SlideShare a Scribd company logo
Question No. 1 2 3 4
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
: 30
MMUP Review Exam - Answer Key
Name: ID.No:
Question No. A B C D
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
: 30
MMUP Review Exam - Answer Sheet
Name: EMP.No:
Cost Control Department
:
MMUP Review Exam
Name: EMP No.
Project:
Date:
Page 1 of 5
Cost Control Department
1 The Performance of a specific task in CPM is known as:
a. Dummy
b. Event
c. Activity
d. Contract
2 Completion of an activity on CPM network diagram is generally known as:
a. Event
b. Node
c. Connector
d. All Of The Above.
3 Pick up the incorrect statement from the following:
a. The Activity Is The Time Consuming Part Of A Project.
b. The Beginning And The End Of A Job Are Called Events.
c. The Activity Which Consumes Maximum Time Is Called Anode.
d. Logically And Sequentially Connected Activities And Events From A Network
4 The time by which activity completion time can be delayed without affecting the start of succeeding
activities is known as:
a. Duration
b. Total Float
c. Free Float
d. Interfering Float
5 The difference between the time available to do a job and the time required to do the job is known as:
a. Event
b. Float
c. Duration
d. Constrain
6 For completion of a project, the critical path of the network represents
a. Minimum Time
b. Maximum Time
c. Maximum Cost
d. Minimum Cost
7 The three time estimates for the activities fo the network shown in the given figure are shown above their
arrows: The earliest expected time for the even 4 is:
3 - 4 - 5 5 - 7 - 9 6 - 8 - 10
a. 19
b. 14
c. 24
d. None Of Those
1 2 3 4
Page 2 of 5
Cost Control Department
8 A subcontractor has the task of erecting 8,400 sq2 of metal scaffolds. The contractor can use several
crews with various cost. It is expected that the production will vary with the crew size as given below:
Consider the following rates:
Labor = $ 96/day; Carpenter = $ 128/day; Foreman = $ 144/day; Scaffolder = $60/day
a. $ 76.22 /Day
b. $ 33.252 /Day
c. $ 70.00 /Day
d. None Of The Above.
9 Assume you can lease an item you need for project for $ 800/day. To purchase the item the cost is $
12,000 plus daily operational cost of $ 400/day. If you need the item for more than 30 days, it is more
economical to:
a. To Lease It
b. To Purchase It
10
Reinforcing steel bars of T10 mm at 10 cm spacing to be replaced by T12 mm. Calculate the new
required spacing
a. 14.4 mm
b. 6.9 mm
c. 12 mm
d. 8.3 mm
11
If a concrete beam is supported as continuous beam, the section at the support must be designated as:
a. T-Beam
b. Rectangular Beam
c. Simply Supported Beam
d. Flange Beam
12 Under normal conditions using an ordinary cement, the period of removal of the form work is:
a. 7 Days For Beam Soffits
b. 14 Days For Bottom Slabs Of Spans 4.6 M And More
c. 21 Days For Bottom Beams Over 6 M Spans
d. All Of The Above.
13 Permissible compressive strength of M 300 concrete grade is
a. 100 Kg/ Cm2
b. 150 Kg/ Cm2
c. 200 Kg/ Cm2
d. 300 Kg/ Cm2
14 Mass concrete is defined as the concrete where: (QCS)
a. The Dimension Is Equal To 1.5 M
b. Where The Large Dimension Exceeds 1.5 M
c. The Least Dimension Exceeds 1.5 M
d. None Of The Above.
Page 3 of 5
Cost Control Department
15 Temperature of fresh concrete should be:
a. Not Exceeds 42 Degrees
b. Equal To 40 Degrees
c. Not Exceeds 32 Degrees
d. None Of The Above.
16 Construction joint should be provided within:
a. The Middle Third Of Spans
b. At 1/3 To 1/4 Of Span In Slabs And Beams
c. Where Bm And S.F. Are Small
d. All Of The Above.
17 Curing:
a. Reduces The Shrinkage Of Concrete
b. Preserves The Properties Of Concrete
c. Prevents The Loss Of Water By Evaporation
d. All Of The Above.
18 The increased cohesiveness of concrete makes it:
a. Less Liable To Segregation
b. More Liable To Segregation
c. More Liable To Bleeding
d. More Liable For Surface Scaling In Frosty Weather
19 Workability improved by adding:
a. Air-Entraining Agent
b. Foaming Agent
c. Oily-Agent
d. All Of The Above.
20 Workability of concrete is measured by:
a. Vicat Apparatus Test
b. Slump Test
c. Minimum Void Method
d. Talbot Richart Test
21 According to the recommendation of IS 456-1978, the expansion joints:
a. Are Provided Where Plane Changes Abruptly
b. Are Provided To Ensure Minimum Resistance.
c. Are Supported On Separate Columns
d. All Of The Above.
22 Shrinkage in concrete can be reduced by using:
a. Low Water Cement Ratio.
b. Less Cement In The Concrete.
c. Proper Concrete Mix.
d. Pre-Saturated Aggregates
23 You are asked to construct a massive dam. The type of cement you will use is:
a. Ordinary Portland Cement
b. Rapid Hardening Cement
c. Low Heat Cement
d. Blast Furnace Slag Cement
Page 4 of 5
Cost Control Department
24 Specified compressive strength of concrete is obtained from cube tests at the end of:
a. 3 Days
b. 7 Days
c. 14 Days
d. 28 Days
25 The grade of concrete M150 means tha compressive strength of a 15 cube after 28 days is
a. 100 Kg/Cm²
b. 150 Kg/Cm²
c. 200 Kg/Cm²
d. 250 Kg/Cm²
26 The main object of compaction of concete is
a. To Elimate Air Holes
b. To Achieve Maximum Density
c. To Provide Intimate Contact Between The Concrete And Embedded Materials
d. All Of The Above
27 Strength of concrete with passage of time
a. Increases
b. Decreases
c. Fluctuates
d. Remains Constant
28
Consider the following statements in relation to the given sketch
1. Soil is partially saturated at degree of saturation = 60%
2. Void Ratio = 40%
3. Water Content = 30%
4. Saturated unit weight = 1.5 glcc
a. 1,2 And 3 Are Correct
b. 1,3 And 4 Are Correct
c. 2,3 And 4 Are Correct
d. 1,2 And 4 Are Correct
29 The structure shown in the given figure is stable if
a. X = 2Y
b. 2X = Y
c. √2
d. X = √2 Y
30
Active earth pressure per meter length on the retaining wall with a smooth vertical back as shown in the
given figure will be
a. 81+
b. 2+
c. 27+
d. 1+
Page 5 of 5

More Related Content

Similar to Mmup questionnaire 5

Mmup questionnaire 8
Mmup questionnaire 8Mmup questionnaire 8
Mmup questionnaire 8
Omar Selim
 
2.concrete technology
2.concrete technology2.concrete technology
2.concrete technology
Mani Das
 
1. Which section of a contract contains guidelines that ensure f.docx
1.   Which section of a contract contains guidelines that ensure f.docx1.   Which section of a contract contains guidelines that ensure f.docx
1. Which section of a contract contains guidelines that ensure f.docx
SONU61709
 
ME REVIEWER
ME REVIEWERME REVIEWER
ME REVIEWER
ArjayFernandez5
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)
Kezar Ali. Shah
 
Retrofitting of RC members and repair works.pptx
Retrofitting of RC members and repair works.pptxRetrofitting of RC members and repair works.pptx
Retrofitting of RC members and repair works.pptx
DP NITHIN
 
1.Which section of a contract contains guidelines that ensure .docx
1.Which section of a contract contains guidelines that ensure .docx1.Which section of a contract contains guidelines that ensure .docx
1.Which section of a contract contains guidelines that ensure .docx
hacksoni
 
Aci mix design very good
Aci mix design very goodAci mix design very good
Aci mix design very good
axmedbaasaay
 
Ssc junior-engineer-question-papers-for-civil-7
Ssc junior-engineer-question-papers-for-civil-7Ssc junior-engineer-question-papers-for-civil-7
Ssc junior-engineer-question-papers-for-civil-7Preethi Divya
 
Concrete technology-questions
Concrete technology-questionsConcrete technology-questions
Concrete technology-questions
HimansuKunwar1
 
CONCRETE Design mix
CONCRETE Design mixCONCRETE Design mix
CONCRETE Design mix
MD AMANULLAH
 
Properities Of Plain & Slag Concrete
Properities Of Plain & Slag ConcreteProperities Of Plain & Slag Concrete
Properities Of Plain & Slag Concrete
PRAKASH KUMAR
 
MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)
Waseem Ahmad
 
Abhishek khandelwal
Abhishek khandelwalAbhishek khandelwal
Abhishek khandelwal
Abhishek17Khandelwal
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
MekonnenAyal
 
2008 - NOV.pdf
2008 - NOV.pdf2008 - NOV.pdf
2008 - NOV.pdf
EdmarTabinas1
 
ppt.pptx
ppt.pptxppt.pptx
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
Ganesh Tatikonda
 

Similar to Mmup questionnaire 5 (20)

Mmup questionnaire 8
Mmup questionnaire 8Mmup questionnaire 8
Mmup questionnaire 8
 
2.concrete technology
2.concrete technology2.concrete technology
2.concrete technology
 
1. Which section of a contract contains guidelines that ensure f.docx
1.   Which section of a contract contains guidelines that ensure f.docx1.   Which section of a contract contains guidelines that ensure f.docx
1. Which section of a contract contains guidelines that ensure f.docx
 
ME REVIEWER
ME REVIEWERME REVIEWER
ME REVIEWER
 
Terms
TermsTerms
Terms
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)
 
Retrofitting of RC members and repair works.pptx
Retrofitting of RC members and repair works.pptxRetrofitting of RC members and repair works.pptx
Retrofitting of RC members and repair works.pptx
 
Concrete mix design
Concrete mix designConcrete mix design
Concrete mix design
 
1.Which section of a contract contains guidelines that ensure .docx
1.Which section of a contract contains guidelines that ensure .docx1.Which section of a contract contains guidelines that ensure .docx
1.Which section of a contract contains guidelines that ensure .docx
 
Aci mix design very good
Aci mix design very goodAci mix design very good
Aci mix design very good
 
Ssc junior-engineer-question-papers-for-civil-7
Ssc junior-engineer-question-papers-for-civil-7Ssc junior-engineer-question-papers-for-civil-7
Ssc junior-engineer-question-papers-for-civil-7
 
Concrete technology-questions
Concrete technology-questionsConcrete technology-questions
Concrete technology-questions
 
CONCRETE Design mix
CONCRETE Design mixCONCRETE Design mix
CONCRETE Design mix
 
Properities Of Plain & Slag Concrete
Properities Of Plain & Slag ConcreteProperities Of Plain & Slag Concrete
Properities Of Plain & Slag Concrete
 
MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)
 
Abhishek khandelwal
Abhishek khandelwalAbhishek khandelwal
Abhishek khandelwal
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
 
2008 - NOV.pdf
2008 - NOV.pdf2008 - NOV.pdf
2008 - NOV.pdf
 
ppt.pptx
ppt.pptxppt.pptx
ppt.pptx
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 

More from Omar Selim

إعادة الإعمار .pdf
إعادة الإعمار .pdfإعادة الإعمار .pdf
إعادة الإعمار .pdf
Omar Selim
 
_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf
Omar Selim
 
SmartHome.pdf
SmartHome.pdfSmartHome.pdf
SmartHome.pdf
Omar Selim
 
_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf
Omar Selim
 
Ch-3.docx
Ch-3.docxCh-3.docx
Ch-3.docx
Omar Selim
 
ch-12.docx
ch-12.docxch-12.docx
ch-12.docx
Omar Selim
 
Ch-4.docx
Ch-4.docxCh-4.docx
Ch-4.docx
Omar Selim
 
ch8.docx
ch8.docxch8.docx
ch8.docx
Omar Selim
 
ch10.docx
ch10.docxch10.docx
ch10.docx
Omar Selim
 
ch-11.docx
ch-11.docxch-11.docx
ch-11.docx
Omar Selim
 
ch9.docx
ch9.docxch9.docx
ch9.docx
Omar Selim
 
ch-13.docx
ch-13.docxch-13.docx
ch-13.docx
Omar Selim
 
Ch-5.docx
Ch-5.docxCh-5.docx
Ch-5.docx
Omar Selim
 
Ch-2.docx
Ch-2.docxCh-2.docx
Ch-2.docx
Omar Selim
 
ch-6.docx
ch-6.docxch-6.docx
ch-6.docx
Omar Selim
 
Ch-1.docx
Ch-1.docxCh-1.docx
Ch-1.docx
Omar Selim
 
all.docx
all.docxall.docx
all.docx
Omar Selim
 
BIMarabia12.pdf
BIMarabia12.pdfBIMarabia12.pdf
BIMarabia12.pdf
Omar Selim
 
BIMarabia22.pdf
BIMarabia22.pdfBIMarabia22.pdf
BIMarabia22.pdf
Omar Selim
 
BIMarabia16.pdf
BIMarabia16.pdfBIMarabia16.pdf
BIMarabia16.pdf
Omar Selim
 

More from Omar Selim (20)

إعادة الإعمار .pdf
إعادة الإعمار .pdfإعادة الإعمار .pdf
إعادة الإعمار .pdf
 
_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf
 
SmartHome.pdf
SmartHome.pdfSmartHome.pdf
SmartHome.pdf
 
_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf_الذكاء الاصطناعي .pdf
_الذكاء الاصطناعي .pdf
 
Ch-3.docx
Ch-3.docxCh-3.docx
Ch-3.docx
 
ch-12.docx
ch-12.docxch-12.docx
ch-12.docx
 
Ch-4.docx
Ch-4.docxCh-4.docx
Ch-4.docx
 
ch8.docx
ch8.docxch8.docx
ch8.docx
 
ch10.docx
ch10.docxch10.docx
ch10.docx
 
ch-11.docx
ch-11.docxch-11.docx
ch-11.docx
 
ch9.docx
ch9.docxch9.docx
ch9.docx
 
ch-13.docx
ch-13.docxch-13.docx
ch-13.docx
 
Ch-5.docx
Ch-5.docxCh-5.docx
Ch-5.docx
 
Ch-2.docx
Ch-2.docxCh-2.docx
Ch-2.docx
 
ch-6.docx
ch-6.docxch-6.docx
ch-6.docx
 
Ch-1.docx
Ch-1.docxCh-1.docx
Ch-1.docx
 
all.docx
all.docxall.docx
all.docx
 
BIMarabia12.pdf
BIMarabia12.pdfBIMarabia12.pdf
BIMarabia12.pdf
 
BIMarabia22.pdf
BIMarabia22.pdfBIMarabia22.pdf
BIMarabia22.pdf
 
BIMarabia16.pdf
BIMarabia16.pdfBIMarabia16.pdf
BIMarabia16.pdf
 

Recently uploaded

Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
Assignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docxAssignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docx
ArianaBusciglio
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
TechSoup
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
kitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptxkitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptx
datarid22
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
Reflective and Evaluative Practice...pdf
Reflective and Evaluative Practice...pdfReflective and Evaluative Practice...pdf
Reflective and Evaluative Practice...pdf
amberjdewit93
 
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
NelTorrente
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
tarandeep35
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
goswamiyash170123
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
Krisztián Száraz
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 

Recently uploaded (20)

Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
Assignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docxAssignment_4_ArianaBusciglio Marvel(1).docx
Assignment_4_ArianaBusciglio Marvel(1).docx
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
kitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptxkitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptx
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
Reflective and Evaluative Practice...pdf
Reflective and Evaluative Practice...pdfReflective and Evaluative Practice...pdf
Reflective and Evaluative Practice...pdf
 
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 

Mmup questionnaire 5

  • 1. Question No. 1 2 3 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 : 30 MMUP Review Exam - Answer Key Name: ID.No:
  • 2. Question No. A B C D 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 : 30 MMUP Review Exam - Answer Sheet Name: EMP.No:
  • 3. Cost Control Department : MMUP Review Exam Name: EMP No. Project: Date: Page 1 of 5
  • 4. Cost Control Department 1 The Performance of a specific task in CPM is known as: a. Dummy b. Event c. Activity d. Contract 2 Completion of an activity on CPM network diagram is generally known as: a. Event b. Node c. Connector d. All Of The Above. 3 Pick up the incorrect statement from the following: a. The Activity Is The Time Consuming Part Of A Project. b. The Beginning And The End Of A Job Are Called Events. c. The Activity Which Consumes Maximum Time Is Called Anode. d. Logically And Sequentially Connected Activities And Events From A Network 4 The time by which activity completion time can be delayed without affecting the start of succeeding activities is known as: a. Duration b. Total Float c. Free Float d. Interfering Float 5 The difference between the time available to do a job and the time required to do the job is known as: a. Event b. Float c. Duration d. Constrain 6 For completion of a project, the critical path of the network represents a. Minimum Time b. Maximum Time c. Maximum Cost d. Minimum Cost 7 The three time estimates for the activities fo the network shown in the given figure are shown above their arrows: The earliest expected time for the even 4 is: 3 - 4 - 5 5 - 7 - 9 6 - 8 - 10 a. 19 b. 14 c. 24 d. None Of Those 1 2 3 4 Page 2 of 5
  • 5. Cost Control Department 8 A subcontractor has the task of erecting 8,400 sq2 of metal scaffolds. The contractor can use several crews with various cost. It is expected that the production will vary with the crew size as given below: Consider the following rates: Labor = $ 96/day; Carpenter = $ 128/day; Foreman = $ 144/day; Scaffolder = $60/day a. $ 76.22 /Day b. $ 33.252 /Day c. $ 70.00 /Day d. None Of The Above. 9 Assume you can lease an item you need for project for $ 800/day. To purchase the item the cost is $ 12,000 plus daily operational cost of $ 400/day. If you need the item for more than 30 days, it is more economical to: a. To Lease It b. To Purchase It 10 Reinforcing steel bars of T10 mm at 10 cm spacing to be replaced by T12 mm. Calculate the new required spacing a. 14.4 mm b. 6.9 mm c. 12 mm d. 8.3 mm 11 If a concrete beam is supported as continuous beam, the section at the support must be designated as: a. T-Beam b. Rectangular Beam c. Simply Supported Beam d. Flange Beam 12 Under normal conditions using an ordinary cement, the period of removal of the form work is: a. 7 Days For Beam Soffits b. 14 Days For Bottom Slabs Of Spans 4.6 M And More c. 21 Days For Bottom Beams Over 6 M Spans d. All Of The Above. 13 Permissible compressive strength of M 300 concrete grade is a. 100 Kg/ Cm2 b. 150 Kg/ Cm2 c. 200 Kg/ Cm2 d. 300 Kg/ Cm2 14 Mass concrete is defined as the concrete where: (QCS) a. The Dimension Is Equal To 1.5 M b. Where The Large Dimension Exceeds 1.5 M c. The Least Dimension Exceeds 1.5 M d. None Of The Above. Page 3 of 5
  • 6. Cost Control Department 15 Temperature of fresh concrete should be: a. Not Exceeds 42 Degrees b. Equal To 40 Degrees c. Not Exceeds 32 Degrees d. None Of The Above. 16 Construction joint should be provided within: a. The Middle Third Of Spans b. At 1/3 To 1/4 Of Span In Slabs And Beams c. Where Bm And S.F. Are Small d. All Of The Above. 17 Curing: a. Reduces The Shrinkage Of Concrete b. Preserves The Properties Of Concrete c. Prevents The Loss Of Water By Evaporation d. All Of The Above. 18 The increased cohesiveness of concrete makes it: a. Less Liable To Segregation b. More Liable To Segregation c. More Liable To Bleeding d. More Liable For Surface Scaling In Frosty Weather 19 Workability improved by adding: a. Air-Entraining Agent b. Foaming Agent c. Oily-Agent d. All Of The Above. 20 Workability of concrete is measured by: a. Vicat Apparatus Test b. Slump Test c. Minimum Void Method d. Talbot Richart Test 21 According to the recommendation of IS 456-1978, the expansion joints: a. Are Provided Where Plane Changes Abruptly b. Are Provided To Ensure Minimum Resistance. c. Are Supported On Separate Columns d. All Of The Above. 22 Shrinkage in concrete can be reduced by using: a. Low Water Cement Ratio. b. Less Cement In The Concrete. c. Proper Concrete Mix. d. Pre-Saturated Aggregates 23 You are asked to construct a massive dam. The type of cement you will use is: a. Ordinary Portland Cement b. Rapid Hardening Cement c. Low Heat Cement d. Blast Furnace Slag Cement Page 4 of 5
  • 7. Cost Control Department 24 Specified compressive strength of concrete is obtained from cube tests at the end of: a. 3 Days b. 7 Days c. 14 Days d. 28 Days 25 The grade of concrete M150 means tha compressive strength of a 15 cube after 28 days is a. 100 Kg/Cm² b. 150 Kg/Cm² c. 200 Kg/Cm² d. 250 Kg/Cm² 26 The main object of compaction of concete is a. To Elimate Air Holes b. To Achieve Maximum Density c. To Provide Intimate Contact Between The Concrete And Embedded Materials d. All Of The Above 27 Strength of concrete with passage of time a. Increases b. Decreases c. Fluctuates d. Remains Constant 28 Consider the following statements in relation to the given sketch 1. Soil is partially saturated at degree of saturation = 60% 2. Void Ratio = 40% 3. Water Content = 30% 4. Saturated unit weight = 1.5 glcc a. 1,2 And 3 Are Correct b. 1,3 And 4 Are Correct c. 2,3 And 4 Are Correct d. 1,2 And 4 Are Correct 29 The structure shown in the given figure is stable if a. X = 2Y b. 2X = Y c. √2 d. X = √2 Y 30 Active earth pressure per meter length on the retaining wall with a smooth vertical back as shown in the given figure will be a. 81+ b. 2+ c. 27+ d. 1+ Page 5 of 5