UNIT III
INTRODUCTION TO COST ESTIMATION
• Importance of costing and estimation
• Methods of costing-elements of cost
estimation
• Types of estimates
• Estimating procedure
• Estimation labor cost, material cost
• Allocation of over head charges
• Calculation of depreciation cost
What is mean by cost estimation?
• Estimation of the expected cost of producing a
job
• Executing a manufacturing order before the
actual production is taken up
• Predicting what new products will cost before
they are made
Definition
Costing or cost accounting means
classifying, recording and allocating the
appropriate expenditure for determining the cost
of production and achieved by keeping a
continuous record of all the costs involved in
manufacturing
REASONS FOR DOING ESTIMATES
• Should the product be produced?
• When a company designs a new product
• To assist management in making an
intelligent decision about producing the
product.
General procedure
• A cost estimate must be developed for jigs,
fixtures, tools, dies and gauges
• Also, the cost of any capital equipment must be
entered into the estimate
• These figures are usually supplied through
quotation by vendors
• An estimate of this nature will include a vast
amount of details, because if management
approves the project, the estimate now becomes
the budget
OBJECTIVES (OR) PURPOSE OF
ESTIMATING
• To establish the selling price of a product
• To ascertain whether a proposed product
can be manufactured and marketed profitably
• To determine how much must be invested in
equipment
• To find whether parts or assemblies can be
more cheaply fabricated or purchased from
outside (make or buy decision)
• To determine the most economical process,
tooling or material for making a product
FUNCTIONS OF ESTIMATING
 To calculate the cost of new material needed to
manufacture a product
 To find the cost of parts to be purchased from outside
vendors
 To find the cost of equipment, machinery, tools, jigs
and fixtures etc. required to be purchased to make the
product
 To calculate the direct and indirect labour cost
associated with the manufacture of the product, based
upon work study.
 To calculate various overhead charges associated with
the product.
 To decide about the profit to be charged, taking
into consideration other manufacturers of same
product in the market
 To calculate the selling price of the product
 To maintain records of previous estimating
activities of the company for future references
 To decide the most economical method of making
the product
 To submit cost estimates with the competent
authority for further action
FUNCTIONS OF ESTIMATING
Contd.,
COMPONENTS OF A COST
ESTIMATE OR JOB ESTIMATE
1. Cost of design
2. Cost of drafting
3. Cost of research and development
4. Cost of raw materials
5. Cost of labour
6. Cost of inspection
7. Cost of tools, jigs and fixtures
8. Overhead cost
1. Cost of Design
• The cost of design of a component or product is
estimated by ascertaining the expected time for the
design of that component
• The estimate design time multiplied by the salary of
designer per unit time gives the estimated cost of
design
• If the design of the component is done by some
outside agency, the total amount paid to outside
agency gives the cost of design.
2. Cost of Drafting
• Once the design of the component is complete,
its drawings have to be prepared by draftsman
• The expected time to be spent in drawing or drafting
is estimated and is then multiplied by the standard
drafting rate or by the salary of the draftsman per unit
time to get estimated cost of drafting
3. Cost of Research and
Development Work
• Before taking up the manufacturing of actual
components/parts considerable time and money has to
be spent on research and development
• The research may be theoretical, experimental or
developmental research.
• The cost of R and D can be estimated by considering
various items of expenditure incurred during R and D
work
4. Cost of Raw Material
• A list of all the materials used in the manufacture of the
product is made which includes the direct as well as
indirect materials
• The quantity (weight or volume) of all the material
expected to be used in the manufacture of the
product is estimated.
• The allowance for material wastage, spoilage and scarp
are also added for each component/part.
• Cost of each material is estimated by multiplying
the estimated quantity of each material with its
estimated future price
• The estimate of future price of a material is made
keeping in view of present prices and general
trends and variations
• Estimated cost of all the materials is added to get
the overall estimated material cost
4. Cost of Raw Material
Contd.,
5. Cost of Labour
• The cost of labour involved in the manufacture of a
product is estimated by estimating the labour time
needed to manufacture the product and multiplying it
by cost of labour per hour.
• In order to estimate the labour time expected to be
spent on a job, one must have thorough knowledge of
the various operations to be performed, machines to
be used, sequence of operations, tools to be used and
labour rates
6. Cost of Inspection
• A product being manufactured is inspected at
various stages during its manufacture
• It may be inspection of raw material or in-
process inspection or inspection of finished
goods
7. Cost and Maintenance Charges of
Tools, Jigs and Fixtures
• The cost of tools, jigs, fixtures etc., is estimated
considering their present prices, market trend and the
number of times a particular tool can be used during
its life-time.
• The estimated cost divided by the number of jobs it
can make, gives the tool cost per unit produced
8. Overhead Costs
• Overhead or indirect costs are those which are not
incurred specifically for any one order or product and
these can not be charged directly to a specific order or
product
• The overhead costs may be estimated by referring
to the records of overhead costs in similar items
produced in past
BASIC STEPS IN COST ESTIMATION
1. Make thorough study of cost estimation request to understand it
fully.
2. Make an analysis of the product and prepare a bill of materials.
3. Make separate lists of parts to be purchased from the market and
parts to be manufactured in plant.
4. Determine the cost of parts to be purchased from outside.
5. Estimate the material cost for the parts/components to be
manufactured in plant.
6. Make manufacturing process plan for the parts to be manufactured
in plant.
7. Estimate the machining time for each operation listed in the
manufacturing process plan.
8. Multiply each operation time by the labour wage rate and add them
up to find direct labour cost
9. Add the estimate of step 4, 5, and 8 to get prime cost of
component.
10. Apply overhead costs to get the total cost of the component.
The selling price of the component is estimated by adding profit to
the total cost obtained in step 10.
BASIC STEPS IN COST ESTIMATION
METHODS OF COSTING
1. Job costing or order costing
2. Batch costing
3. Process costing
4. Departmental costing
5. Operating cost method
6. Unit cost method
7. Multiple cost method
TYPES OF COST ESTIMATES
(a) Factor Method of Cost Estimation
(b) Material Cost Method of Estimation
(c) Function Method of Cost Estimation
Other types
(i) Product comparison
(ii) Data base calculations
Factor Method of Cost Estimation
Estimated cost of an item = Factor for total cost
estimate × Amount of major cost item
Example:
(i) Cost of construction per km of highway
(ii) Cost of fabricated component per kg of casting
(iii) Cost of house construction per Sq.m. of livable
space
Example Problem:
If a casting weighed 15 kg, and the factor of the cost of
casting per kg of casting is Rs. 75, what is the estimated
cost of the casting ?
Estimated cost of the casting = Rs. 75 per kg of casting
× wt. of the casting (15 kg) = Rs. 1125 per casting
Material Cost Method of Estimation
Material cost method predicts the total cost of the
product based on the ratio of the material cost of the
product to the material cost share of the total cost.
Estimated cost of an item
=
Material cost of the item being estimated
Material cost share of item being estimated (in %)
Examples of material cost share :
Product Material cost share (%)
Passenger car 65%
Diesel engine 50%
Clocks, watches 25%
Glass product 10%
Example Problem:
If the material cost of an automobile was Rs. 2.50
Lakhs, what would be the total cost of the automobile ?
Use the table above.
Estimated total cost of automobile = Rs. 2.50 Lakhs /
0.65 = Rs. 3.85 Lakhs
• This method is similar to the factor method, but more
variables are used.
• Function method uses a mathematical expression with
constants and parameters derived for specific process,
such as casting or machining or for specific classes of
parts based on material, size, weight or other cost
parameters.
Function Method of Estimation
According to this method :
Estimated cost of an item = G × (a + b) + (R × c) + (N × d)
where
G = Weight of the item, kg
a = Material cost per kg
b = Tolerance cost per, kg
R = Weight of material Removed, kg
c = Cost per kg of material removed
N = No. of dimensions of a product surface
d = Cost per dimension
Function Method of Estimation
Contd.,
(i) Product comparison :
The new product is compared with existing
products (of similar function, design etc.) and
adjustments/modifications are made for the differences.
(ii) Data base calculations :
The product cost estimate is determined from cost
data bases which a company is expected to maintain
over a period of time (Historical Cost Data Base).
Elements of Cost
• Material cost
(a) Direct material cost
(b) Indirect material cost
• Labour cost
(a) Direct labour cost
(b) Indirect labour cost
• Other expenses
(a) Direct expenses
(b) Indirect expenses
(i) Factory expenses
(ii) Administrative expenses
(iii) Selling and distribution expenses
Material cost
Direct material cost
(i) From the product drawing, make a list of all the
components required to make the final product.
(ii) Calculate the volume of each component from the
drawing dimensions after adding machining allowances,
wherever necessary.
(iii) The volume of component multiplied by the density
of material used gives the weight of the material per
component.
Direct material cost
(iv) Add process rejection and other allowances like
cutting allowance to get the gross weight per
component.
(v) Multiply the gross weight by the cost of material per
unit weight to get the cost of raw material per
component.
(vi) The cost of raw material for all the components is,
similarly, calculated and added up which gives the cost
of direct material for the product.
Material cost
Contd.,
Indirect material cost
• The indirect materials include oils, general tools,
grease, sand papers, coolants, cotton waste etc.
• The cost associated with indirect materials is called
indirect material cost.
Material cost
Labour cost
Direct labour cost
• Direct labourer is one who actually works and
processes the materials to convert it into the final
shape.
• The cost associated with direct labour is called direct
labour cost.
• The direct labour are the workers operating lathes,
milling machines or welders, or assemblers in
assembly shop.
Indirect labour cost
• Indirect labourer is one who is not directly employed
in the manufacturing of the product but his services
are used in some indirect manner.
• The cost associated with indirect labour is called
indirect labour cost.
• The indirect labour includes supervisors, inspectors,
foreman, storekeeper, gatekeeper, maintenance staff,
crane driver etc.
Labour cost
Direct expenses
• Direct expenses include all that expenditure which
can be directly allocated and charged to a particular
job.
• The direct expenses include cost of special jigs or
fixtures, patterns, toolings made for job, or cost of
research and development work done for that specific
job.
Other Expenses
Indirect expenses
• Except direct expenses, all other indirect expenditure
incurred by the manufacturer is called indirect
expenses
• The indirect expenses are also called overhead
expenses or on-cost
The indirect expenses are further classified as
(i) Factory expenses
(ii) Administrative expenses
(iii) Selling and distribution expenses
Other Expenses
Indirect expenses - Factory expenses
• Factory expenses comprise of the indirect expenses
incurred from the receipt of the order to the
completion of production.
• Includes rent of factory building, licence fee,
electricity and telephone bills of factory, insurance
charges etc.
Other Expenses
Indirect expenses - Administrative expenses
• Administrative expenses or office expenses include
the expenditure incurred on control and
administration of the factory
• It includes the salaries of office and administrative
staff, rent of office building, postage and telephone
charges, water and electricity charges for office,
Director’s fee, legal and audit charges etc.
Other Expenses
Indirect expenses - Selling and distribution expenses
• his is the expenditure incurred on Sales Department
for selling the product
• It includes the wages, salaries, commission and
travelling allowances of salesmen and officers in
Sales Department, cost of advertisement, packing,
delivery and distribution expenses, rent of
warehouses etc.
Other Expenses
Methods of Estimating
• Conference method
• Comparison method
• Detailed analysis method
Conference method
 A co-ordinator from either accounting or estimating
collect costs and applies overhead factors to develop a
total manufacturing cost for the product
 If vague or only verbal information is available, then
the total product material, labour and tooling will be
estimated as one lump sum for each
 The degree of accuracy of this method depends upon
the availability of specificaitions, samples and drawings
Comparison method
 In this method of estimating the costs of similar parts
are applied to the product and are adjusted to suit
variations in the workpiece, material and labour costs.
 It is based on the accumulation of past experience data
Detailed analysis method
This method involves
I. Calculation of raw material usage including scrap
allowance and salvage material
II. Processing each individual component (writing the
operation sheet)
III. Determining the production time (direct labour) for each
operation
IV. The equipment required (new, network, or on hand)
V. Tools, gauges, and special fixtures or dies,
VI. Inspection and testing equipment
VII. Packaging and shipping requirements
COST ESTIMATING PROCEDURE
Step 1: Study the cost estimation request thoroughly
and understand it completely
Step 2: Analyse the product and decide the
requirements and specifications of the product
Step 3: Prepare the list of all the parts of the product
and their bill of materials
Step 4: Take make or buy decisions and prepare
separate lists of parts to be manufactured within the
plant and parts to be purchased outside the plant
Step 5: Estimate the materials cost for the parts to be
manufactured in the plant
Material cost =
Weight of the
material
×
Material cost per
unit weight
Step 6 : Determine the cost of parts to be purchased from
outside
Step 7: Make a manufacturing process plan for the parts
to be manufactured in the plant
COST ESTIMATING PROCEDURE
Contd.,
Step 8: Estimate the machining time for each operations listed in
the manufacturing process plan
Step 9: Determine the direct labour cost
Direct labour cost =
Total operation
time
×
Labour
wage rate
Step 10: Determine the prime cost by adding direct expenses,
direct material cost, and direct labour cost
∴ Prime cost =
Direct
labour
cost
+
Direct
material cost
+
Direct
expenses
COST ESTIMATING PROCEDURE
Contd.,
Step 11: Estimate the factory overheads, which include all
indirect expenditure incurred during production such as
indirect material cost, indirect labour cost, depreciation and
expenditure on maintenance of the plant, machinery, power,
etc.
Step 12: Estimate the administrative expenses
COST ESTIMATING PROCEDURE
Contd.,
Step 13: Estimate the selling and distribution expenses
which include packing and delivery charges, advertisement
charges, etc.
Step 14: Now calculate the total cost of the product
Total Cost
=
Prime
Cost
+
Factory
overheads
+
Administrative
expenses
+
Selling and
distribution expenses
COST ESTIMATING PROCEDURE
Contd.,
Step 15: Decide the profit and add the profit to the total cost
to fix the selling price of the part
Selling Price = Total cost + Profit
Step 16: Finally estimate the time of delivery in
consultation with the production and sales department
COST ESTIMATING PROCEDURE
Contd.,
ESTIMATE FORM
After estimating all the
elements of cost
estimate, these estimated
datas are entered into an
estimate form
COST OF PRODUCT
(LADDER OF COSTS)
1. Prime cost = Direct material cost + Direct labour cost
+ Direct expenses
2. Factory cost = Prime cost + Factory expenses
3. Production cost = Factory cost + Administrative
expenses
4. Total or Ultimate cost = Production cost + Selling and
distribution expenses.
5. Selling price = Ultimate cost + Profit
BLOCK DIAGRAM
ESTIMATION OF LABOUR COST
i) Set up time
ii) Operation time
a) Handling time
b) machining time
iii) Tear down time
iv) Miscellaneous allowances
a) Personal allowances
b) fatigue allowances
c) contingency allowances
d) process allowances
e) interference allowances
f) Special allowances
ALLOWANCES IN COST ESTIMATION &
CALCULATION OF STANDARD TIME
Allowances :
Allowance is an amount of time added to
the normal time to provide for personal delays,
unavoidable delays and fatigue of the operator.
TYPES OF ALLOWANCES
1. Relaxation allowances
a) Personal need allowances
b) Fatigue allowances
2. Contingency allowances
3. Process allowances
4. Interference allowances
5. Special allowances
CALCULATION OF STANDARD TIME
• Standard time is the time allowed to an
operator to carry out the specified task under
specified conditions and defined level of
performance.
Standard time= Normal time + Allowances
Normal (or basic) time= observed time x rating
factor
Rating factor= (observed time/ normal time) x 100
Example: Calculate prime cost, factory cost, production cost, total cost and
selling price per item from the data given below for the year 2003-04.
Example : From the following data for a sewing machine manufacturer,
prepare a statement showing prime cost, Works/factory cost, production cost,
total cost and profit.
Example : From the following data for a sewing machine manufacturer,
prepare a statement showing prime cost, Works/factory cost, production cost,
total cost and profit.
ESTIMATION OF MATERIALS COST
Procedure
• Study the given drawing carefully. Then break up the
product into simple geometrical shapes such as cubes,
prisms, cylinders, etc.,
• Calculate the volume of each parts using formulae
• Add volumes to get total volume
• Calculate the weight of material by Volume × Density
• Material cost =
Weight of the
material
×
Material cost per
unit weight
Example
METHODS OF ALLOCATION OF
OVERHEAD EXPENSES
DEPRECIATION
• Depreciation is the process of allocating the
acquisition cost of the tangible asset less
salvage value, if any, in a systematic and a
rational manner over the estimated life of the
asset.
CAUSES OF DEPRECIATION
METHODS OF DEPRECIATION
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx
PPCE Unit-3.pptx

More Related Content

Similar to PPCE Unit-3.pptx

UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
PChakravarthyMECH
 
Process Planning & Cost Estimation
Process Planning & Cost EstimationProcess Planning & Cost Estimation
Process Planning & Cost Estimation
Prabhu Bose
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & Costing
Ganesh Murugan
 
importance of estimation power point presentation
importance of estimation power point presentationimportance of estimation power point presentation
importance of estimation power point presentation
niyatishah939575
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
costestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptxcostestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptx
RedhaElhuni
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
TAMILMECHKIT
 
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docxMFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
ARIV4
 
SAP Product costing Calculation With Components - Skillstek
SAP Product costing Calculation With Components  - SkillstekSAP Product costing Calculation With Components  - Skillstek
SAP Product costing Calculation With Components - Skillstek
Skillstek
 
ppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptxppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptx
mani617576
 
job oder cost system part one.pptx
job oder cost system part one.pptxjob oder cost system part one.pptx
job oder cost system part one.pptx
MohamedAbdi347025
 
Cost accounting By CA Ankush Gupta
Cost accounting By CA Ankush GuptaCost accounting By CA Ankush Gupta
Cost accounting By CA Ankush Gupta
AnkushGupta205
 
UNIT IV COST ACCOUNTING
UNIT IV COST ACCOUNTINGUNIT IV COST ACCOUNTING
UNIT IV COST ACCOUNTING
Ramesh Kumar Natesan
 
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmug
rcaldwell002
 
Introduction to Cost Accounting for BBA, B.com, BBA aviation management
Introduction to Cost Accounting for BBA, B.com, BBA aviation managementIntroduction to Cost Accounting for BBA, B.com, BBA aviation management
Introduction to Cost Accounting for BBA, B.com, BBA aviation management
parimalas3
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process Planning
PraveenManickam2
 
Process Costing.pptx
Process Costing.pptxProcess Costing.pptx
Process Costing.pptx
MarkhorCrafts
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
MD RUKHASAR ALAM
 

Similar to PPCE Unit-3.pptx (20)

UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 
Process Planning & Cost Estimation
Process Planning & Cost EstimationProcess Planning & Cost Estimation
Process Planning & Cost Estimation
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & Costing
 
importance of estimation power point presentation
importance of estimation power point presentationimportance of estimation power point presentation
importance of estimation power point presentation
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
costestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptxcostestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptx
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docxMFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
 
SAP Product costing Calculation With Components - Skillstek
SAP Product costing Calculation With Components  - SkillstekSAP Product costing Calculation With Components  - Skillstek
SAP Product costing Calculation With Components - Skillstek
 
ppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptxppceunit3-211117103659 (1)-2-81 (3).pptx
ppceunit3-211117103659 (1)-2-81 (3).pptx
 
job oder cost system part one.pptx
job oder cost system part one.pptxjob oder cost system part one.pptx
job oder cost system part one.pptx
 
Cost accounting By CA Ankush Gupta
Cost accounting By CA Ankush GuptaCost accounting By CA Ankush Gupta
Cost accounting By CA Ankush Gupta
 
1234
12341234
1234
 
1234
12341234
1234
 
UNIT IV COST ACCOUNTING
UNIT IV COST ACCOUNTINGUNIT IV COST ACCOUNTING
UNIT IV COST ACCOUNTING
 
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmug
 
Introduction to Cost Accounting for BBA, B.com, BBA aviation management
Introduction to Cost Accounting for BBA, B.com, BBA aviation managementIntroduction to Cost Accounting for BBA, B.com, BBA aviation management
Introduction to Cost Accounting for BBA, B.com, BBA aviation management
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process Planning
 
Process Costing.pptx
Process Costing.pptxProcess Costing.pptx
Process Costing.pptx
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
 

More from DJAGADEESH1

INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
DJAGADEESH1
 
PROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESPROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIES
DJAGADEESH1
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATION
DJAGADEESH1
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATION
DJAGADEESH1
 
POM UNIT-I.pdf
POM UNIT-I.pdfPOM UNIT-I.pdf
POM UNIT-I.pdf
DJAGADEESH1
 
POM UNIT-3.pdf
POM UNIT-3.pdfPOM UNIT-3.pdf
POM UNIT-3.pdf
DJAGADEESH1
 
POM UNIT-4.pdf
POM UNIT-4.pdfPOM UNIT-4.pdf
POM UNIT-4.pdf
DJAGADEESH1
 
Unit 5 Controlling.ppt
Unit 5 Controlling.pptUnit 5 Controlling.ppt
Unit 5 Controlling.ppt
DJAGADEESH1
 
POM UNIT-2.pdf
POM UNIT-2.pdfPOM UNIT-2.pdf
POM UNIT-2.pdf
DJAGADEESH1
 
PPCE Unit-5.pptx
PPCE Unit-5.pptxPPCE Unit-5.pptx
PPCE Unit-5.pptx
DJAGADEESH1
 
PPCE Unit -1.pptx
PPCE Unit -1.pptxPPCE Unit -1.pptx
PPCE Unit -1.pptx
DJAGADEESH1
 
PPCE Unit-4.pptx
PPCE Unit-4.pptxPPCE Unit-4.pptx
PPCE Unit-4.pptx
DJAGADEESH1
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptx
DJAGADEESH1
 
Unit V
Unit VUnit V
Unit V
DJAGADEESH1
 
Unit IV
Unit IVUnit IV
Unit IV
DJAGADEESH1
 
Unit III
Unit IIIUnit III
Unit III
DJAGADEESH1
 
Unit II
Unit IIUnit II
Unit II
DJAGADEESH1
 
Unit 1
Unit 1Unit 1
Unit 1
DJAGADEESH1
 
Heat treatment
Heat treatmentHeat treatment
Heat treatment
DJAGADEESH1
 

More from DJAGADEESH1 (19)

INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
PROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESPROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIES
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATION
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATION
 
POM UNIT-I.pdf
POM UNIT-I.pdfPOM UNIT-I.pdf
POM UNIT-I.pdf
 
POM UNIT-3.pdf
POM UNIT-3.pdfPOM UNIT-3.pdf
POM UNIT-3.pdf
 
POM UNIT-4.pdf
POM UNIT-4.pdfPOM UNIT-4.pdf
POM UNIT-4.pdf
 
Unit 5 Controlling.ppt
Unit 5 Controlling.pptUnit 5 Controlling.ppt
Unit 5 Controlling.ppt
 
POM UNIT-2.pdf
POM UNIT-2.pdfPOM UNIT-2.pdf
POM UNIT-2.pdf
 
PPCE Unit-5.pptx
PPCE Unit-5.pptxPPCE Unit-5.pptx
PPCE Unit-5.pptx
 
PPCE Unit -1.pptx
PPCE Unit -1.pptxPPCE Unit -1.pptx
PPCE Unit -1.pptx
 
PPCE Unit-4.pptx
PPCE Unit-4.pptxPPCE Unit-4.pptx
PPCE Unit-4.pptx
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptx
 
Unit V
Unit VUnit V
Unit V
 
Unit IV
Unit IVUnit IV
Unit IV
 
Unit III
Unit IIIUnit III
Unit III
 
Unit II
Unit IIUnit II
Unit II
 
Unit 1
Unit 1Unit 1
Unit 1
 
Heat treatment
Heat treatmentHeat treatment
Heat treatment
 

Recently uploaded

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 

Recently uploaded (20)

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 

PPCE Unit-3.pptx

  • 1. UNIT III INTRODUCTION TO COST ESTIMATION • Importance of costing and estimation • Methods of costing-elements of cost estimation • Types of estimates • Estimating procedure • Estimation labor cost, material cost • Allocation of over head charges • Calculation of depreciation cost
  • 2. What is mean by cost estimation? • Estimation of the expected cost of producing a job • Executing a manufacturing order before the actual production is taken up • Predicting what new products will cost before they are made
  • 3. Definition Costing or cost accounting means classifying, recording and allocating the appropriate expenditure for determining the cost of production and achieved by keeping a continuous record of all the costs involved in manufacturing
  • 4. REASONS FOR DOING ESTIMATES • Should the product be produced? • When a company designs a new product • To assist management in making an intelligent decision about producing the product.
  • 5. General procedure • A cost estimate must be developed for jigs, fixtures, tools, dies and gauges • Also, the cost of any capital equipment must be entered into the estimate • These figures are usually supplied through quotation by vendors • An estimate of this nature will include a vast amount of details, because if management approves the project, the estimate now becomes the budget
  • 6. OBJECTIVES (OR) PURPOSE OF ESTIMATING • To establish the selling price of a product • To ascertain whether a proposed product can be manufactured and marketed profitably • To determine how much must be invested in equipment • To find whether parts or assemblies can be more cheaply fabricated or purchased from outside (make or buy decision) • To determine the most economical process, tooling or material for making a product
  • 7. FUNCTIONS OF ESTIMATING  To calculate the cost of new material needed to manufacture a product  To find the cost of parts to be purchased from outside vendors  To find the cost of equipment, machinery, tools, jigs and fixtures etc. required to be purchased to make the product  To calculate the direct and indirect labour cost associated with the manufacture of the product, based upon work study.  To calculate various overhead charges associated with the product.
  • 8.  To decide about the profit to be charged, taking into consideration other manufacturers of same product in the market  To calculate the selling price of the product  To maintain records of previous estimating activities of the company for future references  To decide the most economical method of making the product  To submit cost estimates with the competent authority for further action FUNCTIONS OF ESTIMATING Contd.,
  • 9. COMPONENTS OF A COST ESTIMATE OR JOB ESTIMATE 1. Cost of design 2. Cost of drafting 3. Cost of research and development 4. Cost of raw materials 5. Cost of labour 6. Cost of inspection 7. Cost of tools, jigs and fixtures 8. Overhead cost
  • 10. 1. Cost of Design • The cost of design of a component or product is estimated by ascertaining the expected time for the design of that component • The estimate design time multiplied by the salary of designer per unit time gives the estimated cost of design • If the design of the component is done by some outside agency, the total amount paid to outside agency gives the cost of design.
  • 11. 2. Cost of Drafting • Once the design of the component is complete, its drawings have to be prepared by draftsman • The expected time to be spent in drawing or drafting is estimated and is then multiplied by the standard drafting rate or by the salary of the draftsman per unit time to get estimated cost of drafting
  • 12. 3. Cost of Research and Development Work • Before taking up the manufacturing of actual components/parts considerable time and money has to be spent on research and development • The research may be theoretical, experimental or developmental research. • The cost of R and D can be estimated by considering various items of expenditure incurred during R and D work
  • 13. 4. Cost of Raw Material • A list of all the materials used in the manufacture of the product is made which includes the direct as well as indirect materials • The quantity (weight or volume) of all the material expected to be used in the manufacture of the product is estimated. • The allowance for material wastage, spoilage and scarp are also added for each component/part.
  • 14. • Cost of each material is estimated by multiplying the estimated quantity of each material with its estimated future price • The estimate of future price of a material is made keeping in view of present prices and general trends and variations • Estimated cost of all the materials is added to get the overall estimated material cost 4. Cost of Raw Material Contd.,
  • 15. 5. Cost of Labour • The cost of labour involved in the manufacture of a product is estimated by estimating the labour time needed to manufacture the product and multiplying it by cost of labour per hour. • In order to estimate the labour time expected to be spent on a job, one must have thorough knowledge of the various operations to be performed, machines to be used, sequence of operations, tools to be used and labour rates
  • 16. 6. Cost of Inspection • A product being manufactured is inspected at various stages during its manufacture • It may be inspection of raw material or in- process inspection or inspection of finished goods
  • 17. 7. Cost and Maintenance Charges of Tools, Jigs and Fixtures • The cost of tools, jigs, fixtures etc., is estimated considering their present prices, market trend and the number of times a particular tool can be used during its life-time. • The estimated cost divided by the number of jobs it can make, gives the tool cost per unit produced
  • 18. 8. Overhead Costs • Overhead or indirect costs are those which are not incurred specifically for any one order or product and these can not be charged directly to a specific order or product • The overhead costs may be estimated by referring to the records of overhead costs in similar items produced in past
  • 19. BASIC STEPS IN COST ESTIMATION 1. Make thorough study of cost estimation request to understand it fully. 2. Make an analysis of the product and prepare a bill of materials. 3. Make separate lists of parts to be purchased from the market and parts to be manufactured in plant. 4. Determine the cost of parts to be purchased from outside. 5. Estimate the material cost for the parts/components to be manufactured in plant.
  • 20. 6. Make manufacturing process plan for the parts to be manufactured in plant. 7. Estimate the machining time for each operation listed in the manufacturing process plan. 8. Multiply each operation time by the labour wage rate and add them up to find direct labour cost 9. Add the estimate of step 4, 5, and 8 to get prime cost of component. 10. Apply overhead costs to get the total cost of the component. The selling price of the component is estimated by adding profit to the total cost obtained in step 10. BASIC STEPS IN COST ESTIMATION
  • 21. METHODS OF COSTING 1. Job costing or order costing 2. Batch costing 3. Process costing 4. Departmental costing 5. Operating cost method 6. Unit cost method 7. Multiple cost method
  • 22. TYPES OF COST ESTIMATES (a) Factor Method of Cost Estimation (b) Material Cost Method of Estimation (c) Function Method of Cost Estimation Other types (i) Product comparison (ii) Data base calculations
  • 23. Factor Method of Cost Estimation Estimated cost of an item = Factor for total cost estimate × Amount of major cost item Example: (i) Cost of construction per km of highway (ii) Cost of fabricated component per kg of casting (iii) Cost of house construction per Sq.m. of livable space
  • 24. Example Problem: If a casting weighed 15 kg, and the factor of the cost of casting per kg of casting is Rs. 75, what is the estimated cost of the casting ? Estimated cost of the casting = Rs. 75 per kg of casting × wt. of the casting (15 kg) = Rs. 1125 per casting
  • 25. Material Cost Method of Estimation Material cost method predicts the total cost of the product based on the ratio of the material cost of the product to the material cost share of the total cost. Estimated cost of an item = Material cost of the item being estimated Material cost share of item being estimated (in %)
  • 26. Examples of material cost share : Product Material cost share (%) Passenger car 65% Diesel engine 50% Clocks, watches 25% Glass product 10% Example Problem: If the material cost of an automobile was Rs. 2.50 Lakhs, what would be the total cost of the automobile ? Use the table above. Estimated total cost of automobile = Rs. 2.50 Lakhs / 0.65 = Rs. 3.85 Lakhs
  • 27. • This method is similar to the factor method, but more variables are used. • Function method uses a mathematical expression with constants and parameters derived for specific process, such as casting or machining or for specific classes of parts based on material, size, weight or other cost parameters. Function Method of Estimation
  • 28. According to this method : Estimated cost of an item = G × (a + b) + (R × c) + (N × d) where G = Weight of the item, kg a = Material cost per kg b = Tolerance cost per, kg R = Weight of material Removed, kg c = Cost per kg of material removed N = No. of dimensions of a product surface d = Cost per dimension Function Method of Estimation Contd.,
  • 29. (i) Product comparison : The new product is compared with existing products (of similar function, design etc.) and adjustments/modifications are made for the differences. (ii) Data base calculations : The product cost estimate is determined from cost data bases which a company is expected to maintain over a period of time (Historical Cost Data Base).
  • 30. Elements of Cost • Material cost (a) Direct material cost (b) Indirect material cost • Labour cost (a) Direct labour cost (b) Indirect labour cost • Other expenses (a) Direct expenses (b) Indirect expenses (i) Factory expenses (ii) Administrative expenses (iii) Selling and distribution expenses
  • 31. Material cost Direct material cost (i) From the product drawing, make a list of all the components required to make the final product. (ii) Calculate the volume of each component from the drawing dimensions after adding machining allowances, wherever necessary. (iii) The volume of component multiplied by the density of material used gives the weight of the material per component.
  • 32. Direct material cost (iv) Add process rejection and other allowances like cutting allowance to get the gross weight per component. (v) Multiply the gross weight by the cost of material per unit weight to get the cost of raw material per component. (vi) The cost of raw material for all the components is, similarly, calculated and added up which gives the cost of direct material for the product. Material cost Contd.,
  • 33. Indirect material cost • The indirect materials include oils, general tools, grease, sand papers, coolants, cotton waste etc. • The cost associated with indirect materials is called indirect material cost. Material cost
  • 34. Labour cost Direct labour cost • Direct labourer is one who actually works and processes the materials to convert it into the final shape. • The cost associated with direct labour is called direct labour cost. • The direct labour are the workers operating lathes, milling machines or welders, or assemblers in assembly shop.
  • 35. Indirect labour cost • Indirect labourer is one who is not directly employed in the manufacturing of the product but his services are used in some indirect manner. • The cost associated with indirect labour is called indirect labour cost. • The indirect labour includes supervisors, inspectors, foreman, storekeeper, gatekeeper, maintenance staff, crane driver etc. Labour cost
  • 36. Direct expenses • Direct expenses include all that expenditure which can be directly allocated and charged to a particular job. • The direct expenses include cost of special jigs or fixtures, patterns, toolings made for job, or cost of research and development work done for that specific job. Other Expenses
  • 37. Indirect expenses • Except direct expenses, all other indirect expenditure incurred by the manufacturer is called indirect expenses • The indirect expenses are also called overhead expenses or on-cost The indirect expenses are further classified as (i) Factory expenses (ii) Administrative expenses (iii) Selling and distribution expenses Other Expenses
  • 38. Indirect expenses - Factory expenses • Factory expenses comprise of the indirect expenses incurred from the receipt of the order to the completion of production. • Includes rent of factory building, licence fee, electricity and telephone bills of factory, insurance charges etc. Other Expenses
  • 39. Indirect expenses - Administrative expenses • Administrative expenses or office expenses include the expenditure incurred on control and administration of the factory • It includes the salaries of office and administrative staff, rent of office building, postage and telephone charges, water and electricity charges for office, Director’s fee, legal and audit charges etc. Other Expenses
  • 40. Indirect expenses - Selling and distribution expenses • his is the expenditure incurred on Sales Department for selling the product • It includes the wages, salaries, commission and travelling allowances of salesmen and officers in Sales Department, cost of advertisement, packing, delivery and distribution expenses, rent of warehouses etc. Other Expenses
  • 41. Methods of Estimating • Conference method • Comparison method • Detailed analysis method
  • 42. Conference method  A co-ordinator from either accounting or estimating collect costs and applies overhead factors to develop a total manufacturing cost for the product  If vague or only verbal information is available, then the total product material, labour and tooling will be estimated as one lump sum for each  The degree of accuracy of this method depends upon the availability of specificaitions, samples and drawings
  • 43. Comparison method  In this method of estimating the costs of similar parts are applied to the product and are adjusted to suit variations in the workpiece, material and labour costs.  It is based on the accumulation of past experience data
  • 44. Detailed analysis method This method involves I. Calculation of raw material usage including scrap allowance and salvage material II. Processing each individual component (writing the operation sheet) III. Determining the production time (direct labour) for each operation IV. The equipment required (new, network, or on hand) V. Tools, gauges, and special fixtures or dies, VI. Inspection and testing equipment VII. Packaging and shipping requirements
  • 45. COST ESTIMATING PROCEDURE Step 1: Study the cost estimation request thoroughly and understand it completely Step 2: Analyse the product and decide the requirements and specifications of the product Step 3: Prepare the list of all the parts of the product and their bill of materials Step 4: Take make or buy decisions and prepare separate lists of parts to be manufactured within the plant and parts to be purchased outside the plant
  • 46. Step 5: Estimate the materials cost for the parts to be manufactured in the plant Material cost = Weight of the material × Material cost per unit weight Step 6 : Determine the cost of parts to be purchased from outside Step 7: Make a manufacturing process plan for the parts to be manufactured in the plant COST ESTIMATING PROCEDURE Contd.,
  • 47. Step 8: Estimate the machining time for each operations listed in the manufacturing process plan Step 9: Determine the direct labour cost Direct labour cost = Total operation time × Labour wage rate Step 10: Determine the prime cost by adding direct expenses, direct material cost, and direct labour cost ∴ Prime cost = Direct labour cost + Direct material cost + Direct expenses COST ESTIMATING PROCEDURE Contd.,
  • 48. Step 11: Estimate the factory overheads, which include all indirect expenditure incurred during production such as indirect material cost, indirect labour cost, depreciation and expenditure on maintenance of the plant, machinery, power, etc. Step 12: Estimate the administrative expenses COST ESTIMATING PROCEDURE Contd.,
  • 49. Step 13: Estimate the selling and distribution expenses which include packing and delivery charges, advertisement charges, etc. Step 14: Now calculate the total cost of the product Total Cost = Prime Cost + Factory overheads + Administrative expenses + Selling and distribution expenses COST ESTIMATING PROCEDURE Contd.,
  • 50. Step 15: Decide the profit and add the profit to the total cost to fix the selling price of the part Selling Price = Total cost + Profit Step 16: Finally estimate the time of delivery in consultation with the production and sales department COST ESTIMATING PROCEDURE Contd.,
  • 51. ESTIMATE FORM After estimating all the elements of cost estimate, these estimated datas are entered into an estimate form
  • 52. COST OF PRODUCT (LADDER OF COSTS) 1. Prime cost = Direct material cost + Direct labour cost + Direct expenses 2. Factory cost = Prime cost + Factory expenses 3. Production cost = Factory cost + Administrative expenses 4. Total or Ultimate cost = Production cost + Selling and distribution expenses. 5. Selling price = Ultimate cost + Profit
  • 54.
  • 55. ESTIMATION OF LABOUR COST i) Set up time ii) Operation time a) Handling time b) machining time iii) Tear down time iv) Miscellaneous allowances a) Personal allowances b) fatigue allowances c) contingency allowances d) process allowances e) interference allowances f) Special allowances
  • 56. ALLOWANCES IN COST ESTIMATION & CALCULATION OF STANDARD TIME Allowances : Allowance is an amount of time added to the normal time to provide for personal delays, unavoidable delays and fatigue of the operator.
  • 57. TYPES OF ALLOWANCES 1. Relaxation allowances a) Personal need allowances b) Fatigue allowances 2. Contingency allowances 3. Process allowances 4. Interference allowances 5. Special allowances
  • 58. CALCULATION OF STANDARD TIME • Standard time is the time allowed to an operator to carry out the specified task under specified conditions and defined level of performance. Standard time= Normal time + Allowances Normal (or basic) time= observed time x rating factor Rating factor= (observed time/ normal time) x 100
  • 59. Example: Calculate prime cost, factory cost, production cost, total cost and selling price per item from the data given below for the year 2003-04.
  • 60.
  • 61.
  • 62. Example : From the following data for a sewing machine manufacturer, prepare a statement showing prime cost, Works/factory cost, production cost, total cost and profit.
  • 63.
  • 64.
  • 65. Example : From the following data for a sewing machine manufacturer, prepare a statement showing prime cost, Works/factory cost, production cost, total cost and profit.
  • 66.
  • 67.
  • 68.
  • 69.
  • 70. ESTIMATION OF MATERIALS COST Procedure • Study the given drawing carefully. Then break up the product into simple geometrical shapes such as cubes, prisms, cylinders, etc., • Calculate the volume of each parts using formulae • Add volumes to get total volume • Calculate the weight of material by Volume × Density • Material cost = Weight of the material × Material cost per unit weight
  • 72.
  • 73.
  • 74. METHODS OF ALLOCATION OF OVERHEAD EXPENSES
  • 75. DEPRECIATION • Depreciation is the process of allocating the acquisition cost of the tangible asset less salvage value, if any, in a systematic and a rational manner over the estimated life of the asset.