SlideShare a Scribd company logo
TEMPORARY SITE CABLES
KEEPING ELECTRICITY
AVAILABLE
exa n s
THE FLEXIBILITY TO ACT
MORE QUICKLY
Construction within
substations
•	 Ideal tool for installing temporaries in transformer 		
	substations
• 	Reducing the disconnecting times of transmission 		
	 lines during conversion
• 	Flexible terminations can be installed quickly and in 	
	 a small space
• 	The cables can be rechecked for partial discharge 		
	 after beeing used
Replacing temporary
overhead lines
• 	Replacing the temporary installation of overhead 		
	lines
• 	Provisional connection of existing overhead lines if 		
	 new ones have to cross
• 	Depending on length required, the cables will be 		
	 simply rolled out and connected
• 	Reduce risk of recourse claims
The construction of new power plants and the growing demand for renewable energy sources has increased
the need to expand and/or convert networks into transformer substations or onto overhead line towers.
As a key player in the energy industry, Nexans is pleased to offer a safe and flexible component for such
projects – pre terminated temporary site cables. These cables can be used to temporarily connect equipment
in a high voltage network, e.g. as a bypass during construction or repair and servicing work, or during
emergencies such as natural disasters or severe weather. When faults occur in overhead or underground
lines, temporary site cables make it possible to restore energy transmission rapidly. While modification work
is underway in a transformer station, temporary connections can be rapidly installed between transformers
and switchgear systems or overhead lines.
Temporary site cables are available from stock or can be manufactured to meet your specific requirements.
PERFECT SOLUTION FOR TEMPORARY USE
At home, at work,
out and about –
there is no life without electrical energy. Electricity is
available at any time; this goes without saying. To ensure
that this remains the case, overhead lines and transformer
substations must always be ready for operation, even if
the transmission grids have to be adapted. Temporary site
cables are perfect for reducing the disconnecting times
of transmission paths during conversion. The cables are
a practical and simple solution as they make it easier
modernize switching sections in substations.
BENEFITS FOR CUSTOMERS
Temporary site cables have
the same design as high
voltage cables but with a
reduced insulation thickness.
This makes them easier to
handle on the construction
site. The cables have a
standardized conductor
cross section of 150 mm2
(300 kcmil) or 300 mm2
(600 kcmil). Depending on customer
requirements, the length can vary between 50 m (65 ft) and
500 m (1640 ft) or more. They are delivered on a special
single chamber or three chamber drum. This special drum
design facilitates safe winding and unwinding of the cable
and the pre-installed terminations.
DESIGN
In case of emergencies
• 	Can be used immediately
• 	The energy supply can be quickly restored, even in
	 emergencies and malfunctions
• 	Can be installed regardless of weather conditions 		
	 including friged temperatures
• 	Temporary site 	cables are save and easy to use and 	
	 secure the supply
Pre-installed flexible silicone rubber
terminations for easy handling
Due to the conditions under which temporary site cables
are installed, the accessories must be easy to use and
have a wide range of possible applications. Nexans’
pre-installed flexible silicone rubber terminations
facilitate use in any position. Thanks to their low weight,
the terminations can operate without any additional
support structures. Their monobloc design makes the
terminations suitable for all voltages from 72.5 kV to
230 kV and up to 750 A per system. Two systems in
parallel double capacity to 1500 A. This setup offers
maximum flexibility and operational reliability.
Advantages of temporary
site cables and accessories
•	Optimized cable design for small bending radii
•	Reduced insulation thickness in order to reduce 		
	 weight and to improve handling
•	The pre-installed silicone rubber terminations are
	 maintenance free and routine tested for partial 		
	 discharge up to a test voltage of 2.5 x U0
. Following 	
	 every use, a new partial discharge measurement 		
	 can be performed on the cables in order to rule out 		
	 possible damage.
•	Special single or three chamber drums make
	 transportation and handling much easier
Mr. Schindelbauer:
Westnetz
„The disconnect times of the
electrical systems are frequently
only short and timed Precisely.
It is a major advantage here
that temporary site cables can
be installed regardless of the
weather Conditions as well as
at minus temperatures.“
„Thanks to their ease of use,
temporary site cables allow the
supply to be restored quickly
and safely if faults arise
in the grid or transformer
station.“
REFERENCES
ACTUAL REFERENCE LIST AVAILABLE UPON REQUEST
Nexans Deutschland GmbH
Land High Voltage Contracting
Kabelkamp 20 · 30179 Hannover · Tel. +49 511 676-3364 · Fax +49 511 676-2254
eMail: hv-team.nd@nexans.com · www.nexans.com
exa n s
Global expert in cables and cabling systems
About Nexans
Nexans brings energy to life through an extensive range of cables and cabling
solutions that deliver increased performance for our customers worldwide. Nexans’
teams are committed to a partnership approach that supports customers in four main
business areas: Power transmission and distribution (submarine and land), Energy
resources (Oil & Gas, Mining and Renewables), Transportation (Road, Rail, Air, Sea)
and Building (Commercial, Residential and Data Centers). Nexans’ strategy is founded
on continuous innovation in products, solutions and services, employee development,
customer training and the introduction of safe, low -environmental- impact industrial
processes.
More information on www.nexans.com
November2015·Copyright©NEXANS

More Related Content

What's hot

Electrical wiring BY Jemish
Electrical wiring BY JemishElectrical wiring BY Jemish
Electrical wiring BY Jemish
Goti Jemish
 
Electrical System Design
Electrical System Design Electrical System Design
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
vishalgohel12195
 
Underground cables
Underground cablesUnderground cables
Underground cables
Jatinder Singh
 
Building electric circuit
Building electric circuitBuilding electric circuit
Building electric circuit
eddie fonte
 
Electrical Systems in a Building
Electrical Systems in a BuildingElectrical Systems in a Building
Electrical Systems in a Building
GAURAV. H .TANDON
 
ppt on fuse by madhav chhabra
ppt on fuse by madhav chhabrappt on fuse by madhav chhabra
ppt on fuse by madhav chhabraMadhav Chhabra
 
Hospital wiring SYSTEM
Hospital wiring SYSTEMHospital wiring SYSTEM
Hospital wiring SYSTEM
AISWARYA TV
 
Distribution boards & switch gears by v guard
Distribution boards & switch gears by v guardDistribution boards & switch gears by v guard
Distribution boards & switch gears by v guard
V-GUARD INDUSTRIES LTD
 
Transmission lines of Electrical powe
Transmission lines of Electrical poweTransmission lines of Electrical powe
Transmission lines of Electrical powe
Darya khan
 
Mechanical Design of Overhead Lines
Mechanical Design of Overhead LinesMechanical Design of Overhead Lines
Mechanical Design of Overhead Lines
Ranjeet Kumar
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
ahmed usama
 
Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)Ritesh Ambadkar
 
Electrical services
Electrical servicesElectrical services
Electrical services
Piyush Purshottam Lalwani
 
Choosing Electrical Panels
Choosing Electrical PanelsChoosing Electrical Panels
Choosing Electrical Panels
BKElectrianServices
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
Apurva Parikh
 
insulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motorsinsulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motors
Chippa Srikanth
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2

What's hot (20)

Electrical wiring BY Jemish
Electrical wiring BY JemishElectrical wiring BY Jemish
Electrical wiring BY Jemish
 
Electrical System Design
Electrical System Design Electrical System Design
Electrical System Design
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
 
Insulators
InsulatorsInsulators
Insulators
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Building electric circuit
Building electric circuitBuilding electric circuit
Building electric circuit
 
Electrical Systems in a Building
Electrical Systems in a BuildingElectrical Systems in a Building
Electrical Systems in a Building
 
ppt on fuse by madhav chhabra
ppt on fuse by madhav chhabrappt on fuse by madhav chhabra
ppt on fuse by madhav chhabra
 
Hospital wiring SYSTEM
Hospital wiring SYSTEMHospital wiring SYSTEM
Hospital wiring SYSTEM
 
Distribution boards & switch gears by v guard
Distribution boards & switch gears by v guardDistribution boards & switch gears by v guard
Distribution boards & switch gears by v guard
 
Transmission lines of Electrical powe
Transmission lines of Electrical poweTransmission lines of Electrical powe
Transmission lines of Electrical powe
 
Mechanical Design of Overhead Lines
Mechanical Design of Overhead LinesMechanical Design of Overhead Lines
Mechanical Design of Overhead Lines
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
 
Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)
 
Electrical services
Electrical servicesElectrical services
Electrical services
 
Choosing Electrical Panels
Choosing Electrical PanelsChoosing Electrical Panels
Choosing Electrical Panels
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
 
insulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motorsinsulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motors
 
ELECTRICAL WIRING
ELECTRICAL WIRINGELECTRICAL WIRING
ELECTRICAL WIRING
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2
Eat105 chapter 2
 

Viewers also liked

Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable TerminationsPfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Thorne & Derrick International
 
Cablesafe Cable Hooks - Presentation
Cablesafe Cable Hooks - PresentationCablesafe Cable Hooks - Presentation
Cablesafe Cable Hooks - Presentation
Thorne & Derrick International
 
Perennial Dilemmas in English Education
Perennial Dilemmas in English EducationPerennial Dilemmas in English Education
Perennial Dilemmas in English Education
Diane Phelps, PhD
 
Hans schaffers smartcities
Hans schaffers smartcitiesHans schaffers smartcities
Hans schaffers smartcities
European Network of Living Labs (ENoLL)
 
Pozoblanco Patricia Molina Palma
 Pozoblanco Patricia Molina Palma  Pozoblanco Patricia Molina Palma
Pozoblanco Patricia Molina Palma iesalonsocano
 
POSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_BiharPOSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN
 
KQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalKQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalBrent Keeter
 
Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...TBEX
 
Informe semestral ene octubre 2015 proyectos promovidos.
Informe  semestral ene octubre 2015 proyectos promovidos.Informe  semestral ene octubre 2015 proyectos promovidos.
Informe semestral ene octubre 2015 proyectos promovidos.
Hermel Cabrera
 
Pathways and Signposts
Pathways and SignpostsPathways and Signposts
Pathways and Signposts
Tony Crispino
 
Couponomy handout
Couponomy handoutCouponomy handout
Couponomy handout
Mike Taylor
 
ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness?  ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness?
Eva Do
 
Linked Data Experiences at Springer Nature
Linked Data Experiences at Springer NatureLinked Data Experiences at Springer Nature
Linked Data Experiences at Springer Nature
Michele Pasin
 
Rryma elektrike
Rryma elektrikeRryma elektrike
Rryma elektrike
flori daut
 
Solving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing ChallengesSolving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing Challenges
eMarketing Strategy
 
Sources of electricity маслей дарья блажковавероника 10 кл
Sources of electricity маслей дарья  блажковавероника 10 клSources of electricity маслей дарья  блажковавероника 10 кл
Sources of electricity маслей дарья блажковавероника 10 клVictorushka
 
El camino del héroe clase 1
El camino del héroe   clase 1El camino del héroe   clase 1
El camino del héroe clase 1
cursavirtual
 

Viewers also liked (20)

Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable TerminationsPfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
 
Cablesafe Cable Hooks - Presentation
Cablesafe Cable Hooks - PresentationCablesafe Cable Hooks - Presentation
Cablesafe Cable Hooks - Presentation
 
Perennial Dilemmas in English Education
Perennial Dilemmas in English EducationPerennial Dilemmas in English Education
Perennial Dilemmas in English Education
 
Hans schaffers smartcities
Hans schaffers smartcitiesHans schaffers smartcities
Hans schaffers smartcities
 
IPTeL Overview
IPTeL OverviewIPTeL Overview
IPTeL Overview
 
Pozoblanco Patricia Molina Palma
 Pozoblanco Patricia Molina Palma  Pozoblanco Patricia Molina Palma
Pozoblanco Patricia Molina Palma
 
POSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_BiharPOSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_Bihar
 
KQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalKQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinal
 
Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...
 
Informe semestral ene octubre 2015 proyectos promovidos.
Informe  semestral ene octubre 2015 proyectos promovidos.Informe  semestral ene octubre 2015 proyectos promovidos.
Informe semestral ene octubre 2015 proyectos promovidos.
 
Detection of vulnerable plaque by nis
Detection of vulnerable plaque by nisDetection of vulnerable plaque by nis
Detection of vulnerable plaque by nis
 
Pathways and Signposts
Pathways and SignpostsPathways and Signposts
Pathways and Signposts
 
Couponomy handout
Couponomy handoutCouponomy handout
Couponomy handout
 
ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness?  ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness?
 
Lactancia Materna
Lactancia MaternaLactancia Materna
Lactancia Materna
 
Linked Data Experiences at Springer Nature
Linked Data Experiences at Springer NatureLinked Data Experiences at Springer Nature
Linked Data Experiences at Springer Nature
 
Rryma elektrike
Rryma elektrikeRryma elektrike
Rryma elektrike
 
Solving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing ChallengesSolving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing Challenges
 
Sources of electricity маслей дарья блажковавероника 10 кл
Sources of electricity маслей дарья  блажковавероника 10 клSources of electricity маслей дарья  блажковавероника 10 кл
Sources of electricity маслей дарья блажковавероника 10 кл
 
El camino del héroe clase 1
El camino del héroe   clase 1El camino del héroe   clase 1
El camino del héroe clase 1
 

Similar to Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132kV & 220kV

Conductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview CablesConductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview Cables
Thorne & Derrick International
 
How expulsion fuses enhance
How expulsion fuses enhanceHow expulsion fuses enhance
How expulsion fuses enhance
COMPAQ INTERNATIONAL (P) LIMITED
 
Sam cables presentation
Sam cables presentation Sam cables presentation
Sam cables presentation
Ankit Joshi
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
ashwini kumar
 
cables.pptx
cables.pptxcables.pptx
cables.pptx
MadhusmitaMohanty29
 
InnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductorInnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductorJorge Cofr
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
ayazkhan261
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
ayazkhan261
 
Gagan
GaganGagan
3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations
Thorne & Derrick International
 
Ca vd4 50k-a(en)y_1vcp000001
Ca vd4 50k-a(en)y_1vcp000001Ca vd4 50k-a(en)y_1vcp000001
Ca vd4 50k-a(en)y_1vcp000001
BeimarHerediaSaigua1
 
Nexans WINDLINK Cable Solutions For Wind Turbines
Nexans WINDLINK Cable Solutions For Wind TurbinesNexans WINDLINK Cable Solutions For Wind Turbines
Nexans WINDLINK Cable Solutions For Wind Turbines
Thorne & Derrick International
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
Praveen Sharma
 
Flexible Cables Solution
Flexible Cables SolutionFlexible Cables Solution
Flexible Cables Solution
prysmianaus
 
Wiring system building services
Wiring system building servicesWiring system building services
Wiring system building services
ManishaBisht26
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiring
Abhidada123
 
Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143
sanjeet kumar
 
Extra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptxExtra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptx
AnirbanSarkar943417
 
8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx
PTD QUYCOCTU
 

Similar to Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132kV & 220kV (20)

Conductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview CablesConductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview Cables
 
Gis4
Gis4Gis4
Gis4
 
How expulsion fuses enhance
How expulsion fuses enhanceHow expulsion fuses enhance
How expulsion fuses enhance
 
Sam cables presentation
Sam cables presentation Sam cables presentation
Sam cables presentation
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
 
cables.pptx
cables.pptxcables.pptx
cables.pptx
 
InnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductorInnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductor
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
 
Gagan
GaganGagan
Gagan
 
3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations
 
Ca vd4 50k-a(en)y_1vcp000001
Ca vd4 50k-a(en)y_1vcp000001Ca vd4 50k-a(en)y_1vcp000001
Ca vd4 50k-a(en)y_1vcp000001
 
Nexans WINDLINK Cable Solutions For Wind Turbines
Nexans WINDLINK Cable Solutions For Wind TurbinesNexans WINDLINK Cable Solutions For Wind Turbines
Nexans WINDLINK Cable Solutions For Wind Turbines
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 
Flexible Cables Solution
Flexible Cables SolutionFlexible Cables Solution
Flexible Cables Solution
 
Wiring system building services
Wiring system building servicesWiring system building services
Wiring system building services
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiring
 
Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143
 
Extra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptxExtra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptx
 
8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx
 

More from Thorne & Derrick International

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
Thorne & Derrick International
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
Thorne & Derrick International
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
Thorne & Derrick International
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
Thorne & Derrick International
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
Thorne & Derrick International
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
Thorne & Derrick International
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Thorne & Derrick International
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
Thorne & Derrick International
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Thorne & Derrick International
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
Thorne & Derrick International
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
Thorne & Derrick International
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
Thorne & Derrick International
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick International
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
Thorne & Derrick International
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
Thorne & Derrick International
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
Thorne & Derrick International
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
Thorne & Derrick International
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Thorne & Derrick International
 

More from Thorne & Derrick International (20)

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
Itron Fact Sheet
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
 

Recently uploaded

PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
Assure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyesAssure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdfSAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
Peter Spielvogel
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
nkrafacyberclub
 
Quantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIsQuantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIs
Vlad Stirbu
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Nexer Digital
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
RinaMondal9
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
mikeeftimakis1
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 

Recently uploaded (20)

PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
Assure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyesAssure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyes
 
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdfSAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
 
Quantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIsQuantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIs
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 

Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132kV & 220kV

  • 1. TEMPORARY SITE CABLES KEEPING ELECTRICITY AVAILABLE exa n s
  • 2. THE FLEXIBILITY TO ACT MORE QUICKLY Construction within substations • Ideal tool for installing temporaries in transformer substations • Reducing the disconnecting times of transmission lines during conversion • Flexible terminations can be installed quickly and in a small space • The cables can be rechecked for partial discharge after beeing used Replacing temporary overhead lines • Replacing the temporary installation of overhead lines • Provisional connection of existing overhead lines if new ones have to cross • Depending on length required, the cables will be simply rolled out and connected • Reduce risk of recourse claims The construction of new power plants and the growing demand for renewable energy sources has increased the need to expand and/or convert networks into transformer substations or onto overhead line towers. As a key player in the energy industry, Nexans is pleased to offer a safe and flexible component for such projects – pre terminated temporary site cables. These cables can be used to temporarily connect equipment in a high voltage network, e.g. as a bypass during construction or repair and servicing work, or during emergencies such as natural disasters or severe weather. When faults occur in overhead or underground lines, temporary site cables make it possible to restore energy transmission rapidly. While modification work is underway in a transformer station, temporary connections can be rapidly installed between transformers and switchgear systems or overhead lines. Temporary site cables are available from stock or can be manufactured to meet your specific requirements. PERFECT SOLUTION FOR TEMPORARY USE At home, at work, out and about – there is no life without electrical energy. Electricity is available at any time; this goes without saying. To ensure that this remains the case, overhead lines and transformer substations must always be ready for operation, even if the transmission grids have to be adapted. Temporary site cables are perfect for reducing the disconnecting times of transmission paths during conversion. The cables are a practical and simple solution as they make it easier modernize switching sections in substations. BENEFITS FOR CUSTOMERS
  • 3. Temporary site cables have the same design as high voltage cables but with a reduced insulation thickness. This makes them easier to handle on the construction site. The cables have a standardized conductor cross section of 150 mm2 (300 kcmil) or 300 mm2 (600 kcmil). Depending on customer requirements, the length can vary between 50 m (65 ft) and 500 m (1640 ft) or more. They are delivered on a special single chamber or three chamber drum. This special drum design facilitates safe winding and unwinding of the cable and the pre-installed terminations. DESIGN In case of emergencies • Can be used immediately • The energy supply can be quickly restored, even in emergencies and malfunctions • Can be installed regardless of weather conditions including friged temperatures • Temporary site cables are save and easy to use and secure the supply Pre-installed flexible silicone rubber terminations for easy handling Due to the conditions under which temporary site cables are installed, the accessories must be easy to use and have a wide range of possible applications. Nexans’ pre-installed flexible silicone rubber terminations facilitate use in any position. Thanks to their low weight, the terminations can operate without any additional support structures. Their monobloc design makes the terminations suitable for all voltages from 72.5 kV to 230 kV and up to 750 A per system. Two systems in parallel double capacity to 1500 A. This setup offers maximum flexibility and operational reliability. Advantages of temporary site cables and accessories • Optimized cable design for small bending radii • Reduced insulation thickness in order to reduce weight and to improve handling • The pre-installed silicone rubber terminations are maintenance free and routine tested for partial discharge up to a test voltage of 2.5 x U0 . Following every use, a new partial discharge measurement can be performed on the cables in order to rule out possible damage. • Special single or three chamber drums make transportation and handling much easier Mr. Schindelbauer: Westnetz „The disconnect times of the electrical systems are frequently only short and timed Precisely. It is a major advantage here that temporary site cables can be installed regardless of the weather Conditions as well as at minus temperatures.“ „Thanks to their ease of use, temporary site cables allow the supply to be restored quickly and safely if faults arise in the grid or transformer station.“ REFERENCES ACTUAL REFERENCE LIST AVAILABLE UPON REQUEST
  • 4. Nexans Deutschland GmbH Land High Voltage Contracting Kabelkamp 20 · 30179 Hannover · Tel. +49 511 676-3364 · Fax +49 511 676-2254 eMail: hv-team.nd@nexans.com · www.nexans.com exa n s Global expert in cables and cabling systems About Nexans Nexans brings energy to life through an extensive range of cables and cabling solutions that deliver increased performance for our customers worldwide. Nexans’ teams are committed to a partnership approach that supports customers in four main business areas: Power transmission and distribution (submarine and land), Energy resources (Oil & Gas, Mining and Renewables), Transportation (Road, Rail, Air, Sea) and Building (Commercial, Residential and Data Centers). Nexans’ strategy is founded on continuous innovation in products, solutions and services, employee development, customer training and the introduction of safe, low -environmental- impact industrial processes. More information on www.nexans.com November2015·Copyright©NEXANS