A Framework for
Project Management
The Project Management Institute
Education Department
2Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Related materials:
 ProjectManager88.info/free-ebook-52-secrets-to-be-professional-
project-manager
 ProjectManager88.info/free-257-project-management-templates
 ProjectManager88.info/free-ebook-62-tips-to-improve-project-
effectiveness
3Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Welcome to this seminar, A Framework for Project Management. It is designed to
provide a basic structure or model that can be helpful in thinking about, understanding,
discussing and managing projects. It will prepare you to develop more advanced skills
by applying seminar content to your position responsibilities, studying the recommended
readings in project management (see Appendix C), and in taking other seminars offered
by PMI® and educational organizations who subscribe to PMI standards of project
management.
During this seminar we ask you to focus on applying these concepts to real-world
projects through your active participation in the exercises and discussions based on your
unique experiences.We believe this learning experience can help you succeed in today’s
environment of constant change, high performance expectations, resource constraints
and global challenges.
PMI is grateful for the contributions of time, energy, and professional expertise of
many PMI members who have reviewed the material and made many suggestions to
improve its effectiveness.
Good luck on what we hope will be an enjoyable educational experience!
Welcome
4Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Your Expectations
 What would you like to learn from this experience?
 Solution to a specific problem?
 Project management concepts/knowledge?
 Specific skills?
 Other?
5Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Additional materials
A. Seminar Evaluation Forms
B. Exercises
C. Resources for Project Management Professional Candidates
A Framework for
Project Management Units
1. Introduction and Key Concepts 6. Controlling Projects
2. Project Life Cycle Models 7. Closing Projects
3. Initiating Projects 8. Organizational Impacts
4. Planning Projects 9. Overview of Knowledge Areas
5. Executing Projects 10. Role of the Project Manager
6Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 1: Introduction and Key Concepts
Upon completion, you will be able to …
 Define key PM concepts
 List the reasons why PM is needed
 Explain the difference between projects and operations
 Identify trends in the PM environment
 List project success and failure factors
 Identify potential benefits of PM
7Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key PM Concepts from the PMBOK® Guide
T h is f ig u r e is a c o n c e p t u a l v ie w o f th e s e
r e la tio n s h ip s . T h e o v e r la p s s h o w n a r e n o t p r o p o r t io n a l.
A p p li c a t io n
A r e a K n o w le d g e
a n d P r a c t ic e
G e n e r a l
M a n a g e m e n t
K n o w l e d g e
a n d P r a c t ic e
T h e P r o je c t
M a n a g e m e n t
B o d y o f K n o w le d g e
G e n e r a l ly A c c e p t e d
P r o je c t M a n a g e m e n t
K n o w l e d g e a n d P r a c t ic e
8Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
* Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
Why Do We Need Project Management?*
 Exponential expansion of human knowledge
 Global demand for goods and services
 Global competition
 Above requires the use of teams versus individuals
9Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project and Statement of Work (SOW)
 A project is “a temporary endeavor undertaken to create a unique
product or service.”
 A SOW is a narrative description of products or services to be supplied
under contract.
10Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Management
“The application of knowledge, skills, tools and techniques
to project activities in order to meet or exceed stakeholder needs
and expectations from a project.”
11Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
PM Environment
Discussion Question
 What are some trends that impact the environment
in which projects are managed today?
12Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Accelerating Trends
 Corporate globalization
 Massive mergers and reorganizations
 Flatter organizations
 Short-term results driven
13Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Accelerating Trends (continued)
 Team environment
 Contract PM and outsourcing
 Primacy of interpersonal skills
 Multinational projects
 Importance of cultural differences
 Dependence on technology
14Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
A Balancing Act
Schedule requirements cost
Source: William Gendron, presentation at 1998 PMI Global Forum
Business
Objective
RiskRisk
The Project
Customer
Expectation
15Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
A Balanced Project
Time Cost
Scope
Quality
16Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Business
Objectives
Expectation and Objective Congruency
Client/Customer Expectations
Low High
Low OK
Customer wants
more than the
organization
intends to provide.
High
Business needs
more from the project
than the customer.
OK
17Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Contrast Projects and Operations
Discussion Question
 How are “projects” different from “operations”?
18Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Operations
 Semi-permanent charter,
organization, and goals
 Maintains status quo
 Standard product or service
 Homogeneous teams
 Ongoing
Contrast Projects and Operations
Projects
 Create own charter,
organization, and goals
 Catalyst for change
 Unique product or service
 Heterogeneous teams
 Start and end date
19Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 1-1
PM Pitfalls and Pluses
 Looking back on projects with which you were associated, what were
the top three factors that caused serious problems?
 That created a perception of success?
20Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Common Pitfalls
 Unclear objectives
 Lack of senior management support
 Lack of effective project integration
 Inadequate funding
 Change in business priorities
 Original assumptions invalid
 Ineffective team
 Lack of effective communication processes
 Other?
21Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Source: NASA study, “Determination of Project Success,” 1974, by David C. Murphy, Bruce N. Baker, and Dalmar Fisher
Factors Affecting Project Success
 Coordination and relations
 Adequacy of structure and control
 Project uniqueness, importance, and public exposure
 Success criteria salience and consensus
 Competitive and budgetary pressure
 Initial over-optimism, conceptual difficulty
 Internal capabilities buildup
22Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Potential Benefits of PM for the Organization
 Improved control
 Improved project support opportunities
 Improved performance
23Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Potential Benefits of PM for You
 Recognition of PM as a profession
 Future source of company leaders
 High visibility of project results
 Growth opportunities
 Build your reputation and network
 Portable skills and experience
24Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Integration Management
Cost Time
Integration
Quality
25Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Summary
 Defined key PM concepts
 Described why PM is needed
 Explained difference between projects and operations
 Identified trends in the PM environment
 Discussed project success and failure factors
 Identified potential benefits of PM
26Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 2: Project Life Cycle Models
Upon completion, you will be able to …
 List the purpose and types of project life cycle models
 Distinguish between project and product life cycle
 Define the role of phase reviews in PM
 Apply a model to a hypothetical and a real project
27Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Concepts
 Project phase: “A collection of logically related project activities usually
culminating in the completion of a major deliverable.”
 Project life cycle: “Collectively the project phases are known as the
project life cycle.”
 Product life cycle: The natural grouping of ideas, decisions, and actions
into product phases, from product conception to operations to product
phase-out.
28Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Generic Cost and Staffing Life Cycle
T i m e
I n it ia l
P h a s e
F in is hS ta r t
I n t e r m e d ia te P h a s e s
( o n e o r m o r e )
F in a l
P h a s e
C o s t a n d
S t a f f in g
L e v e l
29Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Life Cycle
Example Phases
Concept and
Proposal
Development
Implementation
Termination
Verification
Final PhaseIntermediate PhasesInitial Phase
30Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Pharmaceutical Project Life Cycle Model
D r u g S o u r c in g
D is c o v e r y S c r e e n in g
P r e c lin ic a l
D e v e lo p m e n t R e g is t r a tio n ( s ) W o r k u p P o s t s u b m is s io n A c tiv it y
P a te n t P r o c e s s
S c r e e n in g
L e a d
Id e n tifie d
P r e c lin ic a l
IN D
W o r k u p
F ile
IN D
F ile
N D A P o s t r e g is tr a tio n A c tiv ity
P h a s e I
C lin ic a l
T e s ts
P h a s e II
C lin ic a l
T e s ts
P h a s e III
C lin ic a l
T e s ts
A
P
P
R
O
V
A
L
F o r m u la t io n S ta b ility
P r o c e s s D e v e lo p m e n t
M e t a b o lis m
T o x ic o lo g y
T e n P lu s Y e a r s
31Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Construct
Spiral Methodology
Design
IdentifyEvaluate
Test
Evaluation
Evaluation
Risk
Analysis Business
Requirements
System
Requirements
Subsystem
Requirements
Unit
Requirements
Conceptual
Design
Logical
Design
Physical
Design
Final
Design
Proof of
Concept
First
Build
Second
Build
Final
Build
Deploy Operations and
Production Support
32Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Importance of Phase Reviews

Requirements Review
General Design Review
Detailed Design Review
Unit Test
Proposal
Preparation
Requirements
Analysis
General Design
Detailed Design
Code and Debug
33Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Phase Initiation Example
Detailed Design Phase
 Ensure correctness and completeness of previous phase, e.g., general
design phase
 Assess all aspects of requirements, design approach, and deliverables
 Identify and work off items
 Determine contractor rewards/payment for closing phase
 Conduct a readiness review to begin next phase, e.g., detailed design
phase
 Resource estimates and availability
 Design maturity
 Project plan review and update
 Secure stakeholder approval to proceed
34Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 2-1
Project Life Cycle Model
 Divide a current project on which you are working into phases, name
them, and write a brief statement of purpose for each phase
35Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Summary
 Explained the concept and purpose of project life cycles
 Defined the role of phase reviews in PM
 Described life cycle models
 Differentiated project life cycle and product life cycle
 Applied a model to hypothetical and real projects
36Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 3: Initiating Projects
Upon completion, you will be able to …
 List the main functions of each PM process group
 Describe the purpose of the initiation process
 Identify its inputs and outputs, tools and techniques
 Develop a sample project charter
 Give an example of how process groups can apply to the project as a
whole or to a project phase
37Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process Definition
 “A series of actions people take to bring about a desired result.”
 Types of processes
 Project management processes
 Product-oriented processes
 Business-oriented processes
38Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process Groups
Initiating
Processes
Planning
Processes
Controlling
Processes
Executing
Processes
Closing
Processes
39Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process Interactions
 Inputs
 Tools and techniques
 Outputs
 Taxonomy
40Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process Group Overview
T o t h e
P la n n i n g
P r o c e s s e s
( F i g u r e 3 – 5 )
I n i t i a t i n g P r o c e s s e s
5 .1
I n it ia t io n
41Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose of Initiation Process
1. To commit the organization to a project or phase
2. To set the overall solution direction
3. To define top-level project objectives
4. To secure the necessary approvals and resources
5. Validate alignment with strategic objectives
6. To assign a project manager
42Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Product description
2. Strategic plan
3. Project selection criteria
4. Historical information
“Initiation is the process of
formally recognizing that a new
project exists or that an existing
project should continue into its
next phase.”
1. Project charter
2. Project manager identified/
assigned
3. Constraints
4. Assumptions
1. Project selection methods
2. Expert judgment
Initiating Core Process—Initiation
43Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Charter
“A document issued by senior management that
provides the project manager with the authority to apply
organizational resources to project activities.”
44Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Charter Content
 Business need
 Project objectives
 Project deliverables
 Assumptions
 Constraints
 Key staff
 Written authorization
45Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 3-1
Project Charter
 Using the handout, complete the sample project charter
 Assume you are the project manager
 As an example, choose an anticipated major project assignment
46Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Sample Initiating Activities
 Negotiate, write, and refine the project charter
 Confirm how the project links to the business need
 Identify management responsibilities
 Identify geographic locations involved
 Test top-level objectives versus strategic business plans
 Make strategic procurement decisions, e.g., make, buy, or identify
qualified vendors
47Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Outputs of Initiation Process
 Project charter
 Project manager identified/assigned
 Other key positions identified/assigned
 Constraints identified
 Assumptions identified
48Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 4: Planning Projects
Upon completion, you will be able to …
 Describe the purposes of the planning processes
 Identify the inputs and outputs of core planning processes
 Describe the function and develop sample planning deliverables such as
a scope statement, WBS, and milestone chart
 List the major tools and techniques used in the core planning processes
 Identify the planning facilitating processes and their functions
49Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Planning Process Group
Initiating
Processes
Planning
Processes
Controlling
Processes
Executing
Processes
Closing
Processes
50Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose of Planning Processes
To develop a project plan that:
 Facilitates later accomplishment*
 Ensures project wide integration
 Monitors change effectively
 Provides decision support information to stakeholders
 Can be updated by iterative planning activities
* Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
51Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
C o r e P r o c e s s e s
4 .1
P r o je c t P la n
D e v e lo p m e n t
7 .3
C o s t
B u d g e tin g
6 .3
A c ti v ity
D u r a tio n
E s ti m a tin g
6 .2
A c ti v ity
S e q u e n c in g
7 .1
R e s o u r c e
P la n n i n g
5 . 3
S c o p e
D e fin itio n
6 .1
A c tiv it y
D e fin itio n
5 . 2
S c o p e
P la n n in g 6 .4
S c h e d u le
D e v e lo p m e n t
7 .2
C o s t
E s ti m a tin g
T o th e
E x e c u ti n g
P r o c e s s e s
(F ig u r e 3 – 6 )
F r o m th e
In it i a t in g
P r o c e s s e s
(F ig u r e 3 – 4 )
F r o m th e
C o n t r o lli n g
P r o c e s s e s
(F ig u r e 3 – 7 )
F a c ilita tin g P r o c e s s e s
9 .1
O r g a n iz a tio n a l
P la n n i n g
9 .2
S ta ff
A c q u is itio n
1 2 .1
P r o c u r e m e n t
P la n n in g
1 2 . 2
S o li c ita tio n
P la n n in g
8 .1
Q u a lit y
P la n n i n g
1 0 .1
C o m m u n ic a tio n s
P la n n in g
1 1 . 1
R is k
Id e n t ific a tio n
1 1 .2
R is k
Q u a n tific a tio n
1 1 . 3
R is k R e s p o n s e
D e v e lo p m e n t
52Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Product description
2. Project charter
3. Constraints
4. Assumptions
"… the process of developing
a written scope statement as
the basis for future project
decisions including, in
particular, the criteria used to
determine if the project or
phase has been completed
successfully.”
1. Scope statement
2. Supporting detail
3. Scope management plan
1. Product analysis
2. Cost/Benefit analysis
3. Alternative identification
4. Expert judgment
Core Planning Processes
Scope Planning
53Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Scope Statement Purpose
 To provide a general description of the sum of the products and services
to be provided by the project
 To develop a common understanding of project scope among
stakeholders
 May make explicit some exclusions that, based on the audience, would
be assumed to be part of the project
54Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 4-1
Scope Statement
 Using the handout in your manual, develop a project scope statement
based on the project charter developed in the initiating process exercise
55Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Tools and Techniques
1. Work breakdown structure
templates
2. Decomposition
Process OutputInput
1. Scope statement
2. Constraints
3. Assumptions
4. Other planning outputs
5. Historical information
“… subdividing the major
project deliverables (as
identified in the scope
statement) into smaller more
manageable components … ”
1. Work breakdown structure
Core Planning Processes
Scope Definition
56Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Work Breakdown Structure (WBS)
 “A deliverable oriented grouping of project elements which organizes
and defines the total scope of the project.
 Each descending level represents an increasingly detailed definition of a
project component.
 Project components may be products or services.”
57Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
WBS Purpose
 To define:
 Solution strategy or general approach
 Implementation tactics
 To support more accurate estimates of project duration and cost than can
be made at the project level
 To provide a basis for estimating project resources:
 Departmental or subcontractor support
 Vendors and their products
 Services
 Any other identifiable resource
58Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
A ir f r a m e E n g in e C o m m u n ic a tio n N a v ig a tio n F ir e C o n t r o l
T e s t
S e r v ic e s
M a n a g e m e n t
D a t a
D e p o t
L e v e l
D e v e lo p m e n t a l
T e s t
S u p p o r tin g
P M A c t iv it ie s F a c ilitie s
E n g in e e r in g
D a t a
I n te r m e d ia te
L e v e l M a in t e n a n c e
O p e r a t io n a l
T e s t
S y s te m s
E n g in e e r in g
M a n a g e m e n t
E q u ip m e n t
T e c h n ic a l
O r d e r s
O r g a n iz a t io n a l
L e v e l C o n s t r u c t io n M o c k - u p s
P r o je c t
M a n a g e m e n t
T r a in in g D a t a
A ir c r a f t
S y s t e m
S u p p o r t
E q u ip m e n t
F a c ilit ie s
T e s t a n d
E v a lu a t io n
A ir
V e h i c le
T h is W B S is illu s tr a t iv e o n ly . It is n o t in t e n d e d t o r e p r e s e n t t h e fu ll p r o je c t s c o p e o f a n y s p e c if ic
p r o je c t, n o r t o im p ly t h a t th is is th e o n ly w a y to o r g a n iz e a W B S o n th is t y p e o f p r o je c t .
59Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Pro je c t M a n a g e m e n t P ro je c t M a n a g e m e n t
D e s ig n C o n s tru c tio n
W a s te W a te r
T re a tm e n t P la n t
T h is W B S is illu s t ra t iv e o n ly . It is n o t in t e n d e d t o re p re s e n t t h e fu ll p ro je c t s c o p e o f a n y s p e c ific
p ro je c t , n o r t o im p ly t h a t t h is is th e o n ly w a y t o o rg a n ize a W B S o n t h is ty p e o f p ro je c t.
C iv il D ra w in g s H e a d w o rk s
A rc h it e c t u ra l D ra w in g s A e ra t io n B a s in
S t ru c t u ra l D ra w in g s Efflu e n t P u m p in g S ta t io n
M e c h a n ic a l D ra w in g s A ir H a n d lin g B u ild in g
H V A C D ra w in g s S lu d g e B u ild in g
P lu m b in g D ra w in g s
In s t ru m e n ta t io n D ra w in g s
Ele c t ric a l D ra w in g s
La t e r
P h a s e s
Ea rlie r
P h a s e s
60Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Validate Your WBS
 All major elements been identified at top level?
 Decomposed into measurable components?
 Lower level(s) items necessary? All inclusive?
 Would stakeholders agree WBS is satisfactory?
 Can elements be scheduled, budgeted, and assigned to a unit that will
accept responsibility?
 Too much or too little visibility and control ?
 Can status reports be generated at all levels?
61Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Using the WBS to Estimate Cost
 Project manager establishes work requirements by defining the
 What—“shalls” and “wills”
 When—sequence
 Why—dependencies
 Functional managers estimate cost by determining
 How—equipment and methods
 Who—type and level of expertise
 Where—location, department
62Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 4-2
Work Breakdown Structure
 Using “Post-it® Notes,” construct a WBS for your project or subproject
 Apply the WBS validation criteria
 Discuss any learning or insights with a classmate, including any learning
from applying the WBS test criteria
63Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. WBS
2. Scope statement
3. Historical information
4. Constraints
5. Assumptions
“Identifying the specific
activities that must be
performed to produce the
various project deliverables.”
1. Activity list
2. Supporting detail
3. WBS updates
1. Decomposition
2. Templates
Core Planning Processes
Activity Definition
64Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Activity list
2. Product description
3. External dependencies
4. Mandatory dependencies
5. Discretionary dependencies
6. Constraints
7. Assumptions
“… identifying and
documenting interactivity
dependencies.”
1. Project network
2. Activity list updates
1. Precedence diagramming
method
2. Arrow diagramming method
3. Conditional diagramming
method
4. Network templates
Core Planning Processes
Activity Sequencing
65Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Precedence Diagramming Method
C
F
A
D
B
E
S t a r t F in i s h
66Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Activity lists
2. Constraints
3. Assumptions
4. Resource requirements
5. Resource capabilities
6. Resource information
“… assessing the number of
work periods likely to be
needed to complete each
identified activity.”
1. Activity duration
2. Basis of estimates
3. Activity list updates
1. Expert judgment
2. Analogous estimating
3. Simulation
Core Planning Processes
Activity Duration Estimating
67Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Schedule Purpose
 Converts the project plan to an operating plan that is the basic tool for
controlling project activities
Benefits of a realistic schedule?
68Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Benefits of a Realistic Schedule
 Framework for managing critical project activities
 Determines planned start and completion dates
 Identifies activity and task precedence relationships
 Aids project team in defining critical communication content
 Specifies times when staff must be available
 No surprises
 Other?
69Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Scheduling Definitions
 Network
 Network techniques
 Path
 Node
 Arc
 Event
 Activity
70Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Scheduling Techniques
Activity on Arrow Example
S t a r t A
D
B
E
C
F F in is h
71Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Work
Activity 2
Set up
Activity 1
Finish
Activity 3
Result 1 Result 2 Result 3
Network Techniques
AOA Example
 Activities specified on arrows
 Also called arrow diagramming method (ADM)
 Nodes show relationship
72Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Scheduling Techniques
Activity on Node
 Activity on node network format
 Arrows show precedence relationships
 Nodes show activities
 3 types of precedence relationships
 Activity on node 1—successor but no predecessor
 Activity on node 2—predecessor and successor
 Activity on node 3—predecessor but no successor
73Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Task BTask A
Precedence Relationships
Finish to Start
The “from” activity Task A must finish before
the “to” activity Task B can start
74Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Precedence Relationships
Start to Start
The direction of the arrow defines
which task is the predecessor and
which is the successor.
Tasks A and B may start at the same
time, but the successor (B) cannot start
until the predecessor (A) begins.
Task B
Task A
75Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Precedence Relationships
Finish to Finish
Tasks A and B may end at the same
time, but the successor (B) cannot
finish until the predecessor (A) finishes
Task B
Task A
76Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Precedence Relationships
Start to Finish
Task A must start before Task B can
finish (seldom used).
Task B
Task A
77Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
PDM Example
Diverging-Converging Activities
Diverging Activities
Multiple predecessors
with single successor
Single predecessor with
multiple successors
Paint Ceiling
Prep
Paint Trim
Clean-up
Paint Walls
(2nd coat)
Paint Walls
Converging Activities
78Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Forward Pass Definitions
 Early Start Date (ES)
 Earliest possible point in time an activity can start, based on the
network logic and any schedule constraints
 Duration (DU)
 Number of work periods, excluding holidays or other nonworking
periods, required to complete the activity; expressed as workdays
or workweeks
 Early Finish Date (EF)
 Earliest possible time the activity can finish
 Forward Pass
 Starting at the beginning (left) of the network develop early start
and early finish dates for each task, progressing to end (right-most
box) of the network
79Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Forward Pass Calculation
EF = ES + DU – 1
DU = 4
Paint Walls
DU = 3
Paint Ceiling
DU = 2
Paint Trim
DU = 2
Paint Walls (2nd Coat)
DU = 2
Prep
DU = 2
Clean-up
1 2
3 4
3 5
3 6 7 8
9 10
DU
Task
Float
ES
LS
EF
LF
80Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Name Duration ES EF
Prep 2 1 2
Paint Trim 2 3 4
Paint Ceiling 3 3 5
Paint Walls 4 3 6
Paint Walls (2nd Coat) 2 7 8
Clean-up 2 9 10
Task Identification
Forward Pass
81Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Backward Pass Definitions
 Late Start Date (LS)
 Latest point in time that an activity may begin without delaying that
activity’s successor
 If the activity is on the critical path, the project end date will be
affected
 Float or Slack
 Latest point in time a task may be delayed from its earliest start date
without delaying the project finish date
 Late Finish (LF)
 Latest point in time a task may be completed without delaying that
activity’s successor
 If the activity is on the critical path, the project end date will be
affected
 Backward Pass
 Calculate late start and late finish dates by starting at project
completion, using finish times and working backwards
82Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Backward Pass Calculation
83Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Name Duration ES EF LS LF Float
Prep 2 1 2 1 2 0
Paint Trim 2 3 4 7 8 4
Paint Ceiling 3 3 5 6 8 3
Paint Walls 4 3 6 3 6 0
Paint Walls (2nd Coat) 2 7 8 7 8 0
Clean-up 2 9 10 9 10 0
Task Identification
Forward and Backward Passes
84Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Scheduling Techniques
Bar/Gantt Chart
A c t iv it y A
A c t iv it y B
A c t iv it y C
A c t iv it y D
J u n
T im e
J u l A u g S e p O c t N o v
T h e r e a r e m a n y o t h e r a c c e p t a b le w a y s t o d is p la y p r o je c t in f o r m a t io n o n a b a r c h a r t.
85Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Project network diagram
2. Activity duration estimates
3. Resource requirements
4. Resource pool description
5. Calendars
6. Constraints
7. Assumptions
8. Leads and lags
“… determining start
and finish dates for
project activities.”
1. Project schedule
2. Supporting detail
3. Schedule management plan
4. Resource requirements
updates
1. Mathematical analysis
2. Duration compression
3. Simulation
4. Resource leveling heuristics
5. Project management
software
Core Planning Processes
Schedule Development
86Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Scheduling Concepts
 Master schedule
 Crashing
 Hanger
 Workaround
 Schedule variance
87Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Milestone Chart
E v e n t
S u b c o n t r a c ts S ig n e d
S p e c ific a t io n s F in a liz e d
D e s ig n R e v ie w e d
S u b s y s te m T e s t e d
F ir s t U n it D e liv e r e d
P r o d u c tio n P la n C o m p le t e d
F e bJ a n M a r
D a ta
D a te
M a y J u n J u l A u gA p r
T h e r e a r e m a n y o t h e r a c c e p ta b le w a y s t o d is p la y p r o je c t in f o r m a t io n o n a m ile s t o n e c h a r t .
88Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 4-3
Project Milestones
 Identify the major milestones in your project
89Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. WBS
2. Historical information
3. Scope statement
4. Resource pool description
5. Organizational policies
“… determining what
physical resources
(people, equipment,
materials) and what
quantities of each should
be used to perform
project activities.”
1. Resource requirements
1. Expert judgment
2. Alternatives identification
Core Planning Processes
Resource Planning
90Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. WBS
2. Resource requirements
3. Resource rates
4. Activity duration estimates
5. Historical information
6. Chart of accounts
“… developing an
approximation (estimate of the
costs of the resources needed
to complete project activities.”
1. Cost estimates
2. Supporting detail
3. Cost management plan
1. Analogous estimating
2. Parametric modeling
3. Bottom-up estimating
4. Computerized tools
Core Planning Processes
Cost Estimating
91Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Cost estimates
2. WBS
3. Project schedule
“… allocating the overall cost
estimates to individual work
items in order to establish a
cost baseline for measuring
project performance.”
1. Cost baseline
1. Analogous estimating
2. Parametric modeling
3. Bottom-up estimating
4. Computerized tools
Core Planning Processes
Cost Budgeting
92Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Other planning outputs
2. Historical information
3. Organizational policies
4. Constraints
5. Assumptions
“… taking the results of other
planning processes and
putting them into a consistent,
coherent document.”
1. Project plan
2. Supporting detail
1. Project planning
methodology
2. Stakeholder’s skills and
knowledge
3. Project management
information systems
Core Planning Processes
Project Plan Development
93Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Facilitating Planning Processes
 Quality planning
 Communications planning
 Organizational planning
 Procurement planning
 Solicitation planning
 Staff acquisition
 Risk identification
 Risk quantification
 Risk response development
94Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Sample Planning Activities
 Subdividing deliverables into manageable components
 Allocating overall cost estimate to individual work items
 Identifying the specific activities people must perform to produce the
project deliverables
 Identifying the sequence and duration of activities
 Determining project roles and responsibilities
 Other?
95Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Outputs of Planning Processes
The Project Plan
 Schedules  Cost management plan
 Budgets  Cost baseline
 Risk management plan Scope statement
 Quality plan  Work breakdown structure
 Staffing plan  Plan updates
 Procurement plan  Resource requirements
 Schedule management plan  Communications plan
96Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 5: Executing Projects
Upon completion, you will be able to …
 Describe the purposes of the executing processes
 Identify the inputs and outputs of its core processes
 List the major tools and techniques
97Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Executing Processes
Initiating
Processes
Planning
Processes
Controlling
Processes
Executing
Processes
Closing
Processes
98Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose
 To coordinate, integrate, and manage all resources
Why?
 in order to achieve the project objectives
How?
 by carrying out the letter and intent of the project plan
While
 responding to change and mitigating risks
99Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
E x e c u tin g P ro c e s s e s
T o th e
C o n tro llin g
P ro c e s s e s
(F ig u re 3 – 7 )
F ro m th e
P la n n in g
P ro c e s s e s
(F ig u re 3 – 5 )
F ro m th e
C o n tro llin g
P ro c e s s e s
(F ig u re 3 – 7 )
F a c ilita tin g P ro c e s s e s
1 2 .3
S o lic ita tio n
1 2 .4
S o u rc e
S e le c tio n
5 .4
S c o p e
V e rific a tio n
1 2 .5
C o n tra c t
A d m in is tra tio n
1 0 .2
In fo rm a tio n
D is trib u tio n
9 .3
T e a m
D e v e lo p m e n t
8 .2
Q u a lity
A s s u ra n c e
4 .2
P ro je c t P la n
E x e c u tio n
Overview
100Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Project plan
2. Supporting detail
3. Organizational policies
4. Corrective action
“… the primary process for
carrying out the project plan.”
1. Work results
2. Change requests
1. General management skills
2. Product skills and knowledge
3. Work authorization system
4. Status review meetings
5. Project management
information system
6. Organizational procedures
Core Execution Process
Project Plan Execution
101Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Facilitating Execution Processes
 Information distribution
 Team development
 Quality assurance
 Scope verification
 Solicitation
 Source selection
 Contract administration
102Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Sample Executing Activities
 Managing work results and requests for change
 Using tools and techniques in project plan implementation
 Building effective relationships with vendors and project team members
 Choosing from potential sellers
 Distributing status information in time for stakeholders to act
 Other?
103Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 6: Controlling Projects
Upon completion, you will be able to …
 Describe the purposes of the controlling processes
 Identify the inputs and outputs of the core controlling processes
 List and define the major tools and techniques
104Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Controlling Processes
Initiating
Processes
Planning
Processes
Controlling
Processes
Executing
Processes
Closing
Processes
105Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose
To keep the project on track in order to achieve its objectives as outlined
in the project plan by:
 Monitoring and reporting variances
 Controlling scope changes
 Controlling schedule changes
 Controlling costs
 Controlling quality
 Responding to risks
106Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
T o th e
P la n n in g
P ro c e s s e s
(F ig u re 3 – 5 )
T o th e
C lo s in g
P ro c e s s e s
(F ig u re 3 – 8 )
F ro m th e
E x e c u tin g
P ro c e s s e s
(F ig u re 3 – 6 )
C o n tro llin g P ro c e s s e s
F a c ilita tin g P ro c e s s e s
8 .3
Q u a lity
C o n tro l
5 .5
S c o p e C h a n g e
C o n tro l
6 .5
S c h e d u le
C o n tro l
1 1 . 4
R is k R e s p o n s e
C o n tro l
7 .4
C o s t
C o n tro l
1 0 .3
P e rfo rm a n c e
R e p o rtin g
4 .3
O v e ra ll
C h a n g e C o n tro l
Overview
107Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Project plan
2. Work results
3. Other project records
“… collecting and disseminating
performance information. This
includes status reporting,
progress measurements, and
forecasting.”
1. Performance reports
2. Change requests
1. Performance reviews
2. Variance analysis
3. Trend analysis
4. Earned value analysis
5. Information distribution
systems
Core Controlling Processes
Performance Reporting
108Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
Core Controlling Processes
Overall Change Control
1. Project plan
2. Performance reports
3. Change requests
1. Change control system
2. Configuration management
3. Performance measurement
4. Additional planning
5. Project management
information systems
1. Project plan updates
2. Corrective action
3. Lessons learned
“Overall change control is
concerned with:
(a) influencing the factors which
create change to ensure that
changes are beneficial,
(b) determining that a change
has occurred, and
(c) managing the actual change
when and as they occur.”
109Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Facilitating Controlling Processes
 Scope change control
 Quality control
 Schedule control
 Cost control
 Risk response control
110Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Risk management plan
2. Actual risk events
3. Additional risk identification
Facilitating Controlling Processes
Risk Response Control
1. Workarounds
2. Additional risk response
development
1. Corrective action
2. Updates to the risk
management plan
“… involves executing the Risk
Management Plan in order to
respond to risk events over the
course of the project.”
111Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Cost Concept
Earned Value
 A method for measuring project performance
 The budgeted cost of work performed for an activity or group of activities
 Compares the planned amount of work with the accomplished amount of
work to determine if cost and scheduled performance is as planned
112Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Controlling Activities
 Reporting status versus plan and forecasting
 Responding to changes in risk
 Completing and settling the contract, including resolving of any open items
 Identifying and reporting schedule slips
 Determining whether schedule updates require plan modifications
 Other?
113Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 7: Closing Projects
Upon completion, you will be able to …
 Describe the purposes of closing processes
 Identify the inputs and outputs of the core processes
 List the major tools and techniques
114Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Closing Processes
Initiating
Processes
Planning
Processes
Controlling
Processes
Executing
Processes
Closing
Processes
115Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose
Formalizing acceptance of the project and bringing it to an orderly end by:
 Closing the contract
 Achieving administrative closure
116Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Overview
C lo s in g P r o c e s s e s
1 2 .6
C o n t r a c t
C lo s e - o u t
1 0 .4
A d m in is t r a t iv e
C lo s u r e
F r o m t h e
C o n t r o llin g
P r o c e s s e s
( F ig u r e 3 – 7 )
117Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Contract documentation “… involves both product
verification (was all work
completed correctly and
satisfactorily) and administrative
close-out (updating of records
to reflect final results and
archiving of such information for
future use.”
1. Contract file
2. Formal acceptance and
closure
1. Procurement audits
Core Closing Processes
Contract Close-out
118Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process OutputInput
Tools and Techniques
1. Performance measurement
documentation
2. Documentation of the
product of the project
3. Other project records
“… verifying and documenting
project results to formalize
acceptance of the product by
the sponsor, client or
customer.”
1. Project archives
2. Formal acceptance
3. Lessons learned
1. Performance reporting
tools and techniques
Core Closing Process
Administrative Closure
119Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Sample Closing Activities
 Ensuring a record of lessons learned is developed, documented, and
made available for future projects
 Verifying acceptance of products or services
 Collecting all required project records
 Determining if final products meet specifications
 Assessing the quality, correctness, and completeness of all formal
project acceptance documents
 Give performance appraisals and assist in the planned transfer of
personnel to other projects or positions
 Other?
120Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Initiating
Processes
Planning
Processes
Controlling
Processes
Executing
Processes
Closing
Processes
Communication Flow
Plans and
Updates
Status
Guidance
Changes
Direction
Start
Operations
Authorization
121Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 7-1
Process Group Allocation
 Allocate the processes and activities to the correct process group
122Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Questions/Opinions on Processes
 Most important processes?
 Least important?
 Missing?
 Other questions?
123Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Units 3–7 Summary
 Identified the role of each process group
 Identified the inputs and outputs of core processes
 Listed the major tools and techniques used in core processes of each
process group
 Described facilitating processes
 Recognized and allocated processes and activities to their correct
process group
124Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 8: Organizational Impacts
Upon completion, you will be able to …
 Describe how different organizational approaches can impact the
process and effectiveness of project management
125Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
HR Requirements
 PM position descriptions
 Reward system congruence
 Career paths
 Competency models
 Training and development opportunities
 Certification
126Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
( B la c k b o x e s r e p r e s e n t s t a ff e n g a g e d in p r o je c t a c t iv it ie s . )
C h ie f
E x e c u t i v e
P r o je c t
C o o r d in a t io n
F u n c t io n a l
M a n a g e r
S t a f f
S t a f f
F u n c t io n a l
M a n a g e r
S t a f f
S t a f f
F u n c t io n a l
M a n a g e r
S t a f f
S t a f f
127Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
Discussion Question
 In your opinion, what advantages and potential disadvantage does
this type of organizational structure foster?
128Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
Potential Advantages
 Clear reporting relationships
 Highly specialized expertise
 Homogeneous group
 Drive for technical excellence
129Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
Potential Issues
 Project boundaries limited to discipline
 Barrier to customer influence and satisfaction
 Employee development opportunities limited
 Project manager dependent on personal influence
 Hierarchical decision and communication processes
 Overwork technical issues versus build to standard
 Fosters part-time roles
130Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Strong Matrix
F u n c t io n a l
M a n a g e r
M a n a g e r o f
P r o je c t M a n a g e r s
S t a f f
S t a f f
S t a f f
S t a f f
S t a f f
S t a f f
S t a f f
S t a f f
S t a f f
P r o je c t M a n a g e r
P r o je c t M a n a g e r
P r o je c t M a n a g e r
F u n c t io n a l
M a n a g e r
F u n c t io n a l
M a n a g e r
P r o je c t
C o o r d in a t io n
( B la c k b o x e s r e p r e s e n t s ta ff e n g a g e d in p r o je c t a c tiv it ie s .)
C h ie f
E x e c u t iv e
131Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Projectized Organization
P r o j e c t
C o o r d in a t io n
P r o je c t
M a n a g e r
S t a f f
P r o je c t
M a n a g e r
S t a f f
P r o je c t
M a n a g e r
S t a f f
S t a f f
( B la c k b o x e s r e p r e s e n t s ta ff e n g a g e d in p r o je c t a c tiv itie s .)
S t a f f S t a f f
C h ie f
E x e c u t iv e
132Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Projectized Organization
Discussion Question
 Based on your experience, what potential advantages and disadvantage
does this type of organizational approach foster?
133Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project-Based Organization
Potential Advantages
 Strong project manager role
 Full-time administrative staff
 Clear accountability
 Fosters co-location
 Improved focus
 Cost and performance tracking
 Decision-making
 Customer relationships
 Common processes
134Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project-Based Organization
Potential Issues
 Lessening of employee’s “profession” identity
 Reduced focus on technical competence
 Leadership by the nontechnically skilled
 Focus on administrative work versus technical
 Devaluing of functional managers
 Process versus deliverable emphasis
135Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Structure Influence on Projects
136Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 8-1
Organizational Impacts
 If you were given authority for a day and tasked to improve project
management in your organization, what changes would you make:
 To the organization structure and delegation of responsibilities?
 To your role (no major promotions, please)?
137Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Summary
Reviewed how organizational approaches can impact the effectiveness of
project management
 Functional organization
 Matrix organization
 Project-based organization
138Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 9: Overview of Knowledge Areas
Upon completion, you will be able to …
 Identify and describe the nine knowledge areas
 Identify your current development needs and strengths
in the processes in each knowledge area
139Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Overview of Knowledge Areas
Cost Time
Scope
Integration
Human Resources
Communications
Risk
Procurement
Quality
140Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Integration Management
“A subset of project management that includes the processes required to
ensure that the various elements of the project are properly
coordinated.”
 Project plan development
 Project plan execution
 Overall change control
141Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Proposal
Request
Proposal Phase
Requirements Analysis Phase
General Design Phase
Detailed Design Phase
Code and Debug
Overlapped phases can yield cost and
schedule benefits but add to the
integration challenge
The Integration Challenge
Software Product Development Example
142Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Characteristics of Effective Integration
 Overlapped processes
 Effective change control and communication systems
 Reduced development time and cost
 Early and ongoing involvement of all stakeholders
 Early visibility of results
 Early problem identification and resolution
 Use all relevant expertise at earliest meaningful time
143Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Scope Management
“Includes the processes required to ensure that the project includes all of
the work required, and only the work required to complete the project
successfully.”
 Initiation
 Scope planning
 Scope definition
 Scope verification
 Scope change control
144Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Scope Concepts
 Configuration Management
 A mechanism to track budget, schedule variances, and deliverable
versions
 Specification
 A precise definition of a physical item, procedure, service, or result
for the purpose of purchase and/or implementation of an item or
service
 Sources of Scope Change
 Variation in government regulations
 Failure to include a required feature in the design of the product
 Customers who change their minds about the desired nature of the
deliverable
145Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Scope Concepts (continued)
Work Breakdown Structure
 A deliverable-oriented grouping of process elements that organizes and
defines the total scope of the project
 Each descending level represents an increasingly detailed definition of a
project component
 Project components may be products or services
146Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Time Management
 Definition
 A subset of project management that includes the processes required
to ensure timely completion of the project
 Processes
 Activity definition
 Activity sequencing
 Activity duration estimating
 Schedule development
 Schedule control
147Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose of Scheduling Processes
 Illustrates interdependence of project activities, work packages, and
work units
 Monitors and controls timing of project work
 Guides the allocation of resources
 Drives personnel availability issues and activities
148Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Remodel Kitchen WBS
Purchase
Appliances
Purchase
Fixtures
Remodel Kitchen
Design Purchase Carpentry ElectricalLevel 1
Level 2
149Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
ID Task Name Dur
1 1 DESIGN 10d
2 1.1 SELECT DESIGNER 3d
3 1.2 CREATEPLANS 5d
4 1.3 SELECT CONTRACTOR 2d
5 2 PURCHASING 6d
6 2.1 PURCHASEAPPLIANCES 6d
7 3 CARPENTERS 15d
8 3.1 TEAROUT 3d
9 3.2 CHANGEWALLS 4d
10 3.3 INSTALL NEW CABINETS 3d
11 3.4 INSTALL SINK 1d
12 3.5 INSTALL DISHWASHER 2d
13 3.6 INSTALL FLOOR 2d
14 3.7 FINISHANDCLEANUP 1d
15 4 ELECTRICAL 3d
16 4.1 WIRING 2d
17 4.2 INSTALL LIGHTS 1d
18 5 MECHANICAL 2d
19 5.1 INSTALL PIPING 2d
20 6 READY FORDINNER 1d
-3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Kitchen Remodeling
Precedence Relationships
150Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Kitchen Remodeling
Forward Pass - Early Dates
ID Task Name Dur ES Date EF Date
1 DESIGN 10d
2 SELECT DESIGNER 3d
3 CREATEPLANS 5d
4 SELECT CONTRACTOR 2d
5 PURCHASING 6d
6 PURCHASEAPPLIANCES 6d
7 CARPENTERS 15d
8 TEAR OUT 3d
9 CHANGEWALLS 4d
10 INSTALL NEW CABINETS 3d
11 INSTALL SINK 1d
12 INSTALL DISHWASHER 2d
13 INSTALL FLOOR 2d
14 FINISH ANDCLEANUP 1d
15 ELECTRICAL 3d
16 WIRING 2d
17 INSTALL LIGHTS 1d
18 MECHANICAL 2d
19 INSTALL PIPING 2d
20 READY FORDINNER 1d
S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Feb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99
151Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Kitchen Remodeling
Backward Pass - Late Dates
ID Task Name Dur LS Date LF Date
1 DESIGN 10d
2 SELECT DESIGNER 3d
3 CREATEPLANS 5d
4 SELECT CONTRACTOR 2d
5 PURCHASING 6d
6 PURCHASEAPPLIANCES 6d
7 CARPENTERS 15d
8 TEAR OUT 3d
9 CHANGEWALLS 4d
10 INSTALL NEW CABINETS 3d
11 INSTALL SINK 1d
12 INSTALL DISHWASHER 2d
13 INSTALL FLOOR 2d
14 FINISHANDCLEANUP 1d
15 ELECTRICAL 3d
16 WIRING 2d
17 INSTALL LIGHTS 1d
18 MECHANICAL 2d
19 INSTALL PIPING 2d
20 READY FORDINNER 1d
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Feb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99 Mar
152Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Kitchen Remodeling
Total Float
ID Task Name Dur ES Date EF Date LS Date LF Date T Float
1 DESIGN 10d
2 SELECT DESIGNER 3d
3 CREATEPLANS 5d
4 SELECT CONTRACTOR 2d
5 PURCHASING 6d
6 PURCHASEAPPLIANCES 6d
7 CARPENTERS 15d
8 TEAR OUT 3d
9 CHANGEWALLS 4d
10 INSTALL NEW CABINETS 3d
11 INSTALL SINK 1d
12 INSTALL DISHWASHER 2d
13 INSTALL FLOOR 2d
14 FINISH AND CLEANUP 1d
15 ELECTRICAL 3d
16 WIRING 2d
17 INSTALL LIGHTS 1d
18 MECHANICAL 2d
19 INSTALL PIPING 2d
20 READY FOR DINNER 1d
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Feb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99 Ma
Total Float = Late Finish Date – Early Finish Date
153Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Kitchen Remodeling
Summary
ID Task Name Dur ES Date EF date LS Date LF Date T Float
1 DESIGN 10d 1 10 1 10 0d
2 SELECT DESIGNER 3d 1 3 1 3 0d
3 CREATEPLANS 5d 4 8 4 8 0d
4 SELECT CONTRACTOR 2d 9 10 9 10 0d
5 PURCHASING 6d 9 14 12 17 3d
6 PURCHASEAPPLIANCES 6d 9 14 12 17 3d
7 CARPENTERS 15d 11 25 11 25 0d
8 TEAR OUT 3d 11 13 11 13 0d
9 CHANGEWALLS 4d 14 17 14 17 0d
10 INSTALL NEW CABINETS 3d 18 20 18 20 0d
11 INSTALL SINK 1d 21 21 22 22 1d
12 INSTALL DISHWASHER 2d 21 22 21 22 0d
13 INSTALL FLOOR 2d 23 24 23 24 0d
14 FINISHAND CLEANUP 1d 25 25 25 25 0d
15 ELECTRICAL 3d 18 20 20 22 2d
16 WIRING 2d 18 19 20 21 2d
17 INSTALL LIGHTS 1d 20 20 22 22 2d
18 MECHANICAL 2d 18 19 19 20 1d
19 INSTALL PIPING 2d 18 19 19 20 1d
20 READY FORDINNER 1d 26 26 26 26 0d
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Float
154Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Cost Management
“… the processes required to ensure that the project is completed within
the approved budget.”
 Resource planning
 Cost estimating
 Cost budgeting
 Cost control
155Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
One Performance Measurement
 Earned Value
 Budgeted Cost of Work Performed (BCWP)
 Related Terms
 Budgeted Cost of Work Scheduled (BCWS)
 Actual Cost of Work Performed (ACWP)
 Budget at Completion (BAC)
156Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Cumulative Status Display
Dollars
Current Date
BCWS
BAC
ACWP
BCWP
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1999 2000 2001
157Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Variances
 Schedule Variance (SV) = BCWP – BCWS
 Cost Variance (CV) = BCWP – ACWP
 Time Variance (TV) = STWP – ATWP
158Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
What Is the SV?
Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
ACWP = $73,000
BCWS = $56,000
BCWP = $30,800 (55% completed)
Dollars
(000)
Current Date
100
90
80
70
60
50
40
30
20
10
0
Plan BCWS
Earned Value BCWP
Schedule
Variance (SV)
Actual ACWP
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1999 2000 2001
159Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
What Is the CV?
Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
ACWP = $73,000
BCWS = $56,000
BCWP = $30,800
SV = $-25,200
Cost Variance (CV)
Dollars
(000)
Current Date
100
90
80
70
60
50
40
30
20
10
0
1999 2000 2001
Plan BCWS
Earned Value BCWP
Actual ACWP
160Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
What Is the Time Variance?
Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
ACWP = $73,000
BCWS = $56,000
BCWP = $30,800
SV = - $25,200
CV = - $42,200
(000)
Dollars
Actual ACWP
Earned Value BCWP
Cost Variance (CV)
Plan BCWS
TV
6 mos. Delay
STWP ATWP
1999 2000 2001
100
90
80
70
60
50
40
30
20
10
0
161Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Quality Management
“A subset of project management that includes the process required to
ensure that the project will satisfy the needs for which it was
undertaken.”
 Quality planning
 Quality assurance
 Quality control
162Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project HR Management
“… the processes required to make the most effective use of the people
involved with the project.”
 Organizational planning
 Staff acquisition
 Team development
163Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Responsibility Chart
A B C D E F
S R A P P
S A P P
S R A I
R S A P
S P I A
...
P
P
P
P E R S O N
P H A S E
R e q u ir e m e n t s
F u n c t io n a l
D e s ig n
D e v e lo p m e n t
T e s t in g
P = P a r tic ip a n t A = A c c o u n t a b le R = R e v ie w r e q u ir e d
I = In p u t r e q u ir e d S = S ig n - o ff r e q u ir e d
164Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Responsibility Chart Characteristics
 Work Package Level
 Components
 WBS activity
 Responsible organization
 Responsible position title or person
 Type of responsibility
 Approving authority
 Prime implementation accountability
 Support
 Notification
165Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 9-1
Responsibility Allocation
 Using the handout in your manual, complete the responsibility matrix for
your project
 Discuss with a classmate the effectiveness of the allocation of
responsibility and authority depicted
166Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
“… the processes concerned with identifying, analyzing, and responding
to project risk.”
 Risk identification
 Risk quantification
 Risk response development
 Risk response control
Project Risk Management
167Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Risk Decision Tree
168Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 9-2
Risk Assessment
 Construct a risk assessment tree for a critical decision on your project
 If your original project selection does not lend itself to this exercise, feel
free to substitute another project
169Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Communications Management
“… the timely and appropriate generation, collection, dissemination,
storage, and ultimate disposition of project information.”
 Communications planning
 Information distribution
 Performance reporting
 Administrative closure
170Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Procurement Management
“… includes the processes required to acquire goods and services from
outside the performing organization.”
 Procurement planning
 Solicitation planning
 Solicitation
 Source selection
 Contract administration
 Contract closeout
171Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Summary
 Identified and described the nine knowledge areas and the core
processes in each
 Allocated typical processes and activities to their appropriate knowledge
area
172Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 10: Role of the Project Manager
Upon completion, you will be able to …
Identify, in your environment, the most critical project manager:
 Roles
 Responsibilities
 Interpersonal skill requirements
 Your knowledge area gaps and strengths
173Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Manager Roles
 Decision-maker  Manager
 Coach  Sales person
 Communication channel  PM expert
 Encourager Facilitator
 Power broker Behavior model
 Disciplinarian Other?
174Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Manager Responsibilities
 Project plan implementation
 Achievement of objectives
 Project integration
 Communications
 Stakeholder relations
 Change management system
 Priority establishment and maintenance
175Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
More Responsibilities
 Staff acquisition, retention, and motivation
 Selection and use of PM tools and techniques
 Compliance with regulations, state and federal laws, and organization
policies and procedures
 Resolving team conflicts
 Negotiating win/win solutions
 Deliver the project on time and within budget
 Other?
176Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Skill and Knowledge Requirements
T h is f ig u r e is a c o n c e p t u a l v ie w o f th e s e
r e la tio n s h ip s . T h e o v e r la p s s h o w n a r e n o t p r o p o r t io n a l.
A p p li c a t io n
A r e a K n o w le d g e
a n d P r a c t ic e
G e n e r a l
M a n a g e m e n t
K n o w l e d g e
a n d P r a c t ic e
T h e P r o je c t
M a n a g e m e n t
B o d y o f K n o w le d g e
G e n e r a l ly A c c e p t e d
P r o je c t M a n a g e m e n t
K n o w l e d g e a n d P r a c t ic e
177Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Competency can be defined as …
 A qualification equal to a position requirement,
or
 Capacities one must possess to perform satisfactorily in a position.
178Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Success depends on your …
 Knowledge
 Behaviors
 Attitude
 Organizational environment
 Project environment
 Fit
 Self-knowledge and ability to adjust
179Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
One Emerging Operating Style
“We will need scroungers, tinkerers, masters of the extemporaneous,
and those who can make it happen, regardless of the rules,
the odds, or the inevitable second guess.”*
* Project Management Handbook, by David I. Cleland and William R. King
180Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 10-1
Project Manager Interpersonal Skills
 Use the handout to assess the interpersonal skills required to manage a
project successfully in your organization; then assess your skills, and
identify skill gaps and strengths
181Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Recognizing a Successful Project Manager
 Meets cost, schedule, technical, and mission objectives
Plus
 Attains high levels of satisfaction and perception of project success
from:
 Client
 Sponsor
 Users
 Team
182Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Example of an Organization
Competence Assessment Tool
 CMM™ background
 Levels of Software Engineering Maturity Model
 Basic
 Repeatable
 Defined
 Managed
 Optimized
183Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Why Reading Your Environment Is Important
Assessments reveal:
 Fit between you, the organization, and the project
 Your development needs and strengths
 PM strategies most likely to be successful
 PM strategies to be avoided
 Guide for tools and techniques selection
 Guide your performance expectations of self and others
And They:
 Influence your own management style
184Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 10-2
PM Knowledge Needs Assessment
 Complete the exercise in your manual, and then discuss the implications
with a classmate
 Identify knowledge gaps, strengths, and possible developmental activities
including:
 Growth assignments
 Seminars
 Self-study
 Degree programs
 Other?
185Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
PM Knowledge Needs Assessment
Discussion Question
What did you learn from this exercise about:
 Yourself?
 Your project?
 Your organization?
 Your future?
186Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
A Framework for Project Management
Seminar Summary
1. Introduction and Key Concepts
2. Project Life Cycle Models
3. Initiating Projects
4. Planning Projects
5. Executing Projects
6. Controlling Projects
7. Closing Projects
8. Organizational Impacts
9. Overview of Knowledge Areas
10. Role of the Project Manager
187Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
End
 Please complete the seminar evaluation form before leaving.
 Thank you for your participation!

More Related Content

What's hot

Increasing Project Success
Increasing Project Success Increasing Project Success
Increasing Project Success
Carolyn Reid
 
Project management chap 2_final
Project management chap 2_finalProject management chap 2_final
Project management chap 2_final
Martin J. Schyns
 
Strategic Business Execution Introduction
Strategic Business Execution IntroductionStrategic Business Execution Introduction
Strategic Business Execution Introduction
PMO Advisory LLC
 
Make Your PMO Strategic
Make Your PMO StrategicMake Your PMO Strategic
Make Your PMO Strategic
Philippe Husser
 
Project Management: Your Guide in Acing the Project
Project Management: Your Guide in Acing the ProjectProject Management: Your Guide in Acing the Project
Project Management: Your Guide in Acing the Project
Orchestrate Mortgage and Title Solutions, LLC
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
Syed Umair Javed
 
Sophie Walker - Portfolio
Sophie Walker - PortfolioSophie Walker - Portfolio
Sophie Walker - PortfolioSophie Walker
 
The Modern PMO
The Modern PMOThe Modern PMO
The Modern PMO
PMI-Montréal
 
The complete guide to project management for startups
The complete guide to project management for startupsThe complete guide to project management for startups
The complete guide to project management for startups
SameerShaik43
 
A3 Thinking Applied to Policy Deployment
A3 Thinking Applied to Policy DeploymentA3 Thinking Applied to Policy Deployment
A3 Thinking Applied to Policy Deployment
Didier Rabino, Lbc
 
Introduction to project, program & portfolio management
Introduction to project, program & portfolio managementIntroduction to project, program & portfolio management
Introduction to project, program & portfolio management
ray_davis
 
ICT Strategic Planning
ICT Strategic PlanningICT Strategic Planning
ICT Strategic Planning
Suzie Vesper
 
ENTERPRISE PMO “TO BE
ENTERPRISE PMO “TO BEENTERPRISE PMO “TO BE
ENTERPRISE PMO “TO BE
KenMartin18
 
The Virtual PMO
The Virtual PMOThe Virtual PMO
The Virtual PMO
Jerry Manas
 
Project management issues and their solution
Project management issues and their solutionProject management issues and their solution
Project management issues and their solution
Orangescrum
 
Journey to Maturity Building a PMO
Journey to Maturity Building a PMOJourney to Maturity Building a PMO
Journey to Maturity Building a PMOJames Brown
 
Project Planning: How to Achieve the Impossible
Project Planning: How to Achieve the ImpossibleProject Planning: How to Achieve the Impossible
Project Planning: How to Achieve the Impossible
MindGenius
 
Notes - Discover the right tools for your Project Management Office (PMO)
Notes - Discover the right tools for your Project Management Office (PMO)Notes - Discover the right tools for your Project Management Office (PMO)
Notes - Discover the right tools for your Project Management Office (PMO)
Hussain Bandukwala
 
Draeger Performance review
Draeger Performance reviewDraeger Performance review
Draeger Performance reviewRod Spencer
 

What's hot (20)

Increasing Project Success
Increasing Project Success Increasing Project Success
Increasing Project Success
 
Project management chap 2_final
Project management chap 2_finalProject management chap 2_final
Project management chap 2_final
 
Strategic Business Execution Introduction
Strategic Business Execution IntroductionStrategic Business Execution Introduction
Strategic Business Execution Introduction
 
Make Your PMO Strategic
Make Your PMO StrategicMake Your PMO Strategic
Make Your PMO Strategic
 
Project Management: Your Guide in Acing the Project
Project Management: Your Guide in Acing the ProjectProject Management: Your Guide in Acing the Project
Project Management: Your Guide in Acing the Project
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
 
Sophie Walker - Portfolio
Sophie Walker - PortfolioSophie Walker - Portfolio
Sophie Walker - Portfolio
 
The Modern PMO
The Modern PMOThe Modern PMO
The Modern PMO
 
The complete guide to project management for startups
The complete guide to project management for startupsThe complete guide to project management for startups
The complete guide to project management for startups
 
A3 Thinking Applied to Policy Deployment
A3 Thinking Applied to Policy DeploymentA3 Thinking Applied to Policy Deployment
A3 Thinking Applied to Policy Deployment
 
Introduction to project, program & portfolio management
Introduction to project, program & portfolio managementIntroduction to project, program & portfolio management
Introduction to project, program & portfolio management
 
ICT Strategic Planning
ICT Strategic PlanningICT Strategic Planning
ICT Strategic Planning
 
ENTERPRISE PMO “TO BE
ENTERPRISE PMO “TO BEENTERPRISE PMO “TO BE
ENTERPRISE PMO “TO BE
 
DGiles_Project_World_TO_May_2011_presented
DGiles_Project_World_TO_May_2011_presentedDGiles_Project_World_TO_May_2011_presented
DGiles_Project_World_TO_May_2011_presented
 
The Virtual PMO
The Virtual PMOThe Virtual PMO
The Virtual PMO
 
Project management issues and their solution
Project management issues and their solutionProject management issues and their solution
Project management issues and their solution
 
Journey to Maturity Building a PMO
Journey to Maturity Building a PMOJourney to Maturity Building a PMO
Journey to Maturity Building a PMO
 
Project Planning: How to Achieve the Impossible
Project Planning: How to Achieve the ImpossibleProject Planning: How to Achieve the Impossible
Project Planning: How to Achieve the Impossible
 
Notes - Discover the right tools for your Project Management Office (PMO)
Notes - Discover the right tools for your Project Management Office (PMO)Notes - Discover the right tools for your Project Management Office (PMO)
Notes - Discover the right tools for your Project Management Office (PMO)
 
Draeger Performance review
Draeger Performance reviewDraeger Performance review
Draeger Performance review
 

Similar to Project management skills

Pmbok framework helping material
Pmbok framework helping  materialPmbok framework helping  material
Pmbok framework helping materialRamiz Arshad
 
Project Management Introduction General PM lifecycles
Project Management Introduction General PM lifecyclesProject Management Introduction General PM lifecycles
Project Management Introduction General PM lifecycles
Serdar Temiz
 
Pmi acp training in hyderabad
Pmi acp training in hyderabadPmi acp training in hyderabad
Pmi acp training in hyderabad
prathyusha1234
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
prathyusha1234
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
prathyusha1234
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
prathyusha1234
 
Pmp training in Bangalore
Pmp training in BangalorePmp training in Bangalore
Pmp training in Bangalore
likithach1
 
Pmi acp training in hyderabad
Pmi acp training in hyderabadPmi acp training in hyderabad
Pmi acp training in hyderabad
prathyusha1234
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
prathyusha1234
 
Pmp training in Bangalore
Pmp training in BangalorePmp training in Bangalore
Pmp training in Bangalore
likithach1
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
prathyusha1234
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
prathyusha1234
 
Pmi acp training in hyderabad
Pmi acp training in hyderabadPmi acp training in hyderabad
Pmi acp training in hyderabad
prathyusha1234
 
ChapterPM_1.pptx for the course project management
ChapterPM_1.pptx for the course project managementChapterPM_1.pptx for the course project management
ChapterPM_1.pptx for the course project management
DerbewBirhanu2
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
sai12234
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
sai12234
 
Pmp training in kolkata
Pmp training in kolkataPmp training in kolkata
Pmp training in kolkata
TejaspathiLV
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018
sai12234
 
PMP Certifiation
PMP CertifiationPMP Certifiation
PMP Certifiation
priyankaravilla
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018
sai12234
 

Similar to Project management skills (20)

Pmbok framework helping material
Pmbok framework helping  materialPmbok framework helping  material
Pmbok framework helping material
 
Project Management Introduction General PM lifecycles
Project Management Introduction General PM lifecyclesProject Management Introduction General PM lifecycles
Project Management Introduction General PM lifecycles
 
Pmi acp training in hyderabad
Pmi acp training in hyderabadPmi acp training in hyderabad
Pmi acp training in hyderabad
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
 
Pmp training in Bangalore
Pmp training in BangalorePmp training in Bangalore
Pmp training in Bangalore
 
Pmi acp training in hyderabad
Pmi acp training in hyderabadPmi acp training in hyderabad
Pmi acp training in hyderabad
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
 
Pmp training in Bangalore
Pmp training in BangalorePmp training in Bangalore
Pmp training in Bangalore
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
 
Pmi acp training
Pmi acp trainingPmi acp training
Pmi acp training
 
Pmi acp training in hyderabad
Pmi acp training in hyderabadPmi acp training in hyderabad
Pmi acp training in hyderabad
 
ChapterPM_1.pptx for the course project management
ChapterPM_1.pptx for the course project managementChapterPM_1.pptx for the course project management
ChapterPM_1.pptx for the course project management
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
 
Pmp training in kolkata
Pmp training in kolkataPmp training in kolkata
Pmp training in kolkata
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018
 
PMP Certifiation
PMP CertifiationPMP Certifiation
PMP Certifiation
 
Pmp pmbok6 -2018
Pmp   pmbok6 -2018Pmp   pmbok6 -2018
Pmp pmbok6 -2018
 

More from ProjectManager247

Top 10 project management tips
Top 10 project management tipsTop 10 project management tips
Top 10 project management tips
ProjectManager247
 
Schwalbe 07 projectcost
Schwalbe 07 projectcostSchwalbe 07 projectcost
Schwalbe 07 projectcost
ProjectManager247
 
Introductionto projectmanagement
Introductionto projectmanagementIntroductionto projectmanagement
Introductionto projectmanagement
ProjectManager247
 
Project cost management
Project cost managementProject cost management
Project cost management
ProjectManager247
 
Financial management by jon lang
Financial management by jon langFinancial management by jon lang
Financial management by jon lang
ProjectManager247
 
P mpriniciples&practicefor managers
P mpriniciples&practicefor managersP mpriniciples&practicefor managers
P mpriniciples&practicefor managers
ProjectManager247
 
Project management
Project managementProject management
Project management
ProjectManager247
 
Top 8 mistakes in project management interview
Top 8 mistakes in project management interviewTop 8 mistakes in project management interview
Top 8 mistakes in project management interviewProjectManager247
 

More from ProjectManager247 (8)

Top 10 project management tips
Top 10 project management tipsTop 10 project management tips
Top 10 project management tips
 
Schwalbe 07 projectcost
Schwalbe 07 projectcostSchwalbe 07 projectcost
Schwalbe 07 projectcost
 
Introductionto projectmanagement
Introductionto projectmanagementIntroductionto projectmanagement
Introductionto projectmanagement
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Financial management by jon lang
Financial management by jon langFinancial management by jon lang
Financial management by jon lang
 
P mpriniciples&practicefor managers
P mpriniciples&practicefor managersP mpriniciples&practicefor managers
P mpriniciples&practicefor managers
 
Project management
Project managementProject management
Project management
 
Top 8 mistakes in project management interview
Top 8 mistakes in project management interviewTop 8 mistakes in project management interview
Top 8 mistakes in project management interview
 

Recently uploaded

一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
yuhofha
 
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdfRECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
AlessandroMartins454470
 
0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf
Thomas GIRARD BDes
 
Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.
alexthomas971
 
Personal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignmentPersonal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignment
ragingokie
 
Digital Marketing Training In Bangalore
Digital  Marketing Training In BangaloreDigital  Marketing Training In Bangalore
Digital Marketing Training In Bangalore
nidm599
 
Andrea Kate Portfolio Presentation.pdf
Andrea Kate  Portfolio  Presentation.pdfAndrea Kate  Portfolio  Presentation.pdf
Andrea Kate Portfolio Presentation.pdf
andreakaterasco
 
Exploring Career Paths in Cybersecurity for Technical Communicators
Exploring Career Paths in Cybersecurity for Technical CommunicatorsExploring Career Paths in Cybersecurity for Technical Communicators
Exploring Career Paths in Cybersecurity for Technical Communicators
Ben Woelk, CISSP, CPTC
 
lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789
Ghh
 
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdfDOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
Pushpendra Kumar
 
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
atwvhyhm
 
Resumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying OnlineResumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying Online
Bruce Bennett
 
Leadership Ambassador club Adventist module
Leadership Ambassador club Adventist moduleLeadership Ambassador club Adventist module
Leadership Ambassador club Adventist module
kakomaeric00
 
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
pxyhy
 
一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理
yuhofha
 
New Explore Careers and College Majors 2024
New Explore Careers and College Majors 2024New Explore Careers and College Majors 2024
New Explore Careers and College Majors 2024
Dr. Mary Askew
 
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring ChapterHow Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
Hector Del Castillo, CPM, CPMM
 
一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理
一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理
一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理
taqyed
 
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
2zjra9bn
 
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
dsnow9802
 

Recently uploaded (20)

一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
 
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdfRECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
 
0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf
 
Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.
 
Personal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignmentPersonal Brand exploration KE.pdf for assignment
Personal Brand exploration KE.pdf for assignment
 
Digital Marketing Training In Bangalore
Digital  Marketing Training In BangaloreDigital  Marketing Training In Bangalore
Digital Marketing Training In Bangalore
 
Andrea Kate Portfolio Presentation.pdf
Andrea Kate  Portfolio  Presentation.pdfAndrea Kate  Portfolio  Presentation.pdf
Andrea Kate Portfolio Presentation.pdf
 
Exploring Career Paths in Cybersecurity for Technical Communicators
Exploring Career Paths in Cybersecurity for Technical CommunicatorsExploring Career Paths in Cybersecurity for Technical Communicators
Exploring Career Paths in Cybersecurity for Technical Communicators
 
lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789
 
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdfDOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
 
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
 
Resumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying OnlineResumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying Online
 
Leadership Ambassador club Adventist module
Leadership Ambassador club Adventist moduleLeadership Ambassador club Adventist module
Leadership Ambassador club Adventist module
 
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
 
一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理
 
New Explore Careers and College Majors 2024
New Explore Careers and College Majors 2024New Explore Careers and College Majors 2024
New Explore Careers and College Majors 2024
 
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring ChapterHow Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
How Mentoring Elevates Your PM Career | PMI Silver Spring Chapter
 
一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理
一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理
一比一原版(U-Barcelona毕业证)巴塞罗那大学毕业证成绩单如何办理
 
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
 
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
 

Project management skills

  • 1. A Framework for Project Management The Project Management Institute Education Department
  • 2. 2Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Related materials:  ProjectManager88.info/free-ebook-52-secrets-to-be-professional- project-manager  ProjectManager88.info/free-257-project-management-templates  ProjectManager88.info/free-ebook-62-tips-to-improve-project- effectiveness
  • 3. 3Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Welcome to this seminar, A Framework for Project Management. It is designed to provide a basic structure or model that can be helpful in thinking about, understanding, discussing and managing projects. It will prepare you to develop more advanced skills by applying seminar content to your position responsibilities, studying the recommended readings in project management (see Appendix C), and in taking other seminars offered by PMI® and educational organizations who subscribe to PMI standards of project management. During this seminar we ask you to focus on applying these concepts to real-world projects through your active participation in the exercises and discussions based on your unique experiences.We believe this learning experience can help you succeed in today’s environment of constant change, high performance expectations, resource constraints and global challenges. PMI is grateful for the contributions of time, energy, and professional expertise of many PMI members who have reviewed the material and made many suggestions to improve its effectiveness. Good luck on what we hope will be an enjoyable educational experience! Welcome
  • 4. 4Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Your Expectations  What would you like to learn from this experience?  Solution to a specific problem?  Project management concepts/knowledge?  Specific skills?  Other?
  • 5. 5Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Additional materials A. Seminar Evaluation Forms B. Exercises C. Resources for Project Management Professional Candidates A Framework for Project Management Units 1. Introduction and Key Concepts 6. Controlling Projects 2. Project Life Cycle Models 7. Closing Projects 3. Initiating Projects 8. Organizational Impacts 4. Planning Projects 9. Overview of Knowledge Areas 5. Executing Projects 10. Role of the Project Manager
  • 6. 6Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 1: Introduction and Key Concepts Upon completion, you will be able to …  Define key PM concepts  List the reasons why PM is needed  Explain the difference between projects and operations  Identify trends in the PM environment  List project success and failure factors  Identify potential benefits of PM
  • 7. 7Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key PM Concepts from the PMBOK® Guide T h is f ig u r e is a c o n c e p t u a l v ie w o f th e s e r e la tio n s h ip s . T h e o v e r la p s s h o w n a r e n o t p r o p o r t io n a l. A p p li c a t io n A r e a K n o w le d g e a n d P r a c t ic e G e n e r a l M a n a g e m e n t K n o w l e d g e a n d P r a c t ic e T h e P r o je c t M a n a g e m e n t B o d y o f K n o w le d g e G e n e r a l ly A c c e p t e d P r o je c t M a n a g e m e n t K n o w l e d g e a n d P r a c t ic e
  • 8. 8Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. * Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr. Why Do We Need Project Management?*  Exponential expansion of human knowledge  Global demand for goods and services  Global competition  Above requires the use of teams versus individuals
  • 9. 9Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project and Statement of Work (SOW)  A project is “a temporary endeavor undertaken to create a unique product or service.”  A SOW is a narrative description of products or services to be supplied under contract.
  • 10. 10Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Management “The application of knowledge, skills, tools and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project.”
  • 11. 11Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. PM Environment Discussion Question  What are some trends that impact the environment in which projects are managed today?
  • 12. 12Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Accelerating Trends  Corporate globalization  Massive mergers and reorganizations  Flatter organizations  Short-term results driven
  • 13. 13Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Accelerating Trends (continued)  Team environment  Contract PM and outsourcing  Primacy of interpersonal skills  Multinational projects  Importance of cultural differences  Dependence on technology
  • 14. 14Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. A Balancing Act Schedule requirements cost Source: William Gendron, presentation at 1998 PMI Global Forum Business Objective RiskRisk The Project Customer Expectation
  • 15. 15Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. A Balanced Project Time Cost Scope Quality
  • 16. 16Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Business Objectives Expectation and Objective Congruency Client/Customer Expectations Low High Low OK Customer wants more than the organization intends to provide. High Business needs more from the project than the customer. OK
  • 17. 17Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Contrast Projects and Operations Discussion Question  How are “projects” different from “operations”?
  • 18. 18Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Operations  Semi-permanent charter, organization, and goals  Maintains status quo  Standard product or service  Homogeneous teams  Ongoing Contrast Projects and Operations Projects  Create own charter, organization, and goals  Catalyst for change  Unique product or service  Heterogeneous teams  Start and end date
  • 19. 19Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 1-1 PM Pitfalls and Pluses  Looking back on projects with which you were associated, what were the top three factors that caused serious problems?  That created a perception of success?
  • 20. 20Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Common Pitfalls  Unclear objectives  Lack of senior management support  Lack of effective project integration  Inadequate funding  Change in business priorities  Original assumptions invalid  Ineffective team  Lack of effective communication processes  Other?
  • 21. 21Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Source: NASA study, “Determination of Project Success,” 1974, by David C. Murphy, Bruce N. Baker, and Dalmar Fisher Factors Affecting Project Success  Coordination and relations  Adequacy of structure and control  Project uniqueness, importance, and public exposure  Success criteria salience and consensus  Competitive and budgetary pressure  Initial over-optimism, conceptual difficulty  Internal capabilities buildup
  • 22. 22Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Potential Benefits of PM for the Organization  Improved control  Improved project support opportunities  Improved performance
  • 23. 23Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Potential Benefits of PM for You  Recognition of PM as a profession  Future source of company leaders  High visibility of project results  Growth opportunities  Build your reputation and network  Portable skills and experience
  • 24. 24Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Integration Management Cost Time Integration Quality
  • 25. 25Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Summary  Defined key PM concepts  Described why PM is needed  Explained difference between projects and operations  Identified trends in the PM environment  Discussed project success and failure factors  Identified potential benefits of PM
  • 26. 26Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 2: Project Life Cycle Models Upon completion, you will be able to …  List the purpose and types of project life cycle models  Distinguish between project and product life cycle  Define the role of phase reviews in PM  Apply a model to a hypothetical and a real project
  • 27. 27Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Concepts  Project phase: “A collection of logically related project activities usually culminating in the completion of a major deliverable.”  Project life cycle: “Collectively the project phases are known as the project life cycle.”  Product life cycle: The natural grouping of ideas, decisions, and actions into product phases, from product conception to operations to product phase-out.
  • 28. 28Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Generic Cost and Staffing Life Cycle T i m e I n it ia l P h a s e F in is hS ta r t I n t e r m e d ia te P h a s e s ( o n e o r m o r e ) F in a l P h a s e C o s t a n d S t a f f in g L e v e l
  • 29. 29Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Life Cycle Example Phases Concept and Proposal Development Implementation Termination Verification Final PhaseIntermediate PhasesInitial Phase
  • 30. 30Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Pharmaceutical Project Life Cycle Model D r u g S o u r c in g D is c o v e r y S c r e e n in g P r e c lin ic a l D e v e lo p m e n t R e g is t r a tio n ( s ) W o r k u p P o s t s u b m is s io n A c tiv it y P a te n t P r o c e s s S c r e e n in g L e a d Id e n tifie d P r e c lin ic a l IN D W o r k u p F ile IN D F ile N D A P o s t r e g is tr a tio n A c tiv ity P h a s e I C lin ic a l T e s ts P h a s e II C lin ic a l T e s ts P h a s e III C lin ic a l T e s ts A P P R O V A L F o r m u la t io n S ta b ility P r o c e s s D e v e lo p m e n t M e t a b o lis m T o x ic o lo g y T e n P lu s Y e a r s
  • 31. 31Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Construct Spiral Methodology Design IdentifyEvaluate Test Evaluation Evaluation Risk Analysis Business Requirements System Requirements Subsystem Requirements Unit Requirements Conceptual Design Logical Design Physical Design Final Design Proof of Concept First Build Second Build Final Build Deploy Operations and Production Support
  • 32. 32Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Importance of Phase Reviews  Requirements Review General Design Review Detailed Design Review Unit Test Proposal Preparation Requirements Analysis General Design Detailed Design Code and Debug
  • 33. 33Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Phase Initiation Example Detailed Design Phase  Ensure correctness and completeness of previous phase, e.g., general design phase  Assess all aspects of requirements, design approach, and deliverables  Identify and work off items  Determine contractor rewards/payment for closing phase  Conduct a readiness review to begin next phase, e.g., detailed design phase  Resource estimates and availability  Design maturity  Project plan review and update  Secure stakeholder approval to proceed
  • 34. 34Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 2-1 Project Life Cycle Model  Divide a current project on which you are working into phases, name them, and write a brief statement of purpose for each phase
  • 35. 35Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Summary  Explained the concept and purpose of project life cycles  Defined the role of phase reviews in PM  Described life cycle models  Differentiated project life cycle and product life cycle  Applied a model to hypothetical and real projects
  • 36. 36Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 3: Initiating Projects Upon completion, you will be able to …  List the main functions of each PM process group  Describe the purpose of the initiation process  Identify its inputs and outputs, tools and techniques  Develop a sample project charter  Give an example of how process groups can apply to the project as a whole or to a project phase
  • 37. 37Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process Definition  “A series of actions people take to bring about a desired result.”  Types of processes  Project management processes  Product-oriented processes  Business-oriented processes
  • 38. 38Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process Groups Initiating Processes Planning Processes Controlling Processes Executing Processes Closing Processes
  • 39. 39Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process Interactions  Inputs  Tools and techniques  Outputs  Taxonomy
  • 40. 40Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process Group Overview T o t h e P la n n i n g P r o c e s s e s ( F i g u r e 3 – 5 ) I n i t i a t i n g P r o c e s s e s 5 .1 I n it ia t io n
  • 41. 41Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Purpose of Initiation Process 1. To commit the organization to a project or phase 2. To set the overall solution direction 3. To define top-level project objectives 4. To secure the necessary approvals and resources 5. Validate alignment with strategic objectives 6. To assign a project manager
  • 42. 42Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Product description 2. Strategic plan 3. Project selection criteria 4. Historical information “Initiation is the process of formally recognizing that a new project exists or that an existing project should continue into its next phase.” 1. Project charter 2. Project manager identified/ assigned 3. Constraints 4. Assumptions 1. Project selection methods 2. Expert judgment Initiating Core Process—Initiation
  • 43. 43Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Charter “A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.”
  • 44. 44Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Charter Content  Business need  Project objectives  Project deliverables  Assumptions  Constraints  Key staff  Written authorization
  • 45. 45Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 3-1 Project Charter  Using the handout, complete the sample project charter  Assume you are the project manager  As an example, choose an anticipated major project assignment
  • 46. 46Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Sample Initiating Activities  Negotiate, write, and refine the project charter  Confirm how the project links to the business need  Identify management responsibilities  Identify geographic locations involved  Test top-level objectives versus strategic business plans  Make strategic procurement decisions, e.g., make, buy, or identify qualified vendors
  • 47. 47Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Outputs of Initiation Process  Project charter  Project manager identified/assigned  Other key positions identified/assigned  Constraints identified  Assumptions identified
  • 48. 48Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 4: Planning Projects Upon completion, you will be able to …  Describe the purposes of the planning processes  Identify the inputs and outputs of core planning processes  Describe the function and develop sample planning deliverables such as a scope statement, WBS, and milestone chart  List the major tools and techniques used in the core planning processes  Identify the planning facilitating processes and their functions
  • 49. 49Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Planning Process Group Initiating Processes Planning Processes Controlling Processes Executing Processes Closing Processes
  • 50. 50Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Purpose of Planning Processes To develop a project plan that:  Facilitates later accomplishment*  Ensures project wide integration  Monitors change effectively  Provides decision support information to stakeholders  Can be updated by iterative planning activities * Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
  • 51. 51Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. C o r e P r o c e s s e s 4 .1 P r o je c t P la n D e v e lo p m e n t 7 .3 C o s t B u d g e tin g 6 .3 A c ti v ity D u r a tio n E s ti m a tin g 6 .2 A c ti v ity S e q u e n c in g 7 .1 R e s o u r c e P la n n i n g 5 . 3 S c o p e D e fin itio n 6 .1 A c tiv it y D e fin itio n 5 . 2 S c o p e P la n n in g 6 .4 S c h e d u le D e v e lo p m e n t 7 .2 C o s t E s ti m a tin g T o th e E x e c u ti n g P r o c e s s e s (F ig u r e 3 – 6 ) F r o m th e In it i a t in g P r o c e s s e s (F ig u r e 3 – 4 ) F r o m th e C o n t r o lli n g P r o c e s s e s (F ig u r e 3 – 7 ) F a c ilita tin g P r o c e s s e s 9 .1 O r g a n iz a tio n a l P la n n i n g 9 .2 S ta ff A c q u is itio n 1 2 .1 P r o c u r e m e n t P la n n in g 1 2 . 2 S o li c ita tio n P la n n in g 8 .1 Q u a lit y P la n n i n g 1 0 .1 C o m m u n ic a tio n s P la n n in g 1 1 . 1 R is k Id e n t ific a tio n 1 1 .2 R is k Q u a n tific a tio n 1 1 . 3 R is k R e s p o n s e D e v e lo p m e n t
  • 52. 52Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Product description 2. Project charter 3. Constraints 4. Assumptions "… the process of developing a written scope statement as the basis for future project decisions including, in particular, the criteria used to determine if the project or phase has been completed successfully.” 1. Scope statement 2. Supporting detail 3. Scope management plan 1. Product analysis 2. Cost/Benefit analysis 3. Alternative identification 4. Expert judgment Core Planning Processes Scope Planning
  • 53. 53Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Scope Statement Purpose  To provide a general description of the sum of the products and services to be provided by the project  To develop a common understanding of project scope among stakeholders  May make explicit some exclusions that, based on the audience, would be assumed to be part of the project
  • 54. 54Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 4-1 Scope Statement  Using the handout in your manual, develop a project scope statement based on the project charter developed in the initiating process exercise
  • 55. 55Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Tools and Techniques 1. Work breakdown structure templates 2. Decomposition Process OutputInput 1. Scope statement 2. Constraints 3. Assumptions 4. Other planning outputs 5. Historical information “… subdividing the major project deliverables (as identified in the scope statement) into smaller more manageable components … ” 1. Work breakdown structure Core Planning Processes Scope Definition
  • 56. 56Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Work Breakdown Structure (WBS)  “A deliverable oriented grouping of project elements which organizes and defines the total scope of the project.  Each descending level represents an increasingly detailed definition of a project component.  Project components may be products or services.”
  • 57. 57Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. WBS Purpose  To define:  Solution strategy or general approach  Implementation tactics  To support more accurate estimates of project duration and cost than can be made at the project level  To provide a basis for estimating project resources:  Departmental or subcontractor support  Vendors and their products  Services  Any other identifiable resource
  • 58. 58Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. A ir f r a m e E n g in e C o m m u n ic a tio n N a v ig a tio n F ir e C o n t r o l T e s t S e r v ic e s M a n a g e m e n t D a t a D e p o t L e v e l D e v e lo p m e n t a l T e s t S u p p o r tin g P M A c t iv it ie s F a c ilitie s E n g in e e r in g D a t a I n te r m e d ia te L e v e l M a in t e n a n c e O p e r a t io n a l T e s t S y s te m s E n g in e e r in g M a n a g e m e n t E q u ip m e n t T e c h n ic a l O r d e r s O r g a n iz a t io n a l L e v e l C o n s t r u c t io n M o c k - u p s P r o je c t M a n a g e m e n t T r a in in g D a t a A ir c r a f t S y s t e m S u p p o r t E q u ip m e n t F a c ilit ie s T e s t a n d E v a lu a t io n A ir V e h i c le T h is W B S is illu s tr a t iv e o n ly . It is n o t in t e n d e d t o r e p r e s e n t t h e fu ll p r o je c t s c o p e o f a n y s p e c if ic p r o je c t, n o r t o im p ly t h a t th is is th e o n ly w a y to o r g a n iz e a W B S o n th is t y p e o f p r o je c t .
  • 59. 59Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Pro je c t M a n a g e m e n t P ro je c t M a n a g e m e n t D e s ig n C o n s tru c tio n W a s te W a te r T re a tm e n t P la n t T h is W B S is illu s t ra t iv e o n ly . It is n o t in t e n d e d t o re p re s e n t t h e fu ll p ro je c t s c o p e o f a n y s p e c ific p ro je c t , n o r t o im p ly t h a t t h is is th e o n ly w a y t o o rg a n ize a W B S o n t h is ty p e o f p ro je c t. C iv il D ra w in g s H e a d w o rk s A rc h it e c t u ra l D ra w in g s A e ra t io n B a s in S t ru c t u ra l D ra w in g s Efflu e n t P u m p in g S ta t io n M e c h a n ic a l D ra w in g s A ir H a n d lin g B u ild in g H V A C D ra w in g s S lu d g e B u ild in g P lu m b in g D ra w in g s In s t ru m e n ta t io n D ra w in g s Ele c t ric a l D ra w in g s La t e r P h a s e s Ea rlie r P h a s e s
  • 60. 60Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Validate Your WBS  All major elements been identified at top level?  Decomposed into measurable components?  Lower level(s) items necessary? All inclusive?  Would stakeholders agree WBS is satisfactory?  Can elements be scheduled, budgeted, and assigned to a unit that will accept responsibility?  Too much or too little visibility and control ?  Can status reports be generated at all levels?
  • 61. 61Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Using the WBS to Estimate Cost  Project manager establishes work requirements by defining the  What—“shalls” and “wills”  When—sequence  Why—dependencies  Functional managers estimate cost by determining  How—equipment and methods  Who—type and level of expertise  Where—location, department
  • 62. 62Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 4-2 Work Breakdown Structure  Using “Post-it® Notes,” construct a WBS for your project or subproject  Apply the WBS validation criteria  Discuss any learning or insights with a classmate, including any learning from applying the WBS test criteria
  • 63. 63Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. WBS 2. Scope statement 3. Historical information 4. Constraints 5. Assumptions “Identifying the specific activities that must be performed to produce the various project deliverables.” 1. Activity list 2. Supporting detail 3. WBS updates 1. Decomposition 2. Templates Core Planning Processes Activity Definition
  • 64. 64Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Activity list 2. Product description 3. External dependencies 4. Mandatory dependencies 5. Discretionary dependencies 6. Constraints 7. Assumptions “… identifying and documenting interactivity dependencies.” 1. Project network 2. Activity list updates 1. Precedence diagramming method 2. Arrow diagramming method 3. Conditional diagramming method 4. Network templates Core Planning Processes Activity Sequencing
  • 65. 65Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Precedence Diagramming Method C F A D B E S t a r t F in i s h
  • 66. 66Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Activity lists 2. Constraints 3. Assumptions 4. Resource requirements 5. Resource capabilities 6. Resource information “… assessing the number of work periods likely to be needed to complete each identified activity.” 1. Activity duration 2. Basis of estimates 3. Activity list updates 1. Expert judgment 2. Analogous estimating 3. Simulation Core Planning Processes Activity Duration Estimating
  • 67. 67Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Schedule Purpose  Converts the project plan to an operating plan that is the basic tool for controlling project activities Benefits of a realistic schedule?
  • 68. 68Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Benefits of a Realistic Schedule  Framework for managing critical project activities  Determines planned start and completion dates  Identifies activity and task precedence relationships  Aids project team in defining critical communication content  Specifies times when staff must be available  No surprises  Other?
  • 69. 69Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Scheduling Definitions  Network  Network techniques  Path  Node  Arc  Event  Activity
  • 70. 70Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Scheduling Techniques Activity on Arrow Example S t a r t A D B E C F F in is h
  • 71. 71Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Work Activity 2 Set up Activity 1 Finish Activity 3 Result 1 Result 2 Result 3 Network Techniques AOA Example  Activities specified on arrows  Also called arrow diagramming method (ADM)  Nodes show relationship
  • 72. 72Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Scheduling Techniques Activity on Node  Activity on node network format  Arrows show precedence relationships  Nodes show activities  3 types of precedence relationships  Activity on node 1—successor but no predecessor  Activity on node 2—predecessor and successor  Activity on node 3—predecessor but no successor
  • 73. 73Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Task BTask A Precedence Relationships Finish to Start The “from” activity Task A must finish before the “to” activity Task B can start
  • 74. 74Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Precedence Relationships Start to Start The direction of the arrow defines which task is the predecessor and which is the successor. Tasks A and B may start at the same time, but the successor (B) cannot start until the predecessor (A) begins. Task B Task A
  • 75. 75Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Precedence Relationships Finish to Finish Tasks A and B may end at the same time, but the successor (B) cannot finish until the predecessor (A) finishes Task B Task A
  • 76. 76Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Precedence Relationships Start to Finish Task A must start before Task B can finish (seldom used). Task B Task A
  • 77. 77Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. PDM Example Diverging-Converging Activities Diverging Activities Multiple predecessors with single successor Single predecessor with multiple successors Paint Ceiling Prep Paint Trim Clean-up Paint Walls (2nd coat) Paint Walls Converging Activities
  • 78. 78Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Forward Pass Definitions  Early Start Date (ES)  Earliest possible point in time an activity can start, based on the network logic and any schedule constraints  Duration (DU)  Number of work periods, excluding holidays or other nonworking periods, required to complete the activity; expressed as workdays or workweeks  Early Finish Date (EF)  Earliest possible time the activity can finish  Forward Pass  Starting at the beginning (left) of the network develop early start and early finish dates for each task, progressing to end (right-most box) of the network
  • 79. 79Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Forward Pass Calculation EF = ES + DU – 1 DU = 4 Paint Walls DU = 3 Paint Ceiling DU = 2 Paint Trim DU = 2 Paint Walls (2nd Coat) DU = 2 Prep DU = 2 Clean-up 1 2 3 4 3 5 3 6 7 8 9 10 DU Task Float ES LS EF LF
  • 80. 80Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Name Duration ES EF Prep 2 1 2 Paint Trim 2 3 4 Paint Ceiling 3 3 5 Paint Walls 4 3 6 Paint Walls (2nd Coat) 2 7 8 Clean-up 2 9 10 Task Identification Forward Pass
  • 81. 81Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Backward Pass Definitions  Late Start Date (LS)  Latest point in time that an activity may begin without delaying that activity’s successor  If the activity is on the critical path, the project end date will be affected  Float or Slack  Latest point in time a task may be delayed from its earliest start date without delaying the project finish date  Late Finish (LF)  Latest point in time a task may be completed without delaying that activity’s successor  If the activity is on the critical path, the project end date will be affected  Backward Pass  Calculate late start and late finish dates by starting at project completion, using finish times and working backwards
  • 82. 82Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Backward Pass Calculation
  • 83. 83Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Name Duration ES EF LS LF Float Prep 2 1 2 1 2 0 Paint Trim 2 3 4 7 8 4 Paint Ceiling 3 3 5 6 8 3 Paint Walls 4 3 6 3 6 0 Paint Walls (2nd Coat) 2 7 8 7 8 0 Clean-up 2 9 10 9 10 0 Task Identification Forward and Backward Passes
  • 84. 84Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Scheduling Techniques Bar/Gantt Chart A c t iv it y A A c t iv it y B A c t iv it y C A c t iv it y D J u n T im e J u l A u g S e p O c t N o v T h e r e a r e m a n y o t h e r a c c e p t a b le w a y s t o d is p la y p r o je c t in f o r m a t io n o n a b a r c h a r t.
  • 85. 85Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Project network diagram 2. Activity duration estimates 3. Resource requirements 4. Resource pool description 5. Calendars 6. Constraints 7. Assumptions 8. Leads and lags “… determining start and finish dates for project activities.” 1. Project schedule 2. Supporting detail 3. Schedule management plan 4. Resource requirements updates 1. Mathematical analysis 2. Duration compression 3. Simulation 4. Resource leveling heuristics 5. Project management software Core Planning Processes Schedule Development
  • 86. 86Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Scheduling Concepts  Master schedule  Crashing  Hanger  Workaround  Schedule variance
  • 87. 87Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Milestone Chart E v e n t S u b c o n t r a c ts S ig n e d S p e c ific a t io n s F in a liz e d D e s ig n R e v ie w e d S u b s y s te m T e s t e d F ir s t U n it D e liv e r e d P r o d u c tio n P la n C o m p le t e d F e bJ a n M a r D a ta D a te M a y J u n J u l A u gA p r T h e r e a r e m a n y o t h e r a c c e p ta b le w a y s t o d is p la y p r o je c t in f o r m a t io n o n a m ile s t o n e c h a r t .
  • 88. 88Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 4-3 Project Milestones  Identify the major milestones in your project
  • 89. 89Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. WBS 2. Historical information 3. Scope statement 4. Resource pool description 5. Organizational policies “… determining what physical resources (people, equipment, materials) and what quantities of each should be used to perform project activities.” 1. Resource requirements 1. Expert judgment 2. Alternatives identification Core Planning Processes Resource Planning
  • 90. 90Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. WBS 2. Resource requirements 3. Resource rates 4. Activity duration estimates 5. Historical information 6. Chart of accounts “… developing an approximation (estimate of the costs of the resources needed to complete project activities.” 1. Cost estimates 2. Supporting detail 3. Cost management plan 1. Analogous estimating 2. Parametric modeling 3. Bottom-up estimating 4. Computerized tools Core Planning Processes Cost Estimating
  • 91. 91Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Cost estimates 2. WBS 3. Project schedule “… allocating the overall cost estimates to individual work items in order to establish a cost baseline for measuring project performance.” 1. Cost baseline 1. Analogous estimating 2. Parametric modeling 3. Bottom-up estimating 4. Computerized tools Core Planning Processes Cost Budgeting
  • 92. 92Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Other planning outputs 2. Historical information 3. Organizational policies 4. Constraints 5. Assumptions “… taking the results of other planning processes and putting them into a consistent, coherent document.” 1. Project plan 2. Supporting detail 1. Project planning methodology 2. Stakeholder’s skills and knowledge 3. Project management information systems Core Planning Processes Project Plan Development
  • 93. 93Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Facilitating Planning Processes  Quality planning  Communications planning  Organizational planning  Procurement planning  Solicitation planning  Staff acquisition  Risk identification  Risk quantification  Risk response development
  • 94. 94Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Sample Planning Activities  Subdividing deliverables into manageable components  Allocating overall cost estimate to individual work items  Identifying the specific activities people must perform to produce the project deliverables  Identifying the sequence and duration of activities  Determining project roles and responsibilities  Other?
  • 95. 95Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Outputs of Planning Processes The Project Plan  Schedules  Cost management plan  Budgets  Cost baseline  Risk management plan Scope statement  Quality plan  Work breakdown structure  Staffing plan  Plan updates  Procurement plan  Resource requirements  Schedule management plan  Communications plan
  • 96. 96Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 5: Executing Projects Upon completion, you will be able to …  Describe the purposes of the executing processes  Identify the inputs and outputs of its core processes  List the major tools and techniques
  • 97. 97Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Executing Processes Initiating Processes Planning Processes Controlling Processes Executing Processes Closing Processes
  • 98. 98Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Purpose  To coordinate, integrate, and manage all resources Why?  in order to achieve the project objectives How?  by carrying out the letter and intent of the project plan While  responding to change and mitigating risks
  • 99. 99Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. E x e c u tin g P ro c e s s e s T o th e C o n tro llin g P ro c e s s e s (F ig u re 3 – 7 ) F ro m th e P la n n in g P ro c e s s e s (F ig u re 3 – 5 ) F ro m th e C o n tro llin g P ro c e s s e s (F ig u re 3 – 7 ) F a c ilita tin g P ro c e s s e s 1 2 .3 S o lic ita tio n 1 2 .4 S o u rc e S e le c tio n 5 .4 S c o p e V e rific a tio n 1 2 .5 C o n tra c t A d m in is tra tio n 1 0 .2 In fo rm a tio n D is trib u tio n 9 .3 T e a m D e v e lo p m e n t 8 .2 Q u a lity A s s u ra n c e 4 .2 P ro je c t P la n E x e c u tio n Overview
  • 100. 100Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Project plan 2. Supporting detail 3. Organizational policies 4. Corrective action “… the primary process for carrying out the project plan.” 1. Work results 2. Change requests 1. General management skills 2. Product skills and knowledge 3. Work authorization system 4. Status review meetings 5. Project management information system 6. Organizational procedures Core Execution Process Project Plan Execution
  • 101. 101Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Facilitating Execution Processes  Information distribution  Team development  Quality assurance  Scope verification  Solicitation  Source selection  Contract administration
  • 102. 102Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Sample Executing Activities  Managing work results and requests for change  Using tools and techniques in project plan implementation  Building effective relationships with vendors and project team members  Choosing from potential sellers  Distributing status information in time for stakeholders to act  Other?
  • 103. 103Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 6: Controlling Projects Upon completion, you will be able to …  Describe the purposes of the controlling processes  Identify the inputs and outputs of the core controlling processes  List and define the major tools and techniques
  • 104. 104Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Controlling Processes Initiating Processes Planning Processes Controlling Processes Executing Processes Closing Processes
  • 105. 105Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Purpose To keep the project on track in order to achieve its objectives as outlined in the project plan by:  Monitoring and reporting variances  Controlling scope changes  Controlling schedule changes  Controlling costs  Controlling quality  Responding to risks
  • 106. 106Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. T o th e P la n n in g P ro c e s s e s (F ig u re 3 – 5 ) T o th e C lo s in g P ro c e s s e s (F ig u re 3 – 8 ) F ro m th e E x e c u tin g P ro c e s s e s (F ig u re 3 – 6 ) C o n tro llin g P ro c e s s e s F a c ilita tin g P ro c e s s e s 8 .3 Q u a lity C o n tro l 5 .5 S c o p e C h a n g e C o n tro l 6 .5 S c h e d u le C o n tro l 1 1 . 4 R is k R e s p o n s e C o n tro l 7 .4 C o s t C o n tro l 1 0 .3 P e rfo rm a n c e R e p o rtin g 4 .3 O v e ra ll C h a n g e C o n tro l Overview
  • 107. 107Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Project plan 2. Work results 3. Other project records “… collecting and disseminating performance information. This includes status reporting, progress measurements, and forecasting.” 1. Performance reports 2. Change requests 1. Performance reviews 2. Variance analysis 3. Trend analysis 4. Earned value analysis 5. Information distribution systems Core Controlling Processes Performance Reporting
  • 108. 108Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques Core Controlling Processes Overall Change Control 1. Project plan 2. Performance reports 3. Change requests 1. Change control system 2. Configuration management 3. Performance measurement 4. Additional planning 5. Project management information systems 1. Project plan updates 2. Corrective action 3. Lessons learned “Overall change control is concerned with: (a) influencing the factors which create change to ensure that changes are beneficial, (b) determining that a change has occurred, and (c) managing the actual change when and as they occur.”
  • 109. 109Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Facilitating Controlling Processes  Scope change control  Quality control  Schedule control  Cost control  Risk response control
  • 110. 110Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Risk management plan 2. Actual risk events 3. Additional risk identification Facilitating Controlling Processes Risk Response Control 1. Workarounds 2. Additional risk response development 1. Corrective action 2. Updates to the risk management plan “… involves executing the Risk Management Plan in order to respond to risk events over the course of the project.”
  • 111. 111Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Cost Concept Earned Value  A method for measuring project performance  The budgeted cost of work performed for an activity or group of activities  Compares the planned amount of work with the accomplished amount of work to determine if cost and scheduled performance is as planned
  • 112. 112Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Controlling Activities  Reporting status versus plan and forecasting  Responding to changes in risk  Completing and settling the contract, including resolving of any open items  Identifying and reporting schedule slips  Determining whether schedule updates require plan modifications  Other?
  • 113. 113Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 7: Closing Projects Upon completion, you will be able to …  Describe the purposes of closing processes  Identify the inputs and outputs of the core processes  List the major tools and techniques
  • 114. 114Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Closing Processes Initiating Processes Planning Processes Controlling Processes Executing Processes Closing Processes
  • 115. 115Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Purpose Formalizing acceptance of the project and bringing it to an orderly end by:  Closing the contract  Achieving administrative closure
  • 116. 116Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Overview C lo s in g P r o c e s s e s 1 2 .6 C o n t r a c t C lo s e - o u t 1 0 .4 A d m in is t r a t iv e C lo s u r e F r o m t h e C o n t r o llin g P r o c e s s e s ( F ig u r e 3 – 7 )
  • 117. 117Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Contract documentation “… involves both product verification (was all work completed correctly and satisfactorily) and administrative close-out (updating of records to reflect final results and archiving of such information for future use.” 1. Contract file 2. Formal acceptance and closure 1. Procurement audits Core Closing Processes Contract Close-out
  • 118. 118Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Process OutputInput Tools and Techniques 1. Performance measurement documentation 2. Documentation of the product of the project 3. Other project records “… verifying and documenting project results to formalize acceptance of the product by the sponsor, client or customer.” 1. Project archives 2. Formal acceptance 3. Lessons learned 1. Performance reporting tools and techniques Core Closing Process Administrative Closure
  • 119. 119Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Sample Closing Activities  Ensuring a record of lessons learned is developed, documented, and made available for future projects  Verifying acceptance of products or services  Collecting all required project records  Determining if final products meet specifications  Assessing the quality, correctness, and completeness of all formal project acceptance documents  Give performance appraisals and assist in the planned transfer of personnel to other projects or positions  Other?
  • 120. 120Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Initiating Processes Planning Processes Controlling Processes Executing Processes Closing Processes Communication Flow Plans and Updates Status Guidance Changes Direction Start Operations Authorization
  • 121. 121Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 7-1 Process Group Allocation  Allocate the processes and activities to the correct process group
  • 122. 122Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Questions/Opinions on Processes  Most important processes?  Least important?  Missing?  Other questions?
  • 123. 123Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Units 3–7 Summary  Identified the role of each process group  Identified the inputs and outputs of core processes  Listed the major tools and techniques used in core processes of each process group  Described facilitating processes  Recognized and allocated processes and activities to their correct process group
  • 124. 124Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 8: Organizational Impacts Upon completion, you will be able to …  Describe how different organizational approaches can impact the process and effectiveness of project management
  • 125. 125Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. HR Requirements  PM position descriptions  Reward system congruence  Career paths  Competency models  Training and development opportunities  Certification
  • 126. 126Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Functional Organization ( B la c k b o x e s r e p r e s e n t s t a ff e n g a g e d in p r o je c t a c t iv it ie s . ) C h ie f E x e c u t i v e P r o je c t C o o r d in a t io n F u n c t io n a l M a n a g e r S t a f f S t a f f F u n c t io n a l M a n a g e r S t a f f S t a f f F u n c t io n a l M a n a g e r S t a f f S t a f f
  • 127. 127Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Functional Organization Discussion Question  In your opinion, what advantages and potential disadvantage does this type of organizational structure foster?
  • 128. 128Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Functional Organization Potential Advantages  Clear reporting relationships  Highly specialized expertise  Homogeneous group  Drive for technical excellence
  • 129. 129Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Functional Organization Potential Issues  Project boundaries limited to discipline  Barrier to customer influence and satisfaction  Employee development opportunities limited  Project manager dependent on personal influence  Hierarchical decision and communication processes  Overwork technical issues versus build to standard  Fosters part-time roles
  • 130. 130Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Strong Matrix F u n c t io n a l M a n a g e r M a n a g e r o f P r o je c t M a n a g e r s S t a f f S t a f f S t a f f S t a f f S t a f f S t a f f S t a f f S t a f f S t a f f P r o je c t M a n a g e r P r o je c t M a n a g e r P r o je c t M a n a g e r F u n c t io n a l M a n a g e r F u n c t io n a l M a n a g e r P r o je c t C o o r d in a t io n ( B la c k b o x e s r e p r e s e n t s ta ff e n g a g e d in p r o je c t a c tiv it ie s .) C h ie f E x e c u t iv e
  • 131. 131Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Projectized Organization P r o j e c t C o o r d in a t io n P r o je c t M a n a g e r S t a f f P r o je c t M a n a g e r S t a f f P r o je c t M a n a g e r S t a f f S t a f f ( B la c k b o x e s r e p r e s e n t s ta ff e n g a g e d in p r o je c t a c tiv itie s .) S t a f f S t a f f C h ie f E x e c u t iv e
  • 132. 132Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Projectized Organization Discussion Question  Based on your experience, what potential advantages and disadvantage does this type of organizational approach foster?
  • 133. 133Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project-Based Organization Potential Advantages  Strong project manager role  Full-time administrative staff  Clear accountability  Fosters co-location  Improved focus  Cost and performance tracking  Decision-making  Customer relationships  Common processes
  • 134. 134Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project-Based Organization Potential Issues  Lessening of employee’s “profession” identity  Reduced focus on technical competence  Leadership by the nontechnically skilled  Focus on administrative work versus technical  Devaluing of functional managers  Process versus deliverable emphasis
  • 135. 135Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Structure Influence on Projects
  • 136. 136Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 8-1 Organizational Impacts  If you were given authority for a day and tasked to improve project management in your organization, what changes would you make:  To the organization structure and delegation of responsibilities?  To your role (no major promotions, please)?
  • 137. 137Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Summary Reviewed how organizational approaches can impact the effectiveness of project management  Functional organization  Matrix organization  Project-based organization
  • 138. 138Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 9: Overview of Knowledge Areas Upon completion, you will be able to …  Identify and describe the nine knowledge areas  Identify your current development needs and strengths in the processes in each knowledge area
  • 139. 139Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Overview of Knowledge Areas Cost Time Scope Integration Human Resources Communications Risk Procurement Quality
  • 140. 140Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Integration Management “A subset of project management that includes the processes required to ensure that the various elements of the project are properly coordinated.”  Project plan development  Project plan execution  Overall change control
  • 141. 141Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Proposal Request Proposal Phase Requirements Analysis Phase General Design Phase Detailed Design Phase Code and Debug Overlapped phases can yield cost and schedule benefits but add to the integration challenge The Integration Challenge Software Product Development Example
  • 142. 142Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Characteristics of Effective Integration  Overlapped processes  Effective change control and communication systems  Reduced development time and cost  Early and ongoing involvement of all stakeholders  Early visibility of results  Early problem identification and resolution  Use all relevant expertise at earliest meaningful time
  • 143. 143Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Scope Management “Includes the processes required to ensure that the project includes all of the work required, and only the work required to complete the project successfully.”  Initiation  Scope planning  Scope definition  Scope verification  Scope change control
  • 144. 144Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Scope Concepts  Configuration Management  A mechanism to track budget, schedule variances, and deliverable versions  Specification  A precise definition of a physical item, procedure, service, or result for the purpose of purchase and/or implementation of an item or service  Sources of Scope Change  Variation in government regulations  Failure to include a required feature in the design of the product  Customers who change their minds about the desired nature of the deliverable
  • 145. 145Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Key Scope Concepts (continued) Work Breakdown Structure  A deliverable-oriented grouping of process elements that organizes and defines the total scope of the project  Each descending level represents an increasingly detailed definition of a project component  Project components may be products or services
  • 146. 146Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Time Management  Definition  A subset of project management that includes the processes required to ensure timely completion of the project  Processes  Activity definition  Activity sequencing  Activity duration estimating  Schedule development  Schedule control
  • 147. 147Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Purpose of Scheduling Processes  Illustrates interdependence of project activities, work packages, and work units  Monitors and controls timing of project work  Guides the allocation of resources  Drives personnel availability issues and activities
  • 148. 148Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Remodel Kitchen WBS Purchase Appliances Purchase Fixtures Remodel Kitchen Design Purchase Carpentry ElectricalLevel 1 Level 2
  • 149. 149Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. ID Task Name Dur 1 1 DESIGN 10d 2 1.1 SELECT DESIGNER 3d 3 1.2 CREATEPLANS 5d 4 1.3 SELECT CONTRACTOR 2d 5 2 PURCHASING 6d 6 2.1 PURCHASEAPPLIANCES 6d 7 3 CARPENTERS 15d 8 3.1 TEAROUT 3d 9 3.2 CHANGEWALLS 4d 10 3.3 INSTALL NEW CABINETS 3d 11 3.4 INSTALL SINK 1d 12 3.5 INSTALL DISHWASHER 2d 13 3.6 INSTALL FLOOR 2d 14 3.7 FINISHANDCLEANUP 1d 15 4 ELECTRICAL 3d 16 4.1 WIRING 2d 17 4.2 INSTALL LIGHTS 1d 18 5 MECHANICAL 2d 19 5.1 INSTALL PIPING 2d 20 6 READY FORDINNER 1d -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Kitchen Remodeling Precedence Relationships
  • 150. 150Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Kitchen Remodeling Forward Pass - Early Dates ID Task Name Dur ES Date EF Date 1 DESIGN 10d 2 SELECT DESIGNER 3d 3 CREATEPLANS 5d 4 SELECT CONTRACTOR 2d 5 PURCHASING 6d 6 PURCHASEAPPLIANCES 6d 7 CARPENTERS 15d 8 TEAR OUT 3d 9 CHANGEWALLS 4d 10 INSTALL NEW CABINETS 3d 11 INSTALL SINK 1d 12 INSTALL DISHWASHER 2d 13 INSTALL FLOOR 2d 14 FINISH ANDCLEANUP 1d 15 ELECTRICAL 3d 16 WIRING 2d 17 INSTALL LIGHTS 1d 18 MECHANICAL 2d 19 INSTALL PIPING 2d 20 READY FORDINNER 1d S S M T W T F S S M T W T F S S M T W T F S S M T W T F Feb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99
  • 151. 151Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Kitchen Remodeling Backward Pass - Late Dates ID Task Name Dur LS Date LF Date 1 DESIGN 10d 2 SELECT DESIGNER 3d 3 CREATEPLANS 5d 4 SELECT CONTRACTOR 2d 5 PURCHASING 6d 6 PURCHASEAPPLIANCES 6d 7 CARPENTERS 15d 8 TEAR OUT 3d 9 CHANGEWALLS 4d 10 INSTALL NEW CABINETS 3d 11 INSTALL SINK 1d 12 INSTALL DISHWASHER 2d 13 INSTALL FLOOR 2d 14 FINISHANDCLEANUP 1d 15 ELECTRICAL 3d 16 WIRING 2d 17 INSTALL LIGHTS 1d 18 MECHANICAL 2d 19 INSTALL PIPING 2d 20 READY FORDINNER 1d F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S Feb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99 Mar
  • 152. 152Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Kitchen Remodeling Total Float ID Task Name Dur ES Date EF Date LS Date LF Date T Float 1 DESIGN 10d 2 SELECT DESIGNER 3d 3 CREATEPLANS 5d 4 SELECT CONTRACTOR 2d 5 PURCHASING 6d 6 PURCHASEAPPLIANCES 6d 7 CARPENTERS 15d 8 TEAR OUT 3d 9 CHANGEWALLS 4d 10 INSTALL NEW CABINETS 3d 11 INSTALL SINK 1d 12 INSTALL DISHWASHER 2d 13 INSTALL FLOOR 2d 14 FINISH AND CLEANUP 1d 15 ELECTRICAL 3d 16 WIRING 2d 17 INSTALL LIGHTS 1d 18 MECHANICAL 2d 19 INSTALL PIPING 2d 20 READY FOR DINNER 1d T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S Feb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99 Ma Total Float = Late Finish Date – Early Finish Date
  • 153. 153Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Kitchen Remodeling Summary ID Task Name Dur ES Date EF date LS Date LF Date T Float 1 DESIGN 10d 1 10 1 10 0d 2 SELECT DESIGNER 3d 1 3 1 3 0d 3 CREATEPLANS 5d 4 8 4 8 0d 4 SELECT CONTRACTOR 2d 9 10 9 10 0d 5 PURCHASING 6d 9 14 12 17 3d 6 PURCHASEAPPLIANCES 6d 9 14 12 17 3d 7 CARPENTERS 15d 11 25 11 25 0d 8 TEAR OUT 3d 11 13 11 13 0d 9 CHANGEWALLS 4d 14 17 14 17 0d 10 INSTALL NEW CABINETS 3d 18 20 18 20 0d 11 INSTALL SINK 1d 21 21 22 22 1d 12 INSTALL DISHWASHER 2d 21 22 21 22 0d 13 INSTALL FLOOR 2d 23 24 23 24 0d 14 FINISHAND CLEANUP 1d 25 25 25 25 0d 15 ELECTRICAL 3d 18 20 20 22 2d 16 WIRING 2d 18 19 20 21 2d 17 INSTALL LIGHTS 1d 20 20 22 22 2d 18 MECHANICAL 2d 18 19 19 20 1d 19 INSTALL PIPING 2d 18 19 19 20 1d 20 READY FORDINNER 1d 26 26 26 26 0d 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Float
  • 154. 154Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Cost Management “… the processes required to ensure that the project is completed within the approved budget.”  Resource planning  Cost estimating  Cost budgeting  Cost control
  • 155. 155Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. One Performance Measurement  Earned Value  Budgeted Cost of Work Performed (BCWP)  Related Terms  Budgeted Cost of Work Scheduled (BCWS)  Actual Cost of Work Performed (ACWP)  Budget at Completion (BAC)
  • 156. 156Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Cumulative Status Display Dollars Current Date BCWS BAC ACWP BCWP Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 1999 2000 2001
  • 157. 157Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Variances  Schedule Variance (SV) = BCWP – BCWS  Cost Variance (CV) = BCWP – ACWP  Time Variance (TV) = STWP – ATWP
  • 158. 158Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. What Is the SV? Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr. ACWP = $73,000 BCWS = $56,000 BCWP = $30,800 (55% completed) Dollars (000) Current Date 100 90 80 70 60 50 40 30 20 10 0 Plan BCWS Earned Value BCWP Schedule Variance (SV) Actual ACWP Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 1999 2000 2001
  • 159. 159Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 What Is the CV? Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr. ACWP = $73,000 BCWS = $56,000 BCWP = $30,800 SV = $-25,200 Cost Variance (CV) Dollars (000) Current Date 100 90 80 70 60 50 40 30 20 10 0 1999 2000 2001 Plan BCWS Earned Value BCWP Actual ACWP
  • 160. 160Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. What Is the Time Variance? Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr. Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 ACWP = $73,000 BCWS = $56,000 BCWP = $30,800 SV = - $25,200 CV = - $42,200 (000) Dollars Actual ACWP Earned Value BCWP Cost Variance (CV) Plan BCWS TV 6 mos. Delay STWP ATWP 1999 2000 2001 100 90 80 70 60 50 40 30 20 10 0
  • 161. 161Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Quality Management “A subset of project management that includes the process required to ensure that the project will satisfy the needs for which it was undertaken.”  Quality planning  Quality assurance  Quality control
  • 162. 162Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project HR Management “… the processes required to make the most effective use of the people involved with the project.”  Organizational planning  Staff acquisition  Team development
  • 163. 163Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Responsibility Chart A B C D E F S R A P P S A P P S R A I R S A P S P I A ... P P P P E R S O N P H A S E R e q u ir e m e n t s F u n c t io n a l D e s ig n D e v e lo p m e n t T e s t in g P = P a r tic ip a n t A = A c c o u n t a b le R = R e v ie w r e q u ir e d I = In p u t r e q u ir e d S = S ig n - o ff r e q u ir e d
  • 164. 164Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Responsibility Chart Characteristics  Work Package Level  Components  WBS activity  Responsible organization  Responsible position title or person  Type of responsibility  Approving authority  Prime implementation accountability  Support  Notification
  • 165. 165Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 9-1 Responsibility Allocation  Using the handout in your manual, complete the responsibility matrix for your project  Discuss with a classmate the effectiveness of the allocation of responsibility and authority depicted
  • 166. 166Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. “… the processes concerned with identifying, analyzing, and responding to project risk.”  Risk identification  Risk quantification  Risk response development  Risk response control Project Risk Management
  • 167. 167Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Risk Decision Tree
  • 168. 168Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 9-2 Risk Assessment  Construct a risk assessment tree for a critical decision on your project  If your original project selection does not lend itself to this exercise, feel free to substitute another project
  • 169. 169Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Communications Management “… the timely and appropriate generation, collection, dissemination, storage, and ultimate disposition of project information.”  Communications planning  Information distribution  Performance reporting  Administrative closure
  • 170. 170Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Procurement Management “… includes the processes required to acquire goods and services from outside the performing organization.”  Procurement planning  Solicitation planning  Solicitation  Source selection  Contract administration  Contract closeout
  • 171. 171Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Summary  Identified and described the nine knowledge areas and the core processes in each  Allocated typical processes and activities to their appropriate knowledge area
  • 172. 172Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Unit 10: Role of the Project Manager Upon completion, you will be able to … Identify, in your environment, the most critical project manager:  Roles  Responsibilities  Interpersonal skill requirements  Your knowledge area gaps and strengths
  • 173. 173Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Manager Roles  Decision-maker  Manager  Coach  Sales person  Communication channel  PM expert  Encourager Facilitator  Power broker Behavior model  Disciplinarian Other?
  • 174. 174Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Project Manager Responsibilities  Project plan implementation  Achievement of objectives  Project integration  Communications  Stakeholder relations  Change management system  Priority establishment and maintenance
  • 175. 175Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. More Responsibilities  Staff acquisition, retention, and motivation  Selection and use of PM tools and techniques  Compliance with regulations, state and federal laws, and organization policies and procedures  Resolving team conflicts  Negotiating win/win solutions  Deliver the project on time and within budget  Other?
  • 176. 176Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Skill and Knowledge Requirements T h is f ig u r e is a c o n c e p t u a l v ie w o f th e s e r e la tio n s h ip s . T h e o v e r la p s s h o w n a r e n o t p r o p o r t io n a l. A p p li c a t io n A r e a K n o w le d g e a n d P r a c t ic e G e n e r a l M a n a g e m e n t K n o w l e d g e a n d P r a c t ic e T h e P r o je c t M a n a g e m e n t B o d y o f K n o w le d g e G e n e r a l ly A c c e p t e d P r o je c t M a n a g e m e n t K n o w l e d g e a n d P r a c t ic e
  • 177. 177Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Competency can be defined as …  A qualification equal to a position requirement, or  Capacities one must possess to perform satisfactorily in a position.
  • 178. 178Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Success depends on your …  Knowledge  Behaviors  Attitude  Organizational environment  Project environment  Fit  Self-knowledge and ability to adjust
  • 179. 179Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. One Emerging Operating Style “We will need scroungers, tinkerers, masters of the extemporaneous, and those who can make it happen, regardless of the rules, the odds, or the inevitable second guess.”* * Project Management Handbook, by David I. Cleland and William R. King
  • 180. 180Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 10-1 Project Manager Interpersonal Skills  Use the handout to assess the interpersonal skills required to manage a project successfully in your organization; then assess your skills, and identify skill gaps and strengths
  • 181. 181Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Recognizing a Successful Project Manager  Meets cost, schedule, technical, and mission objectives Plus  Attains high levels of satisfaction and perception of project success from:  Client  Sponsor  Users  Team
  • 182. 182Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Example of an Organization Competence Assessment Tool  CMM™ background  Levels of Software Engineering Maturity Model  Basic  Repeatable  Defined  Managed  Optimized
  • 183. 183Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Why Reading Your Environment Is Important Assessments reveal:  Fit between you, the organization, and the project  Your development needs and strengths  PM strategies most likely to be successful  PM strategies to be avoided  Guide for tools and techniques selection  Guide your performance expectations of self and others And They:  Influence your own management style
  • 184. 184Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. Exercise 10-2 PM Knowledge Needs Assessment  Complete the exercise in your manual, and then discuss the implications with a classmate  Identify knowledge gaps, strengths, and possible developmental activities including:  Growth assignments  Seminars  Self-study  Degree programs  Other?
  • 185. 185Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. PM Knowledge Needs Assessment Discussion Question What did you learn from this exercise about:  Yourself?  Your project?  Your organization?  Your future?
  • 186. 186Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. A Framework for Project Management Seminar Summary 1. Introduction and Key Concepts 2. Project Life Cycle Models 3. Initiating Projects 4. Planning Projects 5. Executing Projects 6. Controlling Projects 7. Closing Projects 8. Organizational Impacts 9. Overview of Knowledge Areas 10. Role of the Project Manager
  • 187. 187Copyright © 1999 Project Management Institute, Inc. All Rights Reserved. End  Please complete the seminar evaluation form before leaving.  Thank you for your participation!