Installed Power Generation in India: 2013
http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Indian-installed-power-generation-capacity-in-2013.jpg
68% generation
anti-green &
hazardous for
human health
India’s Global Statistics: 2011
http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Comparison-of-key-energy-statistics-for-select-countries.jpg
Operating Parameters for a typical 210 MW
Coal-fired Power Plant in India
http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Operating-parameters.jpg
Fossil Fuel Production & Reserves in India
http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Fossil-fuel-production-and-reserves-in-India.jpg
Comparison of Centralized Electricity
Generation Options for India
http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Comparison-of-centralized-electricity-generation-options-for-India.jpg
Projected Growth of TPPs in India till 2030 - I
http://www.urbanemissions.info/images/stories/Air%20Pollution%20from
%20India%20Coal%20TPPs%20-%20Coal%20Power%20Expansion.jpg
Projected Growth of TPPs in India till 2030 - III
 Total coal consumption is estimated to increase 2-3 times from 660 million
tons/year to 1800 million tons/year; accordingly the CO2 emissions from 1,590
million tons/year to 4,320 million tons/year
 PM, SO2, and NOx emissions will at least double in the same period. Most of
the planned plants are supercritical- and ultra- TPPs, which tend to utilize
less coal per MWh of electricity generated
 With no emission regulations in place for SO2 and NOx, these are assumed
uncontrolled and allowed to release through the elevated stacks for
dispersion
 100% increase in health impacts - The total premature mortality due to the
emissions from coal-fired TPPs is expected to grow 2-3 times reaching 186,500
to 229,500 annually in 2030. Asthma cases associated with coal-fired TPP
emissions will grow to 42.7 million by 2030
 Limited emission standards for power plants - India currently has no
standards for either SO2 or NOx both of which drive a large portion of the
estimated these health impacts – in the form of secondary sulphates and
secondary nitrates.
http://www.urbanemissions.info/india-power-plants
Projected Growth of TPPs in India till 2030 - IV
 Set emission standards
 Mandate FGD at the plant level
 Practice rigorous monitoring
 Ensure transparency
 Improve EIA
 Large enforcement /redesign costs
http://www.urbanemissions.info/india-power-plants
Shifting Emphasis to Renewable Energy
 Over the last 40 years thermal generation has increased to more than 70%
 Given the difficulty of constructing large hydro projects, its share is unlikely
to increase in the future
 Nuclear installed capacity is projected to increase to about 69 GW (under the
most optimistic scenario) from the existing base of about 5 GW
 Share of coal in the electricity generation mix is likely to range from 50 – 60%
in 2035
 Scenario whereby India reduces the coal mix to 40% is considered as the
highest possible reduction in coal usage would imply a 22% share of
renewable energy in the electricity generation mix
 Even with this high renewable share, the coal installed capacity must grow to
270 GW by 2035
 More likely estimate of installed coal-based power capacity is 340 GW (50%
share) in 2035, which represents significant growth from the existing installed
capacity of 132 GW in 2013 (i.e., growth rate of 4.4% per year).
http://www.worldcoal.org/extract/coal-based-electricity-generation-in-india-3700/
The Rising Health Hazard from TPPs till 2030 - I
http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%2
0Coal%20TPPs%20-%20PM%20and%20SO2%20pollution%20through%202030.jpg
The Rising Health Hazard from TPPs till 2030 - II
Debi Goenka & Sarath Guttikunda, Coal Kills An Assessment of Death and Disease
caused by India’s Dirtiest Energy, Urban Emissions & Greenpeace India, 2014, p. 7
Largest impact:
 Delhi
 Haryana
 Maharashtra
 Madhya Pradesh
 Chhattisgarh
 Indo-Gangetic Plain
 Central-East India
Health Impact of Coal-Based Power Generation - I
http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPPs%20-
%20Population%20Weighted%20PM2.5.jpg
Health Impact of Coal-Based Power Generation - II
http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPPs%20-
%20Anticipated%20Health%20Impacts.jpg
Health Impact of Coal-Based Power Generation - III
http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPPs%20-
%20Benefits%20of%20FGD.jpg
Health Impact of Coal-Based Power Generation - IV
http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPP
s%20-%20Health%20Impacts%20by%20State.jpg
Health Impact of Coal-Based Power Generation - V
Effect Health
Impacts (units)
Impact Cost
Total Premature
Mortality
80000-115000 INR 16-23,000 crore (USD 3.3-4.6 b)
Child Mortality (<5 yrs.) 10000 INR 2100 crore (USD 420 m)
Respiratory Symptoms 625 million INR 6200 crore (USD 1.2 b)
Chronic Bronchitis 170000 INR 900 (USD 170 m)
Chest Discomforts 8.4 million INR 170 crore (USD 35 m)
Asthma Attacks 20.9 million INR 2100 crore (USD 420 m)
Emergency room visits 900000 INR 320 crore (USD 60 m)
Restricted Activity Days 160 million INR 8000 crore (USD 1.60 b)
Sarath K. Guttikunda & Puja Jawahar: Atmospheric emissions and pollution from the coal-fired thermal
power plants in India, Atmospheric Environment 92 (2014) 449-460, Elseiver, 2014
Debi Goenka & Sarath Guttikunda, Coal Kills An Assessment of Death and Disease caused by India’s
Dirtiest Energy, Urban Emissions & Greenpeace India, 2014
Health Impact of Coal-Based Power Generation - VI
Debi Goenka & Sarath Guttikunda, Coal Kills An Assessment of Death and Disease caused by India’s
Dirtiest Energy, Urban Emissions & Greenpeace India, 2014, p. 4
Health impacts resulting in premature deaths include
 Chronic obstructive pulmonary disease
 Lower respiratory infections
 Cerebrovascular disease
 Ischemic heart disease
 Cancers of trachea, bronchitis, and lung
 Systemic inflammation
 Accelerated atherosclerosis
 Altered cardiac function
Should India Depend on Coal?
 Coal is probably the least expensive fossil fuel for power generation or for
industrial use based on the cost per unit energy content in India
 The price of coal is on the order of INR170/GJ (US$3.2/GJ) as compared to
INR1000/GJ for fuel oil (US$20/GJ) or INR240/GJ (US$4.8/ GJ) for natural gas
 Share of imports in the Indian energy supply mix has been increasing over the
last two decades. In 2012 energy imports accounted for about 26% of the total
primary energy supply, mainly due to oil imports
 India imported about 124 million tons of crude oil and about 23 million tons of
petroleum products with exports of about 41 million tons of petroleum
products in 2010
 India’s oil production has been nearly stagnant at about 33–38 million tons
annually
 Foreign exchange rate fluctuation (devaluation of the rupee) results in a major
impact on the economy with an increase in oil prices and resultant inflationary
pressure (in 2013 the $-rupee exchange rate increased from 50INR/US$ to
64INR/US$).
http://www.worldcoal.org/extract/coal-based-electricity-generation-in-india-3700/
72%
28%
Rural Urban
1254019
1268961
1283600
1298041
1312240
1326155
1339741
1352695
1365302
1377442
1388994
1399838
1150000
1200000
1250000
1300000
1350000
1400000
1450000
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Figures in 000s
Grass, Bamboo.
Thatch, Wood,
Mud
21%
Plastic, Polythene
1%
Tiles
30%
Slate
1%
GI, Metal, AC
sheets
12%
Brick
6%
Stone
7%
Concrete
21%
Other Material
1%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
1
2
3
4
5
6
7
100
346
728
1419
2995
6642
15461
25
87
182
355
749
1661
3865
1
Average Population/village Average no. of households @ 4 persons/family unit
The Costs of Renewable Energy
 At current costs this would involve an initial investment of 8 – 8.5 times
the investment required by coal or more than 90% of the existing total
central government outlay
 Hence in the next 25–30 years coal is likely to remain the main source of
electricity supply for India, even though its percentage share in the mix
may decrease.
http://www.worldcoal.org/extract/coal-based-electricity-generation-in-india-3700/
Grid-Linked v. Grid-Neutral Solar Energy
Plusses of Grid-Linked
 Availability for all consumers
 Standard Tariffs fixed by SERC
 Economy of scale?
 Standard O&M procedures
 Complex O&M
Minuses of Grid-Linked
 Variable load affecting
availability
 High-tension consumers in
vicinity affect availability
 Longer breakdown restoration
Plusses of Grid-Neutral
 Assured availability for local
consumers
 Variable by local need & time
 High-tension consumers do
not affect quality &
availability
 Does not need expensive
connectivity to grid
 Speedy breakdown restoration
Minuses of Grid-Neutral
 Economy of scale?
 Local community land
availability and willingness
 Nearly half of India’s rural population
resides in 115,080 villages with population
more than 2,000 but less than 10,000
 Highest 34.64% villages comprise
population range of 2000-4999
 Villages becoming larger in the population
size 1000- 1999, 2000 - 4999, 5000 - 9999 and
10000+
 Decrease in number of villages in the 500
and 500 – 999 population ranges
AlternativeEnergy
All Villages 2000-10000 2000-4999
Minority Villages
SP/BE-based Meat
Cold Storage
Containers
Prefab animal
skin-based micro-
industry
SC/ST Villages
SP/BE-based Cane,
jute, micro-
industry
Cold Storage
Containers
Urban Slums
SP-based Prefab
Homes
Water & Waste
Mgt.
Homeless
SP-based Prefab
Homes
Water & Waste
Mgt.
All habitations
within 100 km
radius of all TPPs
SP/BE-based PHCs
networked with
State MCs
E-Consult ITES
solution
State
Health Mobile Clinics
Mobile OTs
Telemedicine
VSAT connectivity PHCs
Education Mobile e-libraries
Internet Access Vans
Adult Literacy Media Vans
Mobile Classrooms
Extension Services Mobile Agri-labs
Mobile Agri Demo Vans
Mobile Fertilizer Sale Vans
Mobile Post Offices
Mobile PSB branch
Mobile RRBs
State
Communications Mobile Entertainment
Mobile Community TV/Radio Broadcast Center
Mobile Telephone Exchange
Scheme Monitoring &
Evaluation
In situ survey & online reporting Vans
Mobile QA Labs
Mobile Evaluation Teams
Mobile QA Community Publicity Vans
Financial Services VSAT-linked terminals for Cash Deposit
savings & Purchase of Small Savings
Schemes, etc.
VSAT-linked weather, agricultural, etc. info
terminals
State
Skills Development Mobile Classrooms
Mobile Demo Trailers
Prefab Assembly Centers Ready-mades, metal fabrication, etc.
Bamboo & cane furniture manufacturing,
weaving jute products, etc.
Repair and O&M of SP/BE systems, DG
sets, telephone systems, TVs, local energy
grid, etc.
About Us
Modular
Scalable
Portable
Green
Vertical & Horizontal
Integration
GroupCEO
Ex. Secy.
Director
(Consulting)
Director
(Waste Mgt.)
Director
(Water Mgt.)
Director (ITES)
Director
(Security)
Director (Services)
Director (Prefab)
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Client Description of
work
Completion Cost
(in Million INR)
Date of
commissioning
Collaborator Nature of
Collaboration
Collaborative
Turnover
(INR in Million)
Ongoing Projects
(INR in Million)
No. of Projects Implemented Cumulative Group Turnover
(INR in Million)
Share Capital (INR in Million) Paid-up Capital (INR in Million)
Net Profit/Loss (INR in
Million)
Reserves & Surpluses (INR in
Million)
Fixed Assets (INR in Million) Liabilities (INR in Million)
Quick Assets (INR in Million) Contingent Liabilities (INR in
Million)
State Capital Funds
for
Development
Optimal Cost Benefit
Safeguarding Community Health
Creating Rural Community
Infrastructure
Smart & Prosperous Villages
Generating Employment &
Wealth via Skill Development
Curbing Urban Migration
Q
L
I
Q
L
I
AlternativeEnergy
Solar
LED Lighting
Community Energy Needs
Cold Storages
ITES, Media &
Communication
Drip Irrigation
Biomass
Community Energy Needs
Water & Waste Mgt.
Project Consulting
Turnkey
Implementation
Industry-leading
Collaborations
Group Turnover
> Rs. 1000 crore
Dedicated & seasoned
capital project HR
 Number of households – 200
 Average load of 0.4 KW = total load of 80 KW
 Number of pump sets – 50
 Average load of 5 HP per pump set = total load
of 185 KW
 Others (Public Lighting, Commercial,
Industrial)– 75 KW
 Micro village-level grid
 Total Load = 340 KwH
 More illumination per INR of
investment
 Manifold low O&M costs
 Manifold more usable life than CFL
& incandescent lighting
 Casts manifold less load on power
generators
 Low voltage required reduces
demand on generators & makes
power delivery and quality reliable
and stable
 Permits easy mounting on kuchha
roof
Self charging point-based
on rechargeable
appliances & lighting
apparatus on prepaid
meter basis
Local grid prepaid metered
basis
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
Capital Cost of 2KwH solar panels & generator + grid INR 10,00,000 INR 150,00,00,000
Est. Monthly energy bill (on 12 hr daily 7W LED use) INR 20 INR 60,00,000
Monthly revenue earned by local operators less 20%
for O&M, 20% R&R and 20% RoI/annum
INR 2,400 INR 36,00,000
Add Capital cost for 100 x 15W street lights INR 15,000 INR 225,00,00,000
Add Capital Cost for 200 common utility LEDs for
other public spaces
INR 40,000 INR 6,00,00,000
Operator’s revenue less 20% O&M, 20% R&R & 20%
RoI
INR 7,200 INR 1,08,00,000
Total est. capital cost for 30,00,00 families with 50%
state capital subsidy + 50% operator share
- INR 190,50,00,000
Recurring annual cost to users w/o subsidy INR 300 INR 4,50,000
Less 25% obtained by commercial spaces on poles,
utility buildings, solar panels, etc.
INR 225 INR 3,37,500
Payback period without State capital subsidy 11 years 11 years
Payback period with 50% State subsidy 5.5 years 5.5 years
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
Capital Cost of 2KwH solar panels & generator INR 500000 INR 750000000
Est. Monthly energy bill (on 12 hr daily LED use) INR 50 INR 2000000
Monthly revenue earned by local operators less
20% for O&M
INR 40 INR 1600000
Add Capital cost for 100 x 15W street lights INR 15000 INR 2250000000
Add Capital Cost for 200 common utility LEDs for
other public spaces
INR 5000 INR 1500000000
Operator’s revenue less 20% O&M cost - INR 12160000
Total est. capital cost for 300000 families with
100% state capital subsidy
- INR 4500000000
Recurring monthly cost to users w/o subsidy INR 300 INR 90000000
Less 25% obtained by commercial spaces on poles,
utility buildings, solar panels, etc.
INR 225 INR 67500000
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
Capital Cost of 10 KwH solar panels & generator INR 2000000 INR 3000000000
Est. Monthly energy bill (on 12 hr daily LED, 6 hrs.
3x1 HP pump use, potable water, 4 fans & 2
appliances of 100 W each)
INR 2000 INR 600000000
Annual revenue earned by local operators less
20% for O&M + 20% performance bonus
INR 40 INR 4320000000
Add Capital cost for 100 x 15W street lights INR 15000 INR 2250000000
Add Capital Cost for 200 common utility LEDs for
other public spaces
INR 5000 INR 1500000000
Annual operator’s revenue less 20% O&M cost +
2o% performance bonus
- INR 108000000
Total est. capital cost for 300000 families with
50% state subsidy + 50% operator share each
- INR 3375000000
Gross recurring monthly cost to users w/o subsidy INR 2100 INR 630000000
Less 25% obtained by commercial spaces on poles,
utility buildings, solar panels, etc.
INR 1575 INR 472500000
Payback period for State & Private Operator each - 6 years
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
Capital Cost of 10 KwH solar panels & generator INR 2000000 INR 3000000000
Est. Monthly energy bill (on 12 hr daily LED, 6 hrs.
3x1 HP pump use, potable water, 4 fans & 2
appliances of 100 W each)
INR 2000 INR 600000000
Monthly revenue earned by local operators less
20% for O&M + 20% performance bonus
INR 1600 INR 380000000
Add Capital cost for 100 x 15W street lights INR 15000 INR 2250000000
Add Capital Cost for 200 common utility LEDs for
other public spaces
INR 5000 INR 1500000000
Operator’s revenue less 20% O&M cost - INR 12160000
Total est. capital cost for 300000 families with
100% state subsidy
- INR 6750000000
Gross recurring monthly cost to users w/o subsidy INR 2100 INR 630000000
Less 25% obtained by commercial spaces on poles,
utility buildings, solar panels, etc.
INR 1575 INR 472500000
Payback period for State (in 2015 INR) - 12 years
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
State Government’s share INR 11250 INR 3375000000
Private Operator’s share INR 11250 INR 3375000000
Annual revenue earned by private operators - INR 907200000
Less 25% obtained by commercial spaces on
poles, utility buildings, solar panels, etc.
INR 1575 INR 567000000
Payback period for private operator with
50% state subsidy, 20% O&M, 25%
commercial revenue and & 25% RoI/annum
- 9 years
 Prices and tariffs shown are provisional
 Sovereign guarantee of State essential for 9 years
WaterManagement
Use sources within 15 km
radius
Potable Water Filling
Points on prepaid cards
Recycled Water for
Irrigation & WCs
De-ironing Arsenic Removal
Ionizing
Treat other chemical
residues
Filtration Public Spaces & Homes
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
Capital Cost 2000 LPH with bottling capacity &
building & HDPE distribution lines
INR 4500000 INR 6750000000
Est. Monthly water & energy bill INR 250 INR 75000000
Payback period without State subsidy - 12 years
Payback period with 50% State capital subsidy - 6 years
Monthly revenue earned by operators less 20%
for O&M & 20% performance bonus
INR 150 INR 45000000
Less 25% obtained by commercial spaces on poles,
utility buildings, solar panels, etc.
INR 115 INR 33750000
 Prices and tariffs shown are provisional
 Sovereign Guarantee by State Govt. required
Waste
Management
Mobile Waste
Collection
Community
Water Closets
Biogas
Generation
Home Water
Closets
Water
Recycling
Mobile
Incineration
Energy
Generation
Saleable By
Products
Human/Animal
Remains Incineration
Commercial Animal
Skin Recycling
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
Capital Cost (incl. D2D collection, incineration &
energy generation)
INR 2500000 INR 3750000000
Est. Monthly bill INR 1000 INR 300000000
Payback period without State capital subsidy less
20% O&M & 20% performance bonus
13 months 2 years
Less 25% obtained monthly by commercial spaces
on poles, utility buildings, solar panels, etc.
INR 750 INR 225000000
Payback period with 50% State capital subsidy 7 months 1 year
 Prices and tariffs shown are provisional
 Sovereign Guarantee by State Govt. required
Detail Cost/Rent/Year Cost for 1500 small
communities
Est. capital cost of 25 public toilet units (wet
with sewage evacuation for biogas generation)
INR 5000000 INR 7500000000
Monthly rental from individual use & pay
public toilets
INR 75000 INR 112500000
Payback period without State subsidy 6 years 6 years
Payback period with 50% State capital subsidy 3 years 3 years
Monthly revenue earned by local operators less
20% for O&M & 25% RoI
INR 1375 INR 412500000
Payback period for private operator with 50%
capital subsidy, 20% O&M and 25% RoI
9 years 9 years
 Prices and tariffs shown are provisional
 Sovereign Guarantee by State Govt. required
PrefabricatedPortableUnits
Schools
Multipurpose building
Covered Auditoria
Multipurpose Halls
Panchayat HallAuditoria
Homes
2-4 rooms & WCs
Local Manufacturing
Centers
Trade-specific Modules
Stadia
Amphitheatre Daytime Market
Evening Cultural Center
Family Wellness Center
Detail Cost/Rent/Year Cost for 1500 small
communities
Capital Cost (200x 500 sft each, 3X3000 sft
multipurpose halls, one 2000 sft school building,
one amphitheater x 3000 sft, one commodity
market x 5000 sft, one industrial center x 5000
sft, one public utility building x 2000 sft) @ Rs.
2000/sft
INR 250000000 INR 375000000000
Monthly rental from homes INR 250 INR 75000000
Payback period without State subsidy 33 years 33 years
Payback period with 50% State capital subsidy 17 years 17 years
Monthly revenue earned by local operators less
20% for O&M & 25% RoI
INR 1375 INR 412500000
Less 25% obtained by commercial spaces on
poles, utility buildings, solar panels, etc.
INR 1031 INR 3093750000
Payback period for private operator with 50%
capital subsidy, 20% O&M and 25% RoI
- 28 years
 Prices and tariffs shown are provisional
 Sovereign Guarantee by State Govt. required
IT-enabledServices
Schools
Secure Degree Certificates
Secure Mark sheets
Commercial Community
Media
Commercial Radio/Television
Family Wellness Centers
Electronic patient records
Web-based E-Consult with MCs
Info Kiosks
Birth & Death Registration, Agri,
weather, bank, Post Office ,
railway/bus ticketing
IT-enabledServices
Water Mgt.
Web-based meter reading, prepaid
credit purchase
Real-time water flow & timing
monitoring
Waste Mgt.
Movement of mobile waste collection
& incineration vehicles
Energy Generation Mgt.
Solar Energy Mgt.
Web-based O&M, pre-paid credit
purchase, meter reading
Umbrella Services Centers
Birth & Death Registration, Property
Transfer, Agriculture, weather, bank,
Post Office , railway/bus ticketing
Detail Per Unit Cost for 1500 small
communities
(4 lights each)
5-year Lease Cost (250 desktops, 50 laser
printers, 250 solar UPS, networking, interface
with WAN, etc.)
INR 5,00,00,000 INR 75,00,00,00,000
Commercial monthly revenue earned by local
operators (no cost to user)
INR 2,50,000 INR 37,50,00,000
Operator’s revenue less 20% for O&M & 20%
uptime incentive
INR 1,50,000 INR 22,50,00,000
Less 25% obtained by commercial spaces on
poles, utility buildings, solar panels, etc.
INR 1,12,500 INR 16,87,50,000
Payback period for operator with 50% capital
subsidy, 20% O&M, 20% uptime incentive and
25% RoI
19 years 19 years
 Prices and tariffs shown are provisional
 Sovereign Guarantee by State Govt. required
Asset INR
Solar Energy Generation , LED Lighting, Other
appliances, etc. (w/o state subsidy)
1575
Potable Water Supply (w/o State subsidy) 115
Prefab Home Rental (w/o State subsidy) 250
ITES (w/o State subsidy) -
Subscriber’s Total Monthly Bill INR 1940
Benefits 1.20 million families @ min. 4 heads/family = 4.8 million/48
lakh individuals
Cost to State/individual on 50%/100% capital
subsidy basis
INR 41100/82200
Assets Created: Homes, Public Spaces, 24 x 7 energy, water and
waste management, public toilets, ITES, etc.
Est. new O&M jobs created @ 50/community = 45000
Total capital value of assets created in 12-18 months: Rs. 41100 crore
Solar-powered Cold Storage Containers
Horticulture
Marine
Products
Vegetables
& fruits
Meats
Medicines
& Vaccines
Better prices for
produce
22% of veg & fruit worth
Rs. 330 billion p.a. lost
Biomass Gasifier
Energy
Generation
Waste Mgt.
Dr. Amit Kumar: Solar–Biomass Hybrid Cold Storage-cum-Power
Generation system for Rural Applications, Energetica India, TERI, 2012, p. 54
SP/BE-powered toilets
Public Safety Hygiene
Dignity of
Labor
Wet Toilets in Prefab
Homes
Wet Toilets in Public
Spaces
Biogas-based Energy
Generation
Briquette Feedstock for
BE generation
Crop/Horti
Manure
SP/BE-powered & Prefab Housed Media Center
Education Entertainment Awareness
Telephone Exchange –
lines on prepaid credit
Intercom b/w homes
Connectivity to
national telecom N/W
Community TV station
Emergency, Agri, Weather,
Commercial Publicity
Commercial channels on
prepaid credit
Community Radio
Station
Emergency, Agri, Weather,
Commercial Publicity etc.
Skill Development Center
Trained HREmployment
Ministry Saving/Surrender (INR in Million)
Civil Aviation 1437.72
Commerce 1465.92
Information Technology 305.99
Defense 2769.13
DoNER 1212.48
External Affairs 2602.10
Financial Services 12493.63
Health & Family Welfare 9983.73
Heavy Industry 1847.79
Home Affairs – Police 29992.13
Information & Broadcasting 1893.00
Power 2356.64
Road Transport & Highways 56109.00
Space 10965.71
Andaman & Nicobar Islands 2699.09
Urban Development 9271.77
TOTAL (all Depts/Ministries) 7429458.44 (742945.84 crore)
Ministry Saving/Surrender (INR in Million)
Assam 46706.18
Rajasthan 15439.51
Madhya Pradesh 82632.84
Maharashtra 98250.88
Uttar Pradesh 40331.59
Himachal Pradesh 1977.69
Gujarat 12428.43
Haryana 6090.44
TOTAL 303857.58 (INR 30385.76 crore)
S
U
S
T
A
I
N
A
B
I
L
I
T
Y
State bears 100%
of capital cost
Fully utilizes large recurrent
capital Savings/Surrenders
Private Operator Bears
50% with Sovereign
Guarantee
Reduces State’s commitment
& fuel other areas on identical
lines – optimizes application of
capital dev. funds
Prepaid pay-as-you-go tariff
No Pilferage
Enables Advance
Resource Planning
Project’s
Cash Flow
assured
Private Operator collects revenue
& uses 25% each for R&R, O&M,
grid expansion and annual RoI
Localized & Flexible
Development
I
• Refinancing of implementing agencies by FIs
II
• PPP mode (revenue used for payback on BOOT
basis)
III
• State-funded (Capital) – delayed release of
funds – uncertain cash management
IV
• Diffused multi-agency financing with
complicated terms & conditions
V
• Need for concentrating financing through a
single agency/Ministry
Direct refinancing of private operators by FIs
Implementation, O&M and R&R transferred to
private operators against prepaid revenues generated
Divert State/Central Capital budgets to refinancing
private operators for all infrastructure projects
State agencies to monitor O&M and R&R of private
operators
Prepaid-based tariff collection on pay-as-you-go format –
assures cash flow, attracts private/venture capital and
improves O&M, R&R & Future System Extension
Use of Community Land for Facilities
Technology to negate pilferage of energy
Internet connectivity
Mindset change in subscribers for prepaid tariffs
Govt. clearances & policy modifications for refinancing
private operators + sovereign guarantee + self-sustaining
revenue generation
Renewable Energy & Alternative Technologies for Rural India
Renewable Energy & Alternative Technologies for Rural India

More Related Content

What's hot

Energy sector in india 2017 basics and post budget insights arindam (1)
Energy sector in india 2017 basics and post budget insights  arindam (1)Energy sector in india 2017 basics and post budget insights  arindam (1)
Energy sector in india 2017 basics and post budget insights arindam (1)Mr. Arindam Bhattacharjee
 
2011 National Energy Policy Recommendations IEEE-USA
2011 National Energy Policy Recommendations   IEEE-USA2011 National Energy Policy Recommendations   IEEE-USA
2011 National Energy Policy Recommendations IEEE-USAJohn Ragan
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in IndiaDaya Kherwar
 
National energy policy nep presentation r1
National energy policy  nep presentation r1National energy policy  nep presentation r1
National energy policy nep presentation r1Prashantkarhade72
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat
 
Future energy scenario of world
Future energy scenario of worldFuture energy scenario of world
Future energy scenario of worldAsma1122
 
Indian energy scenario by saikat ghosh
Indian energy scenario by saikat ghosh Indian energy scenario by saikat ghosh
Indian energy scenario by saikat ghosh Saikat Ghosh
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat
 
2010 11 - Indian Energy Sector by ibef
2010 11 - Indian Energy Sector by ibef2010 11 - Indian Energy Sector by ibef
2010 11 - Indian Energy Sector by ibefBulbtiger Tiger
 
indian energy sector overview
indian energy sector overviewindian energy sector overview
indian energy sector overviewshivraj negi
 
Power sector in india
Power sector in indiaPower sector in india
Power sector in indiaHarshit Garg
 

What's hot (20)

Energy sector in india 2017 basics and post budget insights arindam (1)
Energy sector in india 2017 basics and post budget insights  arindam (1)Energy sector in india 2017 basics and post budget insights  arindam (1)
Energy sector in india 2017 basics and post budget insights arindam (1)
 
Renewable Energy Sector
Renewable Energy SectorRenewable Energy Sector
Renewable Energy Sector
 
2011 National Energy Policy Recommendations IEEE-USA
2011 National Energy Policy Recommendations   IEEE-USA2011 National Energy Policy Recommendations   IEEE-USA
2011 National Energy Policy Recommendations IEEE-USA
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
 
National energy policy nep presentation r1
National energy policy  nep presentation r1National energy policy  nep presentation r1
National energy policy nep presentation r1
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
 
India : Power Sector Report_August 2013
India : Power Sector Report_August 2013India : Power Sector Report_August 2013
India : Power Sector Report_August 2013
 
Renewable Energy Sector Report - February 2018
Renewable Energy Sector Report - February 2018Renewable Energy Sector Report - February 2018
Renewable Energy Sector Report - February 2018
 
A present energy scenario
A present energy scenarioA present energy scenario
A present energy scenario
 
Renewable Energy Sector Report - February 2019
Renewable Energy Sector Report - February 2019Renewable Energy Sector Report - February 2019
Renewable Energy Sector Report - February 2019
 
Future energy scenario of world
Future energy scenario of worldFuture energy scenario of world
Future energy scenario of world
 
Indian energy scenario by saikat ghosh
Indian energy scenario by saikat ghosh Indian energy scenario by saikat ghosh
Indian energy scenario by saikat ghosh
 
Energy scenario sachin 27.05.14
Energy scenario sachin 27.05.14Energy scenario sachin 27.05.14
Energy scenario sachin 27.05.14
 
Global Scenario - Energy, (ICLEI World Congress 2009)
Global Scenario - Energy, (ICLEI World Congress 2009)Global Scenario - Energy, (ICLEI World Congress 2009)
Global Scenario - Energy, (ICLEI World Congress 2009)
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
 
Power Sector Report October 2017
Power Sector Report October 2017Power Sector Report October 2017
Power Sector Report October 2017
 
Power Sector Report - February 2019
Power Sector Report - February 2019Power Sector Report - February 2019
Power Sector Report - February 2019
 
2010 11 - Indian Energy Sector by ibef
2010 11 - Indian Energy Sector by ibef2010 11 - Indian Energy Sector by ibef
2010 11 - Indian Energy Sector by ibef
 
indian energy sector overview
indian energy sector overviewindian energy sector overview
indian energy sector overview
 
Power sector in india
Power sector in indiaPower sector in india
Power sector in india
 

Viewers also liked

POWER GENERATION IN INDIA -PVT VS GOVT.
POWER GENERATION IN INDIA -PVT VS GOVT.POWER GENERATION IN INDIA -PVT VS GOVT.
POWER GENERATION IN INDIA -PVT VS GOVT.SHIVAJI CHOUDHURY
 
VALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIA
VALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIAVALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIA
VALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIASCHOLEDGE R&D CENTER
 
Corruption in-india-2010-and-before
Corruption in-india-2010-and-beforeCorruption in-india-2010-and-before
Corruption in-india-2010-and-beforeWhat Truly Happened
 
Generation Y and the new way of working
Generation Y and the new way of workingGeneration Y and the new way of working
Generation Y and the new way of workingJeroen Derynck
 
Second generation reforms in india ver 4
Second generation reforms in india ver 4Second generation reforms in india ver 4
Second generation reforms in india ver 4N V
 
Second generation reforms in india
Second generation reforms  in indiaSecond generation reforms  in india
Second generation reforms in indiaGeorgi Mathew
 
NASA - GenY Perspectives
NASA - GenY PerspectivesNASA - GenY Perspectives
NASA - GenY Perspectivesashwinl
 
Generation of mobile communication systems
Generation of mobile communication systemsGeneration of mobile communication systems
Generation of mobile communication systemsjincy-a
 
The Future Is Here: How Social Affects Lead Generation
The Future Is Here: How Social Affects Lead GenerationThe Future Is Here: How Social Affects Lead Generation
The Future Is Here: How Social Affects Lead GenerationMarketo
 
Meet Generation Z: Forget Everything You Learned About Millennials
Meet Generation Z: Forget Everything You Learned About MillennialsMeet Generation Z: Forget Everything You Learned About Millennials
Meet Generation Z: Forget Everything You Learned About Millennialssparks & honey
 

Viewers also liked (12)

From india to next generation
From india to next generationFrom india to next generation
From india to next generation
 
Power Generation in India
Power Generation in IndiaPower Generation in India
Power Generation in India
 
POWER GENERATION IN INDIA -PVT VS GOVT.
POWER GENERATION IN INDIA -PVT VS GOVT.POWER GENERATION IN INDIA -PVT VS GOVT.
POWER GENERATION IN INDIA -PVT VS GOVT.
 
VALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIA
VALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIAVALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIA
VALUE ADDED TAX AND ITS IMPACT ON REVENUE GENERATION IN INDIA
 
Corruption in-india-2010-and-before
Corruption in-india-2010-and-beforeCorruption in-india-2010-and-before
Corruption in-india-2010-and-before
 
Generation Y and the new way of working
Generation Y and the new way of workingGeneration Y and the new way of working
Generation Y and the new way of working
 
Second generation reforms in india ver 4
Second generation reforms in india ver 4Second generation reforms in india ver 4
Second generation reforms in india ver 4
 
Second generation reforms in india
Second generation reforms  in indiaSecond generation reforms  in india
Second generation reforms in india
 
NASA - GenY Perspectives
NASA - GenY PerspectivesNASA - GenY Perspectives
NASA - GenY Perspectives
 
Generation of mobile communication systems
Generation of mobile communication systemsGeneration of mobile communication systems
Generation of mobile communication systems
 
The Future Is Here: How Social Affects Lead Generation
The Future Is Here: How Social Affects Lead GenerationThe Future Is Here: How Social Affects Lead Generation
The Future Is Here: How Social Affects Lead Generation
 
Meet Generation Z: Forget Everything You Learned About Millennials
Meet Generation Z: Forget Everything You Learned About MillennialsMeet Generation Z: Forget Everything You Learned About Millennials
Meet Generation Z: Forget Everything You Learned About Millennials
 

Similar to Renewable Energy & Alternative Technologies for Rural India

Expert Speak_Coal_Gurpreet Chugh
Expert Speak_Coal_Gurpreet ChughExpert Speak_Coal_Gurpreet Chugh
Expert Speak_Coal_Gurpreet ChughAshish Singla
 
Energy security and environmental concerns: By Chandrabhushan
Energy security and environmental concerns: By ChandrabhushanEnergy security and environmental concerns: By Chandrabhushan
Energy security and environmental concerns: By Chandrabhushanbmbks321
 
Renewable energy - India- future
Renewable energy - India- futureRenewable energy - India- future
Renewable energy - India- futureH Janardan Prabhu
 
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...IRJET Journal
 
Energy Management andLecture 2 (1).pptx
Energy Management andLecture 2 (1).pptxEnergy Management andLecture 2 (1).pptx
Energy Management andLecture 2 (1).pptxMuhammadAdeelJamil
 
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...Ajjay Kumar Gupta
 
CEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdf
CEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdfCEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdf
CEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdfRajneesh Katoch
 
Indian future of Renewable energy
Indian future of Renewable energyIndian future of Renewable energy
Indian future of Renewable energyH Janardan Prabhu
 
Modern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis IndiaModern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis IndiaAdityaDesai77
 
Hydropower in-india-key-enablers-for-better-tomorrow
Hydropower in-india-key-enablers-for-better-tomorrowHydropower in-india-key-enablers-for-better-tomorrow
Hydropower in-india-key-enablers-for-better-tomorrowPriya Zadu
 
Milan event presentation
Milan event presentationMilan event presentation
Milan event presentationEAI
 
AMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn India
AMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn IndiaAMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn India
AMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn IndiaAkhilesh Mishra
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET Journal
 
Analytical study of the scope of nuclear energy in indian energy scenario
Analytical study of the scope of nuclear energy in indian energy scenarioAnalytical study of the scope of nuclear energy in indian energy scenario
Analytical study of the scope of nuclear energy in indian energy scenarioIAEME Publication
 
Integrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platformIntegrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platformFarhan Beg
 
AMA - Final Project Report1 dtd 20-06-2015
AMA - Final Project Report1 dtd 20-06-2015AMA - Final Project Report1 dtd 20-06-2015
AMA - Final Project Report1 dtd 20-06-2015Dhiren Patel
 

Similar to Renewable Energy & Alternative Technologies for Rural India (20)

Expert Speak_Coal_Gurpreet Chugh
Expert Speak_Coal_Gurpreet ChughExpert Speak_Coal_Gurpreet Chugh
Expert Speak_Coal_Gurpreet Chugh
 
Energy security and environmental concerns: By Chandrabhushan
Energy security and environmental concerns: By ChandrabhushanEnergy security and environmental concerns: By Chandrabhushan
Energy security and environmental concerns: By Chandrabhushan
 
CII-PWC report: Round the Clock Power Supply
CII-PWC report: Round the Clock Power SupplyCII-PWC report: Round the Clock Power Supply
CII-PWC report: Round the Clock Power Supply
 
Renewable energy - India- future
Renewable energy - India- futureRenewable energy - India- future
Renewable energy - India- future
 
Blue Crude 19-2
Blue Crude 19-2Blue Crude 19-2
Blue Crude 19-2
 
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
 
Energy Management andLecture 2 (1).pptx
Energy Management andLecture 2 (1).pptxEnergy Management andLecture 2 (1).pptx
Energy Management andLecture 2 (1).pptx
 
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
Business Opportunities in Energy Sector. Business Ideas in Power Sector Proje...
 
CEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdf
CEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdfCEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdf
CEEW-A-Green-Hydrogen-Economy-for-India-14Dec20.pdf
 
Indian future of Renewable energy
Indian future of Renewable energyIndian future of Renewable energy
Indian future of Renewable energy
 
Modern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis IndiaModern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis India
 
Hydropower in-india-key-enablers-for-better-tomorrow
Hydropower in-india-key-enablers-for-better-tomorrowHydropower in-india-key-enablers-for-better-tomorrow
Hydropower in-india-key-enablers-for-better-tomorrow
 
Milan event presentation
Milan event presentationMilan event presentation
Milan event presentation
 
AMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn India
AMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn IndiaAMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn India
AMAZING CHAMPIONS OF ENERGY ACE Case Study Submitted to Cairn India
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in India
 
11v3 ch10
11v3 ch1011v3 ch10
11v3 ch10
 
Energy
EnergyEnergy
Energy
 
Analytical study of the scope of nuclear energy in indian energy scenario
Analytical study of the scope of nuclear energy in indian energy scenarioAnalytical study of the scope of nuclear energy in indian energy scenario
Analytical study of the scope of nuclear energy in indian energy scenario
 
Integrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platformIntegrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platform
 
AMA - Final Project Report1 dtd 20-06-2015
AMA - Final Project Report1 dtd 20-06-2015AMA - Final Project Report1 dtd 20-06-2015
AMA - Final Project Report1 dtd 20-06-2015
 

More from Shantanu Basu

Transformation of farmers agitation 2021 in India
Transformation of farmers agitation 2021 in IndiaTransformation of farmers agitation 2021 in India
Transformation of farmers agitation 2021 in IndiaShantanu Basu
 
War Clouds gather on India's horizon
War Clouds gather on India's horizonWar Clouds gather on India's horizon
War Clouds gather on India's horizonShantanu Basu
 
Red challenges to Biden's blue presidency
Red challenges to Biden's blue presidencyRed challenges to Biden's blue presidency
Red challenges to Biden's blue presidencyShantanu Basu
 
War Clouds on India's Horizon
War Clouds on India's HorizonWar Clouds on India's Horizon
War Clouds on India's HorizonShantanu Basu
 
Red challenges to biden's blue presidency
Red challenges to biden's blue presidencyRed challenges to biden's blue presidency
Red challenges to biden's blue presidencyShantanu Basu
 
India's fiscal deficit nightmare 2020 21
India's fiscal deficit nightmare 2020 21India's fiscal deficit nightmare 2020 21
India's fiscal deficit nightmare 2020 21Shantanu Basu
 
One Dimension of the Post-SARS-2 world
One Dimension of the Post-SARS-2 worldOne Dimension of the Post-SARS-2 world
One Dimension of the Post-SARS-2 worldShantanu Basu
 
Redefining nationalism in India
Redefining nationalism in IndiaRedefining nationalism in India
Redefining nationalism in IndiaShantanu Basu
 
India's Public Finances are in Shambles
India's Public Finances are in ShamblesIndia's Public Finances are in Shambles
India's Public Finances are in ShamblesShantanu Basu
 
Should India sell sovereign bonds?
Should India sell sovereign bonds?Should India sell sovereign bonds?
Should India sell sovereign bonds?Shantanu Basu
 
Limitations of Lock Down in India
Limitations of Lock Down in IndiaLimitations of Lock Down in India
Limitations of Lock Down in IndiaShantanu Basu
 
India sovereign bonds 27072019
India sovereign bonds 27072019India sovereign bonds 27072019
India sovereign bonds 27072019Shantanu Basu
 
Revocation of Art. 370 - The Ultimate Victory?
Revocation of Art. 370 - The Ultimate Victory?Revocation of Art. 370 - The Ultimate Victory?
Revocation of Art. 370 - The Ultimate Victory?Shantanu Basu
 
Dance of democracy or descent into mockocracy
Dance of democracy or descent into mockocracyDance of democracy or descent into mockocracy
Dance of democracy or descent into mockocracyShantanu Basu
 
Redefining Nationalism
Redefining NationalismRedefining Nationalism
Redefining NationalismShantanu Basu
 
Redefining Nationalism in India
Redefining Nationalism in IndiaRedefining Nationalism in India
Redefining Nationalism in IndiaShantanu Basu
 
The Modi Adani nexus
The Modi Adani nexusThe Modi Adani nexus
The Modi Adani nexusShantanu Basu
 
The Congress propose Nyaya
The Congress propose NyayaThe Congress propose Nyaya
The Congress propose NyayaShantanu Basu
 
Ten takeaways from india state assembly elections 2018
Ten takeaways from india state assembly elections 2018Ten takeaways from india state assembly elections 2018
Ten takeaways from india state assembly elections 2018Shantanu Basu
 
Telecom Revolution, Governnace and Elections in India
Telecom Revolution, Governnace and Elections in IndiaTelecom Revolution, Governnace and Elections in India
Telecom Revolution, Governnace and Elections in IndiaShantanu Basu
 

More from Shantanu Basu (20)

Transformation of farmers agitation 2021 in India
Transformation of farmers agitation 2021 in IndiaTransformation of farmers agitation 2021 in India
Transformation of farmers agitation 2021 in India
 
War Clouds gather on India's horizon
War Clouds gather on India's horizonWar Clouds gather on India's horizon
War Clouds gather on India's horizon
 
Red challenges to Biden's blue presidency
Red challenges to Biden's blue presidencyRed challenges to Biden's blue presidency
Red challenges to Biden's blue presidency
 
War Clouds on India's Horizon
War Clouds on India's HorizonWar Clouds on India's Horizon
War Clouds on India's Horizon
 
Red challenges to biden's blue presidency
Red challenges to biden's blue presidencyRed challenges to biden's blue presidency
Red challenges to biden's blue presidency
 
India's fiscal deficit nightmare 2020 21
India's fiscal deficit nightmare 2020 21India's fiscal deficit nightmare 2020 21
India's fiscal deficit nightmare 2020 21
 
One Dimension of the Post-SARS-2 world
One Dimension of the Post-SARS-2 worldOne Dimension of the Post-SARS-2 world
One Dimension of the Post-SARS-2 world
 
Redefining nationalism in India
Redefining nationalism in IndiaRedefining nationalism in India
Redefining nationalism in India
 
India's Public Finances are in Shambles
India's Public Finances are in ShamblesIndia's Public Finances are in Shambles
India's Public Finances are in Shambles
 
Should India sell sovereign bonds?
Should India sell sovereign bonds?Should India sell sovereign bonds?
Should India sell sovereign bonds?
 
Limitations of Lock Down in India
Limitations of Lock Down in IndiaLimitations of Lock Down in India
Limitations of Lock Down in India
 
India sovereign bonds 27072019
India sovereign bonds 27072019India sovereign bonds 27072019
India sovereign bonds 27072019
 
Revocation of Art. 370 - The Ultimate Victory?
Revocation of Art. 370 - The Ultimate Victory?Revocation of Art. 370 - The Ultimate Victory?
Revocation of Art. 370 - The Ultimate Victory?
 
Dance of democracy or descent into mockocracy
Dance of democracy or descent into mockocracyDance of democracy or descent into mockocracy
Dance of democracy or descent into mockocracy
 
Redefining Nationalism
Redefining NationalismRedefining Nationalism
Redefining Nationalism
 
Redefining Nationalism in India
Redefining Nationalism in IndiaRedefining Nationalism in India
Redefining Nationalism in India
 
The Modi Adani nexus
The Modi Adani nexusThe Modi Adani nexus
The Modi Adani nexus
 
The Congress propose Nyaya
The Congress propose NyayaThe Congress propose Nyaya
The Congress propose Nyaya
 
Ten takeaways from india state assembly elections 2018
Ten takeaways from india state assembly elections 2018Ten takeaways from india state assembly elections 2018
Ten takeaways from india state assembly elections 2018
 
Telecom Revolution, Governnace and Elections in India
Telecom Revolution, Governnace and Elections in IndiaTelecom Revolution, Governnace and Elections in India
Telecom Revolution, Governnace and Elections in India
 

Recently uploaded

VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...Suhani Kapoor
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escortsaditipandeya
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.Christina Parmionova
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceHigh Profile Call Girls
 
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Recently uploaded (20)

VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
 
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Sanghavi ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
 

Renewable Energy & Alternative Technologies for Rural India

  • 1.
  • 2. Installed Power Generation in India: 2013 http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Indian-installed-power-generation-capacity-in-2013.jpg 68% generation anti-green & hazardous for human health
  • 3. India’s Global Statistics: 2011 http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Comparison-of-key-energy-statistics-for-select-countries.jpg
  • 4. Operating Parameters for a typical 210 MW Coal-fired Power Plant in India http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Operating-parameters.jpg
  • 5. Fossil Fuel Production & Reserves in India http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Fossil-fuel-production-and-reserves-in-India.jpg
  • 6. Comparison of Centralized Electricity Generation Options for India http://www.worldcoal.org/extract/wp-content/uploads/2014/05/Comparison-of-centralized-electricity-generation-options-for-India.jpg
  • 7. Projected Growth of TPPs in India till 2030 - I http://www.urbanemissions.info/images/stories/Air%20Pollution%20from %20India%20Coal%20TPPs%20-%20Coal%20Power%20Expansion.jpg
  • 8. Projected Growth of TPPs in India till 2030 - III  Total coal consumption is estimated to increase 2-3 times from 660 million tons/year to 1800 million tons/year; accordingly the CO2 emissions from 1,590 million tons/year to 4,320 million tons/year  PM, SO2, and NOx emissions will at least double in the same period. Most of the planned plants are supercritical- and ultra- TPPs, which tend to utilize less coal per MWh of electricity generated  With no emission regulations in place for SO2 and NOx, these are assumed uncontrolled and allowed to release through the elevated stacks for dispersion  100% increase in health impacts - The total premature mortality due to the emissions from coal-fired TPPs is expected to grow 2-3 times reaching 186,500 to 229,500 annually in 2030. Asthma cases associated with coal-fired TPP emissions will grow to 42.7 million by 2030  Limited emission standards for power plants - India currently has no standards for either SO2 or NOx both of which drive a large portion of the estimated these health impacts – in the form of secondary sulphates and secondary nitrates. http://www.urbanemissions.info/india-power-plants
  • 9. Projected Growth of TPPs in India till 2030 - IV  Set emission standards  Mandate FGD at the plant level  Practice rigorous monitoring  Ensure transparency  Improve EIA  Large enforcement /redesign costs http://www.urbanemissions.info/india-power-plants
  • 10. Shifting Emphasis to Renewable Energy  Over the last 40 years thermal generation has increased to more than 70%  Given the difficulty of constructing large hydro projects, its share is unlikely to increase in the future  Nuclear installed capacity is projected to increase to about 69 GW (under the most optimistic scenario) from the existing base of about 5 GW  Share of coal in the electricity generation mix is likely to range from 50 – 60% in 2035  Scenario whereby India reduces the coal mix to 40% is considered as the highest possible reduction in coal usage would imply a 22% share of renewable energy in the electricity generation mix  Even with this high renewable share, the coal installed capacity must grow to 270 GW by 2035  More likely estimate of installed coal-based power capacity is 340 GW (50% share) in 2035, which represents significant growth from the existing installed capacity of 132 GW in 2013 (i.e., growth rate of 4.4% per year). http://www.worldcoal.org/extract/coal-based-electricity-generation-in-india-3700/
  • 11. The Rising Health Hazard from TPPs till 2030 - I http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%2 0Coal%20TPPs%20-%20PM%20and%20SO2%20pollution%20through%202030.jpg
  • 12. The Rising Health Hazard from TPPs till 2030 - II Debi Goenka & Sarath Guttikunda, Coal Kills An Assessment of Death and Disease caused by India’s Dirtiest Energy, Urban Emissions & Greenpeace India, 2014, p. 7 Largest impact:  Delhi  Haryana  Maharashtra  Madhya Pradesh  Chhattisgarh  Indo-Gangetic Plain  Central-East India
  • 13. Health Impact of Coal-Based Power Generation - I http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPPs%20- %20Population%20Weighted%20PM2.5.jpg
  • 14. Health Impact of Coal-Based Power Generation - II http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPPs%20- %20Anticipated%20Health%20Impacts.jpg
  • 15. Health Impact of Coal-Based Power Generation - III http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPPs%20- %20Benefits%20of%20FGD.jpg
  • 16. Health Impact of Coal-Based Power Generation - IV http://www.urbanemissions.info/images/stories/Air%20Pollution%20from%20India%20Coal%20TPP s%20-%20Health%20Impacts%20by%20State.jpg
  • 17. Health Impact of Coal-Based Power Generation - V Effect Health Impacts (units) Impact Cost Total Premature Mortality 80000-115000 INR 16-23,000 crore (USD 3.3-4.6 b) Child Mortality (<5 yrs.) 10000 INR 2100 crore (USD 420 m) Respiratory Symptoms 625 million INR 6200 crore (USD 1.2 b) Chronic Bronchitis 170000 INR 900 (USD 170 m) Chest Discomforts 8.4 million INR 170 crore (USD 35 m) Asthma Attacks 20.9 million INR 2100 crore (USD 420 m) Emergency room visits 900000 INR 320 crore (USD 60 m) Restricted Activity Days 160 million INR 8000 crore (USD 1.60 b) Sarath K. Guttikunda & Puja Jawahar: Atmospheric emissions and pollution from the coal-fired thermal power plants in India, Atmospheric Environment 92 (2014) 449-460, Elseiver, 2014 Debi Goenka & Sarath Guttikunda, Coal Kills An Assessment of Death and Disease caused by India’s Dirtiest Energy, Urban Emissions & Greenpeace India, 2014
  • 18. Health Impact of Coal-Based Power Generation - VI Debi Goenka & Sarath Guttikunda, Coal Kills An Assessment of Death and Disease caused by India’s Dirtiest Energy, Urban Emissions & Greenpeace India, 2014, p. 4 Health impacts resulting in premature deaths include  Chronic obstructive pulmonary disease  Lower respiratory infections  Cerebrovascular disease  Ischemic heart disease  Cancers of trachea, bronchitis, and lung  Systemic inflammation  Accelerated atherosclerosis  Altered cardiac function
  • 19. Should India Depend on Coal?  Coal is probably the least expensive fossil fuel for power generation or for industrial use based on the cost per unit energy content in India  The price of coal is on the order of INR170/GJ (US$3.2/GJ) as compared to INR1000/GJ for fuel oil (US$20/GJ) or INR240/GJ (US$4.8/ GJ) for natural gas  Share of imports in the Indian energy supply mix has been increasing over the last two decades. In 2012 energy imports accounted for about 26% of the total primary energy supply, mainly due to oil imports  India imported about 124 million tons of crude oil and about 23 million tons of petroleum products with exports of about 41 million tons of petroleum products in 2010  India’s oil production has been nearly stagnant at about 33–38 million tons annually  Foreign exchange rate fluctuation (devaluation of the rupee) results in a major impact on the economy with an increase in oil prices and resultant inflationary pressure (in 2013 the $-rupee exchange rate increased from 50INR/US$ to 64INR/US$). http://www.worldcoal.org/extract/coal-based-electricity-generation-in-india-3700/
  • 22. Grass, Bamboo. Thatch, Wood, Mud 21% Plastic, Polythene 1% Tiles 30% Slate 1% GI, Metal, AC sheets 12% Brick 6% Stone 7% Concrete 21% Other Material 1%
  • 23.
  • 24. 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1 2 3 4 5 6 7 100 346 728 1419 2995 6642 15461 25 87 182 355 749 1661 3865 1 Average Population/village Average no. of households @ 4 persons/family unit
  • 25. The Costs of Renewable Energy  At current costs this would involve an initial investment of 8 – 8.5 times the investment required by coal or more than 90% of the existing total central government outlay  Hence in the next 25–30 years coal is likely to remain the main source of electricity supply for India, even though its percentage share in the mix may decrease. http://www.worldcoal.org/extract/coal-based-electricity-generation-in-india-3700/
  • 26. Grid-Linked v. Grid-Neutral Solar Energy Plusses of Grid-Linked  Availability for all consumers  Standard Tariffs fixed by SERC  Economy of scale?  Standard O&M procedures  Complex O&M Minuses of Grid-Linked  Variable load affecting availability  High-tension consumers in vicinity affect availability  Longer breakdown restoration Plusses of Grid-Neutral  Assured availability for local consumers  Variable by local need & time  High-tension consumers do not affect quality & availability  Does not need expensive connectivity to grid  Speedy breakdown restoration Minuses of Grid-Neutral  Economy of scale?  Local community land availability and willingness
  • 27.  Nearly half of India’s rural population resides in 115,080 villages with population more than 2,000 but less than 10,000  Highest 34.64% villages comprise population range of 2000-4999  Villages becoming larger in the population size 1000- 1999, 2000 - 4999, 5000 - 9999 and 10000+  Decrease in number of villages in the 500 and 500 – 999 population ranges
  • 28. AlternativeEnergy All Villages 2000-10000 2000-4999 Minority Villages SP/BE-based Meat Cold Storage Containers Prefab animal skin-based micro- industry SC/ST Villages SP/BE-based Cane, jute, micro- industry Cold Storage Containers Urban Slums SP-based Prefab Homes Water & Waste Mgt. Homeless SP-based Prefab Homes Water & Waste Mgt. All habitations within 100 km radius of all TPPs SP/BE-based PHCs networked with State MCs E-Consult ITES solution
  • 29. State Health Mobile Clinics Mobile OTs Telemedicine VSAT connectivity PHCs Education Mobile e-libraries Internet Access Vans Adult Literacy Media Vans Mobile Classrooms Extension Services Mobile Agri-labs Mobile Agri Demo Vans Mobile Fertilizer Sale Vans Mobile Post Offices Mobile PSB branch Mobile RRBs
  • 30. State Communications Mobile Entertainment Mobile Community TV/Radio Broadcast Center Mobile Telephone Exchange Scheme Monitoring & Evaluation In situ survey & online reporting Vans Mobile QA Labs Mobile Evaluation Teams Mobile QA Community Publicity Vans Financial Services VSAT-linked terminals for Cash Deposit savings & Purchase of Small Savings Schemes, etc. VSAT-linked weather, agricultural, etc. info terminals
  • 31. State Skills Development Mobile Classrooms Mobile Demo Trailers Prefab Assembly Centers Ready-mades, metal fabrication, etc. Bamboo & cane furniture manufacturing, weaving jute products, etc. Repair and O&M of SP/BE systems, DG sets, telephone systems, TVs, local energy grid, etc.
  • 34. GroupCEO Ex. Secy. Director (Consulting) Director (Waste Mgt.) Director (Water Mgt.) Director (ITES) Director (Security) Director (Services) Director (Prefab)
  • 35. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 36. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 37. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 38. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 39. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 40. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 41. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 42. Client Description of work Completion Cost (in Million INR) Date of commissioning
  • 43. Collaborator Nature of Collaboration Collaborative Turnover (INR in Million) Ongoing Projects (INR in Million)
  • 44. No. of Projects Implemented Cumulative Group Turnover (INR in Million) Share Capital (INR in Million) Paid-up Capital (INR in Million) Net Profit/Loss (INR in Million) Reserves & Surpluses (INR in Million) Fixed Assets (INR in Million) Liabilities (INR in Million) Quick Assets (INR in Million) Contingent Liabilities (INR in Million)
  • 45.
  • 46.
  • 47. State Capital Funds for Development Optimal Cost Benefit Safeguarding Community Health Creating Rural Community Infrastructure Smart & Prosperous Villages Generating Employment & Wealth via Skill Development Curbing Urban Migration Q L I Q L I
  • 48. AlternativeEnergy Solar LED Lighting Community Energy Needs Cold Storages ITES, Media & Communication Drip Irrigation Biomass Community Energy Needs Water & Waste Mgt.
  • 50.  Number of households – 200  Average load of 0.4 KW = total load of 80 KW  Number of pump sets – 50  Average load of 5 HP per pump set = total load of 185 KW  Others (Public Lighting, Commercial, Industrial)– 75 KW  Micro village-level grid  Total Load = 340 KwH
  • 51.  More illumination per INR of investment  Manifold low O&M costs  Manifold more usable life than CFL & incandescent lighting  Casts manifold less load on power generators  Low voltage required reduces demand on generators & makes power delivery and quality reliable and stable  Permits easy mounting on kuchha roof
  • 52.
  • 53.
  • 54.
  • 55.
  • 56. Self charging point-based on rechargeable appliances & lighting apparatus on prepaid meter basis
  • 57. Local grid prepaid metered basis
  • 58. Detail Per Unit Cost for 1500 small communities (4 lights each) Capital Cost of 2KwH solar panels & generator + grid INR 10,00,000 INR 150,00,00,000 Est. Monthly energy bill (on 12 hr daily 7W LED use) INR 20 INR 60,00,000 Monthly revenue earned by local operators less 20% for O&M, 20% R&R and 20% RoI/annum INR 2,400 INR 36,00,000 Add Capital cost for 100 x 15W street lights INR 15,000 INR 225,00,00,000 Add Capital Cost for 200 common utility LEDs for other public spaces INR 40,000 INR 6,00,00,000 Operator’s revenue less 20% O&M, 20% R&R & 20% RoI INR 7,200 INR 1,08,00,000 Total est. capital cost for 30,00,00 families with 50% state capital subsidy + 50% operator share - INR 190,50,00,000 Recurring annual cost to users w/o subsidy INR 300 INR 4,50,000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 225 INR 3,37,500 Payback period without State capital subsidy 11 years 11 years Payback period with 50% State subsidy 5.5 years 5.5 years
  • 59. Detail Per Unit Cost for 1500 small communities (4 lights each) Capital Cost of 2KwH solar panels & generator INR 500000 INR 750000000 Est. Monthly energy bill (on 12 hr daily LED use) INR 50 INR 2000000 Monthly revenue earned by local operators less 20% for O&M INR 40 INR 1600000 Add Capital cost for 100 x 15W street lights INR 15000 INR 2250000000 Add Capital Cost for 200 common utility LEDs for other public spaces INR 5000 INR 1500000000 Operator’s revenue less 20% O&M cost - INR 12160000 Total est. capital cost for 300000 families with 100% state capital subsidy - INR 4500000000 Recurring monthly cost to users w/o subsidy INR 300 INR 90000000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 225 INR 67500000
  • 60. Detail Per Unit Cost for 1500 small communities (4 lights each) Capital Cost of 10 KwH solar panels & generator INR 2000000 INR 3000000000 Est. Monthly energy bill (on 12 hr daily LED, 6 hrs. 3x1 HP pump use, potable water, 4 fans & 2 appliances of 100 W each) INR 2000 INR 600000000 Annual revenue earned by local operators less 20% for O&M + 20% performance bonus INR 40 INR 4320000000 Add Capital cost for 100 x 15W street lights INR 15000 INR 2250000000 Add Capital Cost for 200 common utility LEDs for other public spaces INR 5000 INR 1500000000 Annual operator’s revenue less 20% O&M cost + 2o% performance bonus - INR 108000000 Total est. capital cost for 300000 families with 50% state subsidy + 50% operator share each - INR 3375000000 Gross recurring monthly cost to users w/o subsidy INR 2100 INR 630000000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 1575 INR 472500000 Payback period for State & Private Operator each - 6 years
  • 61. Detail Per Unit Cost for 1500 small communities (4 lights each) Capital Cost of 10 KwH solar panels & generator INR 2000000 INR 3000000000 Est. Monthly energy bill (on 12 hr daily LED, 6 hrs. 3x1 HP pump use, potable water, 4 fans & 2 appliances of 100 W each) INR 2000 INR 600000000 Monthly revenue earned by local operators less 20% for O&M + 20% performance bonus INR 1600 INR 380000000 Add Capital cost for 100 x 15W street lights INR 15000 INR 2250000000 Add Capital Cost for 200 common utility LEDs for other public spaces INR 5000 INR 1500000000 Operator’s revenue less 20% O&M cost - INR 12160000 Total est. capital cost for 300000 families with 100% state subsidy - INR 6750000000 Gross recurring monthly cost to users w/o subsidy INR 2100 INR 630000000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 1575 INR 472500000 Payback period for State (in 2015 INR) - 12 years
  • 62. Detail Per Unit Cost for 1500 small communities (4 lights each) State Government’s share INR 11250 INR 3375000000 Private Operator’s share INR 11250 INR 3375000000 Annual revenue earned by private operators - INR 907200000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 1575 INR 567000000 Payback period for private operator with 50% state subsidy, 20% O&M, 25% commercial revenue and & 25% RoI/annum - 9 years  Prices and tariffs shown are provisional  Sovereign guarantee of State essential for 9 years
  • 63. WaterManagement Use sources within 15 km radius Potable Water Filling Points on prepaid cards Recycled Water for Irrigation & WCs De-ironing Arsenic Removal Ionizing Treat other chemical residues Filtration Public Spaces & Homes
  • 64. Detail Per Unit Cost for 1500 small communities (4 lights each) Capital Cost 2000 LPH with bottling capacity & building & HDPE distribution lines INR 4500000 INR 6750000000 Est. Monthly water & energy bill INR 250 INR 75000000 Payback period without State subsidy - 12 years Payback period with 50% State capital subsidy - 6 years Monthly revenue earned by operators less 20% for O&M & 20% performance bonus INR 150 INR 45000000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 115 INR 33750000  Prices and tariffs shown are provisional  Sovereign Guarantee by State Govt. required
  • 65. Waste Management Mobile Waste Collection Community Water Closets Biogas Generation Home Water Closets Water Recycling Mobile Incineration Energy Generation Saleable By Products Human/Animal Remains Incineration Commercial Animal Skin Recycling
  • 66. Detail Per Unit Cost for 1500 small communities (4 lights each) Capital Cost (incl. D2D collection, incineration & energy generation) INR 2500000 INR 3750000000 Est. Monthly bill INR 1000 INR 300000000 Payback period without State capital subsidy less 20% O&M & 20% performance bonus 13 months 2 years Less 25% obtained monthly by commercial spaces on poles, utility buildings, solar panels, etc. INR 750 INR 225000000 Payback period with 50% State capital subsidy 7 months 1 year  Prices and tariffs shown are provisional  Sovereign Guarantee by State Govt. required
  • 67. Detail Cost/Rent/Year Cost for 1500 small communities Est. capital cost of 25 public toilet units (wet with sewage evacuation for biogas generation) INR 5000000 INR 7500000000 Monthly rental from individual use & pay public toilets INR 75000 INR 112500000 Payback period without State subsidy 6 years 6 years Payback period with 50% State capital subsidy 3 years 3 years Monthly revenue earned by local operators less 20% for O&M & 25% RoI INR 1375 INR 412500000 Payback period for private operator with 50% capital subsidy, 20% O&M and 25% RoI 9 years 9 years  Prices and tariffs shown are provisional  Sovereign Guarantee by State Govt. required
  • 68. PrefabricatedPortableUnits Schools Multipurpose building Covered Auditoria Multipurpose Halls Panchayat HallAuditoria Homes 2-4 rooms & WCs Local Manufacturing Centers Trade-specific Modules Stadia Amphitheatre Daytime Market Evening Cultural Center Family Wellness Center
  • 69. Detail Cost/Rent/Year Cost for 1500 small communities Capital Cost (200x 500 sft each, 3X3000 sft multipurpose halls, one 2000 sft school building, one amphitheater x 3000 sft, one commodity market x 5000 sft, one industrial center x 5000 sft, one public utility building x 2000 sft) @ Rs. 2000/sft INR 250000000 INR 375000000000 Monthly rental from homes INR 250 INR 75000000 Payback period without State subsidy 33 years 33 years Payback period with 50% State capital subsidy 17 years 17 years Monthly revenue earned by local operators less 20% for O&M & 25% RoI INR 1375 INR 412500000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 1031 INR 3093750000 Payback period for private operator with 50% capital subsidy, 20% O&M and 25% RoI - 28 years  Prices and tariffs shown are provisional  Sovereign Guarantee by State Govt. required
  • 70. IT-enabledServices Schools Secure Degree Certificates Secure Mark sheets Commercial Community Media Commercial Radio/Television Family Wellness Centers Electronic patient records Web-based E-Consult with MCs Info Kiosks Birth & Death Registration, Agri, weather, bank, Post Office , railway/bus ticketing
  • 71. IT-enabledServices Water Mgt. Web-based meter reading, prepaid credit purchase Real-time water flow & timing monitoring Waste Mgt. Movement of mobile waste collection & incineration vehicles Energy Generation Mgt. Solar Energy Mgt. Web-based O&M, pre-paid credit purchase, meter reading Umbrella Services Centers Birth & Death Registration, Property Transfer, Agriculture, weather, bank, Post Office , railway/bus ticketing
  • 72. Detail Per Unit Cost for 1500 small communities (4 lights each) 5-year Lease Cost (250 desktops, 50 laser printers, 250 solar UPS, networking, interface with WAN, etc.) INR 5,00,00,000 INR 75,00,00,00,000 Commercial monthly revenue earned by local operators (no cost to user) INR 2,50,000 INR 37,50,00,000 Operator’s revenue less 20% for O&M & 20% uptime incentive INR 1,50,000 INR 22,50,00,000 Less 25% obtained by commercial spaces on poles, utility buildings, solar panels, etc. INR 1,12,500 INR 16,87,50,000 Payback period for operator with 50% capital subsidy, 20% O&M, 20% uptime incentive and 25% RoI 19 years 19 years  Prices and tariffs shown are provisional  Sovereign Guarantee by State Govt. required
  • 73. Asset INR Solar Energy Generation , LED Lighting, Other appliances, etc. (w/o state subsidy) 1575 Potable Water Supply (w/o State subsidy) 115 Prefab Home Rental (w/o State subsidy) 250 ITES (w/o State subsidy) - Subscriber’s Total Monthly Bill INR 1940 Benefits 1.20 million families @ min. 4 heads/family = 4.8 million/48 lakh individuals Cost to State/individual on 50%/100% capital subsidy basis INR 41100/82200 Assets Created: Homes, Public Spaces, 24 x 7 energy, water and waste management, public toilets, ITES, etc. Est. new O&M jobs created @ 50/community = 45000 Total capital value of assets created in 12-18 months: Rs. 41100 crore
  • 74. Solar-powered Cold Storage Containers Horticulture Marine Products Vegetables & fruits Meats Medicines & Vaccines Better prices for produce 22% of veg & fruit worth Rs. 330 billion p.a. lost Biomass Gasifier Energy Generation Waste Mgt. Dr. Amit Kumar: Solar–Biomass Hybrid Cold Storage-cum-Power Generation system for Rural Applications, Energetica India, TERI, 2012, p. 54
  • 75. SP/BE-powered toilets Public Safety Hygiene Dignity of Labor Wet Toilets in Prefab Homes Wet Toilets in Public Spaces Biogas-based Energy Generation Briquette Feedstock for BE generation Crop/Horti Manure
  • 76. SP/BE-powered & Prefab Housed Media Center Education Entertainment Awareness Telephone Exchange – lines on prepaid credit Intercom b/w homes Connectivity to national telecom N/W Community TV station Emergency, Agri, Weather, Commercial Publicity Commercial channels on prepaid credit Community Radio Station Emergency, Agri, Weather, Commercial Publicity etc. Skill Development Center Trained HREmployment
  • 77. Ministry Saving/Surrender (INR in Million) Civil Aviation 1437.72 Commerce 1465.92 Information Technology 305.99 Defense 2769.13 DoNER 1212.48 External Affairs 2602.10 Financial Services 12493.63 Health & Family Welfare 9983.73 Heavy Industry 1847.79 Home Affairs – Police 29992.13 Information & Broadcasting 1893.00 Power 2356.64 Road Transport & Highways 56109.00 Space 10965.71 Andaman & Nicobar Islands 2699.09 Urban Development 9271.77 TOTAL (all Depts/Ministries) 7429458.44 (742945.84 crore)
  • 78. Ministry Saving/Surrender (INR in Million) Assam 46706.18 Rajasthan 15439.51 Madhya Pradesh 82632.84 Maharashtra 98250.88 Uttar Pradesh 40331.59 Himachal Pradesh 1977.69 Gujarat 12428.43 Haryana 6090.44 TOTAL 303857.58 (INR 30385.76 crore)
  • 79. S U S T A I N A B I L I T Y State bears 100% of capital cost Fully utilizes large recurrent capital Savings/Surrenders Private Operator Bears 50% with Sovereign Guarantee Reduces State’s commitment & fuel other areas on identical lines – optimizes application of capital dev. funds Prepaid pay-as-you-go tariff No Pilferage Enables Advance Resource Planning Project’s Cash Flow assured Private Operator collects revenue & uses 25% each for R&R, O&M, grid expansion and annual RoI Localized & Flexible Development
  • 80. I • Refinancing of implementing agencies by FIs II • PPP mode (revenue used for payback on BOOT basis) III • State-funded (Capital) – delayed release of funds – uncertain cash management IV • Diffused multi-agency financing with complicated terms & conditions V • Need for concentrating financing through a single agency/Ministry
  • 81. Direct refinancing of private operators by FIs Implementation, O&M and R&R transferred to private operators against prepaid revenues generated Divert State/Central Capital budgets to refinancing private operators for all infrastructure projects State agencies to monitor O&M and R&R of private operators Prepaid-based tariff collection on pay-as-you-go format – assures cash flow, attracts private/venture capital and improves O&M, R&R & Future System Extension
  • 82. Use of Community Land for Facilities Technology to negate pilferage of energy Internet connectivity Mindset change in subscribers for prepaid tariffs Govt. clearances & policy modifications for refinancing private operators + sovereign guarantee + self-sustaining revenue generation

Editor's Notes

  1. India’s electricity consumption is barely 22% that of China and the world average and 14% that of South Africa’s. In fact, India’s T&D losses have been admitted by India’s Power Minister recently (http://www.ibtimes.co.in/india-loses-23-power-during-td-reveals-piyush-goyal-604472 on Mar 30, 2015). In turn, this causes dependence on diesel gensets, firewood, charcoal, all anti-green fuels that, again, lead to unparalleled health hazards and concomitant losses as shown on a subsequent slide.
  2. TPPs emit hazardous emissions into the air at relatively high temperatures causing multifarious negativity in human and animal health and produce, deforestation, acid rain, poverty and unemployment. Cumulatively, negative costs sustained far outweigh the currently high cost of alternative technologies, particularly energy.
  3. Although natural gas accounts for the bulk of India’s energy sources, yet clean technologies, limited geographical distribution and expensive emission quality control and a relatively weak regulatory mechanism militates against large-scale countrywide adoption. Indian coal is also mostly low-grade with high ash content and relatively low calorific value (causing high fly ash disposal problems). Oil is mostly imported, albeit in a reducing price regime, consequent upon shale oil production in Canada and the US. While oil perhaps has the largest number of profitable by/end-products, yet clean technologies and weak regulatory and enforcement of emissions militate against its large-scale use. Regrettably, R&D into alternative technologies like hydrogen have not gained in strength primarily owing to less than average private participation and initial State sponsorship. Therefore, it is imperative that alternative clean technologies are promoted by the State.
  4. In computing the cost per MW of solar energy, there is no regard for the losses for human health and productivity, apart from rising health problems and recuperative costs directly and indirectly attributable to TPP energy generation. If the costs for such issues were factored into coal, gas and nuclear power, the costs per MW generated wopuld rise manifold while those of green technologies would considerably decline.
  5. Unfortunately, the State has persevered with TPPs as the most economical option of energy. By 20230, the indirect human cost associated with coal-fired TPPs would rise manifold.
  6. There are large costs and unenforceable regulatory laws and rules involved that would raise the costs of coal, gas and oil-fired energy generators.
  7. All estimates that argue in favor of coal-fired TPPs make a case for their perpetuation, notwithstanding high human costs involved. This is when India receives bright sunshine for 8-10 months every year.
  8. By 2030 India would look more like an active smelting plant with its concomitant irreversible failings.
  9. The areas affected are also the granaries of India and major sources of water supply for the nation’s people although these areas account for large human and animal populations.