The document discusses various project management concepts including project management plans, Gantt charts, work breakdown structures, milestones, network techniques, and dummy activities. It provides definitions and examples of each concept. A project management plan formally defines how a project is executed, monitored, and controlled. A Gantt chart is a bar chart that illustrates a project schedule by showing task durations and dependencies. A work breakdown structure is a hierarchical decomposition of tasks needed to complete a project. Milestones mark significant points in a project's lifecycle. Network diagrams show logical relationships between project activities. Dummy activities depict technological dependencies without consuming resources.
Project management theory, principles, organization functions, risk management, stress management, principles, applications of management, planning and scheduling, initiatives and closing of projects, work breakdown structures,
Project management theory, principles, organization functions, risk management, stress management, principles, applications of management, planning and scheduling, initiatives and closing of projects, work breakdown structures,
03 Construction Project Planning and Schedulingakashpadole
The presentation has prepared as per the syllabus of Mumbai University.
Go through the presentation, if you like it then share it with your friends and classmates.
Thank you :)
A Gantt chart is a visual representation that provides an instant overview of the status of a project. It outlines all activities involved in a project against a timescale.
What do you think about WBS Gantt Chart? Are they the greatest inventions since sliced bread or just another boring project management tool?
Well, we're here to tell you that WBS Gantt Chart are actually pretty awesome, and they can make your project management life a whole lot easier.
---------------------
WBS Gantt Chart for Jira
📚 Download Teamboard for Free Trial 👉 https://bit.ly/TBProScheduler
---------------
About DevSamurai:
🌟 We are Atlassian Gold Marketplace Partners
➡️ We provide DevOps solutions for its growing customer base.
---
Connect with us:
🌏Website: https://teamboard.cloud
🌏Website: https://www.devsamurai.com
📲 Facebook: https://www.facebook.com/itdevsamurai
🤓 Twitter: https://twitter.com/DevsamuraiCom
03 Construction Project Planning and Schedulingakashpadole
The presentation has prepared as per the syllabus of Mumbai University.
Go through the presentation, if you like it then share it with your friends and classmates.
Thank you :)
A Gantt chart is a visual representation that provides an instant overview of the status of a project. It outlines all activities involved in a project against a timescale.
What do you think about WBS Gantt Chart? Are they the greatest inventions since sliced bread or just another boring project management tool?
Well, we're here to tell you that WBS Gantt Chart are actually pretty awesome, and they can make your project management life a whole lot easier.
---------------------
WBS Gantt Chart for Jira
📚 Download Teamboard for Free Trial 👉 https://bit.ly/TBProScheduler
---------------
About DevSamurai:
🌟 We are Atlassian Gold Marketplace Partners
➡️ We provide DevOps solutions for its growing customer base.
---
Connect with us:
🌏Website: https://teamboard.cloud
🌏Website: https://www.devsamurai.com
📲 Facebook: https://www.facebook.com/itdevsamurai
🤓 Twitter: https://twitter.com/DevsamuraiCom
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
Literature Review Basics and Understanding Reference Management.pptxDr Ramhari Poudyal
Three-day training on academic research focuses on analytical tools at United Technical College, supported by the University Grant Commission, Nepal. 24-26 May 2024
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...ssuser7dcef0
Power plants release a large amount of water vapor into the
atmosphere through the stack. The flue gas can be a potential
source for obtaining much needed cooling water for a power
plant. If a power plant could recover and reuse a portion of this
moisture, it could reduce its total cooling water intake
requirement. One of the most practical way to recover water
from flue gas is to use a condensing heat exchanger. The power
plant could also recover latent heat due to condensation as well
as sensible heat due to lowering the flue gas exit temperature.
Additionally, harmful acids released from the stack can be
reduced in a condensing heat exchanger by acid condensation. reduced in a condensing heat exchanger by acid condensation.
Condensation of vapors in flue gas is a complicated
phenomenon since heat and mass transfer of water vapor and
various acids simultaneously occur in the presence of noncondensable
gases such as nitrogen and oxygen. Design of a
condenser depends on the knowledge and understanding of the
heat and mass transfer processes. A computer program for
numerical simulations of water (H2O) and sulfuric acid (H2SO4)
condensation in a flue gas condensing heat exchanger was
developed using MATLAB. Governing equations based on
mass and energy balances for the system were derived to
predict variables such as flue gas exit temperature, cooling
water outlet temperature, mole fraction and condensation rates
of water and sulfuric acid vapors. The equations were solved
using an iterative solution technique with calculations of heat
and mass transfer coefficients and physical properties.
2. Project Management
• Project management is the use of specific
knowledge, skills, tools and techniques to
deliver something of value to people. The
development of software for an improved
business process, the construction of a
building, the relief effort after a natural
disaster, the expansion of sales into a new
geographic market—these are all examples of
projects.
3. Project Management
• A Project management plan is a formal,
approved document that defines how the
project is executed, monitored, and
controlled. It may be a summary or a detailed
document and may include baselines,
subsidiary management plans, and other
planning documents
4. Bar chart/ Gantt Chart
• A Gantt chart is a commonly used graphical
depiction of a project schedule. It's a type of
bar chart showing the start and finish dates of
a project's elements such as resources,
planning and dependencies. 1. Henry Gantt
(1861-1919), an American mechanical
engineer, designed the Gantt chart.
6. Bar chart/ Gantt Chart
• A Gantt chart is a type of bar chart that
illustrates a project schedule.
• This chart lists the tasks to be performed on
the vertical axis, and time intervals on the
horizontal axis.
• The width of the horizontal bars in the graph
shows the duration of each activity.
7. Bar chart/ Gantt Chart
• Gantt charts illustrate the start and finish
dates of the terminal elements and summary
elements of a project.
• Terminal elements and summary elements
constitute the work breakdown structure of
the project.
• Modern Gantt charts also show
the dependency (i.e., precedence network)
relationships between activities
8. Work Breakdown Structure
• Before you create a work breakdown structure, it's
essential to first assess the project scope by talking to all
stakeholders and key team members involved.
• As the project manager, you want to ensure that all critical
input and deliverables are gathered and transparently
prioritized. You may use Gantt charts, flow charts,
spreadsheets, or lists to show the hierarchical outline of
importance and connectivity between the tasks needed to
complete the project.
• After outlining the deliverables and tasks in order of
completion, you can then assign each task to a project
team member. Ensure no team member carries the
majority of the project's weight by spreading duties and
responsibilities across the team.
9. Work Breakdown Structure
• Here are some work breakdown structure
examples. You can use any of these to outline
your WBS.
• WBS spreadsheet: You can structure your WBS
efficiently in a spreadsheet, noting the different
phases, tasks, or deliverables in the columns and
rows.
• WBS flowchart: You can structure your WBS in a
diagrammatic workflow. Most WBS examples and
templates you may find are flowcharts.
10. Work Breakdown Structure
• WBS list: You can structure your WBS as a simple
list of tasks or deliverables and subtasks. This is
the most straightforward approach to make a
WBS.
• Work breakdown structure Gantt chart. You can
structure your WBS as a Gantt chart that
represents both a spreadsheet and a timeline.
With a Gantt chart-structured WBS, you can link
task dependencies and show project milestones.
11.
12.
13. Milestone chart
• A milestone is a specific point within a
project’s life cycle used to measure the
progress toward the ultimate goal. Milestones
in project management are used as signal
posts for a project's start or end date, external
reviews or input, budget checks, submission of
a major deliverable, etc. A milestone is a
reference point that marks a significant event
or a branching decision point within a project.
14. Milestone chart
Examples of project milestones
While the final deliverable or product is indeed a
significant milestone, there are several other
milestones that will help you move smoothly
toward the final goal. An example of a milestone
in project management could be any of the
following:
• The beginning and end dates for project phases
• Getting approval from a stakeholder that allows
you to move to the next phase
• Key deliverables, meetings, or events
17. Network Techniques
• Network diagrams are the preferred technique
for showing activity sequencing
• A network diagram is a schematic display of
the logical relationships among, or sequencing
of, project activities
• Two main formats are the arrow and
precedence diagramming methods
18. Event
• The beginning and end points of an activity
are called events or nodes or connector. This is
usually represented by circle in a network.
• Here, A is known as the activity.
21. Event
• a) Merge Event: When two or more activities come from
an event it is known as merge event.
• b) Burst Event: When more than one activity leaves an
event is known as burst event.
• c) Merge & Burst Event: An activity may be merged and
burst at the same time.
22. Predecessor & Successor Activity
• Predecessor activity: activity that must be
completed immediately prior to the start of
another activity.
• Successor activity: activity which cannot be
started until one or more of other activities
are completed but immediately succeed them
are called successor activity.
25. Dummy activity
• Dummy activity: An activity which does not
consume any kind of resources but merely
depicts the technological dependence is called a
dummy activity. Dummy activity is inserted in a
network to classify the activity pattern in the
following situations:
• i) To make activities with common starting and
finishing points distinguishable.
• ii) To identify and maintain the proper
precedence relationship between activities those
are not connected by events.