ELCIR CYCLE FOR PROJECT MANAGERS:
1-PROJECTINITIATION
contract importfromexcel.pptx
A/PROJECT DEFINITION: First of all we define the project and LG with the accounting
department (Ibrahim)
B/CONTRACT READING: PM should real all contract conditions , specifications and condition
of contract (attach all info on ERP)
C/ DRAWINGS: PM should know and study all the project drawings, and they have to
prepare the list of drawings and RFI’s (Define entity, submittal categories). And send to
Jean Rabahieh ONLY the drawings that are needed for costing of items.
D/ MACRO PLAN: PM prepares a simple macro planning to identify major project milestones
and date. This planning is rather simple and straight forward, it should also be attached on
ERP. Step D (macro plan) goes in parallel with step C (drawings)
C/ESTIMATION: the project manager should define the estimate name (tenders of the
project), and enter the tender BOQ’s manually or by importing it from excel. Then, Email &
NotifyEstimator(jean rabahieh) & Cost control manager (Ibrahim) to proceed with budget
costing. Several estimates can be done for the project if needed using an easy copy/paste
then modify method.
Estimator (jean) should estimate the direct cost of those BOQ’s, and cost controller(Ibrahim)
will do the indirect cost.. After all this, the results should be discussed with theCONCERNED
PM (discuss the budget).After final agreement, the PM should sign the budget and the
General manager (Jean marc). At this point, the budget becomes the responsibility of the
PM.
Accounting
Define project
define LG
PM
Contract/reading
list of drawings/RFI
Macro plan (attach)
WBS
Take off (WBS vs BOQ)
send item drawings to
jean
Estimate/budget
Direct cost (jean)
Indirect cost (ibrahim)
check budget with PM &
General manager
PM Prepares Risk log
2
After the estimation is done the project managers define a contract with all the information
about it (advance payment, retention, taxes…), and they import the BOQ’s of this contract
from the agreed upon estimate (budget) into contracts and partial contract(contract
subdivisions in case the contract is divided by client).
D/ RISKLOG: A risklogthat identifiesthe risksof the projectsasper a special template tobe
providedbyGeneral manager.Thisrisklogshouldbe preparedbyPMafter agreeingonbudget,and
it shouldalsobe attachedonERP.
E/ Work Breakdown Structure:After reading all the drawings , the PM should be able to
divide his project by location according to a logic that suits the relevant project. We call this
a WBS, and the PM has to input the WBS of the Project (WBS master list and detail
list).Examples of Work breakdown structures are as follows:
WBS Example 1
WBS Example 2
bldg
level1
doors crowns
level 2
fire doors doors crowns
bldg
level1
apt1 apt2
level 2
apt 1 apt 2
3
The objective of the WBS is to prepare the take off and production orders as per project
needs, as well as project reporting documents. Typically, This division should reflect the
client requirements, planning and/or the way the Project manager should look at the
project. All concerned parties should speak the “same language” of the project and respect
this division.
E/ TAKE OFF:After defining the WBS and contract, the take off is prepared and every
location (WBS) will include the relevant BOQ’s that are in this WBS/location.
WBS WBS description BOQ BOQ description qty
101100 bldg1-level 1-doors 01fr120x320 fire rate door 120 by320 3
04cr2111 crown width211 cm… 5
05fr213x234 fire rate door 213 by234 8
Take off Example
N.B: most of the steps of project initiation, can go in parallel, and the PM should
orchestrate and coordinate with all the parties (estimation, design, production). It is the
responsibility of the PM to enter, the BOQ, WBS, list of drawings and take off. The
Materials, production time and labor resources and indirect costing INPUT are the
responsibility of the estimators (jean and Ibrahim)
4
2-PROJECTOPERATION
A/MICRO PLANNING: After the budget is done the project manager should draw the
detailed plan of his project. They can use any planning method like primavera, MS project or
even excel. Then they will allocate BOQ items to the tasks at hand (they will know it from
the Take off preparation step before. This will give the procurement plan and know what
are the material that should be bought at the right time so when they are needed they can
find it without affecting on the project plan. Manpower histogram of installation should also
be inputed by the PM to the micro plan.
B/ BARCODING:Once every BOQ has a WBS, we can concatenate the BOQ with the WBS and
we obtain a barcode that can be used and known in design, PM, shipping and production
departments.
wbs desc boq Descry qty unit
101100 bldg1-level 1-doors 01fr120x320 fire rate door 120 by320 3 pcs
04cr2111 crown width211 cm… 5 lm
05fr213x234 fire rate door 213 by234 8 pcs
An example thatindicate the fire rated door of building 1, level 1 is as follows:
Barcode: 101100-01fr120x320
Barcode reading :bldg 1-level 1-doors- fire rate door 120 by 320
C/ SUBMITTALS : there is a procedure to follow-up all the dates and content of all the
submittals to the client, as well as the client responses and their date and content. So, the
history of any submittals is automatically generated once this procedure is followed up by
the PM.
PM Planning
Budget+ plan = procurementplan
withJM(cash flow of purchasing)
Take off +plan=Work order
planningwithproduction(cash
flow of clientpayments)
PM
Progress/paymentcertificate
Submittals
Work orderissue asper plan
RFP
Change orders
Installationbudget/Subcontract
5
Submittals are divided by categories like materials, drawings… .Subcategories are also
possible to report like doors, crowns… separately, if needed.
D/ Request for Purchases (RFP): Prepare the major items to be purchased and their required
times by PM.
E/ WORK ORDERS:As per the planning tasks and their allocated quantities , the project
manager should prepare the work orders in coordination with the production. Client
deadlines should be clear, however, it is possible to put work orders in advance if that suits
the production, but delays should not be acceptable. The planning of work orders should
reflect client/project priorities. The PM responsibility is to issue the work orders and their
deadline/required times. In case, there is a priority of certain quantities for a certain item,
we suggest separating the work orders with priority from those with lower priority.
F/ INSTALLATION BUDGET: an installation budget form is to be prepared by site and
submitted to PM. This file should be attached to contract on ERP.
G/ SUBCONTRACTING: PM should input ad follow the procedure for tender management
system on ERP to so prepare subcontracting contracts with their payment follow up.
H/ CHANGE ORDERS: there is a procedure to prepare variation orders, with follows up on
drawings, letters, and client answers all linked together in submittals.The PM should follow
this procedure in variation order preparation. Once the client accepts/approves a variation
order, then the PM, with one click,puts the VO as an addendum to the contract and can do
progress on it.
I/ PAYMENT CERTIFICATE:Preparation of progress periods and progress quantities should be
inputted by the PM. Once the Client approves the concerned certificate the PM can close
the certificate with one click and the accounting receives the automated receivable invoice
all linked up to the concerned certificate automatically. Once a payment certificate is closed,
it can not be deleted, so a roll back starting from accounting has to be generated first then a
re-opening of the certificate is possible and ready for modification or deletion.
Please note that the PM’s can NOT exceed the cumulative contract quantities without a
variation order (the system does not allow it). In case the contract includes priced items
without quantities, then the allowed progress quantities are open ended, but this should be
indicated in the contract.

More Related Content

What's hot

Construction management
Construction managementConstruction management
Construction management
Mercedita Balbero
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
Kai Yun Pang
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
Software Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - SlidesSoftware Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - Slides
Pang Khai Shuen
 
PP1 Project 1 Project implementation
PP1 Project 1 Project implementationPP1 Project 1 Project implementation
PP1 Project 1 Project implementation
Teo Kean Hui
 
PP1 Project 3 Cover letter
PP1 Project 3 Cover letterPP1 Project 3 Cover letter
PP1 Project 3 Cover letter
Teo Kean Hui
 
Cost Engineering for Tendering & Contracting
Cost Engineering for Tendering & ContractingCost Engineering for Tendering & Contracting
Cost Engineering for Tendering & Contracting
Martin van Vliet
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
Kai Yun Pang
 
PP1 Project 2 Project Report
PP1 Project 2 Project ReportPP1 Project 2 Project Report
PP1 Project 2 Project Report
Teo Kean Hui
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
lohwenjun
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
Quo Ming
 
Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)
Kai Yun Pang
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
Kai Yun Pang
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
Delhi Technological University
 
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
CCT International
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
마 이환
 
Assignment 1 - Software
Assignment 1 - SoftwareAssignment 1 - Software
Assignment 1 - Software
Kai Yun Pang
 
Accounting standard 7
Accounting standard 7Accounting standard 7
Accounting standard 7
Anjali Ramnani
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIM
CCT International
 

What's hot (20)

Construction management
Construction managementConstruction management
Construction management
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Software Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - SlidesSoftware Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - Slides
 
PP1 Project 1 Project implementation
PP1 Project 1 Project implementationPP1 Project 1 Project implementation
PP1 Project 1 Project implementation
 
PP1 Project 3 Cover letter
PP1 Project 3 Cover letterPP1 Project 3 Cover letter
PP1 Project 3 Cover letter
 
Cost Engineering for Tendering & Contracting
Cost Engineering for Tendering & ContractingCost Engineering for Tendering & Contracting
Cost Engineering for Tendering & Contracting
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
PP1 Project 2 Project Report
PP1 Project 2 Project ReportPP1 Project 2 Project Report
PP1 Project 2 Project Report
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
 
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Assignment 1 - Software
Assignment 1 - SoftwareAssignment 1 - Software
Assignment 1 - Software
 
Accounting standard 7
Accounting standard 7Accounting standard 7
Accounting standard 7
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIM
 

Similar to project initiation

Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
Bhalindra Bath - projects & M&A law
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
NithyaPotterhead
 
01.15+Audit-Success.pdf
01.15+Audit-Success.pdf01.15+Audit-Success.pdf
01.15+Audit-Success.pdf
helmut15
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
Cerasela Angelescu
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
MANNU KUMAR
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Antonio Coladarce
 
M Simpson coursework
M Simpson courseworkM Simpson coursework
M Simpson coursework
Milton Simpson
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
Sandeep Yadav
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
Abdulaziz Kaya
 
Major Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdfMajor Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdf
ssuser6d14e4
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
AprilRosal1
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
Hamdija Velagic
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
Ar.Vijay Kumar
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slide
Sithick Mohamed .
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
Sahl Buhary
 
03 Architectural Job Phases
03 Architectural Job Phases03 Architectural Job Phases
03 Architectural Job Phases
Douglas Vail
 
Matrix207
Matrix207Matrix207
Matrix207
jbonvier
 
Qsx
QsxQsx
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
Sysy Jnthn
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
Nekumi Kida
 

Similar to project initiation (20)

Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
01.15+Audit-Success.pdf
01.15+Audit-Success.pdf01.15+Audit-Success.pdf
01.15+Audit-Success.pdf
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
M Simpson coursework
M Simpson courseworkM Simpson coursework
M Simpson coursework
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
 
Major Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdfMajor Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdf
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slide
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
03 Architectural Job Phases
03 Architectural Job Phases03 Architectural Job Phases
03 Architectural Job Phases
 
Matrix207
Matrix207Matrix207
Matrix207
 
Qsx
QsxQsx
Qsx
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 

Recently uploaded

Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 

Recently uploaded (20)

Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 

project initiation

  • 1. 1 ELCIR CYCLE FOR PROJECT MANAGERS: 1-PROJECTINITIATION contract importfromexcel.pptx A/PROJECT DEFINITION: First of all we define the project and LG with the accounting department (Ibrahim) B/CONTRACT READING: PM should real all contract conditions , specifications and condition of contract (attach all info on ERP) C/ DRAWINGS: PM should know and study all the project drawings, and they have to prepare the list of drawings and RFI’s (Define entity, submittal categories). And send to Jean Rabahieh ONLY the drawings that are needed for costing of items. D/ MACRO PLAN: PM prepares a simple macro planning to identify major project milestones and date. This planning is rather simple and straight forward, it should also be attached on ERP. Step D (macro plan) goes in parallel with step C (drawings) C/ESTIMATION: the project manager should define the estimate name (tenders of the project), and enter the tender BOQ’s manually or by importing it from excel. Then, Email & NotifyEstimator(jean rabahieh) & Cost control manager (Ibrahim) to proceed with budget costing. Several estimates can be done for the project if needed using an easy copy/paste then modify method. Estimator (jean) should estimate the direct cost of those BOQ’s, and cost controller(Ibrahim) will do the indirect cost.. After all this, the results should be discussed with theCONCERNED PM (discuss the budget).After final agreement, the PM should sign the budget and the General manager (Jean marc). At this point, the budget becomes the responsibility of the PM. Accounting Define project define LG PM Contract/reading list of drawings/RFI Macro plan (attach) WBS Take off (WBS vs BOQ) send item drawings to jean Estimate/budget Direct cost (jean) Indirect cost (ibrahim) check budget with PM & General manager PM Prepares Risk log
  • 2. 2 After the estimation is done the project managers define a contract with all the information about it (advance payment, retention, taxes…), and they import the BOQ’s of this contract from the agreed upon estimate (budget) into contracts and partial contract(contract subdivisions in case the contract is divided by client). D/ RISKLOG: A risklogthat identifiesthe risksof the projectsasper a special template tobe providedbyGeneral manager.Thisrisklogshouldbe preparedbyPMafter agreeingonbudget,and it shouldalsobe attachedonERP. E/ Work Breakdown Structure:After reading all the drawings , the PM should be able to divide his project by location according to a logic that suits the relevant project. We call this a WBS, and the PM has to input the WBS of the Project (WBS master list and detail list).Examples of Work breakdown structures are as follows: WBS Example 1 WBS Example 2 bldg level1 doors crowns level 2 fire doors doors crowns bldg level1 apt1 apt2 level 2 apt 1 apt 2
  • 3. 3 The objective of the WBS is to prepare the take off and production orders as per project needs, as well as project reporting documents. Typically, This division should reflect the client requirements, planning and/or the way the Project manager should look at the project. All concerned parties should speak the “same language” of the project and respect this division. E/ TAKE OFF:After defining the WBS and contract, the take off is prepared and every location (WBS) will include the relevant BOQ’s that are in this WBS/location. WBS WBS description BOQ BOQ description qty 101100 bldg1-level 1-doors 01fr120x320 fire rate door 120 by320 3 04cr2111 crown width211 cm… 5 05fr213x234 fire rate door 213 by234 8 Take off Example N.B: most of the steps of project initiation, can go in parallel, and the PM should orchestrate and coordinate with all the parties (estimation, design, production). It is the responsibility of the PM to enter, the BOQ, WBS, list of drawings and take off. The Materials, production time and labor resources and indirect costing INPUT are the responsibility of the estimators (jean and Ibrahim)
  • 4. 4 2-PROJECTOPERATION A/MICRO PLANNING: After the budget is done the project manager should draw the detailed plan of his project. They can use any planning method like primavera, MS project or even excel. Then they will allocate BOQ items to the tasks at hand (they will know it from the Take off preparation step before. This will give the procurement plan and know what are the material that should be bought at the right time so when they are needed they can find it without affecting on the project plan. Manpower histogram of installation should also be inputed by the PM to the micro plan. B/ BARCODING:Once every BOQ has a WBS, we can concatenate the BOQ with the WBS and we obtain a barcode that can be used and known in design, PM, shipping and production departments. wbs desc boq Descry qty unit 101100 bldg1-level 1-doors 01fr120x320 fire rate door 120 by320 3 pcs 04cr2111 crown width211 cm… 5 lm 05fr213x234 fire rate door 213 by234 8 pcs An example thatindicate the fire rated door of building 1, level 1 is as follows: Barcode: 101100-01fr120x320 Barcode reading :bldg 1-level 1-doors- fire rate door 120 by 320 C/ SUBMITTALS : there is a procedure to follow-up all the dates and content of all the submittals to the client, as well as the client responses and their date and content. So, the history of any submittals is automatically generated once this procedure is followed up by the PM. PM Planning Budget+ plan = procurementplan withJM(cash flow of purchasing) Take off +plan=Work order planningwithproduction(cash flow of clientpayments) PM Progress/paymentcertificate Submittals Work orderissue asper plan RFP Change orders Installationbudget/Subcontract
  • 5. 5 Submittals are divided by categories like materials, drawings… .Subcategories are also possible to report like doors, crowns… separately, if needed. D/ Request for Purchases (RFP): Prepare the major items to be purchased and their required times by PM. E/ WORK ORDERS:As per the planning tasks and their allocated quantities , the project manager should prepare the work orders in coordination with the production. Client deadlines should be clear, however, it is possible to put work orders in advance if that suits the production, but delays should not be acceptable. The planning of work orders should reflect client/project priorities. The PM responsibility is to issue the work orders and their deadline/required times. In case, there is a priority of certain quantities for a certain item, we suggest separating the work orders with priority from those with lower priority. F/ INSTALLATION BUDGET: an installation budget form is to be prepared by site and submitted to PM. This file should be attached to contract on ERP. G/ SUBCONTRACTING: PM should input ad follow the procedure for tender management system on ERP to so prepare subcontracting contracts with their payment follow up. H/ CHANGE ORDERS: there is a procedure to prepare variation orders, with follows up on drawings, letters, and client answers all linked together in submittals.The PM should follow this procedure in variation order preparation. Once the client accepts/approves a variation order, then the PM, with one click,puts the VO as an addendum to the contract and can do progress on it. I/ PAYMENT CERTIFICATE:Preparation of progress periods and progress quantities should be inputted by the PM. Once the Client approves the concerned certificate the PM can close the certificate with one click and the accounting receives the automated receivable invoice all linked up to the concerned certificate automatically. Once a payment certificate is closed, it can not be deleted, so a roll back starting from accounting has to be generated first then a re-opening of the certificate is possible and ready for modification or deletion. Please note that the PM’s can NOT exceed the cumulative contract quantities without a variation order (the system does not allow it). In case the contract includes priced items without quantities, then the allowed progress quantities are open ended, but this should be indicated in the contract.