This document discusses several options for optimizing the efficiency of combined cycle power plants, including:
1. Improving compressor cleanliness by using HEPA filters, which can increase power output by 6% and extend time between cleanings.
2. Making operational adjustments such as optimizing low load setpoints and reducing heat loss.
3. Installing aftermarket systems like ECOMAX automated combustion tuning to improve heat rate by 0.2-0.25% and boost output up to 11 MW.
4. A technology called TurboPHASE that uses a reciprocating engine to add compressed air to combustion turbines, allowing 10-20% faster response time and up to 7% improved heat rate.
Water Efficiency in Thermal power PlantAtanu Maity
Ministry of Environment, Forest and Climate Change (MoEF)
in its recent notification dated December 07, 2015 on
Environment (Protection) Amendment Rules, 2015 have
notified the following:
I. All plants with Once Through Cooling (OTC) shall install Cooling Tower (CT) and achieve specific water consumption upto maximum of 3.5m3/MWh within a period of two years from the date of publication of this notification.
II. All existing CT-based plants shall have to reduce specific water consumption upto maximum of 3.5m3/MWh within a period of two years from the date of publication of this notification.
III. New plants to be installed after 1st January, 2017 shall have to meet specific water consumption upto maximum of 2.5 m3/MWh and achieve zero waste water discharged.
In light of the above a presentation on water consumption in cooling towers / Air Cooled Condensers and other comparisons.
To Improve Thermal Efficiency of 27mw Coal Fired Power PlantIJMER
Booming demand for electricity, especially in the developing countries, has raised power generation technologies in the headlines. At the same time the discussion about causes of global warming has focused on emissions originating from power generation and on CO2 reduction technologies such as:
(1) Alternative primary energy sources,
(2) Capture and storage of CO2,
(3) Increasing the efficiency of converting primary energy content into electricity.
In the dissertation, the thermal efficiency of the power plant is improved when Control of furnace draft (nearer to balanced draft). Oxygen level decreases percentage of flue gases. Above this level heat losses are increases & below this carbon mono-oxide is formed. Steam power plant is using fuel to generate electrical power. The used of the fuel must be efficient so the boiler can generate for the maximum electrical power. By the time the steam cycle in the boiler, it also had heat losses through some parts and it effect on the efficiency of the boiler. This project will analyze about the parts of losses and boiler efficiency. to find excess air which effect heat losses in boiler. By using the 27 MW coal fired thermal power plant of Birla Corporation Limited, Satna (M.P.) the data is collect by using types of Combustion & heat flow in boiler. Result of the analysis show that the efficiency of boiler depends on mass of coal burnt & type of combustion .This study is fulfilling the objective of analysis to find the boiler efficiency and heat losses in boiler for 27 MW thermal power plant of Birla Corporation Limited, Satna (M.P.)
Water Efficiency in Thermal power PlantAtanu Maity
Ministry of Environment, Forest and Climate Change (MoEF)
in its recent notification dated December 07, 2015 on
Environment (Protection) Amendment Rules, 2015 have
notified the following:
I. All plants with Once Through Cooling (OTC) shall install Cooling Tower (CT) and achieve specific water consumption upto maximum of 3.5m3/MWh within a period of two years from the date of publication of this notification.
II. All existing CT-based plants shall have to reduce specific water consumption upto maximum of 3.5m3/MWh within a period of two years from the date of publication of this notification.
III. New plants to be installed after 1st January, 2017 shall have to meet specific water consumption upto maximum of 2.5 m3/MWh and achieve zero waste water discharged.
In light of the above a presentation on water consumption in cooling towers / Air Cooled Condensers and other comparisons.
To Improve Thermal Efficiency of 27mw Coal Fired Power PlantIJMER
Booming demand for electricity, especially in the developing countries, has raised power generation technologies in the headlines. At the same time the discussion about causes of global warming has focused on emissions originating from power generation and on CO2 reduction technologies such as:
(1) Alternative primary energy sources,
(2) Capture and storage of CO2,
(3) Increasing the efficiency of converting primary energy content into electricity.
In the dissertation, the thermal efficiency of the power plant is improved when Control of furnace draft (nearer to balanced draft). Oxygen level decreases percentage of flue gases. Above this level heat losses are increases & below this carbon mono-oxide is formed. Steam power plant is using fuel to generate electrical power. The used of the fuel must be efficient so the boiler can generate for the maximum electrical power. By the time the steam cycle in the boiler, it also had heat losses through some parts and it effect on the efficiency of the boiler. This project will analyze about the parts of losses and boiler efficiency. to find excess air which effect heat losses in boiler. By using the 27 MW coal fired thermal power plant of Birla Corporation Limited, Satna (M.P.) the data is collect by using types of Combustion & heat flow in boiler. Result of the analysis show that the efficiency of boiler depends on mass of coal burnt & type of combustion .This study is fulfilling the objective of analysis to find the boiler efficiency and heat losses in boiler for 27 MW thermal power plant of Birla Corporation Limited, Satna (M.P.)
In electric power generation a combined cycle is an assembly of heat engines that work in tandem from the same source of heat, converting it into mechanical energy, which in turn usually drives electrical generators. The principle is that after completing its cycle (in the first engine), the temperature of the working fluid engine is still high enough that a second subsequent heat engine may extract energy from the waste heat that the first engine produced. By combining these multiple streams of work upon a single mechanical shaft turning an electric generator, the overall net efficiency of the system may be increased by 50–60%. That is, from an overall efficiency of say 34% (in a single cycle) to possibly an overall efficiency of 51% (in a mechanical combination of two cycles) in net Carnot thermodynamic efficiency. This can be done because heat engines are only able to use a portion of the energy their fuel generates (usually less than 50%). In an ordinary (non combined cycle) heat engine the remaining heat (e.g., hot exhaust fumes) from combustion is generally wasted.
Combining two or more thermodynamic cycles results in improved overall efficiency, reducing fuel costs. In stationary power plants, a widely used combination is a gas turbine (operating by the Brayton cycle) burning natural gas or synthesis gas from coal, whose hot exhaust powers a steam power plant (operating by the Rankine cycle). This is called a Combined Cycle Gas Turbine (CCGT) plant, and can achieve a best-of-class real (HHV - see below) thermal efficiency of around 54% in base-load operation, in contrast to a single cycle steam power plant which is limited to efficiencies of around 35–42%. Many new gas power plants in North America and Europe are of the Combined Cycle Gas Turbine type. Such an arrangement is also used for marine propulsion, and is called a combined gas and steam (COGAS) plant. Multiple stage turbine or steam cycles are also common.
Power plant engineering unit 3 notes by Varun Pratap SinghVarun Pratap Singh
Download Link: https://sites.google.com/view/varunpratapsingh/teaching-engagements (Copy URL)
Unit-3
Diesel power plant
General layout, performance of diesel engine, fuel system, lubrication system, air intake and admission system, supercharging system, exhaust system, diesel plant operation and efficiency, heat balance.
Gas turbine power plant
Elements of gas turbine power plants, Gas turbine fuels, cogeneration, auxiliary systems such as fuel, controls and lubrication, operation and maintenance, Combined cycle power plants.
Power plant engineering unit 2 notes by Varun Pratap SinghVarun Pratap Singh
Download Link: https://sites.google.com/view/varunpratapsingh/teaching-engagements (Copy URL)
SYLLABUS
Unit-II
Steam power plant
Power plant boilers including critical and super critical boilers. Fluidized bed boilers, boilers
mountings and accessories.
General layout of steam power plant. Different systems such as fuel handling system,
pulverizes and coal burners, combustion system, draft, ash handling system, feed water
treatment and condenser and cooling system, turbine auxiliary systems such as governing, feed
heating, reheating, flange heating and gland leakage.
Operation and maintenance of steam power plant, heat balance and efficiency.
Detailed Internship Report about RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Includes information about Thermodynamic Cycles, Combined Cycle, HRSG (Heat Recovery Steam Generator), and various components of a Combined Cycle Power Plant.
In electric power generation a combined cycle is an assembly of heat engines that work in tandem from the same source of heat, converting it into mechanical energy, which in turn usually drives electrical generators. The principle is that after completing its cycle (in the first engine), the temperature of the working fluid engine is still high enough that a second subsequent heat engine may extract energy from the waste heat that the first engine produced. By combining these multiple streams of work upon a single mechanical shaft turning an electric generator, the overall net efficiency of the system may be increased by 50–60%. That is, from an overall efficiency of say 34% (in a single cycle) to possibly an overall efficiency of 51% (in a mechanical combination of two cycles) in net Carnot thermodynamic efficiency. This can be done because heat engines are only able to use a portion of the energy their fuel generates (usually less than 50%). In an ordinary (non combined cycle) heat engine the remaining heat (e.g., hot exhaust fumes) from combustion is generally wasted.
Combining two or more thermodynamic cycles results in improved overall efficiency, reducing fuel costs. In stationary power plants, a widely used combination is a gas turbine (operating by the Brayton cycle) burning natural gas or synthesis gas from coal, whose hot exhaust powers a steam power plant (operating by the Rankine cycle). This is called a Combined Cycle Gas Turbine (CCGT) plant, and can achieve a best-of-class real (HHV - see below) thermal efficiency of around 54% in base-load operation, in contrast to a single cycle steam power plant which is limited to efficiencies of around 35–42%. Many new gas power plants in North America and Europe are of the Combined Cycle Gas Turbine type. Such an arrangement is also used for marine propulsion, and is called a combined gas and steam (COGAS) plant. Multiple stage turbine or steam cycles are also common.
Power plant engineering unit 3 notes by Varun Pratap SinghVarun Pratap Singh
Download Link: https://sites.google.com/view/varunpratapsingh/teaching-engagements (Copy URL)
Unit-3
Diesel power plant
General layout, performance of diesel engine, fuel system, lubrication system, air intake and admission system, supercharging system, exhaust system, diesel plant operation and efficiency, heat balance.
Gas turbine power plant
Elements of gas turbine power plants, Gas turbine fuels, cogeneration, auxiliary systems such as fuel, controls and lubrication, operation and maintenance, Combined cycle power plants.
Power plant engineering unit 2 notes by Varun Pratap SinghVarun Pratap Singh
Download Link: https://sites.google.com/view/varunpratapsingh/teaching-engagements (Copy URL)
SYLLABUS
Unit-II
Steam power plant
Power plant boilers including critical and super critical boilers. Fluidized bed boilers, boilers
mountings and accessories.
General layout of steam power plant. Different systems such as fuel handling system,
pulverizes and coal burners, combustion system, draft, ash handling system, feed water
treatment and condenser and cooling system, turbine auxiliary systems such as governing, feed
heating, reheating, flange heating and gland leakage.
Operation and maintenance of steam power plant, heat balance and efficiency.
Detailed Internship Report about RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Includes information about Thermodynamic Cycles, Combined Cycle, HRSG (Heat Recovery Steam Generator), and various components of a Combined Cycle Power Plant.
Study: The Future of VR, AR and Self-Driving CarsLinkedIn
We asked LinkedIn members worldwide about their levels of interest in the latest wave of technology: whether they’re using wearables, and whether they intend to buy self-driving cars and VR headsets as they become available. We asked them too about their attitudes to technology and to the growing role of Artificial Intelligence (AI) in the devices that they use. The answers were fascinating – and in many cases, surprising.
This SlideShare explores the full results of this study, including detailed market-by-market breakdowns of intention levels for each technology – and how attitudes change with age, location and seniority level. If you’re marketing a tech brand – or planning to use VR and wearables to reach a professional audience – then these are insights you won’t want to miss.
The technologies and people we are designing experiences for are constantly changing, in most cases they are changing at a rate that is difficult keep up with. When we think about how our teams are structured and the design processes we use in light of this challenge, a new design problem (or problem space) emerges, one that requires us to focus inward. How do we structure our teams and processes to be resilient? What would happen if we looked at our teams and design process as IA’s, Designers, Researchers? What strategies would we put in place to help them be successful? This talk will look at challenges we face leading, supporting, or simply being a part of design teams creating experiences for user groups with changing technological needs.
Combined Cycle Gas Turbine Power Plant Part 1Anurak Atthasit
Introduction to Combined Cycle Gas Turbine Power Plant. Describing the advantage and design limit of the CCGT. Overview of Brayton Cycle and Rankine Cycle - showing some basic thermodynamic to explain some background of CCGT.
Lawrence Livermore National Laboratory
المحرك الصاروخي المعدل بقي حقيقه وقفزة علمية
بدأ اعتمادا علي المحاكاة فقط وصلا للنجاح وطبعا تحت مظلة وزاره الدفاع الامريكيه لتأمين الدعم اللازم و...
اضافة مؤثرة فعلا في تلك الصناعة
وأهم حاجه فيه ان الثرست زاد مع زياده الكفاءه ايضا ده غير ان الثرست نفسه بيعتمد علي الارتفاع
ده هيطور رحلات الذهاب >> والعوده!! كمان بشكل كبير
https://str.llnl.gov/november-2015/burton
multi mission radar (MMR) - EL/M-2084 FOR IRON DOMEHossam Zein
multi mission radar (MMR) - EL/M-2084 FOR IRON DOME
from IAI MELTA
for more detailed info. visit -::-
http://hossamozein.blogspot.com/2011/10/iron-dome.html
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...ssuser7dcef0
Power plants release a large amount of water vapor into the
atmosphere through the stack. The flue gas can be a potential
source for obtaining much needed cooling water for a power
plant. If a power plant could recover and reuse a portion of this
moisture, it could reduce its total cooling water intake
requirement. One of the most practical way to recover water
from flue gas is to use a condensing heat exchanger. The power
plant could also recover latent heat due to condensation as well
as sensible heat due to lowering the flue gas exit temperature.
Additionally, harmful acids released from the stack can be
reduced in a condensing heat exchanger by acid condensation. reduced in a condensing heat exchanger by acid condensation.
Condensation of vapors in flue gas is a complicated
phenomenon since heat and mass transfer of water vapor and
various acids simultaneously occur in the presence of noncondensable
gases such as nitrogen and oxygen. Design of a
condenser depends on the knowledge and understanding of the
heat and mass transfer processes. A computer program for
numerical simulations of water (H2O) and sulfuric acid (H2SO4)
condensation in a flue gas condensing heat exchanger was
developed using MATLAB. Governing equations based on
mass and energy balances for the system were derived to
predict variables such as flue gas exit temperature, cooling
water outlet temperature, mole fraction and condensation rates
of water and sulfuric acid vapors. The equations were solved
using an iterative solution technique with calculations of heat
and mass transfer coefficients and physical properties.
2. Options for Optimizing Combined Cycle
Plants
12/01/2015 | Thomas W. Overton, JD
With low gas prices and renewable generation boosting demand and capacity
factors for combined cycle plants, plant operators are being called upon to
squeeze out every last megawatt from their systems. Fortunately, there have
never been more ways to do it. Here are some you may not have thought of.
Gas-fired power is booming—even more than expected. For only the second
time ever, but also the second time this year, gas generated more electricity in a
month in the U.S. than coal. According to statistics from the Energy
Information Administration (EIA), in July 2015 coal generated 139 TWh, while
natural gas generated 140 TWh. Those statistics are a stark break from 2014,
when coal produced 150 TWh and gas was responsible for only 114 TWh.
While coal remained in the lead with a 34.5%-to-31.1% advantage in the power
mix through July, those numbers represent a fairly substantial departure from
EIA predictions. In its Annual Energy Outlook this year, the EIA predicted gas
would reach a 31% share—in 2040.
With gas-fired plants being called upon to shoulder an ever-growing share of
the power mix, plant owners are looking for more and better ways to squeeze
extra performance out of their equipment, without breaking the bank.
While gas turbine manufacturers such as GE, Siemens, and Mitsubishi-Hitachi
Power Systems offer a selection of upgrade packages to improve performance,
these kinds of choices are both expensive and require significant down time.
For plants that are not in the position to undertake costly outages and upgrades,
and those newer plants already operating state-of-the-art equipment, there are
still some ways to tweak out a few extra kilowatts.
3. Clean-Up Time
Jeff Fassett of IEM Energy Consultants, who spoke to POWER in October,
recommended that plant operators think first about cleanliness.
Fassett pointed out that a substantial portion of a turbine’s energy is used by the
compressor, which means dirty compressor blades can have a serious effect on
efficiency. “When the blades are dirty, the airflow is more turbulent, and that
will degrade performance.”
Of course, the importance of maintaining inlet filters and keeping intake air
clean isn’t a novel idea. Poor-quality inlet air can also lead to blade erosion and
corrosion of turbine components, both of which will hurt efficiency. One
problem is that the effects of poor-quality air are cumulative: Though cleaning
can address blade fouling to some extent, restoring original turbine
performance is typically not possible—and erosion can only be addressed by
replacement. Thus, it behooves turbine operators to keep air quality as high as
possible from initial startup.
But Fassett said the solution he recommends isn’t one operators often take:
Swapping out standard ASHRAE filters for HEPA-rated filters.
“The common approach is just changing the filters more often,” he said, “but
this doesn’t get to the root problem,” which is that lower-rated filters allow
more particulate matter into the turbine and that everything getting into the
compressor that doesn’t belong there degrades both short-term and long-term
performance.
Fassett has worked with plant managers to upgrade their turbine filters, which
usually involves a retrofit, depending on the configuration of the filter house.
A number of companies currently market gas turbine HEPA filters. Louisville,
Ky.–based AAF, which has supplied HEPA filters for more than 50 F-class
turbines worldwide, estimates that using these filters can recover 6% of the
power output normally lost to engine fouling. With HEPA filters, time between
turbine cleaning cycles can be at least 8,000 hours (Figure 1). Though the use
4. of HEPA filters results in a larger pressure differential, the initial power loss is
more than compensated for by substantially increased cleanliness and reduced
downtime.
1. Clean sweep. The differences in turbine blade fouling from operating with
different filters can be dramatic. The left photo shows turbine blades after 8,000
hours with a HEPA filter; the right photo, after 2,000 hours with a standard
filter. Courtesy: AAF International
Bill Lovejoy, chief engineer for engineering services firm NAES, concurred on
the importance of maintaining cleanliness, not just because of impact on the
turbine blades but also because of the effects dirty filters will have on
performance.
“It can catch up to you over time, and you are really hurting yourself. You pay
for that pressure drop in your overall efficiency.”
Operational Adjustments
Another performance element Fassett recommends that operators think about is
the low-load setpoints on their gas turbines—not just because of effects on the
gas turbine but also the downstream effects on the steam turbine.
“When the steam turbine is operating at low loads, you can exhaust the thermal
energy before the steam reaches the final stages and get condensation. That can
cause erosion of the turbine blades.”
5. Fassett said low-load setpoints for the gas turbines need to consider effects not
just on the turbines themselves but also on the rest of the plant.
Other efficiency losses can be found and eliminated by thinking about ways
energy may be escaping the system.
“One site we worked with has an auxiliary boiler and is using it to keep vacuum
on the steam turbine generator,” Fassett said. “All excess steam is being piped
to the heat-recovery steam generator (HRSG) to keep the boilers warm, so hot
restarts are minimized.” Another relatively simple tweak is installing heat
blankets to insulate the steam turbine, which cuts down on cold restarts, he said.
Aftermarket Add-Ons
In addition to relatively simple tweaks, there are more sophisticated aftermarket
tuning solutions that can be added to existing plants.
EthosEnergy has marketed its ECOMAX automated combustion tuning system
for several years. ECOMAX is designed to address performance instabilities
that can result from manual tuning to maintain emissions compliance,
particularly for NOx. Operating with lean premixed flames in the combustor
keeps NOx low but can cause instability in combustion dynamics, which can
damage turbine components over time. These instabilities are exacerbated by
large ambient temperature swings—common in many areas where gas is a
major element of the power mix, such as the U.S. Southwest and West Coast—
as well as by fuel quality and instrument drift. When the operating envelope
strays outside the optimized range, performance will suffer and emissions can
fall out of compliance.
Using real-time monitoring of combustion and emissions, the ECOMAX
system automatically tunes combustion to keep the turbine within the optimized
operational envelope (Figure 2). ECOMAX can communicate directly with the
turbine or integrate with the plant’s digital control system.
6. 2. Autopilot. The ECOMAX automated combustion tuning system is capable
of monitoring a range of key turbine operating parameters and keeping output
within a specified range to avoid emissions problems and to maintain peak
performance. Courtesy: EthosEnergy
ECOMAX can also be used to boost performance, as necessary, with the
addition of the Tru-Curve option, which raises the baseload fuel-air ratio while
still controlling emissions and combustion dynamics. Tru-Curve can be turned
on and off as desired.
EthosEnergy says the ECOMAX Tru-Curve package can improve heat rate by
0.20% to 0.25% and boost power output by up to 11 MW, depending on the
size of the plant.
Another, more outside-the-box upgrade is the Turbophase compressed air
peaking power system. Offered by Jupiter, Fla.–based Powerphase, the
Turbophase unit uses a separate reciprocating engine to add additional
compression to the turbine air inlet, without the use of steam or water injection,
which can cause operational issues. Powerphase says this system allows faster
peaking response than existing options, allowing 10% to 20% additional
peaking power capability and up to 7% heat rate improvement, depending on
the model of turbine.
7. Low-Load Combined Cycle Operation
Combined cycle plants often do not operate in combined cycle mode at low
loads because the system is optimized for baseload operation, and improper
optimization can result in damage to the heat recovery steam generator, as well
as emissions violations. However, giving up the ability to operate at low loads
can mean lost revenue.
Many of the newest models of combined cycle plants are designed for load
following and low-load operation, but with the right approach, some older
plants can optimize their operations for low-load generation as well. The
Electric Power Research Institute (EPRI) recently conducted a proprietary
study determining the best ways to optimize combined cycle operation at a
plant using GE 7FA turbines. Though proper optimization procedures will vary
from plant to plant and depend on operational profiles, the EPRI study found
that a tradeoff between lower exhaust gas temperature and higher exhaust flow
would allow lower-load operation without damage to the HRSG and without
causing NOx emissions to spike.
Making it work requires careful monitoring of NOx and CO emission levels,
combustion dynamics, attemperator performance, main steam-line superheater
level, and inlet-guide vane position, in order to determine the minimum
generation load at the lowest possible turbi0ne-exhaust temperature.
Though there are trade-offs with nearly any performance enhancement, plant
operators have more options these days than ever.
— Thomas W. Overton, JD is a POWER associate editor.
Quickly Boost Your Combustion Turbine
Response
10/01/2014 | Dr. Robert Peltier, PE
8. Morris Cogeneration, a combined cycle cogeneration plant near Chicago, has
installed TurboPHASE, a fast-responding, modular “turbocharger” installed to
boost capacity and PJM regulation revenue. How does it perform?
Twice this year, PJM flirted with blackouts when brutal winter storms (dubbed
a polar vortex) struck the Eastern U.S. in January. The cold weather set a new
winter peak demand record of 141,500 MW on Jan. 7, busting the record set in
February 2007 by nearly 5,000 MW. In fact, the five biggest demands ever
placed on the PJM grid, and eight of the 10 largest, occurred between Jan. 7 and
Jan. 30. PJM reported that at one point, 36,000 MW was out of service due to
forced outages, which amounts to 20% of its installed capacity. Adam Keech,
director of wholesale market operations, is reported by RTO Insider as saying—
the morning after setting the winter peak record—“We really exhausted every
megawatt we had on the system.” Peaking capacity and fast unit response is a
necessity during summer and winter peaks, and many regional transmission
organizations (RTOs) are willing to pay well for the service.
A solid majority of new plant construction in PJM is gas fired, led by simple or
combined cycle plants. Simple cycle combustion turbine (CT) plants are less
efficient than combined cycle plants but are able to start more rapidly and add
valuable power to the grid in minutes, which is extremely valuable to a system
like PJM as synchronized reserve, fast grid regulation, or black start service. In
fact, ancillary service payments often justify the cost of constructing a simple
cycle peaking plant.
A New Option
Jupiter, Florida–based PowerPhase LLC has successfully demonstrated a new
technology called TurboPHASE that may allow an existing simple cycle CT or
combined cycle plant to add as much as 10% to 20% more power to the grid in
seconds, depending on plant configuration, addressing the quick-start and fast-
response needs of the modern grid.
The TurboPHASE system consists of a multistage intercooled centrifugal
compressor that delivers hot compressed air to the CT’s compressor discharge
section, thereby allowing the CT to operate at its rated capacity irrespective of
9. the ambient conditions (5C to 50C) or altitude (Figure 1). The system takes
advantage of the CT operating below its limits during hot weather much like an
inlet chiller or evaporative cooling system, although TurboPHASE can also
operate in conjunction with either of those inlet cooling options.
1. Turbocharging combustion turbines. TurboPHASE consists of four main components:
engine, gearbox, compressor, and recuperator. A gas-fired engine-compressor set
produces compressed air that is added to the combustion turbine’s compressor discharge
section to negate the effect of a high ambient temperature performance derate.
Courtesy: PowerPhase LLC
A separately fueled reciprocating engine direct drives the compressor. The heat
from the exhaust of the engine is used to heat the compressed air in the
recuperator before entering the CT compressor section. On an operating CT,
TurboPHASE is said to be able to ramp to full load in 60 seconds or less and
from part load to full load in 10 seconds or less. This design feature is sure to
be of interest to grid dispatchers anxious to have the ability to quickly backfill
lost capacity during a system emergency or to quickly respond to the
intermittency of renewable resources.
Field Tests Completed
Two prototype TurboPHASE modules (TPMs) were tested in August, and the
data and test results were provided to POWER on an exclusive basis. The tests
10. were conducted at Atlantic Power Corp.’s Morris Cogeneration Plant (Morris),
located just outside Chicago (Figure 2). The gas-fired 177-MW combined cycle
facility is located within the Equistar Chemicals petrochemical plant in Morris,
Ill. All of the steam (after passing through a steam turbine) and a portion of the
electricity produced by the plant is sold to Equistar, and the remainder of the
power is sold into the PJM West market. Morris is configured with three gas-
fired General Electric Frame 6B CTs, each with a heat-recovery steam
generator (HRSG).
2. Demonstration plant. Two TurboPHASE modules (TPMs) were installed at
Atlantic Power Corp.’s Morris Cogeneration Plant (lower left of photo) and
were recently performance tested. The TPMs each added over 3 MW of quick
response capacity to a Frame 6B combustion turbine and steam turbine system.
Courtesy: PowerPhase LLC
PowerPhase engineers ran a series of predictive performance models using
ThermoFlow in advance of the field tests. The models predicted that the CT
full-load performance would increase ~2.63 MW and the steam turbine by
~0.43 MW, for a total power increase of ~3.06 MW. The cost of the increased
11. output is the additional fuel burned by the CT (~10 MMBtu/hr) and the fuel
burned by the engine (~16.3 MMBtu/hr). Therefore, the incremental heat rate
of the unit with one TPM in service was expected to be on the order of 26.3
MMBtu/hr/3.06 MW = 8,650 Btu/kWh.
The demonstration test was conducted in two parts. The first test was designed
to demonstrate the increase in output capacity when using a single TPM. The
second test measured the response or ramping speed of the plant with one or
two TPMs injecting air into the plant’s CT1. Each of the TPMs used at Morris
is powered by MTU 20V4000L32 gas-fired engines, each rated at 2 MW.
Morris is also equipped with inlet chilling and HRSG duct-firing capability, and
both were in operation during the demonstration tests. The tests were conducted
with the CT at full power at an ambient temperature that averaged ~85F. At no
time during the tests were the operating limits of the CT exceeded.
Day One Tests. On the first day of testing, compressed air from TPM2 was
injected into CT1 as the system cycled off and on three times. Data was
collected at one-second intervals and then averaged. CT fuel flow
measurements were taken from plant instruments, and TPM fuel flow was
measured (at the inlet to the engine) at 16.3 MMBtu/hr as expected. TPM air
injection flow rate was measured by an annubar-type flow meter on the main
air header prior to entering the CT. The airflow from each TPM was measured
as 11.5 lb/sec at ~156 psi.
The measured test results at Morris showed that the average CT power boost
was 2.74 MW and that the steam turbine produced an additional 0.32 MW, for
a total power increase of 3.06 MW per TPM, very close to the prediction. As an
additional benefit, the TPM compressor intercoolers produced an average of 1.2
gallons per minute of clean water during the tests.
The second test of the day was measurement of the plant response to a demand
signal. The test procedure was to first ramp up TPM2 to full speed, no load. No
compressed air was produced by TPM2 while the system was idling. When
warmed up, TPM2 was ramped up to 75% load while venting the compressed
air produced to the atmosphere through a vent valve, bypassing the CT.
12. Simulating receipt of a demand signal with TPM2 at 75% load, the vent valve
was closed and the injection valve was opened, thereby sending compressed air
to the CT compressor discharge. The air injection quickly produced an
incremental power increase of about 1.5 MW, ramping up to ~2 MW when the
vent valve was fully closed and injection valve was fully open. Next, TPM2
was ramped to full power, and the CT responded by producing an increase of
~2.74 MW, with the steam plant power increase following. The test ended with
the load on TPM2 reduced to 75%, followed by opening the vent valve and
closing the air inject valve to the CT. Figure 3 shows the results of the response
testing completed on day one. The TPM was able to add much, although not all,
of the incremental power from the CT within the 60-second goal set by the
company.
3. Day one tests. Results of the first day of TurboPHASE demonstration tests
are illustrated. The blue line represents the temperature at the inlet to the
combustion turbine. The orange line shows the response of the combined cycle
plant to full air injection. Courtesy: PowerPhase LLC
13. Day Two Tests. The response tests were repeated on the second day of testing
using TPM1. Figure 4 illustrates the data collected during these tests, which
were very consistent with the previous day’s tests.
4. Day two tests. The test results of the second day of TurboPHASE demonstration tests
are illustrated. The last test of the day was with both TurboPHASE systems in operation
followed by a trip of one system. Courtesy: PowerPhase LLC
The second test of the day was to run both TPMs in parallel and inject the
produced compressed air into CT1. The final test simulated an unexpected trip
of a TPM. When the air supply from TPM2 ceased, a check valve in the TPM
prevented reverse flow, and TPM1 continued supplying compressed air to the
CT as expected.
The piping system pressure drop between the TPMs and the CT was ~11 psi
with one TPM operating (flowing 11.5 lb/sec) rising to ~40 psi with two TPMs
operating, so the airflow into the CT was slightly less than double (22 lb/sec).
The pressure drop effect is apparent in Figure 4 where a single TPM produces
14. ~3 MW while two TPMs produce slightly under ~6 MW. A line size increase
from 6 inches to 8 inches would solve this problem, but since Morris doesn’t
anticipate operating the plant in this manner, the cost of the pipe size increase
isn’t justified.
Pluses and Minuses
Before assessing the results of the testing, it’s best to remember that this was
the first full-scale demonstration test of the TurboPHASE and we were privy to
only an overview of the testing and the performance results. That said, we are
still able to reflect on the performance of the system in relation to the important
ancillary services PJM and other RTOs desire: synchronized reserve, fast grid
regulation, and black start service.
Synchronized Reserve. A single TPM consists of a single MTU gas-fired
engine that will produce 2 MW were it fitted with a generator and operated
standalone, which is the obvious competitor to the TurboPHASE system.
Further, according to data on the MTU website, this model gas engine with a
generator operates at a heat rate of ~8,000 Btu/kWh, which is a very efficient
engine, and more efficient than the CT. This class engine, in “hot start
conditions” (usually defined as lubricating oil preheated, engine bearing
prelubricated, and cooling water preheated) can be started and synchronized to
the grid in ~60 seconds or less and reach full load in ~90 to 180 seconds. The
downside is the extra cost of the generator and switchgear.
The 60-second response of the TPM is based on the engine operating at 75%
load with compressed air bypassing the CT. A “start” signal puts the
compressed air into the CT and increased power is achieved in ~60 seconds in
the CT, about 2.75 MW. The capacitance in the HRSG and steam turbine
system brings the remaining ~0.25 MW along well after the 60-second goal.
Although the data provided did not state the time period, the two figures are
suggestive that the time lag is several minutes, as one would expect.
The report suggested that the average incremental heat rate of the TPM (8,650
Btu/kWh predicted) was 8,495 Btu/kWh based on the full ~3 MW power
increase. However, the fuel flow data taken from station instruments showed
15. significant variation, so it’s best to consider the incremental heat rate as
anecdotal rather than a hard number. Also, for comparison purposes, a more
appropriate incremental heat rate should be based on the CT output alone rather
than the CT plus steam turbine output because of the several-minute time lag of
the steam system.
How does the TurboPHASE stack up against using the same engine in a
standby package for synchronized reserve power? Both packages must be
running, in standby mode, and synchronized to the grid to qualify. However,
the engine-generator can be synchronized, kept at minimum load (lower fuel
consumption), and can take on 2 MW of load within ~30 seconds or so. The
TPM must also be running but held at 75% load in order to add 2.75 MW to the
grid within 60 seconds, but it does so at a higher heat rate than the engine-
generator alone. The economics are very CT and site specific.
Fast Grid Regulation. Once the TurboPHASE is operating, then its response
to rapid changes in grid demand must be considered. Although the specific data
wasn’t available, the TPM response to a step increase in load demand can be
estimated from Figures 3 and 4. The data does confirm that TurboPHASE
responds quickly, with the nearly vertical lines representing the CT response
followed by the slower steam turbine. The data also shows the CT responds in
about 2 to 3 minutes, with the additional steam turbine power available within
10 minutes. The standard PJM response requirement for grid regulation power
is 10 minutes. Regardless, adding the TPM did improve the grid response of the
Morris plant and may allow the plant to move into a grid response category
with a higher payment.
The competitive 2-MW gas-fired engine-generator could also be started,
synchronized, and at maximum load in less than the 10 minutes standard to
supply grid regulation power. But then again, a simple cycle Frame 7FA (227
MW) can start and reach 50% load within 10 minutes and then ramp up at 40
MW/min. Aeroderivative engines start and synchronize even faster.
Black Start Service. The TurboPHASE has the potential to become an
interesting black start option for some utilities with combined cycle plants.
However, it’s difficult to compete with a diesel engine when the weather gets
16. very cold (see “Prepare Your Gas Plant for Cold Weather Operations” in this
issue), particularly when natural gas supplies are limited for power generation
at some gas plants. The best black start systems will be an independent system
that can supply power to just the critical plant systems needed for restart. On
the other hand, a TPM can be installed in two to three months while a new
engine-generator will likely take six months or longer.
Final Analysis
TurboPHASE has the potential for reinvigorating existing combined cycle or
simple cycle plants with additional peaking capacity, especially during warmer
days when the output of the CT is otherwise limited. The response of the
TurboPHASE, from the limited information we have reviewed, is on the same
order as a gas-fired reciprocating engine. Efficiency leans toward the engine-
generator because the combined cycle plant has a higher heat rate. This balance
point could easily change should the TPM be installed on a more efficient CT,
although there aren’t many that CTs with a heat rate less than 8,000 Btu/kWh
(for example, the 60-Hz 7FA is 8,680 Btu/kWh).
On the other hand, the cost of a TPM is likely less than a bank of centrifugal
chillers and coils that are often used to increase CT power output during warm
weather. Also, since the TPM produces compressed air at 300 psi, the system
can be used on any CT with a compressor discharge pressure of 290 psi or less,
which includes many E-, F-, and G-class CTs and some aeroderivative engines,
assuming there is a suitable open port on the casing at the compressor
discharge.
The response of the TurboPHASE does meet the PJM requirements for grid
regulation power but only when the unit is running and the compressor is
charged and ready to dump compressed air into the CT. A potential owner must
consider the economics of balancing the regulation payments from PJM against
the cost of the TPM and the added fuel costs. Also, it probably goes without
saying that potential adopters must be located within an RTO that has a grid
fast regulation payment scheme.
17. What do the OEMs think about an owner adding compressed air into the engine
casing for peaking power or fast regulation purposes? General Electric’s GER-
3567H states, “GE [heavy duty] gas turbines are designed to allow up to 5% of
the compressor airflow for steam injection to the combustor and compressor
discharge.” If superheated steam injection is acceptable to GE, as it has been
for over 30 years, then one would expect that compressed air in like mass flow
will also be acceptable. Also, it seems to me that injecting clean compressed air
upstream of the combustor is certainly preferable to wet compression resulting
from the use of evaporative coolers. ■
— Dr. Robert Peltier, PE is POWER’s consulting editor.