This document discusses date fields in Primavera P6 scheduling software. It begins by introducing P6 and some of the key differences between how it and P3 handle dates. Specifically, P6 stores dates down to the second rather than requiring whole day increments. It then categorizes P6's various date fields and provides examples. The document explains how P6 calculates dates, which is based on hours/time periods rather than fixed day increments. It discusses early/late dates and how P6 calculates and displays them differently than other software.
Multi sites construction management and supervision - Oracle Primavera P6 Co...p6academy
Juliana Achcar is a planning engineer at Concremat Engineering who developed a construction management solution for a multi-site school construction project across several states in Brazil. The solution uses Primavera P6 Enterprise Project Portfolio Management integrated with the Team Member mobile app to provide real-time progress updates, dashboards, and earned value analysis for monitoring and controlling the complex, distributed project. Supervisors in the field use the app to update progress directly, ensuring accurate and timely schedule updates can flow to planning engineers and stakeholders for improved decision making.
1) Loading cost in a schedule can be done through either creating a global cost resource or expense item.
2) Loading cost as a resource provides more benefits like early/late cash flows, customizable resource curves, and automatic calculation of actual/remaining costs. However, it does not allow costs before/after an activity.
3) Loading cost as an expense allows costs before/after an activity but provides fewer cost analysis options and does not automatically calculate costs in all situations.
4) Overall, using a resource for cost loading provides more benefits for analysis, but an expense may be preferable in some limited cases. The method chosen should best suit the specific schedule and cost tracking needs.
The document discusses how to generate S-curves in Oracle Primavera P6 to analyze project progress. S-curves show cumulative costs, labor hours, or other metrics plotted against time and typically have an S-shape. In Primavera P6, S-curves can be generated by activity or resource in the usage profile windows. Various analysis can be done using S-curves, such as determining project growth, slippage, or progress by comparing baseline, target, and actual S-curves. The S-curves can then be published from Primavera P6 as prints or web pages for reporting to clients and management.
This document introduces and analyzes the "banana curve", which is a combination of the early and late progress or cost curves plotted on a single graph. It discusses how the banana curve can help project managers monitor project progress and identify variances compared to the planned schedule. It then provides four methods for generating the early and late curves from a Primavera P6 project schedule that can be combined to form the banana curve: using the activity usage profile, reports tool, activity usage spreadsheet, and resource assignment data. The document aims to explain what early and late curves are, how the banana curve is formed, and how project managers can benefit from this analysis and monitoring technique.
In this video you will learn
1- What is a Project
2- What is a Project Management
3- EPS & OBS Purpose
4- How to Create a New Project in P6 Software
Welcome to Primavera Training-02 ’ E-course on Oracle’s Primavera P6 Professional (Project Management application).
CivilMDC.com is an Online learning platform, offers educational training courses in the fields of Designing, software, technology and creative skills. The company, through its instructional video tutorials, offers courses in the areas of CAD, design, Analysis,Civil Engineering education, Planning and many more e-learning courses.
To Build a relationship, Please CLICK THE SUBSCRIBE BUTTON..
For the download of the Primavera P6 Professional Software , follow the link below, get register yourself before downloading of software.
https://edelivery.oracle.com/osdc/faces/Home.jspx;jsessionid=4G19HLHB74aadvpYjWAkwe-GriiTyj2OUoSp8IaqFdpwhvgjSq4E!-1802076090
If you face any difficulty...... Feel free to contact.
Contact Details
www.civilmdc.com
Professional Trainers
Email ID: civilmdcgroup@gmail.com
This document provides an overview and agenda for a presentation on integrating ERP and Primavera Unifier to track and manage project costs. The presentation discusses how cost overruns occur for projects and proposes an approach to integrate different systems like ERP, Primavera P6, and Unifier to provide a holistic view of project costs and simplify cost management. It demonstrates integrating these systems for activities like resource management, project scheduling and budgeting, procurement, and cost monitoring and control. The integration is intended to improve transparency, accountability, and communication for managing projects profitably.
This document discusses project scope management. It defines project scope as what is included in and excluded from a project, including the expected cost and timeline. The key activities of project scope management are scope planning, scope definition, creating a work breakdown structure (WBS), scope verification, and scope control. Any changes to the project scope require scope change control procedures. Effective scope management helps ensure a project delivers the intended outcomes within budget and schedule.
This document discusses date fields in Primavera P6 scheduling software. It begins by introducing P6 and some of the key differences between how it and P3 handle dates. Specifically, P6 stores dates down to the second rather than requiring whole day increments. It then categorizes P6's various date fields and provides examples. The document explains how P6 calculates dates, which is based on hours/time periods rather than fixed day increments. It discusses early/late dates and how P6 calculates and displays them differently than other software.
Multi sites construction management and supervision - Oracle Primavera P6 Co...p6academy
Juliana Achcar is a planning engineer at Concremat Engineering who developed a construction management solution for a multi-site school construction project across several states in Brazil. The solution uses Primavera P6 Enterprise Project Portfolio Management integrated with the Team Member mobile app to provide real-time progress updates, dashboards, and earned value analysis for monitoring and controlling the complex, distributed project. Supervisors in the field use the app to update progress directly, ensuring accurate and timely schedule updates can flow to planning engineers and stakeholders for improved decision making.
1) Loading cost in a schedule can be done through either creating a global cost resource or expense item.
2) Loading cost as a resource provides more benefits like early/late cash flows, customizable resource curves, and automatic calculation of actual/remaining costs. However, it does not allow costs before/after an activity.
3) Loading cost as an expense allows costs before/after an activity but provides fewer cost analysis options and does not automatically calculate costs in all situations.
4) Overall, using a resource for cost loading provides more benefits for analysis, but an expense may be preferable in some limited cases. The method chosen should best suit the specific schedule and cost tracking needs.
The document discusses how to generate S-curves in Oracle Primavera P6 to analyze project progress. S-curves show cumulative costs, labor hours, or other metrics plotted against time and typically have an S-shape. In Primavera P6, S-curves can be generated by activity or resource in the usage profile windows. Various analysis can be done using S-curves, such as determining project growth, slippage, or progress by comparing baseline, target, and actual S-curves. The S-curves can then be published from Primavera P6 as prints or web pages for reporting to clients and management.
This document introduces and analyzes the "banana curve", which is a combination of the early and late progress or cost curves plotted on a single graph. It discusses how the banana curve can help project managers monitor project progress and identify variances compared to the planned schedule. It then provides four methods for generating the early and late curves from a Primavera P6 project schedule that can be combined to form the banana curve: using the activity usage profile, reports tool, activity usage spreadsheet, and resource assignment data. The document aims to explain what early and late curves are, how the banana curve is formed, and how project managers can benefit from this analysis and monitoring technique.
In this video you will learn
1- What is a Project
2- What is a Project Management
3- EPS & OBS Purpose
4- How to Create a New Project in P6 Software
Welcome to Primavera Training-02 ’ E-course on Oracle’s Primavera P6 Professional (Project Management application).
CivilMDC.com is an Online learning platform, offers educational training courses in the fields of Designing, software, technology and creative skills. The company, through its instructional video tutorials, offers courses in the areas of CAD, design, Analysis,Civil Engineering education, Planning and many more e-learning courses.
To Build a relationship, Please CLICK THE SUBSCRIBE BUTTON..
For the download of the Primavera P6 Professional Software , follow the link below, get register yourself before downloading of software.
https://edelivery.oracle.com/osdc/faces/Home.jspx;jsessionid=4G19HLHB74aadvpYjWAkwe-GriiTyj2OUoSp8IaqFdpwhvgjSq4E!-1802076090
If you face any difficulty...... Feel free to contact.
Contact Details
www.civilmdc.com
Professional Trainers
Email ID: civilmdcgroup@gmail.com
This document provides an overview and agenda for a presentation on integrating ERP and Primavera Unifier to track and manage project costs. The presentation discusses how cost overruns occur for projects and proposes an approach to integrate different systems like ERP, Primavera P6, and Unifier to provide a holistic view of project costs and simplify cost management. It demonstrates integrating these systems for activities like resource management, project scheduling and budgeting, procurement, and cost monitoring and control. The integration is intended to improve transparency, accountability, and communication for managing projects profitably.
This document discusses project scope management. It defines project scope as what is included in and excluded from a project, including the expected cost and timeline. The key activities of project scope management are scope planning, scope definition, creating a work breakdown structure (WBS), scope verification, and scope control. Any changes to the project scope require scope change control procedures. Effective scope management helps ensure a project delivers the intended outcomes within budget and schedule.
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel
The document provides guidelines for reviewing baseline construction schedules and updated schedules submitted by contractors. It discusses reviewing the schedules for conformance with contract requirements and construction best practices. The review includes checking global schedule parameters, scheduling mechanics, activity durations and logic, and analyzing the schedule's reasonableness. Subcontractor input, an appropriate level of detail, and proper consideration of weather factors are important for developing a high quality, realistic baseline schedule.
The document outlines the RIBA Plan of Work, which provides a systematic approach to managing projects. It describes the 12 key stages of a construction project from appraisal to after practical completion. Each stage involves specific tasks such as developing proposals, obtaining approvals, preparing tender documents, and overseeing construction. The plan is intended to help structure project management processes and information exchange between parties involved in a construction project.
The document is a template for a Project Administration Plan that contains summaries of plans for various aspects of project management including scope management, time/cost management, quality management, human resource management, communication management, risk management, and procurement management. It provides optional text for different approaches that can be selected and customized for a specific project.
This document outlines the key aspects of project management. It defines projects and operations, and provides examples of each. Projects are unique, temporary endeavors with a defined start and end date, while operations are ongoing, routine tasks. The document then discusses the characteristics of projects, definitions of project management, the roles and responsibilities of a project manager, the project management framework including its nine knowledge areas, and constraints of project scope, time, cost, and quality. Project life cycle phases and the construction team are also mentioned.
This course is a detailed course about Primavera Project Management.
The course contains so many details about the software and its relation to the project management science.
the material consists of 7 sessions.
this material is a primer effort and might be updated then uploaded.
I hope it will be beneficial to the persons who cares about project management.
The document discusses various aspects of project termination including:
1. Activities after project completion involve closing tasks, payments, and documenting lessons learned.
2. Projects can terminate through extinction (success), addition (institutionalization), integration (distribution to parent organization), or starvation (budget cuts).
3. A final report summarizes all project stages and allows readers to recreate the project steps. It includes sections like abstract, introduction, background, design, realization, evaluation, lessons learned, and references.
] po [ is an open-source project management software that integrates various business functions like CRM, project planning, collaboration, timesheets, and financial controlling. It provides a central repository for all project information and processes to improve project initiation, planning, tracking, resource management, and knowledge sharing. Key features include centralized project data, workflow automation, resource scheduling, timesheet tracking, and financial reporting.
This document provides an overview of basic functions and features in Primavera P6 for initial stage learners. It covers topics such as starting a new project, creating activities and defining relationships between them, setting up calendars, scheduling the project, assigning resources and costs, tracking progress with percent complete, creating baselines, importing and exporting project data, using filters and layouts, and generating common reports. The summary also introduces concepts like milestones, non-uniform resources, reflections, notes, risks, and thresholds.
Installation of primavera (optional)
Open primavera
Create EPS
Create your own project with minimum 30 activities(Live projects are preferable)
Data entry
Inserting activities
Assigning relationship
Activates codes
Basic formatting of Bars(Bar style, Bar label)
Inserting and modifying columns
Group by and short by
User defined filed
Interfering floats
Make 2 more of your self
Filters
New filters
Modify filters
Cases of Constraints
Case of difference between total float and free float
calendar
Import & Export
Live project Information
Filters ( 1-line, 2-line, 3-line Filters)
RESOURCE ASSIGNING AND LEVELLING
Resource Levelling
RESOURCE LOADING (Bell type, front loaded, back loaded, linear etc.)
EARNED VALUE ANALYSIS
Cost Account
Expenses
Reports
Role
User Defined fields
Admin Preferences
Renumbering Activities
Project Portfolio
Edit Columns
Save layout
Working with multiple projects
Activity Steps
Global change
Multiple Projects
USING WORK PRODUCTS AND DOCUMENTS
UPDATING PROJECT BY "AUTO ACTUALS" METHOD
UPDATING, SCHEDULING PROJECT - WITH SPOTLIGHT FEATURE
ASSIGN BASELINE
MAINTAIN BASELINE
PROJECT CODES
5 Steps Of Project Scheduling Process For Absolute BeginnersPraveen Malik, PMP
This presentation explains the 5 basic steps and associated techniques of project scheduling process. It is meant for beginners and intermediate level professionals.
Project cost management a simplified approach white paper - Oracle Primaver...p6academy
Project organizations struggle with predicting long-term project costs, assessing return on investment, and managing cash flow over a project's lifecycle. Integrating financial systems and Oracle Primavera applications can provide cost visibility and control. The document proposes integrating ERP, Primavera Unifier, and Primavera P6 to facilitate sharing accurate, timely data across teams. This would automate processes to improve productivity, empower stakeholders, streamline workflows, and improve task management for executing profitable projects aligned with organizational strategy.
This document provides information about administering projects including common project administration tasks, what constitutes a project, and assessments for two subjects - Administer Projects BSBADM407B and Develop Teams and Individuals BSBLED401A.
Key tasks of project administration include communicating, preparing documents like budgets and reports, evaluating costs, planning, allocating resources and responsibilities, problem solving, and monitoring progress. A project is defined as a one-off task with clear goals, timelines and limited resources.
The assessments for the two subjects involve creating project planning and monitoring tools, delivering a training session, and individual reflective reports that analyze skills and provide a learning plan based on identified gaps. Project scope defines the high-level
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
This document provides a project report for the planning, scheduling, and estimation of a residential building project consisting of a ground floor and first floor. It includes the project objective, various drawings of the site plan, floor plans, and elevations. It also provides details on the construction planning principles, estimation process, and a title abstract estimate with quantities and costs for various construction items.
This document provides guidance and instructions for submitting final reports for projects funded by the Alpine Space Programme 2007-2013. It outlines the documents and sections required for the final report, including a publishable summary of key achievements and lessons learned (Section A), a technical report on project impacts and cooperation (Section B), and a declaration from the lead partner (Section C). Instructions are provided for the last progress report, highlighting the transnational impact and updating the budget. Projects must maintain their website and outputs for at least two years after closure and comply with subsidy contract terms regarding record keeping, dissemination of results, and avoiding substantial project modifications.
The document discusses key steps for effective construction project scheduling including examining contracts, listing obligations, dividing the project into work areas, accounting for technology and sequence, calculating duration and costs, and adjusting schedules over time. It also describes how network diagrams can help planning by visually showing precedence relationships between activities and how the flow of work. Two common types of network diagrams - activity-on-arrow and activity-on-node - are described as well as how activities differ from milestone events.
The document outlines the steps to properly close a project: 1) Get acceptance from the customer that deliverables meet requirements. 2) Conduct an evaluation to determine if goals/objectives were achieved on time and on budget. 3) Write a final report summarizing the project and lessons learned. 4) Celebrate the completion with the project team to recognize their work.
This document provides a template for a project plan that includes sections on the planning basis, project plan details, and appendix. The planning basis section outlines the project scope, milestones, phases, activities, tasks, effort required for each task, and resources allocated. The project plan section provides a summarized schedule, lists dependencies between phases and activities, and outlines any assumptions and constraints. An appendix can include additional relevant documents like a detailed project schedule.
The document outlines a human resource plan for a "Smart Homes" project. It includes roles and responsibilities for team members, a project organization chart, and a staffing management plan covering how resources will be acquired and trained, performance reviews, and a recognition and rewards system. Key roles include a project manager, architect, structural engineer, interior decorator, procurement manager, and accountant. A resource histogram shows projected work hours needed over the course of the project timeline.
Dashboard Reporting Using Business Intelligence provides an dynamic approach to the visibility of the progress to the team. It also enables the team to provide real time information on the project status.
The document provides an overview of project management offices (PMOs) and Microsoft Project Online. It discusses what a PMO is, why organizations establish PMOs, and how to set up a PMO in 5 phases. It then provides examples of PMOs from different organizations and industries. Finally, it gives a high-level overview of Project Online, its target users, top 10 benefits, and key terms.
This document describes Ryan Mifsud's approach to professional project management. It involves managing the end-to-end delivery of IT solutions through a phased approach. The phases include engagement, design, proof of concept and pilot testing, deployment, and close. Methodologies like PRINCE2 and PMI are used along with tools like RAG reporting and financial tracking spreadsheets. The goal is to deliver projects on time, on budget, and with quality assurance through an emphasis on people, process, and innovation.
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel
The document provides guidelines for reviewing baseline construction schedules and updated schedules submitted by contractors. It discusses reviewing the schedules for conformance with contract requirements and construction best practices. The review includes checking global schedule parameters, scheduling mechanics, activity durations and logic, and analyzing the schedule's reasonableness. Subcontractor input, an appropriate level of detail, and proper consideration of weather factors are important for developing a high quality, realistic baseline schedule.
The document outlines the RIBA Plan of Work, which provides a systematic approach to managing projects. It describes the 12 key stages of a construction project from appraisal to after practical completion. Each stage involves specific tasks such as developing proposals, obtaining approvals, preparing tender documents, and overseeing construction. The plan is intended to help structure project management processes and information exchange between parties involved in a construction project.
The document is a template for a Project Administration Plan that contains summaries of plans for various aspects of project management including scope management, time/cost management, quality management, human resource management, communication management, risk management, and procurement management. It provides optional text for different approaches that can be selected and customized for a specific project.
This document outlines the key aspects of project management. It defines projects and operations, and provides examples of each. Projects are unique, temporary endeavors with a defined start and end date, while operations are ongoing, routine tasks. The document then discusses the characteristics of projects, definitions of project management, the roles and responsibilities of a project manager, the project management framework including its nine knowledge areas, and constraints of project scope, time, cost, and quality. Project life cycle phases and the construction team are also mentioned.
This course is a detailed course about Primavera Project Management.
The course contains so many details about the software and its relation to the project management science.
the material consists of 7 sessions.
this material is a primer effort and might be updated then uploaded.
I hope it will be beneficial to the persons who cares about project management.
The document discusses various aspects of project termination including:
1. Activities after project completion involve closing tasks, payments, and documenting lessons learned.
2. Projects can terminate through extinction (success), addition (institutionalization), integration (distribution to parent organization), or starvation (budget cuts).
3. A final report summarizes all project stages and allows readers to recreate the project steps. It includes sections like abstract, introduction, background, design, realization, evaluation, lessons learned, and references.
] po [ is an open-source project management software that integrates various business functions like CRM, project planning, collaboration, timesheets, and financial controlling. It provides a central repository for all project information and processes to improve project initiation, planning, tracking, resource management, and knowledge sharing. Key features include centralized project data, workflow automation, resource scheduling, timesheet tracking, and financial reporting.
This document provides an overview of basic functions and features in Primavera P6 for initial stage learners. It covers topics such as starting a new project, creating activities and defining relationships between them, setting up calendars, scheduling the project, assigning resources and costs, tracking progress with percent complete, creating baselines, importing and exporting project data, using filters and layouts, and generating common reports. The summary also introduces concepts like milestones, non-uniform resources, reflections, notes, risks, and thresholds.
Installation of primavera (optional)
Open primavera
Create EPS
Create your own project with minimum 30 activities(Live projects are preferable)
Data entry
Inserting activities
Assigning relationship
Activates codes
Basic formatting of Bars(Bar style, Bar label)
Inserting and modifying columns
Group by and short by
User defined filed
Interfering floats
Make 2 more of your self
Filters
New filters
Modify filters
Cases of Constraints
Case of difference between total float and free float
calendar
Import & Export
Live project Information
Filters ( 1-line, 2-line, 3-line Filters)
RESOURCE ASSIGNING AND LEVELLING
Resource Levelling
RESOURCE LOADING (Bell type, front loaded, back loaded, linear etc.)
EARNED VALUE ANALYSIS
Cost Account
Expenses
Reports
Role
User Defined fields
Admin Preferences
Renumbering Activities
Project Portfolio
Edit Columns
Save layout
Working with multiple projects
Activity Steps
Global change
Multiple Projects
USING WORK PRODUCTS AND DOCUMENTS
UPDATING PROJECT BY "AUTO ACTUALS" METHOD
UPDATING, SCHEDULING PROJECT - WITH SPOTLIGHT FEATURE
ASSIGN BASELINE
MAINTAIN BASELINE
PROJECT CODES
5 Steps Of Project Scheduling Process For Absolute BeginnersPraveen Malik, PMP
This presentation explains the 5 basic steps and associated techniques of project scheduling process. It is meant for beginners and intermediate level professionals.
Project cost management a simplified approach white paper - Oracle Primaver...p6academy
Project organizations struggle with predicting long-term project costs, assessing return on investment, and managing cash flow over a project's lifecycle. Integrating financial systems and Oracle Primavera applications can provide cost visibility and control. The document proposes integrating ERP, Primavera Unifier, and Primavera P6 to facilitate sharing accurate, timely data across teams. This would automate processes to improve productivity, empower stakeholders, streamline workflows, and improve task management for executing profitable projects aligned with organizational strategy.
This document provides information about administering projects including common project administration tasks, what constitutes a project, and assessments for two subjects - Administer Projects BSBADM407B and Develop Teams and Individuals BSBLED401A.
Key tasks of project administration include communicating, preparing documents like budgets and reports, evaluating costs, planning, allocating resources and responsibilities, problem solving, and monitoring progress. A project is defined as a one-off task with clear goals, timelines and limited resources.
The assessments for the two subjects involve creating project planning and monitoring tools, delivering a training session, and individual reflective reports that analyze skills and provide a learning plan based on identified gaps. Project scope defines the high-level
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
This document provides a project report for the planning, scheduling, and estimation of a residential building project consisting of a ground floor and first floor. It includes the project objective, various drawings of the site plan, floor plans, and elevations. It also provides details on the construction planning principles, estimation process, and a title abstract estimate with quantities and costs for various construction items.
This document provides guidance and instructions for submitting final reports for projects funded by the Alpine Space Programme 2007-2013. It outlines the documents and sections required for the final report, including a publishable summary of key achievements and lessons learned (Section A), a technical report on project impacts and cooperation (Section B), and a declaration from the lead partner (Section C). Instructions are provided for the last progress report, highlighting the transnational impact and updating the budget. Projects must maintain their website and outputs for at least two years after closure and comply with subsidy contract terms regarding record keeping, dissemination of results, and avoiding substantial project modifications.
The document discusses key steps for effective construction project scheduling including examining contracts, listing obligations, dividing the project into work areas, accounting for technology and sequence, calculating duration and costs, and adjusting schedules over time. It also describes how network diagrams can help planning by visually showing precedence relationships between activities and how the flow of work. Two common types of network diagrams - activity-on-arrow and activity-on-node - are described as well as how activities differ from milestone events.
The document outlines the steps to properly close a project: 1) Get acceptance from the customer that deliverables meet requirements. 2) Conduct an evaluation to determine if goals/objectives were achieved on time and on budget. 3) Write a final report summarizing the project and lessons learned. 4) Celebrate the completion with the project team to recognize their work.
This document provides a template for a project plan that includes sections on the planning basis, project plan details, and appendix. The planning basis section outlines the project scope, milestones, phases, activities, tasks, effort required for each task, and resources allocated. The project plan section provides a summarized schedule, lists dependencies between phases and activities, and outlines any assumptions and constraints. An appendix can include additional relevant documents like a detailed project schedule.
The document outlines a human resource plan for a "Smart Homes" project. It includes roles and responsibilities for team members, a project organization chart, and a staffing management plan covering how resources will be acquired and trained, performance reviews, and a recognition and rewards system. Key roles include a project manager, architect, structural engineer, interior decorator, procurement manager, and accountant. A resource histogram shows projected work hours needed over the course of the project timeline.
Dashboard Reporting Using Business Intelligence provides an dynamic approach to the visibility of the progress to the team. It also enables the team to provide real time information on the project status.
The document provides an overview of project management offices (PMOs) and Microsoft Project Online. It discusses what a PMO is, why organizations establish PMOs, and how to set up a PMO in 5 phases. It then provides examples of PMOs from different organizations and industries. Finally, it gives a high-level overview of Project Online, its target users, top 10 benefits, and key terms.
This document describes Ryan Mifsud's approach to professional project management. It involves managing the end-to-end delivery of IT solutions through a phased approach. The phases include engagement, design, proof of concept and pilot testing, deployment, and close. Methodologies like PRINCE2 and PMI are used along with tools like RAG reporting and financial tracking spreadsheets. The goal is to deliver projects on time, on budget, and with quality assurance through an emphasis on people, process, and innovation.
monitoring your project (and portfolio) on a consistent manner, enabling Stakeholders receiving the correct information about their strategic decisions( projects)
This document provides an overview of a Project Management Office's (PMO) methodology for project delivery. It includes sections on PMO roles and responsibilities, phases of project delivery, key performance indicators, tools used by the PMO, and processes for activities like status reporting, risk management, and quality assurance. The goal of the PMO methodology is to ensure successful project delivery in terms of being on time, on budget, and meeting client and employee satisfaction objectives.
eCIO PPT Roles for a SAP and Systems Integration ProjectDavid Niles
The document outlines the roles and responsibilities of an IT Project Management Office (PMO) for a large Systems Integration project using the ASAP (Accelerated SAP) methodology. It describes the six phases of the ASAP methodology and provides details on deliverables, milestones, and objectives for each phase. It also defines the roles of various project managers, administrators, and SAP specialists involved in the project and how they would be organized and report within the proposed PMO structure.
The 3-day training program provides an overview of project management fundamentals and processes. It will define key concepts, compare methodologies, evaluate BMW's current practices, and apply the generic project lifecycle of initiation, planning, implementation, and closure. Participants will complete introductory and learning activities to develop project documents including a terms of reference, plan, schedule, and risk assessment. The program aims to establish best practices for effective project management at BMW.
Pmp project management professional free sampleNada Sallam
This document provides an overview of project management concepts and techniques for preparing for the Project Management Professional (PMP) exam. It defines project management, discusses the triple constraint of scope, time and cost, and introduces the project life cycle and organizational structures. Methods for estimating activity durations like three point estimates and reserve analysis are also summarized.
This document discusses the evolution of project management processes at Advanced Technology Division (ATD) from version 1.0 to 2.0. It explains how early PM tools focused on cost, schedule and resources for individual projects. It then summarizes how ATD developed a standardized project lifecycle template, identified resources, and began capturing more program-level data on priorities and capacity planning. Finally, it outlines how the new Innovator PM tool integrated projects and provides more timely updates across multiple levels from individual projects to programs.
The document discusses enterprise portfolio management and provides information on several topics:
- It introduces the concepts of enterprise portfolio management and presents a specific business case.
- It shows a network of enterprise portfolio management business partners and discusses project and enterprise environments.
- It also mentions project portfolio management, people, projects, companies, and various applications and reporting and analysis functions.
This document discusses various tools and techniques for project management planning and execution. It covers selecting project management software tools, developing risk management plans, quality management plans, procurement management plans, and monitoring and controlling the project schedule, costs, communications and issues. It emphasizes establishing a project baseline, tracking project metrics, analyzing variances from the plan, and managing changes through a formal change control process.
This document discusses project portfolio management implementation at IT Services Hungary Ltd. It provides background on the company's ownership history and growth. It explains that as the company grew, project management became more complex and a centralized project portfolio management approach was needed. The document outlines the objectives and requirements for a project portfolio management framework. It describes the organizational structure and governance process established, including a Project Portfolio Board. A high-level project lifecycle is presented, from project initiation and selection through monitoring and closure. An implementation roadmap is outlined to improve maturity over time. Stakeholder feedback on the approach is summarized, including suggestions around prioritization and resource allocation processes.
Pmp project management professional free sampleNada Sallam
This document provides an overview of project management concepts and techniques. It defines project management, discusses the triple constraint of scope, time and cost, and introduces project life cycles and organizational structures. Methods for estimating activity durations like three point estimates and PERT calculations are presented. The document also covers topics like developing the work breakdown structure, validating scope, and developing the project schedule using tools like critical path method.
Here is the Project Time Management Part 1 as a part of PMP Training by SKillogic Knowledge Solutions. Other slides will upload soon.
If you are looking for PMP Certification training classes in Bangalore, Chennai, Delhi, Hyderabad, and Mumbai visit http://in.skillogic.com/
The document provides an agenda for a presentation on an EPM tool (MS-Project Server 2013), including: an introduction to PMO and EPM methodology and tools; the main functions of MS-Project Server; the MS-Project Server dashboard; SharePoint workflows; EPM deployment architecture; integrating EPM with ALM; and using InfoPath. It also discusses how MS-Project Server can implement portfolio management features and workflows using SharePoint Designer 2013.
Epm demonstration projerct online and project server 2013Jerome Quinton
This document outlines an EPM demonstration by Pcubed. It introduces Pcubed and their long-term Microsoft partnership. It then discusses the key functional areas of Project Server and Project Online like portfolio selection, resource management, scheduling, collaboration, and reporting. The document concludes with an overview of Pcubed's implementation approach and support services.
Hatem Hegazi discusses avoiding unrealistic schedules and provides tips for developing realistic schedules that follow best practices. Some key points:
- Unrealistic schedules can be caused by rush pressures, lack of planning, or underestimating the work. Realistic schedules require proper planning, team buy-in, and accounting for changes.
- The AACE recommends following their practices for schedule planning, development, review, management and control to develop realistic schedules. This includes defining activities, logic, durations, and contingencies.
- Realistic schedules also require defining responsibilities, developing the work breakdown structure, and outlining the schedule with appropriate level of detail and constraints.
The document discusses project management paradigms and approaches. It defines project management as having the customer agree that the project is "done" based on measures that are meaningful to them. It then discusses various frameworks for project management like PMI PMBOK, CMMI, Prince2, and Scrum. A key theme is that these approaches identify the work, plan the work, estimate costs, execute the work, measure performance, and adjust plans as needed while engaging stakeholders. The document advocates using deliverables-based planning with four core processes: identify capabilities and requirements, establish a project baseline, execute against the baseline, and manage changes.
Startup Program Management Playbook (v1) - Pls check for v2Becky Flint
This document discusses program management for startups and scaling companies. It provides an overview of how program management can help with strategic planning, portfolio management, and project execution. It then describes the specific processes and tools used by the author to implement program management, including standardizing a product development lifecycle, configuring tools like Jira and Confluence, and implementing cadences and artifacts to track progress and resources.
This document discusses planning and scheduling a residential construction project using Primavera software. The main goals of the project are to study the basics of Primavera, select a residential building plan, estimate quantities, schedule activities, create a work breakdown structure, budget the project, and generate reports. Primavera is a project management tool that uses critical path methodology to calculate activity durations and floats. It has Gantt chart views to display the project schedule. The document defines key terms like project, activity, resource, and time and cost parameters that can be measured using planning software. It also describes the project life cycle and monitoring process to ensure the project stays on schedule and budget.
Similar to Project planning logic, how to optimise your schedule (20)
The document discusses mobility as a service (MaaS) and the key aspects of developing a comprehensive MaaS system. It outlines technologies like blockchain, artificial intelligence, and real-time data integration that can power a MaaS platform. It emphasizes building a customer-centric service that provides route planning, ticketing, payment options and personalized assistance. The goal is to create an optimal customer experience, including for those with special needs, through predictive analytics and swift response to disruptions. Infrastructure support like widespread connectivity and cashless payments are also highlighted as important success factors for MaaS.
The document discusses the roles and responsibilities of a Project Management Office (PMO). It outlines various project functions the PMO is involved in including requirements management, architectural design, testing, training, implementation, acceptance, and risk assessment. It also provides examples of reporting and analytics used by the PMO to track project progress, costs, budgets, and quality.
The document discusses the implementation of the European Directive (EU) 2016/1148 (NIS Directive) for critical infrastructures. It provides an overview of the types of critical infrastructures that are in scope, such as energy, IT, transport, health, and finance. It then outlines a framework for identifying critical infrastructure assets and dependencies, assessing risks, implementing security measures, and auditing protections. This includes developing an inventory of hardware, software, networks and their configurations, as well as a statement of applicability, risk assessment, and documentation of security processes.
This document discusses Mobility as a Service (MaaS) in Flanders. It covers various aspects of a MaaS system including a route planner, ticketing, payment methods, journey guidance, use of data and artificial intelligence to optimize the customer experience. It also addresses accessibility for less mobile customers and features like indoor navigation. The document outlines a customer-centric approach with an emphasis on user profiles, preferences and privacy management. Blockchain and other technologies could also play a role in areas like settlement between transport service providers.
The document discusses forecasting costs for projects through various modeling techniques. It describes parametric cost estimating using mathematical formulas to relate cost drivers to project costs. The document also discusses using a rolling average approach and Monte Carlo simulations to forecast project costs. It emphasizes the importance of accurate data and metrics in developing a performant cost model to provide confident forecasts for executive management.
The document discusses bringing portfolio management (PMO) services to the next level. It proposes composing a balanced portfolio or roadmap that matches an organization's strategic ambitions. This involves ranking and prioritizing project initiatives based on factors like costs, benefits, and risks. It then demonstrates simulating different portfolio compositions to determine which provides the best outcome for an organization in terms of budget, costs, risks, cash flow, and return on investment. The goal is to provide data to help management make effective decisions.
bringing pmo to the next level! Managing your portfolio, optimising the outcome of the investment portfolio, enhancing the predictability of the expedient result: what will be cash flow, or our the market share next year, profit, costs, opex capex, ... it is all in your project portfolio!
how to start ? setting up tracking & reporting tool (MS Excel). All data are extracked from MS Project. aligned with Graphical project management reporting (earlier posted on Slideshare)
The document discusses setting up a Project Management Office (PMO) as a service to improve project success rates and organizational strategy execution. The PMO would execute the organization's strategy by composing a project roadmap, calculating returns on investment, and assigning resources and tools to projects. It would also take on a "watch dog" role to improve planning, reporting, risk management, and alignment of projects, programs and portfolios. Key metrics discussed for the PMO to monitor include time, cost, scope, quality and resource data. Charts are provided as examples to track schedule performance, cost performance, and milestone budgets versus actuals.
This document discusses using a balanced scorecard (BSC) approach combined with system dynamics to improve project management and organizational performance. It identifies key factors that impact outcomes like margins, such as costs, customer satisfaction, efficiency, and innovation. These factors are interrelated and must be balanced. The document recommends identifying metrics related to projects, the organization, performance, finance, and quality to measure these factors. Setting targets and tracking performance indicators and key goals will provide knowledge to learn and improve over time.
The document discusses the role and functions of a Trusted Archive Authority (TAA). A TAA is responsible for long-term storage of data and ensuring evidence of data integrity over time. The document outlines the key components and functionalities needed to enable a TAA service, including policies, procedures, infrastructure design, security, and audit capabilities. It also discusses document management systems, electronic signatures, timestamping, and other relevant standards and technologies.
12 steps to transform your organization into the agile org you deservePierre E. NEIS
During an organizational transformation, the shift is from the previous state to an improved one. In the realm of agility, I emphasize the significance of identifying polarities. This approach helps establish a clear understanding of your objectives. I have outlined 12 incremental actions to delineate your organizational strategy.
Org Design is a core skill to be mastered by management for any successful org change.
Org Topologies™ in its essence is a two-dimensional space with 16 distinctive boxes - atomic organizational archetypes. That space helps you to plot your current operating model by positioning individuals, departments, and teams on the map. This will give a profound understanding of the performance of your value-creating organizational ecosystem.
Comparing Stability and Sustainability in Agile SystemsRob Healy
Copy of the presentation given at XP2024 based on a research paper.
In this paper we explain wat overwork is and the physical and mental health risks associated with it.
We then explore how overwork relates to system stability and inventory.
Finally there is a call to action for Team Leads / Scrum Masters / Managers to measure and monitor excess work for individual teams.
Specific ServPoints should be tailored for restaurants in all food service segments. Your ServPoints should be the centerpiece of brand delivery training (guest service) and align with your brand position and marketing initiatives, especially in high-labor-cost conditions.
408-784-7371
Foodservice Consulting + Design
A presentation on mastering key management concepts across projects, products, programs, and portfolios. Whether you're an aspiring manager or looking to enhance your skills, this session will provide you with the knowledge and tools to succeed in various management roles. Learn about the distinct lifecycles, methodologies, and essential skillsets needed to thrive in today's dynamic business environment.
Employment PracticesRegulation and Multinational CorporationsRoopaTemkar
Employment PracticesRegulation and Multinational Corporations
Strategic decision making within MNCs constrained or determined by the implementation of laws and codes of practice and by pressure from political actors. Managers in MNCs have to make choices that are shaped by gvmt. intervention and the local economy.
Public Speaking Tips to Help You Be A Strong Leader.pdfPinta Partners
In the realm of effective leadership, a multitude of skills come into play, but one stands out as both crucial and challenging: public speaking.
Public speaking transcends mere eloquence; it serves as the medium through which leaders articulate their vision, inspire action, and foster engagement. For leaders, refining public speaking skills is essential, elevating their ability to influence, persuade, and lead with resolute conviction. Here are some key tips to consider: https://joellandau.com/the-public-speaking-tips-to-help-you-be-a-stronger-leader/
Sethurathnam Ravi: A Legacy in Finance and LeadershipAnjana Josie
Sethurathnam Ravi, also known as S Ravi, is a distinguished Chartered Accountant and former Chairman of the Bombay Stock Exchange (BSE). As the Founder and Managing Partner of Ravi Rajan & Co. LLP, he has made significant contributions to the fields of finance, banking, and corporate governance. His extensive career includes directorships in over 45 major organizations, including LIC, BHEL, and ONGC. With a passion for financial consulting and social issues, S Ravi continues to influence the industry and inspire future leaders.
Enriching engagement with ethical review processesstrikingabalance
New ethics review processes at the University of Bath. Presented at the 8th World Conference on Research Integrity by Filipa Vance, Head of Research Governance and Compliance at the University of Bath. June 2024, Athens
Project planning logic, how to optimise your schedule
1. 03-23-05April 2014
PROJECT PLANNING LOGIC(-al) viewPROJECT PLANNING LOGIC(-al) view
Presented by Jan Biets
Jan_biets@hotmail.com +32(0)477 32 90 11 Mechelen - Belgium
page 1 • view on planning
2. PMO – PMO as a ServicePMO – PMO as a Service April 2014 page 2 • View on PLANNING
• It is not the author’s intention to be aligned with whatever existing methodology,
nor framework;
• ‘projects’– in this presentation, ‘projects’ can mean projects, programme, or portfolio
ForewordForeword
3. PMO – PMO as a ServicePMO – PMO as a Service April 2014
Planning Logic : intention and purposesPlanning Logic : intention and purposes
page 3 • View on PLANNING
• What is the purpose:
– Increase success rate of -strategically- projects, by increasing / enhancing the
planning quality;
– Decrease failure rate of -strategically- projects, by optimising (improving) the
planning quality, optimising the elapsed time of project execution;
– Improve planning quality;
– Improve baseline information to take decision upon;
– Improve communication, by qualitative planning;
4. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : optimising you planningPLANNING – logic : optimising you planning
page 4 • View on Reporting
•Planning might be a complex task for a project manager;
•Although, it is the a priori straigth forward logical listing and
consistency of the de-rolling of tasks, thus his task: managing the
project with all tasks, sub-tasks, leading to a result: project delivery;
How to order the tasks?
•Correct ordering the tasks (most of the time chronologically, or
logically) might be very helpful to manage the project;
•Knowing what tasks to be linked is important to optimise the project
planning;
•finding the tasks (and identifying the correct order) in the (MS Project
) planning might be difficult, confusing and need your upmost
concentration (line x is the predecessor of line y);
The LOGIC is a tool which assists the project manager in linking most
optimal the tasks;
5. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : rules !PLANNING – logic : rules !
page 5 • View on Planning
Important to know (and apply):
•Never link summary tasks, to another / sub-sequent task
[ See presentation ]
•Always link tasks, status (deliverable), or milestones: measureable
facts;
•Could also be called ‘tollgate-ing’*
Tollgate:
Definition of tollgate: A measurable objective that is used to enable a prospective customer
to pass from one stage (e.g. task) to another (e.g. task) (according: Six Sigma )
6. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : what is in for me, PM !PLANNING – logic : what is in for me, PM !
page 6 • View on Planning
Tollgate:
Definition of tollgate: A measurable objective that is used to enable a prospective customer
to pass from one stage (e.g. task) to another (e.g. task) (according: Six Sigma )
Advantages:
•Analysing, knowing, and understanding your project;
•Quality check of the planning (most favourable order to execute);
•Identifying / understanding the ‘shortest way’ to deliver the project
(identifying / understanding critical path);
•Optimising & reducing elapsed time by logically flow of tasks (and
milestones)
Dis-advantages:
•none
7. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : basicsPLANNING – logic : basics
page 7 • View on Planning
‘typically ‘ “a project” starts with:
• signed contract,
• gathered ‘requirements’,
• “architectural design’ approved by appointed stakeholder(-s), and
• “functional design” approved by appointed stakeholder(-s);
After sign-off of the ‘functional design’ (milestone / deliverable) your
project is ready to set off!
E.g.proof of concept (PoC), bill of materials (BoM), operating system
(OS), hardware (HW),… can be started up, in parallel (simultaneously)
Important to know:
The steps (blue balls on the next slides) are always ‘finalised’ /
approved / formally accepted /or tollgated statuses
Note: the numbering is to increase the read-ability of your planning (WBS)
8. PMO – PMO as a ServicePMO – PMO as a Service April 2014 page 8 • View on PLANNING
PLANNING: example 1: 18 days elapsed timePLANNING: example 1: 18 days elapsed time
9. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : example 1PLANNING – logic : example 1
page 9 • View on Planning
Abbreviations:
CPM – Critical Path Method
FQT – final qualification testing
FAT – factory acceptance test
POC – proof of concept
logic planning composition
Critical Path method (elapsed time)
Rationale:
•quality check of planning
Explanation:
•optimising or reducing elapsed time
by logically flow of milestones.
10. PMO – PMO as a ServicePMO – PMO as a Service April 2014 page 10 • View on PLANNING
PLANNING: example 1: 12 days elapsed timePLANNING: example 1: 12 days elapsed time
Optimising the planning by linking the correct tasks on a logical manner,
offers a gain of 33%. In this example duration 18 days to 12 days.
11. PMO – PMO as a ServicePMO – PMO as a Service April 2014
1
Requirements
approved
2
Architectural
Design
approved
3
HL Functional
Design
approved
4
system
detailed
design appr.
4
1
purchased
4
2
installed
4
3
tested
5
approach
&strategy
5
1
Scenario’s
5
2
Data
preparation
Architectural
6
Instruct&
inform
Test
People
Process
7
Updated
UC
7
1
validated
UC
7
2
approved
UC
6
1
Profiling&
organisation
6
2
OPS-training
System
8
installed
8
2
configured
5
3
Final tested
9
Acceptance (for factory
qualification testing)
1
0
Final
Acceptance
& production
31/jul
7
3
approved
Detailed
FD(R2)
‘Project’ As-built
file&documentation
Administration
6
2
SYS-training
8
1
drivers
Life Cycle
mgt
1
1
Life cycle
mgt
Abbreviations:
UC: use case
12. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : example 3PLANNING – logic : example 3
page 12 • View on PLANNING
13. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : example 4PLANNING – logic : example 4
page 13 • View on PLANNING
14. PMO – PMO as a ServicePMO – PMO as a Service April 2014
PLANNING – logic : example 5PLANNING – logic : example 5
page 14 • View on PLANNING
M
1
M
2
M
3
Requirements approved
Architecture design
approved
Functional design (FD)
approved
M
4
PCB: Detailed
design
approved
M
4
PCB:
prototype
approved
Ticketer
detail design
approved
M
4
Ticketer
prototype
approved
M
5
M
8
Drivers:detail
design
approved
M
9
Ticketer OS:
released
M
5
.
1M
5
.
2
M
5
Ticketer MOS
port approved
Ticketer MOS
port release
approved
Master device
prototype
approved
M
6
Master device
CE certified
Master device
housing detail
design
approved
M
4
Master device
housing
prototype
approved
M
4
Master device
business
application
detail design
approved
M
9
Master device
business
application
phase1
released
M
9
Master device
business
application
phase2
released
M
9
Master device
business
application
phase3
released
M
9
Master device
business
application
released FQT
M
9
Technical
frame
detailed
design
approved
M
8
Technical
frame
released
M
8
Master device
tooling
released
M
7.
1
Master device
BoM released
M
8
Master device
sw released
M
8
Master device
released for
production
M
8
15. PMO – PMO as a ServicePMO – PMO as a Service April 2014
Easy to modify according the nature of your project
page 15 • View on PLANNING
PLANNING – logic : and now youPLANNING – logic : and now you
16. PMO – PMO as a ServicePMO – PMO as a Service April 2014
Time is up.
Much more to talk about this interesting topic….
Questions ?
Linkedin Jan Biets - Jan_biets@hotmail.com - +32(0)477 329011
page 16 • View on Planning
? ?????? ? ?
17. PMO – PMO as a ServicePMO – PMO as a Service Juni 2012
Time is up. Much more to talk about this interesting topic….
Questions ?
Linkedin Jan Biets - Jan_biets@hotmail.com - +32(0)477 329011
page 17 • View on Reporting
? ?????? ? ?