SlideShare a Scribd company logo
1 of 29
Download to read offline
A
TRAINING REPORT
ON
“THERMAL POWER PLANT”
STUDENT’S NAME: PRATIK GUPTA
COURSE: B.E.
BRANCH: ELECTRICAL & ELECTRONICS
YEAR/ SEM: 2ND
/4TH
COLLEGE: DR. C.V. RAMAN INSTITUTE OF
SCIENCE & TECHNOLOGY, KOTA
INDUSTRIAL NAME: SIPAT SUPER THERMAL POWER
CORP. (NTPC SIPAT)
SUBMITTED BY: SUBMITTED TO:
PRATIK GUPTA MR. PRAVIN PATEL
(EEE 4TH
SEM)
CERTIFICATE
This is to certify that the project report entitled as
NATIONAL THERMAL POWER PLANT has been done
by PRATIK GUPTA during his vocational training period
from 20-06-13 to 20-07-13 at “SIPAT SUPER
THERMAL POWER PROJECT” is a record of studies,
site experience and keen interest to the subject and
analysis carried out by him under my supervision and
guidance. This is a part of partial fulfilment of their
vocational training programme.
Guided by:-
1. MR. SHALABH SAHRMA
2. MR. J.P.Patel
3. MR. Dilip Khalatkar
4. MR. P.K. DAS
DECLARATION
The training work has been carried out and the report
prepared by me during 20th
June to 20th
July 2013 under
the guidance of faculties ntpc ltd/sipat thermal power
plant and organised by employ development centre,
human resource development.
This is the original work carried out by me and not has
been taken from any other sources nor been submitted to
any institute or organisation as a fulfilment of any other
curriculum.
ACKNOWLEDGEMENT
I hereby convey my deep and sincere gratitude in all humbleness to
respected
5. MR. SHALABH SAHRMA
6. MR. J.P.Patel
7. MR. Dilip Khalatkar
8. MR. P.K. DAS
Who provided me with an opportunity to learn under their gracious
guidance, meticulous care and throughout the training. Their personal
supervision and guidance has enabled me to complete this Project. I
also thankfully acknowledgement the assistance received from MR
PRAVIN PATEL and others for their co-operation during the
preparation of this project report. The project report would not have
been shaped in this form without their encouragement and guidance.
Contents
1. Introduction of NTPC
2. Introduction about Project
3. Production of Electricity
4. Principal of Steam Power Plant
5. Coal Handling Plant
6. Coal Handling Plant Power Distribution
7. Demineral Plant(DM Plant)
8. Coal ,Water and Steam Cycle
9. H.T. Switch gear
10. L.T. Switch gear
11. Generators and Transformers
12. D.C. System
13. Switch Yard
14. Conclusion
INTRODUCTION OF NTPC
India’s largest power company, NTPC was set up in 1975 to accelerate power
development in India. NTPC is emerging as a diversified power major with
presence in the entire value chain of the power generation business. Apart from
power generation, which is the mainstay of the company, NTPC has already
ventured into consultancy, power trading, ash utilization and coal mining. NTPC
ranked 337th
in the ‘2012, Forbes Global 2000’ ranking of the World’s biggest
companies. NTPC became a Maharatna company in May, 2010, one of the only
four companies to be awarded this status.
The total installed capacity of the company is 41,184 MW (including JVs) with 16
coal based and 7 gas based stations, located across the country. In addition
under JVs, 7 stations are coal based & another station uses naptha/LNG as fuel
and 2 renewable energy projects. The company has set a target to have an
installed power generating capacity of 1,28,000 MW by the year 2032. The
capacity will have a diversified fuel mix comprising 56% coal, 16% Gas, 11%
Nuclear and 17% Renewable Energy Sources(RES) including hydro. By 2032,
non fossil fuel based generation capacity shall make up nearly 28% of NTPC’s
portfolio.
NTPC has been operating its plants at high efficiency levels. Although the
company has 17.75% of the total national capacity, it contributes 27.40% of
total power generation due to its focus on high efficiency.
In October 2004, NTPC launched its Initial Public Offering (IPO) consisting of
5.25% as fresh issue and 5.25% as offer for sale by Government of India. NTPC
thus became a listed company in November 2004 with the Government holding
89.5% of the equity share capital. In February 2010, the Shareholding of
Government of India was reduced from 89.5% to 84.5% through Further Public
Offer. The rest is held by Institutional Investors and the Public.
At NTPC, People before Plant Load Factor is the mantra that guides all HR related
policies. NTPC has been awarded No.1, Best Workplace in India among large
organizations and the best PSU for the year 2010, by the Great Places to Work
Institute, India Chapter in collaboration with The Economic Times.
The concept of Corporate Social Responsibility is deeply ingrained in NTPC's
culture. Through its expansive CSR initiatives, NTPC strives to develop mutual
trust with the communities that surround its power stations.
INTRODUCTION ABOUT PROJECT
Sipat Super Thermal Power Station is located at Sipat in Bilaspur district in state of Chhattisgarh.
The power plant is one of the coal based power plants of NTPC. The coal for the power plant is
sourced from Dipika Mines of South Eastern Coalfields Limited.
The project has an installed capacity of 2980 MW consisting of two stages, stage one which got
commissioned late was of 3 units of 660 MW each involving super-critical boilers technology and
stage two consisted of 2 units of 500 MW each.
Stage Unit Number Installed Capacity (MW) Date of Commissioning Status
1st 1 660 2011 June Running
1st 2 660 2011 December Running
1st 3 660 2012 June [1]
Running
2nd 4 500 2007 May Running
2nd 5 500 2008 August Running
Total Five 2980
Sipat
Sipat' is a small developing town, approximately 22 kilometers away from Bilaspur, Chhattisgarh, the
second largest city in Chhattisgarh. It has been in news due to setup of new power plant by NTPC
Limited in that area. The project was started on 2001 by Indian former Prime Minister Mr. Atal Bihari
Vajpayee.NTPC Sipat has total installed capacity of 2980 MW.NTPC Sipat has two stages: Stage-I
comprises 3 units of 660MW each and Stage-II comprises 2 units of 500MW each. The thermal power
generation in NTPC sipat Stage-II is based on "Super Critical Boiler Technology" which is the
advanced technology in thermal power generation. NTPC Limited has helped this town in developing
by providing business prospective in that area and by providing education, healthcare facilities.
PRODUCTION OF ELECTRICITY
The means and steps involved in the production of electricity in a coal-fired power station are
described below.
The coal, brought to the station by train or other means, travels from the coal handling plant by
conveyer belt to the coal bunkers, from where it is fed to the pulverizing mills which grinds it as fine
as face powder. The finely powdered coal mixed with pre-heated air is then blown into the boiler by
fan called Primary Air Fan where it burns, more like a gas than as a solid in convectional domestic or
industrial grate, with additional amount of air called secondary air supplied by Forced Draft Fan. As
the coal has been grounded so finely the resultant ash is also a fine powder. Some of this ash binds
together to form lumps which fall into the ash pits at the bottom of the furnace. The water quenched
ash from the bottom of the furnace is conveyed to pits for subsequent disposal or sale. Most of ash,
still in fine particles form is carried out of the boiler to the precipitators as dust, where it is trapped
by electrodes charged with high voltage electricity. The dust is then conveyed by water to disposal
areas or to bunkers for sale while the cleaned flue gases pass on through ID Fan to be discharged up
the chimney.
Meanwhile the heat released from the coal has been absorbed by the many kilometres of tubing
which line the boiler walls. Inside the tubes is the boiler feed water which is transformed by the heat
into the steam at high pressure and temperature. The steam super-heated in further tubes (Super
Heater) passes to the turbine where it is discharged through the nozzles on the turbine blades. Just
the energy of the wind turns the sail of the wind-mill, so the energy of the steam, striking the blades,
makes the turbine rotate.
Coupled to the end of the turbine is the rotor of the generator – a large cylindrical magnet, so that
when the turbine rotates the rotor turns with it. The rotor is housed inside the stator having heavy
coils of copper bars in which electricity is produced through the movement of the magnetic field
created by the rotor. The electricity passes from the stator winding to the step-up transformer which
increases its voltage so that it can be transmitted efficiently over the power lines of the grid.
The steam which has given up its heat energy is changed back into water in the condenser so that it
is ready for re-use. The condenser contains many kilometres of tubing through which the colder is
constantly pumped. The steam passing around the tubes looses the heat and is rapidly changed back
to water. But the two lots of water (i.e. boiler feed water & cooling water) must NEVER MIX. The
cooling water is drawn from the river, but the boiler feed water must be absolutely pure, far purer
than the water we drink, if it is not to damage the boiler tubes. Chemistry at the power station is
largely the chemistry of water.
To condense the large quantities of steam, huge and continuous volume of cooling water is
essential. In most of the power stations the same water is to be used over and over again. So the
heat which the water extracts from the steam in the condenser is removed by pumping the water
out to the cooling towers. The cooling towers are simply concrete shells acting as huge chimneys
creating a draught (natural/mechanically assisted by fans) of air. The water is sprayed out at the top
of towers and as it falls into the pond beneath it is cooled by the upward draught of air. The cold
water in the pond is then circulated by pumps to the condensers. Inevitably, however, some of the
water is drawn upwards as vapours by the draught and it is this which forms the familiar white clouds
which emerge from the towers seen sometimes.
Why bother to change steam from the turbine back into water if it has to be heated up again
immediately? The answer lies in the law of physics which states that the boiling point of water is
related to pressure. The lower the pressure, the lower the temperature at which water boils. The
turbine designer want as low boiling point of water as possible because he can only utilize the energy
of the steam – when the steam changes back into water he can get NO more work out of it. So a
condenser is built, which by rapidly changing the steam back into water creates a vacuum. This
vacuum results in a much lower boiling point which, in turns, means he can continue getting work
out of the steam well below 100 degree Celsius at which it would normally change into water.
Principle of the Steam Power Plant
The working principle of a steam plant is based upon the Rankine cycle.
Generally steam is taken as the working medium due to its ability to be stable
and that it’s readily stable. The flow of steam in the plant can be very easily be
understood by the flow diagram of the plant. A graph plotted between the
temperature and the entropy would indicate the technical details of the
working by the rankine cycle. The entropy of a system can be understood as an
index of degradation of energy.
PLANT FLOW DIAGRAM
COAL HANDLING PLANT
Introduction: -
NTPC SIPAT gets its coal supply mainly from dipka mines. The coal being filled in the wagons of the
rail reaches plant. The purpose of this plant is to convey the coal to the bunker in the size not larger
than 20mm.It handles and transports the coal to the bunker from the wagons by passing through
various conveyors, transfer points, crusher houses, etc.
Type of unloading the coal: -
1. Manual Unloading: -Previously, manpower was used for unloading the wagons. But it was very
time consuming and more workers were required for the job to be done.
2. Box in (using wagon tippler for unloading): -For this method, Indian Railway grants 10 hours for
unloading the 58 wagons. In this method, Wagons are separated and tippled by using wagon
tippler. The Beetle Feeder is used to move the wagon on wagon tippler. The coal from the
wagons gets accumulated in The Track Hopper. At this time; the size of the coal is approximately
300mm.
3. BOBR: - Indian Railway grants only 2.5 hours for Unloading 58 BOBR wagons. This is an advanced
technology in which we use the compressor system.
In Bottom Open Bottom Release (BOBR) technology the wagons are opened from side. Pressure
is applied by the compressor to open the bottom gates of the wagon so that the coal gets
released over the track hopper and wagon get unloaded quickly.
Various equipment used in CHP: -
1. WAGON TIPPLER: - The wagon tippler is a most important device in thermal power project. The
Wagon tippler turns back the wagon at 135-degree angle and the structure of the wagon tippler
is to be very heavy. Upper side of the wagon is fixed with the many angles for supporting the
wagon. When the wagon is fixed on the Platform then whole platform is turned back and the
coal fall down in the wagon tippler hopper. The unloading time of the Rack is 6hours
2. PADDLE FEEDER: - They have been installed on conveyors below the manual unloading track
hopper. There are 6 nos. of paddle feeders, 3 on each conveyer. 3 Paddle Feeders of each
conveyer move to and fro within a limiting range. The rotating part of the paddle feeder is called
as plough wheel. Plough wheel has 6 blades. By the rotation of the plough wheel, the coal of the
track hopper gets accumulated between the blades and is discharged on the conveyor below it.
3. VIBRATING FEEDER: - They have been installed below the track hoppers of wagon tippler.
The coal is accumulated over the vibrating feeder so by giving vibrations to the vibrating feeder
we discharge the coal from track hopper to the conveyors. Their main purpose is to provide
uniform feeding on the conveyors. The vibrating feeders consist of a tray to which vibrator body
is fixed on the rear end.
4. TRANSFER POINTS: -Transfer Point is provided with flap gate and Conveyer. In transfer Point the
coal is transferred from one conveyer to other conveyer.
5. PRIMARY CRUSHER (ROTARY BREAKER): - In Primary Crusher House, the coal breaks in Rotary
Breaker. Here the coal comes from the Transfer point; breaks here and the stone fall down to a
separate place. Coal is converted from 300mm to 150mm size.
Part of the Primary Crusher House – a- Rotary Breaker b- Belt Feeder
6. SECONDARY CRUSHER (RING GRANULATOR): - In Secondary crusher House first the
magnetic part separate from the coal and then feed to the Secondary Crusher. This Crusher
breaks the coal in 20mm size and coal is sent to the Flap Gate and then feeded to the conveyer.
The Secondary crusher is hammer type. H.T. motor are used for breaking of the coal.
Specifications are 700KW 6.6KVMotor.
7. CROSS BELT MAGNETIC SEPRATORS: - They will remove the ferrous particles, which passes
along with the coal. It consists of electromagnet around which a belt is moving. It is suspended
from top, perpendicular to the conveyor belt at certain height. Whenever any iron particle
passes below the CBMS, it is attracted by the magnet and stick to the cross belt below it. The
CBMS capacity is of 50kg.
8. METAL DETECTOR: - The purpose of installation is to detect any metallic piece passing through
the conveyor. Whenever the pieces pass below the search coil of the metal detector, it gives the
trip command to the conveyor. Simultaneously, sand bag marker will fall on the conveyor belt so
that the metal can be searched easily and removed.
9. STACKER/RECLAIMER: -It is a very important device. The whole Structure of it is called Super
Structure. It stacks the excessive coal and reclaims the coal on its requirement. It is a two-way
device.
10. TRANSFER TOWER: -Here the coal is send to the Tipper. Transfer Tower is provided with a coal
sampler.
11. TIPPER: - The Tipper is a three-way device to feed the coal in Bunker. It is moveable device. It
is move on its track.
12. BUNKER: - Here the coal is collected from the tipper and stored. The capacity of the bunker for
Stage-I is 4800MT & Stage-II is 8700MT
DEMINERAL (DM) PLANT
INTRODUCTION: --
Water is required in plant for many purposes like for formation of steam, for removal of ash, for
safety during fire, etc. But the water required for the formation of steam should be perfectly devoid
of minerals because if minerals are present in the steam and the steam strike the blades of the
turbine, then due to being high in pressure it produces scars or holes on the turbine blades.
PURIFICATION OF WATER: -
Water is purified in DM plant through a chain of processes as under: --
1. Carbon filter – Water taken from the river is first sent to the carbon filter for the removal of
carbon contents in the water.
2. Strong acid cation exchanger – After passing through the carbon filter, water is sent to the
strong acid cation exchanger, which is filled with the concentrated HCL. The acid produces
anions, which get combined with the cations present in the water.
3. Strong base anion exchanger – After that the water is sent to the strong base anion
exchanger, which is filled with the concentrated NaOH.The base produces cations, which get
combined with the anions present in the water.
4. Mixed bed exchanger – And then water is sent to the chamber of mixed bed exchanger
where the remaining ions are removed. This is the last stage of purification.
COAL, WATER & STEAM CYCLES
COAL CYCLE
C.H.P Plant Bunker R.C Feeder Pulverization mill Boiler section
1. R.C Feeder: It is an induction motor driven device, which determine the Quantity of coal
enter in the pulverize mill.
2. Pulverization mill: Pulverization means exposing a large surface area to the action of
oxygen .Two Types of mill are used in the plant.
3. Ball mail: A ball mill operates normally under suction. A large drum partly filled with steel
balls, is used in this mill .The drum is rotated slowly while coal is fed in to it .The ball pulverize
the coal by crushing.
4. Contact mail: This mill uses impact principle. All the grinding elements and the primary air
fan are mounted on a single shaft. The flow of air carries coal to the primary stage where it is
reduced to a fine granular state by impact with a series of hammers.
WATER CYCLE
D.M Plant Hot well C.E.P Pump Low Pressure Heater 1, 2, 3 Derater
Boiler Feed Pump High Pressure Heater 5, 6 Feed Regulating station Economizer
Boiler Drum
1. DERATER: Feed strong tank of water. To produce sufficient pressure before feeding to B.F.D. .Filter
the harmful chemicals.
2. FEED REGULATING STATIONS: Control the quantity of water in to boiler drum.
3. ECONOMISER: Flux gases coming out of the boilers carry lot of heat. An economizer extracts a part
of this heat from the flue gases and uses it for heating the feed water.
4.DRAFTS SYSTEM: In forced draft system the fan is installed near the base of the boiler furnace. This
fan forces air through the furnace, economizer, air preheater and chimney. In an induced draft
system, the fan is installed near the base of Chimney.
STEAM CYCLE
Boiler Drum Ring Header Boiler Drum (Steam chamber) Super Heater H.P
Turbine Repeater I.P Turbine L.P Turbine condenser
1. BOILER: Boiler drum consists two chambers water chamber, steam chamber. Before Entering
in super heater the steam is going in to boiler drum, where the boiler drum filtered the
moisture and stored in to water chamber.
2. SUPER HEATER: The function of super heater is to remove the last traces of moisture from
the saturated steam leaving the tube boiler. The temperature is approx.530 o
C.
3. TURBINE: Steam turbine converts the heat energy in to mechanical energy and drives the
alternator. The velocity attained during expansions depends on initial and final heat content
of the steam. Turbine having number of stages in which the pressure drops takes place.
H.T.SWITCH GEAR
OPERATIONG VOLTAGE - 6.6KV
For low voltage circuits fuses may be used to isolate the faulty circuit. For voltage higher than 3.3 kV
isolation is achieved by circuit breaker.
Requirement of circuit breaker:
1. After occurrence of fault the switchgears must isolate the faulty circuit as quickly as possible
i.e. keeping the delay to minimum.
2. It should not operate when an over current flows under healthy condition.
Basic principal of operation of circuit breaker:
Circuit breaker consists of a fix contact and sliding contact into which moves a moving contact. The
end of moving contact it attached to a handle that can be manually operated or may operate
automatically with the help of mechanism that has a trip coil energized by secondary of CT. Under
normal condition the secondary of CT is not energized sufficiently to trip the coil but under false
condition the coil is energized fully to operate the trip coil and the circuit breaker is operated.
1. MOCB (Minimum oil circuit breaker)
2. SF6 (Sulphur hexafluoride circuit breaker)
Here oil and SF6 are used to quench the arc.
L.T SWITCH GEAR
OPERATING VOLTAGE- 415VOLT
TYPES OF CIRCUIT BREAKER: - Air break circuit breaker
Air brake circuit breaker:
The arc interruption process of air- based circuit breaker is based on the natural deionization of gases
by cooling action. The arc is resilient and can be stretched, and has a resistance, which can be
increased both by length and confinement. Hence the arc resistance is increased by stretching the
arc and as the resistance increases to higher value, the short circuit current drops to zero and arc is
extinguished.
Reducing the phase difference between the system voltage and the short circuit current assure that
when the are current is interrupt at its zero value, the recovery voltage has very low value at its not
allowed to reach 2-3 times the value of the system peak voltage, a phenomenon that occurs in most
cases, when arc current is interrupted at low power factor.
GENERATORS AND TRANSFORMERS
INTRODUCTION-
The auxiliaries in a plant can be divided into two categories-
1. URGENT AUXILIARIES- the urgent auxiliaries are those, which are associated with running of
unit.
2. SERVICE AUXILIARIES- the service auxiliaries are those whose loss would not affect output.
GENERATOR SPECIFICATIONS-
TURBO GENERATOR (gen1, gen2)
KVA 247000
Pf 0.85
Volts of stator 15750
Amperes of stator 9050
Volts of rotor 310
Amperes of rotor 2600
Rpm 3000
Hz 50
Phase 3
Connection YY
Coolant Water (stator)& hydrogen (rotor)
Gas pressure 3.5kg/cm-sq.
Insulation class B
EXCITATION SYSTEM-
1. STATIC EXCITATION SYSTEM-The generators in stage -1(u-1&u-2) have this excitation system.
Static excitation system has slip ring and carbon brush arrangement. It consists of step down
transformer, converter and AVR (automatic voltage regulator).
2. BRUSHLESS EXCITATION SYSTEM –The generators in stage -2(U-3, U-4& &U- 5) have this
excitation system. It has two exciters, one is main exciter and other is pilot exciter.
GENERATOR PROTECTION-
1. STATOR PROTECTION- The neutral of star connected winding is connected to primary of
neutral grounding transformer, so that earth fault current is limited by over voltage relay.
2. DIFFERENTIAL PROTECTION- In case of phase-to-phase fault generator is protected by
longitudinal differential relay.
3. ROTOR PROTECTION- Rotor winding may be damaged by earth faults or open circuits. The
field is biased by a dc voltage, which causes current to flow through the relay for an earth
fault anywhere on the field system.
4. OVER SPEED PROTECTION – Mechanically over speed device that is usually in the form of
centrifugally operated rings mounted on the rotor shaft, which fly out and close the stop
valves if the speed of the set increase more than 10%.
5. OVER VOLTAGE PROTECTION – It is provided with an over voltage relay. The relay is usually
induction pattern. The relay open the main circuit break and the field switch if the over
voltage persists.
6. SEAL OIL SYSTEM – Hydrogen in the generator is under very high pressure. There is a
possibility of this hydrogen to come out of gaps, which is very hazardous. So, seal oil is used
to seal the gaps so that hydrogen doesn’t come out.
7. LUBRICATION OIL SYSTEM –Turbine lubrication-oil system seeks to provide proper
lubrication of turbo generator bearings and operation of barring gear. Pumps are used to
circulate lubrication-oil inside the generator. The oil of the lubrication and the governing
system is cooled in the oil coolers. The cooling medium for these coolers is circulating water.
TRANSFORMER
TYPE PF TRANSFORMERS—
1. UNIT AUXILIARY TRANSFORMER: --This is a step down transformer. The primary receives
from generator and secondary supplies a 6.6 KV bus. This is oil cooled. These are 8 in
number.
2. NEUTRAL GROUNDED TRANSFORMER: --This transformer is connected with supply coming
out of UAT in stage-2. This is used to ground the excess voltage if occurs in the secondary of
UAT in spite of rated voltage.
3. GENRATOR TRANSFORMER: -- This is a step up transformer. This supply gets its primary
Supply from generator and its secondary supplies the switchyard from where it is transmitted
to grid. This transformer is oil cooled. The primary of this transformer is connected in star.
The secondary is connected in delta. These are four in number.
4. STATION TRANSFORMER: --This transformer has almost the same rating as the generator
transformer. Its primary is connected in delta and secondary in star. It is a step down
transformer. These are 4 in number.
SPECIFICATIONS
Generator transformer (GT-1 & GT-2)
KV 15.75/242
MVA 250
Phase 3
Hz 50
Connections Y-D 11
Type of cooling OFAF/ONAF/ONAN
Rated HV and IV (MVA) 250/150/100
Rated LV (MVA) 250/150/100
No Load Voltage HV (KV) 242
No Load Voltage IV (KV)
No Load Voltage LV (KV) 15.75
Line current HV (Amps) 597.14/358.29/238.86
Line current IV (Amps)
Line current LV (Amps) 9175.15/5505.09/3670.66
Temp rise coil o
C 50
Temp rise winding o
C 55
Neural grounded transformer (NGT)
KVA 1150
Phase 3
Hz 50
Type of cooling ONAF/ONAN
No load voltage HV (volts) 6600
No load voltage LV (volts) 250
Line current HV (Amps) 105.9
Line current LV (Amps) 2655.8
Temp rise oil o
C 50
Temp rise winding 55
Potential Transformer
KVA 1000
Phase 3
Hz 50
Type of Cooling ONAN
No Load Voltage HV (volts) 6600
No Load Voltage LV (volts) 433
Line Current HV (Amps) 87.53
Line Current LV (Amps) 133.5
Temp rise oil o
C 50
Temp rise winding o
C 55
D.C SYSTEM
INTRODUCTION:
DC system is generally used for control and protection operation, as AC supply is not fully
dependable. To maintain constant supply in case of power failure we use DC supply.
DC system consists of a battery charger. These are the mode of energy storage.
CHARGING EQUIPMENTS:
The battery charging equipment comprises of trickle charger, quick charger, battery panel, main
distribution board and switch control and signaling board.
CHARGING EQUATION:
In battery PbO2 used as positive plate and Pb as negative plate.
1. DISCHARGING PROCESS
2. CHARGING PROCESS
BATTERY CHARGER:
Battery charger normally operates in two modes.
1. Float charging: It is constant voltage mode and works as a trickle charger.
2. Boost charging: It is constant current mode and works as a quick charger.
TRICKLE CHARGER:
This charger is fed from three-phase ac supply and gives a dc-stabilized output at rated full load
current. The variation of the dc output voltage is limited to +/- 1% for 0 to 100% load variation and
simultaneously ac voltage variation of +/- 10% of frequency variation of +/- 5% from 50 Hz.
The rectification is obtained through full bridge controlled silicon rectifier. Stack comprising of these
SCR and three diode with the surge suppression RC network connected across each SCR and diode.
SWITCH YARD
As we know that electrical energy can’t be stored like cells, so what we generate should be
consumed instantaneously. But as the load is not constants therefore we generate electricity
according to need i.e. the generation depends upon load. The yard is the places from where the
electricity is send outside. It has both outdoor and indoor equipments.
SINGLE LINE DIAGRAM OF 220KV SWITCH YARD-
OUTDOOR EQUIPMENTS
1. BUS BAR
2. LIGHTENING ARRESTER
3. WAVE TRAP
4. BREAKER
5. CAPACITOR VOLTAGE TRANSFORMER
6. CORONA RING
7. EARTHING ROD
8. CURRENT TRANSFORMER
INDOOR EQUIPMENTS
1. RELAYS
2. CONTROL PANELS
9. POTENTIAL TRANSFORMER
10. LIGHTENING MASK
11. LIGHTENING MOOSE
CIRCUIT BREAKER:
The code for circuit breaker is 52. An electric power system needs some form of switchgear
in order to operate it safely & efficiently under both normal and abnormal conditions.
Circuit breaker is an arrangement by which we can break the circuit or flow of current. A circuit
breaker in station serves the same purpose as switch but it has many added and complex features.
The basic construction of any circuit breaker requires the separation of contact in an insulating fluid
that servers two functions:
1. It extinguishes the arc drawn between the contacts when circuit breaker opens.
2. It provides adequate insulation between the contacts and from each contact to earth.
The insulating fluids commonly used in circuit breakers are:
1. Compressed air
2. Oil which produces hydrogen for arc excitation.
3. Ultra high vacuum
4. Sulphur hexafluorides
The Specifications of the circuit breaker used are:
LIGHTING ARRESTER:
It saves the transformer and reactor from over voltage and over currents. We have to use the
lightning arrester both in primary and secondary of transformer and in reactors.
A meter is provided which indicates the surface leakage and internal grading current of arrester.
1. Green – arrester is healthy
2. Red – arrester is defective.
In case of red we first de-energize the arrester and then do the operation.
AIR BREAK EARTHING SWITCH:
The code of earthling switch is 5, 6, 7.The work of this equipment comes into picture when we want
to shut down the supply for maintenance purpose. This help to neutralize the system from induced
voltage from extra high voltage. This induced power is up to 2KV in case of 400 KV lines.
The specification of earthling switch is:
MAKE S & S POWER
TYPE MADRAS
VOLTAGE 245 KV
CURRENT 10 KA
MOTOR VOLT (AC) 415 VOLTS
CONTROL VOLT (DC) 220 VOLTS
MAKE CROMPTON GREAVES LTD.
TYPE AIR BLAST CIRCUITREAKER
RATED VOLTAGE 245 KV
RATED LIGHTING IMPULSE
WITHSTAND VOLTAGE 1050 KV
RATED SHORT CIRCUIT BREAKING
CURRENT
25 - 40KA
RATED FREQUENCY 50HZ
RATED NORMAL CURRENT 2000 A TO 4000 A
RATED CLOSING VOLTAGE 220 V DC
RATED OPENING VOLTAGE 220 V DC
BUS BAR:
Bus bars generally are of high conductive aluminum conforming to IS-5082 or copper of
adequate cross section .Bus bar located in air –insulated enclosures & segregated from all other
components .Bus bar is preferably cover with polyurethane.
1. Current Transformer (CT):
A current transformer is a type of instrument transformer designed to provide a current in its
secondary winding proportional to the alternating current flowing in its primary
.
Current Transformer Diagram
Application:
1. They are commonly used in metering and protective relaying in the electrical power
industry where they facilitate the safe measurement of large currents, often in the
presence of high voltages.
2. The current transformer safely isolates measurement and control circuitry from the
high voltages typically present on the circuit being measured.
3. Current transformers are used extensively for measuring current and monitoring the
operation of the power grid. The CT is typically described by its current ratio from
primary to secondary. Often, multiple CTs are installed as a "stack" for various uses
(for example, protection devices and revenue metering may use separate CTs).
Similarly potential transformers are used for measuring voltage and monitoring the
operation of the power grid.
4. Capacitive Voltage Transformer (CVT):
A capacitor voltage transformer (CVT) is a transformer used in power systems to step-down extra
high voltage signals and provide low voltage signals either for measurement or to operate a
protective relay. In its most basic form the device consists of three parts: two capacitors across which
the voltage signal is split, an inductive element used to tune the device to the supply frequency and a
transformer used to isolate and further step-down the voltage for the instrumentation or protective
relay as shown in figure below.
The device has at least four terminals, a high-voltage terminal for connection to the high voltage
signal, a ground terminal and at least one set of secondary terminals for connection to the
instrumentation or protective relay. CVTs are typically single-phase devices used for measuring
voltages in excess of one hundred kilovolts where the use of voltage transformers would be
uneconomical. In practice the first capacitor, C1, is often replaced by a stack of capacitors connected
in series.This results in a large voltage drop across the stack of capacitors that replaced the first
capacitor and a comparatively small voltage drop across the second capacitor C2, and hence the
secondary terminals.
Conclusion
On completion of my vocational training at Feroze Gandhi Unchahar Thermal
Power Project, Unchahar I have come to know about how the very necessity of
our lives nowadays i.e., electricity is generated. What all processes are needed
to generate and run the plant on a 24x7 basis.
NTPC Unchahar is one the plants in India to be under highest load factor
for the maximum duration of time and that to operating at highest plant
efficiencies. This plant is an example in terms of working efficiency and
management of resources to all other thermal plants in our country. The
operating plf of the NTPC as compared to the rest of country is the highest with
87.54% the highest since its inception.
The training gave me an opportunity to clear my concepts from practical point
of view with the availability of machinery of such large rating.
Ntpc 131113070238-phpapp02

More Related Content

What's hot

Vikas ntpc report complete
Vikas ntpc report completeVikas ntpc report complete
Vikas ntpc report completeVikas Singh
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpcLalitGoyal27
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALMilind Punj
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarRishikesh .
 
NTPC Training Report
NTPC Training ReportNTPC Training Report
NTPC Training ReportPratik Gupta
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarRishikesh .
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC SimhadriAshish Uppu
 
NTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORTNTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORTAnil Jadon
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC Shivam Singh
 
DADRI GAS POWER PLANT report
DADRI GAS POWER PLANT reportDADRI GAS POWER PLANT report
DADRI GAS POWER PLANT report94600banti
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer trainingAnubhav Ghosh
 
Industrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadIndustrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadPawan Agrawal
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC pptkirbadh
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2Power System Operation
 
NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015LekhraJ Meena
 
Summer internship report of DCCPP
Summer internship report of DCCPPSummer internship report of DCCPP
Summer internship report of DCCPPDurgSingh
 

What's hot (20)

Vikas ntpc report complete
Vikas ntpc report completeVikas ntpc report complete
Vikas ntpc report complete
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpc
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 
NTPC Training Report
NTPC Training ReportNTPC Training Report
NTPC Training Report
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
 
Reports ntpc
Reports ntpcReports ntpc
Reports ntpc
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
NTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORTNTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORT
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
 
DADRI GAS POWER PLANT report
DADRI GAS POWER PLANT reportDADRI GAS POWER PLANT report
DADRI GAS POWER PLANT report
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
Industrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadIndustrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC Faridabad
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
 
NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015
 
Summer internship report of DCCPP
Summer internship report of DCCPPSummer internship report of DCCPP
Summer internship report of DCCPP
 
REPORT-NHPC
REPORT-NHPCREPORT-NHPC
REPORT-NHPC
 

Viewers also liked

Kirby vacation - BITE5390 ECU
Kirby vacation - BITE5390 ECUKirby vacation - BITE5390 ECU
Kirby vacation - BITE5390 ECUkirbys12
 
Parks mark vacation
Parks mark vacationParks mark vacation
Parks mark vacationMark Parks
 
#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...
#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...
#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...Kelly Hungerford
 
BHEL HARIDWAR VOCATIONAL TRAINING REPORT
BHEL HARIDWAR VOCATIONAL TRAINING REPORTBHEL HARIDWAR VOCATIONAL TRAINING REPORT
BHEL HARIDWAR VOCATIONAL TRAINING REPORTk,l polytechnic roorkee
 
Tapping Twitter! How to Target Your Audience For Job and Talent Search
Tapping Twitter! How to Target Your Audience For Job and Talent SearchTapping Twitter! How to Target Your Audience For Job and Talent Search
Tapping Twitter! How to Target Your Audience For Job and Talent SearchKelly Hungerford
 
Api managers
Api managersApi managers
Api managersCloudAppi
 
Gobierno de apis
Gobierno de apisGobierno de apis
Gobierno de apisCloudAppi
 

Viewers also liked (15)

Summer traNING
Summer traNINGSummer traNING
Summer traNING
 
Kirby vacation - BITE5390 ECU
Kirby vacation - BITE5390 ECUKirby vacation - BITE5390 ECU
Kirby vacation - BITE5390 ECU
 
Tampax Puzzle
Tampax PuzzleTampax Puzzle
Tampax Puzzle
 
Parks mark vacation
Parks mark vacationParks mark vacation
Parks mark vacation
 
MORENA...!!!!
MORENA...!!!!MORENA...!!!!
MORENA...!!!!
 
Comcereal sa 2003
Comcereal sa 2003Comcereal sa 2003
Comcereal sa 2003
 
#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...
#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...
#FusionMex Content Workshop: Content Marketing in Practice, Antwerp June 10, ...
 
BHEL HARIDWAR VOCATIONAL TRAINING REPORT
BHEL HARIDWAR VOCATIONAL TRAINING REPORTBHEL HARIDWAR VOCATIONAL TRAINING REPORT
BHEL HARIDWAR VOCATIONAL TRAINING REPORT
 
Tapping Twitter! How to Target Your Audience For Job and Talent Search
Tapping Twitter! How to Target Your Audience For Job and Talent SearchTapping Twitter! How to Target Your Audience For Job and Talent Search
Tapping Twitter! How to Target Your Audience For Job and Talent Search
 
Tampax Puzzle
Tampax PuzzleTampax Puzzle
Tampax Puzzle
 
Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02
 
Api managers
Api managersApi managers
Api managers
 
Gobierno de apis
Gobierno de apisGobierno de apis
Gobierno de apis
 
Bhel turbine_shop_block-3
 Bhel turbine_shop_block-3 Bhel turbine_shop_block-3
Bhel turbine_shop_block-3
 
Twitter Smarter in 2016
Twitter Smarter in 2016 Twitter Smarter in 2016
Twitter Smarter in 2016
 

Similar to Ntpc 131113070238-phpapp02

Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil Singh
 
Ntpc power plant
Ntpc power plantNtpc power plant
Ntpc power plantNikesh Har
 
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...Navin Pathak
 
Vocational training report
Vocational training reportVocational training report
Vocational training reportATUL RAJ
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc reportravi kant
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc reportravi kant
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
rajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportrajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportRaj Sharma
 
Thermal power plant.pptx
Thermal power plant.pptxThermal power plant.pptx
Thermal power plant.pptxPranish Karn
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)abdul mohammad
 
Training reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishorTraining reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishorNAVAL KISHOR
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...haxxo24
 
kota super thermal power station
kota super thermal power stationkota super thermal power station
kota super thermal power stationdeeanshu
 

Similar to Ntpc 131113070238-phpapp02 (20)

ntpc
ntpcntpc
ntpc
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Ntpc report harsh
 
Ntpc power plant
Ntpc power plantNtpc power plant
Ntpc power plant
 
Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
 
steam turbine presentations
steam turbine presentationssteam turbine presentations
steam turbine presentations
 
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...
 
Vocational training report
Vocational training reportVocational training report
Vocational training report
 
report on VTPS
report on VTPSreport on VTPS
report on VTPS
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc report
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc report
 
CESC Report
CESC ReportCESC Report
CESC Report
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
rajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportrajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-report
 
Thermal power plant.pptx
Thermal power plant.pptxThermal power plant.pptx
Thermal power plant.pptx
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
Training reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishorTraining reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishor
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
 
kota super thermal power station
kota super thermal power stationkota super thermal power station
kota super thermal power station
 

More from k,l polytechnic roorkee

More from k,l polytechnic roorkee (9)

33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
220kV Grid Transmission Substation vt report
220kV Grid Transmission Substation vt report220kV Grid Transmission Substation vt report
220kV Grid Transmission Substation vt report
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
electronic communication
electronic communicationelectronic communication
electronic communication
 
TURBO GENERATOR
TURBO GENERATORTURBO GENERATOR
TURBO GENERATOR
 
Bhelparamjeet 121106032837-phpapp02 1-
Bhelparamjeet 121106032837-phpapp02 1-Bhelparamjeet 121106032837-phpapp02 1-
Bhelparamjeet 121106032837-phpapp02 1-
 
Apresentationonturbogeneratorandexcitor 1312012333
Apresentationonturbogeneratorandexcitor 1312012333Apresentationonturbogeneratorandexcitor 1312012333
Apresentationonturbogeneratorandexcitor 1312012333
 
Acelectricalgeneratorsasope 120408063101-phpapp01 (1)
Acelectricalgeneratorsasope 120408063101-phpapp01 (1)Acelectricalgeneratorsasope 120408063101-phpapp01 (1)
Acelectricalgeneratorsasope 120408063101-phpapp01 (1)
 
Bhel training report
Bhel training reportBhel training report
Bhel training report
 

Recently uploaded

Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Hyundai Motor Group
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 

Recently uploaded (20)

Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 

Ntpc 131113070238-phpapp02

  • 1. A TRAINING REPORT ON “THERMAL POWER PLANT” STUDENT’S NAME: PRATIK GUPTA COURSE: B.E. BRANCH: ELECTRICAL & ELECTRONICS YEAR/ SEM: 2ND /4TH COLLEGE: DR. C.V. RAMAN INSTITUTE OF SCIENCE & TECHNOLOGY, KOTA INDUSTRIAL NAME: SIPAT SUPER THERMAL POWER CORP. (NTPC SIPAT) SUBMITTED BY: SUBMITTED TO: PRATIK GUPTA MR. PRAVIN PATEL (EEE 4TH SEM) CERTIFICATE
  • 2. This is to certify that the project report entitled as NATIONAL THERMAL POWER PLANT has been done by PRATIK GUPTA during his vocational training period from 20-06-13 to 20-07-13 at “SIPAT SUPER THERMAL POWER PROJECT” is a record of studies, site experience and keen interest to the subject and analysis carried out by him under my supervision and guidance. This is a part of partial fulfilment of their vocational training programme. Guided by:- 1. MR. SHALABH SAHRMA 2. MR. J.P.Patel 3. MR. Dilip Khalatkar 4. MR. P.K. DAS DECLARATION
  • 3. The training work has been carried out and the report prepared by me during 20th June to 20th July 2013 under the guidance of faculties ntpc ltd/sipat thermal power plant and organised by employ development centre, human resource development. This is the original work carried out by me and not has been taken from any other sources nor been submitted to any institute or organisation as a fulfilment of any other curriculum. ACKNOWLEDGEMENT
  • 4. I hereby convey my deep and sincere gratitude in all humbleness to respected 5. MR. SHALABH SAHRMA 6. MR. J.P.Patel 7. MR. Dilip Khalatkar 8. MR. P.K. DAS Who provided me with an opportunity to learn under their gracious guidance, meticulous care and throughout the training. Their personal supervision and guidance has enabled me to complete this Project. I also thankfully acknowledgement the assistance received from MR PRAVIN PATEL and others for their co-operation during the preparation of this project report. The project report would not have been shaped in this form without their encouragement and guidance. Contents 1. Introduction of NTPC 2. Introduction about Project
  • 5. 3. Production of Electricity 4. Principal of Steam Power Plant 5. Coal Handling Plant 6. Coal Handling Plant Power Distribution 7. Demineral Plant(DM Plant) 8. Coal ,Water and Steam Cycle 9. H.T. Switch gear 10. L.T. Switch gear 11. Generators and Transformers 12. D.C. System 13. Switch Yard 14. Conclusion INTRODUCTION OF NTPC India’s largest power company, NTPC was set up in 1975 to accelerate power development in India. NTPC is emerging as a diversified power major with presence in the entire value chain of the power generation business. Apart from power generation, which is the mainstay of the company, NTPC has already ventured into consultancy, power trading, ash utilization and coal mining. NTPC ranked 337th in the ‘2012, Forbes Global 2000’ ranking of the World’s biggest
  • 6. companies. NTPC became a Maharatna company in May, 2010, one of the only four companies to be awarded this status. The total installed capacity of the company is 41,184 MW (including JVs) with 16 coal based and 7 gas based stations, located across the country. In addition under JVs, 7 stations are coal based & another station uses naptha/LNG as fuel and 2 renewable energy projects. The company has set a target to have an installed power generating capacity of 1,28,000 MW by the year 2032. The capacity will have a diversified fuel mix comprising 56% coal, 16% Gas, 11% Nuclear and 17% Renewable Energy Sources(RES) including hydro. By 2032, non fossil fuel based generation capacity shall make up nearly 28% of NTPC’s portfolio. NTPC has been operating its plants at high efficiency levels. Although the company has 17.75% of the total national capacity, it contributes 27.40% of total power generation due to its focus on high efficiency. In October 2004, NTPC launched its Initial Public Offering (IPO) consisting of 5.25% as fresh issue and 5.25% as offer for sale by Government of India. NTPC thus became a listed company in November 2004 with the Government holding 89.5% of the equity share capital. In February 2010, the Shareholding of Government of India was reduced from 89.5% to 84.5% through Further Public Offer. The rest is held by Institutional Investors and the Public.
  • 7. At NTPC, People before Plant Load Factor is the mantra that guides all HR related policies. NTPC has been awarded No.1, Best Workplace in India among large organizations and the best PSU for the year 2010, by the Great Places to Work Institute, India Chapter in collaboration with The Economic Times. The concept of Corporate Social Responsibility is deeply ingrained in NTPC's culture. Through its expansive CSR initiatives, NTPC strives to develop mutual trust with the communities that surround its power stations.
  • 8. INTRODUCTION ABOUT PROJECT Sipat Super Thermal Power Station is located at Sipat in Bilaspur district in state of Chhattisgarh. The power plant is one of the coal based power plants of NTPC. The coal for the power plant is sourced from Dipika Mines of South Eastern Coalfields Limited. The project has an installed capacity of 2980 MW consisting of two stages, stage one which got commissioned late was of 3 units of 660 MW each involving super-critical boilers technology and stage two consisted of 2 units of 500 MW each. Stage Unit Number Installed Capacity (MW) Date of Commissioning Status 1st 1 660 2011 June Running 1st 2 660 2011 December Running 1st 3 660 2012 June [1] Running 2nd 4 500 2007 May Running 2nd 5 500 2008 August Running Total Five 2980 Sipat Sipat' is a small developing town, approximately 22 kilometers away from Bilaspur, Chhattisgarh, the second largest city in Chhattisgarh. It has been in news due to setup of new power plant by NTPC Limited in that area. The project was started on 2001 by Indian former Prime Minister Mr. Atal Bihari Vajpayee.NTPC Sipat has total installed capacity of 2980 MW.NTPC Sipat has two stages: Stage-I comprises 3 units of 660MW each and Stage-II comprises 2 units of 500MW each. The thermal power generation in NTPC sipat Stage-II is based on "Super Critical Boiler Technology" which is the advanced technology in thermal power generation. NTPC Limited has helped this town in developing by providing business prospective in that area and by providing education, healthcare facilities.
  • 9. PRODUCTION OF ELECTRICITY The means and steps involved in the production of electricity in a coal-fired power station are described below. The coal, brought to the station by train or other means, travels from the coal handling plant by conveyer belt to the coal bunkers, from where it is fed to the pulverizing mills which grinds it as fine as face powder. The finely powdered coal mixed with pre-heated air is then blown into the boiler by fan called Primary Air Fan where it burns, more like a gas than as a solid in convectional domestic or industrial grate, with additional amount of air called secondary air supplied by Forced Draft Fan. As the coal has been grounded so finely the resultant ash is also a fine powder. Some of this ash binds together to form lumps which fall into the ash pits at the bottom of the furnace. The water quenched ash from the bottom of the furnace is conveyed to pits for subsequent disposal or sale. Most of ash, still in fine particles form is carried out of the boiler to the precipitators as dust, where it is trapped by electrodes charged with high voltage electricity. The dust is then conveyed by water to disposal areas or to bunkers for sale while the cleaned flue gases pass on through ID Fan to be discharged up the chimney. Meanwhile the heat released from the coal has been absorbed by the many kilometres of tubing which line the boiler walls. Inside the tubes is the boiler feed water which is transformed by the heat into the steam at high pressure and temperature. The steam super-heated in further tubes (Super Heater) passes to the turbine where it is discharged through the nozzles on the turbine blades. Just the energy of the wind turns the sail of the wind-mill, so the energy of the steam, striking the blades, makes the turbine rotate. Coupled to the end of the turbine is the rotor of the generator – a large cylindrical magnet, so that when the turbine rotates the rotor turns with it. The rotor is housed inside the stator having heavy coils of copper bars in which electricity is produced through the movement of the magnetic field created by the rotor. The electricity passes from the stator winding to the step-up transformer which increases its voltage so that it can be transmitted efficiently over the power lines of the grid.
  • 10. The steam which has given up its heat energy is changed back into water in the condenser so that it is ready for re-use. The condenser contains many kilometres of tubing through which the colder is constantly pumped. The steam passing around the tubes looses the heat and is rapidly changed back to water. But the two lots of water (i.e. boiler feed water & cooling water) must NEVER MIX. The cooling water is drawn from the river, but the boiler feed water must be absolutely pure, far purer than the water we drink, if it is not to damage the boiler tubes. Chemistry at the power station is largely the chemistry of water. To condense the large quantities of steam, huge and continuous volume of cooling water is essential. In most of the power stations the same water is to be used over and over again. So the heat which the water extracts from the steam in the condenser is removed by pumping the water out to the cooling towers. The cooling towers are simply concrete shells acting as huge chimneys creating a draught (natural/mechanically assisted by fans) of air. The water is sprayed out at the top of towers and as it falls into the pond beneath it is cooled by the upward draught of air. The cold water in the pond is then circulated by pumps to the condensers. Inevitably, however, some of the water is drawn upwards as vapours by the draught and it is this which forms the familiar white clouds which emerge from the towers seen sometimes. Why bother to change steam from the turbine back into water if it has to be heated up again immediately? The answer lies in the law of physics which states that the boiling point of water is related to pressure. The lower the pressure, the lower the temperature at which water boils. The turbine designer want as low boiling point of water as possible because he can only utilize the energy of the steam – when the steam changes back into water he can get NO more work out of it. So a condenser is built, which by rapidly changing the steam back into water creates a vacuum. This vacuum results in a much lower boiling point which, in turns, means he can continue getting work out of the steam well below 100 degree Celsius at which it would normally change into water.
  • 11. Principle of the Steam Power Plant The working principle of a steam plant is based upon the Rankine cycle. Generally steam is taken as the working medium due to its ability to be stable and that it’s readily stable. The flow of steam in the plant can be very easily be understood by the flow diagram of the plant. A graph plotted between the temperature and the entropy would indicate the technical details of the working by the rankine cycle. The entropy of a system can be understood as an index of degradation of energy. PLANT FLOW DIAGRAM COAL HANDLING PLANT Introduction: - NTPC SIPAT gets its coal supply mainly from dipka mines. The coal being filled in the wagons of the rail reaches plant. The purpose of this plant is to convey the coal to the bunker in the size not larger than 20mm.It handles and transports the coal to the bunker from the wagons by passing through various conveyors, transfer points, crusher houses, etc. Type of unloading the coal: - 1. Manual Unloading: -Previously, manpower was used for unloading the wagons. But it was very time consuming and more workers were required for the job to be done.
  • 12. 2. Box in (using wagon tippler for unloading): -For this method, Indian Railway grants 10 hours for unloading the 58 wagons. In this method, Wagons are separated and tippled by using wagon tippler. The Beetle Feeder is used to move the wagon on wagon tippler. The coal from the wagons gets accumulated in The Track Hopper. At this time; the size of the coal is approximately 300mm. 3. BOBR: - Indian Railway grants only 2.5 hours for Unloading 58 BOBR wagons. This is an advanced technology in which we use the compressor system. In Bottom Open Bottom Release (BOBR) technology the wagons are opened from side. Pressure is applied by the compressor to open the bottom gates of the wagon so that the coal gets released over the track hopper and wagon get unloaded quickly. Various equipment used in CHP: - 1. WAGON TIPPLER: - The wagon tippler is a most important device in thermal power project. The Wagon tippler turns back the wagon at 135-degree angle and the structure of the wagon tippler is to be very heavy. Upper side of the wagon is fixed with the many angles for supporting the wagon. When the wagon is fixed on the Platform then whole platform is turned back and the coal fall down in the wagon tippler hopper. The unloading time of the Rack is 6hours 2. PADDLE FEEDER: - They have been installed on conveyors below the manual unloading track hopper. There are 6 nos. of paddle feeders, 3 on each conveyer. 3 Paddle Feeders of each conveyer move to and fro within a limiting range. The rotating part of the paddle feeder is called as plough wheel. Plough wheel has 6 blades. By the rotation of the plough wheel, the coal of the track hopper gets accumulated between the blades and is discharged on the conveyor below it. 3. VIBRATING FEEDER: - They have been installed below the track hoppers of wagon tippler. The coal is accumulated over the vibrating feeder so by giving vibrations to the vibrating feeder we discharge the coal from track hopper to the conveyors. Their main purpose is to provide uniform feeding on the conveyors. The vibrating feeders consist of a tray to which vibrator body is fixed on the rear end. 4. TRANSFER POINTS: -Transfer Point is provided with flap gate and Conveyer. In transfer Point the coal is transferred from one conveyer to other conveyer. 5. PRIMARY CRUSHER (ROTARY BREAKER): - In Primary Crusher House, the coal breaks in Rotary Breaker. Here the coal comes from the Transfer point; breaks here and the stone fall down to a separate place. Coal is converted from 300mm to 150mm size. Part of the Primary Crusher House – a- Rotary Breaker b- Belt Feeder 6. SECONDARY CRUSHER (RING GRANULATOR): - In Secondary crusher House first the magnetic part separate from the coal and then feed to the Secondary Crusher. This Crusher breaks the coal in 20mm size and coal is sent to the Flap Gate and then feeded to the conveyer. The Secondary crusher is hammer type. H.T. motor are used for breaking of the coal. Specifications are 700KW 6.6KVMotor. 7. CROSS BELT MAGNETIC SEPRATORS: - They will remove the ferrous particles, which passes along with the coal. It consists of electromagnet around which a belt is moving. It is suspended from top, perpendicular to the conveyor belt at certain height. Whenever any iron particle
  • 13. passes below the CBMS, it is attracted by the magnet and stick to the cross belt below it. The CBMS capacity is of 50kg. 8. METAL DETECTOR: - The purpose of installation is to detect any metallic piece passing through the conveyor. Whenever the pieces pass below the search coil of the metal detector, it gives the trip command to the conveyor. Simultaneously, sand bag marker will fall on the conveyor belt so that the metal can be searched easily and removed. 9. STACKER/RECLAIMER: -It is a very important device. The whole Structure of it is called Super Structure. It stacks the excessive coal and reclaims the coal on its requirement. It is a two-way device. 10. TRANSFER TOWER: -Here the coal is send to the Tipper. Transfer Tower is provided with a coal sampler. 11. TIPPER: - The Tipper is a three-way device to feed the coal in Bunker. It is moveable device. It is move on its track. 12. BUNKER: - Here the coal is collected from the tipper and stored. The capacity of the bunker for Stage-I is 4800MT & Stage-II is 8700MT DEMINERAL (DM) PLANT INTRODUCTION: -- Water is required in plant for many purposes like for formation of steam, for removal of ash, for safety during fire, etc. But the water required for the formation of steam should be perfectly devoid of minerals because if minerals are present in the steam and the steam strike the blades of the turbine, then due to being high in pressure it produces scars or holes on the turbine blades. PURIFICATION OF WATER: - Water is purified in DM plant through a chain of processes as under: --
  • 14. 1. Carbon filter – Water taken from the river is first sent to the carbon filter for the removal of carbon contents in the water. 2. Strong acid cation exchanger – After passing through the carbon filter, water is sent to the strong acid cation exchanger, which is filled with the concentrated HCL. The acid produces anions, which get combined with the cations present in the water. 3. Strong base anion exchanger – After that the water is sent to the strong base anion exchanger, which is filled with the concentrated NaOH.The base produces cations, which get combined with the anions present in the water. 4. Mixed bed exchanger – And then water is sent to the chamber of mixed bed exchanger where the remaining ions are removed. This is the last stage of purification. COAL, WATER & STEAM CYCLES COAL CYCLE C.H.P Plant Bunker R.C Feeder Pulverization mill Boiler section 1. R.C Feeder: It is an induction motor driven device, which determine the Quantity of coal enter in the pulverize mill.
  • 15. 2. Pulverization mill: Pulverization means exposing a large surface area to the action of oxygen .Two Types of mill are used in the plant. 3. Ball mail: A ball mill operates normally under suction. A large drum partly filled with steel balls, is used in this mill .The drum is rotated slowly while coal is fed in to it .The ball pulverize the coal by crushing. 4. Contact mail: This mill uses impact principle. All the grinding elements and the primary air fan are mounted on a single shaft. The flow of air carries coal to the primary stage where it is reduced to a fine granular state by impact with a series of hammers. WATER CYCLE D.M Plant Hot well C.E.P Pump Low Pressure Heater 1, 2, 3 Derater Boiler Feed Pump High Pressure Heater 5, 6 Feed Regulating station Economizer Boiler Drum 1. DERATER: Feed strong tank of water. To produce sufficient pressure before feeding to B.F.D. .Filter the harmful chemicals. 2. FEED REGULATING STATIONS: Control the quantity of water in to boiler drum. 3. ECONOMISER: Flux gases coming out of the boilers carry lot of heat. An economizer extracts a part of this heat from the flue gases and uses it for heating the feed water. 4.DRAFTS SYSTEM: In forced draft system the fan is installed near the base of the boiler furnace. This fan forces air through the furnace, economizer, air preheater and chimney. In an induced draft system, the fan is installed near the base of Chimney. STEAM CYCLE Boiler Drum Ring Header Boiler Drum (Steam chamber) Super Heater H.P Turbine Repeater I.P Turbine L.P Turbine condenser 1. BOILER: Boiler drum consists two chambers water chamber, steam chamber. Before Entering in super heater the steam is going in to boiler drum, where the boiler drum filtered the moisture and stored in to water chamber. 2. SUPER HEATER: The function of super heater is to remove the last traces of moisture from the saturated steam leaving the tube boiler. The temperature is approx.530 o C.
  • 16. 3. TURBINE: Steam turbine converts the heat energy in to mechanical energy and drives the alternator. The velocity attained during expansions depends on initial and final heat content of the steam. Turbine having number of stages in which the pressure drops takes place. H.T.SWITCH GEAR OPERATIONG VOLTAGE - 6.6KV For low voltage circuits fuses may be used to isolate the faulty circuit. For voltage higher than 3.3 kV isolation is achieved by circuit breaker.
  • 17. Requirement of circuit breaker: 1. After occurrence of fault the switchgears must isolate the faulty circuit as quickly as possible i.e. keeping the delay to minimum. 2. It should not operate when an over current flows under healthy condition. Basic principal of operation of circuit breaker: Circuit breaker consists of a fix contact and sliding contact into which moves a moving contact. The end of moving contact it attached to a handle that can be manually operated or may operate automatically with the help of mechanism that has a trip coil energized by secondary of CT. Under normal condition the secondary of CT is not energized sufficiently to trip the coil but under false condition the coil is energized fully to operate the trip coil and the circuit breaker is operated. 1. MOCB (Minimum oil circuit breaker) 2. SF6 (Sulphur hexafluoride circuit breaker) Here oil and SF6 are used to quench the arc.
  • 18. L.T SWITCH GEAR OPERATING VOLTAGE- 415VOLT TYPES OF CIRCUIT BREAKER: - Air break circuit breaker Air brake circuit breaker: The arc interruption process of air- based circuit breaker is based on the natural deionization of gases by cooling action. The arc is resilient and can be stretched, and has a resistance, which can be increased both by length and confinement. Hence the arc resistance is increased by stretching the arc and as the resistance increases to higher value, the short circuit current drops to zero and arc is extinguished. Reducing the phase difference between the system voltage and the short circuit current assure that when the are current is interrupt at its zero value, the recovery voltage has very low value at its not allowed to reach 2-3 times the value of the system peak voltage, a phenomenon that occurs in most cases, when arc current is interrupted at low power factor.
  • 19. GENERATORS AND TRANSFORMERS INTRODUCTION- The auxiliaries in a plant can be divided into two categories- 1. URGENT AUXILIARIES- the urgent auxiliaries are those, which are associated with running of unit. 2. SERVICE AUXILIARIES- the service auxiliaries are those whose loss would not affect output. GENERATOR SPECIFICATIONS- TURBO GENERATOR (gen1, gen2) KVA 247000 Pf 0.85 Volts of stator 15750 Amperes of stator 9050 Volts of rotor 310 Amperes of rotor 2600 Rpm 3000 Hz 50 Phase 3 Connection YY Coolant Water (stator)& hydrogen (rotor) Gas pressure 3.5kg/cm-sq. Insulation class B
  • 20. EXCITATION SYSTEM- 1. STATIC EXCITATION SYSTEM-The generators in stage -1(u-1&u-2) have this excitation system. Static excitation system has slip ring and carbon brush arrangement. It consists of step down transformer, converter and AVR (automatic voltage regulator). 2. BRUSHLESS EXCITATION SYSTEM –The generators in stage -2(U-3, U-4& &U- 5) have this excitation system. It has two exciters, one is main exciter and other is pilot exciter. GENERATOR PROTECTION- 1. STATOR PROTECTION- The neutral of star connected winding is connected to primary of neutral grounding transformer, so that earth fault current is limited by over voltage relay. 2. DIFFERENTIAL PROTECTION- In case of phase-to-phase fault generator is protected by longitudinal differential relay. 3. ROTOR PROTECTION- Rotor winding may be damaged by earth faults or open circuits. The field is biased by a dc voltage, which causes current to flow through the relay for an earth fault anywhere on the field system. 4. OVER SPEED PROTECTION – Mechanically over speed device that is usually in the form of centrifugally operated rings mounted on the rotor shaft, which fly out and close the stop valves if the speed of the set increase more than 10%. 5. OVER VOLTAGE PROTECTION – It is provided with an over voltage relay. The relay is usually induction pattern. The relay open the main circuit break and the field switch if the over voltage persists. 6. SEAL OIL SYSTEM – Hydrogen in the generator is under very high pressure. There is a possibility of this hydrogen to come out of gaps, which is very hazardous. So, seal oil is used to seal the gaps so that hydrogen doesn’t come out. 7. LUBRICATION OIL SYSTEM –Turbine lubrication-oil system seeks to provide proper lubrication of turbo generator bearings and operation of barring gear. Pumps are used to circulate lubrication-oil inside the generator. The oil of the lubrication and the governing system is cooled in the oil coolers. The cooling medium for these coolers is circulating water.
  • 21. TRANSFORMER TYPE PF TRANSFORMERS— 1. UNIT AUXILIARY TRANSFORMER: --This is a step down transformer. The primary receives from generator and secondary supplies a 6.6 KV bus. This is oil cooled. These are 8 in number. 2. NEUTRAL GROUNDED TRANSFORMER: --This transformer is connected with supply coming out of UAT in stage-2. This is used to ground the excess voltage if occurs in the secondary of UAT in spite of rated voltage. 3. GENRATOR TRANSFORMER: -- This is a step up transformer. This supply gets its primary Supply from generator and its secondary supplies the switchyard from where it is transmitted to grid. This transformer is oil cooled. The primary of this transformer is connected in star. The secondary is connected in delta. These are four in number. 4. STATION TRANSFORMER: --This transformer has almost the same rating as the generator transformer. Its primary is connected in delta and secondary in star. It is a step down transformer. These are 4 in number. SPECIFICATIONS Generator transformer (GT-1 & GT-2) KV 15.75/242 MVA 250 Phase 3 Hz 50 Connections Y-D 11 Type of cooling OFAF/ONAF/ONAN Rated HV and IV (MVA) 250/150/100 Rated LV (MVA) 250/150/100 No Load Voltage HV (KV) 242 No Load Voltage IV (KV) No Load Voltage LV (KV) 15.75 Line current HV (Amps) 597.14/358.29/238.86
  • 22. Line current IV (Amps) Line current LV (Amps) 9175.15/5505.09/3670.66 Temp rise coil o C 50 Temp rise winding o C 55 Neural grounded transformer (NGT) KVA 1150 Phase 3 Hz 50 Type of cooling ONAF/ONAN No load voltage HV (volts) 6600 No load voltage LV (volts) 250 Line current HV (Amps) 105.9 Line current LV (Amps) 2655.8 Temp rise oil o C 50 Temp rise winding 55 Potential Transformer KVA 1000 Phase 3 Hz 50 Type of Cooling ONAN No Load Voltage HV (volts) 6600 No Load Voltage LV (volts) 433 Line Current HV (Amps) 87.53 Line Current LV (Amps) 133.5 Temp rise oil o C 50 Temp rise winding o C 55
  • 23. D.C SYSTEM INTRODUCTION: DC system is generally used for control and protection operation, as AC supply is not fully dependable. To maintain constant supply in case of power failure we use DC supply. DC system consists of a battery charger. These are the mode of energy storage. CHARGING EQUIPMENTS: The battery charging equipment comprises of trickle charger, quick charger, battery panel, main distribution board and switch control and signaling board. CHARGING EQUATION: In battery PbO2 used as positive plate and Pb as negative plate. 1. DISCHARGING PROCESS 2. CHARGING PROCESS BATTERY CHARGER: Battery charger normally operates in two modes. 1. Float charging: It is constant voltage mode and works as a trickle charger. 2. Boost charging: It is constant current mode and works as a quick charger. TRICKLE CHARGER: This charger is fed from three-phase ac supply and gives a dc-stabilized output at rated full load current. The variation of the dc output voltage is limited to +/- 1% for 0 to 100% load variation and simultaneously ac voltage variation of +/- 10% of frequency variation of +/- 5% from 50 Hz. The rectification is obtained through full bridge controlled silicon rectifier. Stack comprising of these SCR and three diode with the surge suppression RC network connected across each SCR and diode.
  • 24. SWITCH YARD As we know that electrical energy can’t be stored like cells, so what we generate should be consumed instantaneously. But as the load is not constants therefore we generate electricity according to need i.e. the generation depends upon load. The yard is the places from where the electricity is send outside. It has both outdoor and indoor equipments. SINGLE LINE DIAGRAM OF 220KV SWITCH YARD- OUTDOOR EQUIPMENTS 1. BUS BAR 2. LIGHTENING ARRESTER 3. WAVE TRAP 4. BREAKER 5. CAPACITOR VOLTAGE TRANSFORMER 6. CORONA RING 7. EARTHING ROD 8. CURRENT TRANSFORMER INDOOR EQUIPMENTS 1. RELAYS 2. CONTROL PANELS
  • 25. 9. POTENTIAL TRANSFORMER 10. LIGHTENING MASK 11. LIGHTENING MOOSE CIRCUIT BREAKER: The code for circuit breaker is 52. An electric power system needs some form of switchgear in order to operate it safely & efficiently under both normal and abnormal conditions. Circuit breaker is an arrangement by which we can break the circuit or flow of current. A circuit breaker in station serves the same purpose as switch but it has many added and complex features. The basic construction of any circuit breaker requires the separation of contact in an insulating fluid that servers two functions: 1. It extinguishes the arc drawn between the contacts when circuit breaker opens. 2. It provides adequate insulation between the contacts and from each contact to earth. The insulating fluids commonly used in circuit breakers are: 1. Compressed air 2. Oil which produces hydrogen for arc excitation. 3. Ultra high vacuum 4. Sulphur hexafluorides The Specifications of the circuit breaker used are:
  • 26. LIGHTING ARRESTER: It saves the transformer and reactor from over voltage and over currents. We have to use the lightning arrester both in primary and secondary of transformer and in reactors. A meter is provided which indicates the surface leakage and internal grading current of arrester. 1. Green – arrester is healthy 2. Red – arrester is defective. In case of red we first de-energize the arrester and then do the operation. AIR BREAK EARTHING SWITCH: The code of earthling switch is 5, 6, 7.The work of this equipment comes into picture when we want to shut down the supply for maintenance purpose. This help to neutralize the system from induced voltage from extra high voltage. This induced power is up to 2KV in case of 400 KV lines. The specification of earthling switch is: MAKE S & S POWER TYPE MADRAS VOLTAGE 245 KV CURRENT 10 KA MOTOR VOLT (AC) 415 VOLTS CONTROL VOLT (DC) 220 VOLTS MAKE CROMPTON GREAVES LTD. TYPE AIR BLAST CIRCUITREAKER RATED VOLTAGE 245 KV RATED LIGHTING IMPULSE WITHSTAND VOLTAGE 1050 KV RATED SHORT CIRCUIT BREAKING CURRENT 25 - 40KA RATED FREQUENCY 50HZ RATED NORMAL CURRENT 2000 A TO 4000 A RATED CLOSING VOLTAGE 220 V DC RATED OPENING VOLTAGE 220 V DC
  • 27. BUS BAR: Bus bars generally are of high conductive aluminum conforming to IS-5082 or copper of adequate cross section .Bus bar located in air –insulated enclosures & segregated from all other components .Bus bar is preferably cover with polyurethane. 1. Current Transformer (CT): A current transformer is a type of instrument transformer designed to provide a current in its secondary winding proportional to the alternating current flowing in its primary . Current Transformer Diagram Application: 1. They are commonly used in metering and protective relaying in the electrical power industry where they facilitate the safe measurement of large currents, often in the presence of high voltages. 2. The current transformer safely isolates measurement and control circuitry from the high voltages typically present on the circuit being measured. 3. Current transformers are used extensively for measuring current and monitoring the operation of the power grid. The CT is typically described by its current ratio from primary to secondary. Often, multiple CTs are installed as a "stack" for various uses (for example, protection devices and revenue metering may use separate CTs). Similarly potential transformers are used for measuring voltage and monitoring the operation of the power grid. 4. Capacitive Voltage Transformer (CVT): A capacitor voltage transformer (CVT) is a transformer used in power systems to step-down extra high voltage signals and provide low voltage signals either for measurement or to operate a protective relay. In its most basic form the device consists of three parts: two capacitors across which the voltage signal is split, an inductive element used to tune the device to the supply frequency and a transformer used to isolate and further step-down the voltage for the instrumentation or protective relay as shown in figure below.
  • 28. The device has at least four terminals, a high-voltage terminal for connection to the high voltage signal, a ground terminal and at least one set of secondary terminals for connection to the instrumentation or protective relay. CVTs are typically single-phase devices used for measuring voltages in excess of one hundred kilovolts where the use of voltage transformers would be uneconomical. In practice the first capacitor, C1, is often replaced by a stack of capacitors connected in series.This results in a large voltage drop across the stack of capacitors that replaced the first capacitor and a comparatively small voltage drop across the second capacitor C2, and hence the secondary terminals. Conclusion On completion of my vocational training at Feroze Gandhi Unchahar Thermal Power Project, Unchahar I have come to know about how the very necessity of our lives nowadays i.e., electricity is generated. What all processes are needed to generate and run the plant on a 24x7 basis. NTPC Unchahar is one the plants in India to be under highest load factor for the maximum duration of time and that to operating at highest plant efficiencies. This plant is an example in terms of working efficiency and management of resources to all other thermal plants in our country. The operating plf of the NTPC as compared to the rest of country is the highest with 87.54% the highest since its inception. The training gave me an opportunity to clear my concepts from practical point of view with the availability of machinery of such large rating.