This document provides an overview and guidance for municipalities on developing microgrids. It discusses site selection factors, engaging utilities, identifying critical loads, generation sources, controls, and interconnection processes. The presentation emphasizes safety, reliability, and cost effectiveness of microgrids. Interconnection requires coordination with utilities and adherence to technical standards for both grid-connected and island modes of operation.
4. 4
Microgrid Development – Site selection
Multiple critical facilities
Physical location – within reasonable walking distance
Widely spaced facilities with numerous non‐critical
sites interspersed will greatly increase cost of microgrid
Widely spaced facilities with numerous non‐critical
sites between will greatly increase cost of microgrid
Are all microgrid facilities within a campus, or will
power have to cross public roads?
What does the Microgrid look like?
8. 8
Microgrid Development – Site selection
Meet with EDU/MEU
Questions to ask:
‐ Are all of the Critical Facilities now served from the same feeder circuit?
‐ What is the primary service voltage?
‐ How difficult (expensive) will it be to isolate these facilities from the rest
of the grid?
‐ What portions of the proposed microgrid would be constructed owed
and operated by the EDU/MEU?
‐ Will other customers be affected?
‐ What are the historical electrical demand loads for the critical facilities?
11. 11
Selection of Generation Sources
Efficiency
Environment
Fuel Source
‐ Non‐interruptible OR
‐ 2 week supply
Load following ability
Voltage and frequency source
‐ Most inverter based sources not grid independent.
Location within microgrid
‐ Central within microgrid preferable
‐ Single location preferable to scattered generators
‐ Noise and environmental concerns
‐ Thermal and other efficiency concerns.
Total generation capacity 120% of critical facility load.
18. The Interconnection Process
Scope:
‐ Scoping Meeting
‐ Review for grid connected mode(Normal Interconnection
process)
‐ Review of operational procedure (Joint Operation)
‐ Review in Island mode will include Protection, voltage,
frequency & short circuit impact
‐ Design Electrical distribution system to support Microgrid
‐ Design of communication system (SCADA)
Timelines: Depends on complexity of project
18
33. 33
Ways to mitigate slow ramp rates
Load bank
‐ Inefficient
Storage
‐ Efficient
‐ More effective use of generating capacity
‐ Expensive
‐ Can reduce spinning reserve requirements.
Base load vs. peaking units
‐ Slow ramping units operate at nearly constant load
‐ Load following done by generators with rapid response
capability
‐ Example: base load fuel cells with diesels used for load
following
35. 35
Microgrid Controls
Islanded Operation
System voltage and frequency controlled by microgrid generation
All instantaneous load peaks must be carried by microgrid
generation
All VAR demand must be met by microgrid generation
‐ Motor starting is a consideration
‐ Elevators
‐ Air conditioning equipment
‐ Refrigeration/ industrial loads.
‐ Inverters have little ability to handle VAR demand
‐ Synchronous generators best able to provide reserve VARs
36. 36
Microgrid Controls
Islanded Operation
Frequency must be controlled by generation
Microgrid must be able to absorb swings in load
Ramp rate of generators becomes an issue
How is load shared among multiple generators?
Isochronous vs. droop governing
Lower available fault current
‐ Will likely require different settings for protective relays
‐ Different short circuit coordination requirements
‐ Potentially greater arc‐flash requirements
37. 37
Microgrid Controls
Load management
Spinning reserve
120% of facility load
Load peak reduction
‐ Shedding of less critical loads
‐ Load shifting
‐ Load shedding response ‐ instantaneous (3‐5 cycles)
Contingency management
Partial generator loss
‐ Must reduce load immediately to less than 100% of on‐line
generation to avoid blackout
‐ Building EMS systems can not react fast enough to reduce load
39. 39
Microgrid Controls
Transition control
Grid Parallel to Island Operation
‐ Grid tie circuit breaker trips open
‐ Excess load shed if spinning generators have less capacity than
load. (high speed load shed)
‐ All generators switch from load control to frequency control
‐ All generators switch from power factor control to voltage
control
‐ Additional generation brought on‐line if needed.
‐ Previously shed loads can be restored, if microgrid has full
generation capacity
40. 40
Microgrid Controls
Transition control
Island Operation to Grid Parallel
‐ Generators adjust to match grid voltage
‐ Microgrid frequency and phase angle adjusted to match grid
‐ Grid tie circuit breaker closed
‐ Generators switch to load (output) control
‐ Generators switch from voltage to power factor control
‐ Excess generation can be shut down according to normal
operating schedule
‐ Any non‐critical loads shed during island operation can be
restored