SlideShare a Scribd company logo
Sneak Peek into Session
Leading Construction Industry to
Lean-Agile (LeAgile) Project
Management
Session Code: NA15AGL01
Suhail Iqbal, PE, PfMP, PgMP, PMP, PMI-PBA, PMI-SP, PMI-RMP, PMI-ACP, CAPM
SysComp International Private Limited, Pakistan.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Objective
To introduce a new concept of Lean-Agile
(LeAgile) Project Management for Construction
Industry.
Not only to highlight the positive need for adoption
of agility in construction but also an attempt to
marry it up with the lean construction.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Questions Addressed
1. What is LeAgile? Does this term exist already or we just
invented it?
2. What is the biggest challenge in introducing agile in
construction industry?
3. How do we propose lean and agile approaches can be used in
construction industry?
4. Is there any existing methodology or approach which closely
resembles the idea of LeAgile in Construction?
5. Will the existence of Lean Construction facilitate the
acceptance of LeAgile Construction?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Question #1
What is LeAgile? Does this term exist
already or we just invented it?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Answer #1: What is LeAgile? Does this
term exist already or we just invented it?
• LeAgile – A combination of Lean and Agile
Methodologies
• Leagile – A term exists since 1999
– Lean and Agile links back to JIT (1960)
– Term LeAgile first used for SCM (1999)
• For Construction
– LeAgile - Never used for construction
– Agile and Lean – first used by ENNOVA (2011)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
History of Lean and Agile
Exhibit 1 – History of Lean and Agile
(Copyright Ennova 2011, Friday, 23 September 2011)
1960 - JIT by Taiichi Ohno 1982 - Lean as a formal approach
1990 - Lean in quality and supply-chain 1993 - Effective scheduling for construction
1998 - Repetitive scheduling method
/ LBMS
1999 – LeAgile for Supply Chain Management
1950 - Line of Balance (LoB), a visual method of construction planning
2000 - Last Planner System
2011 – Agile and Lean for Construction (ENNOVA)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Definitions – Lean is Value
• “Lean is an approach that identifies the value
inherent in specific products, identifies the
value stream for each product, supports the
flow of value, lets the customer pull value from
the producer, and pursues perfection.”
(Karkukly, 2013)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Definitions – Lean
Doing more with less
• “Lean is doing more with less. Use the least
amount of effort, energy, equipment, time, facility
space, materials, and capital – while giving
customers exactly what they want.”
(Womack & Jones, 2008)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Definitions - Agile
• Agility is the ability to both create and respond
to change in order to profit in a turbulent
business environment.
• Agility is the ability to balance flexibility and
stability.
(Highsmith, 2002)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Definitions – LeAgile (Lacher View)
• Lacher and Bodamer (2009)
– Agility in Project Management.
– Agile in the perspective of lean.
• Lacher and Varisco (2008)
– Agile is the implementation of Lean Thinking.
– Lean-Agile is a combination of Lean Thinking and
Agile disciplines.
– Lean is the ‘What’ and Agile is the ‘How’.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
LeAgile Supply Chain Management
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Question #2
What is the biggest challenge in introducing
agile in construction industry?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Answer #2: What is the biggest challenge in
introducing agile in construction industry?
Resistant to change
• Processes and tools are valued more and status quo
maintained.
• Trend for gold-plating and exceeding the basic
specification.
• Contract is the binding force in any construction
projects, not customer.
• Longer phase durations and fixed scope.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Agile Manifesto (2001)
Software Industry
• Individuals and interactions over processes and
tools
• Working software over comprehensive
documentation
• Customer collaboration over contract negotiation
• Responding to change over following a plan
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Agile Manifesto (2001)
• Created for software industry
• Adopted by several other industries
• Possibility for Construction industry
– Change ‘software’ to ‘product’ in 2nd point
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Agile Manifesto – How Can It Apply?
Construction Industry
Individuals and interactions over processes and
tools
• Processes and tools are valued more and status quo
maintained.
• Still Construction industry evolves, innovates and adapt.
• What if we consciously promote creativity
• Give initiatives to team and stakeholders to innovate.
• LBMS where a conventional schedule may not be workable for
all locations, plan separately for each location.
• Start prioritizing individuals and interactions over processes and
tools.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Agile Manifesto – How Can It Apply?
Construction Industry
Working product over comprehensive
documentation.
• Needs a workable product but perfection sought.
• Results in gold-plating and exceeding the basic specification.
• If not for customer’s changing requirement, we are causing
waste and are not even meeting the target of being lean.
• In LP system, the schedule is divided into five layers, only first
being mandatory, and are not detailed or restrictive.
• LPS has already taught us to reduce documentation and take to
the last planner level.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Agile Manifesto – How Can It Apply?
Construction Industry
Customer collaboration over contract negotiation.
• Contract is the binding force in any construction project.
• Engineers will never agree to give priority to customer
collaboration over the contract.
• Contract revisions and changes, anyways, still occur.
• Why can’t we remove this barrier and work as partners?
• In LP system, last planner improves his bottom-level plan due to
feedback of the customer.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Agile Manifesto – How Can It Apply?
Construction Industry
Responding to change over following a plan.
• We must be ready to respond to change as and when it is
needed.
• Make our construction phases smaller in size and iterative in
nature.
• In LP system, Weekly Plans are prepared and collaboration with
customer is promoted.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Question #3
How do we propose lean and agile
approaches can be used in construction
industry?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Answer #3: How do we propose lean and agile
approaches can be used in construction industry?
• Difficult to draw a parallel or clear distinction.
• Most organized and well managed industry
– still causes a lot of waste
– already realised the need to be lean,
• Concept of lean construction is already accepted.
• Clearer objectives and static scope
• Assumed “agile is not for construction”
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
‘Lean’ and ‘Agile’
• ‘Lean’ and ‘Agile’ - two separate approaches
• Some identified relationship
• Parallel development paths
• Some common features and intrusions
• Sometimes mistaken to be the same.
• Both approaches - distinct and unique in purpose
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
‘Lean’ and ‘Agile’ – What to do?
• Find a way how to best utilize them together.
• Find the similarities and differences
• Try to have the best of the both worlds.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
‘Lean’ and ‘Agile’ - LeAgile
• If lean and agile can work together in software
and other industries, then why not construction?
• Construction projects may be few but command
larger budgets.
• Greatest benefits to reap if agile and lean can
work for them together.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
‘Lean’ and ‘Agile’ – Diverse Views
• Many researchers and diverse views
– Agile - as a way to do things within the overall
perspective of lean
– Some debate they cannot work together at all. We
will try to establish
• Reinforce the commonalities of both and
• Smoothen out the jagged edges
• Present a fit for construction industry.
• Marriage of convenience - LeAgile
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Question #4
Is there any existing methodology or
approach which closely resembles the idea
of LeAgile in Construction?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Answer #4: Is there any existing methodology
or approach which closely resembles the idea of
LeAgile in Construction?
• Difficult to draw a parallel or clear distinction.
• Most organized and well managed industry
– still causes a lot of waste
– already realised the need to be lean,
• Concept of lean construction is already accepted.
• Clearer objectives and static scope
• Assumed “agile is not for construction”
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
‘LPS’ and ‘LBMS’
Common Characteristics
• Both systems are lean by nature
• Both focus on decreasing waste and increasing
productivity.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
‘LPS’ and ‘Agile’
Similarities
• LPS uses approach similar to agile
• Last Planner is the person actually doing the
work or the lowest level supervisor.
• The planning is not centric and involvement of
this last planner is essential.
• This makes the planning a collaborative effort
and better commitments are achieved.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
‘LBMS’ and ‘Agile’
Similarities
• LBMS is more of a technical system in which
work flow lines are created for different locations
• Overall plan may be governed by traditional CPM
and PERT methods.
• LBMS makes the buffers of critical chain explicit
• LBMS forecasts future performance based on
statistical projections.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Last Planner System - Phases
Exhibit 3 – Scheduling Levels in Last Planner
(Copyright Ennova 2011, Friday, 23 September 2011)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Last Planner in Construction
Exhibit 4 – Last Planner in Construction Management
(Copyright Ennova 2011, Friday, 23 September 2011)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Question #5
Will the existence of Lean Construction
facilitate the acceptance of LeAgile
Construction?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Answer #5: Will the existence of Lean
Construction facilitate the acceptance of LeAgile
Construction?
• No proposed application exists so far
• Discussion to stir up minds to the possibility of
LeAgile
• Some research and white papers exist but none
for construction.
• Lean Construction does exist.
• LeAgility in Construction is not a far-fetched idea.
• LPS and LBMS already hold the key to LeAgility.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Expected Benefits of LeAgility
• Opposition expected from construction industry
• Opening the floodgates of new possibilities
• Reduce waste in construction projects
• Make them much more efficient and profitable
• Can be fast and flexile
• Saving enormously on time and cost
• Satisfy our stakeholders and
• Be able to sell more
• Making even more profits
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only.
Leagile Construction System (LCS)
37
• Name: Suhail Iqbal
• Web: http://www.syscompk.com
• Email: suhail@syscompk.com
• Twitter: http://twitter.com/shewal786
• LinkedIn: http://pk.linkedin.com/in/suhail
• Facebook: http://www.facebook.com/suhail.iqbal.54
• Google+: http://plus.google.com/u/0/10456095253363094682
9/posts
Thank you!
To rate my session
Click on my session and
answer the survey questions

More Related Content

What's hot

Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?
Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?
Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?
Edunomica
 
Beyond Scrum and SAFe
Beyond Scrum and SAFeBeyond Scrum and SAFe
Beyond Scrum and SAFe
Washington DC Scrum User Group
 
Does the Cloud Change Anything? What can be learned from the Changing Enterpr...
Does the Cloud Change Anything? What can be learned from the Changing Enterpr...Does the Cloud Change Anything? What can be learned from the Changing Enterpr...
Does the Cloud Change Anything? What can be learned from the Changing Enterpr...Flexera
 
3 things about EA that TOGAF doesnt say
3 things about EA that TOGAF doesnt say3 things about EA that TOGAF doesnt say
3 things about EA that TOGAF doesnt say
cccamericas
 
Global-i Capabilities Presentation
Global-i Capabilities PresentationGlobal-i Capabilities Presentation
Global-i Capabilities Presentation
daveroy
 
Developing an Agile Schedule in Microsoft Project - It is Possible!
Developing an Agile Schedule in Microsoft Project - It is Possible!Developing an Agile Schedule in Microsoft Project - It is Possible!
Developing an Agile Schedule in Microsoft Project - It is Possible!
International Institute for Learning
 
Rejuvenating Architecture Governance in a Redesigned Organization
Rejuvenating Architecture Governance in a Redesigned OrganizationRejuvenating Architecture Governance in a Redesigned Organization
Rejuvenating Architecture Governance in a Redesigned OrganizationIver Band
 
Agile Enterprise Architecture in Government Business Transformations (Capgemi...
Agile Enterprise Architecture in Government Business Transformations (Capgemi...Agile Enterprise Architecture in Government Business Transformations (Capgemi...
Agile Enterprise Architecture in Government Business Transformations (Capgemi...
jensenwaud
 
Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...
Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...
Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...
Iver Band
 
The Good Shepherd - the Role of BAs in Agile
The Good Shepherd - the Role of BAs in AgileThe Good Shepherd - the Role of BAs in Agile
The Good Shepherd - the Role of BAs in Agile
Dave Sharrock
 
Modeling TOGAF with ArchiMate
Modeling TOGAF with ArchiMateModeling TOGAF with ArchiMate
Modeling TOGAF with ArchiMate
Iver Band
 
Implementing ACORD with ArchiMate
Implementing ACORD with ArchiMateImplementing ACORD with ArchiMate
Implementing ACORD with ArchiMate
Iver Band
 
Business Agility is the new competitive advantage!
Business Agility is the new competitive advantage!Business Agility is the new competitive advantage!
Business Agility is the new competitive advantage!
NUS-ISS
 
Extracting archimate views from custom ontological ea models
Extracting archimate views from custom ontological ea modelsExtracting archimate views from custom ontological ea models
Extracting archimate views from custom ontological ea modelsMatteo Busanelli
 
Digiblu strategy and approach - Fusion Wealth
Digiblu strategy and approach - Fusion WealthDigiblu strategy and approach - Fusion Wealth
Digiblu strategy and approach - Fusion Wealth
Tom Carr
 
How «Toyota Way» principles guided the architecture of Toyota’s product datah...
How «Toyota Way» principles guided the architecture of Toyota’s product datah...How «Toyota Way» principles guided the architecture of Toyota’s product datah...
How «Toyota Way» principles guided the architecture of Toyota’s product datah...
Institut Lean France
 
Enterprise Architecture with the Zachman Framework and the Archimate Language
Enterprise Architecture with the Zachman Framework and the Archimate LanguageEnterprise Architecture with the Zachman Framework and the Archimate Language
Enterprise Architecture with the Zachman Framework and the Archimate Language
Iver Band
 
Enterprise communication using archiMate
Enterprise communication using archiMateEnterprise communication using archiMate
Enterprise communication using archiMateLouw Labuschagne
 
Approach and strategy - fusion
Approach and strategy - fusionApproach and strategy - fusion
Approach and strategy - fusion
Tom Carr
 

What's hot (20)

Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?
Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?
Sunil Mundra: Fаst-paced Change-Threat Or Opportunity?
 
Beyond Scrum and SAFe
Beyond Scrum and SAFeBeyond Scrum and SAFe
Beyond Scrum and SAFe
 
Does the Cloud Change Anything? What can be learned from the Changing Enterpr...
Does the Cloud Change Anything? What can be learned from the Changing Enterpr...Does the Cloud Change Anything? What can be learned from the Changing Enterpr...
Does the Cloud Change Anything? What can be learned from the Changing Enterpr...
 
3 things about EA that TOGAF doesnt say
3 things about EA that TOGAF doesnt say3 things about EA that TOGAF doesnt say
3 things about EA that TOGAF doesnt say
 
Global-i Capabilities Presentation
Global-i Capabilities PresentationGlobal-i Capabilities Presentation
Global-i Capabilities Presentation
 
Developing an Agile Schedule in Microsoft Project - It is Possible!
Developing an Agile Schedule in Microsoft Project - It is Possible!Developing an Agile Schedule in Microsoft Project - It is Possible!
Developing an Agile Schedule in Microsoft Project - It is Possible!
 
Rejuvenating Architecture Governance in a Redesigned Organization
Rejuvenating Architecture Governance in a Redesigned OrganizationRejuvenating Architecture Governance in a Redesigned Organization
Rejuvenating Architecture Governance in a Redesigned Organization
 
Agile Enterprise Architecture in Government Business Transformations (Capgemi...
Agile Enterprise Architecture in Government Business Transformations (Capgemi...Agile Enterprise Architecture in Government Business Transformations (Capgemi...
Agile Enterprise Architecture in Government Business Transformations (Capgemi...
 
Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...
Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...
Modeling and Evolving a Web Portal with the TOGAF Framework and the ArchiMate...
 
The Good Shepherd - the Role of BAs in Agile
The Good Shepherd - the Role of BAs in AgileThe Good Shepherd - the Role of BAs in Agile
The Good Shepherd - the Role of BAs in Agile
 
SathyanarayananGururajan
SathyanarayananGururajanSathyanarayananGururajan
SathyanarayananGururajan
 
Modeling TOGAF with ArchiMate
Modeling TOGAF with ArchiMateModeling TOGAF with ArchiMate
Modeling TOGAF with ArchiMate
 
Implementing ACORD with ArchiMate
Implementing ACORD with ArchiMateImplementing ACORD with ArchiMate
Implementing ACORD with ArchiMate
 
Business Agility is the new competitive advantage!
Business Agility is the new competitive advantage!Business Agility is the new competitive advantage!
Business Agility is the new competitive advantage!
 
Extracting archimate views from custom ontological ea models
Extracting archimate views from custom ontological ea modelsExtracting archimate views from custom ontological ea models
Extracting archimate views from custom ontological ea models
 
Digiblu strategy and approach - Fusion Wealth
Digiblu strategy and approach - Fusion WealthDigiblu strategy and approach - Fusion Wealth
Digiblu strategy and approach - Fusion Wealth
 
How «Toyota Way» principles guided the architecture of Toyota’s product datah...
How «Toyota Way» principles guided the architecture of Toyota’s product datah...How «Toyota Way» principles guided the architecture of Toyota’s product datah...
How «Toyota Way» principles guided the architecture of Toyota’s product datah...
 
Enterprise Architecture with the Zachman Framework and the Archimate Language
Enterprise Architecture with the Zachman Framework and the Archimate LanguageEnterprise Architecture with the Zachman Framework and the Archimate Language
Enterprise Architecture with the Zachman Framework and the Archimate Language
 
Enterprise communication using archiMate
Enterprise communication using archiMateEnterprise communication using archiMate
Enterprise communication using archiMate
 
Approach and strategy - fusion
Approach and strategy - fusionApproach and strategy - fusion
Approach and strategy - fusion
 

Similar to Sneak peek na15 agl01 leading construction industry to lean-agile (leagile) project management

PMI Global Congress 2012
PMI Global Congress 2012PMI Global Congress 2012
PMI Global Congress 2012
DC-DinsmoreCompass
 
SMAC and Transforming Innovation
SMAC and Transforming InnovationSMAC and Transforming Innovation
PMI Global Congress North America 2015 - Change the system, not the people.
PMI Global Congress North America 2015 - Change the system, not the people.PMI Global Congress North America 2015 - Change the system, not the people.
PMI Global Congress North America 2015 - Change the system, not the people.
Michal Raczka
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Felipe Moreira
 
Managing an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT programManaging an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT programGottfried Rudorfer
 
An Introduction to Visual Management Systems
An Introduction to Visual Management SystemsAn Introduction to Visual Management Systems
An Introduction to Visual Management SystemsDerek Huether
 
Project management and organizational change management
Project management and organizational change managementProject management and organizational change management
Project management and organizational change managementSusan Boyd
 
PMI Global Congress 2012 Presentation
PMI Global Congress 2012 PresentationPMI Global Congress 2012 Presentation
PMI Global Congress 2012 Presentation
ZahidKhan007
 
Scope: Mastering the Fuzzy Constraint
Scope: Mastering the Fuzzy ConstraintScope: Mastering the Fuzzy Constraint
Scope: Mastering the Fuzzy Constraint
bbigelow
 
DevOps Thinking for the Line of Business
DevOps Thinking for the Line of BusinessDevOps Thinking for the Line of Business
DevOps Thinking for the Line of Business
Sanjeev Sharma
 
PMI-ACP Lesson 01 Nugget 1 Introduction to Agile
PMI-ACP Lesson 01 Nugget 1 Introduction to AgilePMI-ACP Lesson 01 Nugget 1 Introduction to Agile
PMI-ACP Lesson 01 Nugget 1 Introduction to Agile
Thanh Nguyen
 
PMI Auckland 09 May: Agile Overview
PMI Auckland 09 May: Agile OverviewPMI Auckland 09 May: Agile Overview
PMI Auckland 09 May: Agile Overview
Carolyn Sanders
 
Approaches to business architecture
Approaches to business architectureApproaches to business architecture
Approaches to business architecture
Real IRM
 
Approaches to business architecture
Approaches to business architectureApproaches to business architecture
Approaches to business architecture
The Open Group SA
 
Multi Model Performance Improvement
Multi Model Performance ImprovementMulti Model Performance Improvement
Multi Model Performance ImprovementGeorge Brotbeck
 
Risk on complex_projects_project_auditors
Risk on complex_projects_project_auditorsRisk on complex_projects_project_auditors
Risk on complex_projects_project_auditors
Joy Gumz
 
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...Marco Negri, PMP, CBAP, COBIT5
 
IBM Z for the Digital Enterprise 2018 - Automate Delivery Pipeline
IBM Z for the Digital Enterprise 2018 - Automate Delivery PipelineIBM Z for the Digital Enterprise 2018 - Automate Delivery Pipeline
IBM Z for the Digital Enterprise 2018 - Automate Delivery Pipeline
DevOps for Enterprise Systems
 

Similar to Sneak peek na15 agl01 leading construction industry to lean-agile (leagile) project management (20)

PMI Global Congress 2012
PMI Global Congress 2012PMI Global Congress 2012
PMI Global Congress 2012
 
SMAC and Transforming Innovation
SMAC and Transforming InnovationSMAC and Transforming Innovation
SMAC and Transforming Innovation
 
PMI Global Congress North America 2015 - Change the system, not the people.
PMI Global Congress North America 2015 - Change the system, not the people.PMI Global Congress North America 2015 - Change the system, not the people.
PMI Global Congress North America 2015 - Change the system, not the people.
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
 
Managing an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT programManaging an ITIL SaaS implementation IT program
Managing an ITIL SaaS implementation IT program
 
An Introduction to Visual Management Systems
An Introduction to Visual Management SystemsAn Introduction to Visual Management Systems
An Introduction to Visual Management Systems
 
Project management and organizational change management
Project management and organizational change managementProject management and organizational change management
Project management and organizational change management
 
PMI Global Congress 2012 Presentation
PMI Global Congress 2012 PresentationPMI Global Congress 2012 Presentation
PMI Global Congress 2012 Presentation
 
Scope: Mastering the Fuzzy Constraint
Scope: Mastering the Fuzzy ConstraintScope: Mastering the Fuzzy Constraint
Scope: Mastering the Fuzzy Constraint
 
DevOps Thinking for the Line of Business
DevOps Thinking for the Line of BusinessDevOps Thinking for the Line of Business
DevOps Thinking for the Line of Business
 
GOV05-final-ppt
GOV05-final-pptGOV05-final-ppt
GOV05-final-ppt
 
GOV05-final-ppt
GOV05-final-pptGOV05-final-ppt
GOV05-final-ppt
 
PMI-ACP Lesson 01 Nugget 1 Introduction to Agile
PMI-ACP Lesson 01 Nugget 1 Introduction to AgilePMI-ACP Lesson 01 Nugget 1 Introduction to Agile
PMI-ACP Lesson 01 Nugget 1 Introduction to Agile
 
PMI Auckland 09 May: Agile Overview
PMI Auckland 09 May: Agile OverviewPMI Auckland 09 May: Agile Overview
PMI Auckland 09 May: Agile Overview
 
Approaches to business architecture
Approaches to business architectureApproaches to business architecture
Approaches to business architecture
 
Approaches to business architecture
Approaches to business architectureApproaches to business architecture
Approaches to business architecture
 
Multi Model Performance Improvement
Multi Model Performance ImprovementMulti Model Performance Improvement
Multi Model Performance Improvement
 
Risk on complex_projects_project_auditors
Risk on complex_projects_project_auditorsRisk on complex_projects_project_auditors
Risk on complex_projects_project_auditors
 
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...
 
IBM Z for the Digital Enterprise 2018 - Automate Delivery Pipeline
IBM Z for the Digital Enterprise 2018 - Automate Delivery PipelineIBM Z for the Digital Enterprise 2018 - Automate Delivery Pipeline
IBM Z for the Digital Enterprise 2018 - Automate Delivery Pipeline
 

Recently uploaded

在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Protected Workmen required today for growth
Protected Workmen required today for growthProtected Workmen required today for growth
Protected Workmen required today for growth
rivaraj2711
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
Alexey Krivitsky
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
Ram V Chary
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
Jim Smith
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
EUS+ Management & Consulting Excellence
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
tdt5v4b
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
Matthew Sinclair
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
Pinta Partners
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
tdt5v4b
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
A. F. M. Rubayat-Ul Jannat
 

Recently uploaded (20)

在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Protected Workmen required today for growth
Protected Workmen required today for growthProtected Workmen required today for growth
Protected Workmen required today for growth
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
 

Sneak peek na15 agl01 leading construction industry to lean-agile (leagile) project management

  • 1. Sneak Peek into Session Leading Construction Industry to Lean-Agile (LeAgile) Project Management Session Code: NA15AGL01 Suhail Iqbal, PE, PfMP, PgMP, PMP, PMI-PBA, PMI-SP, PMI-RMP, PMI-ACP, CAPM SysComp International Private Limited, Pakistan.
  • 2. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Objective To introduce a new concept of Lean-Agile (LeAgile) Project Management for Construction Industry. Not only to highlight the positive need for adoption of agility in construction but also an attempt to marry it up with the lean construction.
  • 3. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Questions Addressed 1. What is LeAgile? Does this term exist already or we just invented it? 2. What is the biggest challenge in introducing agile in construction industry? 3. How do we propose lean and agile approaches can be used in construction industry? 4. Is there any existing methodology or approach which closely resembles the idea of LeAgile in Construction? 5. Will the existence of Lean Construction facilitate the acceptance of LeAgile Construction?
  • 4. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Question #1 What is LeAgile? Does this term exist already or we just invented it?
  • 5. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Answer #1: What is LeAgile? Does this term exist already or we just invented it? • LeAgile – A combination of Lean and Agile Methodologies • Leagile – A term exists since 1999 – Lean and Agile links back to JIT (1960) – Term LeAgile first used for SCM (1999) • For Construction – LeAgile - Never used for construction – Agile and Lean – first used by ENNOVA (2011)
  • 6. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. History of Lean and Agile Exhibit 1 – History of Lean and Agile (Copyright Ennova 2011, Friday, 23 September 2011) 1960 - JIT by Taiichi Ohno 1982 - Lean as a formal approach 1990 - Lean in quality and supply-chain 1993 - Effective scheduling for construction 1998 - Repetitive scheduling method / LBMS 1999 – LeAgile for Supply Chain Management 1950 - Line of Balance (LoB), a visual method of construction planning 2000 - Last Planner System 2011 – Agile and Lean for Construction (ENNOVA)
  • 7. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Definitions – Lean is Value • “Lean is an approach that identifies the value inherent in specific products, identifies the value stream for each product, supports the flow of value, lets the customer pull value from the producer, and pursues perfection.” (Karkukly, 2013)
  • 8. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Definitions – Lean Doing more with less • “Lean is doing more with less. Use the least amount of effort, energy, equipment, time, facility space, materials, and capital – while giving customers exactly what they want.” (Womack & Jones, 2008)
  • 9. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Definitions - Agile • Agility is the ability to both create and respond to change in order to profit in a turbulent business environment. • Agility is the ability to balance flexibility and stability. (Highsmith, 2002)
  • 10. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Definitions – LeAgile (Lacher View) • Lacher and Bodamer (2009) – Agility in Project Management. – Agile in the perspective of lean. • Lacher and Varisco (2008) – Agile is the implementation of Lean Thinking. – Lean-Agile is a combination of Lean Thinking and Agile disciplines. – Lean is the ‘What’ and Agile is the ‘How’.
  • 11. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. LeAgile Supply Chain Management
  • 12. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Question #2 What is the biggest challenge in introducing agile in construction industry?
  • 13. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Answer #2: What is the biggest challenge in introducing agile in construction industry? Resistant to change • Processes and tools are valued more and status quo maintained. • Trend for gold-plating and exceeding the basic specification. • Contract is the binding force in any construction projects, not customer. • Longer phase durations and fixed scope.
  • 14. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Agile Manifesto (2001) Software Industry • Individuals and interactions over processes and tools • Working software over comprehensive documentation • Customer collaboration over contract negotiation • Responding to change over following a plan
  • 15. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Agile Manifesto (2001) • Created for software industry • Adopted by several other industries • Possibility for Construction industry – Change ‘software’ to ‘product’ in 2nd point
  • 16. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Agile Manifesto – How Can It Apply? Construction Industry Individuals and interactions over processes and tools • Processes and tools are valued more and status quo maintained. • Still Construction industry evolves, innovates and adapt. • What if we consciously promote creativity • Give initiatives to team and stakeholders to innovate. • LBMS where a conventional schedule may not be workable for all locations, plan separately for each location. • Start prioritizing individuals and interactions over processes and tools.
  • 17. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Agile Manifesto – How Can It Apply? Construction Industry Working product over comprehensive documentation. • Needs a workable product but perfection sought. • Results in gold-plating and exceeding the basic specification. • If not for customer’s changing requirement, we are causing waste and are not even meeting the target of being lean. • In LP system, the schedule is divided into five layers, only first being mandatory, and are not detailed or restrictive. • LPS has already taught us to reduce documentation and take to the last planner level.
  • 18. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Agile Manifesto – How Can It Apply? Construction Industry Customer collaboration over contract negotiation. • Contract is the binding force in any construction project. • Engineers will never agree to give priority to customer collaboration over the contract. • Contract revisions and changes, anyways, still occur. • Why can’t we remove this barrier and work as partners? • In LP system, last planner improves his bottom-level plan due to feedback of the customer.
  • 19. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Agile Manifesto – How Can It Apply? Construction Industry Responding to change over following a plan. • We must be ready to respond to change as and when it is needed. • Make our construction phases smaller in size and iterative in nature. • In LP system, Weekly Plans are prepared and collaboration with customer is promoted.
  • 20. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Question #3 How do we propose lean and agile approaches can be used in construction industry?
  • 21. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Answer #3: How do we propose lean and agile approaches can be used in construction industry? • Difficult to draw a parallel or clear distinction. • Most organized and well managed industry – still causes a lot of waste – already realised the need to be lean, • Concept of lean construction is already accepted. • Clearer objectives and static scope • Assumed “agile is not for construction”
  • 22. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. ‘Lean’ and ‘Agile’ • ‘Lean’ and ‘Agile’ - two separate approaches • Some identified relationship • Parallel development paths • Some common features and intrusions • Sometimes mistaken to be the same. • Both approaches - distinct and unique in purpose
  • 23. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. ‘Lean’ and ‘Agile’ – What to do? • Find a way how to best utilize them together. • Find the similarities and differences • Try to have the best of the both worlds.
  • 24. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. ‘Lean’ and ‘Agile’ - LeAgile • If lean and agile can work together in software and other industries, then why not construction? • Construction projects may be few but command larger budgets. • Greatest benefits to reap if agile and lean can work for them together.
  • 25. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. ‘Lean’ and ‘Agile’ – Diverse Views • Many researchers and diverse views – Agile - as a way to do things within the overall perspective of lean – Some debate they cannot work together at all. We will try to establish • Reinforce the commonalities of both and • Smoothen out the jagged edges • Present a fit for construction industry. • Marriage of convenience - LeAgile
  • 26. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Question #4 Is there any existing methodology or approach which closely resembles the idea of LeAgile in Construction?
  • 27. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Answer #4: Is there any existing methodology or approach which closely resembles the idea of LeAgile in Construction? • Difficult to draw a parallel or clear distinction. • Most organized and well managed industry – still causes a lot of waste – already realised the need to be lean, • Concept of lean construction is already accepted. • Clearer objectives and static scope • Assumed “agile is not for construction”
  • 28. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. ‘LPS’ and ‘LBMS’ Common Characteristics • Both systems are lean by nature • Both focus on decreasing waste and increasing productivity.
  • 29. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. ‘LPS’ and ‘Agile’ Similarities • LPS uses approach similar to agile • Last Planner is the person actually doing the work or the lowest level supervisor. • The planning is not centric and involvement of this last planner is essential. • This makes the planning a collaborative effort and better commitments are achieved.
  • 30. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. ‘LBMS’ and ‘Agile’ Similarities • LBMS is more of a technical system in which work flow lines are created for different locations • Overall plan may be governed by traditional CPM and PERT methods. • LBMS makes the buffers of critical chain explicit • LBMS forecasts future performance based on statistical projections.
  • 31. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Last Planner System - Phases Exhibit 3 – Scheduling Levels in Last Planner (Copyright Ennova 2011, Friday, 23 September 2011)
  • 32. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Last Planner in Construction Exhibit 4 – Last Planner in Construction Management (Copyright Ennova 2011, Friday, 23 September 2011)
  • 33. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Question #5 Will the existence of Lean Construction facilitate the acceptance of LeAgile Construction?
  • 34. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Answer #5: Will the existence of Lean Construction facilitate the acceptance of LeAgile Construction? • No proposed application exists so far • Discussion to stir up minds to the possibility of LeAgile • Some research and white papers exist but none for construction. • Lean Construction does exist. • LeAgility in Construction is not a far-fetched idea. • LPS and LBMS already hold the key to LeAgility.
  • 35. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Expected Benefits of LeAgility • Opposition expected from construction industry • Opening the floodgates of new possibilities • Reduce waste in construction projects • Make them much more efficient and profitable • Can be fast and flexile • Saving enormously on time and cost • Satisfy our stakeholders and • Be able to sell more • Making even more profits
  • 36. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Permission is granted to PMI for PMI® Marketplace use only. Leagile Construction System (LCS)
  • 37. 37 • Name: Suhail Iqbal • Web: http://www.syscompk.com • Email: suhail@syscompk.com • Twitter: http://twitter.com/shewal786 • LinkedIn: http://pk.linkedin.com/in/suhail • Facebook: http://www.facebook.com/suhail.iqbal.54 • Google+: http://plus.google.com/u/0/10456095253363094682 9/posts Thank you! To rate my session Click on my session and answer the survey questions