SlideShare a Scribd company logo
1 of 41
Pakistan Housing
Authority
Commercial &
Residential Building
Presented By:
Adnan Ali
& Babar Khan
Outline
•Project Introduction
•Materials Used in site.
•Construction Equipment.
•Test Performed on site.
•Procedure of Construction.
Location Plan
Kurri Road, Park
Enclave
Islamabad
Description of Project
Sr No. Description Category No. Covered Area (Sq. ft)
1 Basement Shop 20 270
2 Ground Floor Shop 20 270
3
1st Floor
Appartment-1 04 892.50
Appartment-2 04 948.62
Appartment-3 02 1055
4
2nd Floor
Appartment-1 04 892.50
Appartment-2 04 948.62
Appartment-3 02 1055
5 3rd Floor
Appartment-1 04 892.50
Appartment-2 04 948.62
Appartment-3 02 1055
Project Stakeholders
• Client :
Pakistan HousingAuthority(PHA).
• Designer :
MEINHARDT
• Consultant :
JV-CIVTECH EPEC Consultants.
• Contractor :
MALIK ABID BROTHERS CONSTRUCTORS.
1. Material used In Site
• Termite Bi flex
• Fine Aggregate
• Coarse Aggregate
• Ordinary Portland Cement(OPC)
• Reinforcement
• Water Stopper
• Concrete spacer
Termite Bi Flex
•Double Action Protection
•Long Protection Period
•Low Environmental Impact
Fine Aggregate/Sand
• Lawernancepur Sand
• Passed from #4 sieve
• Free from Clay
• Density of sand is 1650
kg/cubic meter.
Coarse Aggregate/Crush
• Margalla Crush Used in site.
• Passed from Sieve ¾” size.
• Free from Stone dust & other
particles.
• Density of coarse aggregate is
1550 kg/cubic meter.
Ordinary Portland Cement
• Bestway Cement used in site.
• It will used with month after
manufacturing
• Stored in Controlled
Environment.
Reinforcement/Rebar
• 60 Grade Steel
• Mostly No.4 & No. 6 Bar used in
structure.
• No.3 Bar used for Strips.
Water Stopper
• Water Stops are flexible
Plastic strips which provide a
physical barrier to Water at
concrete joints, mostly in
basements and below ground
level construction.
Concrete Spacers
• There are two type of spacer
made on site.
• 1.5inch thick spacer.
• 2inch thick spacer.
Diaphragm for
spacer
Concrete Spacers
2.Construction Equipment
•Excavator
•Tipper
•Concrete Mixer
Excavator
•Excavators are used
in digging foundation,
backfilling etc.
Tipper
• Tippers are used to travel a
massive storage of material from
one place to another place.
• In one trip it will transfer about
400 to 500 CFT material.
Concrete Mixer
•Make 250 to 300 CFT per
Hour. If Operator work
efficiently.
3.Tests Perform on Site
• Field DensityTest (FDT)
• SlumpTest
• CubeTest For Compressive Strength
Field DensityTest (FDT)
• It is perform to measure the compaction of soil.
• Speedy moisture bottle is used to measure the moisture contact in soil.
• Minimum Compaction required on site is 95%.but in our project it achieved
98% compaction.
• Moisture content in our site is about 7%.
• Compaction should achieved by using 3 ton Roller for one day working.
• Soil in this is hard.
Continue…..
Digging
Hole of 6” Measuring Hole
depth.
Filling Sand
in Hole
Moisture Content
by Speedy
Moisture
SlumpTest
• Slump test is used to check the
workability of concrete.
• Value of Slump is 3” in site when
pouring of concrete.
• It is performed by using slump
cone apparatus.
CubeTest for Compressive Strength
• Cube test performed by consultant
for checking the strength of concrete.
• 3000 Psi concrete test lies between
the range of 2900 to 3100psi .
• Proper process followed in filling
according to British Code.
4. Process of Construction
• Survey
• Boundary Marking
• Excavation
• Compaction
• Anti-Termite Proofing.
• Lean Concreting.
• Layout of Grids & Columns
• Raft Foundation.
• RetainingWall
• Columns steel fixing & Levels.
• Beam & Slab Shuttering
• Defect &TheirTreatment
Survey
• Before Starting the Project Initial survey should be done by Client to take
information about site.The Following information's are given below:
• Site Accessibility
• Utilities
• Soil Conditions'
Boundary Marking
• After awarding the contract client, consultant & contractor will
make a joint survey and locate site boundaries and Temporary
Bench Mark using for leveling purpose.
Excavation
• Excavation done on site by
excavator.
• It will done by Slope & Stepped
method.
• Average depth of excavation is
10.64ft.
Compaction
• Soil strata of this site is hard so no any vibratory compaction needed.
• Compaction should be achieved by using 3Ton Roller.
• Working hour of roller was 12 hours.
• After compaction we check relative compaction by using FDTTest.
• The relative compaction of soil is 98%.
Anti-TermiteTreatment
• Termite bi flex is used for termite
proofing.
• It is used 20 L/100square meter.
Lean Leveling &
Concreting
• Mark k levels of lean levels by using
auto level .
• Thickness of lean concrete was 4”.
• It was completed in one day.
Layout of Grids & Columns
• Laying of Girds X,Y direction on ground.
• There are three different sizes of column in this
structure.
• C1 : 12x30 = 4 No.
• C2 : 12x 24 = 36 No.
• C3 : 12 x 12 = 12 No.
Raft Foundation
Steel fixing of 1st Mesh
Fixing of Steel Chairs
Continue…..
2nd Steel Mesh Completed &
Installation of water stopper
Dowel Bars for Stairs
Retaining Wall
Reinforcement &
Sheeting work
Pouring of concrete &
Compaction byVibrator
Final RetainingWall
Steel Reinforcement & Leveling
Reinforcement & Lap in
Column
Curing with Jute Bags
Continue….
Levels Mark on
Column
Column Cups for
monolithic Joint
Beam & Slab Shuttering
Defect &TheirTreatment
• Defect due improper compaction.
• It was treated my preparing a
cement paste with (1:2).
OtherThings We Observed on Site
Steel Storage &
Cutting Area
Temporary Platform
for Concrete Mixer
Prayer Place on
Site
Conclusion
• The Bestway to memorize thermotical knowledge to see a practical
example.
• Not use any safety measure on site.
Steps Involves in Building Construction

More Related Content

What's hot

Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
ALI HYDER GADHI
 
Field Joint of Cement lined Pipe
Field Joint of Cement lined PipeField Joint of Cement lined Pipe
Field Joint of Cement lined Pipe
Johnson Prabu
 
80623277 cost-estimator
80623277 cost-estimator80623277 cost-estimator
80623277 cost-estimator
imaduddin91
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
AMIT PAYAL
 

What's hot (20)

Concreting operation
Concreting operationConcreting operation
Concreting operation
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Batching, mixing, placing, and curing of concrete - Report
Batching, mixing, placing, and curing of concrete - ReportBatching, mixing, placing, and curing of concrete - Report
Batching, mixing, placing, and curing of concrete - Report
 
Batching and mixing
Batching and mixingBatching and mixing
Batching and mixing
 
Field Joint of Cement lined Pipe
Field Joint of Cement lined PipeField Joint of Cement lined Pipe
Field Joint of Cement lined Pipe
 
Concrete,batc,mix,trans,copaction etc
Concrete,batc,mix,trans,copaction etcConcrete,batc,mix,trans,copaction etc
Concrete,batc,mix,trans,copaction etc
 
Fineness of fine aggregates perfect (1)
Fineness of fine aggregates perfect  (1)Fineness of fine aggregates perfect  (1)
Fineness of fine aggregates perfect (1)
 
L#8 batching,mixing
L#8 batching,mixingL#8 batching,mixing
L#8 batching,mixing
 
80623277 cost-estimator
80623277 cost-estimator80623277 cost-estimator
80623277 cost-estimator
 
Ready Mix Concrete (RMC) Production Efficiency
Ready Mix Concrete (RMC) Production EfficiencyReady Mix Concrete (RMC) Production Efficiency
Ready Mix Concrete (RMC) Production Efficiency
 
Concrete 3
Concrete 3Concrete 3
Concrete 3
 
Fresh Concrete
Fresh ConcreteFresh Concrete
Fresh Concrete
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Inovasi makmal (1)
Inovasi makmal (1)Inovasi makmal (1)
Inovasi makmal (1)
 
Compaction Factor Test
Compaction Factor TestCompaction Factor Test
Compaction Factor Test
 
Fresh concrete for civil engineering
Fresh concrete for civil engineeringFresh concrete for civil engineering
Fresh concrete for civil engineering
 
Concrete mix design
Concrete mix designConcrete mix design
Concrete mix design
 
Bottom ash as a partial replacement of fine aggregate
Bottom ash as a partial replacement of fine aggregateBottom ash as a partial replacement of fine aggregate
Bottom ash as a partial replacement of fine aggregate
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
 
How to determine Initial and Final Setting Time of Cement?
How to determine Initial and Final Setting Time of Cement?How to determine Initial and Final Setting Time of Cement?
How to determine Initial and Final Setting Time of Cement?
 

Similar to Steps Involves in Building Construction

Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
Anshul Shakya
 
CONCRETE TECHNOLOGY an introduction to concrete
CONCRETE TECHNOLOGY an introduction to concreteCONCRETE TECHNOLOGY an introduction to concrete
CONCRETE TECHNOLOGY an introduction to concrete
ARUNKUMARC39
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
Jaspreet singh
 

Similar to Steps Involves in Building Construction (20)

Summer training report
Summer training reportSummer training report
Summer training report
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation
 
May17
May17May17
May17
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant Construction
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Building construction
Building constructionBuilding construction
Building construction
 
Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
 
siddhant .construction field visit.pptx
siddhant .construction field visit.pptxsiddhant .construction field visit.pptx
siddhant .construction field visit.pptx
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
 
CONCRETE TECHNOLOGY an introduction to concrete
CONCRETE TECHNOLOGY an introduction to concreteCONCRETE TECHNOLOGY an introduction to concrete
CONCRETE TECHNOLOGY an introduction to concrete
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Presentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,deptPresentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,dept
 
FE.pdf
FE.pdfFE.pdf
FE.pdf
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 

Recently uploaded

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Recently uploaded (20)

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 

Steps Involves in Building Construction

  • 1.
  • 2. Pakistan Housing Authority Commercial & Residential Building Presented By: Adnan Ali & Babar Khan
  • 3. Outline •Project Introduction •Materials Used in site. •Construction Equipment. •Test Performed on site. •Procedure of Construction.
  • 4. Location Plan Kurri Road, Park Enclave Islamabad
  • 5. Description of Project Sr No. Description Category No. Covered Area (Sq. ft) 1 Basement Shop 20 270 2 Ground Floor Shop 20 270 3 1st Floor Appartment-1 04 892.50 Appartment-2 04 948.62 Appartment-3 02 1055 4 2nd Floor Appartment-1 04 892.50 Appartment-2 04 948.62 Appartment-3 02 1055 5 3rd Floor Appartment-1 04 892.50 Appartment-2 04 948.62 Appartment-3 02 1055
  • 6. Project Stakeholders • Client : Pakistan HousingAuthority(PHA). • Designer : MEINHARDT • Consultant : JV-CIVTECH EPEC Consultants. • Contractor : MALIK ABID BROTHERS CONSTRUCTORS.
  • 7. 1. Material used In Site • Termite Bi flex • Fine Aggregate • Coarse Aggregate • Ordinary Portland Cement(OPC) • Reinforcement • Water Stopper • Concrete spacer
  • 8. Termite Bi Flex •Double Action Protection •Long Protection Period •Low Environmental Impact
  • 9. Fine Aggregate/Sand • Lawernancepur Sand • Passed from #4 sieve • Free from Clay • Density of sand is 1650 kg/cubic meter.
  • 10. Coarse Aggregate/Crush • Margalla Crush Used in site. • Passed from Sieve ¾” size. • Free from Stone dust & other particles. • Density of coarse aggregate is 1550 kg/cubic meter.
  • 11. Ordinary Portland Cement • Bestway Cement used in site. • It will used with month after manufacturing • Stored in Controlled Environment.
  • 12. Reinforcement/Rebar • 60 Grade Steel • Mostly No.4 & No. 6 Bar used in structure. • No.3 Bar used for Strips.
  • 13. Water Stopper • Water Stops are flexible Plastic strips which provide a physical barrier to Water at concrete joints, mostly in basements and below ground level construction.
  • 14. Concrete Spacers • There are two type of spacer made on site. • 1.5inch thick spacer. • 2inch thick spacer. Diaphragm for spacer Concrete Spacers
  • 16. Excavator •Excavators are used in digging foundation, backfilling etc.
  • 17. Tipper • Tippers are used to travel a massive storage of material from one place to another place. • In one trip it will transfer about 400 to 500 CFT material.
  • 18. Concrete Mixer •Make 250 to 300 CFT per Hour. If Operator work efficiently.
  • 19. 3.Tests Perform on Site • Field DensityTest (FDT) • SlumpTest • CubeTest For Compressive Strength
  • 20. Field DensityTest (FDT) • It is perform to measure the compaction of soil. • Speedy moisture bottle is used to measure the moisture contact in soil. • Minimum Compaction required on site is 95%.but in our project it achieved 98% compaction. • Moisture content in our site is about 7%. • Compaction should achieved by using 3 ton Roller for one day working. • Soil in this is hard.
  • 21. Continue….. Digging Hole of 6” Measuring Hole depth. Filling Sand in Hole Moisture Content by Speedy Moisture
  • 22. SlumpTest • Slump test is used to check the workability of concrete. • Value of Slump is 3” in site when pouring of concrete. • It is performed by using slump cone apparatus.
  • 23. CubeTest for Compressive Strength • Cube test performed by consultant for checking the strength of concrete. • 3000 Psi concrete test lies between the range of 2900 to 3100psi . • Proper process followed in filling according to British Code.
  • 24. 4. Process of Construction • Survey • Boundary Marking • Excavation • Compaction • Anti-Termite Proofing. • Lean Concreting. • Layout of Grids & Columns • Raft Foundation. • RetainingWall • Columns steel fixing & Levels. • Beam & Slab Shuttering • Defect &TheirTreatment
  • 25. Survey • Before Starting the Project Initial survey should be done by Client to take information about site.The Following information's are given below: • Site Accessibility • Utilities • Soil Conditions'
  • 26. Boundary Marking • After awarding the contract client, consultant & contractor will make a joint survey and locate site boundaries and Temporary Bench Mark using for leveling purpose.
  • 27. Excavation • Excavation done on site by excavator. • It will done by Slope & Stepped method. • Average depth of excavation is 10.64ft.
  • 28. Compaction • Soil strata of this site is hard so no any vibratory compaction needed. • Compaction should be achieved by using 3Ton Roller. • Working hour of roller was 12 hours. • After compaction we check relative compaction by using FDTTest. • The relative compaction of soil is 98%.
  • 29. Anti-TermiteTreatment • Termite bi flex is used for termite proofing. • It is used 20 L/100square meter.
  • 30. Lean Leveling & Concreting • Mark k levels of lean levels by using auto level . • Thickness of lean concrete was 4”. • It was completed in one day.
  • 31. Layout of Grids & Columns • Laying of Girds X,Y direction on ground. • There are three different sizes of column in this structure. • C1 : 12x30 = 4 No. • C2 : 12x 24 = 36 No. • C3 : 12 x 12 = 12 No.
  • 32. Raft Foundation Steel fixing of 1st Mesh Fixing of Steel Chairs
  • 33. Continue….. 2nd Steel Mesh Completed & Installation of water stopper Dowel Bars for Stairs
  • 34. Retaining Wall Reinforcement & Sheeting work Pouring of concrete & Compaction byVibrator Final RetainingWall
  • 35. Steel Reinforcement & Leveling Reinforcement & Lap in Column Curing with Jute Bags
  • 36. Continue…. Levels Mark on Column Column Cups for monolithic Joint
  • 37. Beam & Slab Shuttering
  • 38. Defect &TheirTreatment • Defect due improper compaction. • It was treated my preparing a cement paste with (1:2).
  • 39. OtherThings We Observed on Site Steel Storage & Cutting Area Temporary Platform for Concrete Mixer Prayer Place on Site
  • 40. Conclusion • The Bestway to memorize thermotical knowledge to see a practical example. • Not use any safety measure on site.