricity by utilizing hydropower is known as hydroelectricity which is very
much effective for solving power crisis. Many countries of the world have already utilized it in a huge amount.
At the end of 2015, the leading hydropower engendering countries were Canada, the US, Brazil, Russia, China
and India. However, three types of hydropower stations can be found in the world: ‘pumped storage’, where
stored water is recycled by pumping it back up to a higher reservoir in order to be relinquished again;
‘reservoir’, where power is engendered through the relinquishment of stored water; ‘run of river’, where the
electricity is engendered through the flow of a river’ [16]. At present, Bangladesh has only hydro power station
at Kaptai. Although, the scope of engendering hydropower is very limited in Bangladesh due to its plain lands
except in some hilly region in the southeast & northeast parts of the country, but there are lot of canals, branch
of major river like Shangu, Karnafuli, Matamuhuri as well as small waterfalls which have good potentials for
establishing micro and mini hydropower unit in Chittagong Hill Tracts (CHT) region [17]. Bangladesh Regime
and other private organizations must be conscientious of establishing hydro power plants in order to solve the
power crisis.
Geothermal Energy: Geothermal energy is the renewable energy source which has the ability to solve power
crisis. Developed countries have already established enough geo- thermal power plants in order to engender
electricity. Three types of geothermal power plants are generally found in these countries, such as flash steam,
dry steam and binary cycle [18]. Flash steam power plant can move high-pressure geothermal water into low-
pressure tanks for engendering a flash of steam to spin a turbine and after the utilizing of the steam, it is cooled
and condensed back into the water and finally injected back down to the reservoir [18]. The dry steam power
plant can directly utilize steam in order to spin a turbine and can throw up the hazardous substances into the
atmosphere. Since these systems utilize a very small amount of water, hence the denomination 'dry' [18]. Dry
steam plants can be found in USA, Italy. On the other hand, binary cycle plant utilizes geothermal water in
order to heat a secondary fluid that spins a turbine and the plant relies on the cycling of two fluids - the hot
water and a secondary fluid [18]. The northern parts of Bangladesh can be very much efficacious for
establishing geothermal power plants. However, the essentiality of electricity is incrementing in the country, but
our engendering of electricity is not incrementing. So, there is a huge necessity of electricity in the rural area
which can be covered by the engendering of electricity through geothermal energy.
Wave Energy: Wave energy is engendered straight away from the ocean waves. It is another special kind of
renewable energy which is utilized in many places of the world in order to decrement the harmful emissions of
greenhouse gasses associated with the power engendering purport. It can be a huge source of electricity for
Bangladesh. The Oscillating Water Column method is technically feasible and becoming economically
impressive for this purport [19]. This type of wave energy harnessing technique is being accepted by several
countries such as Ireland (3.5 MW), the United Kingdom (500 kW), India (150 kW), Norway (100 kW) etc.
[20]. Bangladesh has the ability for harnessing ocean wave energy from the BAY OF BENGAL [20]. So, the
Government must take compulsory steps in an early possible time in order to harness ocean energy which can
be a great solution to our power crisis.
By utilizing renewable energy, Bangladesh can solve power crisis. Taking some steps like all the industries that
run by electric power can utilize solar energy to engender electricity for running lights and fans of their
industries by setting short or large solar plants and by doing this, they can preserve some power from the
national grid. The industries that situated in village side can also set biogas plant to run lights and fans of their
industries. In the big city of Bangladesh, the owners of the big building can set solar energy collectors on their
building's roof and by this collector if they run only one light or fan of every floor then they can preserve a good
part of electricity from national grid and our regime can utilize that electricity in other sectors. On the other
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 26
hand, farmers of Bangladesh can set biogas or solar plant for their irrigation system because at summer season
Bangladesh regime can't supply total farmer's requisite electricity to run their pump for irrigation and so they
face load shedding. Even Bangladesh can utilize other renewable energy like wind, wave, hydroelectricity and
geothermal energy to engender electricity that described above. As some renewable energy used plants are very
costly, so Bangladesh regime can set more and more solar, biogas or other renewable energy used plant or can
help general and village people financially to set this type of plants. However, good news is that Bangladesh
regime has taken action to set renewable energy used power plants to solve power crisis and that will start very
soon.
V. FUTURE OBJECTIVES
The Power Station Master Plan 2016, sponsored by Japan International Corporation Agency, aims at assisting
Bangladesh in formulating an extensive energy and power development plan up to the year 2041, covering
energy balance, power balance [21].
Bangladesh has an aspiration to become a high-income country by 2041. The new Power Station Master Plan
study covers all the aforementioned challenges comprehensively and come up with feasible proposals and
action plans for Bangladesh to implement [21].
5.1 Vision 2041
Power system master plan 2016 [21]
5.1.1 Value-up Plan 1
Robust infrastructure for Primary Energy Import
5.1.2 Value-up Plan 2
Domestic Energy Resource Development and Efficient Use
5.1.3 Value-up Plan 3
High Quality and Robust Power System Development
5.1.4 Value-up Plan 4
Advanced Development of Green Energy
5.1.5 Value-up Plan 5
Policy and Human Capital Development for Stable Energy Supply
5.2 Aim
Aims of these value-up plans in Bangladesh following the achievements of High-Income Country are given
below:
5.2.1 Value-up Plan 1 & Value-up Plan 2
Primary Energy Demand: Energy intensity [3.42~2.56 toe/million BDT]
Gas/LNG: Domestic gas [2,500~2,000 mmcfd incl.YTF] Imported LNG [0~4,000 mmcfd]
Coal: Domestic coal [0.7~11 million tons/year] Imported coal [0~60 million tons/year]
Oil: Imported oil [5~30 million tons/year]
5.2.2 Value-up Plan 3
Power Generation: Complete phase-out of rental power [3,000 MW~0 MW]
Electricity for all [250~1,500 kWh/person/year]
Power Quality: No power shortage [500 MW~0MW]
Fluctuation of world top quality [±1.5 Hz~±0.2 Hz]
Operations and Maintenance: High thermal efficiency [30%~50%]
Power Import/Nuclear Power: Import [500~9,000 MW]/Nuclear [0~7,200 MW]
5.2.3 Value-up Plan 4
Renewable Energy: Maximizing RE generation potential under limited land
Bio-gas [4~62 mmcfd]
5.2.4 Value-up Plan 5
Energy Tariff Policy: No gap between tariff and supply costs
[Power: 2.6%/year until 2031 and 1.5%/year afterwards]
[Gas: 10-20%/year increase until 2031 and 1.5% year afterwards]
Human Capital Development: Training centers
Internationally recognized qualifications Professional engineers
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 27
Short-term and medium-term power development plans are to be formulated after verifying the appropriateness
of matters with a little short-term uncertainty in the formulation of a long-term power development plan. The
optimum power source composition is to be determined in the preparation of the future vision of the power
source composition by conducting a quantitative evaluation of the economic, environmental and energy security
values of scenarios with different composition ratios for the gas and coal power generation. Power plants with a
total output capacity of approximately 14,000 MW are to be constructed in the next ten years. The current status
of each thermal power development plan was confirmed based on the discussion with related companies, such
as BPDB, BIFPCL, CPGCBL, NWPGCL, Orion Group, etc. Guarantee of the long-term stability of the fuel
supply is a very important factor in the formulation of a power development plan. The existence of a port
infrastructure required for the importing of fuels including gas and coal during operation has to be a
precondition for the decision on the CODs of new power plants. Bangladesh is in a good position to utilize the
sufficient regional renewable energy potential and import it through the cross-border transmission network.
Targets that Bangladesh wants to achieve by 2041 [21]:
1. Domestic renewable energy power generation: 2,470MW (by 2021), and 3,864MW (by 2041).
2. Domestic biogas production: 790,000m3
/day, including additional 600,000m3
/day by 2031, 3 millions
m3
/day.
3. Cross-border energy import rules and regulations’ set-up, associated with capacity building.
4. Cross-border Energy Imports: 3,500~8,500MW (by 2031), 9,000MW (by 2041).
VI. CONCLUSION
Electricity is one of the blessings which science has given to us. Since, it has already become a component of
our daily life, so we cannot even imagine a single day without electricity. But the problem is that power crisis
has become a major issue in Bangladesh. Immediate steps must be taken otherwise it can go beyond control.
Renewable energy can play a vital role in solving the disgusting power crisis of Bangladesh. However, it is the
proper time to look forward and make necessary plans for utilizing renewable energy to engender electricity in
lieu of avoiding dependence on the conventional method. Biomass based power plant has the ability to create
electricity at a low cost. So, the country can establish it to meet the future power demand. Since Bangladesh has
a plenty of rivers and has the facility to utilize the energy of Bay of Bengal, small power plants should be
established utilizing wave and hydro energy. Moreover, wind power plants must be established in the coastal
areas, like Sandip. Since solar energy is very powerful & efficacious, Bangladesh can additionally utilize it.
Moreover, the Government and various organizations must come forward to establish renewable energy based
power plants in order to solve this disturbing power crisis.
REFERENCES
[1] Energy crisis, Wikipedia [internet], Accessed: 28 February, 2018, Available from:
https://en.wikipedia.org/wiki/Energy_crisis.
[2] Govt. set up power stations, The Financial Express [internet], Accessed: 20 February, 2018, Available
from: http://www.thefinancialexpress-bd.com/2016/12/18/56675/Govt-set-up-81-power-stations-
generated-10,353-MW-in-8-yrs.
[3] Bangladesh Energy Situation, Energypedia [internet], Accessed: 30 March 2018, Available from:
https://energypedia.info/wiki/Bangladesh_Energy_Situation.
[4] Green energy creates 1.14 lakh new jobs, The Daily Star [internet], Accessed: 31 March, 2018,
Available from: http://www.thedailystar.net/green-energy-creates-1-14-lakh-new-jobs-24166.
[5] Annual Report, Power Division, Government of the People’s Republic of Bangladesh [internet],
Accessed: 09 June, 2018, Available from: http://powerdivision.portal.gov.bd/site/view/annual_reports.
[6] Key Statistics, Bangladesh Power Development Board [internet], Accessed: 10 June, 2018, Available
from: http://www.bpdb.gov.bd/bpdb/index.php?option=com_content&view=article&id=5&Itemid=6.
[7] List of power stations in Bangladesh, Wikipedia [internet], Accessed: 29 March, 2018, Available from:
https://en.wikipedia.org/wiki/List_of_power_stations_in_Bangladesh,
[8] Arafat Ahmed Bhuiyan and A.K.M. Sadrul Islam, Performance and Social Aspect of LED based Solar
Home System: Bangladesh, World Renewable Energy Congress XI, Abu Dhabi, UAE, 25-30
September 2010.
[9] Renewable Energy Technology Course: Study Guide, The Division of Heat and Power Technology,
Department of Energy Technology, Royal Institute of Technology, Stockholm, Sweden, 2008.
[10] Goldenravi, Introduction, Scribd [internet], Accessed: 03 May, 2018, Available from:
https://www.scribd.com/document/93740018/Introduction,
Solving Power Crisis of Bangladesh by Utilizing...
www.ijmrem.com IJMREM Page 28
[11] Biomass Sources, Eisenhardt [internet], Accessed: 20 March, 2018, Available from:
http://www.eisenhardt-trading.com/productosindustriales/biomasa-english2.html.
[12] Bioenergy, Wikipedia [internet], Accessed: 04 April, 2018, Available from:
https://en.wikipedia.org/wiki/Bioenergy.
[13] Photosynthetic Efficiency - Efficiencies of Various Bio fuel Crops, LiquiSearch [internet], Accessed:
25 March, 2018, Available from:
http://www.liquisearch.com/photosynthetic_efficiency/efficiencies_of_various_biofuel_crops.
[14] BIO-ENERGY, Project Gutenberg Self-Publishing Press [internet], Accessed: 30 April, 2018,
Available from: http://www.gutenberg.us/articles/bio-energy.
[15] Energy supply with renewable – Made in Germany, Dena (German Energy Agency) [internet],
Accessed: 05 April, 2018, Available from: http://www.renewables-made-in-
germany.com/en/renewables-made-in-germany/technologies/wind-energy/wind-energy/technologies-
and-applications.html.
[16] Energy Resources, World Energy Council [internet], Accessed: 1 May, 2018, Available from:
https://www.worldenergy.org/data/resources/resource/hydropower/.
[17] M. A. Matin, H. Rahman, M. R. Hossain, M. A. Ehsan, G. M. I. Hossain and M. M. I. Mahfuj, Present
Scenario and Future Prospect of Renewable Energy in Bangladesh, 1st International Conference on
Physics for Sustainable Development & Technology (ICPSDT), Chittagong University of Engineering
& Technology (CUET), Chittagong - 4349, Bangladesh, 19-20 August 2015.
[18] Geothermal Energy: Advantages and Disadvantages, Study.com [internet], Accessed: 2 May, 2018,
Available from: http://study.com/academy/lesson/geothermal-and-tidal-energy-advantages-and-
disadvantages.html.
[19] Alimul Haque Khan, Kazi Rehnuma Zafreen & Mir Muntasir Hossain, A Review of Current
Renewable Energy Activities in Bangladesh, Scribd [internet], Accessed: 3 May, 2018, Available
from: https://www.scribd.com/document/333152777/A-Review-of-Current-Renewable-Energy-
Activities-in-Bangladesh.
[20] Khairul Anam, Husnain-Al-Bustam, Power Crisis & Its Solution through Renewable Energy in
Bangladesh, Cyber Journals: Multidisciplinary Journals in Science and Technology, Journal of
Selected Areas in Renewable and Sustainable Energy (JRSE), September Edition, 2011.
[21] Survey on Power System Master Plan 2016-Final Draft, Scribd [internet], Accessed: 16 February,
2018, Available from: https://www.scribd.com/document/332241567/Survey-on-Power-System-
Master-Plan-2016-Final-Draft.
Afshana Morshed Tithi, et al. “Solving Power Crisis of Bangladesh by Utilizing Renewable
Energy.” International Journal of Modern Research in Engineering & Management (IJMREM),
vol. 1, no. 6, 18 June 2018, pp. 20–28., www.ijmrem.com.

More Related Content

What's hot

Nuclear India Dr.Arunachalam (Barc)
Nuclear India Dr.Arunachalam (Barc)Nuclear India Dr.Arunachalam (Barc)
Nuclear India Dr.Arunachalam (Barc)falkor
 
IRJET-A Review of Renewable Energy Scenario in India
IRJET-A Review of Renewable Energy Scenario in IndiaIRJET-A Review of Renewable Energy Scenario in India
IRJET-A Review of Renewable Energy Scenario in IndiaIRJET Journal
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat
 
Renewable Energy & Alternative Technologies for Rural India
Renewable Energy & Alternative Technologies for Rural IndiaRenewable Energy & Alternative Technologies for Rural India
Renewable Energy & Alternative Technologies for Rural IndiaShantanu Basu
 

What's hot (20)

Renewable Energy Sector Report - April 2018
Renewable Energy Sector Report - April 2018Renewable Energy Sector Report - April 2018
Renewable Energy Sector Report - April 2018
 
Renewable Energy Sector Report May 2018
Renewable Energy Sector Report May 2018Renewable Energy Sector Report May 2018
Renewable Energy Sector Report May 2018
 
Renewable Energy SectorReport - July 2018
Renewable Energy SectorReport - July 2018Renewable Energy SectorReport - July 2018
Renewable Energy SectorReport - July 2018
 
Nuclear India Dr.Arunachalam (Barc)
Nuclear India Dr.Arunachalam (Barc)Nuclear India Dr.Arunachalam (Barc)
Nuclear India Dr.Arunachalam (Barc)
 
Power Sectore Report December 2016
Power Sectore Report December 2016Power Sectore Report December 2016
Power Sectore Report December 2016
 
Power Sector Report - March 2019
Power Sector Report - March 2019Power Sector Report - March 2019
Power Sector Report - March 2019
 
Power Sector Report February 2018
Power Sector Report February 2018Power Sector Report February 2018
Power Sector Report February 2018
 
Power Sectore Report November 2016
Power Sectore Report November 2016Power Sectore Report November 2016
Power Sectore Report November 2016
 
Power Ppt
Power PptPower Ppt
Power Ppt
 
Power Sector Report March 2018
Power Sector Report March 2018Power Sector Report March 2018
Power Sector Report March 2018
 
IRJET-A Review of Renewable Energy Scenario in India
IRJET-A Review of Renewable Energy Scenario in IndiaIRJET-A Review of Renewable Energy Scenario in India
IRJET-A Review of Renewable Energy Scenario in India
 
Renewable Energy Sector Report September 2017
Renewable Energy Sector Report September 2017Renewable Energy Sector Report September 2017
Renewable Energy Sector Report September 2017
 
Indian Energy Sector
Indian Energy SectorIndian Energy Sector
Indian Energy Sector
 
Power Sector Report - July 2018
Power Sector Report - July 2018Power Sector Report - July 2018
Power Sector Report - July 2018
 
Power Sectore Report - January 2017
Power Sectore Report - January 2017Power Sectore Report - January 2017
Power Sectore Report - January 2017
 
Power Sectore Report - December 2016
Power Sectore Report - December 2016Power Sectore Report - December 2016
Power Sectore Report - December 2016
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
 
Renewable Energy & Alternative Technologies for Rural India
Renewable Energy & Alternative Technologies for Rural IndiaRenewable Energy & Alternative Technologies for Rural India
Renewable Energy & Alternative Technologies for Rural India
 
Power Sector Report - October 2018
Power Sector Report - October 2018Power Sector Report - October 2018
Power Sector Report - October 2018
 
Power Sector Repor June 2018
Power Sector Repor June 2018Power Sector Repor June 2018
Power Sector Repor June 2018
 

Similar to Solving Power Crisis of Bangladesh by Utilizing Renewable Energy

Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...
Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...
Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...Farzad Hossain
 
Solving Power Crisis of Bangladesh by Utilizing Renewable Energy
Solving Power Crisis of Bangladesh by Utilizing Renewable EnergySolving Power Crisis of Bangladesh by Utilizing Renewable Energy
Solving Power Crisis of Bangladesh by Utilizing Renewable EnergyIJMREMJournal
 
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...IRJET Journal
 
The Global Survey of the Electrical Energy Distribution System: A Review
The Global Survey of the Electrical Energy Distribution System: A ReviewThe Global Survey of the Electrical Energy Distribution System: A Review
The Global Survey of the Electrical Energy Distribution System: A ReviewIJECEIAES
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpcLalitGoyal27
 
Wind energy integration in Africa: development, impacts and barriers
Wind energy integration in Africa: development, impacts and barriersWind energy integration in Africa: development, impacts and barriers
Wind energy integration in Africa: development, impacts and barriersIJECEIAES
 
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...Ajjay Kumar Gupta
 
Resources of Renewable Energy in India
Resources of Renewable Energy in IndiaResources of Renewable Energy in India
Resources of Renewable Energy in IndiaIJERA Editor
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET Journal
 
Development of renewable energy 55 59_62_71
Development of renewable energy 55 59_62_71Development of renewable energy 55 59_62_71
Development of renewable energy 55 59_62_71domsr
 
Feasibility Report of Small Hydroelectric Power Plant
Feasibility Report of Small Hydroelectric Power PlantFeasibility Report of Small Hydroelectric Power Plant
Feasibility Report of Small Hydroelectric Power PlantSulaman Muhammad
 
Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...
Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...
Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...Dr Nathaniel Babajide BTech, MSc, PhD, FHEA
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat
 
Report on Power Scenario in Arunachal Pradesh
Report on Power Scenario in Arunachal PradeshReport on Power Scenario in Arunachal Pradesh
Report on Power Scenario in Arunachal PradeshAnuradha Goswami
 
wind energy
wind energywind energy
wind energyShayan29
 
Energy Management through Bio-gas Based Electricity Generation System during ...
Energy Management through Bio-gas Based Electricity Generation System during ...Energy Management through Bio-gas Based Electricity Generation System during ...
Energy Management through Bio-gas Based Electricity Generation System during ...TELKOMNIKA JOURNAL
 
IRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in India
IRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in IndiaIRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in India
IRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in IndiaIRJET Journal
 

Similar to Solving Power Crisis of Bangladesh by Utilizing Renewable Energy (20)

Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...
Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...
Present Conventional & Non- Conventional Energy Scenario in Bangladesh and It...
 
Solving Power Crisis of Bangladesh by Utilizing Renewable Energy
Solving Power Crisis of Bangladesh by Utilizing Renewable EnergySolving Power Crisis of Bangladesh by Utilizing Renewable Energy
Solving Power Crisis of Bangladesh by Utilizing Renewable Energy
 
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
 
Prospect of renewable energy resources in Bangladesh
Prospect of renewable energy resources in BangladeshProspect of renewable energy resources in Bangladesh
Prospect of renewable energy resources in Bangladesh
 
The Global Survey of the Electrical Energy Distribution System: A Review
The Global Survey of the Electrical Energy Distribution System: A ReviewThe Global Survey of the Electrical Energy Distribution System: A Review
The Global Survey of the Electrical Energy Distribution System: A Review
 
H0371056061
H0371056061H0371056061
H0371056061
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpc
 
Wind energy integration in Africa: development, impacts and barriers
Wind energy integration in Africa: development, impacts and barriersWind energy integration in Africa: development, impacts and barriers
Wind energy integration in Africa: development, impacts and barriers
 
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
 
Resources of Renewable Energy in India
Resources of Renewable Energy in IndiaResources of Renewable Energy in India
Resources of Renewable Energy in India
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in India
 
Development of renewable energy 55 59_62_71
Development of renewable energy 55 59_62_71Development of renewable energy 55 59_62_71
Development of renewable energy 55 59_62_71
 
Feasibility Report of Small Hydroelectric Power Plant
Feasibility Report of Small Hydroelectric Power PlantFeasibility Report of Small Hydroelectric Power Plant
Feasibility Report of Small Hydroelectric Power Plant
 
Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...
Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...
Economic Feasibility of Integrating Renewable Energy in the Nigerian Power Ge...
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
 
Report on Power Scenario in Arunachal Pradesh
Report on Power Scenario in Arunachal PradeshReport on Power Scenario in Arunachal Pradesh
Report on Power Scenario in Arunachal Pradesh
 
wind energy
wind energywind energy
wind energy
 
power plants and working
power plants and workingpower plants and working
power plants and working
 
Energy Management through Bio-gas Based Electricity Generation System during ...
Energy Management through Bio-gas Based Electricity Generation System during ...Energy Management through Bio-gas Based Electricity Generation System during ...
Energy Management through Bio-gas Based Electricity Generation System during ...
 
IRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in India
IRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in IndiaIRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in India
IRJET- SOLAR POWER: Challenges, Mission and Potential of Solar Power in India
 

Recently uploaded

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Solving Power Crisis of Bangladesh by Utilizing Renewable Energy

  • 1. International Journal of Modern Research in Engineering & Management (IJMREM) ||Volume|| 1||Issue|| 6 ||Pages|| 20-28 || June 2018|| ISSN: 2581-4540 www.ijmrem.com IJMREM Page 20 Solving Power Crisis of Bangladesh by Utilizing Renewable Energy 1, Afshana Morshed, 2, Farzad Hossain, 3, Rifat Sultana Setu 1,2,3 Department of Mechanical Engineering, Military Institute of Science and Technology, Dhaka, Bangladesh -------------------------------------------------ABSTRACT--------------------------------------------------------- Bangladesh is a developing country and crisis of power is one of the acute quandaries in any developing country like Bangladesh. Power is the most paramount factor and the demand of power is incrementing rapidly in the country. There are several reasons behind the power failure like lack of commitment of ascendancy, system loss, circumscription of resources, high demand, corruption in potency, low generation capacity etc. To overcome the problem of power crisis, renewable energy can be a great source. Bangladesh has huge untapped renewable energy resources which can be utilized to solve and aid the power crisis. In this paper we described about different forms of renewable energy that can be acclimated to meet the power demand by proper utilization at low cost and less risk. We also discussed about several sectors of renewable energy sources such as solar energy, wind energy, tidal energy, bio energy, hydro power, geothermal, ocean wave energy and energy from Bay-of-Bengal. Skilled manpower and new technology are required for taking initiative steps for power sectors utilizing renewable energy. KEYWORDS: Power crisis, Paramount factor, Lack of commitment, Renewable energy, Implementation. --------------------------------------------------------------------------------------------------------------------------------------- Date of Submission: Date, 06 June 2018 Date of Publication: 11 June 2018 --------------------------------------------------------------------------------------------------------------------------------------- I. INTRODUCTION Power is the key and main requisite for running different sectors like agricultural, industrial, conveyance and the sectors which we face in our circadian activities. Electricity is the main source of energy. In the modern age, the world’s whole development and most of the economical activities depend on the electric power. People of the whole world cannot cerebrate a moment without electric power. Day by day the authoritative ordinance of electric power and energy is incremented but the engenderment and source of electric power are circumscribed. The main reason of this lack of electric power is due to the energy crisis throughout the world. The term energy crisis is any significant bottleneck in the supply of energy resources to an economy [1]. However, it often refers to one of the energy sources utilized at a particular time and place that can supply national electricity grid. Like other developing countries, Bangladesh is also an energy hungry country. The energy crisis is one of the major quandaries for people and economical activities of this country. Power infrastructure of Bangladesh remains same but the demand is rapidly incrementing. The per capita power consumption in Bangladesh is about 407KWH [2], which is one of the lowest in the world but for huge population density our power section is under enormous pressure. In Bangladesh at 2016, the total number of consumers connected to the grid is 21.8 million of the population [3] and the access to electricity is 76% of total population until June, 2016 [3]. So, 24% of the population still does not have direct access to electricity and those who get the electricity are additionally suffering astronomically immense for load shedding. In order to achieve the growth rate; availability of a reasonably priced and reliable source of electricity is a prerequisite [3]. The present condition of electricity cannot meet consumers growing demand. So, it is not possible to fulfill constant supply of electric power to all consumers throughout the country. Gradually the demand for electric power is increasing rapidly, so it is compulsory to take salutary steps to solve this power crisis. It is necessary to increase production of electricity and we need to concentrate on utilizing renewable energy like solar, wind, geothermal, tidal energy etc to produce adequate amount of electricity. The International Renewable Energy Agency (IRENA) ranked Bangladesh as the sixth largest renewable energy related work force in the world with 114,000 jobs in 2013 [4]. So, Bangladesh has enough possibility to utilize this renewable energy satisfactorily for installing sufficient electric power and setting power stations.
  • 2. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 21 II. PRESENT SITUATION OF POWER SECTOR IN BANGLADESH To solve the power crisis at first, it is necessary to focus on the present situation of Bangladesh power sector and production capacity. Bangladesh government electric sectors management control structure at a glance [3]: Figure 1: Present Structure of Power Sector Table 1 shows the manufacturing condition of Bangladesh at 2016 and 2017 [5]. Table 1: Manufacturing condition of Bangladesh at 2016 and 2017 Subject Unit 2016 2017 Production capability MW 14,565 15,755 Grid Sub-station Power MVA 26,690 30,993 Number of village with electricity Number 58,500 66,900 Production from renewable sources MW 202 216 Allotment for annual development program Crore 16,217 22,885 System loss Percentage 13.10% 12.19% From table 1, it is clear that with the increasing of manufacturing, system loss has been decreased to 12.19% in the year 2017. Moreover, within a year, we can see increment in the production capability, grid sub-station power, production from renewable sources, number of village with electricity, and allotment for annual development program. Table 2 and 3 shows present installed generation capacity (MW) in public and private sectors respectively as on January 5, 2018 [6] Table 2: Present Installed Generation Capacity (MW) in public sectors as on June 5, 2018 Public Sector Installed Generation Capacity (MW) BPDB 5266 APSCL 1444 EGCB 839 NWPGCL 1070 RPCL 77 BPDB-RPCL JV 149 Subtotal 8845 (57%)
  • 3. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 22 Table 3: Present Installed Generation Capacity (MW) in private sectors as on June 5, 2018 Private Sector Installed Generation Capacity (MW) IPPs 3953 SIPPs (BPDB) 99 SIPPs (REB) 251 15 YR. Rental 169 3/5 YR. Rental 1576 Power Import 660 Subtotal 6708 (43%) From the table 2 and 3, it is seen that total amount of 15,553 has been generated from the public and private sectors as on June 5, 2018. If we include captive power then the power installed capacity becomes (15,553 + 2800 = 18,353 MW). Installed Capacity as on May, 2018 (By Plant Type) is shown in the pie chart (Fig. 2) and installed capacity as on May, 2018 (By Fuel Type) is shown in another pie chart (Fig. 3). Figure 2: Installed Capacity as on May, 2018 (By Plant Type) Figure 3: Installed Capacity as on May, 2018 (By Fuel Type) 37% 33% 9% 15% 2% 4% Installed Capacity as on May, 2018 (By Plant Type) Combined Cycle Reciprocating Engine Gas Turbine Steam Turbine Hydro Others 62% 21% 8% 3% 2% 4% Installed Capacity as on May, 2018 (By Fuel Type) Natural Gas Furnace Oil Diesel Coal Hydro Others
  • 4. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 23 The figures 2 and 3 show the total installed generation capacity of Bangladesh on May, 2018. The percentage of Natural gas, Furnace oil, Coal, Diesel, Hydro, Steam turbine, Gas turbine, Combined cycle, Reciprocating engine of the year 2018 is represented in the pie charts. Different type of power stations can be seen in Bangladesh. Maximum power stations of Bangladesh use natural gas as their fuel. They are summarized below in a tabular form [7]. Table 4: Types of Power Station in Bangladesh Type of Power Station Power Station Capacity Fuel Type Coal fired Barapukuria 250 Coal Oil and Gas fired Thermal Ashuganj 638 Oil & natural gas Oil and Gas fired Thermal Ghorashal 950 Oil & natural gas Oil and Gas fired Thermal Siddhirganj 260 Natural gas Oil and Gas fired Thermal Shikalbaha 60 Natural gas Gas turbines Haripur 360 Natural gas Gas turbines Ashuganj 146 Natural gas Gas turbines Raozan 240 Natural gas Gas turbines Gopalganj 100 Natural gas Gas turbines Meghnaghat 450 Natural gas Gas turbines Golpara Barge 56 Natural gas Gas engines Gazipur 53 Natural gas Gas engines Siddhirganj 240 Natural gas Gas engines Mymensingh 216 Natural gas Gas engines Maona 35 Natural gas Gas engines Fenchuganj 51 Natural gas Gas engines Dhaka 7 Natural gas Gas engines Ghorasal Regent 108 Natural gas Gas engines Baghabari 50 Natural gas Hydroelectric Karnafuli 230 Hydroelectricity III. RENEWABLE ENERGY AND ITS TYPES Renewable energy is a kind of energy which can be obtained from innate processes and can be replenished constantly. Solar, wind, wave, hydro-power, geothermal, biomass etc. are considered renewable sources of energy which are environmentally safe and naturally replenished. Solar Energy: The amount of solar energy which is incident on the earth every year is identically equivalent to 160 times the energy stores in the world’s proven reserves of fossil fuels and equipollent to more than 15000 times the world’s annual utilization of fossil & nuclear fuels and hydro power [8]. However, among the total solar incoming radiation: 30% is reflected back to space, 47% is utilized to warm the earth’s surface and 23% is absorbed by evaporation of water [8]. Moreover, relatively small portions are habituated to drive the winds & waves and are absorbed by plants in photosynthesis [8]. Wind Energy: Wind energy has the facility to engender adequate amount of electricity without engendering any environmental quandaries. Sundry amounts of wind turbines are utilized all over the world for electricity engendering and water pumping purposes. Since the wind will perpetuate to be utilized for this purport, it is the utilization of wind energy as a pollution-free designates of engendering electricity on a potentially paramount scale that has the ability to magnetize most current interest. Wave Energy: A variety of designs for contrivances for extracting energy from waves has been proposed [9]. Experimental versions of several have already been tried, but the technology has not yet reached the commercial stage [9]. Several countries, including the UK have a paramount potential for utilizing wave energy [9]. Hydro-power: Hydro electricity is well established as one of the principle energy engendering technologies around the world providing 20 percent of the world’s electricity and in the developing countries, the proportion rises to around forty percent [9]. However, the capacity of the large hydroelectric schemes can be several times that of a usual power station and they are highly reliable, efficient and durable [9]. Moreover, the dams and
  • 5. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 24 lakes of large schemes also have environmental and gregarious impacts. There are additionally numerous devices for extracting energy from small and medium sized rivers and streams, with and without dams. Geothermal Energy: The interior of the earth is very much warmer than its surface, with estimated temperatures of several thousand degrees Celsius [9]. There are various places where the hot rock is very near or genuinely on the earth’s surface and heats water in underground aquifers [9]. However, hot water or steam has been provided by such places for centuries [9]. Moreover, many countries are utilizing geothermal steam because of electricity engendering and water heating purposes. Biomass: Biomass plant is one of the major world fuel resources especially in the third world where it provides forty percent of requisites [9]. It is also important in some of the forest-rich parts of the industrial nations (14% in Canada, 8% in Sweden) [9]. Though wood is the essential fuel, but animal dung and straw are widely utilized. Wood fuel can be called a renewable resource if its consuming rate is no more dominant than renewing rate. Moreover, Gas and liquid fuels can additionally be found from biological sources. IV. SOLVING POWER CRISIS USING RENEWABLE ENERGY Solar Energy: The most important renewable energy is solar energy. Utilizing solar energy can solve most of the power crisis by producing electricity. Already solar energy is being used in different places of Bangladesh. But the usage is not widely done in Bangladesh. Most of the countries in the world utilize solar energy to solve their power demand. By following and applying their technologies and processes, Bangladesh can also utilize renewable energy to solve power crisis problem through different power plants for producing electricity. There are some methods of converting photons into electricity. Solar Dynamic (SD) Technology: Solar dynamic utilizes a heat engine to drive a turbine or a piston which connects to a generator [10]. Photovoltaic (PV) Technology: Photovoltaic uses semiconductor cells to directly convert sunlight photons into voltage via a quantum mechanical mechanism [10]. They are not subjected to the thermodynamic circumscriptions of thermal engines such as those utilized in 50 accumulation system. Already Bangladesh is utilizing this technology in rural areas and Saint Martin Island. It is additionally utilized on road to run the road lights. However, if we utilize it in all road lights of Bangladesh, we can preserve some power for household and industrial needs. Concentrating Photovoltaic Technology: It is possible to utilize the concentrating photovoltaic system. It is like solar dynamic which is a form of subsisting terrestrial concentrating. Solar energy approaches which converts concentrated light into electricity by photovoltaic. To solve power crisis in sea side like Saint Martin island or Cox’s bazaar, Bangladesh can follow the solar oases produce renewable energy by utilizing alternative energy sources and desalinated brine for supplying the population in arid regions with aliment, energy, water and to establish fundamentals for development. Biomass: Another paramount and subsidiary renewable energy is biomass. The biomass utilized for electricity engenderment ranges by region forest by products, such as wood residues are popular in the United States [11]. Agriculture waste is prevalent in Southeast Asia (rice husks) and Mauritius (sugar cane residue) [11]. Animal husbandry residues such as, poultry litter is popular in the UK [11]. In Brazil, sugar or ethanol plants engender electricity in need from and residuals from sugar cane are left over by the milling process and it sells the surplus electricity to the public grid [12].The sucrose accounts for minor more than 30% is the chemical energy stored in the matured plant, 35% is in the leaves and stem tips, which are left in the fields during harvest, and 35% are in the fibrous material left over from pressing [13].The production process of sugar and ethanol in Brazil thoroughly capitalizes on the energy stored in sugar cane and they engender 600 MW of current for self-use and 100 MW for sale [14]. In Bangladesh, there is one sugar mill present. If government wants, a sugar and ethanol power plant can be placed as like Brazil, to engender electricity by utilizing the sugar cane residue to solve the power crisis around the mill. Wind Energy: Wind power is a great source of renewable energy which can convert the kinetic energy of wind to engender electricity or mechanical power. This is done by utilizing a huge wind turbine usually consisting of propellers which is connected to an engenderer to produce electricity. Though it is not widely utilized in Bangladesh, many countries have already utilized it in a large scale. Many developed countries have already installed a lot of large and small wind turbines and can be able to solve their power crisis. Small wind turbines are concretely agreed for self-sufficient power generation or local electricity producing in off-grid areas [15].
  • 6. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 25 Moreover, small wind turbines require a maximum rotor area of 200 m², which is equal to a maximum nominal power of 50 kW for an electrical voltage of below 1500 V DC or 1000 V AC [15]. Onshore wind turbines are also utilized in the developing countries which require low investment cost. Moreover, electricity engenderment can be possible with less investment and less transmission losses. On the other hand, offshore wind turbines are utilized in the developed countries in order to replace conventional power stations in the long term due to higher wind speeds at sea and can be possible to utilize 100% of the energy. However, wind energy can be one of the effective solutions to solve power crisis of Bangladesh. Small Wind Turbine (SWT) is considered the most opportune option for Bangladesh to solve power crisis which can be conveyed and installed with minimum land and infrastructure requisite. Moreover, wind turbines may be established in the coastal and higher altitude areas which can be very much subsidiary for engendering of electricity in the coastal region of Bangladesh. So, Bangladesh Government and other private organizations must be conscientious of establishing more wind power plants in order to solve the power crisis. Hydro-electricity: Engendering electricity by utilizing hydropower is known as hydroelectricity which is very much effective for solving power crisis. Many countries of the world have already utilized it in a huge amount. At the end of 2015, the leading hydropower engendering countries were Canada, the US, Brazil, Russia, China and India. However, three types of hydropower stations can be found in the world: ‘pumped storage’, where stored water is recycled by pumping it back up to a higher reservoir in order to be relinquished again; ‘reservoir’, where power is engendered through the relinquishment of stored water; ‘run of river’, where the electricity is engendered through the flow of a river’ [16]. At present, Bangladesh has only hydro power station at Kaptai. Although, the scope of engendering hydropower is very limited in Bangladesh due to its plain lands except in some hilly region in the southeast & northeast parts of the country, but there are lot of canals, branch of major river like Shangu, Karnafuli, Matamuhuri as well as small waterfalls which have good potentials for establishing micro and mini hydropower unit in Chittagong Hill Tracts (CHT) region [17]. Bangladesh Regime and other private organizations must be conscientious of establishing hydro power plants in order to solve the power crisis. Geothermal Energy: Geothermal energy is the renewable energy source which has the ability to solve power crisis. Developed countries have already established enough geo- thermal power plants in order to engender electricity. Three types of geothermal power plants are generally found in these countries, such as flash steam, dry steam and binary cycle [18]. Flash steam power plant can move high-pressure geothermal water into low- pressure tanks for engendering a flash of steam to spin a turbine and after the utilizing of the steam, it is cooled and condensed back into the water and finally injected back down to the reservoir [18]. The dry steam power plant can directly utilize steam in order to spin a turbine and can throw up the hazardous substances into the atmosphere. Since these systems utilize a very small amount of water, hence the denomination 'dry' [18]. Dry steam plants can be found in USA, Italy. On the other hand, binary cycle plant utilizes geothermal water in order to heat a secondary fluid that spins a turbine and the plant relies on the cycling of two fluids - the hot water and a secondary fluid [18]. The northern parts of Bangladesh can be very much efficacious for establishing geothermal power plants. However, the essentiality of electricity is incrementing in the country, but our engendering of electricity is not incrementing. So, there is a huge necessity of electricity in the rural area which can be covered by the engendering of electricity through geothermal energy. Wave Energy: Wave energy is engendered straight away from the ocean waves. It is another special kind of renewable energy which is utilized in many places of the world in order to decrement the harmful emissions of greenhouse gasses associated with the power engendering purport. It can be a huge source of electricity for Bangladesh. The Oscillating Water Column method is technically feasible and becoming economically impressive for this purport [19]. This type of wave energy harnessing technique is being accepted by several countries such as Ireland (3.5 MW), the United Kingdom (500 kW), India (150 kW), Norway (100 kW) etc. [20]. Bangladesh has the ability for harnessing ocean wave energy from the BAY OF BENGAL [20]. So, the Government must take compulsory steps in an early possible time in order to harness ocean energy which can be a great solution to our power crisis. By utilizing renewable energy, Bangladesh can solve power crisis. Taking some steps like all the industries that run by electric power can utilize solar energy to engender electricity for running lights and fans of their industries by setting short or large solar plants and by doing this, they can preserve some power from the national grid. The industries that situated in village side can also set biogas plant to run lights and fans of their industries. In the big city of Bangladesh, the owners of the big building can set solar energy collectors on their building's roof and by this collector if they run only one light or fan of every floor then they can preserve a good part of electricity from national grid and our regime can utilize that electricity in other sectors. On the other
  • 7. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 26 hand, farmers of Bangladesh can set biogas or solar plant for their irrigation system because at summer season Bangladesh regime can't supply total farmer's requisite electricity to run their pump for irrigation and so they face load shedding. Even Bangladesh can utilize other renewable energy like wind, wave, hydroelectricity and geothermal energy to engender electricity that described above. As some renewable energy used plants are very costly, so Bangladesh regime can set more and more solar, biogas or other renewable energy used plant or can help general and village people financially to set this type of plants. However, good news is that Bangladesh regime has taken action to set renewable energy used power plants to solve power crisis and that will start very soon. V. FUTURE OBJECTIVES The Power Station Master Plan 2016, sponsored by Japan International Corporation Agency, aims at assisting Bangladesh in formulating an extensive energy and power development plan up to the year 2041, covering energy balance, power balance [21]. Bangladesh has an aspiration to become a high-income country by 2041. The new Power Station Master Plan study covers all the aforementioned challenges comprehensively and come up with feasible proposals and action plans for Bangladesh to implement [21]. 5.1 Vision 2041 Power system master plan 2016 [21] 5.1.1 Value-up Plan 1 Robust infrastructure for Primary Energy Import 5.1.2 Value-up Plan 2 Domestic Energy Resource Development and Efficient Use 5.1.3 Value-up Plan 3 High Quality and Robust Power System Development 5.1.4 Value-up Plan 4 Advanced Development of Green Energy 5.1.5 Value-up Plan 5 Policy and Human Capital Development for Stable Energy Supply 5.2 Aim Aims of these value-up plans in Bangladesh following the achievements of High-Income Country are given below: 5.2.1 Value-up Plan 1 & Value-up Plan 2 Primary Energy Demand: Energy intensity [3.42~2.56 toe/million BDT] Gas/LNG: Domestic gas [2,500~2,000 mmcfd incl.YTF] Imported LNG [0~4,000 mmcfd] Coal: Domestic coal [0.7~11 million tons/year] Imported coal [0~60 million tons/year] Oil: Imported oil [5~30 million tons/year] 5.2.2 Value-up Plan 3 Power Generation: Complete phase-out of rental power [3,000 MW~0 MW] Electricity for all [250~1,500 kWh/person/year] Power Quality: No power shortage [500 MW~0MW] Fluctuation of world top quality [±1.5 Hz~±0.2 Hz] Operations and Maintenance: High thermal efficiency [30%~50%] Power Import/Nuclear Power: Import [500~9,000 MW]/Nuclear [0~7,200 MW] 5.2.3 Value-up Plan 4 Renewable Energy: Maximizing RE generation potential under limited land Bio-gas [4~62 mmcfd] 5.2.4 Value-up Plan 5 Energy Tariff Policy: No gap between tariff and supply costs [Power: 2.6%/year until 2031 and 1.5%/year afterwards] [Gas: 10-20%/year increase until 2031 and 1.5% year afterwards] Human Capital Development: Training centers Internationally recognized qualifications Professional engineers
  • 8. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 27 Short-term and medium-term power development plans are to be formulated after verifying the appropriateness of matters with a little short-term uncertainty in the formulation of a long-term power development plan. The optimum power source composition is to be determined in the preparation of the future vision of the power source composition by conducting a quantitative evaluation of the economic, environmental and energy security values of scenarios with different composition ratios for the gas and coal power generation. Power plants with a total output capacity of approximately 14,000 MW are to be constructed in the next ten years. The current status of each thermal power development plan was confirmed based on the discussion with related companies, such as BPDB, BIFPCL, CPGCBL, NWPGCL, Orion Group, etc. Guarantee of the long-term stability of the fuel supply is a very important factor in the formulation of a power development plan. The existence of a port infrastructure required for the importing of fuels including gas and coal during operation has to be a precondition for the decision on the CODs of new power plants. Bangladesh is in a good position to utilize the sufficient regional renewable energy potential and import it through the cross-border transmission network. Targets that Bangladesh wants to achieve by 2041 [21]: 1. Domestic renewable energy power generation: 2,470MW (by 2021), and 3,864MW (by 2041). 2. Domestic biogas production: 790,000m3 /day, including additional 600,000m3 /day by 2031, 3 millions m3 /day. 3. Cross-border energy import rules and regulations’ set-up, associated with capacity building. 4. Cross-border Energy Imports: 3,500~8,500MW (by 2031), 9,000MW (by 2041). VI. CONCLUSION Electricity is one of the blessings which science has given to us. Since, it has already become a component of our daily life, so we cannot even imagine a single day without electricity. But the problem is that power crisis has become a major issue in Bangladesh. Immediate steps must be taken otherwise it can go beyond control. Renewable energy can play a vital role in solving the disgusting power crisis of Bangladesh. However, it is the proper time to look forward and make necessary plans for utilizing renewable energy to engender electricity in lieu of avoiding dependence on the conventional method. Biomass based power plant has the ability to create electricity at a low cost. So, the country can establish it to meet the future power demand. Since Bangladesh has a plenty of rivers and has the facility to utilize the energy of Bay of Bengal, small power plants should be established utilizing wave and hydro energy. Moreover, wind power plants must be established in the coastal areas, like Sandip. Since solar energy is very powerful & efficacious, Bangladesh can additionally utilize it. Moreover, the Government and various organizations must come forward to establish renewable energy based power plants in order to solve this disturbing power crisis. REFERENCES [1] Energy crisis, Wikipedia [internet], Accessed: 28 February, 2018, Available from: https://en.wikipedia.org/wiki/Energy_crisis. [2] Govt. set up power stations, The Financial Express [internet], Accessed: 20 February, 2018, Available from: http://www.thefinancialexpress-bd.com/2016/12/18/56675/Govt-set-up-81-power-stations- generated-10,353-MW-in-8-yrs. [3] Bangladesh Energy Situation, Energypedia [internet], Accessed: 30 March 2018, Available from: https://energypedia.info/wiki/Bangladesh_Energy_Situation. [4] Green energy creates 1.14 lakh new jobs, The Daily Star [internet], Accessed: 31 March, 2018, Available from: http://www.thedailystar.net/green-energy-creates-1-14-lakh-new-jobs-24166. [5] Annual Report, Power Division, Government of the People’s Republic of Bangladesh [internet], Accessed: 09 June, 2018, Available from: http://powerdivision.portal.gov.bd/site/view/annual_reports. [6] Key Statistics, Bangladesh Power Development Board [internet], Accessed: 10 June, 2018, Available from: http://www.bpdb.gov.bd/bpdb/index.php?option=com_content&view=article&id=5&Itemid=6. [7] List of power stations in Bangladesh, Wikipedia [internet], Accessed: 29 March, 2018, Available from: https://en.wikipedia.org/wiki/List_of_power_stations_in_Bangladesh, [8] Arafat Ahmed Bhuiyan and A.K.M. Sadrul Islam, Performance and Social Aspect of LED based Solar Home System: Bangladesh, World Renewable Energy Congress XI, Abu Dhabi, UAE, 25-30 September 2010. [9] Renewable Energy Technology Course: Study Guide, The Division of Heat and Power Technology, Department of Energy Technology, Royal Institute of Technology, Stockholm, Sweden, 2008. [10] Goldenravi, Introduction, Scribd [internet], Accessed: 03 May, 2018, Available from: https://www.scribd.com/document/93740018/Introduction,
  • 9. Solving Power Crisis of Bangladesh by Utilizing... www.ijmrem.com IJMREM Page 28 [11] Biomass Sources, Eisenhardt [internet], Accessed: 20 March, 2018, Available from: http://www.eisenhardt-trading.com/productosindustriales/biomasa-english2.html. [12] Bioenergy, Wikipedia [internet], Accessed: 04 April, 2018, Available from: https://en.wikipedia.org/wiki/Bioenergy. [13] Photosynthetic Efficiency - Efficiencies of Various Bio fuel Crops, LiquiSearch [internet], Accessed: 25 March, 2018, Available from: http://www.liquisearch.com/photosynthetic_efficiency/efficiencies_of_various_biofuel_crops. [14] BIO-ENERGY, Project Gutenberg Self-Publishing Press [internet], Accessed: 30 April, 2018, Available from: http://www.gutenberg.us/articles/bio-energy. [15] Energy supply with renewable – Made in Germany, Dena (German Energy Agency) [internet], Accessed: 05 April, 2018, Available from: http://www.renewables-made-in- germany.com/en/renewables-made-in-germany/technologies/wind-energy/wind-energy/technologies- and-applications.html. [16] Energy Resources, World Energy Council [internet], Accessed: 1 May, 2018, Available from: https://www.worldenergy.org/data/resources/resource/hydropower/. [17] M. A. Matin, H. Rahman, M. R. Hossain, M. A. Ehsan, G. M. I. Hossain and M. M. I. Mahfuj, Present Scenario and Future Prospect of Renewable Energy in Bangladesh, 1st International Conference on Physics for Sustainable Development & Technology (ICPSDT), Chittagong University of Engineering & Technology (CUET), Chittagong - 4349, Bangladesh, 19-20 August 2015. [18] Geothermal Energy: Advantages and Disadvantages, Study.com [internet], Accessed: 2 May, 2018, Available from: http://study.com/academy/lesson/geothermal-and-tidal-energy-advantages-and- disadvantages.html. [19] Alimul Haque Khan, Kazi Rehnuma Zafreen & Mir Muntasir Hossain, A Review of Current Renewable Energy Activities in Bangladesh, Scribd [internet], Accessed: 3 May, 2018, Available from: https://www.scribd.com/document/333152777/A-Review-of-Current-Renewable-Energy- Activities-in-Bangladesh. [20] Khairul Anam, Husnain-Al-Bustam, Power Crisis & Its Solution through Renewable Energy in Bangladesh, Cyber Journals: Multidisciplinary Journals in Science and Technology, Journal of Selected Areas in Renewable and Sustainable Energy (JRSE), September Edition, 2011. [21] Survey on Power System Master Plan 2016-Final Draft, Scribd [internet], Accessed: 16 February, 2018, Available from: https://www.scribd.com/document/332241567/Survey-on-Power-System- Master-Plan-2016-Final-Draft. Afshana Morshed Tithi, et al. “Solving Power Crisis of Bangladesh by Utilizing Renewable Energy.” International Journal of Modern Research in Engineering & Management (IJMREM), vol. 1, no. 6, 18 June 2018, pp. 20–28., www.ijmrem.com.