SlideShare a Scribd company logo
1 of 5
Download to read offline
Risk Management:
Identification of Risk and Prioritize the Risk is called Risk Management.
Phases of Risk Management
1. Risk Identification and Prioritize the Risk
2. Management of Risk
Process of Risk Management
1. Assign Risk to owner
2. Risk Paining
3. Risk Monitoring
4. Derive Safe guards
Risk Identification and Prioritize the Risk
Identification of Risk:
The Risk in a project may be in the form of Technical, Cost, Schedule, Client, Contractual, Weather,
Finance, Political, Environmental, People etc.
So, First of all we need to analyze weather the identified thing is a Risk we will face now a days or in
coming future in project Management. Example:
Let suppose we are running a project of IT in for a high security company. And we have identified two
things.
1. There is no resilience or failover for our servers.
2. An outage is informed by Power Company for half an hour tomorrow but we have a UPS which
may keep alive our servers for two hours in case of any outage.
So, first identification is really a Risk as we don’t have any resilience or failover servers in case of any
unexpected catastrophic or disastrous situation.
But
2nd
identification is not a Risk as we have Backup power supply in like UPS which will Keep Alive our
Servers for two hours.
Prioritize the Risk:
By keeping view the severity of Risk we assign the priority to Risk. The severity of risk is very important
to assign a priority of Risk.
How we will know severity of risk?
There are two ways to know if the risk is sever or not.
 Probability chance of occurrence.
 Impact.
Probability chance of occurrence:
Very Expected: Means we are sure that we will meet this Risk. Example in case of any latency to
start the project from due date the project cost will increase. Because the material prices will hike.
Expected: Means we expect that in a specific phase of the project we will face this Risk. Example at
the last stage of project implementation we may expect that funds are running out.
Possible: Means we see possibility that we will meet this risk. Example in worst weather conditions
the implementation team will reduce its working capabilities in field work.
Unexpected/doubtful: Means we are not sure sometimes a specific condition will cause for risk
sometimes not during project implementation. Example if there will be more foggy days in coming
week then we will have latency from Logistic Support to get material on project sight.
Very Unexpected: Means we meet with a risk which is very unexpected. Example Natural disasters.
Now we will See Impact of Risk:
Negligible: Means if the Risk will not leave any affect on a project.
Minor: Means if the Risk will leave very little affect on the project.
Moderate: Means if The Risk will leave the affect but that can be easily bearable.
Significant: Means if The Risk will leave a serious affect and cause for notable losses on project.
Severe: Means if the Risk disrupt the whole project and zero percent chance to comeback.
Process of Risk Management
1. Assign Risk to owner
2. Risk Paining
3. Risk Monitoring
4. Derive Safe guards
Assign Risk to owner:
Once the Risk is identified and also prioritized by keeping view its severity, Now it is
most important to Assign the Key Person who will responsible to Track and record the progress to
resolve the risk
Risk Monitoring:
The Risk Owner will monitor the Risk by:
 Planning the Risk
 Seeing continuously the impact of risk on project
 Setting up meetings with team or subcontractor to record for history data and its resolving.
Risk Paining:
A Risk Management Plain is designed to eliminate or minimize the impact of risks.
Type of Risk Paining:
1. Negative Risk Management Strategies
 Avoid A Risk
 Transfer a Risk
 Mitigate a Risk
 Accept a Risk
2. Positive Risk Management Strategies
 Exploit a Risk
 Share a Risk
 Enhance a Risk
Negative Risk Management Strategies:
Avoid a Risk:
To eliminate or avoid the Risk Project Manager change or isolate the objectives which may
cause for trouble. He may do several things like
 Collect the history data about how that risk was eliminated in past
 Improve the communication between stakeholders
 Reschedule or Change the scope of project etc.
Transfer a Risk:
Shift the Risk to a 3rd Party. For Example
 Involve the insurance company to pay for losses.
 Let Vendor or ownership handle the Risk.
 Let involve the Banks and take loan in case of shortage of project funds ect.
Mitigate a Risk:
This mitigation reduces or minimizes the impact of risk on a project.
 Take an earlier Action to reduce the impact of Risk
 Fix or Repair the Damages
 Develop a prototype to measure the level of Risk
 Try for Free Products and Services.
Accept a Risk:
If there is no chance to avoid the risk or there is no any strategy to avoid it then we accept
the Risk. There are two types of Risk Acceptance
 Passive Acceptance:
 Document a Risk with no action and write the detail of Risk as possible as.
 Leave the Team to deal the Risks as they occur
 Active Acceptance
 Design a Plain to Recover the Loss of Time, Money, and Resources etc
Positive Risk Management Strategies
Exploit the Risk:
Increase the chance of positive Risk happening and In case of happening of Risk adopt or
implement very intelligent strategies like
 During Costing of a project add the percentage of Risk in cost product/Services
 Add the Budget or Finance in Project Fund
Enhance The Risk:
Increase the chance of positive Risk happening and identify the various Risk activities like
 Adding Resource to complete a project before time.
Share A Risk:
If a project team is not technically capable Project Manager higher subcontractor or Partner
Company to implement the project. Like
 We are a Telecom company and we need also civil work in the project
so Project Manager will hire a Partner Company to do the civil work
for this project.
Derive Safe guards:
If the risk is expected in coming future the Risk Manager will implement some
strategies by which he can eliminate/minimize impact of the Risk. Example during final testing or
commissioning of project the subcontract should be involved to avoid any kind of inconvenience.

More Related Content

What's hot

Particpate in whs processes wk 6
Particpate in whs processes wk 6Particpate in whs processes wk 6
Particpate in whs processes wk 6
catherinejyoung
 

What's hot (15)

An introduction to Risk Management, 14 March 2017
An introduction to Risk Management, 14 March 2017An introduction to Risk Management, 14 March 2017
An introduction to Risk Management, 14 March 2017
 
Calculating contingency for management reserve
Calculating contingency for management reserveCalculating contingency for management reserve
Calculating contingency for management reserve
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Particpate in whs processes wk 6
Particpate in whs processes wk 6Particpate in whs processes wk 6
Particpate in whs processes wk 6
 
Five ways to prepare for a disaster
Five ways to prepare for a disasterFive ways to prepare for a disaster
Five ways to prepare for a disaster
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinking
 
London 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingencyLondon 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingency
 
The Art of Playcalling: Building an Incident Response Playbook
The Art of Playcalling: Building an Incident Response PlaybookThe Art of Playcalling: Building an Incident Response Playbook
The Art of Playcalling: Building an Incident Response Playbook
 
risk management
risk managementrisk management
risk management
 
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
 
Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
Project Management Uncertainty, Presented by upul chanaka from Sri Lanka Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
Project Management Uncertainty, Presented by upul chanaka from Sri Lanka
 
Risk management
Risk managementRisk management
Risk management
 
Reliability
ReliabilityReliability
Reliability
 
Risk analysis Chapter
Risk analysis ChapterRisk analysis Chapter
Risk analysis Chapter
 
Analyzing And Managing Project Risk
Analyzing And Managing Project RiskAnalyzing And Managing Project Risk
Analyzing And Managing Project Risk
 

Similar to Risk management

· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx
alinainglis
 
Agile-Risk-Management in Project Management
Agile-Risk-Management in Project ManagementAgile-Risk-Management in Project Management
Agile-Risk-Management in Project Management
Najmul Hussain
 

Similar to Risk management (20)

Risk response planning.pptx
Risk response planning.pptxRisk response planning.pptx
Risk response planning.pptx
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222
 
Risk-Management-Plan.docx
Risk-Management-Plan.docxRisk-Management-Plan.docx
Risk-Management-Plan.docx
 
Chap007
Chap007Chap007
Chap007
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Risk management
Risk managementRisk management
Risk management
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Risk management
Risk management Risk management
Risk management
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx
 
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
 
Risk guideline
Risk guidelineRisk guideline
Risk guideline
 
Risk: the Elephant in the Room
Risk: the Elephant in the RoomRisk: the Elephant in the Room
Risk: the Elephant in the Room
 
Agile-Risk-Management in Project Management
Agile-Risk-Management in Project ManagementAgile-Risk-Management in Project Management
Agile-Risk-Management in Project Management
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
 
Project Risk Management in Product Development
Project Risk Management in Product DevelopmentProject Risk Management in Product Development
Project Risk Management in Product Development
 
Risk management
Risk managementRisk management
Risk management
 
Risk project mgt, infra
Risk project mgt, infraRisk project mgt, infra
Risk project mgt, infra
 
CORPORATE GOVERNANCE ppt.pptx
CORPORATE GOVERNANCE ppt.pptxCORPORATE GOVERNANCE ppt.pptx
CORPORATE GOVERNANCE ppt.pptx
 

More from Nabeel Ahmad (7)

What is the role of science and technology in risk related policy making
What is the role of science and technology in risk related policy makingWhat is the role of science and technology in risk related policy making
What is the role of science and technology in risk related policy making
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Upload-Virtual-Hardisk-On-Azure.pdf
Upload-Virtual-Hardisk-On-Azure.pdfUpload-Virtual-Hardisk-On-Azure.pdf
Upload-Virtual-Hardisk-On-Azure.pdf
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
RAID-Level Configuration on BIOS of DELL Server.pdf
RAID-Level Configuration on BIOS of DELL Server.pdfRAID-Level Configuration on BIOS of DELL Server.pdf
RAID-Level Configuration on BIOS of DELL Server.pdf
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
Very Simple way of subnetting for Class C.
Very Simple way of  subnetting for Class C.Very Simple way of  subnetting for Class C.
Very Simple way of subnetting for Class C.
 

Recently uploaded

1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Recently uploaded (20)

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 

Risk management

  • 1. Risk Management: Identification of Risk and Prioritize the Risk is called Risk Management. Phases of Risk Management 1. Risk Identification and Prioritize the Risk 2. Management of Risk Process of Risk Management 1. Assign Risk to owner 2. Risk Paining 3. Risk Monitoring 4. Derive Safe guards Risk Identification and Prioritize the Risk Identification of Risk: The Risk in a project may be in the form of Technical, Cost, Schedule, Client, Contractual, Weather, Finance, Political, Environmental, People etc. So, First of all we need to analyze weather the identified thing is a Risk we will face now a days or in coming future in project Management. Example: Let suppose we are running a project of IT in for a high security company. And we have identified two things. 1. There is no resilience or failover for our servers. 2. An outage is informed by Power Company for half an hour tomorrow but we have a UPS which may keep alive our servers for two hours in case of any outage. So, first identification is really a Risk as we don’t have any resilience or failover servers in case of any unexpected catastrophic or disastrous situation. But 2nd identification is not a Risk as we have Backup power supply in like UPS which will Keep Alive our Servers for two hours. Prioritize the Risk: By keeping view the severity of Risk we assign the priority to Risk. The severity of risk is very important to assign a priority of Risk. How we will know severity of risk? There are two ways to know if the risk is sever or not.  Probability chance of occurrence.  Impact.
  • 2. Probability chance of occurrence: Very Expected: Means we are sure that we will meet this Risk. Example in case of any latency to start the project from due date the project cost will increase. Because the material prices will hike. Expected: Means we expect that in a specific phase of the project we will face this Risk. Example at the last stage of project implementation we may expect that funds are running out. Possible: Means we see possibility that we will meet this risk. Example in worst weather conditions the implementation team will reduce its working capabilities in field work. Unexpected/doubtful: Means we are not sure sometimes a specific condition will cause for risk sometimes not during project implementation. Example if there will be more foggy days in coming week then we will have latency from Logistic Support to get material on project sight. Very Unexpected: Means we meet with a risk which is very unexpected. Example Natural disasters. Now we will See Impact of Risk: Negligible: Means if the Risk will not leave any affect on a project. Minor: Means if the Risk will leave very little affect on the project. Moderate: Means if The Risk will leave the affect but that can be easily bearable. Significant: Means if The Risk will leave a serious affect and cause for notable losses on project. Severe: Means if the Risk disrupt the whole project and zero percent chance to comeback. Process of Risk Management
  • 3. 1. Assign Risk to owner 2. Risk Paining 3. Risk Monitoring 4. Derive Safe guards Assign Risk to owner: Once the Risk is identified and also prioritized by keeping view its severity, Now it is most important to Assign the Key Person who will responsible to Track and record the progress to resolve the risk Risk Monitoring: The Risk Owner will monitor the Risk by:  Planning the Risk  Seeing continuously the impact of risk on project  Setting up meetings with team or subcontractor to record for history data and its resolving. Risk Paining: A Risk Management Plain is designed to eliminate or minimize the impact of risks. Type of Risk Paining: 1. Negative Risk Management Strategies  Avoid A Risk  Transfer a Risk  Mitigate a Risk  Accept a Risk 2. Positive Risk Management Strategies  Exploit a Risk  Share a Risk  Enhance a Risk Negative Risk Management Strategies: Avoid a Risk: To eliminate or avoid the Risk Project Manager change or isolate the objectives which may cause for trouble. He may do several things like  Collect the history data about how that risk was eliminated in past  Improve the communication between stakeholders  Reschedule or Change the scope of project etc. Transfer a Risk:
  • 4. Shift the Risk to a 3rd Party. For Example  Involve the insurance company to pay for losses.  Let Vendor or ownership handle the Risk.  Let involve the Banks and take loan in case of shortage of project funds ect. Mitigate a Risk: This mitigation reduces or minimizes the impact of risk on a project.  Take an earlier Action to reduce the impact of Risk  Fix or Repair the Damages  Develop a prototype to measure the level of Risk  Try for Free Products and Services. Accept a Risk: If there is no chance to avoid the risk or there is no any strategy to avoid it then we accept the Risk. There are two types of Risk Acceptance  Passive Acceptance:  Document a Risk with no action and write the detail of Risk as possible as.  Leave the Team to deal the Risks as they occur  Active Acceptance  Design a Plain to Recover the Loss of Time, Money, and Resources etc Positive Risk Management Strategies Exploit the Risk: Increase the chance of positive Risk happening and In case of happening of Risk adopt or implement very intelligent strategies like  During Costing of a project add the percentage of Risk in cost product/Services  Add the Budget or Finance in Project Fund Enhance The Risk: Increase the chance of positive Risk happening and identify the various Risk activities like  Adding Resource to complete a project before time. Share A Risk: If a project team is not technically capable Project Manager higher subcontractor or Partner Company to implement the project. Like  We are a Telecom company and we need also civil work in the project so Project Manager will hire a Partner Company to do the civil work for this project.
  • 5. Derive Safe guards: If the risk is expected in coming future the Risk Manager will implement some strategies by which he can eliminate/minimize impact of the Risk. Example during final testing or commissioning of project the subcontract should be involved to avoid any kind of inconvenience.