SlideShare a Scribd company logo
1 of 12
N:Ahmed Usama Saleh
G:E501
 An overhead cable is a cable for the
transmission of information, laid on utility
poles. Overhead telephone and cable TV
lines are common in North America.
Elsewhere, overhead cables are laid mainly
for telephone connections of remote
buildings and temporary mechanisms.
 as for example building sites. The same
poles sometimes carry overhead power
lines for the supply of electric power. Power
supply companies may also use them for an
in-house communication network.
 Sometimes these cables are integrated in
the ground or power conductor. Otherwise
an additional line is strung on the masts.
 Undergrounding is the replacement
of overhead cables providing electrical
power or telecommunications, with
underground cables. This is typically
performed for aesthetic purposes, but also
serves the additional significant purpose of
making the power lines less susceptible to
outages during high wind thunderstorms or
heavy snow or ice storms. Undergrounding
can increase the initial costs of electric power
transmission and distribution but may
decrease operational costs over the lifetime
of the cables.
 Advantages:
 The main advantage is that they are easier to repair if
damaged (Usually just go up a ladder and do the
necessary work)
 They are not restricted by the landscape that they are
in e.g. you can easily suspend them over a motorway
or river
 Also they have a less chance of electrocuting people
as they are so high up
 Lose less energy then if they were underground as
they do not have any good conductors near them to
transfer energy away as easily
 Cheaper to set up and maintain than if they were
underground
 Disadvantages:
 Main problem is that they
visually pollute the areas
they are set up in
 Suffer from problems like
vandalism, assisting
terrorism (Easy access),
and lightning strikes
 Birds and low flying
aircrafts can sometimes
fly into them
 The main advantages of underground cables are:
 • Reduced visual impact.
 • Reduction or elimination of electrical and
magnetic fields above ground, and hence
elimination of potential health concerns.
 • Reduced transmission losses.
 • Reduced planning delays.
 • Increased security of supply, with elimination
of disruption due to extreme weather.
 • Road side developments can be made without
Section 37 application.
 Cost of Underground Cables: The cost of HVDC
underground cables has been quoted by SHETL as
being approximately three times that of a 400kV
overhead line. Underground cables carrying 400kV AC
are more expensive, but the very high costs quoted by
SHETL have been challenged by an independent report
by Jacobs Babtie (2005). This report dealt specifically
with the conditions found on the Beauly to Denny line,
with cost ratios quoted in the range 6 to 12 times that
of an overhead line. Unit costs increase with a
reduction in length of line placed underground, and
also with the use of fluid filled cable. The Jacobs
Babtie report does not give detailed costing for
underground cables in reinforced concrete troughs,
but the additional cost associated with this technology
will be offset by the use of the cheaper XLPE cables.
 Undergrounding is more expensive, since the cost of burying cables at transmission
voltages is several times greater than overhead power lines, and the life-cycle cost
of an underground power cable is two to four times the cost of an overhead power
line. Above ground lines cost around $10 per foot and underground lines cost in the
range of $20 to $40 per foot.[4] In highly urbanized areas the cost of underground
transmission can be 10-14 times as expensive as overhead.
 Whereas finding and repairing overhead wire breaks can be accomplished in hours,
underground repairs can take days or weeks,[6] and for this reason redundant lines
are run.
 Underground cable locations are not always obvious, which can lead to unwary
diggers damaging cables or being electrocuted.
 Operations are more difficult since the high reactive power of underground cables
produces large charging currents and so makes voltage control more difficult.[citation
needed]
 Whereas overhead lines can easily be uprated by modifying line clearances and
power poles to carry more power, underground cables cannot be uprated and must
be supplemented or replaced to increase capacity. Transmission and distribution
companies generally future-proof underground lines by installing the highest-rated
cables while being still cost-effective.
 Underground cables are more subject to damage by ground movement. The 2011
Christchurch earthquake in New Zealand caused damage to 360 kilometres (220 mi)
of high voltage underground cables and subsequently cut power to large parts of
Christchurch city, whereas only a few kilometres of overhead lines were damaged,
largely due to pole foundations being compromised by liquefaction.
 Underground cables offer an affordable and
justifiable solution for critical parts, and in
some cases the entire length, of overhead
high voltage power lines. With appropriate
technology used in appropriate places, the
environmental impact of underground cables
can be minimized.
 Electric Power needs to be carried over long distances from the point
of generation to the point of consumption. This Transmission is
done either through overhead lines or underground cables. Each of
these two methods of transmission has its own advantages and
disadvantages.
Overhead Transmission lines are cheaper as the insulation cost is
lesser and the conductor material cost is lesser too. They also have
better heat dissipation.
However, they have significant disadvantages. Overhead lines are
vulnerable to lightning strikes which can cause
interruption. Overhead lines use bare conductors and can cause
damage if they break. They are considered to be unsightly as they
mar the scenery of the landscape. The maintenance cost of
overhead lines is more and the voltage drop in overhead lines is
more.
 Underground transmission due to cables is costlier than overhead
transmission as the ground needs to be excavated. This can be
difficult when passing though geographic obstructions such as hills,
marshes and rivers. Special trenches need to be constructed when
passing through loose soil. Besides, heat dissipation in
underground cables is an issue. Hence, the conductors have to be
thicker. The insulation required for the cables is expensive. Hence,
it is difficult to use underground cables for voltages at HV levels (>
33 kV).
 Underground cables may have to be rerouted to accommodate other
underground structures such as pipelines, sewage lines, etc. It is
necessary that the routes of underground lines are clearly marked
with sign boards to prevent accidents when excavations are carried
out for other reasons at a later date.

More Related Content

What's hot

Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parametersfiraoltemesgen1
 
Various Bus-Bar Arrangements.
Various Bus-Bar Arrangements.Various Bus-Bar Arrangements.
Various Bus-Bar Arrangements.SaiSampath16
 
Bundle conductors in transmission line
Bundle conductors in transmission line Bundle conductors in transmission line
Bundle conductors in transmission line chandan kumar
 
Generation of High D.C. Voltage (HVDC generation)
Generation of High D.C. Voltage (HVDC generation)Generation of High D.C. Voltage (HVDC generation)
Generation of High D.C. Voltage (HVDC generation)RP6997
 
Mechanical design of overhead lines
Mechanical design of overhead linesMechanical design of overhead lines
Mechanical design of overhead linesMd. Rimon Mia
 
Electrical power distribution and utilization
Electrical power distribution and utilizationElectrical power distribution and utilization
Electrical power distribution and utilizationMuhammadAliImran11
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007Vaishnavee Patel
 
Chapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentChapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentmukund mukund.m
 
Conductor material and ferranti effect
Conductor material and ferranti effectConductor material and ferranti effect
Conductor material and ferranti effectAbhishekLalkiya
 
Underground cables
Underground cablesUnderground cables
Underground cablesAnu71
 
Effect of earth on transmission line, bundle conductor & method of gmd
Effect of earth on transmission line, bundle conductor & method of gmdEffect of earth on transmission line, bundle conductor & method of gmd
Effect of earth on transmission line, bundle conductor & method of gmdvishalgohel12195
 
Skin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona dischargeSkin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona dischargeRoungpaSukhe
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...vishalgohel12195
 

What's hot (20)

Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
Various Bus-Bar Arrangements.
Various Bus-Bar Arrangements.Various Bus-Bar Arrangements.
Various Bus-Bar Arrangements.
 
Bundle conductors in transmission line
Bundle conductors in transmission line Bundle conductors in transmission line
Bundle conductors in transmission line
 
Electric power system
Electric power systemElectric power system
Electric power system
 
Generation of High D.C. Voltage (HVDC generation)
Generation of High D.C. Voltage (HVDC generation)Generation of High D.C. Voltage (HVDC generation)
Generation of High D.C. Voltage (HVDC generation)
 
Corona effect
Corona effectCorona effect
Corona effect
 
Mechanical design of overhead lines
Mechanical design of overhead linesMechanical design of overhead lines
Mechanical design of overhead lines
 
Electrical power distribution and utilization
Electrical power distribution and utilizationElectrical power distribution and utilization
Electrical power distribution and utilization
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007
 
Chapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentChapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and current
 
Over head power lines
Over head power linesOver head power lines
Over head power lines
 
Conductor material and ferranti effect
Conductor material and ferranti effectConductor material and ferranti effect
Conductor material and ferranti effect
 
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
High voltage underground cables
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Effect of earth on transmission line, bundle conductor & method of gmd
Effect of earth on transmission line, bundle conductor & method of gmdEffect of earth on transmission line, bundle conductor & method of gmd
Effect of earth on transmission line, bundle conductor & method of gmd
 
Skin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona dischargeSkin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona discharge
 
High voltage
High voltageHigh voltage
High voltage
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Electric substation
Electric substation Electric substation
Electric substation
 
Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...
 

Similar to Comparison of overhead and underground transmission lines

Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Ivan Rojas Soliz
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission linesHamzaAbbas43
 
3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cablesssuser30d0c22
 
Electric power system
Electric power systemElectric power system
Electric power systemvishalmahar3
 
NEI Underground Presentation 06-09-09 (1).pdf
NEI Underground Presentation 06-09-09 (1).pdfNEI Underground Presentation 06-09-09 (1).pdf
NEI Underground Presentation 06-09-09 (1).pdftadepeace23
 
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...Leonardo ENERGY
 
Electricity distribution
Electricity distributionElectricity distribution
Electricity distributionghumman88
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationSubhrajit Ghosh
 
Underground Wiring System : A Comprehensive Guide by We-Bore-It
Underground Wiring System : A Comprehensive Guide by We-Bore-ItUnderground Wiring System : A Comprehensive Guide by We-Bore-It
Underground Wiring System : A Comprehensive Guide by We-Bore-ItWe-Bore-It
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...nak maneth
 
Chapter 3 - Electromagnetism, 3.5 Generation & Transmission of Electricity
Chapter 3 - Electromagnetism, 3.5 Generation & Transmission of ElectricityChapter 3 - Electromagnetism, 3.5 Generation & Transmission of Electricity
Chapter 3 - Electromagnetism, 3.5 Generation & Transmission of ElectricityQhaiyum Shah
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)Abhishek Choksi
 

Similar to Comparison of overhead and underground transmission lines (20)

Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
 
underground presentation
underground presentation underground presentation
underground presentation
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
 
3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables
 
Electric power system
Electric power systemElectric power system
Electric power system
 
NEI Underground Presentation 06-09-09 (1).pdf
NEI Underground Presentation 06-09-09 (1).pdfNEI Underground Presentation 06-09-09 (1).pdf
NEI Underground Presentation 06-09-09 (1).pdf
 
Pdu 2021 s2
Pdu 2021 s2Pdu 2021 s2
Pdu 2021 s2
 
Cables
CablesCables
Cables
 
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
 
Electricity distribution
Electricity distributionElectricity distribution
Electricity distribution
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv Substation
 
Underground Wiring System : A Comprehensive Guide by We-Bore-It
Underground Wiring System : A Comprehensive Guide by We-Bore-ItUnderground Wiring System : A Comprehensive Guide by We-Bore-It
Underground Wiring System : A Comprehensive Guide by We-Bore-It
 
transmission line installation
transmission line installationtransmission line installation
transmission line installation
 
Electric09
Electric09Electric09
Electric09
 
Chapter 8N.pptx
Chapter 8N.pptxChapter 8N.pptx
Chapter 8N.pptx
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
 
Chapter 3 - Electromagnetism, 3.5 Generation & Transmission of Electricity
Chapter 3 - Electromagnetism, 3.5 Generation & Transmission of ElectricityChapter 3 - Electromagnetism, 3.5 Generation & Transmission of Electricity
Chapter 3 - Electromagnetism, 3.5 Generation & Transmission of Electricity
 
EHV AC
EHV ACEHV AC
EHV AC
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Comparison of overhead and underground transmission lines

  • 2.  An overhead cable is a cable for the transmission of information, laid on utility poles. Overhead telephone and cable TV lines are common in North America. Elsewhere, overhead cables are laid mainly for telephone connections of remote buildings and temporary mechanisms.  as for example building sites. The same poles sometimes carry overhead power lines for the supply of electric power. Power supply companies may also use them for an in-house communication network.  Sometimes these cables are integrated in the ground or power conductor. Otherwise an additional line is strung on the masts.
  • 3.  Undergrounding is the replacement of overhead cables providing electrical power or telecommunications, with underground cables. This is typically performed for aesthetic purposes, but also serves the additional significant purpose of making the power lines less susceptible to outages during high wind thunderstorms or heavy snow or ice storms. Undergrounding can increase the initial costs of electric power transmission and distribution but may decrease operational costs over the lifetime of the cables.
  • 4.  Advantages:  The main advantage is that they are easier to repair if damaged (Usually just go up a ladder and do the necessary work)  They are not restricted by the landscape that they are in e.g. you can easily suspend them over a motorway or river  Also they have a less chance of electrocuting people as they are so high up  Lose less energy then if they were underground as they do not have any good conductors near them to transfer energy away as easily  Cheaper to set up and maintain than if they were underground
  • 5.  Disadvantages:  Main problem is that they visually pollute the areas they are set up in  Suffer from problems like vandalism, assisting terrorism (Easy access), and lightning strikes  Birds and low flying aircrafts can sometimes fly into them
  • 6.  The main advantages of underground cables are:  • Reduced visual impact.  • Reduction or elimination of electrical and magnetic fields above ground, and hence elimination of potential health concerns.  • Reduced transmission losses.  • Reduced planning delays.  • Increased security of supply, with elimination of disruption due to extreme weather.  • Road side developments can be made without Section 37 application.
  • 7.  Cost of Underground Cables: The cost of HVDC underground cables has been quoted by SHETL as being approximately three times that of a 400kV overhead line. Underground cables carrying 400kV AC are more expensive, but the very high costs quoted by SHETL have been challenged by an independent report by Jacobs Babtie (2005). This report dealt specifically with the conditions found on the Beauly to Denny line, with cost ratios quoted in the range 6 to 12 times that of an overhead line. Unit costs increase with a reduction in length of line placed underground, and also with the use of fluid filled cable. The Jacobs Babtie report does not give detailed costing for underground cables in reinforced concrete troughs, but the additional cost associated with this technology will be offset by the use of the cheaper XLPE cables.
  • 8.  Undergrounding is more expensive, since the cost of burying cables at transmission voltages is several times greater than overhead power lines, and the life-cycle cost of an underground power cable is two to four times the cost of an overhead power line. Above ground lines cost around $10 per foot and underground lines cost in the range of $20 to $40 per foot.[4] In highly urbanized areas the cost of underground transmission can be 10-14 times as expensive as overhead.  Whereas finding and repairing overhead wire breaks can be accomplished in hours, underground repairs can take days or weeks,[6] and for this reason redundant lines are run.  Underground cable locations are not always obvious, which can lead to unwary diggers damaging cables or being electrocuted.  Operations are more difficult since the high reactive power of underground cables produces large charging currents and so makes voltage control more difficult.[citation needed]  Whereas overhead lines can easily be uprated by modifying line clearances and power poles to carry more power, underground cables cannot be uprated and must be supplemented or replaced to increase capacity. Transmission and distribution companies generally future-proof underground lines by installing the highest-rated cables while being still cost-effective.  Underground cables are more subject to damage by ground movement. The 2011 Christchurch earthquake in New Zealand caused damage to 360 kilometres (220 mi) of high voltage underground cables and subsequently cut power to large parts of Christchurch city, whereas only a few kilometres of overhead lines were damaged, largely due to pole foundations being compromised by liquefaction.
  • 9.  Underground cables offer an affordable and justifiable solution for critical parts, and in some cases the entire length, of overhead high voltage power lines. With appropriate technology used in appropriate places, the environmental impact of underground cables can be minimized.
  • 10.
  • 11.  Electric Power needs to be carried over long distances from the point of generation to the point of consumption. This Transmission is done either through overhead lines or underground cables. Each of these two methods of transmission has its own advantages and disadvantages. Overhead Transmission lines are cheaper as the insulation cost is lesser and the conductor material cost is lesser too. They also have better heat dissipation. However, they have significant disadvantages. Overhead lines are vulnerable to lightning strikes which can cause interruption. Overhead lines use bare conductors and can cause damage if they break. They are considered to be unsightly as they mar the scenery of the landscape. The maintenance cost of overhead lines is more and the voltage drop in overhead lines is more.
  • 12.  Underground transmission due to cables is costlier than overhead transmission as the ground needs to be excavated. This can be difficult when passing though geographic obstructions such as hills, marshes and rivers. Special trenches need to be constructed when passing through loose soil. Besides, heat dissipation in underground cables is an issue. Hence, the conductors have to be thicker. The insulation required for the cables is expensive. Hence, it is difficult to use underground cables for voltages at HV levels (> 33 kV).  Underground cables may have to be rerouted to accommodate other underground structures such as pipelines, sewage lines, etc. It is necessary that the routes of underground lines are clearly marked with sign boards to prevent accidents when excavations are carried out for other reasons at a later date.