Mazlan Alias has over 35 years of experience in oil and gas industries, achieving project targets for major companies in Malaysia and abroad. He has extensive experience managing offshore and onshore engineering projects from design through completion, ensuring safety, quality control, and on-time delivery. Some of his roles include Project Engineer, Project Manager, and General Manager. He has expertise in project planning, contract management, and overseeing construction, installation, commissioning, and handover of large-scale oil and gas infrastructure projects.
Senior Pipeline/ Piping Mechanical Engineer Construction & CommissioningMohamed Mustafa
Highly ambitious and self-motivated Project Management Professional with over 10 years in the Oil & Gas Industry in the fields of Project Construction & Commissioning. All experience enhanced by multi-functional business trips in United Arab Emirates, Oman, Algeria and Egypt for large scale EPC projects with Major EPC and Petroleum companies’ region.
1. Resume Of Mazlan Alias
summary of experience
Over 35 years experiences in oil and gas industries, achieving/delivered the
companies aspirations during project’s development and execution phases with
special attention to HSE, QA/QC and Project Deliverable within time frame and
Project Cost in various stages of project engineering and onshore/offshore
constructions, transportation/installation (T&I) of offshore facilities/structures, the
works comprises- the installations of subsea pipelines/risers/PLEM/SPM, mooring
tower, gravity base structure (GBS),CPP topsides ,well heads and tension legs
jackets and Petrochemical Plant for major oil and gas companies ,both in Malaysia
and abroad, as Project Engineer ,Client’s Representative, Project Manager and the
most recent designation was General Manager of Offshore Package, undertakes the
projects from the start to completion date in harsh environment. Experienced in
dealing both with technical and contractual issues in various contract environments
such as EPCI’s, EPC’s , lump sum, reimbursable and cost plus. Proficient in project
management skills which includes, for example, development of project execution
plans, contracting strategies, contracts, bid evaluation and developing various
construction procedures of the above tasks. Also, experienced in implementation of
‘Shell Standard Approach’ of problems solving known as IPOP’s-Implementation
Project On Papers prior commencement of works.
Name:
Home Address:
Email address:
Date of birth:
Age:
Nationality:
Mazlan Alias
B-0-7 Ampang 971,
Jalan Ritchie Off Jalan Ampang,
55000 Kuala Lumpur,
Malaysia.
017-316 6135(mobile phone)
mazlan__alias971@yahoo.com
23 February 1957
59 years old
Malaysian
1
2. Education: Sekolah Menengah Tuanku Abdul Rahman Ipoh, Perak
Qualifications:
1974 – 1976
1976 – 1980
A level
Poole Technical College
Bsc (Hons) Mechanical Engineering
University of Leeds, Leeds UK
1980-1992
Position-Staff
1992-1994
Position-Contract
1995-1998
Position-Contract
1998 -2003
Position-Contract
2003 – 2005
Position-Contract
2005-2008
Position-Contract
2008 – 2010
Position-Direct hire
Sarawak Shell Bhd
Offshore Const. Engineer
Titan Petrochemical Plant,Pasir Gudang
Snr. Package Project Engineer-Export/Import Terminal.
Esso Production Malaysia(EPMI) /JCM,Kertih
Snr Project Engineer–Onshore/Offshore pipelines
construction and installation.
OPI/Brunei Shell Berhad-Development of New Facilities
AMPA/AMCA 9,Champion Field for Brunei Shell.
Offshore/pipeline Construction Supt on DLB264.
Sarawak Shell Berhad (EPA-T-ECB),Miri
Offshore pipeline/decommissioning work-Cat-1
Operation-DLB 264,323 And K-1
Company Site Representative(CSR)
(Re-entered Shell after resignation)
Petronas/Petrodar Operating Co(Sudan)-Construction of
Onshore Pipelines and Pump Stations, from South of
Sudan to Export Terminal(Port Of Sudan).
Snr Project Engineer.
Petronas Carigali-PTTEPI Operating Company Sdn
Bhd,MMHE -Construction of Tension Jacket
Legs(8legged),Living Quarter(LQ),Load Out of CPP and
Pre-Commissioning Of CPP At JDA Field.
Company Site Representative (CSR).
2
3. 2010 – 2011
Position-Contract
2011-2015
Position-Direct Hire
2013(July)-2015
Position-contract
2015(March)-Sept 2015
Petronas Carigali/Technip/MMHE (Turkemenistan) Sdn
Bhd, Kinyaly Yard,Turkemenistan-Construction Of
Gravity Base Structure(GBS)
Snr Offshore Construction/ Transportation And
Installation(T&I) Engineer
Kebabangan Petroleum Operating Company(KPOC)
(A joint venture between Petronas, Shell And Conoco
Phillips)
CSR On Board DLB264 for Offshore Pipelines
Installation /T&I of 130km twin pipelines(24in/14in)
Exxon Mobil/Hafar Neptune- Mobil Cepu, Banyu Urip
Field.Offshore Of Surabaya.Indonesia.
Project Manager/OCS On Board Hafar Neptune Barge
For Offshore Pipelines Installation.
SK-EC (Nghi Son Refinery& Petrochemical Complex
Project (NSRP), Thanh Hoa Province, Hanoi, Vietnam-
Marine Construction and Pipelines(48in Twin Pipelines
And FiberOptic,SPM/PLEM Installation). And Line Pipes
Transportation.
General Manager/Company Site Representative (CSR)
On Board Hyundai Barge(HD 2500)
3
4. Experiences Recorded –
Summary
Sarawak Shell Bhd Achieved a company target for completing the minor
fabrication/construction of structure and piping
modification of CPP and well head platforms of Shell’s
assets.
Task involved and achievement,
Reviewed the fabrication design and construction
methods within applicable engineering codes.
Reviewed the execution plan and developed
mitigation plan.
Developed scope of work for contractor to submit
the bid
Management project review reporting and approval
Reviewed the work plan and methodology.
TitanPetrochemical
Plant,Pasir Gudang,Malaysia
Achieved the completion of work within specified time
frame without having LTI and maintaining the quality
of work within the approved QA/QC plans
The work of the above tasks are summarized –the
construction of export and import jetty and the
construction of above ground pipelines, includes
mechanical/piping work package, installation of loading
Arms, package pre-commissioning and system start up
and work handed over/completion dossier.
Esso Production Malaysia
Inc (EPMI) / JCM.
Achieved for the assigned task, completing the work
within project schedule without major construction
delays and maintaining LTI record in construction and
installation of 18in pipeline (offshore and onshore tie-
in) for sludge catcher project for gas processing plant
for Petronas.
Task involved,
Developed Implementation Project on Paper,
Ensuring all risks are addressed and implemented.
Developed project scope of work and construction
procedures
Developed safety plan and enforcement.
4
5. Experiences Recorded –
Summary
Reviewed procurement plan and delivery schedule
Reviewed and developed master schedule in line
with project deliverable plans.
Reviewed hydro testing method in line to HSE’s
requirement.
OPI/Brunei Shell Bhd Achieved in delivering project schedule without LTI
during transportation and installation (T&I) and
construction and installation of CPP and Pipelines, 6
lagged Jacket/Risers /Connecting Bridge of AMPA9 and
AMCA9 at Champion Field-Brunei Shell.
Task involved,
Developing of construction/installation procedures.
Safety review and enforcement.
Schedule review and mitigation
Barge movement and Marines support
management
Progress reporting and developing an action plans.
Developed hydro testing plan for pipeline in
accordance to Client’s guide line.
Sarawak Shell
Berhad(SSB),Miri,Sarawak,
Malaysia
Achieved the target date of project delivery of offshore
construction and installation of 18in pipeline in
compliance with Company’s requirement, covering
HSE, QA/QC, Management Of Changed (MOC) and
Marines Support Management.
Task involved,
Monitored/coordinate the Transportation Line pipes
schedule.
Trouble shooting on automatic welding
performance.
Anchor pattern developing and barge/marine
support management.
Progress reporting and recommendation.
Monitoring approved engineering calculation
5
6. Experiences Recorded –
Summary
sheets/data/drawings/method of statement of pipe lay
barge.
Petronas/Petrodar
Operating Co.Sudan
Achieved the construction/installation of 1700km
onshore pipelines and construction of pump
Stations (6 pump stations), Employed for Melut Oil
Development Project (Pump Stations/Pipeline) block3
and 7.
Task responsibility and achievement.
Assigned to project management team,
undertaking constructability review, covering HSE,
construction’s developing work’s procedures,
manpower planning QA/QC management and
procurement delivery/logistics plans.
Reviewed and comments on sub-contractors
construction and installation plans to meet the tight
contract project schedule.
Reviewed an interface plan with other packaged
contractors in line with first oil date target.
Reviewed the equipment vendors delivery plans,
this includes the transportation and logistics plans.
there are Sulzer Pumps, Wartsila Diesel Engine
Driver, Atlas Copco Compressors, Bono Heater,
Rolls Royce Gen-set and others equipment.
Undertaking weekly project progress review and
management reporting, highlighting potential
construction delay in advance, this includes,
developing a recovery/catching up plan.
Petronas Carigali-PTTEPI
Operating Company
(CPOC)-A joint venture
between Carigali and
Thailand Petroleum Co.
Achieved the deliverable plans date of the construction
and installation schedule of 8 legged tension jacket,
140 pax of Living Quarter (LQ), WH Platform, Load out
and Pre-Commissioning of CPP modules at JDA field.
Task involved as CSR,
Reviewed site construction/fabrication
constructability plans by each of contractors, the
construction site spread in three (3) deference
locations, MMHE, Sime Sembawang and Pulau
6
7. Experiences Recorded –
Summary
Indah.
Reviewed load out engineering sheets and
methodology equipment deployments, undertaken
by load out contractor/ALE.
Coordinate with engineering team in all phases of
IFC’s drawing, vendors’ specification and codes in
line with project specifications .Includes the
developing the MOC(management of change)if any
issue arises on engineering and construction
discrepancy.
And reviewed the pre-commissioning plan by HUC
contractor for CPP.
Petronas Carigali
(Turkemenistan)/MMHE/
Technip.
As Snr Offshore Construction/T&I Engineer, the
primary task is delivering the schedule of construction,
out fittings, load out, sail away and field installation
and pre-commissioning of GBS.
The GBS was designed by Arup/Technip and the
installation party is by Technip Houston.
Task involved as Snr Offshore Construction/T&I.
Reviewed Construction/Fabrication submitted by
each trade of contractor.
Reviewed manpower loading chart to reflect the
contractor’s schedule plan, include the recovery
plan if the progress of the work slipped away.
Enforcing HSE management plan at various level of
trades/subcontractors.
Reviewed and comment load out plan/procedures,
includes the equipment preparation/testing.
Reviewed the ballast pumps installation, testing
and functional test, the pumps are used to
ballast/de-ballast the GBS during transportation
and installation at field.
Kebabangan Petroleum
Operating Company
(KPOC)-A joint ventures
between Petronas Carigali,
Shell and Conoco Phillips.
Achieved the target completion date of installation twin
24in/14in pipelines, 130km at Sabah water, water
depth of about 600 feet. My primary task as CSR on
board of DLB 264 barge are outlined below,
Coordinate with engineering/survey teams on the
engineering inputs on proposed pipe lay activities.
7
8. Experiences Recorded –
Summary
Reviewed the suitability/engineering inputs of the
barge for the work include the stringer/pipeline
rollers setting.
Reviewed and approved the pipelines hydro test
and testing plans.
Exxon Mobil/Hafar Neptune-
Mobil Cepu, Banyu Urip-
Project Manager Pipeline
and Mooring tower.
A primary task as Project Manager of shallow water
pipeline and mooring installation work of EPCI
contract, the length of pipe line is37km, diameter of
pipe 22in and water depth is approximately 35m. This
is some task brief as outlined below,
Managing and provide direction to project team in
engineering, procurement, construction and
installation teams on scope of work planned ,this is
included, among others, The HSE, project
deliverable, QA/QC, barge and marine supports and
other project management issue such as
contracting management.
Developed project/construction procedures/method
of statement and interaction with client for their
approvals very tough indeed.
Local Authority submission/approval plans.
Managed the Barge movement and Marine supports
in maintaining the progress of work (pipe lay).
Nghi Son Refinery&
Petrochemical Complex
Project(NSRP),Thanh Hoa
Province, Hanoi, Vietnam.
(A joint venture between
Kuwait
Investment/JGS/Chiyoda/S
KEC and Petro Vietnam).
This is an EPCC contract, the task as General Manager,
amongst others (other than above brief),mainly
involved in contract management and project control
and delegating the engineering, construction and
installation matters/issues to each department
managers.
Project Brief And Achievement.
Completed 48in shallow water twin pipelines.
Completed installation of SPM’s and PLEM’s
Completed Fiber Optic installation and completed
onshore tie-in and hydro testing/ preservation of
pipelines.
The End Of My Resume.