Kuwait Metro & Rail, 17-18 April 2012
        Day 2
        13h30-14h00


        Presented by:

        Craig Tengström (Director)




Copyright © 2010 Tubular Track. All rights reserved   Confidential
• Began in the South African mining industry in 1989 to solve water drainage
  issues, reduce maintenance and increase track availability
• With further development, was introduced into the surface environment
  with installations as far back as 1993
• Full scale laboratory testing was done at the Transnet Freight Rail Testing
  Facility in 2000 to fully develop the system into pre-cast modular form
• Has since evolved into a pre-cast track system with major capex and life
  cycle cost benefits
• Installations in South Africa, Namibia, Botswana, Zambia, Canada, USA &
  Saudi Arabia
• Representation in South Africa, Brazil, Australia, Namibia and Saudi Arabia
Low Cost, Modular, Pre-cast, Ballast-less, Desert Proven




Main Components of T-Track:
 30MPa reinforced concrete beams
 Galvanized gauge bars
 Galvanized stirrups
 Rail fasteners
 Resilient pad




                                                           Confidential   3
T-Track – a Cost Revolution in Major Track Systems




                                          BALLAST-LESS TRACK
         BALLASTED TRACK             T-TRACK                   SLAB TRACK
CAPEX           1                    0.9 – 1.5                    2–4
OPEX            1                    0.2 – 0.4                  0.2 – 0.4


                                                                            Confidential   4
T-Track – a Cost Revolution in Major Track Systems




                                                     Confidential   5
T-Track – the Universal Rail Solution

    Ideal for Track applications:       in all Environments:
   Main line                          Desert
   Turnouts                           Savanna
   Level crossings                    Tropics
   Bridges                            Tundra
   Viaducts                           Underground
   Tunnels                            Urban
   Sidings
      Loading
      HAZMAT                           as a result of:
   Incline shafts                     Low initial cost
                                       Low maintenance cost
    for Services such as:              Reduction in required rail sizes
   Mass transit                       Improved drainage
   Light rail                         Fixed geometry
   Theme parks                        Guaranteed resilience
   Inter-city passenger               Continuous support of rails
   General freight                    Integrated design
   Heavy haul freight                 Strong partnerships                Confidential   6
T-Track – the Universal Rail Solution

  Ideal for Track applications:         in all Environments:




                                        as a result of:
  for Services such as:




                                                               Confidential   7
Desert proven: No ballast – No Contamination. T-Track mitigates sand
     contamination
               Ballasted Track in KSA      T-Track in KSA
During                                                       2008
                                 2009
Construction




                                    2011                      2011
In Operation




                                                                     Confidential   8
Additional benefits of T-Track: Reduction in Earthworks and
Formation Volumes




                                                              Confidential   9
Additional benefits of T-Track: Mitigation of Flooding




                                                         Confidential   10
Additional benefits of T-Track: Trench-free Cabling




   Broadband fibre optic along the rail reserve
   Signalling communications
   Local power for points machines, interlockings, signals
   Reduces trenching costs

                                                              Confidential   11
Additional benefits of T-Track: Simple third rail designs




                                                            Confidential   12
Additional benefits of T-Track: Mitigation of DC stray currents

                                           Rebar in the T-Track module
 DC traction return current often strays   "collects" the stray current
 from the return rail




                                                         Properly
                                                         interconnected
                                                         rebar negates
Extensive research on how T-Track                        corrosion risk
Mitigates stray current
                                                                     Confidential   13
Material and Load
                      Characterization


                      Structural Analysis


                     Pavement Response
                           s&e
                                                    Design
                      Transfer Functions          Iterations


                     Predict Pavement Life




               YES                           No
Final Design             ADEQUATE
Tubular Track: Coal Line - Ermelo Balloon (End of Beam)

                   Granular Layers                               FEM Input Data
                                                                                        Safety Factor      Load
        Layer                    Material                                                    (F)        Repetitions N
Layer             Thickness                       Moisture         s1           s3
        Name                      Type
 1       SSB        200             G4           Moderate        168.30        19.93        1.67         7.057E+08
 2        SB        200             G4           Moderate        111.60        18.30        2.58         1.641E+11
 3        A         200             G6           Moderate         90.30        6.31         1.17         3.625E+07
                   Subgrade Layers                                        me
 4        B         300             G7                                  690                              1.027E+08
 5      In-situ     5000            G8                                  450                              7.443E+09
                                                                                            Min          3.625E+07
                                                                                        Axle load (t)        26
                                                                                         MGT/year           100
                                                                                        Life (Years)       37.70
T-Track: In the KSA desert since 2008




                                        Confidential   17
ISO 9001: 2008 Certified for
Design, Manufacture, Supply
and Installation




                               Confidential   18
Mr. craig tengström   kuwait metro and rail

More Related Content

Similar to Mr. craig tengström kuwait metro and rail

Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Johan Granlund
 
Lect2 up040 (100324)
Lect2 up040 (100324)Lect2 up040 (100324)
Lect2 up040 (100324)
aicdesign
 
Photovoltaic Training - Session 2 - Construction and Start-Up
Photovoltaic Training - Session 2 - Construction and Start-UpPhotovoltaic Training - Session 2 - Construction and Start-Up
Photovoltaic Training - Session 2 - Construction and Start-Up
Leonardo ENERGY
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
satish choudhari
 
Solving the 5G fronthaul challenge with Ethernet and passive WDM
Solving the 5G fronthaul challenge with Ethernet and passive WDMSolving the 5G fronthaul challenge with Ethernet and passive WDM
Solving the 5G fronthaul challenge with Ethernet and passive WDM
ADVA
 
IRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using Ansys
IRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using AnsysIRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using Ansys
IRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using Ansys
IRJET Journal
 
Roadstab 2017
Roadstab 2017Roadstab 2017
Final tssa design and realization of passive phase shifters
Final tssa design and realization of passive phase shiftersFinal tssa design and realization of passive phase shifters
Final tssa design and realization of passive phase shifters
Dr.Joko Suryana
 
High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...
High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...
High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...
ayubimoak
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
Kumar VEL
 
SPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARK
Tsuyoshi Horigome
 
The Network After SONET
The Network After SONETThe Network After SONET
The Network After SONET
Cisco Service Provider
 
Transmission Line Basics
Transmission Line BasicsTransmission Line Basics
Transmission Line Basics
John Williams
 
Tubular Track - Namibia
Tubular Track - NamibiaTubular Track - Namibia
Tubular Track - Namibia
Tubular Track
 
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
Altair
 
Final distribution presentation
Final distribution presentationFinal distribution presentation
Final distribution presentation
Hamed Moosaei
 
Final distribution presentation
Final distribution presentationFinal distribution presentation
Final distribution presentation
Hamed Moosaei
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
bala506586
 
LTCC Overview
LTCC OverviewLTCC Overview
LTCC Overview
Steve Dai
 
Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...
Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...
Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...
Sematron UK Ltd
 

Similar to Mr. craig tengström kuwait metro and rail (20)

Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
 
Lect2 up040 (100324)
Lect2 up040 (100324)Lect2 up040 (100324)
Lect2 up040 (100324)
 
Photovoltaic Training - Session 2 - Construction and Start-Up
Photovoltaic Training - Session 2 - Construction and Start-UpPhotovoltaic Training - Session 2 - Construction and Start-Up
Photovoltaic Training - Session 2 - Construction and Start-Up
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
 
Solving the 5G fronthaul challenge with Ethernet and passive WDM
Solving the 5G fronthaul challenge with Ethernet and passive WDMSolving the 5G fronthaul challenge with Ethernet and passive WDM
Solving the 5G fronthaul challenge with Ethernet and passive WDM
 
IRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using Ansys
IRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using AnsysIRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using Ansys
IRJET- Analysis of Precast Post Tensioned Segmental Bridge Column using Ansys
 
Roadstab 2017
Roadstab 2017Roadstab 2017
Roadstab 2017
 
Final tssa design and realization of passive phase shifters
Final tssa design and realization of passive phase shiftersFinal tssa design and realization of passive phase shifters
Final tssa design and realization of passive phase shifters
 
High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...
High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...
High-Performance In0.75Ga0.25As Implant-Free n-Type MOSFETs for Low Power App...
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
 
SPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC6004 (Professional+BDP Model) in SPICE PARK
 
The Network After SONET
The Network After SONETThe Network After SONET
The Network After SONET
 
Transmission Line Basics
Transmission Line BasicsTransmission Line Basics
Transmission Line Basics
 
Tubular Track - Namibia
Tubular Track - NamibiaTubular Track - Namibia
Tubular Track - Namibia
 
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
An Improved Subgrade Model for Crash Analysis of Guardrail Posts - University...
 
Final distribution presentation
Final distribution presentationFinal distribution presentation
Final distribution presentation
 
Final distribution presentation
Final distribution presentationFinal distribution presentation
Final distribution presentation
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
 
LTCC Overview
LTCC OverviewLTCC Overview
LTCC Overview
 
Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...
Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...
Newtec - Optimisation of Satellite Capacity Efficiency for IP Trunking Applic...
 

More from imadhammoud

Dr. kim jraiw the economics of rail and metro development
Dr. kim jraiw   the economics of rail and metro developmentDr. kim jraiw   the economics of rail and metro development
Dr. kim jraiw the economics of rail and metro development
imadhammoud
 
Dr. mansour el bardisi -noise impact assessment for metro and railway
Dr. mansour el  bardisi -noise impact assessment for metro and railwayDr. mansour el  bardisi -noise impact assessment for metro and railway
Dr. mansour el bardisi -noise impact assessment for metro and railway
imadhammoud
 
Dr. rustom kanga latest trends in video analytics for railways
Dr. rustom kanga latest trends in video analytics for railwaysDr. rustom kanga latest trends in video analytics for railways
Dr. rustom kanga latest trends in video analytics for railways
imadhammoud
 
Eng. issam chehimi part 1 the driverless unattended metro
Eng. issam chehimi part 1  the driverless unattended metroEng. issam chehimi part 1  the driverless unattended metro
Eng. issam chehimi part 1 the driverless unattended metro
imadhammoud
 
Eng. issam chehimi part 2 catenary-free solution
Eng. issam chehimi part 2  catenary-free solutionEng. issam chehimi part 2  catenary-free solution
Eng. issam chehimi part 2 catenary-free solution
imadhammoud
 
Mr. jose solorza haramain high speed railway phase 2
Mr. jose solorza  haramain high speed railway phase 2Mr. jose solorza  haramain high speed railway phase 2
Mr. jose solorza haramain high speed railway phase 2
imadhammoud
 
Mr. juan pablo barahona future of high speeds
Mr. juan pablo barahona   future of high speedsMr. juan pablo barahona   future of high speeds
Mr. juan pablo barahona future of high speeds
imadhammoud
 
Mr. oliver andre the hidden costs and benefits of the telecommunications sys...
Mr. oliver andre  the hidden costs and benefits of the telecommunications sys...Mr. oliver andre  the hidden costs and benefits of the telecommunications sys...
Mr. oliver andre the hidden costs and benefits of the telecommunications sys...
imadhammoud
 
Mr. roger fogtec fire protection
Mr. roger   fogtec fire protectionMr. roger   fogtec fire protection
Mr. roger fogtec fire protection
imadhammoud
 
Mr. teemu sipila protecting rolling stock - water mist fire protection
Mr. teemu sipila  protecting rolling stock - water mist fire protectionMr. teemu sipila  protecting rolling stock - water mist fire protection
Mr. teemu sipila protecting rolling stock - water mist fire protection
imadhammoud
 
Ms. susana gozalo turnkey services for high speed railway. from vision to re...
Ms. susana gozalo  turnkey services for high speed railway. from vision to re...Ms. susana gozalo  turnkey services for high speed railway. from vision to re...
Ms. susana gozalo turnkey services for high speed railway. from vision to re...
imadhammoud
 
Dr. ulrich koegler effective psp in metro and rail projects vfff
Dr. ulrich koegler   effective psp in metro and rail projects vfffDr. ulrich koegler   effective psp in metro and rail projects vfff
Dr. ulrich koegler effective psp in metro and rail projects vfff
imadhammoud
 
Mr. mohamad dichari us standards for railroad types, infrastructure and are...
Mr. mohamad dichari   us standards for railroad types, infrastructure and are...Mr. mohamad dichari   us standards for railroad types, infrastructure and are...
Mr. mohamad dichari us standards for railroad types, infrastructure and are...
imadhammoud
 
Mr. roger dirksmeier active fire protection in railway vehicles as ‘compens...
Mr. roger dirksmeier   active fire protection in railway vehicles as ‘compens...Mr. roger dirksmeier   active fire protection in railway vehicles as ‘compens...
Mr. roger dirksmeier active fire protection in railway vehicles as ‘compens...
imadhammoud
 
Sebastian Emig - silver bullet for future urban mobilitity or waste of money
Sebastian Emig - silver bullet for future urban mobilitity or waste of moneySebastian Emig - silver bullet for future urban mobilitity or waste of money
Sebastian Emig - silver bullet for future urban mobilitity or waste of money
imadhammoud
 
Richard woods integration of public transport modes in kuwait
Richard woods  integration of public transport modes in kuwaitRichard woods  integration of public transport modes in kuwait
Richard woods integration of public transport modes in kuwait
imadhammoud
 
Peter Jenkins - 10 steps to great station design
Peter Jenkins - 10 steps to great station designPeter Jenkins - 10 steps to great station design
Peter Jenkins - 10 steps to great station design
imadhammoud
 
Kim Jraiw - the importance of integrating metro and rail projects with nation...
Kim Jraiw - the importance of integrating metro and rail projects with nation...Kim Jraiw - the importance of integrating metro and rail projects with nation...
Kim Jraiw - the importance of integrating metro and rail projects with nation...imadhammoud
 
Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...
imadhammoud
 
Juan Pablo - the future of high speed
Juan Pablo - the future of high speedJuan Pablo - the future of high speed
Juan Pablo - the future of high speed
imadhammoud
 

More from imadhammoud (20)

Dr. kim jraiw the economics of rail and metro development
Dr. kim jraiw   the economics of rail and metro developmentDr. kim jraiw   the economics of rail and metro development
Dr. kim jraiw the economics of rail and metro development
 
Dr. mansour el bardisi -noise impact assessment for metro and railway
Dr. mansour el  bardisi -noise impact assessment for metro and railwayDr. mansour el  bardisi -noise impact assessment for metro and railway
Dr. mansour el bardisi -noise impact assessment for metro and railway
 
Dr. rustom kanga latest trends in video analytics for railways
Dr. rustom kanga latest trends in video analytics for railwaysDr. rustom kanga latest trends in video analytics for railways
Dr. rustom kanga latest trends in video analytics for railways
 
Eng. issam chehimi part 1 the driverless unattended metro
Eng. issam chehimi part 1  the driverless unattended metroEng. issam chehimi part 1  the driverless unattended metro
Eng. issam chehimi part 1 the driverless unattended metro
 
Eng. issam chehimi part 2 catenary-free solution
Eng. issam chehimi part 2  catenary-free solutionEng. issam chehimi part 2  catenary-free solution
Eng. issam chehimi part 2 catenary-free solution
 
Mr. jose solorza haramain high speed railway phase 2
Mr. jose solorza  haramain high speed railway phase 2Mr. jose solorza  haramain high speed railway phase 2
Mr. jose solorza haramain high speed railway phase 2
 
Mr. juan pablo barahona future of high speeds
Mr. juan pablo barahona   future of high speedsMr. juan pablo barahona   future of high speeds
Mr. juan pablo barahona future of high speeds
 
Mr. oliver andre the hidden costs and benefits of the telecommunications sys...
Mr. oliver andre  the hidden costs and benefits of the telecommunications sys...Mr. oliver andre  the hidden costs and benefits of the telecommunications sys...
Mr. oliver andre the hidden costs and benefits of the telecommunications sys...
 
Mr. roger fogtec fire protection
Mr. roger   fogtec fire protectionMr. roger   fogtec fire protection
Mr. roger fogtec fire protection
 
Mr. teemu sipila protecting rolling stock - water mist fire protection
Mr. teemu sipila  protecting rolling stock - water mist fire protectionMr. teemu sipila  protecting rolling stock - water mist fire protection
Mr. teemu sipila protecting rolling stock - water mist fire protection
 
Ms. susana gozalo turnkey services for high speed railway. from vision to re...
Ms. susana gozalo  turnkey services for high speed railway. from vision to re...Ms. susana gozalo  turnkey services for high speed railway. from vision to re...
Ms. susana gozalo turnkey services for high speed railway. from vision to re...
 
Dr. ulrich koegler effective psp in metro and rail projects vfff
Dr. ulrich koegler   effective psp in metro and rail projects vfffDr. ulrich koegler   effective psp in metro and rail projects vfff
Dr. ulrich koegler effective psp in metro and rail projects vfff
 
Mr. mohamad dichari us standards for railroad types, infrastructure and are...
Mr. mohamad dichari   us standards for railroad types, infrastructure and are...Mr. mohamad dichari   us standards for railroad types, infrastructure and are...
Mr. mohamad dichari us standards for railroad types, infrastructure and are...
 
Mr. roger dirksmeier active fire protection in railway vehicles as ‘compens...
Mr. roger dirksmeier   active fire protection in railway vehicles as ‘compens...Mr. roger dirksmeier   active fire protection in railway vehicles as ‘compens...
Mr. roger dirksmeier active fire protection in railway vehicles as ‘compens...
 
Sebastian Emig - silver bullet for future urban mobilitity or waste of money
Sebastian Emig - silver bullet for future urban mobilitity or waste of moneySebastian Emig - silver bullet for future urban mobilitity or waste of money
Sebastian Emig - silver bullet for future urban mobilitity or waste of money
 
Richard woods integration of public transport modes in kuwait
Richard woods  integration of public transport modes in kuwaitRichard woods  integration of public transport modes in kuwait
Richard woods integration of public transport modes in kuwait
 
Peter Jenkins - 10 steps to great station design
Peter Jenkins - 10 steps to great station designPeter Jenkins - 10 steps to great station design
Peter Jenkins - 10 steps to great station design
 
Kim Jraiw - the importance of integrating metro and rail projects with nation...
Kim Jraiw - the importance of integrating metro and rail projects with nation...Kim Jraiw - the importance of integrating metro and rail projects with nation...
Kim Jraiw - the importance of integrating metro and rail projects with nation...
 
Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...
 
Juan Pablo - the future of high speed
Juan Pablo - the future of high speedJuan Pablo - the future of high speed
Juan Pablo - the future of high speed
 

Recently uploaded

The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
Corey Perlman, Social Media Speaker and Consultant
 
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
bosssp10
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
LuanWise
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
ecamare2
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Lviv Startup Club
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
Christian Dahlen
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
AnnySerafinaLove
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
Chandresh Chudasama
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
Kirill Klimov
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
taqyea
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
SOFTTECHHUB
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
MJ Global
 

Recently uploaded (20)

The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
 
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 8867766396 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
 

Mr. craig tengström kuwait metro and rail

  • 1. Kuwait Metro & Rail, 17-18 April 2012 Day 2 13h30-14h00 Presented by: Craig Tengström (Director) Copyright © 2010 Tubular Track. All rights reserved Confidential
  • 2. • Began in the South African mining industry in 1989 to solve water drainage issues, reduce maintenance and increase track availability • With further development, was introduced into the surface environment with installations as far back as 1993 • Full scale laboratory testing was done at the Transnet Freight Rail Testing Facility in 2000 to fully develop the system into pre-cast modular form • Has since evolved into a pre-cast track system with major capex and life cycle cost benefits • Installations in South Africa, Namibia, Botswana, Zambia, Canada, USA & Saudi Arabia • Representation in South Africa, Brazil, Australia, Namibia and Saudi Arabia
  • 3. Low Cost, Modular, Pre-cast, Ballast-less, Desert Proven Main Components of T-Track:  30MPa reinforced concrete beams  Galvanized gauge bars  Galvanized stirrups  Rail fasteners  Resilient pad Confidential 3
  • 4. T-Track – a Cost Revolution in Major Track Systems BALLAST-LESS TRACK BALLASTED TRACK T-TRACK SLAB TRACK CAPEX 1 0.9 – 1.5 2–4 OPEX 1 0.2 – 0.4 0.2 – 0.4 Confidential 4
  • 5. T-Track – a Cost Revolution in Major Track Systems Confidential 5
  • 6. T-Track – the Universal Rail Solution Ideal for Track applications: in all Environments:  Main line  Desert  Turnouts  Savanna  Level crossings  Tropics  Bridges  Tundra  Viaducts  Underground  Tunnels  Urban  Sidings  Loading  HAZMAT as a result of:  Incline shafts  Low initial cost  Low maintenance cost for Services such as:  Reduction in required rail sizes  Mass transit  Improved drainage  Light rail  Fixed geometry  Theme parks  Guaranteed resilience  Inter-city passenger  Continuous support of rails  General freight  Integrated design  Heavy haul freight  Strong partnerships Confidential 6
  • 7. T-Track – the Universal Rail Solution Ideal for Track applications: in all Environments: as a result of: for Services such as: Confidential 7
  • 8. Desert proven: No ballast – No Contamination. T-Track mitigates sand contamination Ballasted Track in KSA T-Track in KSA During 2008 2009 Construction 2011 2011 In Operation Confidential 8
  • 9. Additional benefits of T-Track: Reduction in Earthworks and Formation Volumes Confidential 9
  • 10. Additional benefits of T-Track: Mitigation of Flooding Confidential 10
  • 11. Additional benefits of T-Track: Trench-free Cabling  Broadband fibre optic along the rail reserve  Signalling communications  Local power for points machines, interlockings, signals  Reduces trenching costs Confidential 11
  • 12. Additional benefits of T-Track: Simple third rail designs Confidential 12
  • 13. Additional benefits of T-Track: Mitigation of DC stray currents Rebar in the T-Track module DC traction return current often strays "collects" the stray current from the return rail Properly interconnected rebar negates Extensive research on how T-Track corrosion risk Mitigates stray current Confidential 13
  • 14. Material and Load Characterization Structural Analysis Pavement Response s&e Design Transfer Functions Iterations Predict Pavement Life YES No Final Design ADEQUATE
  • 15.
  • 16. Tubular Track: Coal Line - Ermelo Balloon (End of Beam) Granular Layers FEM Input Data Safety Factor Load Layer Material (F) Repetitions N Layer Thickness Moisture s1 s3 Name Type 1 SSB 200 G4 Moderate 168.30 19.93 1.67 7.057E+08 2 SB 200 G4 Moderate 111.60 18.30 2.58 1.641E+11 3 A 200 G6 Moderate 90.30 6.31 1.17 3.625E+07 Subgrade Layers me 4 B 300 G7 690 1.027E+08 5 In-situ 5000 G8 450 7.443E+09 Min 3.625E+07 Axle load (t) 26 MGT/year 100 Life (Years) 37.70
  • 17. T-Track: In the KSA desert since 2008 Confidential 17
  • 18. ISO 9001: 2008 Certified for Design, Manufacture, Supply and Installation Confidential 18