Reference class forecasting -
useful method, or random
number generator?
1
18th of October 2023
Dr Michala Techau, Head of Resilience and
Sustainability at Oxford Global Projects
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
For the Association for Project Management
Using mega projects as a force for good
The why, when, and how to use Reference Class
Forecasting (RCF) as a method for systematically taking
an outside view to predict uncertainty in mega project
planning and delivery.
Wider context - mega projects are key to the green
transitioning and getting estimates (more) right, is
important in mapping how to reach net zero targets.
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
2
What will we cover?
• Example of mega project performance
• What are the main causes of mega project risk?
• What are the cures for mega project risk?
• How do you apply reference class forecasting?
• What are typical misconceptions about reference class
forecasting?
• Q&A
3
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Examples of Mega Project
Performance
In mega project performance – there is room for improvement…
5
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
6
Edinburgh tram - delivery can be doomed before you
start
…if your forecast is wrong
• Estimate: £498m + a £37m contingency = £535m (2007, Phase 1a only), opening 2011.
• Reality: £776m, opening 2014 ~ 52% over budget (and reduced scope).
• RCF estimate: £697-£781m
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Source: The City of Edinburgh Council, 2013.
Report for the Edinburgh Tram Inquiry, 2018, B. Flyvbjerg and A. Budzier
7
Hong Kong express rail link – using the “wrong anchor”
can set you up to fail
• Estimate: HK$39.5bn and 4 years to build.
• Reality: Four years in, no end in sight and ballooning
budget.
• RCF estimate: HK$85bn (high confidence, low risk) and a
six-year project schedule.
• XLR completed within budget and time.
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Poll
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
8
Which of these five industries do you think perform best?
How reliably do we deliver our promises across industries?
Ø duration, years
Cost overrun
Benefits
overrun
Frequency of
cost overrun
Schedule
overrun
Cost
Black Swans
Olympics
7.1
157%
n/a
10 of 10
0%
57%
IT-led
change
3.3
73%
-28%
4 of 10
43%
18%
Dams
7.9
74%
-11%
8 of 10
45%
23%
Roads
4.9
15%
-4%
6 of 10
36%
3%
8.1
Rail
32%
-23%
7 of 10
31%
9%
Buildings
57%
-5%
7 of 10
29%
18%
6.7 6.8
238%
-23%
9 of 10
70%
43%
Nuclear
waste
storage
Solar
power
2.2
1%
n/a
4 of 10
2%
0%
Source: Oxford Global Projects Database (Q4 2022)
Note: Measured from date of decision to build, in constant prices
Black Swans (outliers) are defined as 1.5 times the Inter-Quartile Range (IQR) IQR=difference difference between the third quartile (Q3) and the first quartile (Q1).
9
100.0%
47.9%
8.5%
0.5%
All projects
(n=16,357)
On-budget (or
better)
On-budget &
on-time
(or better)
On-budget &
on-time &
on-benefits
(or better)
Iron Law of (Mega)-Projects
“Over budget, over time, under benefits, over
and over again” (Professor Bent Flyvbjerg)
The iron law of mega projects
10
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
100.0%
47.9%
8.5%
0.5%
All projects
(n=16,357)
On-budget (or
better)
On-budget &
on-time
(or better)
On-budget &
on-time &
on-benefits
(or better)
11
This is the likelihood of success
if we deliver projects as we have
always done!
The iron law of mega projects
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
What are the Main Causes of
Mega Project Risk?
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 13
The root cause of overruns – the main risks are
internal, not external
Why do we
underestimate risk?
Risk is external All risks are internal
Overrun Underestimation
1. Technical: Estimation error (Vanston &
Vanston)
2. Psychological: Optimism bias, Planning fallacy
etc. (Kahneman, Tversky, Lovallo)
3. Political-economic: Strategic
misrepresentation (Wachs, Flyvbjerg)
© Bent Flyvbjerg
Three types of explanation for risk underestimation –
technical and behavioural biases
14
15
Optimism bias: “The cognitive predisposition
found with most people to judge future events in
a more positive light than is warranted by actual
experience.” (Flyvbjerg 2006)
“The planning fallacy is a consequence of the tendency to
neglect distributional data, and to adopt what may be
termed an 'internal approach' to prediction, where one
focuses on the constituents of the specific problem rather
than on the distribution of outcomes in similar cases.”
(Kahneman & Tversky 1977)
Psychological explanation – what are the most
important biases in projects management?
16
How optimism bias influence our decision making -
experimental demonstration
• Almost all newlyweds in a US study expected their marriage to
last a lifetime, even while aware of the divorce statistics
• Professional financial analysts consistently overestimated
corporate earnings
• Second-year MBA students overestimated the number of job
offers they would receive and their starting salary
• Most smokers believed they are less at risk of developing
smoking-related diseases than others who smoke
Economic-political bias
“Strategic misrepresentation is the planned,
systematic distortion or misstatement of fact –
lying – in response to incentives in the budget
process.”
– Jones and Euske, 1991
© Bent Flyvbjerg 17
A planner on cost underestimation
“…as a planner, you will often know the real
costs. You know that the budget is too low, but it
is difficult to pass such a message to the
counsellors [politicians] and the private actors.
They know that high costs reduce the chances
of national funding.”
18
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Poll
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 19
Which of these two impact your project most?
What are the Cures for Mega
Project Risk?
The Big Idea
Reference Class Forecasting (RCF) is an alternative
forecasting method that uses data from past similar projects to
forecast the range of possible outturn costs and / or schedule.
The best predictor of performance in a planned project
is actual performance in a class of implemented,
comparable projects. Reference Class Forecasts do not
guarantee accuracy, just most accurate forecasts.
The method is based on theories that won the Nobel Prize in
Economics (planning fallacy, optimism bias).
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 21
Reference Class
Forecasting
Our reference class forecasting tool has been cited by Nobel
Laureate Daniel Kahneman as “the single most important
piece of advice regarding how to increase accuracy in
forecasting through improved methods.”
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 22
What reference class forecasting does
23
1 2
2
Outside View
Reference
Class
Inside View
Experts’ Forecast
Regresses best guess toward
the mean of the reference class
1
Expands estimate of interval
to interval of the reference class
2
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Unknown-unknowns
RCF takes into account “unknown unknowns”.
How? By incorporating in the reference class ALL effects on
performance, including “unknown unknowns”.
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 24
How do you Apply Reference Class
Forecasting to Mega Projects?
The three steps of RCF
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
We show the cost overruns experienced
by the projects in the reference class as a
cumulative distribution....
50% of projects had an
overrun of 25%
1. Build a reference class of similar projects
2. Establish probability distribution for the reference class
3. Compare your project with the distribution
26
Cost overrun is calculated as
𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡
𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡
P80 = 85%
…which - provided your project performs
no better or worse than projects in the
reference class - can be translated into
probability.
1. 2. 3.
High Speed 2 - Phase One cost estimate provided by
OGP in 2019
Cost heading Cost GBP million*
Contracts & Delivery team 1,150
Tunnels 2,910
Civils 3,990
Stations 2,545
Depots and stabling 720
Railway systems 1,560
On-network works 480
Land & property 1,630
Corporate overheads 1,265
Total cost 15,650
27
HS2 Ltd’s Phase one base cost estimate @ OBC
Source: UK Department for Transport
*2013 cost year
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
HS2 Ltd’s Outline Business Case estimate of cost risk*
applying Quantitative Risk Analysis (QRA)
28
P95 = £5.75bn
= +37%
P50 = £3.75bn =
+24%
Risk
identification
workshop
Expert
assessment
Monte Carlo
simulation
Limitations
ignored
* Size of a potential cost
overrun over the £15.65bn
base cost estimate in real
terms, Outline Business Case
(OBC)
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
• Selecting past similar projects, based on statistical similarity
• Testing whether average, median (P50), P80, P90, P95 are statistically
significantly different from high-speed rail
• Only fixed links are comparable for the full range of estimates from
P50-P95
• Final selected reference class included 39 high-speed rail projects
and 132 fixed links = 171 projects
Is this project type a
suitable comparator for
HSR projects? (n=39)
Average P50 P80 P90 P95
Conv. rail (n=113) ✔ ✔ ✔
Fixed link (n=132) ✔ ✔ ✔ ✔ ✔
Metro (n=196) ✔ ✔ ✔
Road (n=658) ✔ ✔
✔ No statistically
significant difference
✗ Statistically
significant
difference
Step 1: Building a reference class for HS2
29
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Step 2: Establishing the cost risk distribution for the
reference class
30
• Cost overruns in 3 out of 4
projects but also cost
underruns
• High-cost overruns not
unlikely: 1 in 8 projects more
than doubled in cost
50% of projects had
an overrun of 23%
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Step 3: Comparing the inside view estimate with the
RCF “outside view”
31
• P50 risk (+24%) in conventional forecast = P51 in reference class
• P95 risk (+37%) in conventional forecast = P70 in reference class!
• P95 in reference class = +136%
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Step 3: Comparing inside view and the RCF “outside
view”
Cost risk estimate* OBC: “inside view” RCF: “outside view”
P50 £3.75bn £3.60bn
P80 £4.66bn £10.64bn
P95 £5.76bn £21.28bn
© Bent Flyvbjerg 32
* Size of a potential cost overrun over the £15.65bn base cost estimate at OBC (Outline Business Case) in real terms.
Cost year 2013 ~ £43.94bn in 2023, assuming average inflation rate of 1.8% per year.
Total cost estimate OBC: “inside view” RCF: “outside view”
P50 £19.40bn £19.25bn
P80 £20.31bn £26.29bn
P95 £21.40bn £36.93bn
33
Institute for Government publication “HS2: costs and controversies. How much has the HS2 project cost since its inception?” 5th October 2023
Comparing RCF estimate with current status of HS2 –
Phase 1 only estimated to cost around £40bn
Recent abandonment of Phase 2 limits estimated spend to £35-45bn (2019 prices) for Phase 1.
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
What are Typical Misconceptions
About RCF?
35
Examples of typical misconceptions about RCF
• Contingency upon contingency
• Where we have data without contingency, the resulting RCF provides suggested uplift to add to deterministic baseline cost
– do you know how much padding is already added to your estimate?
• History repeating
• No – set out to beat the odds. RCF makes you aware of how projects performed in the past, set out to understand why, so
you can mitigate and outperform previous projects.
• Comparing apples with rocks
• RCF is not about exact similarity of technology, but about similarity of risk distributions, e.g., for FoaK projects types, it is
still insightful to see how other FoaK projects performed.
• It is too subjective
• Adjustments to where your project sits on the RCF curve needs to be made as objectively AND consistently as possible.
• Our project will never be approved
• Inflating project cost / schedule using RCF suggested uplifts does look scary – but there to inform discussions on risk
appetite and affordability. More projects should go back to the drawing board!
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Key take home message on RCF
Enhances accuracy of
estimates by leveraging
full distributions of
historical data - to provide
a more realistic and
objective basis for decision
making
36
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
37
So how do we beat the odds and use mega projects as a
force for good?
• Informing policy for better incentivisation?
• Optimising resource allocation
• Project appraisal – selection effect
• Often the worst projects are approved, because they look
best on paper (highest BCR)
• Require more efficient delivery of projects
• Experience – people and technology
• Avoid the eternal beginner syndrome
• Modularity
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Questions?
38
Dr Michala Techau
Oxford Global Projects
Head of Resilience and Sustainability
michala.techau@oxfordglobalprojects.com
+44 (0)7887755446
Appendix
39
When to apply RCF and how it complements QRA
Estimate adjustments are needed before there is enough
certainty for QRA* - the IPA recommends using RCF
first, and then transitioning to QRA
Source: Infrastructure and Projects authority (2021).
Project Routemap: Risk Management UK Module. London.
• At early planning stages when little is known
about the project (SOC), RCF provides a top-
down overall risk estimate.
• As more is known about the project and risk
becomes clearer (OBC), the QRA becomes
more reliable.
• As the project matures to FBC the RCF is used
as a benchmark to check the QRA is realistic
and correct for any biases and unknowns.
Low
Certainty
Business case
stages
SOC OBC FBC
Increasing
certainty
Medium
Certainty
High
Certainty
*QRA – Quantitative Risk Assessment
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 40
How risk distribution for historical data compares to
an example of a current estimate in the nuclear industry
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 41
Clear difference between the Monte Carlo risk model (green) and the historical data, both inclusive (blue) and exclusive (orange) of the North
American projects. Especially for values greater than P50.
Bad data +
bad models
→ Error
Error means
• Overestimation as likely
as underestimation
• Overestimation similar
size as underestimation
• In the long run they
average out
Transport
infrastructure
(n=1,505)
Average
overrun
Standard
deviation
Level of significance
(p)
Cost 28% 61% < 0.001
Schedule 37% 53% < 0.001
Benefits -6% 43% < 0.001
The project performance data reject the error hypothesis.
Technical explanation
42
• Within an industry, programmes or projects
are statistically very similar, in terms of cost,
schedule and benefit risks.
• The assumption of uniqueness does not stand
up to hard, statistical test, it’s a myth.
• Truly unique programs are rare; even projects
like the Greenlandic Arctic Circle Road have
similarities with other projects.
• Statistical similarity is all we need for RCF and
better risk management.
Uniqueness bias – unique projects are rarer than you think
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 43
44
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
• Risk appetite reflects decision-makers’ willingness to make investments
with uncertain outcomes
• Risk appetite depends not only on the risks involved in a specific capital
project but also on the organisations general attitude to risk as well as the
size of other risks the organisation carries
• In the context of projects’ forecasts, risk appetite determines the level of
certainty sought in a forecast, or inversely, the acceptable chance of an
overrun for the project
• More risk averse organisations seeking higher level of confidence in their
estimates have lower acceptable chance of overruns
• However, there is a trade-off between economic viability, affordability, and
target setting that must be negotiated
Project appraisal
question
Risk appetite
level
Level of certainty
of estimates
Economic
viability for
organisation
Risk neutral at
portfolio level
P40-P60
Affordability in
worst case
scenario
Very low risk P80-P95
Target setting to
incentivise
performance
Moderate to low
risk
P30-P50
OGP guides projects to navigate around complex risk appetite
discussions on economic viability, affordability &
performance incentives
Applying the findings to your project
How RCFs are applied to your project
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
The S-curve is used to calculate the uplifts that need to be
added to the baseline estimate to provide different levels
of certainty of preventing an overrun
• You can then select the appropriate level of
probability for your risk appetite and apply
the corresponding uplift.
• Or you can compare your existing total
contingency to find out what level of
probability your current contingency
provides.
45
Edinburgh tram extension – taking an outside view
from the beginning for a better forecast
• For the extension of the Edinburgh tram, from St Andrew Square to the waterfront at Ocean Terminal, OGP provided
support with budget and schedule estimation
• The decision was to use P50 – and the extension was completed on time and on budget
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
https://www.railtech.com/all/2023/02/21/edinburgh-trams-extension-opening-finally-announced/
Report for the Edinburgh Tram Inquiry, 2018, B. Flyvbjerg and A. Budzier
46
47
Top 10 behavioural biases in project planning and
management
Top Ten Behavioral Biases in Project Management: An Overview https://journals.sagepub.com/doi/full/10.1177/87569728211049046
Other methods
48
Appropriate budget contingency
determination for construction projects:
State-of-the-art
Author links open overlay
panelTaher Ammar, Mohamed Abdel-
Monem, Karim El-Dash
The External View: 20+ Years of Megaproject Research
13
Optimism bias
Political bias
Escalation of
commitment
Decision
making
Builder-buyer-user-funder
federation
Governance
Delivery model
Formal authority Informal authority
Strategy &
governance
Socio-politics
Leadership
Capabilities
Capacity
Manufacturing
integration and
coordination
Programatics
Commercials
System
integration
Systems
Procedures
Tools
Novelty
Scale &
pace
Emergence &
change
Predict &
provide
Predict &
prevent
Contingency
Buffer
Risk &
uncertainty
Institutional
context
Structures
Rules
Informal
norms
Fragmentation
Community
engagement
Stakeholder
engagement
Megaproject
performance
Adapted from:
Denicol, J., Davies, A. and Krystallis, I., 2020. What are the causes and cures of poor megaproject performance? A systematic literature review and research agenda. Project Management Journal, 51(3), pp.328-345.
49
Iron Law of (Mega)-Projects
“Over budget, over time, under
benefits, over and over again”
Summary
2 Key Challenges to Overcome the Iron Law (of many)
Decision Quality
Value Tracking
+
• Reference Class Forecasting
• Decision checklists
• Early-Warning Sign Systems
• Real-time tracking
Build
er
User Buyer
• Builder-Buyer-User Federation
• Shared values, behaviors, culture
Optimism bias
Political bias
Escalation of
commitment
Decision
making
Builder-buyer-user-funder
federation
Governance
Delivery model
Formal authority Informal authority
Strategy &
governance
Socio-politics
Leadership
Capabilities
Capacity
Manufacturing
integration and
coordination
Programatics
Commercials
System
integration
Systems
Procedures
Tools
Novelty
Scale &
pace
Emergence &
change
Predict &
provide
Predict &
prevent
Contingency
Buffer
Risk &
uncertainty
Institutional
context
Structures
Rules
Informal
norms
Fragmentation
Community
engagement
Stakeholder
engagement
Megaproject
performance
50
CONFIDENTIAL & PROPRIETARY
Scope.
Our RCFs assure project estimates using five
inter-linked approaches.
51
CONFIDENTIAL & PROPRIETARY
Outcomes.
“How can we beat the
odds and outperform
history?”
Our RCF approach provides objective findings
that can answer practical questions.
52
Independent Studies
1. Sydney Water Corporation, 11 infrastructure projects with RCF showed a significantly increased likelihood of completing under budget
(Napier and Liu, 2008).
2. Australian State Road and Traffic Authority, 44 projects with RCF showed increased forecast accuracy (Liu, Wehbe, and Siscovic, 2010).
3. Bridge construction forecast based on RCF and Bayesian updating produced more accurate forecasts (Kim and Reinschmidt, 2011)
4. RCF and Bayesian forecast of healthcare cost in 8 car manufacturing plants produced more accurate forecasts (Bordley, 2014)
5. A study of 56 construction projects shows that RCF outperforms conventional techniques, i.e. bottom-up estimation EVM and Monte Carlo
simulations (Batselier and Vanhoucke, 2016)
6. Application of RCF to Bujagali hydropower dam project increased accuracy of the cost-benefit analysis (Awojobi and Jenkins, 2016)
7. A study of 399 political forecasters shows that those trained and using RCF, taking different perspectives, and post-mortem analyses
produced more accurate forecasts (Chang, Chen, Mellers, and Tetlock, 2016)
8. Application of RCF on 369 Turkish public works projects resulted in reasonably accurate predictions (Bayram and Al-Jibouri, 2017)
9. Integrating RCF into EVM on 23 construction projects produced more accurate predictions of schedule performance (Batselier and
Vanhoucke, 2017)
10. RCF on 222 chemical industry projects proved effective for large homogenous projects but useless for less homogenous projects with little
historical data (Walcak and Majchrzak, 2018)
11. RCF improved the estimates of the cost of contaminated spoil removal in 3 nuclear projects (Devine, 2019)
12. A re-signaling project in Denmark applied RCF but still overran the budget because managers re-introduced optimism when selecting the
reference class (Themsen, 2019)
13. A modified RCF approach to estimate the remaining schedule to complete was accurate to 5 percentage points in 4 offshore oil and gas
projects (Dehghan et al., 2020)
14. RCF led to less optimistic forecasts in 322 project forecasts conducted as part of an experimental study (Friesdorf, 2020)
15. Providing RCF information to guide schedule forecasts in 139 experimental estimates improved the forecast accuracy, but more detailed
information about the task did not (Lorko et al., 2020)
16. The application of RCF to oil and gas production rates for the Norwegian Continental Shelf reduced optimism bias and increased forecast
accuracy
from 33% to 77% (at P80) (Jehan and Storsveen, 2020)
17. The first-ever RCF application in Germany, on Stuttgart 21, would have predicted the current cost overrun (Steininger et al., 2021)
18. The average cost overrun of UK major projects has reduced from 50% to 5% following the introduction of RCF (Park, 2021).
53
A typical conclusion was drawn by
Batselier and Vanhoucke (2016),
who said: "The conducted
evaluation is entirely based on
real-life project data and shows
that RCF indeed performs best, for
both cost and time forecasting, and
therefore supports the practical
relevance of the technique.”
• Introduced as Government Policy in major projects in the UK in 2004;
updated in 2021 for Department for Transport* and currently by Treasury
• Hong Kong’s DEVB introduced RCF starting in 2012**
• In 2019 adopted as policy in Ireland’s Spending Code and first adopted by Transport
Infrastructure Ireland in 2020
We help clients
navigate the UK
Government’s
business case
and approval
process for
projects & and
programmes.
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
Our definition of risk
Risk = Negative uncertainty (downside)
Uncertainty = More than one possible outcome, i.e., “more things can happen than will
happen”
Positive uncertainty = Opportunity (upside)
Avg
Cost, schedule
or benefit
1sd 2sd
55
56
M+ Museum in Hong Kong
• Hong Kong's M+ Museum (set opening date at RCF80;
managed to hit that target).
• From an initial HK$21.6 billion ($2.75 billion) to more
than HK$47.1 billion ($6 billion) after a reevaluation in
2013 and almost HK$70 billion ($8.91 billion) in 2021.
(M+ itself had an initial cost of HK$5.9 billion [$750
million] that city authorities confirmed has been
exceeded). On a broader scale, despite the district’s built
progress, there is still a lack of clear proposed public
policy that would foster local art production, a void
which paints the scheme as tourism-oriented rather than
for the benefit of the city’s arts scene.
CONFIDENTIAL & PROPRIETARY
Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
https://www.scmp.com/news/hong-kong/hong-kong-economy/article/3103507/head-hong-kongs-west-kowloon-cultural-district
Cost and schedule overrun
Cost overrun is calculated as 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡
𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡
Schedule overrun is calculated as 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛
𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛
Actual project cost refers to total project cost, which
includes all costs that materialised in the project.
Estimated project cost is the most likely project cost
estimate. Same for schedule.
As such, the overrun RCF data represent how much
additional budget or time projects needed to complete.
-30%
-20%
-10%
0%
10%
20%
30%
40%
50%
60%
70%
5% 15% 25% 35% 45% 55% 65% 75% 85% 95%
57
Productivity 1995-Today
(GDP created by 1 hour of work in each industry baselined to 1995 = 100)
Note: 27 EU countries 58
100
125
150
175
200
1995 2000 2005 2010 2015 2020
Year
Productivity
per
hour
worked
(1996=100) Construction
Finance
ICT
Industry
Manufacturing
Prof. services
Trade
ICT
Manufacturing
Industry
Finance
Trade
Construction
Professional services

Reference Class Forecasting - useful method, or random number generator? webinar

  • 1.
    Reference class forecasting- useful method, or random number generator? 1 18th of October 2023 Dr Michala Techau, Head of Resilience and Sustainability at Oxford Global Projects CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited For the Association for Project Management
  • 2.
    Using mega projectsas a force for good The why, when, and how to use Reference Class Forecasting (RCF) as a method for systematically taking an outside view to predict uncertainty in mega project planning and delivery. Wider context - mega projects are key to the green transitioning and getting estimates (more) right, is important in mapping how to reach net zero targets. CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 2
  • 3.
    What will wecover? • Example of mega project performance • What are the main causes of mega project risk? • What are the cures for mega project risk? • How do you apply reference class forecasting? • What are typical misconceptions about reference class forecasting? • Q&A 3 CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 4.
    Examples of MegaProject Performance
  • 5.
    In mega projectperformance – there is room for improvement… 5 CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 6.
    6 Edinburgh tram -delivery can be doomed before you start …if your forecast is wrong • Estimate: £498m + a £37m contingency = £535m (2007, Phase 1a only), opening 2011. • Reality: £776m, opening 2014 ~ 52% over budget (and reduced scope). • RCF estimate: £697-£781m CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited Source: The City of Edinburgh Council, 2013. Report for the Edinburgh Tram Inquiry, 2018, B. Flyvbjerg and A. Budzier
  • 7.
    7 Hong Kong expressrail link – using the “wrong anchor” can set you up to fail • Estimate: HK$39.5bn and 4 years to build. • Reality: Four years in, no end in sight and ballooning budget. • RCF estimate: HK$85bn (high confidence, low risk) and a six-year project schedule. • XLR completed within budget and time. CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 8.
    Poll CONFIDENTIAL & PROPRIETARY Anyuse of this material without specific permission of Oxford Global Projects is strictly prohibited 8 Which of these five industries do you think perform best?
  • 9.
    How reliably dowe deliver our promises across industries? Ø duration, years Cost overrun Benefits overrun Frequency of cost overrun Schedule overrun Cost Black Swans Olympics 7.1 157% n/a 10 of 10 0% 57% IT-led change 3.3 73% -28% 4 of 10 43% 18% Dams 7.9 74% -11% 8 of 10 45% 23% Roads 4.9 15% -4% 6 of 10 36% 3% 8.1 Rail 32% -23% 7 of 10 31% 9% Buildings 57% -5% 7 of 10 29% 18% 6.7 6.8 238% -23% 9 of 10 70% 43% Nuclear waste storage Solar power 2.2 1% n/a 4 of 10 2% 0% Source: Oxford Global Projects Database (Q4 2022) Note: Measured from date of decision to build, in constant prices Black Swans (outliers) are defined as 1.5 times the Inter-Quartile Range (IQR) IQR=difference difference between the third quartile (Q3) and the first quartile (Q1). 9
  • 10.
    100.0% 47.9% 8.5% 0.5% All projects (n=16,357) On-budget (or better) On-budget& on-time (or better) On-budget & on-time & on-benefits (or better) Iron Law of (Mega)-Projects “Over budget, over time, under benefits, over and over again” (Professor Bent Flyvbjerg) The iron law of mega projects 10 CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 11.
    100.0% 47.9% 8.5% 0.5% All projects (n=16,357) On-budget (or better) On-budget& on-time (or better) On-budget & on-time & on-benefits (or better) 11 This is the likelihood of success if we deliver projects as we have always done! The iron law of mega projects CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 12.
    What are theMain Causes of Mega Project Risk?
  • 13.
    CONFIDENTIAL & PROPRIETARY Anyuse of this material without specific permission of Oxford Global Projects is strictly prohibited 13 The root cause of overruns – the main risks are internal, not external Why do we underestimate risk? Risk is external All risks are internal Overrun Underestimation
  • 14.
    1. Technical: Estimationerror (Vanston & Vanston) 2. Psychological: Optimism bias, Planning fallacy etc. (Kahneman, Tversky, Lovallo) 3. Political-economic: Strategic misrepresentation (Wachs, Flyvbjerg) © Bent Flyvbjerg Three types of explanation for risk underestimation – technical and behavioural biases 14
  • 15.
    15 Optimism bias: “Thecognitive predisposition found with most people to judge future events in a more positive light than is warranted by actual experience.” (Flyvbjerg 2006) “The planning fallacy is a consequence of the tendency to neglect distributional data, and to adopt what may be termed an 'internal approach' to prediction, where one focuses on the constituents of the specific problem rather than on the distribution of outcomes in similar cases.” (Kahneman & Tversky 1977) Psychological explanation – what are the most important biases in projects management?
  • 16.
    16 How optimism biasinfluence our decision making - experimental demonstration • Almost all newlyweds in a US study expected their marriage to last a lifetime, even while aware of the divorce statistics • Professional financial analysts consistently overestimated corporate earnings • Second-year MBA students overestimated the number of job offers they would receive and their starting salary • Most smokers believed they are less at risk of developing smoking-related diseases than others who smoke
  • 17.
    Economic-political bias “Strategic misrepresentationis the planned, systematic distortion or misstatement of fact – lying – in response to incentives in the budget process.” – Jones and Euske, 1991 © Bent Flyvbjerg 17
  • 18.
    A planner oncost underestimation “…as a planner, you will often know the real costs. You know that the budget is too low, but it is difficult to pass such a message to the counsellors [politicians] and the private actors. They know that high costs reduce the chances of national funding.” 18 CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 19.
    Poll CONFIDENTIAL & PROPRIETARY Anyuse of this material without specific permission of Oxford Global Projects is strictly prohibited 19 Which of these two impact your project most?
  • 20.
    What are theCures for Mega Project Risk?
  • 21.
    The Big Idea ReferenceClass Forecasting (RCF) is an alternative forecasting method that uses data from past similar projects to forecast the range of possible outturn costs and / or schedule. The best predictor of performance in a planned project is actual performance in a class of implemented, comparable projects. Reference Class Forecasts do not guarantee accuracy, just most accurate forecasts. The method is based on theories that won the Nobel Prize in Economics (planning fallacy, optimism bias). CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 21
  • 22.
    Reference Class Forecasting Our referenceclass forecasting tool has been cited by Nobel Laureate Daniel Kahneman as “the single most important piece of advice regarding how to increase accuracy in forecasting through improved methods.” CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 22
  • 23.
    What reference classforecasting does 23 1 2 2 Outside View Reference Class Inside View Experts’ Forecast Regresses best guess toward the mean of the reference class 1 Expands estimate of interval to interval of the reference class 2 CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 24.
    Unknown-unknowns RCF takes intoaccount “unknown unknowns”. How? By incorporating in the reference class ALL effects on performance, including “unknown unknowns”. CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 24
  • 25.
    How do youApply Reference Class Forecasting to Mega Projects?
  • 26.
    The three stepsof RCF CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited We show the cost overruns experienced by the projects in the reference class as a cumulative distribution.... 50% of projects had an overrun of 25% 1. Build a reference class of similar projects 2. Establish probability distribution for the reference class 3. Compare your project with the distribution 26 Cost overrun is calculated as 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡 𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡 P80 = 85% …which - provided your project performs no better or worse than projects in the reference class - can be translated into probability. 1. 2. 3.
  • 27.
    High Speed 2- Phase One cost estimate provided by OGP in 2019 Cost heading Cost GBP million* Contracts & Delivery team 1,150 Tunnels 2,910 Civils 3,990 Stations 2,545 Depots and stabling 720 Railway systems 1,560 On-network works 480 Land & property 1,630 Corporate overheads 1,265 Total cost 15,650 27 HS2 Ltd’s Phase one base cost estimate @ OBC Source: UK Department for Transport *2013 cost year CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 28.
    HS2 Ltd’s OutlineBusiness Case estimate of cost risk* applying Quantitative Risk Analysis (QRA) 28 P95 = £5.75bn = +37% P50 = £3.75bn = +24% Risk identification workshop Expert assessment Monte Carlo simulation Limitations ignored * Size of a potential cost overrun over the £15.65bn base cost estimate in real terms, Outline Business Case (OBC) CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 29.
    • Selecting pastsimilar projects, based on statistical similarity • Testing whether average, median (P50), P80, P90, P95 are statistically significantly different from high-speed rail • Only fixed links are comparable for the full range of estimates from P50-P95 • Final selected reference class included 39 high-speed rail projects and 132 fixed links = 171 projects Is this project type a suitable comparator for HSR projects? (n=39) Average P50 P80 P90 P95 Conv. rail (n=113) ✔ ✔ ✔ Fixed link (n=132) ✔ ✔ ✔ ✔ ✔ Metro (n=196) ✔ ✔ ✔ Road (n=658) ✔ ✔ ✔ No statistically significant difference ✗ Statistically significant difference Step 1: Building a reference class for HS2 29 CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 30.
    Step 2: Establishingthe cost risk distribution for the reference class 30 • Cost overruns in 3 out of 4 projects but also cost underruns • High-cost overruns not unlikely: 1 in 8 projects more than doubled in cost 50% of projects had an overrun of 23% CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 31.
    Step 3: Comparingthe inside view estimate with the RCF “outside view” 31 • P50 risk (+24%) in conventional forecast = P51 in reference class • P95 risk (+37%) in conventional forecast = P70 in reference class! • P95 in reference class = +136% CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 32.
    Step 3: Comparinginside view and the RCF “outside view” Cost risk estimate* OBC: “inside view” RCF: “outside view” P50 £3.75bn £3.60bn P80 £4.66bn £10.64bn P95 £5.76bn £21.28bn © Bent Flyvbjerg 32 * Size of a potential cost overrun over the £15.65bn base cost estimate at OBC (Outline Business Case) in real terms. Cost year 2013 ~ £43.94bn in 2023, assuming average inflation rate of 1.8% per year. Total cost estimate OBC: “inside view” RCF: “outside view” P50 £19.40bn £19.25bn P80 £20.31bn £26.29bn P95 £21.40bn £36.93bn
  • 33.
    33 Institute for Governmentpublication “HS2: costs and controversies. How much has the HS2 project cost since its inception?” 5th October 2023 Comparing RCF estimate with current status of HS2 – Phase 1 only estimated to cost around £40bn Recent abandonment of Phase 2 limits estimated spend to £35-45bn (2019 prices) for Phase 1. CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 34.
    What are TypicalMisconceptions About RCF?
  • 35.
    35 Examples of typicalmisconceptions about RCF • Contingency upon contingency • Where we have data without contingency, the resulting RCF provides suggested uplift to add to deterministic baseline cost – do you know how much padding is already added to your estimate? • History repeating • No – set out to beat the odds. RCF makes you aware of how projects performed in the past, set out to understand why, so you can mitigate and outperform previous projects. • Comparing apples with rocks • RCF is not about exact similarity of technology, but about similarity of risk distributions, e.g., for FoaK projects types, it is still insightful to see how other FoaK projects performed. • It is too subjective • Adjustments to where your project sits on the RCF curve needs to be made as objectively AND consistently as possible. • Our project will never be approved • Inflating project cost / schedule using RCF suggested uplifts does look scary – but there to inform discussions on risk appetite and affordability. More projects should go back to the drawing board! CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 36.
    Key take homemessage on RCF Enhances accuracy of estimates by leveraging full distributions of historical data - to provide a more realistic and objective basis for decision making 36 CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 37.
    37 So how dowe beat the odds and use mega projects as a force for good? • Informing policy for better incentivisation? • Optimising resource allocation • Project appraisal – selection effect • Often the worst projects are approved, because they look best on paper (highest BCR) • Require more efficient delivery of projects • Experience – people and technology • Avoid the eternal beginner syndrome • Modularity CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited
  • 38.
    Questions? 38 Dr Michala Techau OxfordGlobal Projects Head of Resilience and Sustainability michala.techau@oxfordglobalprojects.com +44 (0)7887755446
  • 39.
  • 40.
    When to applyRCF and how it complements QRA Estimate adjustments are needed before there is enough certainty for QRA* - the IPA recommends using RCF first, and then transitioning to QRA Source: Infrastructure and Projects authority (2021). Project Routemap: Risk Management UK Module. London. • At early planning stages when little is known about the project (SOC), RCF provides a top- down overall risk estimate. • As more is known about the project and risk becomes clearer (OBC), the QRA becomes more reliable. • As the project matures to FBC the RCF is used as a benchmark to check the QRA is realistic and correct for any biases and unknowns. Low Certainty Business case stages SOC OBC FBC Increasing certainty Medium Certainty High Certainty *QRA – Quantitative Risk Assessment CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 40
  • 41.
    How risk distributionfor historical data compares to an example of a current estimate in the nuclear industry CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 41 Clear difference between the Monte Carlo risk model (green) and the historical data, both inclusive (blue) and exclusive (orange) of the North American projects. Especially for values greater than P50.
  • 42.
    Bad data + badmodels → Error Error means • Overestimation as likely as underestimation • Overestimation similar size as underestimation • In the long run they average out Transport infrastructure (n=1,505) Average overrun Standard deviation Level of significance (p) Cost 28% 61% < 0.001 Schedule 37% 53% < 0.001 Benefits -6% 43% < 0.001 The project performance data reject the error hypothesis. Technical explanation 42
  • 43.
    • Within anindustry, programmes or projects are statistically very similar, in terms of cost, schedule and benefit risks. • The assumption of uniqueness does not stand up to hard, statistical test, it’s a myth. • Truly unique programs are rare; even projects like the Greenlandic Arctic Circle Road have similarities with other projects. • Statistical similarity is all we need for RCF and better risk management. Uniqueness bias – unique projects are rarer than you think CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited 43
  • 44.
    44 CONFIDENTIAL & PROPRIETARY Anyuse of this material without specific permission of Oxford Global Projects is strictly prohibited • Risk appetite reflects decision-makers’ willingness to make investments with uncertain outcomes • Risk appetite depends not only on the risks involved in a specific capital project but also on the organisations general attitude to risk as well as the size of other risks the organisation carries • In the context of projects’ forecasts, risk appetite determines the level of certainty sought in a forecast, or inversely, the acceptable chance of an overrun for the project • More risk averse organisations seeking higher level of confidence in their estimates have lower acceptable chance of overruns • However, there is a trade-off between economic viability, affordability, and target setting that must be negotiated Project appraisal question Risk appetite level Level of certainty of estimates Economic viability for organisation Risk neutral at portfolio level P40-P60 Affordability in worst case scenario Very low risk P80-P95 Target setting to incentivise performance Moderate to low risk P30-P50 OGP guides projects to navigate around complex risk appetite discussions on economic viability, affordability & performance incentives Applying the findings to your project
  • 45.
    How RCFs areapplied to your project CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited The S-curve is used to calculate the uplifts that need to be added to the baseline estimate to provide different levels of certainty of preventing an overrun • You can then select the appropriate level of probability for your risk appetite and apply the corresponding uplift. • Or you can compare your existing total contingency to find out what level of probability your current contingency provides. 45
  • 46.
    Edinburgh tram extension– taking an outside view from the beginning for a better forecast • For the extension of the Edinburgh tram, from St Andrew Square to the waterfront at Ocean Terminal, OGP provided support with budget and schedule estimation • The decision was to use P50 – and the extension was completed on time and on budget CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited https://www.railtech.com/all/2023/02/21/edinburgh-trams-extension-opening-finally-announced/ Report for the Edinburgh Tram Inquiry, 2018, B. Flyvbjerg and A. Budzier 46
  • 47.
    47 Top 10 behaviouralbiases in project planning and management Top Ten Behavioral Biases in Project Management: An Overview https://journals.sagepub.com/doi/full/10.1177/87569728211049046
  • 48.
    Other methods 48 Appropriate budgetcontingency determination for construction projects: State-of-the-art Author links open overlay panelTaher Ammar, Mohamed Abdel- Monem, Karim El-Dash
  • 49.
    The External View:20+ Years of Megaproject Research 13 Optimism bias Political bias Escalation of commitment Decision making Builder-buyer-user-funder federation Governance Delivery model Formal authority Informal authority Strategy & governance Socio-politics Leadership Capabilities Capacity Manufacturing integration and coordination Programatics Commercials System integration Systems Procedures Tools Novelty Scale & pace Emergence & change Predict & provide Predict & prevent Contingency Buffer Risk & uncertainty Institutional context Structures Rules Informal norms Fragmentation Community engagement Stakeholder engagement Megaproject performance Adapted from: Denicol, J., Davies, A. and Krystallis, I., 2020. What are the causes and cures of poor megaproject performance? A systematic literature review and research agenda. Project Management Journal, 51(3), pp.328-345. 49
  • 50.
    Iron Law of(Mega)-Projects “Over budget, over time, under benefits, over and over again” Summary 2 Key Challenges to Overcome the Iron Law (of many) Decision Quality Value Tracking + • Reference Class Forecasting • Decision checklists • Early-Warning Sign Systems • Real-time tracking Build er User Buyer • Builder-Buyer-User Federation • Shared values, behaviors, culture Optimism bias Political bias Escalation of commitment Decision making Builder-buyer-user-funder federation Governance Delivery model Formal authority Informal authority Strategy & governance Socio-politics Leadership Capabilities Capacity Manufacturing integration and coordination Programatics Commercials System integration Systems Procedures Tools Novelty Scale & pace Emergence & change Predict & provide Predict & prevent Contingency Buffer Risk & uncertainty Institutional context Structures Rules Informal norms Fragmentation Community engagement Stakeholder engagement Megaproject performance 50
  • 51.
    CONFIDENTIAL & PROPRIETARY Scope. OurRCFs assure project estimates using five inter-linked approaches. 51
  • 52.
    CONFIDENTIAL & PROPRIETARY Outcomes. “Howcan we beat the odds and outperform history?” Our RCF approach provides objective findings that can answer practical questions. 52
  • 53.
    Independent Studies 1. SydneyWater Corporation, 11 infrastructure projects with RCF showed a significantly increased likelihood of completing under budget (Napier and Liu, 2008). 2. Australian State Road and Traffic Authority, 44 projects with RCF showed increased forecast accuracy (Liu, Wehbe, and Siscovic, 2010). 3. Bridge construction forecast based on RCF and Bayesian updating produced more accurate forecasts (Kim and Reinschmidt, 2011) 4. RCF and Bayesian forecast of healthcare cost in 8 car manufacturing plants produced more accurate forecasts (Bordley, 2014) 5. A study of 56 construction projects shows that RCF outperforms conventional techniques, i.e. bottom-up estimation EVM and Monte Carlo simulations (Batselier and Vanhoucke, 2016) 6. Application of RCF to Bujagali hydropower dam project increased accuracy of the cost-benefit analysis (Awojobi and Jenkins, 2016) 7. A study of 399 political forecasters shows that those trained and using RCF, taking different perspectives, and post-mortem analyses produced more accurate forecasts (Chang, Chen, Mellers, and Tetlock, 2016) 8. Application of RCF on 369 Turkish public works projects resulted in reasonably accurate predictions (Bayram and Al-Jibouri, 2017) 9. Integrating RCF into EVM on 23 construction projects produced more accurate predictions of schedule performance (Batselier and Vanhoucke, 2017) 10. RCF on 222 chemical industry projects proved effective for large homogenous projects but useless for less homogenous projects with little historical data (Walcak and Majchrzak, 2018) 11. RCF improved the estimates of the cost of contaminated spoil removal in 3 nuclear projects (Devine, 2019) 12. A re-signaling project in Denmark applied RCF but still overran the budget because managers re-introduced optimism when selecting the reference class (Themsen, 2019) 13. A modified RCF approach to estimate the remaining schedule to complete was accurate to 5 percentage points in 4 offshore oil and gas projects (Dehghan et al., 2020) 14. RCF led to less optimistic forecasts in 322 project forecasts conducted as part of an experimental study (Friesdorf, 2020) 15. Providing RCF information to guide schedule forecasts in 139 experimental estimates improved the forecast accuracy, but more detailed information about the task did not (Lorko et al., 2020) 16. The application of RCF to oil and gas production rates for the Norwegian Continental Shelf reduced optimism bias and increased forecast accuracy from 33% to 77% (at P80) (Jehan and Storsveen, 2020) 17. The first-ever RCF application in Germany, on Stuttgart 21, would have predicted the current cost overrun (Steininger et al., 2021) 18. The average cost overrun of UK major projects has reduced from 50% to 5% following the introduction of RCF (Park, 2021). 53 A typical conclusion was drawn by Batselier and Vanhoucke (2016), who said: "The conducted evaluation is entirely based on real-life project data and shows that RCF indeed performs best, for both cost and time forecasting, and therefore supports the practical relevance of the technique.” • Introduced as Government Policy in major projects in the UK in 2004; updated in 2021 for Department for Transport* and currently by Treasury • Hong Kong’s DEVB introduced RCF starting in 2012** • In 2019 adopted as policy in Ireland’s Spending Code and first adopted by Transport Infrastructure Ireland in 2020
  • 54.
    We help clients navigatethe UK Government’s business case and approval process for projects & and programmes.
  • 55.
    CONFIDENTIAL & PROPRIETARY Anyuse of this material without specific permission of Oxford Global Projects is strictly prohibited Our definition of risk Risk = Negative uncertainty (downside) Uncertainty = More than one possible outcome, i.e., “more things can happen than will happen” Positive uncertainty = Opportunity (upside) Avg Cost, schedule or benefit 1sd 2sd 55
  • 56.
    56 M+ Museum inHong Kong • Hong Kong's M+ Museum (set opening date at RCF80; managed to hit that target). • From an initial HK$21.6 billion ($2.75 billion) to more than HK$47.1 billion ($6 billion) after a reevaluation in 2013 and almost HK$70 billion ($8.91 billion) in 2021. (M+ itself had an initial cost of HK$5.9 billion [$750 million] that city authorities confirmed has been exceeded). On a broader scale, despite the district’s built progress, there is still a lack of clear proposed public policy that would foster local art production, a void which paints the scheme as tourism-oriented rather than for the benefit of the city’s arts scene. CONFIDENTIAL & PROPRIETARY Any use of this material without specific permission of Oxford Global Projects is strictly prohibited https://www.scmp.com/news/hong-kong/hong-kong-economy/article/3103507/head-hong-kongs-west-kowloon-cultural-district
  • 57.
    Cost and scheduleoverrun Cost overrun is calculated as 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡 𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑠𝑡 Schedule overrun is calculated as 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 Actual project cost refers to total project cost, which includes all costs that materialised in the project. Estimated project cost is the most likely project cost estimate. Same for schedule. As such, the overrun RCF data represent how much additional budget or time projects needed to complete. -30% -20% -10% 0% 10% 20% 30% 40% 50% 60% 70% 5% 15% 25% 35% 45% 55% 65% 75% 85% 95% 57
  • 58.
    Productivity 1995-Today (GDP createdby 1 hour of work in each industry baselined to 1995 = 100) Note: 27 EU countries 58 100 125 150 175 200 1995 2000 2005 2010 2015 2020 Year Productivity per hour worked (1996=100) Construction Finance ICT Industry Manufacturing Prof. services Trade ICT Manufacturing Industry Finance Trade Construction Professional services