SlideShare a Scribd company logo
1 of 12
Download to read offline
Progressive Erection Applied to Box Girder
with Strutted Wing Slab
Koji Osada1
, Taketo Kanamoto1
, Kimito Saito2
, Takahiro Arai2
1 Introduction
The Uchimaki Viaduct is a multi-span
continuous box girder bridge with strutted
wing slabs (photo 1-1). It is erected
progressively by assembling divided parts
of the cross section. The erection of the
central part of the box girder is followed by
the construction of wing slabs.
This paper presents the bridge
technologies applied to progressive erection
of the Uchimaki viaduct. The technologies
include concrete material as well as
machinery for producing and erecting the
precast segments and special form travelers
for constructing the wing slabs.
2 Overview of the project
The Uchimaki viaduct is a multi-span continuous box girder bridge built as a part
of the New Tomei Expressway. The Uchimaki viaduct consists of the eastbound and
westbound bridges, which are constructed in parallel to each other. Both bridges are
around 1 km long (Fig. 2-1). The span length is standardized into approximately 50 m
1
Central Nippon Expressway Co.,LTD., Japan
2
Kajima Corporation, Japan
Photo 1-1:Completion image
Fig 2-1: General view
in 36 of the 42 spans in total.
Span-by-span erection with
precast segments is adopted
because of the sufficient project
length and standardized spans.
The traffic width of the
Uchimaki viaduct is 16.5 m,
which accommodates three traffic
lanes, though many expressways
other than the New Tomei and New Meishin expressways have only two traffic lanes.
Even with three lanes, the weight of the superstructure and the size of the substructure
must be reduced. As a result, diagonal struts supporting the wing slabs are applied to
the Uchimaki viaduct. The diagonal struts reduce the deck slab thickness and the
bottom slab width (Fig 2-2).
Applying span-by-span erection to the box girder with strutted wing slabs, two
erection methodologies were compared under the conditions of this project. As the
first option, precast segments including the entire cross section (hereafter referred as
to ‘whole segment’) are erected. As the other, the cross section is divided into several
parts, which are erected progressively. The precast segments exclude large part of the
wing slabs and diagonal struts (hereafter referred as to ‘core segment’). As a result,
progressive erection with divided parts of cross section was selected.
The decision was made because the progressive erection method was found to be
beneficial in relation to pier segment erection, fabrication of precast segments and
span-by-span erection. In terms of prefabricating segments in particular, it would be
impractical to produce whole segments because the casting yard has limited space.
The progressive erection applied to the Uchimaki viaduct consists of three major
phases (Fig. 2-3). In the first phase, cast-in-situ pier and abutment segments are
erected. In the second phase, precast segments are fabricated and erected. In the third
phase, precast struts are installed and wing slabs are constructed. In the following
section, the erection of whole segments and the progressive erection in each
construction phase are compared. In addition, some features in each construction
phase are introduced.
Fig. 2-2: Cross section
Phase 1 Phase 2 Phase 3
Fig 2-3: Construction phases
3 Pier and abutment segments
3.1 Comparison of erection methods
In a number of precast segmental
bridges, pier and abutment segments
are fabricated as precast members.
However, the pier and abutment
segments of the Uchimaki viaduct
must be cast-in-situ, because the
casting yard that fabricates precast
segments is located on a field
developed for the New Tomei
Expressway adjacent to the bridge
(Fig. 3-1). The casting yard is not
large enough to set up special casting
beds for pier and abutment segments.
In addition, the structure of the
launching truss for span-by-span
erection can be simplified, because an erection truss is not required for erecting pier
and abutment segments.
In the Uchimaki viaduct, 21 of the 40 pier columns are around 40 m high. All pier
columns are designed to have an identical width to the bottom slab width of the box
girder (Photo 3-1). This design is selected because a box girder with strutted wing
slabs is employed mainly to reduce the size of the substructure. If cast-in-situ whole
pier segments were constructed at the top of the pier columns, large falsework
carrying wide wing slabs would have been required. Therefore, erection of whole
segments would not have been economically viable in relation to cast-in-situ pier
segments. On the other hand, casting core segments enable construction using
relatively simple supports on the pier columns. From these discussions, progressive
erection was determined to be more beneficial in relation to pier segments.
A1
A1
Westbound
Eastbound
60,800
167,000
Storage Area
Re-bar
Assembling Area
Casting Bed
Fig. 3-1: Casting yard
Photo 3-1: Completed pier segment
3.2 Construction of cast-in-situ core segment
In this project, four abutment segments and 40 pier segments on the eastbound
and westbound bridges are to be constructed. To construct all pier and abutment
segments, four sets of falsework were used in rotation. It took approximately 20
months to erect all cast-in-situ core segments.
In the concrete of pier and abutment segments, ordinary Portland cement and
low-heat Portland cement were used in spring, autumn and winter, and in summer,
respectively to control hydration heat. Water was circulated in the ducts for
longitudinal tendons to cool the inside of the segments (Photo 3-1).
4 Prefabrication of typical segment
4.1 Comparison of erection methods
As described earlier, precast segments are
produced in the relatively small casting yard
on the field developed for the New Tomei
Expressway. By using precast core segments,
150 segments can be temporarily stored in
the yard (Fig. 3-1, Photo 4-1). If precast
whole segments had been used, only 80
segments could have been stored, which
would have reduced the flexibility of
segment prefabrication and erection
scheduling, and strict control of schedules
would have been impractical. Furthermore,
precast whole segments are likely to suffer bowing deformation, because the ratio of
segment length (3.0 m) to width (17.680 m) was approximately 1:6, and because the
wing slab has a large width of 5.640 m on each side. In relation to the prefabrication
of typical segments, progressive erection was found to be more beneficial.
4.2 Fabrication of precast core segment
The number of typical core segments to
be prefabricated is 636. The typical segment
has a length of 3.0 m and weighs 492 kN.
The short-line match cast system is
employed in this project. Two casting beds
are equipped for typical core segments. The
box girder has projections at the bottom ends
of webs for connection with struts. Then, the
side forms are designed to move horizontally
to enable the setting of a re-bar cage with the
projections (Photo 4-2). Reinforcing bars are
Photo 4-1: Completed precast core
Photo 4-2: Re-bar cage
projected from the side edge of the slab to connect with the wing slabs. The formwork
at the point was made of wood to facilitate assembly and dismantling. Steam curing
was utilized to facilitate concrete hardening in winter. The producing rate for typical
segments without deviation block was one per day, and for those with deviation block
was one every two days. It took approximately 21 months to prefabricate all typical
segments.
5 Span-by-span erection
5.1 Comparison of erection methods
Span-by-span erection of the whole
segments increases the weight of segments
erected in a typical span by approximately
3000 kN, or by 36% over the weight in the
case of erecting core segments. The whole
segment is 17.680 m wide while the core
segment is 9.200 m wide. As mentioned
above, the width of the Uchimaki viaduct is
relatively large among the highway bridges
in Japan. The width of the core segment is
close to the width of highways with two
traffic lanes generally found in Japan. By
using core segments, a launching truss that
is applicable to ordinary two-lane highways can be used, whereas erecting the whole
segments would have required a special launching truss to accommodate the weight
and width of the segment.
For span-by-span erection, erecting core segments is considered more beneficial.
5.2 Erection of precast core segment
The Uchimaki viaduct is erected over
undulating land at the western half (the
Nagoya side) and the eastern end. The
viaduct also crosses four highways and one
river. It is therefore difficult in most of the
spans to transport precast segments to the
place directly below the span to be erected
and to lift them from the launching truss
above. The casting yard is located adjacent to
the end of the viaduct on the Nagoya side, so
vehicles can easily access from the yard to
the bridge surface. It was decided to start the
erection from the Nagoya end toward Tokyo, and precast segments were transported
on the previously erected bridge surface.
Photo 5-1: Overhead launching truss
Photo 5-2: Polypropylene fiber
An overhead launching truss was used for span-by-span erection (Photo 5-1). The
launching truss weighs approximately 7800 kN. Sixteen segments are assembled in a
typical span. Expansive concrete was used for closure joints to avoid cracking due to
shrinkage. Polypropylene fibers were mixed into concrete to prevent concrete at
closure joints from spalling (Photo 5-2). The erecting rate of typical spans was one
span in nine days.
6 Wing slab erection
Whole-segment erection is considered
to be more advantageous than
progressive erection in relation to wing
slab because progressive erection of
divided parts of the girder cross section
requires special form travelers for
constructing wing slabs and a longer
construction period. In the case where
progressive erection is adopted,
minimizing the cost of special form
travelers and shortening the construction
period are very important.
After the completion of span-by-span
erection of precast core segments, struts
are installed and wing slabs are
constructed simultaneously at three
points using three special form travelers.
Multi-functional guide struts are used to
reduce the weight of the form traveler
(Fig. 6-2). Highly elastic epoxy resin is
used at the bottom end connection of the strut.
Expansive concrete is used for the wing slabs to prevent cracking due to concrete
shrinkage.
The procedure for constructing wing slabs using form travelers is shown in Fig.
6-1. Constructing a 15-m-long block takes six days.
6.1 Form travelers
It was necessary to minimize the
weight of the form traveler to control
tensile stress acting on the wing slab as
the form traveler advanced. It was also
necessary to maximize the length of
construction block to shorten the
construction period. In this project, form
travelers are designed to weigh 1180 kN
Guide strut Guide strut
Fig. 6-2: Cross section of form traveler
(6) Assemble re-bars and post tensioning
(7) Place and cure concrete
(8) Post tensioning
(9) Dismantle formwork
(10) Dismantle guide struts and falsework
(1) Launch form traveler
(2) Assemble guide struts and falsework
(3) Assemble formwork in typical sections
(4) Install struts
(5) Assemble formwork in strut sections
Fig. 6-1: Erection procedure for wing slabs
and enable the
construction of 15-m-long
blocks (Photo 6-1).
The form traveler used
in this project is composed
of six main frames placed
transverse to the bridge
axis (Fig. 6-3). The
frames are longitudinally
connected to one another
relatively loosely; loose
connection enables the frames to adjust to the horizontal alignment of the bridge and
changes in longitudinal or transverse slope.
The main structural features of the form traveler are multi-functional diagonal
members called ‘guide struts’ (Fig. 6-2). The tip of the guide struts is placed at the
bottom end of the web, and the other tip is connected to the vertical member of the
main frame on both sides. Using guide struts prevents the number and stiffness of
members from increasing, and helps reducing the weight of the form traveler. The
functions of the guide strut are described in detail below.
The guide struts are integrated with the falsework under the formwork (Fig. 6-2,
Photo 6-2). After launching the form traveler, lifting the guide struts and setting the
tip of the guide struts at the bottom end of the web complete the assembly of the
falsework under the formwork (erection procedure (2)). Similarly, removing the tip of
the guide strut from the bottom end of the web and lowering the guide strut complete
the dismantling of falsework under the formwork (erection procedure (10)).
Supporting struts by guide struts after installing the struts until dismantling the
formwork considerably reduces the displacement of struts (Photo 6-2). This is
because guide struts increase the overall stiffness of the main frame by directly
transmitting compression force to the box girder. The displacement at the top end of
the strut during concrete placement is kept to 5 mm.
Guide struts keep the displacements at side edges of the wing slabs due to
concrete placement to approximately 5 mm (Photo 6-2). This is because the guide
struts support the main frames from the box girder.
Advancing direction
Main frame
Fig. 6-3: Side view of form traveler
Photo 6-1: Form traveler Photo 6-2:Bottom tip of guide struts
6.2 Precast struts
Precast struts are employed on the
viaduct. The strut of a
300-mm-diamter circular cross
section is 5260 mm long and weighs
9.1 kN.
Struts are produced at a plant for
making concrete products
approximately 50 km away from the
erection site because the casting yard
does not have sufficient space to
produce struts as well as pier and
abutment segments.
The concrete is encased into a
fiber reinforced plastic tube to
prevent concrete from spalling. The tube is also used as the formwork during concrete
placement. The tubes are held vertically when placing concrete.
The plant was therefore equipped with a platform to hold the tubes and gantry
cranes for lifting concrete buckets to the top of the tubes (Photo 6-3).
After assembling the formwork in sections without struts, the bottom end of the
strut is connected to the bottom end of the web (erection procedure (4)). Highly
elastic epoxy resin is applied as an interface, because a thin layer of epoxy resin
ensures that the entire bottom surface of the strut makes contact with the contacting
plane at the bottom end of the web. The layer also adjusts the angle of the strut.
7 Conclusions
This paper described progressive erection on the Uchimaki Viaduct.
Progressive erection was selected after comparing it with the whole segment
erection method. Progressive erection enables the downsizing of construction
equipment and rational construction in relation to the construction of pier segments
and the production and erection of typical segments.
For constructing the wing slabs, the weight of the form traveler is reduced to
enable the construction of longer blocks of wing slabs and thereby shorten the
construction period. Struts are installed in a simple manner.
Progressive erection enables the construction of bridges with a large width using
smaller construction machinery. For the Uchimaki Viaduct, new form travelers were
produced for constructing wing slabs. Progressive construction using existing
construction machinery in every erection phase makes the construction more rational.
Photo 6-3: Prefabrication of strut
8 Recent application of progressive election for the New
Tomei project
The New Tomei is planed to have its traffic width 16.5m finally. But for
reducing the initial construction cost, the traffic width was partially planed to be
10.5m and widen to 16.5m afterward. From the deep consideration of retrofit projects
after opening the expressway and under traffic regulations, most of the retrofit
projects are extremely hard and have the risk of decline the toll benefit. Therefore,
most of the bridge width was determined to be changed to have 16.5m of traffic width
initially.
At the beginning of construction, the traffic width of Nakanogo viaduct was
10.5m which accommodated two traffic lanes. And the construction has already
started. So, progressive election was applied to this bridge. In photo 8-1 to 8-8, the
details of the progressive erection are shown.
Photo 8-1
Photo 8-2
Launching girder for
span-by-span cast-in-situ
Completed box girder without
plinths at the bottom ends of webs
for connection with struts
Photo 8-3
Photo 8-4
Precast plate for connection
with struts
Retrofit process for setting
precast plate
Photo 8-5
Special form traveler for
constructing wing slabs
Photo 8-7
Supporting struts by guide
struts after installing the struts
until dismantling the
formwork
Photo 8-6
Special form traveler for
constructing wing slabs
(close-range view)
Supporting struts by guide
struts after installing the struts
until dismantling the
formwork (root of struts in
detail)
Photo 8-8
9 Acknowledgement
The authors are grateful to the members of the Technical Committee on the
Design and Construction of Prestressed Concrete Bridges with Strutted Wing Slabs
chaired by Professor Yamazaki of Nihon University in connection with the
Construction of the Uchimaki Viaduct.
The authors also thank Mr. Mine of Yokogawa Construction who designed the
form traveler for this project.
References
1) Kimio SAITO et al.: The Superstructure Design of the Uchimaki Viaduct, The
11th Symposium on Developments in Prestressed Concrete, Japan, Nov., 2001
2) Kimio Saito et al.: Design of Precast Segmental Box Girder Bridge with Strutted
Wing Slab, The 1st fib Congress, Japan, Oct., 2002
3) Kimio SAITO et al.: Design of Precast Segment with Deviation Block for Large
Capacity External Tendon -Uchimaki Viaduct-, The 12th Symposium on
Developments in Prestressed Concrete, Japan, Oct., 2003
4) Kimio SAITO et al.: Span-by-Span Erection Applied to Core Segments of
Uchimaki Viaduct, The 13th Symposium on Developments in Prestressed
Concrete, Japan, Oct., 2004

More Related Content

What's hot

Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girdersMD.Yeasin Mostafiz
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPiyush Kumar Santhalia
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girderlotuseye
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge BearingsAyushHajare
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Gantry Girder Design.pptx
Gantry Girder Design.pptxGantry Girder Design.pptx
Gantry Girder Design.pptxneeraj dubey
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their designBhavya Jaiswal
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel StructureGaurang Kakadiya
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repairKartikSuryawanshi2
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges David Collings
 

What's hot (20)

Rail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysisRail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysis
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Guntry girder
Guntry girderGuntry girder
Guntry girder
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girder
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge Bearings
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
Composite deck bridge systems
Composite deck bridge systemsComposite deck bridge systems
Composite deck bridge systems
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Gantry Girder Design.pptx
Gantry Girder Design.pptxGantry Girder Design.pptx
Gantry Girder Design.pptx
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their design
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repair
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges
 

Similar to Spine and wing method for box girders

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelIRJET Journal
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...theijes
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Hossam Shafiq II
 
The hanging basket stress calculation and stability analysis during cantileve...
The hanging basket stress calculation and stability analysis during cantileve...The hanging basket stress calculation and stability analysis during cantileve...
The hanging basket stress calculation and stability analysis during cantileve...IJERA Editor
 
STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...
STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...
STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...IRJET Journal
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxSanjeevGupta660170
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...IRJET Journal
 
Building Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeBuilding Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeColby Hooi
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET Journal
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracturekhushal tadas
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail BridgeKorutla Harish
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESIRJET Journal
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Dr.Subramanian Narayanan
 
BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1Nur Zaas
 

Similar to Spine and wing method for box girders (20)

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
The hanging basket stress calculation and stability analysis during cantileve...
The hanging basket stress calculation and stability analysis during cantileve...The hanging basket stress calculation and stability analysis during cantileve...
The hanging basket stress calculation and stability analysis during cantileve...
 
STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...
STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...
STRUCTURAL PERFORMANCE OF INNOVATIVE FABRICATED COUPLED COMPOSITE COLUMN IN M...
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptx
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
 
Building Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeBuilding Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine Bridge
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
S7
S7S7
S7
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Flat_slab.pptx
Flat_slab.pptxFlat_slab.pptx
Flat_slab.pptx
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Bridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdfBridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdf
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
 
BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1
 

More from Shubham Bhargava Slideshares

More from Shubham Bhargava Slideshares (7)

CV Shubham Bhargava
CV Shubham BhargavaCV Shubham Bhargava
CV Shubham Bhargava
 
CV Shubham Bhargava
CV  Shubham BhargavaCV  Shubham Bhargava
CV Shubham Bhargava
 
Cv shubham bhargava
Cv   shubham bhargavaCv   shubham bhargava
Cv shubham bhargava
 
Cv shubham bhargava
Cv   shubham bhargavaCv   shubham bhargava
Cv shubham bhargava
 
Comparative Study on Soil Stabilization by Sugar Bagasse Ash and Rice Husk Ash
Comparative Study on Soil Stabilization by Sugar Bagasse Ash and Rice Husk Ash Comparative Study on Soil Stabilization by Sugar Bagasse Ash and Rice Husk Ash
Comparative Study on Soil Stabilization by Sugar Bagasse Ash and Rice Husk Ash
 
Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)
 
Erection of box girder With Launching Truss
Erection of box girder With Launching TrussErection of box girder With Launching Truss
Erection of box girder With Launching Truss
 

Recently uploaded

Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 

Recently uploaded (20)

Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 

Spine and wing method for box girders

  • 1. Progressive Erection Applied to Box Girder with Strutted Wing Slab Koji Osada1 , Taketo Kanamoto1 , Kimito Saito2 , Takahiro Arai2 1 Introduction The Uchimaki Viaduct is a multi-span continuous box girder bridge with strutted wing slabs (photo 1-1). It is erected progressively by assembling divided parts of the cross section. The erection of the central part of the box girder is followed by the construction of wing slabs. This paper presents the bridge technologies applied to progressive erection of the Uchimaki viaduct. The technologies include concrete material as well as machinery for producing and erecting the precast segments and special form travelers for constructing the wing slabs. 2 Overview of the project The Uchimaki viaduct is a multi-span continuous box girder bridge built as a part of the New Tomei Expressway. The Uchimaki viaduct consists of the eastbound and westbound bridges, which are constructed in parallel to each other. Both bridges are around 1 km long (Fig. 2-1). The span length is standardized into approximately 50 m 1 Central Nippon Expressway Co.,LTD., Japan 2 Kajima Corporation, Japan Photo 1-1:Completion image Fig 2-1: General view
  • 2. in 36 of the 42 spans in total. Span-by-span erection with precast segments is adopted because of the sufficient project length and standardized spans. The traffic width of the Uchimaki viaduct is 16.5 m, which accommodates three traffic lanes, though many expressways other than the New Tomei and New Meishin expressways have only two traffic lanes. Even with three lanes, the weight of the superstructure and the size of the substructure must be reduced. As a result, diagonal struts supporting the wing slabs are applied to the Uchimaki viaduct. The diagonal struts reduce the deck slab thickness and the bottom slab width (Fig 2-2). Applying span-by-span erection to the box girder with strutted wing slabs, two erection methodologies were compared under the conditions of this project. As the first option, precast segments including the entire cross section (hereafter referred as to ‘whole segment’) are erected. As the other, the cross section is divided into several parts, which are erected progressively. The precast segments exclude large part of the wing slabs and diagonal struts (hereafter referred as to ‘core segment’). As a result, progressive erection with divided parts of cross section was selected. The decision was made because the progressive erection method was found to be beneficial in relation to pier segment erection, fabrication of precast segments and span-by-span erection. In terms of prefabricating segments in particular, it would be impractical to produce whole segments because the casting yard has limited space. The progressive erection applied to the Uchimaki viaduct consists of three major phases (Fig. 2-3). In the first phase, cast-in-situ pier and abutment segments are erected. In the second phase, precast segments are fabricated and erected. In the third phase, precast struts are installed and wing slabs are constructed. In the following section, the erection of whole segments and the progressive erection in each construction phase are compared. In addition, some features in each construction phase are introduced. Fig. 2-2: Cross section Phase 1 Phase 2 Phase 3 Fig 2-3: Construction phases
  • 3. 3 Pier and abutment segments 3.1 Comparison of erection methods In a number of precast segmental bridges, pier and abutment segments are fabricated as precast members. However, the pier and abutment segments of the Uchimaki viaduct must be cast-in-situ, because the casting yard that fabricates precast segments is located on a field developed for the New Tomei Expressway adjacent to the bridge (Fig. 3-1). The casting yard is not large enough to set up special casting beds for pier and abutment segments. In addition, the structure of the launching truss for span-by-span erection can be simplified, because an erection truss is not required for erecting pier and abutment segments. In the Uchimaki viaduct, 21 of the 40 pier columns are around 40 m high. All pier columns are designed to have an identical width to the bottom slab width of the box girder (Photo 3-1). This design is selected because a box girder with strutted wing slabs is employed mainly to reduce the size of the substructure. If cast-in-situ whole pier segments were constructed at the top of the pier columns, large falsework carrying wide wing slabs would have been required. Therefore, erection of whole segments would not have been economically viable in relation to cast-in-situ pier segments. On the other hand, casting core segments enable construction using relatively simple supports on the pier columns. From these discussions, progressive erection was determined to be more beneficial in relation to pier segments. A1 A1 Westbound Eastbound 60,800 167,000 Storage Area Re-bar Assembling Area Casting Bed Fig. 3-1: Casting yard Photo 3-1: Completed pier segment
  • 4. 3.2 Construction of cast-in-situ core segment In this project, four abutment segments and 40 pier segments on the eastbound and westbound bridges are to be constructed. To construct all pier and abutment segments, four sets of falsework were used in rotation. It took approximately 20 months to erect all cast-in-situ core segments. In the concrete of pier and abutment segments, ordinary Portland cement and low-heat Portland cement were used in spring, autumn and winter, and in summer, respectively to control hydration heat. Water was circulated in the ducts for longitudinal tendons to cool the inside of the segments (Photo 3-1). 4 Prefabrication of typical segment 4.1 Comparison of erection methods As described earlier, precast segments are produced in the relatively small casting yard on the field developed for the New Tomei Expressway. By using precast core segments, 150 segments can be temporarily stored in the yard (Fig. 3-1, Photo 4-1). If precast whole segments had been used, only 80 segments could have been stored, which would have reduced the flexibility of segment prefabrication and erection scheduling, and strict control of schedules would have been impractical. Furthermore, precast whole segments are likely to suffer bowing deformation, because the ratio of segment length (3.0 m) to width (17.680 m) was approximately 1:6, and because the wing slab has a large width of 5.640 m on each side. In relation to the prefabrication of typical segments, progressive erection was found to be more beneficial. 4.2 Fabrication of precast core segment The number of typical core segments to be prefabricated is 636. The typical segment has a length of 3.0 m and weighs 492 kN. The short-line match cast system is employed in this project. Two casting beds are equipped for typical core segments. The box girder has projections at the bottom ends of webs for connection with struts. Then, the side forms are designed to move horizontally to enable the setting of a re-bar cage with the projections (Photo 4-2). Reinforcing bars are Photo 4-1: Completed precast core Photo 4-2: Re-bar cage
  • 5. projected from the side edge of the slab to connect with the wing slabs. The formwork at the point was made of wood to facilitate assembly and dismantling. Steam curing was utilized to facilitate concrete hardening in winter. The producing rate for typical segments without deviation block was one per day, and for those with deviation block was one every two days. It took approximately 21 months to prefabricate all typical segments. 5 Span-by-span erection 5.1 Comparison of erection methods Span-by-span erection of the whole segments increases the weight of segments erected in a typical span by approximately 3000 kN, or by 36% over the weight in the case of erecting core segments. The whole segment is 17.680 m wide while the core segment is 9.200 m wide. As mentioned above, the width of the Uchimaki viaduct is relatively large among the highway bridges in Japan. The width of the core segment is close to the width of highways with two traffic lanes generally found in Japan. By using core segments, a launching truss that is applicable to ordinary two-lane highways can be used, whereas erecting the whole segments would have required a special launching truss to accommodate the weight and width of the segment. For span-by-span erection, erecting core segments is considered more beneficial. 5.2 Erection of precast core segment The Uchimaki viaduct is erected over undulating land at the western half (the Nagoya side) and the eastern end. The viaduct also crosses four highways and one river. It is therefore difficult in most of the spans to transport precast segments to the place directly below the span to be erected and to lift them from the launching truss above. The casting yard is located adjacent to the end of the viaduct on the Nagoya side, so vehicles can easily access from the yard to the bridge surface. It was decided to start the erection from the Nagoya end toward Tokyo, and precast segments were transported on the previously erected bridge surface. Photo 5-1: Overhead launching truss Photo 5-2: Polypropylene fiber
  • 6. An overhead launching truss was used for span-by-span erection (Photo 5-1). The launching truss weighs approximately 7800 kN. Sixteen segments are assembled in a typical span. Expansive concrete was used for closure joints to avoid cracking due to shrinkage. Polypropylene fibers were mixed into concrete to prevent concrete at closure joints from spalling (Photo 5-2). The erecting rate of typical spans was one span in nine days. 6 Wing slab erection Whole-segment erection is considered to be more advantageous than progressive erection in relation to wing slab because progressive erection of divided parts of the girder cross section requires special form travelers for constructing wing slabs and a longer construction period. In the case where progressive erection is adopted, minimizing the cost of special form travelers and shortening the construction period are very important. After the completion of span-by-span erection of precast core segments, struts are installed and wing slabs are constructed simultaneously at three points using three special form travelers. Multi-functional guide struts are used to reduce the weight of the form traveler (Fig. 6-2). Highly elastic epoxy resin is used at the bottom end connection of the strut. Expansive concrete is used for the wing slabs to prevent cracking due to concrete shrinkage. The procedure for constructing wing slabs using form travelers is shown in Fig. 6-1. Constructing a 15-m-long block takes six days. 6.1 Form travelers It was necessary to minimize the weight of the form traveler to control tensile stress acting on the wing slab as the form traveler advanced. It was also necessary to maximize the length of construction block to shorten the construction period. In this project, form travelers are designed to weigh 1180 kN Guide strut Guide strut Fig. 6-2: Cross section of form traveler (6) Assemble re-bars and post tensioning (7) Place and cure concrete (8) Post tensioning (9) Dismantle formwork (10) Dismantle guide struts and falsework (1) Launch form traveler (2) Assemble guide struts and falsework (3) Assemble formwork in typical sections (4) Install struts (5) Assemble formwork in strut sections Fig. 6-1: Erection procedure for wing slabs
  • 7. and enable the construction of 15-m-long blocks (Photo 6-1). The form traveler used in this project is composed of six main frames placed transverse to the bridge axis (Fig. 6-3). The frames are longitudinally connected to one another relatively loosely; loose connection enables the frames to adjust to the horizontal alignment of the bridge and changes in longitudinal or transverse slope. The main structural features of the form traveler are multi-functional diagonal members called ‘guide struts’ (Fig. 6-2). The tip of the guide struts is placed at the bottom end of the web, and the other tip is connected to the vertical member of the main frame on both sides. Using guide struts prevents the number and stiffness of members from increasing, and helps reducing the weight of the form traveler. The functions of the guide strut are described in detail below. The guide struts are integrated with the falsework under the formwork (Fig. 6-2, Photo 6-2). After launching the form traveler, lifting the guide struts and setting the tip of the guide struts at the bottom end of the web complete the assembly of the falsework under the formwork (erection procedure (2)). Similarly, removing the tip of the guide strut from the bottom end of the web and lowering the guide strut complete the dismantling of falsework under the formwork (erection procedure (10)). Supporting struts by guide struts after installing the struts until dismantling the formwork considerably reduces the displacement of struts (Photo 6-2). This is because guide struts increase the overall stiffness of the main frame by directly transmitting compression force to the box girder. The displacement at the top end of the strut during concrete placement is kept to 5 mm. Guide struts keep the displacements at side edges of the wing slabs due to concrete placement to approximately 5 mm (Photo 6-2). This is because the guide struts support the main frames from the box girder. Advancing direction Main frame Fig. 6-3: Side view of form traveler Photo 6-1: Form traveler Photo 6-2:Bottom tip of guide struts
  • 8. 6.2 Precast struts Precast struts are employed on the viaduct. The strut of a 300-mm-diamter circular cross section is 5260 mm long and weighs 9.1 kN. Struts are produced at a plant for making concrete products approximately 50 km away from the erection site because the casting yard does not have sufficient space to produce struts as well as pier and abutment segments. The concrete is encased into a fiber reinforced plastic tube to prevent concrete from spalling. The tube is also used as the formwork during concrete placement. The tubes are held vertically when placing concrete. The plant was therefore equipped with a platform to hold the tubes and gantry cranes for lifting concrete buckets to the top of the tubes (Photo 6-3). After assembling the formwork in sections without struts, the bottom end of the strut is connected to the bottom end of the web (erection procedure (4)). Highly elastic epoxy resin is applied as an interface, because a thin layer of epoxy resin ensures that the entire bottom surface of the strut makes contact with the contacting plane at the bottom end of the web. The layer also adjusts the angle of the strut. 7 Conclusions This paper described progressive erection on the Uchimaki Viaduct. Progressive erection was selected after comparing it with the whole segment erection method. Progressive erection enables the downsizing of construction equipment and rational construction in relation to the construction of pier segments and the production and erection of typical segments. For constructing the wing slabs, the weight of the form traveler is reduced to enable the construction of longer blocks of wing slabs and thereby shorten the construction period. Struts are installed in a simple manner. Progressive erection enables the construction of bridges with a large width using smaller construction machinery. For the Uchimaki Viaduct, new form travelers were produced for constructing wing slabs. Progressive construction using existing construction machinery in every erection phase makes the construction more rational. Photo 6-3: Prefabrication of strut
  • 9. 8 Recent application of progressive election for the New Tomei project The New Tomei is planed to have its traffic width 16.5m finally. But for reducing the initial construction cost, the traffic width was partially planed to be 10.5m and widen to 16.5m afterward. From the deep consideration of retrofit projects after opening the expressway and under traffic regulations, most of the retrofit projects are extremely hard and have the risk of decline the toll benefit. Therefore, most of the bridge width was determined to be changed to have 16.5m of traffic width initially. At the beginning of construction, the traffic width of Nakanogo viaduct was 10.5m which accommodated two traffic lanes. And the construction has already started. So, progressive election was applied to this bridge. In photo 8-1 to 8-8, the details of the progressive erection are shown. Photo 8-1 Photo 8-2 Launching girder for span-by-span cast-in-situ Completed box girder without plinths at the bottom ends of webs for connection with struts
  • 10. Photo 8-3 Photo 8-4 Precast plate for connection with struts Retrofit process for setting precast plate Photo 8-5 Special form traveler for constructing wing slabs
  • 11. Photo 8-7 Supporting struts by guide struts after installing the struts until dismantling the formwork Photo 8-6 Special form traveler for constructing wing slabs (close-range view) Supporting struts by guide struts after installing the struts until dismantling the formwork (root of struts in detail) Photo 8-8
  • 12. 9 Acknowledgement The authors are grateful to the members of the Technical Committee on the Design and Construction of Prestressed Concrete Bridges with Strutted Wing Slabs chaired by Professor Yamazaki of Nihon University in connection with the Construction of the Uchimaki Viaduct. The authors also thank Mr. Mine of Yokogawa Construction who designed the form traveler for this project. References 1) Kimio SAITO et al.: The Superstructure Design of the Uchimaki Viaduct, The 11th Symposium on Developments in Prestressed Concrete, Japan, Nov., 2001 2) Kimio Saito et al.: Design of Precast Segmental Box Girder Bridge with Strutted Wing Slab, The 1st fib Congress, Japan, Oct., 2002 3) Kimio SAITO et al.: Design of Precast Segment with Deviation Block for Large Capacity External Tendon -Uchimaki Viaduct-, The 12th Symposium on Developments in Prestressed Concrete, Japan, Oct., 2003 4) Kimio SAITO et al.: Span-by-Span Erection Applied to Core Segments of Uchimaki Viaduct, The 13th Symposium on Developments in Prestressed Concrete, Japan, Oct., 2004