SlideShare a Scribd company logo
1 of 18
Quebec Bridge
25-Jan-19 Majzoob Mohammed Arbab 1
About
• Quebec bridge is a rail, road and pedestrian bridge situated on the St.
Lawrence River, Quebec, Canada.
• It was at time of construction the longest cantilever bridge in the world with
clear span of 549 m.
• The bridge construction was finally completed in 1917 after Two Failures or
tragedies to bridge the harsh icy waters of the St. Lawrence river.
• First collapse occurred on August 26, 1907. Second collapse occurred almost
after a decade on September 11, 1916
• Quebec bridge is a cantilever truss bridge with two spans cantilever from
both sides and simple span suspended in between.
25-Jan-19 Majzoob Mohammed Arbab 2
History
• The story of the bridge begins back in 1887 with the formation of
Quebec Bridge company which came up with the proposal to erect the
bridge over the river to increase business traffic in the city of Quebec
and places nearby.
• Various proposals for the bridge were submitted out of which The
Phoenix Bridge Company’s proposal was selected which called for a
cantilever bridge of 45 m in height above the high water mark.
• Theodore Cooper, a well-known American bridge designer, was selected
as the project’s consulting engineer by the Quebec Bridge company. He
endorsed the Phoenix design as the “best and the cheapest” of those
submitted, although he decided to lengthen the center span from 488 m
to 549 m in order to eliminate the uncertainty of constructing piers in
such deep water, lessen the effects of ice, and shorten the time of
construction of the piers.
25-Jan-19 Majzoob Mohammed Arbab 3
Concept Dimensions & Details
25-Jan-19 Majzoob Mohammed Arbab 4
First Collapse 1/5
• As soon as the south anchor arm was completed (in early 1906) the
assembly of the cantilever arm could begin (the falsework was then
also moved to the other side of the river for the construction of the
north anchor arm).
• Using the anchor arm as a counterweight – securely anchored at the
end for the uplift forces – the main span was being erected using the
cantilever technique (one half from either side of the river).
• At just about this point in the construction (in early 1906) it was
discovered that the amount of steel material delivered to the bridge
site considerably exceeded the originally estimated amount. It was
because no correction for self weight of the structure was made when
the span length was increased from 488 m to 549 m. Cooper however,
decided to forge ahead and Not introduce any changes.
25-Jan-19 Majzoob Mohammed Arbab 5
First Collapse 2/5
25-Jan-19 Majzoob Mohammed Arbab 6
First Collapse 3/5
• When the cantilever had been extended further out over the river,
increasing the stresses even more in the truss members – it was found
that the out of plane bending of chord A9-L had increased from some
20 mm to alarmingly 57 mm.
• Even though this deformation – representing an out-of-plane
deflection of L/305 (the length L of the member being 17.44 m) – is
hard to detect by the naked eye, it was a clear signal that something
was quite wrong.
25-Jan-19 Majzoob Mohammed Arbab 7
First Collapse 4/5
• Cooper, realizing the danger of the situation, wanting the
construction to come to an immediate halt, telegraphed to the
Phoenix Bridge Company: “Add no more load till after due
consideration of facts’’.
• However, the contractor (i.e. the Phoenix Bridge Company) was
under great pressure not to delay the construction, so the work
continued by unfortunately moving an erection crane one step
further out on the cantilever.
25-Jan-19 Majzoob Mohammed Arbab 8
First Collapse 5/5
• The A9L bottom
compression chord,
which was already bent,
gave way under the
increasing weight of the
bridge. The load
transferred to the
opposite A9R chord,
which also buckled. The
piers were the only part
of the structure that
survived.25-Jan-19 Majzoob Mohammed Arbab 9
25-Jan-19 Majzoob Mohammed Arbab 10
Second Collapse
• In spite of the enormity of the accident, it was decided that the project
must be completed. In 1908, a board of engineers was appointed that
arranged for and supervised the design and erection of a new bridge.
Except for the piers, nothing from the previous structure was recoverable.
• In April 1911, the contract was awarded to the St. Lawrence Bridge
Company of Montreal. As before, the design called for a cantilever-type
bridge, but it differed from the previous one with the lower chords of the
cantilever arms several times stronger. One important innovation that
added strength to the bridge was the K-truss design.
25-Jan-19 Majzoob Mohammed Arbab 11
25-Jan-19 Majzoob Mohammed Arbab 12
• Construction of the bridge started in 1913, and eventually the two
approach spans, the anchor arms and cantilevers went up on either side
of the river. By 1916, the bridge was nearly completed.
• The workmen faced a difficult task in moving the span upstream, but all
went well with that part of the job. The span was carried on scows that
were guided by tugs. It was a slow process, but eventually the span was
maneuvered into position between the cantilever arms where huge
lifting hangers, attached to the ends of the arms, raised it by hydraulic
means off the scows. The span was to be lifted two feet at a time in a
repeat operation until it was in place between the two arms.
25-Jan-19 Majzoob Mohammed Arbab 13
• The southwest corner of the span tore away and sagged. A few seconds
later, the other ends pulled off their supports and the whole span came
loose and disappeared into the river. Thirteen men were carried to their
deaths and several others were injured.25-Jan-19 Majzoob Mohammed Arbab 14
The investigation by the board of engineers determined that
the span did not buckle as Larocque and others claimed.
Rather, the loss resulted from the failure of a casting in the
erection equipment that temporarily supported the southwest
corner of the span.
25-Jan-19 Majzoob Mohammed Arbab 15
Final Completion
• On Sept. 20, 1917, the suspended span was lifted into position and fastened to the
cantilever arms. At last, the world’s longest cantilever bridge was completed and the
first train crossed it in October. Two months later it was opened to regular trains,
vehicle and pedestrian traffic.
25-Jan-19 Majzoob Mohammed Arbab 16
Major Causes of Failure
• An underestimation of the self-weight of the structure
• Temporary splicing of the chords using bolts
• The load carrying capacity had been overestimated resulting
in weak cross-sections
• The stabilizing bars (the crossing diagonals and horizontals)
were not strong enough to resist out-of-plane buckling of the
compression chords
25-Jan-19 Majzoob Mohammed Arbab 17
Lessons Learned
• The collapse of the bridge finally led to the development of Canadian
design specifications for bridge structures.
• Engineering design is necessary for the means and methods of lifting
operations.
• The responsibility of execution and design of such an important
structure must Not be left in the hands of one person
25-Jan-19 Majzoob Mohammed Arbab 18

More Related Content

What's hot

Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating EquipmentKiran Goswami
 
case study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failurecase study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failureJainam Shah
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEsrinivas cnu
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projectsSULAKSHYA GAUR
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slidesWaqas Javaid
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Mohamed Yassin
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringLatif Hyder Wadho
 
Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Ankur Saxena
 
The kansas city hyatt regency walkway collapse
The kansas city hyatt regency walkway collapseThe kansas city hyatt regency walkway collapse
The kansas city hyatt regency walkway collapseArpit Modh
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 

What's hot (20)

Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating Equipment
 
Steel truss ppt
Steel truss pptSteel truss ppt
Steel truss ppt
 
Pisa Tower
Pisa TowerPisa Tower
Pisa Tower
 
CULVERTS.pdf
CULVERTS.pdfCULVERTS.pdf
CULVERTS.pdf
 
CASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGECASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGE
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
case study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failurecase study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failure
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projects
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slides
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway Engineering
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Golden gate bridge, San Francisco
Golden gate bridge, San Francisco
 
The kansas city hyatt regency walkway collapse
The kansas city hyatt regency walkway collapseThe kansas city hyatt regency walkway collapse
The kansas city hyatt regency walkway collapse
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 

Similar to Quebec Bridge Collapse - Case Study

Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Ferit Fazliu
 
Howrah bridge ppt
Howrah bridge pptHowrah bridge ppt
Howrah bridge pptSourav Roy
 
Brooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudyBrooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudyBhavik A Shah
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Vivek Chauhan
 
1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015John Newquist
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge constructionKundan Sanap
 
Engineering Landmarks in London
Engineering Landmarks in LondonEngineering Landmarks in London
Engineering Landmarks in LondonTristan Robinson
 
Bridge Report
Bridge ReportBridge Report
Bridge Reportsaif khan
 
S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.Shivu P
 
Physics project writing assesment
Physics project writing assesmentPhysics project writing assesment
Physics project writing assesmentPlayersGuide
 
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdfCase Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdfSANDEEPARIHANT
 

Similar to Quebec Bridge Collapse - Case Study (20)

Quebec disaster
Quebec disasterQuebec disaster
Quebec disaster
 
Saga of a steel bridge
Saga of a steel bridgeSaga of a steel bridge
Saga of a steel bridge
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Bridge project
Bridge projectBridge project
Bridge project
 
Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02
 
Bridge project
Bridge projectBridge project
Bridge project
 
Resonance Phenomenon
Resonance PhenomenonResonance Phenomenon
Resonance Phenomenon
 
Howrah bridge ppt
Howrah bridge pptHowrah bridge ppt
Howrah bridge ppt
 
Brooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudyBrooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudy
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)
 
1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015
 
Josh
JoshJosh
Josh
 
Alan sutton
Alan suttonAlan sutton
Alan sutton
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge construction
 
Engineering Landmarks in London
Engineering Landmarks in LondonEngineering Landmarks in London
Engineering Landmarks in London
 
Bridge Report
Bridge ReportBridge Report
Bridge Report
 
S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.
 
Physics project writing assesment
Physics project writing assesmentPhysics project writing assesment
Physics project writing assesment
 
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdfCase Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
 

Recently uploaded

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 

Recently uploaded (20)

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 

Quebec Bridge Collapse - Case Study

  • 2. About • Quebec bridge is a rail, road and pedestrian bridge situated on the St. Lawrence River, Quebec, Canada. • It was at time of construction the longest cantilever bridge in the world with clear span of 549 m. • The bridge construction was finally completed in 1917 after Two Failures or tragedies to bridge the harsh icy waters of the St. Lawrence river. • First collapse occurred on August 26, 1907. Second collapse occurred almost after a decade on September 11, 1916 • Quebec bridge is a cantilever truss bridge with two spans cantilever from both sides and simple span suspended in between. 25-Jan-19 Majzoob Mohammed Arbab 2
  • 3. History • The story of the bridge begins back in 1887 with the formation of Quebec Bridge company which came up with the proposal to erect the bridge over the river to increase business traffic in the city of Quebec and places nearby. • Various proposals for the bridge were submitted out of which The Phoenix Bridge Company’s proposal was selected which called for a cantilever bridge of 45 m in height above the high water mark. • Theodore Cooper, a well-known American bridge designer, was selected as the project’s consulting engineer by the Quebec Bridge company. He endorsed the Phoenix design as the “best and the cheapest” of those submitted, although he decided to lengthen the center span from 488 m to 549 m in order to eliminate the uncertainty of constructing piers in such deep water, lessen the effects of ice, and shorten the time of construction of the piers. 25-Jan-19 Majzoob Mohammed Arbab 3
  • 4. Concept Dimensions & Details 25-Jan-19 Majzoob Mohammed Arbab 4
  • 5. First Collapse 1/5 • As soon as the south anchor arm was completed (in early 1906) the assembly of the cantilever arm could begin (the falsework was then also moved to the other side of the river for the construction of the north anchor arm). • Using the anchor arm as a counterweight – securely anchored at the end for the uplift forces – the main span was being erected using the cantilever technique (one half from either side of the river). • At just about this point in the construction (in early 1906) it was discovered that the amount of steel material delivered to the bridge site considerably exceeded the originally estimated amount. It was because no correction for self weight of the structure was made when the span length was increased from 488 m to 549 m. Cooper however, decided to forge ahead and Not introduce any changes. 25-Jan-19 Majzoob Mohammed Arbab 5
  • 6. First Collapse 2/5 25-Jan-19 Majzoob Mohammed Arbab 6
  • 7. First Collapse 3/5 • When the cantilever had been extended further out over the river, increasing the stresses even more in the truss members – it was found that the out of plane bending of chord A9-L had increased from some 20 mm to alarmingly 57 mm. • Even though this deformation – representing an out-of-plane deflection of L/305 (the length L of the member being 17.44 m) – is hard to detect by the naked eye, it was a clear signal that something was quite wrong. 25-Jan-19 Majzoob Mohammed Arbab 7
  • 8. First Collapse 4/5 • Cooper, realizing the danger of the situation, wanting the construction to come to an immediate halt, telegraphed to the Phoenix Bridge Company: “Add no more load till after due consideration of facts’’. • However, the contractor (i.e. the Phoenix Bridge Company) was under great pressure not to delay the construction, so the work continued by unfortunately moving an erection crane one step further out on the cantilever. 25-Jan-19 Majzoob Mohammed Arbab 8
  • 9. First Collapse 5/5 • The A9L bottom compression chord, which was already bent, gave way under the increasing weight of the bridge. The load transferred to the opposite A9R chord, which also buckled. The piers were the only part of the structure that survived.25-Jan-19 Majzoob Mohammed Arbab 9
  • 11. Second Collapse • In spite of the enormity of the accident, it was decided that the project must be completed. In 1908, a board of engineers was appointed that arranged for and supervised the design and erection of a new bridge. Except for the piers, nothing from the previous structure was recoverable. • In April 1911, the contract was awarded to the St. Lawrence Bridge Company of Montreal. As before, the design called for a cantilever-type bridge, but it differed from the previous one with the lower chords of the cantilever arms several times stronger. One important innovation that added strength to the bridge was the K-truss design. 25-Jan-19 Majzoob Mohammed Arbab 11
  • 13. • Construction of the bridge started in 1913, and eventually the two approach spans, the anchor arms and cantilevers went up on either side of the river. By 1916, the bridge was nearly completed. • The workmen faced a difficult task in moving the span upstream, but all went well with that part of the job. The span was carried on scows that were guided by tugs. It was a slow process, but eventually the span was maneuvered into position between the cantilever arms where huge lifting hangers, attached to the ends of the arms, raised it by hydraulic means off the scows. The span was to be lifted two feet at a time in a repeat operation until it was in place between the two arms. 25-Jan-19 Majzoob Mohammed Arbab 13
  • 14. • The southwest corner of the span tore away and sagged. A few seconds later, the other ends pulled off their supports and the whole span came loose and disappeared into the river. Thirteen men were carried to their deaths and several others were injured.25-Jan-19 Majzoob Mohammed Arbab 14
  • 15. The investigation by the board of engineers determined that the span did not buckle as Larocque and others claimed. Rather, the loss resulted from the failure of a casting in the erection equipment that temporarily supported the southwest corner of the span. 25-Jan-19 Majzoob Mohammed Arbab 15
  • 16. Final Completion • On Sept. 20, 1917, the suspended span was lifted into position and fastened to the cantilever arms. At last, the world’s longest cantilever bridge was completed and the first train crossed it in October. Two months later it was opened to regular trains, vehicle and pedestrian traffic. 25-Jan-19 Majzoob Mohammed Arbab 16
  • 17. Major Causes of Failure • An underestimation of the self-weight of the structure • Temporary splicing of the chords using bolts • The load carrying capacity had been overestimated resulting in weak cross-sections • The stabilizing bars (the crossing diagonals and horizontals) were not strong enough to resist out-of-plane buckling of the compression chords 25-Jan-19 Majzoob Mohammed Arbab 17
  • 18. Lessons Learned • The collapse of the bridge finally led to the development of Canadian design specifications for bridge structures. • Engineering design is necessary for the means and methods of lifting operations. • The responsibility of execution and design of such an important structure must Not be left in the hands of one person 25-Jan-19 Majzoob Mohammed Arbab 18