− A dynamic professional with over 19 years of rich experience in Project Execution & Construction
Management for Thermal, Captive Power Plant, Work in renewal energy like Solar Power, Polysilicon Plant,
Wafer plant, PV module plant, Metro Rail, Flyover, High rise Building, Airport terminal, Logistic park, Real
estate etc.
− Currently with Triveni Turbine Limited as an EPC contractor for the site of Bhilai Steel Plant, Project Work
of 7 MTPA expansion work for the construction of 25MW STG and 4MW BPTG Building, Bhilai,
Chhattisgarh. Proficient in Micro Planning for execution of civil work and material procurement for
construction area. PMG with experience in Project budgeting, Cost-control and Value Engineering.
− Hold the distinction of managing diverse projects for construction, erection and commissioning activities of
Turbine, Generator, Gear box, Deaerator, PRDS, Condenser, 36 MVA transformer, Reactor, Breaker, High-rise
Buildings, RCC pavements, Piling, Flyover bridge, Subway, culvert, industrial structures like turbine building,
CVD Reactor Building, TCS Plant, Vent and Oil Gas Recovery Structure, Reservoir, H2 Generation and
Purification, Compressed Dry Air, Nitrogen Storage, Boiler Foundation, 132 KV Sub Station, LDO and HFO
Tanks, Dematerialized Water Generation, Plant Water System, Caustic Storage, Vent Scrubber System, Vent
Treatment Plant, HCL Unit, West Water Treatment Plant, Recovery Water Pump House, Clarifier Tank, Paving
work, Settling, Surge Tank, CW pump house, 10 Cell Cooling Tower, switch yard, transformer yard, ESP
control building, PA and FD fan foundation, Installation of HVAC system, Firefighting system, Construction
of RCC Chimney by slip form, Erection of flue can segment by stand jack, Infrastructure Development and so
on.
− Extensive experience in Civil Engineering Works with specialisation in Executing, Contracts Management,
Planning and Coordination.
− Astute professional with a flair for adopting modern management methodologies/ systems in compliance with
prevailing standards.
− Expertise in swiftly wrapping up projects with competent cross-functional skills on time within specified
budget parameters.
− Ensuring safety guidelines in construction area by Hazard Identification and Risk Analysis (HIRA), Tool box
talking, Near miss reporting etc.
− Strong relationship management, communication skills with the ability to network with Project team,
Consultants, Contractors with consummate ease.
− Taking input from store site, Reconciliation of material.
− Making protocol/ Joint records after completion of work for raise the invoice.
AREAS OF EXPERTISE
Project Planning
− Conceptualising detailed project reports and project execution plans after thorough discussion with
management, architects and consultants. Establishing time span of project execution as per client
specifications.
− Listing the resources needed for projects, preparing resource deployment & mobilisation schedule after
considering the lead time, set time frame and budgetary parameters.
− Evaluating designs, coordinating with Architects and Consultants in the preparation of tenders, float tenders
and award contracts after consulting with top management.
− Supervising project costing by estimating and updating it based on Execution Drawings and taking
appropriate measures.
− Monitoring the Project Progress, proceeding for orders to be placed at different stages of the project for various
packages and assessing the resource requirements for various packages.
− Inspecting project status during the course of periodic project review meetings.
− Developing MIS and ensuring relevant reports are generated and sent to the concerned at identified intervals.
Co-ordination
− Liaising with Consultants, Contractors, vendors and all other parties involved ensuring smooth progress of
work and timely clearances like drawings, technical specifications and construction related issues.
− Coordinating with Architects and consultants for design reviews and value addition.
− Leading Contracts Team and coordinate with all the departments, consultants and contractors from the
concept to completion of the project.
− Monitoring the Project Progress, following-up for orders to be placed at different stages of the project for
various packages, assessing the resource requirements for various packages and coordinate between all the
agencies involved in the Project.
− Settling all techno commercial differences / clarifications during execution of project.
− Coordinating all construction activities including providing technical inputs for methodologies of construction
& coordination with site based personal.
EMPLOYMENT DETAIL
Since April’12 with Triveni Turbine Limited, EPC Division Bhilai, Chhattisgarh as Manager Projects
Project : 7 MTPA, Steel Plant, Bhilai, Chhattisgarh.
Responsibilities:
− Overseeing the construction and installation work of 25MW Steam turbine Generator Power House Building, 4
MW Back Pressure Turbine generator Power House Building, Cooling Water Pump House, 10 cell Cooling
Tower, CW Control Building, Side Stream filtration Plant, 600 RM Pipe Trestle, Extended Switch gear Building,
25 Meter High Overhead Tank, Warehouse, Railway cross country pipe line, Bridge, drain, Paving work and
Power evacuation system.
− Erection and commissioning activities of Turbine, Generator, Gear box, Condenser, 36 MVA transformer,
Reactor, Breaker,
− Ensuring work activities as per time schedule with safety management plan.
− Liaising with client and contractors.
− Handling the execution of industrial RCC Structures with high vibrating machine foundations, Reactors and
Breaker Building, RCC pavements, finishing works, etc.
Aug’10 – March 12 with Lanco Infratech Ltd., EPC Division Rajnandgaon, Chhattisgarh Deputy Manager
Project : Lanco Solar Pvt. Limited 1500 TPA, Poly Silicon Plant, Rajnandgaon, Chhattisgarh.
Responsibilities:
− Overseeing the construction work of CVD Building, TCS Plant, VGR Structure Area, Wafer plant, 50 MW PV
module plant, Reservoir, H2 Building, Nitrogen Storage, Boiler Foundation, 132 KV Sub Station, LDO and
HFO Tanks, Plant Water System, Caustic Storage, Vent Scrubber System, Vent Treatment Plant, HCL Storage,
West Water Treatment Plant, Recovery Water Pump House, Clarifier Tank, Paving work, Settling and Surge
Tank.
− Experience in Delhi Metro rail and Airport terminal.
− Ensuring work activities as per time schedule with safety management plan.
− Liaising with client and contractors.
− Handling the execution of industrial RCC Structures with high vibrating machine foundations, Reactors
Building, RCC pavements, finishing works, etc.
Feb’09 – July’ 10 with Simplex Infra. Ltd., Mundra, Kutch, Gujarat as Dy. Manager (Construction)
Project : ADANI Power Ltd. 5x 660 MW TPP, Mundra, Kutch, Gujarat.
Responsibilities:
− Overseeing the construction work of RCC Silos, Fly Ash Water Pump House, Using of slip form in
construction of RCC Chimney, Erection of flue can segment by stand jack, Bottom Ash Water Pump House,
Recovery Water Pump House, Clarifier Tank, Paving work, Settling and Surge Tank.
− Ensuring work activities as per time schedule with safety management plan.
− Liaising with clients and contractors.
− Handling the execution of industrial RCC structures with piling, high vibrating machine foundations,
multistoried buildings, RCC pavements, slip form shuttering system, finishing works, etc., with optimum
utilisation of manpower & machinery.
Mar’07 – Jan’09 with Tata Projects Ltd., (at 1 x 80 MW CPP Hindustan Zinc Ltd., Chanderia, Chittorgarh) Rajasthan
as Engineer Construction
Responsibilities:
Executing the task of ID Fan foundation, FD fan, PA fan Foundation, Bowl Mill foundation, Bunker slab, ESP
control room, TG Building, MCC room, Installation of HVAC system, Firefighting system, CEP Foundation, Switch
yard, Transformer yard, GT foundation, Road and Drain, Ash handling system and Coal stock yard.
May’05 – Feb’07 with BHEL PSER at 2x250 MW TPP CSEB, Korba (East), Chatishgarh as Jr. Engineer
Responsibilities
Constructing 220 meter high RCC Chimney by using of slip form and erection of flue can by using of stand jack
(Twin steel flue liner chimney), raw water pump house, CW pump house, pipe rack foundation, Warehouse, LDO,
HFO tank, ESP control building, Administration Building and ID System foundation.
Sept’04 – Mar’05 with Govt. Polytechnic Korba, (C.G.) as a Project Officer (Planning)
Responsibilities
− Overseeing the construction of percolation tank, dyke wall, extra room, etc.
Jun’96 - Aug’04 with B. B. Verma Co. Engineers & Contractors Pvt. Ltd., Korba as a Site Engineer (4 x 135 MW,
CPP Balco Plant)
Responsibilities
− Executing and supervising the activities in the electrical distribution room, cable trench, duct bank, CW canal,
Piling, Flyover Bridge, Subway, culvert, road and drain work, construction of hollow blocks at Mahamaya
Bricks Industries Bilaspur, construction of high-rise Buildings, Real estate.
− Monitoring the work under PMGSY, SADA colony, bridge, culvert, etc.
EDUCATION
Graduation in Civil Engineering AIMES Mehsana, Gujarat, 2010
ANNA UNIVERSITY (UGC Approved)
Management BABA AMTEY SPS Dewas, MP 2000
Diploma in Civil Engineering Govt. Polytechnic Raigarh, CG 1996
MP Technical Education Board, Bhopal.
HS (PCM) MP, Board, Bhopal 1992
IT SKILLS
Well versed with MS Office, MS Projects, Auto CAD, POL and SAP software
Training:
Training in Computer proficiency from SCERT, Bhopal, MP 6 months
Training of Certificate in Project Management from PMA-India 6 days
Training in Logical framework approach from UNDP, Hyderabad 5 days
PERSONAL DOSSIER
Date of Birth : 23rd March, 1975
Address : B-44, Street No. 11, Smriti Nagar, Bhilai,
Dist. - Durg - 490021, Chhatishgarh
Languages known : English and Hindi

Resume 2015

  • 1.
    MOHAN SINGH E-Mail: mohan_civil29@rediffmail.com≈ Mobile: +91 9407921200, 8827338002, Senior level positions in Civil / Construction Project Management with reputed organisations (Preferably with Manufacturing, Power sectors) PROFESSIONAL PROFILE − A dynamic professional with over 19 years of rich experience in Project Execution & Construction Management for Thermal, Captive Power Plant, Work in renewal energy like Solar Power, Polysilicon Plant, Wafer plant, PV module plant, Metro Rail, Flyover, High rise Building, Airport terminal, Logistic park, Real estate etc. − Currently with Triveni Turbine Limited as an EPC contractor for the site of Bhilai Steel Plant, Project Work of 7 MTPA expansion work for the construction of 25MW STG and 4MW BPTG Building, Bhilai, Chhattisgarh. Proficient in Micro Planning for execution of civil work and material procurement for construction area. PMG with experience in Project budgeting, Cost-control and Value Engineering. − Hold the distinction of managing diverse projects for construction, erection and commissioning activities of Turbine, Generator, Gear box, Deaerator, PRDS, Condenser, 36 MVA transformer, Reactor, Breaker, High-rise Buildings, RCC pavements, Piling, Flyover bridge, Subway, culvert, industrial structures like turbine building, CVD Reactor Building, TCS Plant, Vent and Oil Gas Recovery Structure, Reservoir, H2 Generation and Purification, Compressed Dry Air, Nitrogen Storage, Boiler Foundation, 132 KV Sub Station, LDO and HFO Tanks, Dematerialized Water Generation, Plant Water System, Caustic Storage, Vent Scrubber System, Vent Treatment Plant, HCL Unit, West Water Treatment Plant, Recovery Water Pump House, Clarifier Tank, Paving work, Settling, Surge Tank, CW pump house, 10 Cell Cooling Tower, switch yard, transformer yard, ESP control building, PA and FD fan foundation, Installation of HVAC system, Firefighting system, Construction of RCC Chimney by slip form, Erection of flue can segment by stand jack, Infrastructure Development and so on. − Extensive experience in Civil Engineering Works with specialisation in Executing, Contracts Management, Planning and Coordination. − Astute professional with a flair for adopting modern management methodologies/ systems in compliance with prevailing standards. − Expertise in swiftly wrapping up projects with competent cross-functional skills on time within specified budget parameters. − Ensuring safety guidelines in construction area by Hazard Identification and Risk Analysis (HIRA), Tool box talking, Near miss reporting etc. − Strong relationship management, communication skills with the ability to network with Project team, Consultants, Contractors with consummate ease. − Taking input from store site, Reconciliation of material. − Making protocol/ Joint records after completion of work for raise the invoice. AREAS OF EXPERTISE Project Planning − Conceptualising detailed project reports and project execution plans after thorough discussion with management, architects and consultants. Establishing time span of project execution as per client specifications. − Listing the resources needed for projects, preparing resource deployment & mobilisation schedule after considering the lead time, set time frame and budgetary parameters.
  • 2.
    − Evaluating designs,coordinating with Architects and Consultants in the preparation of tenders, float tenders and award contracts after consulting with top management. − Supervising project costing by estimating and updating it based on Execution Drawings and taking appropriate measures. − Monitoring the Project Progress, proceeding for orders to be placed at different stages of the project for various packages and assessing the resource requirements for various packages. − Inspecting project status during the course of periodic project review meetings. − Developing MIS and ensuring relevant reports are generated and sent to the concerned at identified intervals. Co-ordination − Liaising with Consultants, Contractors, vendors and all other parties involved ensuring smooth progress of work and timely clearances like drawings, technical specifications and construction related issues. − Coordinating with Architects and consultants for design reviews and value addition. − Leading Contracts Team and coordinate with all the departments, consultants and contractors from the concept to completion of the project. − Monitoring the Project Progress, following-up for orders to be placed at different stages of the project for various packages, assessing the resource requirements for various packages and coordinate between all the agencies involved in the Project. − Settling all techno commercial differences / clarifications during execution of project. − Coordinating all construction activities including providing technical inputs for methodologies of construction & coordination with site based personal. EMPLOYMENT DETAIL Since April’12 with Triveni Turbine Limited, EPC Division Bhilai, Chhattisgarh as Manager Projects Project : 7 MTPA, Steel Plant, Bhilai, Chhattisgarh. Responsibilities: − Overseeing the construction and installation work of 25MW Steam turbine Generator Power House Building, 4 MW Back Pressure Turbine generator Power House Building, Cooling Water Pump House, 10 cell Cooling Tower, CW Control Building, Side Stream filtration Plant, 600 RM Pipe Trestle, Extended Switch gear Building, 25 Meter High Overhead Tank, Warehouse, Railway cross country pipe line, Bridge, drain, Paving work and Power evacuation system. − Erection and commissioning activities of Turbine, Generator, Gear box, Condenser, 36 MVA transformer, Reactor, Breaker, − Ensuring work activities as per time schedule with safety management plan. − Liaising with client and contractors. − Handling the execution of industrial RCC Structures with high vibrating machine foundations, Reactors and Breaker Building, RCC pavements, finishing works, etc. Aug’10 – March 12 with Lanco Infratech Ltd., EPC Division Rajnandgaon, Chhattisgarh Deputy Manager Project : Lanco Solar Pvt. Limited 1500 TPA, Poly Silicon Plant, Rajnandgaon, Chhattisgarh. Responsibilities: − Overseeing the construction work of CVD Building, TCS Plant, VGR Structure Area, Wafer plant, 50 MW PV module plant, Reservoir, H2 Building, Nitrogen Storage, Boiler Foundation, 132 KV Sub Station, LDO and HFO Tanks, Plant Water System, Caustic Storage, Vent Scrubber System, Vent Treatment Plant, HCL Storage, West Water Treatment Plant, Recovery Water Pump House, Clarifier Tank, Paving work, Settling and Surge Tank. − Experience in Delhi Metro rail and Airport terminal. − Ensuring work activities as per time schedule with safety management plan. − Liaising with client and contractors. − Handling the execution of industrial RCC Structures with high vibrating machine foundations, Reactors Building, RCC pavements, finishing works, etc.
  • 3.
    Feb’09 – July’10 with Simplex Infra. Ltd., Mundra, Kutch, Gujarat as Dy. Manager (Construction) Project : ADANI Power Ltd. 5x 660 MW TPP, Mundra, Kutch, Gujarat. Responsibilities: − Overseeing the construction work of RCC Silos, Fly Ash Water Pump House, Using of slip form in construction of RCC Chimney, Erection of flue can segment by stand jack, Bottom Ash Water Pump House, Recovery Water Pump House, Clarifier Tank, Paving work, Settling and Surge Tank. − Ensuring work activities as per time schedule with safety management plan. − Liaising with clients and contractors. − Handling the execution of industrial RCC structures with piling, high vibrating machine foundations, multistoried buildings, RCC pavements, slip form shuttering system, finishing works, etc., with optimum utilisation of manpower & machinery. Mar’07 – Jan’09 with Tata Projects Ltd., (at 1 x 80 MW CPP Hindustan Zinc Ltd., Chanderia, Chittorgarh) Rajasthan as Engineer Construction Responsibilities: Executing the task of ID Fan foundation, FD fan, PA fan Foundation, Bowl Mill foundation, Bunker slab, ESP control room, TG Building, MCC room, Installation of HVAC system, Firefighting system, CEP Foundation, Switch yard, Transformer yard, GT foundation, Road and Drain, Ash handling system and Coal stock yard. May’05 – Feb’07 with BHEL PSER at 2x250 MW TPP CSEB, Korba (East), Chatishgarh as Jr. Engineer Responsibilities Constructing 220 meter high RCC Chimney by using of slip form and erection of flue can by using of stand jack (Twin steel flue liner chimney), raw water pump house, CW pump house, pipe rack foundation, Warehouse, LDO, HFO tank, ESP control building, Administration Building and ID System foundation. Sept’04 – Mar’05 with Govt. Polytechnic Korba, (C.G.) as a Project Officer (Planning) Responsibilities − Overseeing the construction of percolation tank, dyke wall, extra room, etc. Jun’96 - Aug’04 with B. B. Verma Co. Engineers & Contractors Pvt. Ltd., Korba as a Site Engineer (4 x 135 MW, CPP Balco Plant) Responsibilities − Executing and supervising the activities in the electrical distribution room, cable trench, duct bank, CW canal, Piling, Flyover Bridge, Subway, culvert, road and drain work, construction of hollow blocks at Mahamaya Bricks Industries Bilaspur, construction of high-rise Buildings, Real estate. − Monitoring the work under PMGSY, SADA colony, bridge, culvert, etc. EDUCATION Graduation in Civil Engineering AIMES Mehsana, Gujarat, 2010 ANNA UNIVERSITY (UGC Approved) Management BABA AMTEY SPS Dewas, MP 2000 Diploma in Civil Engineering Govt. Polytechnic Raigarh, CG 1996 MP Technical Education Board, Bhopal. HS (PCM) MP, Board, Bhopal 1992 IT SKILLS
  • 4.
    Well versed withMS Office, MS Projects, Auto CAD, POL and SAP software Training: Training in Computer proficiency from SCERT, Bhopal, MP 6 months Training of Certificate in Project Management from PMA-India 6 days Training in Logical framework approach from UNDP, Hyderabad 5 days PERSONAL DOSSIER Date of Birth : 23rd March, 1975 Address : B-44, Street No. 11, Smriti Nagar, Bhilai, Dist. - Durg - 490021, Chhatishgarh Languages known : English and Hindi