SlideShare a Scribd company logo
Method Statement for Execution of the Civil Works for the 
Refurbishment of the Agricultural Laboratory of the University of 
Liberia 
· Receipt of Contract 
When the contract is awarded to City construction Inc. the following will be executed in a 
suitable and shortest time as per steps laid down below. 
The works that will be carried comprise of the following: 
· Carry out Pre-demolition and Refurbishment survey to identify all walls as shown in 
dotted line and concrete shell to be clean within the existing structure to be used as 
Main Laboratory Building. 
· Demolition of walls, clearing and storing debris for future use if necessary and 
preparation of site. 
· Excavation of new foundations. 
· Use of equipment to construct the existing and new buildings sub and superstructure. 
· Scaffolding 
· Consultants shall supervise these works, produce verification reports and carry out the 
necessary checking of materials and testing of concrete when required. 
1
Table of Contents 
□ General 
□ Pre-Construction 
□ Site Management 
□ Personnel 
□ Scaffolding 
□ Dust and Debris 
□ Working Hours 
□ Equipment for work 
□ Security and Warehouse 
2
 General 
This method statement has been prepared on the basis of the tender information as issued 
and gives an indication of our general approach to the construction and management of 
the project. 
We have included our intentions for managing and supporting the project and the 
particular approaches that will be taken for certain key aspects. 
 Pre-construction 
Prior to commencement of site works, an external survey will be carried out to confirm 
the existing site levels, extent of any existing services and the condition of the existing 
environs. 
These will be plotted on a drawing and a photographic record will be taken, which will be 
maintained as a record throughout the stages of the contract. 
 Site Establishment Managements 
The site establishment will be managed by the site supervisor who will be stationed at site until 
the project is completed. He will take steps for ensuring that all resources, man and materials 
are available at site in time. All of our site staff will be governed by rules and procedure of City 
Construction Inc.which will include the following: 
· Working conditions 
· Health and safety(All of our site staff will be tested before the work commencement of 
contract when awarded) 
· Conduct at site 
· Facilities at site 
● Reporting of site activities to head office on regular basis. 
Personnel 
All personnel will be inducted prior to gaining access to the site. They will be informed of the 
specific site rules required in the preliminaries relating to this project as well as City 
Construction Inc. site rules and their own companies method statement 
Listed below are key personnel that will be present on site: 
3
· Project Engineer (Civil Engineer) 
· Site Supervisor ( Civil Engineer) 
· Laborers 
· First Aiders (Nurse) 
· Employer Representative 
 Scaffolding 
Scaffoldings where required, will be independent to suit the nature; location and type of the 
particular operations. All scaffolding will be securely tied to the structure and will include 
suitable ladder access. Scaffolding will be provided, erected and maintained in accordance with 
all current statutory regulations. No person other than certified competent scaffolders will be 
permitted to erect, alter, adapt or dismantle any scaffolding. 
 Dust and Debris 
The site will be kept clean and tidy at all times and will accord with any statutory requirements. 
Particular attention will be given to preventing the contamination of existing water courses. 
 Working hour 
There will be one hour of break during every working day for lunch. All employees of ours will be 
identified with a tag symbolizing our company name and location with numbers on it. 
Time arrangement 8.00 am – 5.00pm Monday – Saturday (12noon-1:00pm lunch time) 
 Equipments for work 
These are equipments that will be used to execute the project when the contract is awarded to 
us. 
Excavator fitted with shears selector grab 
Demolition tracked machine fitted with controlled attachments tractor and towable water 
bower and jet spray for dust suppression 
4
4 utility mobiles for elevating demolished materials 
4 tankers for sucking of oil and fuel 
1 Water pumps 
 Security and Warehouse 
All necessary registers, diary, time book method statement, health and safety plan will be kept 
on site under the control of the project engineer and can be inspected at any time. All accidents 
are to be reported to and entered in the site accident book. 
A supply of spare hard hats, overalls, gloves, and goggles masks, all of these materials will be 
store on site. 
City Construction Inc. will ensure a high standard of health safety carried out at all times on site. 
All operatives on site must wear full PPE accordance with the health safety requirements 
including safety boots, hard hats and a high visibility vets or coat as standard. 
No smoking on site policy will be adhered to at all times; smoking will only take place in the site 
designated area. 
There will be private guards appointed to ensure that all properties and lives are well taken care 
of on site at all time. 
A temporary warehouse will be built when the contract is awarded to us before the start date of 
the contract for storage of materials that should not be exposing to water and etc. 
5
CONCLUSION 
The above method statement has been developed specifically to demonstrate our 
understanding of the project requirements and the detailed methodology required to carry 
out a project of this nature, in the most viable and safe manner to achieve a completed 
project to the satisfaction of all parties involved. 
6
CONCLUSION 
The above method statement has been developed specifically to demonstrate our 
understanding of the project requirements and the detailed methodology required to carry 
out a project of this nature, in the most viable and safe manner to achieve a completed 
project to the satisfaction of all parties involved. 
6

More Related Content

What's hot

Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
David H Moloney
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Minh Bui Si
 
Method of Statement - Road furniture works
Method of Statement - Road furniture worksMethod of Statement - Road furniture works
Method of Statement - Road furniture works
Mohd Nizam Mohd Zan
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In Construction
Sunil Manjeri
 
Material approval procedure
Material approval procedureMaterial approval procedure
Material approval procedure
Mohammad Eyaz Ansari
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
David H Moloney
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
Al-Amin Ahmed Nabin
 
Ms for concrete repairing
Ms for concrete repairingMs for concrete repairing
Ms for concrete repairing
Pham Dinh Thac
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
Dwarika Bhushan Sharma
 
Erection method statement
Erection method statementErection method statement
Erection method statement
kanalbiru
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
HaGun Gunawan
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
GERServices
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surfaceMinh Bui Si
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing Construction
Lek Yuen
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
DusanJankovic8
 
HSE Temporary works management plan
HSE Temporary works management planHSE Temporary works management plan
HSE Temporary works management plan
Dwarika Bhushan Sharma
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14Winter Sonata
 

What's hot (20)

Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0
 
Method of Statement - Road furniture works
Method of Statement - Road furniture worksMethod of Statement - Road furniture works
Method of Statement - Road furniture works
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In Construction
 
Material approval procedure
Material approval procedureMaterial approval procedure
Material approval procedure
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Ms for concrete repairing
Ms for concrete repairingMs for concrete repairing
Ms for concrete repairing
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
Erection method statement
Erection method statementErection method statement
Erection method statement
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing Construction
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
 
HSE Temporary works management plan
HSE Temporary works management planHSE Temporary works management plan
HSE Temporary works management plan
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14
 

Viewers also liked

072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
Dr Fereidoun Dejahang
 
Method Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial SystemsMethod Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial SystemsFernox
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
Mohd Nizam Mohd Zan
 
Rectangular tank example_latest
Rectangular tank example_latestRectangular tank example_latest
Rectangular tank example_latestVedachalam Mani
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
dhineshkumar002
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
IEI GSC
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workthanhuce
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
Surya Kant
 
Method statement painting
Method statement painting Method statement painting
Method statement painting
Daniel SLSA CLA
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 

Viewers also liked (12)

072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
 
Pca rectangular concrete tanks (1)
Pca rectangular concrete tanks (1)Pca rectangular concrete tanks (1)
Pca rectangular concrete tanks (1)
 
Method Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial SystemsMethod Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial Systems
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Rectangular tank example_latest
Rectangular tank example_latestRectangular tank example_latest
Rectangular tank example_latest
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-work
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Method statement painting
Method statement painting Method statement painting
Method statement painting
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 

Similar to METHOD STATEMENT

Seg 2 Fort Macon
Seg 2 Fort MaconSeg 2 Fort Macon
Seg 2 Fort Macon
StuartECU
 
CV of Safety Supervisor
CV of Safety SupervisorCV of Safety Supervisor
CV of Safety SupervisorMeghnath Baral
 
Construction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docxConstruction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docx
melvinjrobinson2199
 
Saqib Shahzad CV updated
Saqib Shahzad CV updatedSaqib Shahzad CV updated
Saqib Shahzad CV updatedSaqib Shahzad
 
Thesis on Pile Driving Management
Thesis on Pile Driving ManagementThesis on Pile Driving Management
Thesis on Pile Driving Management
rizwanshawlca
 
First engineering contracting
First engineering contractingFirst engineering contracting
First engineering contracting
MohamedAwaad23
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
mahmoud909178
 
Ernie Engr. Supervisor or Commissioning Engr. - Updated
Ernie Engr. Supervisor or Commissioning Engr. - UpdatedErnie Engr. Supervisor or Commissioning Engr. - Updated
Ernie Engr. Supervisor or Commissioning Engr. - UpdatedErnesto Costorio
 
CV-Joedon Cunanan (latest)
CV-Joedon Cunanan (latest)CV-Joedon Cunanan (latest)
CV-Joedon Cunanan (latest)Joedon Cunanan
 
Firstcool electromechanical works llc
Firstcool electromechanical works llcFirstcool electromechanical works llc
Firstcool electromechanical works llc
MohamedAwaad23
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Philip_Murray_ CV 13-01-16
Philip_Murray_  CV 13-01-16Philip_Murray_  CV 13-01-16
Philip_Murray_ CV 13-01-16Phil Murray
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
Enbridge Details Document
Enbridge Details DocumentEnbridge Details Document
Enbridge Details DocumentJohn Dawson
 
The Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction IndustryThe Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction Industry
Aussie Hydro-Vac Services
 

Similar to METHOD STATEMENT (20)

Short termim workplan_20100602_part3
Short termim workplan_20100602_part3Short termim workplan_20100602_part3
Short termim workplan_20100602_part3
 
Seg 2 Fort Macon
Seg 2 Fort MaconSeg 2 Fort Macon
Seg 2 Fort Macon
 
CVFTCabunoc
CVFTCabunocCVFTCabunoc
CVFTCabunoc
 
CV of Safety Supervisor
CV of Safety SupervisorCV of Safety Supervisor
CV of Safety Supervisor
 
Construction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docxConstruction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docx
 
Saqib Shahzad CV updated
Saqib Shahzad CV updatedSaqib Shahzad CV updated
Saqib Shahzad CV updated
 
"
""
"
 
Thesis on Pile Driving Management
Thesis on Pile Driving ManagementThesis on Pile Driving Management
Thesis on Pile Driving Management
 
First engineering contracting
First engineering contractingFirst engineering contracting
First engineering contracting
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
Ernie Engr. Supervisor or Commissioning Engr. - Updated
Ernie Engr. Supervisor or Commissioning Engr. - UpdatedErnie Engr. Supervisor or Commissioning Engr. - Updated
Ernie Engr. Supervisor or Commissioning Engr. - Updated
 
CV-Joedon Cunanan (latest)
CV-Joedon Cunanan (latest)CV-Joedon Cunanan (latest)
CV-Joedon Cunanan (latest)
 
Firstcool electromechanical works llc
Firstcool electromechanical works llcFirstcool electromechanical works llc
Firstcool electromechanical works llc
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Philip_Murray_ CV 13-01-16
Philip_Murray_  CV 13-01-16Philip_Murray_  CV 13-01-16
Philip_Murray_ CV 13-01-16
 
1.0 Company Profile
1.0 Company Profile1.0 Company Profile
1.0 Company Profile
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
ALAQ ALEZDEHAR1
ALAQ ALEZDEHAR1ALAQ ALEZDEHAR1
ALAQ ALEZDEHAR1
 
Enbridge Details Document
Enbridge Details DocumentEnbridge Details Document
Enbridge Details Document
 
The Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction IndustryThe Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction Industry
 

METHOD STATEMENT

  • 1. Method Statement for Execution of the Civil Works for the Refurbishment of the Agricultural Laboratory of the University of Liberia · Receipt of Contract When the contract is awarded to City construction Inc. the following will be executed in a suitable and shortest time as per steps laid down below. The works that will be carried comprise of the following: · Carry out Pre-demolition and Refurbishment survey to identify all walls as shown in dotted line and concrete shell to be clean within the existing structure to be used as Main Laboratory Building. · Demolition of walls, clearing and storing debris for future use if necessary and preparation of site. · Excavation of new foundations. · Use of equipment to construct the existing and new buildings sub and superstructure. · Scaffolding · Consultants shall supervise these works, produce verification reports and carry out the necessary checking of materials and testing of concrete when required. 1
  • 2. Table of Contents □ General □ Pre-Construction □ Site Management □ Personnel □ Scaffolding □ Dust and Debris □ Working Hours □ Equipment for work □ Security and Warehouse 2
  • 3.  General This method statement has been prepared on the basis of the tender information as issued and gives an indication of our general approach to the construction and management of the project. We have included our intentions for managing and supporting the project and the particular approaches that will be taken for certain key aspects.  Pre-construction Prior to commencement of site works, an external survey will be carried out to confirm the existing site levels, extent of any existing services and the condition of the existing environs. These will be plotted on a drawing and a photographic record will be taken, which will be maintained as a record throughout the stages of the contract.  Site Establishment Managements The site establishment will be managed by the site supervisor who will be stationed at site until the project is completed. He will take steps for ensuring that all resources, man and materials are available at site in time. All of our site staff will be governed by rules and procedure of City Construction Inc.which will include the following: · Working conditions · Health and safety(All of our site staff will be tested before the work commencement of contract when awarded) · Conduct at site · Facilities at site ● Reporting of site activities to head office on regular basis. Personnel All personnel will be inducted prior to gaining access to the site. They will be informed of the specific site rules required in the preliminaries relating to this project as well as City Construction Inc. site rules and their own companies method statement Listed below are key personnel that will be present on site: 3
  • 4. · Project Engineer (Civil Engineer) · Site Supervisor ( Civil Engineer) · Laborers · First Aiders (Nurse) · Employer Representative  Scaffolding Scaffoldings where required, will be independent to suit the nature; location and type of the particular operations. All scaffolding will be securely tied to the structure and will include suitable ladder access. Scaffolding will be provided, erected and maintained in accordance with all current statutory regulations. No person other than certified competent scaffolders will be permitted to erect, alter, adapt or dismantle any scaffolding.  Dust and Debris The site will be kept clean and tidy at all times and will accord with any statutory requirements. Particular attention will be given to preventing the contamination of existing water courses.  Working hour There will be one hour of break during every working day for lunch. All employees of ours will be identified with a tag symbolizing our company name and location with numbers on it. Time arrangement 8.00 am – 5.00pm Monday – Saturday (12noon-1:00pm lunch time)  Equipments for work These are equipments that will be used to execute the project when the contract is awarded to us. Excavator fitted with shears selector grab Demolition tracked machine fitted with controlled attachments tractor and towable water bower and jet spray for dust suppression 4
  • 5. 4 utility mobiles for elevating demolished materials 4 tankers for sucking of oil and fuel 1 Water pumps  Security and Warehouse All necessary registers, diary, time book method statement, health and safety plan will be kept on site under the control of the project engineer and can be inspected at any time. All accidents are to be reported to and entered in the site accident book. A supply of spare hard hats, overalls, gloves, and goggles masks, all of these materials will be store on site. City Construction Inc. will ensure a high standard of health safety carried out at all times on site. All operatives on site must wear full PPE accordance with the health safety requirements including safety boots, hard hats and a high visibility vets or coat as standard. No smoking on site policy will be adhered to at all times; smoking will only take place in the site designated area. There will be private guards appointed to ensure that all properties and lives are well taken care of on site at all time. A temporary warehouse will be built when the contract is awarded to us before the start date of the contract for storage of materials that should not be exposing to water and etc. 5
  • 6. CONCLUSION The above method statement has been developed specifically to demonstrate our understanding of the project requirements and the detailed methodology required to carry out a project of this nature, in the most viable and safe manner to achieve a completed project to the satisfaction of all parties involved. 6
  • 7. CONCLUSION The above method statement has been developed specifically to demonstrate our understanding of the project requirements and the detailed methodology required to carry out a project of this nature, in the most viable and safe manner to achieve a completed project to the satisfaction of all parties involved. 6