SlideShare a Scribd company logo
INTERNSHIP
INTRODUCTION
• Engineering is the professional art of applying science to the optimum conversion of
the resources of nature to benefit man.
• The internship at Cochin Shipyard,DMRC and Vytilla helped in bridging the gap
between theory and practice and provided practical,field based and real world
experience.
C O C H I N
S H I P YA R D
L I M I T E D
( C S L )
COCHIN SHIPYARD
• Started on Dec 3 and ended on Dec 15
• On the first day of our internship there,an introduction video was showed which
highlighted the need and importance of safety at construction site.
• During these days we also got the opportunity to visit the construction site of INS
Vikrant(R11).It is the first aircraft carrier built in India.
• The remaining days were scheduled to visit the Infra Projects Department.There we
had an opportunity to visit the two main ongoing projects under the department.
 Dry Dock
ISRF
NEW DRY DOCK PROJECT
• At present CSL has two dry dock has two dry dock.One predominantly used
for ship building,of size 255m X 43m X 9m and capacity 1,10,000 DWT and
other for ship repair of size 270m X 45m X 12mand capacity 1,25,000 DWT
• This third dry dock of northern end of existing CSL yard with size of 310m X
75/60m X 13m will be the largest of dry dock in CSL to enhance capability
to take up construction maritime equipments such as rigs to be repaired
or constructed at the wider part of the dock.
• The new dry dock will be equipped with one gantry crane of capacity
600T,two LLTT cranes of capacity 75T and other allied facilities .
• The estimated cost of total dry dock project is Rs.1799 crores.
• The new dry dock project is in line with the “Make in INDIA ” programme of
govt. of India, which promotes creation of additional ship building and
repair facilities.
• Employer:CSL
• Engineer: Royal Haskoning DHV
• Contractor: L&T
• The duration of the work is 36 months and the tentative data of
completionis 31st May 2021.
• The main works taking place are
Piling
PVD
Cofferdam
PILING
• Construction Procedure
Bored pile with temporary casing using polymer system consists of three
main stages,which are :surveying,boring,reinforcing and casting.
Surveying works
 For the fixation of piles, standard reference points are used.Atleast two
reference points is required for coordinate system and atleast one
reference point is for standard level.
 Using precise survey instrument like total station,coordinates of pile is
fixed on ground with respect to standard coordinates.
 Before starting piling work coordinates are verified again to minimise
location error.
Reinforcement Cages
 Steel reinforcement cages will be prepared according to approved drawings and
materials.Bundle bars consisting of three steel bars are used for reinforcing.
 A lap length of 5d is adopted.Both welding and coupling is used for lapping the bars
.For providing coupler,bars undergoes cutting,forging and threading.Reducing couplers
are used to join bars of different diameter.Vizag steel of length 24m are used in the site.
Boring
 A temporary short steel casing of depth 9m is installed for guiding in boring of pile.It
also supports top loose soil and prevents collapse due to machine movement and
vibration.The diameter of casing is 2m.
 Piles were drilled using hydraulic hydraulic rotating rig.Borehole is filled with polymeric
slurry which is prepared and stored in special tanks.This slurry will maintain stability by
providing a thin film coatingin the borehole wall.
 Properties of polymer mix
Viscosity: >55sec
pH value: 9-12
Sand content : <3%
Density: 1-1.06 g/cc
Placing of reinforcement
 When founding level has been reached ,steel reinforcing cage will be
lowered into the borehole.Concrete spacers are used ensure that it is
located centrally.
Placing of Concrete
 The principle used here is that when the concrete of densith 2400kg/cm3
is poured into the borehole,the polymer with lower density gets displaced
from the bottom.After concreting the temporary casing is pulled out.
• The total number of piles is 5200.Out of which 1210piles were
completed.Around700 are anchor piles and remaining bearing piles.
• Bearing piles are provided to take up compressive load.
• Sheet piles are provided throughout,these are anchored into pile cap of
anchor piles using rods.These take up tension.
PVD
• The entire area is divided into six zones namely A,B,C,D,E &F and a granular
layer of 500mm is laid.
• PVD is installed with 1m c/c spacing in triangular pattern.A non-woven
geotextile is laid above that.as per design 4.5m thick surcharge was placed
over geotextile.
• The entire setup facilitate vertical as well as radial consolidation.The water
drained is collected in the drains at the sides..
• The zones A,B and C are placed in single stage(26 weeks).For the zones D &E
surcharge were placed in 3 stages (32 weeks)
• 4 vibrating wire piezometers were installed at each zones with one at the
center.6 settlement gauges were installed in each zone.
• PVDs are installed to reduce active pressure on the dock walls.
PVD Installation
ISRF
• Cochin Port Trust has a small dry dock and marine workshop at the
southern end of Willington Island,facing Mattancherry channel.It is for
reparing and maintenance of small vessels.
• ISRF is a brownfield project since ship repair activities are presently
progressing in dry dock and marine workshop.As a part of modernization
CSL is presently in the process of setting up a shiplift and transfer system of
6000T lifting capacity.
• The project cost is estimated to be 970 crores .Repairs of around 85 vessels
per are expected once the facility becomes fully operational.
• Location : Willington Island
• Engineer : Marine work - Inros-lackner (German based)
• : Land work - Tata Consultancy Engineers Ltd.
• Contractor : Simplex Constructions
• Commencement : 17 November 2017
• Duration : 24 months
• Estimated cost : 970 crore Rupees
GEOTECHNICAL INVESTIGATION
• A geotechnical investigation was conducted at the marine boreholes.It was
proposed take 14 boreholes.
• Soil investigation was entrusted to M/S Engineer’s Diagnostic Centre(Pvt)
Limited,Cochin.This pact deals with ground investigation works to find out
an ideal foundation for the proposed project.
• The works included site reconnaissance, drilling and sampling of boreholes,
conducting field and lab tests and the report preparation.
• The primary purpose of these activities was to collect subsurface
information at site for design of foundations for the proposed work.
FIELD EXPLORATION AND TESTING
• Boring was done in accordance with the provisions of IS 1892-1979,using
rotary calyx rig technique which is mechanically operated.While drilling
through the top soil layers sodium bentonite slurry was circulated in order
to prevent the sides from collapsing.
• SPT were taken at various depths using standard split spoon sampler as
per IS 2131-1981.The number of blows required to penetrate first 15cm is
for seating and is not considered for assessing strength characteristics.
• Results are recorded in borelog.Soil sample is collected in plastic bags for
visual inspection and classification of strata.
• Samples obtained from samplers are tested for :strength and properties
to classify strata.
• Moisture content(IS 2720 Part II-1973)
Water content is an important index for establishing relation between
soil properties and behaviour. Consistency of fine grained soil
depends upon its water content. It is used in expressing phase
relations.
• Grain Size Distribution(IS 2720 Part IV-1985)
Both sieve analysis and hydrometer analysis were conducted on
different samples and findings are tabulated.Particle diameter span
many orders of magnitude for natural sediments so base to log scale
was used to represent grain size information for sediment
distribution.
• Specific Gravity(IS 2720 Part III 1980)
It was determined using pycnometer or density bottle.
• The total area of site is 42 acres out of which 14 acres is covered by water.
Marine and land piling works are now progressing. Total piles are 1688 in
number. In this there are 722 marine piles and 966 land piles. Following
super structures are also under construction:
1. Security cabin
2. Main electrical substation
3. Paint store
4. Mains receiving station
5. Compressor shed
6. Toilet block
7. Acetylene station
• In addition to this a 1.3 km long compound wall is under construction.
• Plum concrete is used in the compound wall and foundation of
superstructure.
• Basically, plum means large sized aggregates (boulders) that are rubbles of
180-210mm size.
• These are adopted if large sized top aggregates are not available. Strength
will be same as rubble masonry.
• Here alternate layers are made with PCC and rubbles of mentioned size. Out
of total 100%, 60% will be concrete and rest 40% aggregate.
• Concrete of this type is called plum concrete. Here M15 grade concrete is
used as PCC.
PILING
• For both land and marine piling casing used are permanent and they are
made at the site by rolling metallic sheets of 8mm thickness and welding
them together.
• Casing is provided only up to 20m depth. Instead of using
polymer,bentonite slurry is used which helps in flushing the bore hole
and also supports the unlined soil with the formation of thin film.
• Piles of 1m, 1.2m and 1.5m diameters are used at different areas and
depth of pile in both marine and land areas vary from 46 to 61m. For
M30 and M40 grade concrete, an admixture is used.
• It is Auramix 400 by Forsoc. Auramix 400 is an advanced low viscosity,
high performance super plasticizer, based on polycarboxylic technology.
• The properties are:
Appearance: Light yellow coloured liquid
 pH: Minimum 6.0
 Chloride content: Nil to IS: 456
 Alkali content: Typically, less than 1.5g Na2O equivalent/litre of
admixture
 Normal dosage range: Between 0.5 to 3.0 litres/100kg of cementitious
mate
D E L H I M E T R O
R A I L
C O R P O R AT I O N
( D M R C )
• The Delhi Metro Rail Corporation (DMRC) is a state-owned company that
operates the Delhi Metro in the National Capital Region of India.
• DMRC undertakes the planning and implementation of metro rail, mono rail
and high-speed rail projects in India.
• In Kerala the DMRC undertakes the construction of Kochi Metro.
• Geometrical design norms are based on international practices adopted for
similar metro systems
• assumption maximum permissible speed on the section = 80 km.
• Tracks will be carried on U-shaped elevated decking supported by single
circular piers generally spaced at 28 m centres
• Track centre on the elevated section will be 3.7 m on portions of tracks which
are straight or having curvature up to radius of 150 m.
• Track centre will be increased to 4 m on curves with radius sharper than 150 m.
PILE CONSTRUCTION
• Deep foundation
• Piles of diameter 1 & 1.2m are used in this project.
• The maxim m height of the pile is 42 m.
• M40 grade concrete is used for the construction of piles.
BORED CAST IN SITU PILE
• Digging a hole in the ground by rotary method with the use of temporary casing
• Total Station is used to set out pile position
• Drive steel casing to a minimum a depth of 1 m below the ground level to take
lateral loads and movements at site
• Soil samples from each intermediate soil strata at different depths are taken for
soil tests.
• reinforcement cage is lowered into to the borehole vertically, without disturbing
the sides of the hole.
• cover blocks are provided all around the cage
• Stirrups, stiffeners and laps are then welded to prevent
breakage.
• tremie method of piling is adopted -to bring the
concrete through a pipe to the interior of the concrete
being poured, thus preventing contact with the
surrounding water.
• Concrete is continuously fed to the tremie pipe-
through a hopper and the pipe is lifted as the concrete
level rises.
• Concrete is added continuously until the pouring is
completed.
PILE CAP CONSTRUCTION:
Pile Cap: A reinforced concrete slab or block which interconnects a group of
piles and acts as a medium to transmit the load from wall or column to the
Piles
• 4 pile cap and 6 pile cap reinforcement works were in progress
• designed like a footing on soil but instead of uniform reaction from the
soil, the reactions in this case are concentrated either point loads or
distributed.
UNDER REAMED
PILE
CONSTRUCTION
SITE
DETAILS ABOUT THE PROJECT
• The site was at Vytilla and the proposed work was the construction of a 3 storey
building. The pile depth was 12 m at the site. A sum total of 63 piles are required
in this project and among these 11 piles were completed before our site visit.
• The pile diameter adopted was 50 cm and the bulb diameter was 60 cm. The
concrete used for the pile was M50 and the reinforcement of 12 mm diameter
along with 8 mm diameter rings were provided.
• The piles were either single under reamed or double under reamed, which
depended on the sand content and the depth at which clay layer occurred.
• Auger boring is done on the site up to the depth of 12 m and bulb is given at a
distance of 50 cm from the bottom of the pile (Bottom bulb). If double under
reamed pile was installed the next bulb was given near clay layer.
UNDER REAMED PILE
• Under reamed piles are bored cast-in-situ concrete piles having one or more
number of bulbs formed by enlarging the pile stem.
• These piles are best suited in soils where considerable ground movements
occur due to seasonal variations, filled up grounds or in soft soil strata.
• Provision of under reamed bulbs has the advantage of increasing the bearing
and uplift capacities.
• It also provides better anchorage at greater depths.
• These piles are efficiently used in machine foundations, over bridges, electrical
transmission tower foundation sand water tanks.
• Indian Standard IS 2911 (Part III) - 1980 covers the design and construction of
under reamed piles having one or more bulbs.
• According to the code the diameter of under reamed bulbs may vary from 2 to 3
times the stem diameter depending upon the feasibility of construction and design
requirements.
• The code suggests a spacing of 1.25 to 1.5 times the bulb diameter for the bulbs. An
angle of 450 with horizontal is recommended for all under reamed bulbs.
• The code also gives mathematical expressions for calculating the bearing and uplift
capacities.
CONSTRUCTION OF UNDER REAMED
PILE
• Under reamed piles are bored cast-in-situ concrete piles having one or more
number of bulbs formed by enlarging the pile stem.
• These piles are best suited in soils where considerable ground movements occur
due to seasonal variations, filled up grounds or in soft soil strata.
• Provision of under reamed bulbs has the advantage of increasing the bearing
and uplift capacities.
• It also provides better anchorage at greater depths.
• The process consists of various stages involving: boring by augers, under reaming by under-reamer,
placing reinforcement cage in position, concreting of pile, concreting of pile caps, plinth beams and
curtain walls.
Stages in Construction of Under Reamed Pile
• The equipment required for construction of pile are
Auger boring guide
Spiral auger with extension rods
Under reamer with soil bucket
Concreting funnel
• The use of boring guide is necessary to keep bore holes vertical and also in
position.
• After setting the guide assembly in position, the spiral auger is introduced into the
circular collar of the by opening out two sets flaps of the guide assembly.
• The auger is pressed down and rotated manually until the spirals are half full of
earth. The auger is then taken out and earth removed.
• The boring process is repeated till the required depth is reached.
• Under reaming or enlarging the stem of bore hole at required depth is achieved by
means of the under reamer consisting of a set of two collapsible blades assembly
fixed around the central shaft and a detachable bucket for receiving cut soil.
• The equipment is attached to extension rods and lowered down the hole which has
been bored to the required depth, until the bucket rests at the bottom of the bore
hole.
• The guide flaps are then closed. The tool is pressed down constantly and rotated
slowly.
• The cutting blades of the tool widen out and start cutting sides of hole. The loose
earth is collected in a bucket at the bottom.
• When bucket is full, the assembly is pulled out and bucket is emptied. The depth of
the of bore hole is checked each time before insertion of under reamer so that any
loose earth spilled from the bucket is removed.
Under Reamer
THANK YOU

More Related Content

What's hot

Vacuum consolidation method worldwide practice and the lastest improvement ...
Vacuum consolidation method   worldwide practice and the lastest improvement ...Vacuum consolidation method   worldwide practice and the lastest improvement ...
Vacuum consolidation method worldwide practice and the lastest improvement ...
John Tran
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground Improvement
ADFIAP
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
IEI GSC
 
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
Sukesh Nayak
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Sravan Muguda
 
Flyash in geotechnical engineering
Flyash in geotechnical engineeringFlyash in geotechnical engineering
Flyash in geotechnical engineering
Niranjan Reddy
 
W16 ground improvement techniques-dycus
W16 ground improvement techniques-dycusW16 ground improvement techniques-dycus
W16 ground improvement techniques-dycus
APWA Florida Chapter 2013 Annual Meeting and Trade Show
 
Horticulture and landscape
Horticulture and landscapeHorticulture and landscape
Horticulture and landscape
Rajiva Gupta
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
Satish Kambaliya
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Andy Sugianto
 
ground control and improvement, Xanthakos , 1994
ground control and improvement, Xanthakos , 1994ground control and improvement, Xanthakos , 1994
ground control and improvement, Xanthakos , 1994
8621
 
Latest technology used for underwater lining of canal
Latest technology used for underwater lining of canalLatest technology used for underwater lining of canal
Latest technology used for underwater lining of canal
Shivam Mittal
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniques
AHMED NADIM JILANI
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel Bridge
Jill Reeves
 
Soil stabilization using fly ash & Rice husk ash
Soil stabilization using fly ash & Rice husk ashSoil stabilization using fly ash & Rice husk ash
Soil stabilization using fly ash & Rice husk ash
safiullah khan
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
ajinkya gaikwad
 
Recycling of the pavements
Recycling of the pavementsRecycling of the pavements
Recycling of the pavements
Bhavya Jaiswal
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
Moe Abadla
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
Begum Emte Ajom
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
Shubham Parab
 

What's hot (20)

Vacuum consolidation method worldwide practice and the lastest improvement ...
Vacuum consolidation method   worldwide practice and the lastest improvement ...Vacuum consolidation method   worldwide practice and the lastest improvement ...
Vacuum consolidation method worldwide practice and the lastest improvement ...
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground Improvement
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Flyash in geotechnical engineering
Flyash in geotechnical engineeringFlyash in geotechnical engineering
Flyash in geotechnical engineering
 
W16 ground improvement techniques-dycus
W16 ground improvement techniques-dycusW16 ground improvement techniques-dycus
W16 ground improvement techniques-dycus
 
Horticulture and landscape
Horticulture and landscapeHorticulture and landscape
Horticulture and landscape
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
 
ground control and improvement, Xanthakos , 1994
ground control and improvement, Xanthakos , 1994ground control and improvement, Xanthakos , 1994
ground control and improvement, Xanthakos , 1994
 
Latest technology used for underwater lining of canal
Latest technology used for underwater lining of canalLatest technology used for underwater lining of canal
Latest technology used for underwater lining of canal
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniques
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel Bridge
 
Soil stabilization using fly ash & Rice husk ash
Soil stabilization using fly ash & Rice husk ashSoil stabilization using fly ash & Rice husk ash
Soil stabilization using fly ash & Rice husk ash
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Recycling of the pavements
Recycling of the pavementsRecycling of the pavements
Recycling of the pavements
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 

Similar to May17

Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
KriShna Sharma
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
ARUNKUMARC39
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
Vicky Matwan
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
rakeshchoudhary129
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
Amir Amdani
 
Design construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteDesign construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concrete
Lữ Phát
 
mbl
mblmbl
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
Ravi Shankar
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallu
rohinibjn
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
Jaspreet singh
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
PPT DGFH.pptx
PPT DGFH.pptxPPT DGFH.pptx
PPT DGFH.pptx
RajeshKumar25548
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
Jaspreet singh
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Pervious or Porous Concrete
Pervious or Porous ConcretePervious or Porous Concrete
Pervious or Porous Concrete
MANUJ sinh
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
ktx500
 
Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docx
odiliagilby
 
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET Journal
 
Steps Involves in Building Construction
Steps Involves in Building ConstructionSteps Involves in Building Construction
Steps Involves in Building Construction
Adnan. Ali
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
Sandeep Reddy
 

Similar to May17 (20)

Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Design construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concreteDesign construction and behavior of bored cast in situ concrete
Design construction and behavior of bored cast in situ concrete
 
mbl
mblmbl
mbl
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallu
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
PPT DGFH.pptx
PPT DGFH.pptxPPT DGFH.pptx
PPT DGFH.pptx
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Pervious or Porous Concrete
Pervious or Porous ConcretePervious or Porous Concrete
Pervious or Porous Concrete
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docx
 
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
 
Steps Involves in Building Construction
Steps Involves in Building ConstructionSteps Involves in Building Construction
Steps Involves in Building Construction
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
 

More from tp jayamohan

COMPLAINTS AND APPEALS in Research examples from abroad
COMPLAINTS AND APPEALS in Research examples from abroadCOMPLAINTS AND APPEALS in Research examples from abroad
COMPLAINTS AND APPEALS in Research examples from abroad
tp jayamohan
 
research methodology
research methodologyresearch methodology
research methodology
tp jayamohan
 
prevention of flood using reataining wall
prevention of flood using reataining wallprevention of flood using reataining wall
prevention of flood using reataining wall
tp jayamohan
 
Flood modelling and prediction 1
Flood modelling and prediction 1Flood modelling and prediction 1
Flood modelling and prediction 1
tp jayamohan
 
Project
ProjectProject
Project
tp jayamohan
 
Body corctd
Body corctdBody corctd
Body corctd
tp jayamohan
 
Precautions cold weather
Precautions cold weatherPrecautions cold weather
Precautions cold weather
tp jayamohan
 
Self plan
Self planSelf plan
Self plan
tp jayamohan
 
elevation
elevationelevation
elevation
tp jayamohan
 
houseplan1 (1)
 houseplan1 (1) houseplan1 (1)
houseplan1 (1)
tp jayamohan
 
Internship front pages (3 files merged)
Internship front pages (3 files merged)Internship front pages (3 files merged)
Internship front pages (3 files merged)
tp jayamohan
 
sedimentation
sedimentationsedimentation
sedimentation
tp jayamohan
 
William john maquorn rankine
William john maquorn rankineWilliam john maquorn rankine
William john maquorn rankine
tp jayamohan
 
William john macquorn rankine
William john macquorn rankineWilliam john macquorn rankine
William john macquorn rankine
tp jayamohan
 
Utilization of jarosite generated from lead
Utilization of jarosite generated from leadUtilization of jarosite generated from lead
Utilization of jarosite generated from lead
tp jayamohan
 
Shahul
ShahulShahul
Shahul
tp jayamohan
 
Report
ReportReport
Report
tp jayamohan
 
Ousep abstract
Ousep  abstractOusep  abstract
Ousep abstract
tp jayamohan
 
Introduction presentation of project
Introduction presentation of projectIntroduction presentation of project
Introduction presentation of project
tp jayamohan
 
Considering soil
Considering soilConsidering soil
Considering soil
tp jayamohan
 

More from tp jayamohan (20)

COMPLAINTS AND APPEALS in Research examples from abroad
COMPLAINTS AND APPEALS in Research examples from abroadCOMPLAINTS AND APPEALS in Research examples from abroad
COMPLAINTS AND APPEALS in Research examples from abroad
 
research methodology
research methodologyresearch methodology
research methodology
 
prevention of flood using reataining wall
prevention of flood using reataining wallprevention of flood using reataining wall
prevention of flood using reataining wall
 
Flood modelling and prediction 1
Flood modelling and prediction 1Flood modelling and prediction 1
Flood modelling and prediction 1
 
Project
ProjectProject
Project
 
Body corctd
Body corctdBody corctd
Body corctd
 
Precautions cold weather
Precautions cold weatherPrecautions cold weather
Precautions cold weather
 
Self plan
Self planSelf plan
Self plan
 
elevation
elevationelevation
elevation
 
houseplan1 (1)
 houseplan1 (1) houseplan1 (1)
houseplan1 (1)
 
Internship front pages (3 files merged)
Internship front pages (3 files merged)Internship front pages (3 files merged)
Internship front pages (3 files merged)
 
sedimentation
sedimentationsedimentation
sedimentation
 
William john maquorn rankine
William john maquorn rankineWilliam john maquorn rankine
William john maquorn rankine
 
William john macquorn rankine
William john macquorn rankineWilliam john macquorn rankine
William john macquorn rankine
 
Utilization of jarosite generated from lead
Utilization of jarosite generated from leadUtilization of jarosite generated from lead
Utilization of jarosite generated from lead
 
Shahul
ShahulShahul
Shahul
 
Report
ReportReport
Report
 
Ousep abstract
Ousep  abstractOusep  abstract
Ousep abstract
 
Introduction presentation of project
Introduction presentation of projectIntroduction presentation of project
Introduction presentation of project
 
Considering soil
Considering soilConsidering soil
Considering soil
 

Recently uploaded

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 

Recently uploaded (20)

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 

May17

  • 2. INTRODUCTION • Engineering is the professional art of applying science to the optimum conversion of the resources of nature to benefit man. • The internship at Cochin Shipyard,DMRC and Vytilla helped in bridging the gap between theory and practice and provided practical,field based and real world experience.
  • 3. C O C H I N S H I P YA R D L I M I T E D ( C S L )
  • 4. COCHIN SHIPYARD • Started on Dec 3 and ended on Dec 15 • On the first day of our internship there,an introduction video was showed which highlighted the need and importance of safety at construction site. • During these days we also got the opportunity to visit the construction site of INS Vikrant(R11).It is the first aircraft carrier built in India. • The remaining days were scheduled to visit the Infra Projects Department.There we had an opportunity to visit the two main ongoing projects under the department.  Dry Dock ISRF
  • 5. NEW DRY DOCK PROJECT • At present CSL has two dry dock has two dry dock.One predominantly used for ship building,of size 255m X 43m X 9m and capacity 1,10,000 DWT and other for ship repair of size 270m X 45m X 12mand capacity 1,25,000 DWT • This third dry dock of northern end of existing CSL yard with size of 310m X 75/60m X 13m will be the largest of dry dock in CSL to enhance capability to take up construction maritime equipments such as rigs to be repaired or constructed at the wider part of the dock. • The new dry dock will be equipped with one gantry crane of capacity 600T,two LLTT cranes of capacity 75T and other allied facilities .
  • 6. • The estimated cost of total dry dock project is Rs.1799 crores. • The new dry dock project is in line with the “Make in INDIA ” programme of govt. of India, which promotes creation of additional ship building and repair facilities. • Employer:CSL • Engineer: Royal Haskoning DHV • Contractor: L&T • The duration of the work is 36 months and the tentative data of completionis 31st May 2021. • The main works taking place are Piling PVD Cofferdam
  • 7. PILING • Construction Procedure Bored pile with temporary casing using polymer system consists of three main stages,which are :surveying,boring,reinforcing and casting. Surveying works  For the fixation of piles, standard reference points are used.Atleast two reference points is required for coordinate system and atleast one reference point is for standard level.  Using precise survey instrument like total station,coordinates of pile is fixed on ground with respect to standard coordinates.  Before starting piling work coordinates are verified again to minimise location error.
  • 8. Reinforcement Cages  Steel reinforcement cages will be prepared according to approved drawings and materials.Bundle bars consisting of three steel bars are used for reinforcing.  A lap length of 5d is adopted.Both welding and coupling is used for lapping the bars .For providing coupler,bars undergoes cutting,forging and threading.Reducing couplers are used to join bars of different diameter.Vizag steel of length 24m are used in the site. Boring  A temporary short steel casing of depth 9m is installed for guiding in boring of pile.It also supports top loose soil and prevents collapse due to machine movement and vibration.The diameter of casing is 2m.  Piles were drilled using hydraulic hydraulic rotating rig.Borehole is filled with polymeric slurry which is prepared and stored in special tanks.This slurry will maintain stability by providing a thin film coatingin the borehole wall.  Properties of polymer mix Viscosity: >55sec pH value: 9-12 Sand content : <3% Density: 1-1.06 g/cc
  • 9. Placing of reinforcement  When founding level has been reached ,steel reinforcing cage will be lowered into the borehole.Concrete spacers are used ensure that it is located centrally. Placing of Concrete  The principle used here is that when the concrete of densith 2400kg/cm3 is poured into the borehole,the polymer with lower density gets displaced from the bottom.After concreting the temporary casing is pulled out. • The total number of piles is 5200.Out of which 1210piles were completed.Around700 are anchor piles and remaining bearing piles. • Bearing piles are provided to take up compressive load. • Sheet piles are provided throughout,these are anchored into pile cap of anchor piles using rods.These take up tension.
  • 10. PVD • The entire area is divided into six zones namely A,B,C,D,E &F and a granular layer of 500mm is laid. • PVD is installed with 1m c/c spacing in triangular pattern.A non-woven geotextile is laid above that.as per design 4.5m thick surcharge was placed over geotextile. • The entire setup facilitate vertical as well as radial consolidation.The water drained is collected in the drains at the sides.. • The zones A,B and C are placed in single stage(26 weeks).For the zones D &E surcharge were placed in 3 stages (32 weeks) • 4 vibrating wire piezometers were installed at each zones with one at the center.6 settlement gauges were installed in each zone. • PVDs are installed to reduce active pressure on the dock walls.
  • 12. ISRF • Cochin Port Trust has a small dry dock and marine workshop at the southern end of Willington Island,facing Mattancherry channel.It is for reparing and maintenance of small vessels. • ISRF is a brownfield project since ship repair activities are presently progressing in dry dock and marine workshop.As a part of modernization CSL is presently in the process of setting up a shiplift and transfer system of 6000T lifting capacity. • The project cost is estimated to be 970 crores .Repairs of around 85 vessels per are expected once the facility becomes fully operational.
  • 13. • Location : Willington Island • Engineer : Marine work - Inros-lackner (German based) • : Land work - Tata Consultancy Engineers Ltd. • Contractor : Simplex Constructions • Commencement : 17 November 2017 • Duration : 24 months • Estimated cost : 970 crore Rupees
  • 14. GEOTECHNICAL INVESTIGATION • A geotechnical investigation was conducted at the marine boreholes.It was proposed take 14 boreholes. • Soil investigation was entrusted to M/S Engineer’s Diagnostic Centre(Pvt) Limited,Cochin.This pact deals with ground investigation works to find out an ideal foundation for the proposed project. • The works included site reconnaissance, drilling and sampling of boreholes, conducting field and lab tests and the report preparation. • The primary purpose of these activities was to collect subsurface information at site for design of foundations for the proposed work.
  • 15. FIELD EXPLORATION AND TESTING • Boring was done in accordance with the provisions of IS 1892-1979,using rotary calyx rig technique which is mechanically operated.While drilling through the top soil layers sodium bentonite slurry was circulated in order to prevent the sides from collapsing. • SPT were taken at various depths using standard split spoon sampler as per IS 2131-1981.The number of blows required to penetrate first 15cm is for seating and is not considered for assessing strength characteristics. • Results are recorded in borelog.Soil sample is collected in plastic bags for visual inspection and classification of strata.
  • 16. • Samples obtained from samplers are tested for :strength and properties to classify strata. • Moisture content(IS 2720 Part II-1973) Water content is an important index for establishing relation between soil properties and behaviour. Consistency of fine grained soil depends upon its water content. It is used in expressing phase relations. • Grain Size Distribution(IS 2720 Part IV-1985) Both sieve analysis and hydrometer analysis were conducted on different samples and findings are tabulated.Particle diameter span many orders of magnitude for natural sediments so base to log scale was used to represent grain size information for sediment distribution. • Specific Gravity(IS 2720 Part III 1980) It was determined using pycnometer or density bottle.
  • 17. • The total area of site is 42 acres out of which 14 acres is covered by water. Marine and land piling works are now progressing. Total piles are 1688 in number. In this there are 722 marine piles and 966 land piles. Following super structures are also under construction: 1. Security cabin 2. Main electrical substation 3. Paint store 4. Mains receiving station 5. Compressor shed 6. Toilet block 7. Acetylene station
  • 18. • In addition to this a 1.3 km long compound wall is under construction. • Plum concrete is used in the compound wall and foundation of superstructure. • Basically, plum means large sized aggregates (boulders) that are rubbles of 180-210mm size. • These are adopted if large sized top aggregates are not available. Strength will be same as rubble masonry. • Here alternate layers are made with PCC and rubbles of mentioned size. Out of total 100%, 60% will be concrete and rest 40% aggregate. • Concrete of this type is called plum concrete. Here M15 grade concrete is used as PCC.
  • 19. PILING • For both land and marine piling casing used are permanent and they are made at the site by rolling metallic sheets of 8mm thickness and welding them together. • Casing is provided only up to 20m depth. Instead of using polymer,bentonite slurry is used which helps in flushing the bore hole and also supports the unlined soil with the formation of thin film. • Piles of 1m, 1.2m and 1.5m diameters are used at different areas and depth of pile in both marine and land areas vary from 46 to 61m. For M30 and M40 grade concrete, an admixture is used. • It is Auramix 400 by Forsoc. Auramix 400 is an advanced low viscosity, high performance super plasticizer, based on polycarboxylic technology.
  • 20. • The properties are: Appearance: Light yellow coloured liquid  pH: Minimum 6.0  Chloride content: Nil to IS: 456  Alkali content: Typically, less than 1.5g Na2O equivalent/litre of admixture  Normal dosage range: Between 0.5 to 3.0 litres/100kg of cementitious mate
  • 21. D E L H I M E T R O R A I L C O R P O R AT I O N ( D M R C )
  • 22. • The Delhi Metro Rail Corporation (DMRC) is a state-owned company that operates the Delhi Metro in the National Capital Region of India. • DMRC undertakes the planning and implementation of metro rail, mono rail and high-speed rail projects in India. • In Kerala the DMRC undertakes the construction of Kochi Metro. • Geometrical design norms are based on international practices adopted for similar metro systems • assumption maximum permissible speed on the section = 80 km. • Tracks will be carried on U-shaped elevated decking supported by single circular piers generally spaced at 28 m centres • Track centre on the elevated section will be 3.7 m on portions of tracks which are straight or having curvature up to radius of 150 m. • Track centre will be increased to 4 m on curves with radius sharper than 150 m.
  • 23.
  • 24. PILE CONSTRUCTION • Deep foundation • Piles of diameter 1 & 1.2m are used in this project. • The maxim m height of the pile is 42 m. • M40 grade concrete is used for the construction of piles.
  • 25. BORED CAST IN SITU PILE • Digging a hole in the ground by rotary method with the use of temporary casing • Total Station is used to set out pile position • Drive steel casing to a minimum a depth of 1 m below the ground level to take lateral loads and movements at site • Soil samples from each intermediate soil strata at different depths are taken for soil tests. • reinforcement cage is lowered into to the borehole vertically, without disturbing the sides of the hole.
  • 26. • cover blocks are provided all around the cage • Stirrups, stiffeners and laps are then welded to prevent breakage. • tremie method of piling is adopted -to bring the concrete through a pipe to the interior of the concrete being poured, thus preventing contact with the surrounding water. • Concrete is continuously fed to the tremie pipe- through a hopper and the pipe is lifted as the concrete level rises. • Concrete is added continuously until the pouring is completed.
  • 27. PILE CAP CONSTRUCTION: Pile Cap: A reinforced concrete slab or block which interconnects a group of piles and acts as a medium to transmit the load from wall or column to the Piles • 4 pile cap and 6 pile cap reinforcement works were in progress • designed like a footing on soil but instead of uniform reaction from the soil, the reactions in this case are concentrated either point loads or distributed.
  • 29. DETAILS ABOUT THE PROJECT • The site was at Vytilla and the proposed work was the construction of a 3 storey building. The pile depth was 12 m at the site. A sum total of 63 piles are required in this project and among these 11 piles were completed before our site visit. • The pile diameter adopted was 50 cm and the bulb diameter was 60 cm. The concrete used for the pile was M50 and the reinforcement of 12 mm diameter along with 8 mm diameter rings were provided. • The piles were either single under reamed or double under reamed, which depended on the sand content and the depth at which clay layer occurred. • Auger boring is done on the site up to the depth of 12 m and bulb is given at a distance of 50 cm from the bottom of the pile (Bottom bulb). If double under reamed pile was installed the next bulb was given near clay layer.
  • 30. UNDER REAMED PILE • Under reamed piles are bored cast-in-situ concrete piles having one or more number of bulbs formed by enlarging the pile stem. • These piles are best suited in soils where considerable ground movements occur due to seasonal variations, filled up grounds or in soft soil strata. • Provision of under reamed bulbs has the advantage of increasing the bearing and uplift capacities. • It also provides better anchorage at greater depths.
  • 31. • These piles are efficiently used in machine foundations, over bridges, electrical transmission tower foundation sand water tanks. • Indian Standard IS 2911 (Part III) - 1980 covers the design and construction of under reamed piles having one or more bulbs. • According to the code the diameter of under reamed bulbs may vary from 2 to 3 times the stem diameter depending upon the feasibility of construction and design requirements. • The code suggests a spacing of 1.25 to 1.5 times the bulb diameter for the bulbs. An angle of 450 with horizontal is recommended for all under reamed bulbs. • The code also gives mathematical expressions for calculating the bearing and uplift capacities.
  • 32. CONSTRUCTION OF UNDER REAMED PILE • Under reamed piles are bored cast-in-situ concrete piles having one or more number of bulbs formed by enlarging the pile stem. • These piles are best suited in soils where considerable ground movements occur due to seasonal variations, filled up grounds or in soft soil strata. • Provision of under reamed bulbs has the advantage of increasing the bearing and uplift capacities. • It also provides better anchorage at greater depths.
  • 33. • The process consists of various stages involving: boring by augers, under reaming by under-reamer, placing reinforcement cage in position, concreting of pile, concreting of pile caps, plinth beams and curtain walls. Stages in Construction of Under Reamed Pile
  • 34. • The equipment required for construction of pile are Auger boring guide Spiral auger with extension rods Under reamer with soil bucket Concreting funnel • The use of boring guide is necessary to keep bore holes vertical and also in position. • After setting the guide assembly in position, the spiral auger is introduced into the circular collar of the by opening out two sets flaps of the guide assembly. • The auger is pressed down and rotated manually until the spirals are half full of earth. The auger is then taken out and earth removed. • The boring process is repeated till the required depth is reached.
  • 35. • Under reaming or enlarging the stem of bore hole at required depth is achieved by means of the under reamer consisting of a set of two collapsible blades assembly fixed around the central shaft and a detachable bucket for receiving cut soil. • The equipment is attached to extension rods and lowered down the hole which has been bored to the required depth, until the bucket rests at the bottom of the bore hole. • The guide flaps are then closed. The tool is pressed down constantly and rotated slowly. • The cutting blades of the tool widen out and start cutting sides of hole. The loose earth is collected in a bucket at the bottom. • When bucket is full, the assembly is pulled out and bucket is emptied. The depth of the of bore hole is checked each time before insertion of under reamer so that any loose earth spilled from the bucket is removed.