Mobilisation
1
2
Mobilisation Timeline
Mobilisation Timescales
Mobilisation
commences 01/09/15
Contract start
01st December 2015
‘Go-Live’
Mobilisation
01/09/15 – 01/12/15
Transition
01/12/15 – 01/03/16
Business As Usual
(BAU)
01/03/2016 – onwards
3 Months 3 Months
4
● Our mobilisation approach is flexible according to Client needs.
● However there are certain steps which need to happen at the beginning of any mobilisation to ensure
equal understanding and clarity, these are:
• Mobilisation Reporting Approach meeting
• Project Plan – Deep Dive
• Integrated Project Team (IPT) Workshop
Mobilisation Approach
5
● To ensure that Mobilisation and Transition remain on track, we host a regular set of one off and weekly
meetings:
1. Contract Kick-off meeting
2. Individual Workstream Review’s (optional)
3. Internal weekly conference calls
4. Weekly Client Review
5. Weekly Governance call
6. Weekly Risk Register review
Meetings
6
● This first level of reporting is for the key (Internal) stakeholders
● It is the highest, summary level of reporting
● Governance reporting is carried out weekly and is supported by a conference call to discuss
progress in greater detail
● The Governance report includes details on;
– Plan on a Page summary of all workstream functions
– Risks and issues (high, medium and low)
– Achievements and Highlights
– Planned achievements for the next reporting period
Level 0 – Governance Reporting
7
● The Plan on a Page document highlights each of the workstream’s activity milestones
● The document is broken down into
– Central functions
– Operational functions
– Additional functions
● Each workstream reports on their milestones weekly so that the Plan on a Page document can then be
updated centrally.
● The Plan on a Page highlights key dates along the mobilisation and transition project timeline.
Level 1 – Plan on a Page & Milestones
8
● Each workstream reports weekly
● Each workstream lead sends in their workstream slide update to the Project Management Office
(PMO), they are then collated into a presentation deck
● Each slide includes;
– Weekly activity summary
– Exceptions to plan
– Milestones (traffic light system and 4 week view)
– Achievements and Highlights
– Planned achievements for next reporting period
– Risks, Issues and Dependencies
● The Milestones are drawn from the Level 1 – Plan on a Page document.
Level 2 – Workstream Slide Deck
9
● The Project Plan goes into greater detail and breaks each of the stages down into individual tasks
● The Project Plan also gives each task and stage a specific time frame for that activity to be completed
● The Project Plan is developed at the Kick-off meeting stage by workstream leads in collaboration with the
PMO to ensure the demands of the project fit into the given time frames
● The Project Plan feeds detail into the Plan on a Page document
Level 3 – Project Plan
10
● There are a number of other document's you will be responsible for updating and providing supporting
information for, these are:
– The Risk Register
– Contract Quality Management Plan
– Business Continuity Plan
– Countdown Newsletters
Supporting documents
STATUS UPDATE OVERALL PROJECT STATUS
Current G
Previous G
STATUS UPDATE
CENTRAL SUPPORT FUNCTIONS
Account
Management
People &
Communications
Commercial &
Legal
Finance IT Systems QHSE
Current G G G G G G
Previous G G G G G G
STATUS UPDATE
OPERATIONAL DELIVERY FUNCTIONS
Mail Services M & E Services Security Services Front of House Cleaning Services Specialist Services
Current G G G G G G
Previous G G G G G G
STATUS UPDATE
ADDITIONAL FUNCTIONS
Projects
Current G
Previous G
Red Risks Amber Risks
None Reported None Reported
Workgroup Weekly Update Slides
Plan on a Page – Central Functions
Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16
Account
Management
People &
Communications
Commercial &
Legal
Finance
Mobilisation Phase Transition Phase
Business As
Usual
04/09 – Issue TUPE RFI
23/10 – Review ‘Welcome presentations’
with Thales
15/10 – Contact recognised Unions
30/10 – TUPE welcome packs
organised
18/12 – Collate intended measures
18/12 – All TUPE Individual consultations completed (to obtain RTW docs and issue
handbooks)
24/12 – Individual TUPE consultations completed
19/10 – Execute Contract
09/11 – Define WBS Structure for SAP
31/12 – Finance reporting
requirements established
02/12 – Contract Summary
produced
08/01 – Host Finance Workshop
04/12 – All Billing types mapped
04/12 – Finalise Contract Obligations Tracker
20/10 – All vetting forms completed by IFM
team
18/12 – CQMP and BCP reviewed by
AD
08/01 – TOM finalised
02/11 – Change control
Process agreed
11/12 – AD to complete schedule of deliverables
22/10 – Due Diligence schedule
agreed with Thales
08/01 – Transition Milestones
finalised
16/10 – Risk Register
review scheduled
17/11 – Escalation process and Hierarchy
agreed
06/11 – Draft Obligations Tracker
23/12 – Finalised list of subcontractors
agreed
27/11 – Review of contract and cost model completed
1st October 2015 11th January 2016 11th April 2016
08/01 – Contract review workshops completed Internal
MOU’s
25/01 – Contract Handbook
produced
10/12 - KPI and reporting structure agreed and
circulated
24/12 – Quality Assurance testing completed on
Helpdesk
16/10 – Implications of pay date changes investigated
30/10 – All Light
touch sessions
completed
13/11 – Review and agree additional billing
processes
11/11 – In receipt of all uniform orders 04/01 – Workflow Process
20/11 – Send service leads preparation doc
27/11 – Schedule Individual Employee Consultations
and send consultation grid to incumbents
10/01 – Completion of TUPE process
17/12 – Dispersal plan draft for ongoing update
18/12 – Ordering of IT Equipment Laptops and Phones
24/12 – Understanding Company cars on TUPE transfer
06/01 – Incident Management Escalations - review all Workstreams
Plan on a Page – Central Functions Cont…
Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16
IT Systems
(inc Helpdesk &
MiWorld)
QHSE
Mobilisation Phase Transition Phase
Business As
Usual
09/11 – Commence WAN ordering
process
23/10 – Obtain reactive
call data
12/12 – Helpdesk UAT testing
complete
08/01 – CAFM system ready for Go-
Live
08/01 – Helpdesk ready for calls
26/11 - Airsweb set-up complete
15/12 – Draft BCP
produced
16/10 – Draft Risk Register produced
30/10 – Draft Health and Safety Plan
15/12 – Draft CQMP Produced
Key
On Target
Complete
Milestone has been missed but will not affect delivery
Milestone has been missed and will affect delivery
11/01 – Miworld ready for Go-Live
11/12 – Core QHSE training
identified
11th April 2016
11th January 2016
1st October 2015
27/11 – Info Sec questionnaire complete
27/11 – Confirm all
Workstream IT requirements
02/01 – Maximo ready for Go-Live
31/12 – All draft Risk Assessments completed
Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16
Mail Services
(inc Portering)
M&E Services
(inc Direct Audits)
Security Services
Front of House
Services (inc
Switchboard &
Room Booking)
Plan on a Page – Operational Functions
Mobilisation Phase Transition Phase Business As Usual
11/01 – RAM’s completed on Key sites (where
practical)
20/11 – Produce CAFM Methodology
05/01– Day 1 Contingency plans
produced
11/12 – Draft AI’s produced
31/12 – Obtain and confirm rota’s for month 1
31/12 – Risk Assessments and
Method statements per site agreed
24/12 – Critical spares list collated
18/12 – Contingency plans
developed
30/11 – Uniform order placed
27/11 – Provide Helpdesk escalation
info
22/01 – DA logins circulated
24/12 – TOM
finalised
04/12 – All DD visits complete
30/11 – Uniform order placed
11/12 – Any additional recruitment needs
agreed with Thales
18/12 – TUPE consultation and
paperwork complete
18/12 – Pool of SC cleared guards identified
15/01 – Asset data surveys complete
06/11 – Uniform orders placed
11/12 – All DD visits complete
16/10 – Agree level of
security clearance for all staff
11/12 – All DD findings reported to AD
11th April 2016
11th January 2016
1st October 2015
11/12 – Revised BCP submitted
23/10 – Confirm ownership of
existing equipment
30/11 – Order/Novate equipment
13/11 – DD visit to
Basingstoke
16/11 – Order new
equipment
27/11 – Helpdesk request for info complete
13/11 – DD visit to Reading
13/11 – DD visit to Crawley
11/12 – Complete starter documents for
TUPE
24/12 – TOM finalised
06/11 – Uniform order placed
11/12 – All TUPE paperwork
complete
24/12 – TOM finalised
18/12 – Finalised list of subcontractors
11/12 – All TUPE paperwork completed
24/12 – TOM finalised
05/02 – Permanent CAFM Solution deployed
22/01 – Permanent CAFM Solution Client Readiness
review
11/01 – Interim CAFM Solution deployed
15/12 – Interim CAFM Solution readiness review
11/12 – AI’s Signed by the client
Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16
Cleaning
Services
Specialist
Services (inc
Waste, Pest &
Landscaping)
Plan on a Page – Operational Functions Cont…
Mobilisation Phase Transition Phase
Business As
Usual
31/12 – Work schedules and method statements
15/12 – Pest site visit schedule
agreed
10/12 - Individual TUPE consultations complete
01/01 – All draft Risk
Assessments completed
17/12 – Incorporate building security into Your
Company docs
15/12 – Security policies per building
understood
Key
On Target
Complete
Milestone has been missed but will not affect delivery
Milestone has been missed and will affect delivery
08/01 - Ezitracker system order placed
30/11 – Site equipment ordered
28/12 – Compliance and
communication packs built
15/12 – 3rd Party suppliers updated
11th April 2016
11th January 2016
1st October 2015
18/12 – Bin delivery schedule agreed
11/12 – Out of Hours process and call out procedures recorded
18/12 – Consumables ordered and matrix
produced
04/12 – All DD visits complete
06/11 – uniform order
placed
18/12 – All TUPE paperwork complete
13/11 – Payment movement
understood
08/01 – Delivery to site of all new equipment
04/12 – All DD visits completed
24/12 – TOM finalised
24/12 – TOM finalised
Risk and Issues (Sample)
● TUPE no shows
● Agency staff – not visible through TUPE process
● Security – Vacancies in existing staff compliment (lead in for security clearance for new starters)
● Cleaning – Laundry Services, existing suppliers being set up on Your Company systems
● Alarm Monitoring – Clarity required on who is doing what (and where)
● Agreement of incumbent exit process and service handovers –
● Site specific Risk Assessments
● Your Company Bridging Helpdesk Solution
● Deliveries to sites for Go-Live
Achievements and Highlights
● Continual review of CQMP by all Workstreams
● IT equipment, email accounts and mobile devices for new employees ordered
● Welcome letters issued to Workstreams for their respective employees
● Forms for company cards - fleet organising vehicles
● Risk Assessment matrix completed
Planned achievements for next reporting period
● Review of CMQP/Risk Register by Workstreams
● BAFO Vs TOM – review structure
● Further FAQ’s to be completed and issued to incumbents
● Further guidance re Electricity pension query
● Create aspects and impacts register
● Identify QHSE Training requirements
● Risk Assessments to be uploaded
● Finalise Dispersal Plan
● Review Transition Milestones and cascade to Workstreams
Central Functions
• Account Management
• People and Communications
• Commercial and Legal
• Finance
• IT/Systems (inc Helpdesk)
• QHSE
Account Management
RAG Overall Process Risk Identification
Comms with affected
employees
Project Governance Team Vetting
Current G G G G G G
Previous G G G G G G
Summary
Exceptions to plan (Reasons for Reds/Ambers and Path to Green)
• None Reported
Achievements & Highlights Planned Achievements for next reporting period
 EXAMPLE • EXAMPLE
 Risks, Issues, Dependencies Key Milestones (4 week view)
Risks:
None reported
Issues:
None Reported
Dependencies:
None Reported
Milestone Forecast Date RAG Commentary
KPI and reporting structure
agreed
10/12/2015 B
Agreed with Thales to
complete during transition
Dispersal Plan build draft for
ongoing update
17/12/2015 B Draft available 15/12/15
Ordering of IT equipment -
Phones and Laptops
17/12/2015 B Order placed 14/12/15
People and Communications
RAG Overall TOM completion Union buy in
Comms with
affected employees
Movement of
employees on
SAP/ISAMs
On-going Comms
with Unions until
legal separation
Current G G G G G G
Previous G G G G G G
Summary
Exceptions to plan (Reasons for Reds/Ambers and Path to Green)
• None Reported
Achievements & Highlights Planned Achievements for next reporting period
 EXAMPLE • EXAMPLE
Risks, Issues, Dependencies Key Milestones (4 week view)
Risks:
None Reported
Issues:
None Reported
Dependencies:
None Reported
Milestone
Forecast
Date
RAG Commentary
Schedule Individual
Employee Consultations
and send consultation grid
to incumbents
27/11/20
15
B
Collate intended measures
and formally write to
incumbent and
subcontractors to confirm
18/12/20
15
G
All TUPE Individual
consultations completed
(to obtain RTW docs and
issue handbooks)
18/12/20
15
G
Commercial and Legal
RAG Overall Contract drafting Contract approval Obligations Variations/CR Final update
Current G G G G G G
Previous G G G G G G
Summary
Exceptions to plan (Reasons for Reds/Ambers and Path to Green)
• None Reported
Achievements & Highlights Planned Achievements for next reporting period
EXAMPLE • EXAMPLE
Risks, Issues, Dependencies Key Milestones (4 week view)
Risks:
None Reported
Issues:
None Reported
Dependencies:
None Reported
Milestone
Forecast
Date
RAG Commentary
Contract Summary
produced
02/12/201
5
B
Uploaded to
SharePoint
Finalise Contract
Obligations Tracker
04/12/201
5
B
Final list of subcontractors
agreed
23/12/201
5
G
Finance
RAG Overall Allocate Budgets
Contract & Cost
Model
Reporting
Contract
Schedules
Final Update
Current G G G G G G
Previous G G G G G G
Summary
Exceptions to plan (Reasons for Reds/Ambers and Path to Green)
• None Reported
Achievements & Highlights Planned Achievements for next reporting period
 EXAMPLE • EXAMPLE
Risks, Issues, Dependencies Key Milestones (4 week view)
Risks:
None Reported
Issues:
None Reported
Dependencies:
None Reported
Milestone
Forecast
Date
RAG Commentary
Review of contract
and cost model
completed
27/11/201
5
B
All billing types
mapped
04/12/201
5
B
Finance reporting
requirements
established
31/12/201
5
G
IT Systems
RAG Overall Progress Vs Plan Information Costs Risks & Issues Reports
Current G G G G G G
Previous G G G G G G
Summary
Exceptions to plan (Reasons for Reds/Ambers and Path to Green)
• None Reported
Achievements & Highlights Planned Achievements for next reporting period
 EXAMPLE • EXAMPLE
Risks, Issues, Dependencies Key Milestones (4 week view)
Risks:
None Reported
Issues:
None Reported
Dependencies:
None Reported
Milestone Forecast Date RAG Commentary
Security Information check
completed
27/11/2015 B
Confirm all Workstream IT
requirements
27/11/2015 B
Helpdesk Go-Live UAT
and testing complete
14/12/2015 A
Revised date submitted
18/12/2015 as testing
underway
QHSE
RAG Overall Progress vs. Plan Costs Risks & Issues Information Resources
Current G G G G G G
Previous G G G G G G
Summary
Exceptions to plan (Reasons for Reds/Ambers and Path to Green)
• None Reported
Achievements & Highlights Planned Achievements for next reporting period
 EXAMPLE • EXAMPLE
Risks, Issues, Dependencies Key Milestones (4 week view)
Risks:
None Reported
Issues:
None reported
Dependencies:
None Reported
Milestone
Forecast
Date
RAG Commentary
Core future QHSE
training identified
11/12/2015 B
Draft Business Continuity
Plan produced
15/12/2015 B
Draft Contract Quality
Management Plan
produced
15/12/2015 B
Copyright © 2018 by Baachu 26
Copyright © 2018 by Baachu, Baskar Sundaram
All rights reserved. No part of this publication may be reproduced, distributed, or transmitted in any form or by any means, including photocopying, recording, or other electronic or
mechanical methods, without the prior written permission of the publisher, except in the case of certain other noncommercial uses permitted by copyright law. For permission requests,
write to the publisher, addressed “Attention: Legal,” at the address below.
Baachu
Sussex Innovation, No.1 Croydon, 12-16 Addiscombe Rd, Croydon CR0 0XT
www.mybidbuddy.com
Disclaimer
While an effort is made to use the most accurate available information, Baachu does not guarantee that the information shared is always current. Baachu does not warrant or make any
representations as to the content, accuracy or completeness of the information, text, graphics, links and other items contained on its printed material and web pages.

More Related Content

What's hot

Cutover strategy in sap fico
Cutover strategy in sap ficoCutover strategy in sap fico
Cutover strategy in sap fico
Bhushan Dhande
 
Sarah Melendrez Resume Current
Sarah Melendrez Resume CurrentSarah Melendrez Resume Current
Sarah Melendrez Resume CurrentSarah Melendrez
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status reportTom Evans
 
Qrqc 8 d competition 2011 presentation logistics rev3
Qrqc 8 d competition 2011 presentation logistics rev3Qrqc 8 d competition 2011 presentation logistics rev3
Qrqc 8 d competition 2011 presentation logistics rev3Keith Ross
 
CV UTi - Marius Hancox
CV UTi - Marius HancoxCV UTi - Marius Hancox
CV UTi - Marius HancoxMARIUS HANCOX
 

What's hot (6)

2509- CV
2509- CV2509- CV
2509- CV
 
Cutover strategy in sap fico
Cutover strategy in sap ficoCutover strategy in sap fico
Cutover strategy in sap fico
 
Sarah Melendrez Resume Current
Sarah Melendrez Resume CurrentSarah Melendrez Resume Current
Sarah Melendrez Resume Current
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status report
 
Qrqc 8 d competition 2011 presentation logistics rev3
Qrqc 8 d competition 2011 presentation logistics rev3Qrqc 8 d competition 2011 presentation logistics rev3
Qrqc 8 d competition 2011 presentation logistics rev3
 
CV UTi - Marius Hancox
CV UTi - Marius HancoxCV UTi - Marius Hancox
CV UTi - Marius Hancox
 

Similar to Master class-mobilisation-v2.0

Sumter County FL Strategic Plan
Sumter County FL Strategic PlanSumter County FL Strategic Plan
Sumter County FL Strategic Plan
Tracy Quintana
 
Darryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio ManagementDarryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio ManagementDarryl Poulton
 
Hazel Burns CV Feb 2016
Hazel Burns CV Feb 2016Hazel Burns CV Feb 2016
Hazel Burns CV Feb 2016Hazel Burns
 
Final_CV_-_Lize_Oosthuizen Updated with MRC
Final_CV_-_Lize_Oosthuizen Updated with MRCFinal_CV_-_Lize_Oosthuizen Updated with MRC
Final_CV_-_Lize_Oosthuizen Updated with MRCLize Oosthuizen
 
Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath
gaihe
 
Abe jacobs occupational health and safety cv sept2017
Abe jacobs occupational health and safety cv sept2017Abe jacobs occupational health and safety cv sept2017
Abe jacobs occupational health and safety cv sept2017
Abe Jacobs
 
Motorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementMotorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementAras
 
Day 1 GSP: Introduction to the 2014 reporting and review process
Day 1 GSP: Introduction to the 2014 reporting and review processDay 1 GSP: Introduction to the 2014 reporting and review process
Day 1 GSP: Introduction to the 2014 reporting and review process
elodieperrat
 
AuditOnline_Introduction.pdf
AuditOnline_Introduction.pdfAuditOnline_Introduction.pdf
AuditOnline_Introduction.pdf
Dharma920345
 
Sapsa niscayah presentation
Sapsa niscayah presentationSapsa niscayah presentation
Sapsa niscayah presentationTina Hammar
 
Updated CV & Skills - Clive Crews
Updated CV & Skills - Clive CrewsUpdated CV & Skills - Clive Crews
Updated CV & Skills - Clive CrewsClive Crews
 
Copy of CV Elizma Kleyn.new.
Copy of CV Elizma Kleyn.new.Copy of CV Elizma Kleyn.new.
Copy of CV Elizma Kleyn.new.Elizma Kleyn
 
Cms Solution 07162010
Cms Solution 07162010Cms Solution 07162010
Cms Solution 07162010
larrybaker90
 
OGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC deliveryOGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC delivery
Association for Project Management
 

Similar to Master class-mobilisation-v2.0 (20)

The construction programme - assurance and controls
The construction programme - assurance and controlsThe construction programme - assurance and controls
The construction programme - assurance and controls
 
Kedar_CV
Kedar_CVKedar_CV
Kedar_CV
 
CV Lisa Cuthbert
CV Lisa CuthbertCV Lisa Cuthbert
CV Lisa Cuthbert
 
Sumter County FL Strategic Plan
Sumter County FL Strategic PlanSumter County FL Strategic Plan
Sumter County FL Strategic Plan
 
Student Transcript
Student TranscriptStudent Transcript
Student Transcript
 
Darryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio ManagementDarryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio Management
 
Hazel Burns CV Feb 2016
Hazel Burns CV Feb 2016Hazel Burns CV Feb 2016
Hazel Burns CV Feb 2016
 
Final_CV_-_Lize_Oosthuizen Updated with MRC
Final_CV_-_Lize_Oosthuizen Updated with MRCFinal_CV_-_Lize_Oosthuizen Updated with MRC
Final_CV_-_Lize_Oosthuizen Updated with MRC
 
Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath Project update and plan Year 2, by Cecile Hoareau-McGrath
Project update and plan Year 2, by Cecile Hoareau-McGrath
 
JDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work OrdersJDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work Orders
 
Abe jacobs occupational health and safety cv sept2017
Abe jacobs occupational health and safety cv sept2017Abe jacobs occupational health and safety cv sept2017
Abe jacobs occupational health and safety cv sept2017
 
Motorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementMotorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio Management
 
Day 1 GSP: Introduction to the 2014 reporting and review process
Day 1 GSP: Introduction to the 2014 reporting and review processDay 1 GSP: Introduction to the 2014 reporting and review process
Day 1 GSP: Introduction to the 2014 reporting and review process
 
AuditOnline_Introduction.pdf
AuditOnline_Introduction.pdfAuditOnline_Introduction.pdf
AuditOnline_Introduction.pdf
 
Sapsa niscayah presentation
Sapsa niscayah presentationSapsa niscayah presentation
Sapsa niscayah presentation
 
Updated CV & Skills - Clive Crews
Updated CV & Skills - Clive CrewsUpdated CV & Skills - Clive Crews
Updated CV & Skills - Clive Crews
 
Copy of CV Elizma Kleyn.new.
Copy of CV Elizma Kleyn.new.Copy of CV Elizma Kleyn.new.
Copy of CV Elizma Kleyn.new.
 
Cms Solution 07162010
Cms Solution 07162010Cms Solution 07162010
Cms Solution 07162010
 
OGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC deliveryOGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC delivery
 
ABDUL RASHEED
ABDUL RASHEEDABDUL RASHEED
ABDUL RASHEED
 

More from nirosuganya

Baachu core-message-canvas
Baachu core-message-canvasBaachu core-message-canvas
Baachu core-message-canvas
nirosuganya
 
Baachu perfect 1-on-1-sheet writeable-1
Baachu perfect 1-on-1-sheet writeable-1Baachu perfect 1-on-1-sheet writeable-1
Baachu perfect 1-on-1-sheet writeable-1
nirosuganya
 
Baachu one page-annual-growth-plan final
Baachu one page-annual-growth-plan finalBaachu one page-annual-growth-plan final
Baachu one page-annual-growth-plan final
nirosuganya
 
Baachu health checklist
Baachu health checklistBaachu health checklist
Baachu health checklist
nirosuganya
 
Baachu 90 day-gameplan-scalable writeable blank (1)
Baachu 90 day-gameplan-scalable writeable blank (1)Baachu 90 day-gameplan-scalable writeable blank (1)
Baachu 90 day-gameplan-scalable writeable blank (1)
nirosuganya
 
Baachu 90 day-gameplan-editable (1)
Baachu 90 day-gameplan-editable (1)Baachu 90 day-gameplan-editable (1)
Baachu 90 day-gameplan-editable (1)
nirosuganya
 
Baachu 12 month-look back-v2 (1)
Baachu 12 month-look back-v2 (1)Baachu 12 month-look back-v2 (1)
Baachu 12 month-look back-v2 (1)
nirosuganya
 
Baachu sov worksheet
Baachu sov worksheet Baachu sov worksheet
Baachu sov worksheet
nirosuganya
 
Baachu promotional planning-worksheet
Baachu promotional planning-worksheetBaachu promotional planning-worksheet
Baachu promotional planning-worksheet
nirosuganya
 
Uk fm cleaning services market 31 dec 2020
Uk fm cleaning services market   31 dec 2020Uk fm cleaning services market   31 dec 2020
Uk fm cleaning services market 31 dec 2020
nirosuganya
 
Uk fm in offices and commercial buildings 31 dec 2020
Uk fm in offices and commercial buildings   31 dec 2020Uk fm in offices and commercial buildings   31 dec 2020
Uk fm in offices and commercial buildings 31 dec 2020
nirosuganya
 
Fm market competitive landscape 31 dec 2020
Fm market competitive landscape    31 dec 2020Fm market competitive landscape    31 dec 2020
Fm market competitive landscape 31 dec 2020
nirosuganya
 
Storyboarding 1
Storyboarding 1Storyboarding 1
Storyboarding 1
nirosuganya
 
Sales management
Sales managementSales management
Sales management
nirosuganya
 
Sales operations
Sales operationsSales operations
Sales operations
nirosuganya
 
Rebid management-masterclass-
Rebid management-masterclass-Rebid management-masterclass-
Rebid management-masterclass-
nirosuganya
 
Pricing and-estimating-masterclass-
Pricing and-estimating-masterclass-Pricing and-estimating-masterclass-
Pricing and-estimating-masterclass-
nirosuganya
 
Master class-sales-pipeline-v2.0
Master class-sales-pipeline-v2.0Master class-sales-pipeline-v2.0
Master class-sales-pipeline-v2.0
nirosuganya
 
Micro certifications-marketing
Micro certifications-marketingMicro certifications-marketing
Micro certifications-marketing
nirosuganya
 
Knowledge management
Knowledge managementKnowledge management
Knowledge management
nirosuganya
 

More from nirosuganya (20)

Baachu core-message-canvas
Baachu core-message-canvasBaachu core-message-canvas
Baachu core-message-canvas
 
Baachu perfect 1-on-1-sheet writeable-1
Baachu perfect 1-on-1-sheet writeable-1Baachu perfect 1-on-1-sheet writeable-1
Baachu perfect 1-on-1-sheet writeable-1
 
Baachu one page-annual-growth-plan final
Baachu one page-annual-growth-plan finalBaachu one page-annual-growth-plan final
Baachu one page-annual-growth-plan final
 
Baachu health checklist
Baachu health checklistBaachu health checklist
Baachu health checklist
 
Baachu 90 day-gameplan-scalable writeable blank (1)
Baachu 90 day-gameplan-scalable writeable blank (1)Baachu 90 day-gameplan-scalable writeable blank (1)
Baachu 90 day-gameplan-scalable writeable blank (1)
 
Baachu 90 day-gameplan-editable (1)
Baachu 90 day-gameplan-editable (1)Baachu 90 day-gameplan-editable (1)
Baachu 90 day-gameplan-editable (1)
 
Baachu 12 month-look back-v2 (1)
Baachu 12 month-look back-v2 (1)Baachu 12 month-look back-v2 (1)
Baachu 12 month-look back-v2 (1)
 
Baachu sov worksheet
Baachu sov worksheet Baachu sov worksheet
Baachu sov worksheet
 
Baachu promotional planning-worksheet
Baachu promotional planning-worksheetBaachu promotional planning-worksheet
Baachu promotional planning-worksheet
 
Uk fm cleaning services market 31 dec 2020
Uk fm cleaning services market   31 dec 2020Uk fm cleaning services market   31 dec 2020
Uk fm cleaning services market 31 dec 2020
 
Uk fm in offices and commercial buildings 31 dec 2020
Uk fm in offices and commercial buildings   31 dec 2020Uk fm in offices and commercial buildings   31 dec 2020
Uk fm in offices and commercial buildings 31 dec 2020
 
Fm market competitive landscape 31 dec 2020
Fm market competitive landscape    31 dec 2020Fm market competitive landscape    31 dec 2020
Fm market competitive landscape 31 dec 2020
 
Storyboarding 1
Storyboarding 1Storyboarding 1
Storyboarding 1
 
Sales management
Sales managementSales management
Sales management
 
Sales operations
Sales operationsSales operations
Sales operations
 
Rebid management-masterclass-
Rebid management-masterclass-Rebid management-masterclass-
Rebid management-masterclass-
 
Pricing and-estimating-masterclass-
Pricing and-estimating-masterclass-Pricing and-estimating-masterclass-
Pricing and-estimating-masterclass-
 
Master class-sales-pipeline-v2.0
Master class-sales-pipeline-v2.0Master class-sales-pipeline-v2.0
Master class-sales-pipeline-v2.0
 
Micro certifications-marketing
Micro certifications-marketingMicro certifications-marketing
Micro certifications-marketing
 
Knowledge management
Knowledge managementKnowledge management
Knowledge management
 

Recently uploaded

Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop.com LTD
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 

Recently uploaded (20)

Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 

Master class-mobilisation-v2.0

  • 3. Mobilisation Timescales Mobilisation commences 01/09/15 Contract start 01st December 2015 ‘Go-Live’ Mobilisation 01/09/15 – 01/12/15 Transition 01/12/15 – 01/03/16 Business As Usual (BAU) 01/03/2016 – onwards 3 Months 3 Months
  • 4. 4 ● Our mobilisation approach is flexible according to Client needs. ● However there are certain steps which need to happen at the beginning of any mobilisation to ensure equal understanding and clarity, these are: • Mobilisation Reporting Approach meeting • Project Plan – Deep Dive • Integrated Project Team (IPT) Workshop Mobilisation Approach
  • 5. 5 ● To ensure that Mobilisation and Transition remain on track, we host a regular set of one off and weekly meetings: 1. Contract Kick-off meeting 2. Individual Workstream Review’s (optional) 3. Internal weekly conference calls 4. Weekly Client Review 5. Weekly Governance call 6. Weekly Risk Register review Meetings
  • 6. 6 ● This first level of reporting is for the key (Internal) stakeholders ● It is the highest, summary level of reporting ● Governance reporting is carried out weekly and is supported by a conference call to discuss progress in greater detail ● The Governance report includes details on; – Plan on a Page summary of all workstream functions – Risks and issues (high, medium and low) – Achievements and Highlights – Planned achievements for the next reporting period Level 0 – Governance Reporting
  • 7. 7 ● The Plan on a Page document highlights each of the workstream’s activity milestones ● The document is broken down into – Central functions – Operational functions – Additional functions ● Each workstream reports on their milestones weekly so that the Plan on a Page document can then be updated centrally. ● The Plan on a Page highlights key dates along the mobilisation and transition project timeline. Level 1 – Plan on a Page & Milestones
  • 8. 8 ● Each workstream reports weekly ● Each workstream lead sends in their workstream slide update to the Project Management Office (PMO), they are then collated into a presentation deck ● Each slide includes; – Weekly activity summary – Exceptions to plan – Milestones (traffic light system and 4 week view) – Achievements and Highlights – Planned achievements for next reporting period – Risks, Issues and Dependencies ● The Milestones are drawn from the Level 1 – Plan on a Page document. Level 2 – Workstream Slide Deck
  • 9. 9 ● The Project Plan goes into greater detail and breaks each of the stages down into individual tasks ● The Project Plan also gives each task and stage a specific time frame for that activity to be completed ● The Project Plan is developed at the Kick-off meeting stage by workstream leads in collaboration with the PMO to ensure the demands of the project fit into the given time frames ● The Project Plan feeds detail into the Plan on a Page document Level 3 – Project Plan
  • 10. 10 ● There are a number of other document's you will be responsible for updating and providing supporting information for, these are: – The Risk Register – Contract Quality Management Plan – Business Continuity Plan – Countdown Newsletters Supporting documents
  • 11. STATUS UPDATE OVERALL PROJECT STATUS Current G Previous G STATUS UPDATE CENTRAL SUPPORT FUNCTIONS Account Management People & Communications Commercial & Legal Finance IT Systems QHSE Current G G G G G G Previous G G G G G G STATUS UPDATE OPERATIONAL DELIVERY FUNCTIONS Mail Services M & E Services Security Services Front of House Cleaning Services Specialist Services Current G G G G G G Previous G G G G G G STATUS UPDATE ADDITIONAL FUNCTIONS Projects Current G Previous G Red Risks Amber Risks None Reported None Reported Workgroup Weekly Update Slides
  • 12. Plan on a Page – Central Functions Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Account Management People & Communications Commercial & Legal Finance Mobilisation Phase Transition Phase Business As Usual 04/09 – Issue TUPE RFI 23/10 – Review ‘Welcome presentations’ with Thales 15/10 – Contact recognised Unions 30/10 – TUPE welcome packs organised 18/12 – Collate intended measures 18/12 – All TUPE Individual consultations completed (to obtain RTW docs and issue handbooks) 24/12 – Individual TUPE consultations completed 19/10 – Execute Contract 09/11 – Define WBS Structure for SAP 31/12 – Finance reporting requirements established 02/12 – Contract Summary produced 08/01 – Host Finance Workshop 04/12 – All Billing types mapped 04/12 – Finalise Contract Obligations Tracker 20/10 – All vetting forms completed by IFM team 18/12 – CQMP and BCP reviewed by AD 08/01 – TOM finalised 02/11 – Change control Process agreed 11/12 – AD to complete schedule of deliverables 22/10 – Due Diligence schedule agreed with Thales 08/01 – Transition Milestones finalised 16/10 – Risk Register review scheduled 17/11 – Escalation process and Hierarchy agreed 06/11 – Draft Obligations Tracker 23/12 – Finalised list of subcontractors agreed 27/11 – Review of contract and cost model completed 1st October 2015 11th January 2016 11th April 2016 08/01 – Contract review workshops completed Internal MOU’s 25/01 – Contract Handbook produced 10/12 - KPI and reporting structure agreed and circulated 24/12 – Quality Assurance testing completed on Helpdesk 16/10 – Implications of pay date changes investigated 30/10 – All Light touch sessions completed 13/11 – Review and agree additional billing processes 11/11 – In receipt of all uniform orders 04/01 – Workflow Process 20/11 – Send service leads preparation doc 27/11 – Schedule Individual Employee Consultations and send consultation grid to incumbents 10/01 – Completion of TUPE process 17/12 – Dispersal plan draft for ongoing update 18/12 – Ordering of IT Equipment Laptops and Phones 24/12 – Understanding Company cars on TUPE transfer 06/01 – Incident Management Escalations - review all Workstreams
  • 13. Plan on a Page – Central Functions Cont… Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 IT Systems (inc Helpdesk & MiWorld) QHSE Mobilisation Phase Transition Phase Business As Usual 09/11 – Commence WAN ordering process 23/10 – Obtain reactive call data 12/12 – Helpdesk UAT testing complete 08/01 – CAFM system ready for Go- Live 08/01 – Helpdesk ready for calls 26/11 - Airsweb set-up complete 15/12 – Draft BCP produced 16/10 – Draft Risk Register produced 30/10 – Draft Health and Safety Plan 15/12 – Draft CQMP Produced Key On Target Complete Milestone has been missed but will not affect delivery Milestone has been missed and will affect delivery 11/01 – Miworld ready for Go-Live 11/12 – Core QHSE training identified 11th April 2016 11th January 2016 1st October 2015 27/11 – Info Sec questionnaire complete 27/11 – Confirm all Workstream IT requirements 02/01 – Maximo ready for Go-Live 31/12 – All draft Risk Assessments completed
  • 14. Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Mail Services (inc Portering) M&E Services (inc Direct Audits) Security Services Front of House Services (inc Switchboard & Room Booking) Plan on a Page – Operational Functions Mobilisation Phase Transition Phase Business As Usual 11/01 – RAM’s completed on Key sites (where practical) 20/11 – Produce CAFM Methodology 05/01– Day 1 Contingency plans produced 11/12 – Draft AI’s produced 31/12 – Obtain and confirm rota’s for month 1 31/12 – Risk Assessments and Method statements per site agreed 24/12 – Critical spares list collated 18/12 – Contingency plans developed 30/11 – Uniform order placed 27/11 – Provide Helpdesk escalation info 22/01 – DA logins circulated 24/12 – TOM finalised 04/12 – All DD visits complete 30/11 – Uniform order placed 11/12 – Any additional recruitment needs agreed with Thales 18/12 – TUPE consultation and paperwork complete 18/12 – Pool of SC cleared guards identified 15/01 – Asset data surveys complete 06/11 – Uniform orders placed 11/12 – All DD visits complete 16/10 – Agree level of security clearance for all staff 11/12 – All DD findings reported to AD 11th April 2016 11th January 2016 1st October 2015 11/12 – Revised BCP submitted 23/10 – Confirm ownership of existing equipment 30/11 – Order/Novate equipment 13/11 – DD visit to Basingstoke 16/11 – Order new equipment 27/11 – Helpdesk request for info complete 13/11 – DD visit to Reading 13/11 – DD visit to Crawley 11/12 – Complete starter documents for TUPE 24/12 – TOM finalised 06/11 – Uniform order placed 11/12 – All TUPE paperwork complete 24/12 – TOM finalised 18/12 – Finalised list of subcontractors 11/12 – All TUPE paperwork completed 24/12 – TOM finalised 05/02 – Permanent CAFM Solution deployed 22/01 – Permanent CAFM Solution Client Readiness review 11/01 – Interim CAFM Solution deployed 15/12 – Interim CAFM Solution readiness review 11/12 – AI’s Signed by the client
  • 15. Workgroup Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Cleaning Services Specialist Services (inc Waste, Pest & Landscaping) Plan on a Page – Operational Functions Cont… Mobilisation Phase Transition Phase Business As Usual 31/12 – Work schedules and method statements 15/12 – Pest site visit schedule agreed 10/12 - Individual TUPE consultations complete 01/01 – All draft Risk Assessments completed 17/12 – Incorporate building security into Your Company docs 15/12 – Security policies per building understood Key On Target Complete Milestone has been missed but will not affect delivery Milestone has been missed and will affect delivery 08/01 - Ezitracker system order placed 30/11 – Site equipment ordered 28/12 – Compliance and communication packs built 15/12 – 3rd Party suppliers updated 11th April 2016 11th January 2016 1st October 2015 18/12 – Bin delivery schedule agreed 11/12 – Out of Hours process and call out procedures recorded 18/12 – Consumables ordered and matrix produced 04/12 – All DD visits complete 06/11 – uniform order placed 18/12 – All TUPE paperwork complete 13/11 – Payment movement understood 08/01 – Delivery to site of all new equipment 04/12 – All DD visits completed 24/12 – TOM finalised 24/12 – TOM finalised
  • 16. Risk and Issues (Sample) ● TUPE no shows ● Agency staff – not visible through TUPE process ● Security – Vacancies in existing staff compliment (lead in for security clearance for new starters) ● Cleaning – Laundry Services, existing suppliers being set up on Your Company systems ● Alarm Monitoring – Clarity required on who is doing what (and where) ● Agreement of incumbent exit process and service handovers – ● Site specific Risk Assessments ● Your Company Bridging Helpdesk Solution ● Deliveries to sites for Go-Live
  • 17. Achievements and Highlights ● Continual review of CQMP by all Workstreams ● IT equipment, email accounts and mobile devices for new employees ordered ● Welcome letters issued to Workstreams for their respective employees ● Forms for company cards - fleet organising vehicles ● Risk Assessment matrix completed
  • 18. Planned achievements for next reporting period ● Review of CMQP/Risk Register by Workstreams ● BAFO Vs TOM – review structure ● Further FAQ’s to be completed and issued to incumbents ● Further guidance re Electricity pension query ● Create aspects and impacts register ● Identify QHSE Training requirements ● Risk Assessments to be uploaded ● Finalise Dispersal Plan ● Review Transition Milestones and cascade to Workstreams
  • 19. Central Functions • Account Management • People and Communications • Commercial and Legal • Finance • IT/Systems (inc Helpdesk) • QHSE
  • 20. Account Management RAG Overall Process Risk Identification Comms with affected employees Project Governance Team Vetting Current G G G G G G Previous G G G G G G Summary Exceptions to plan (Reasons for Reds/Ambers and Path to Green) • None Reported Achievements & Highlights Planned Achievements for next reporting period  EXAMPLE • EXAMPLE  Risks, Issues, Dependencies Key Milestones (4 week view) Risks: None reported Issues: None Reported Dependencies: None Reported Milestone Forecast Date RAG Commentary KPI and reporting structure agreed 10/12/2015 B Agreed with Thales to complete during transition Dispersal Plan build draft for ongoing update 17/12/2015 B Draft available 15/12/15 Ordering of IT equipment - Phones and Laptops 17/12/2015 B Order placed 14/12/15
  • 21. People and Communications RAG Overall TOM completion Union buy in Comms with affected employees Movement of employees on SAP/ISAMs On-going Comms with Unions until legal separation Current G G G G G G Previous G G G G G G Summary Exceptions to plan (Reasons for Reds/Ambers and Path to Green) • None Reported Achievements & Highlights Planned Achievements for next reporting period  EXAMPLE • EXAMPLE Risks, Issues, Dependencies Key Milestones (4 week view) Risks: None Reported Issues: None Reported Dependencies: None Reported Milestone Forecast Date RAG Commentary Schedule Individual Employee Consultations and send consultation grid to incumbents 27/11/20 15 B Collate intended measures and formally write to incumbent and subcontractors to confirm 18/12/20 15 G All TUPE Individual consultations completed (to obtain RTW docs and issue handbooks) 18/12/20 15 G
  • 22. Commercial and Legal RAG Overall Contract drafting Contract approval Obligations Variations/CR Final update Current G G G G G G Previous G G G G G G Summary Exceptions to plan (Reasons for Reds/Ambers and Path to Green) • None Reported Achievements & Highlights Planned Achievements for next reporting period EXAMPLE • EXAMPLE Risks, Issues, Dependencies Key Milestones (4 week view) Risks: None Reported Issues: None Reported Dependencies: None Reported Milestone Forecast Date RAG Commentary Contract Summary produced 02/12/201 5 B Uploaded to SharePoint Finalise Contract Obligations Tracker 04/12/201 5 B Final list of subcontractors agreed 23/12/201 5 G
  • 23. Finance RAG Overall Allocate Budgets Contract & Cost Model Reporting Contract Schedules Final Update Current G G G G G G Previous G G G G G G Summary Exceptions to plan (Reasons for Reds/Ambers and Path to Green) • None Reported Achievements & Highlights Planned Achievements for next reporting period  EXAMPLE • EXAMPLE Risks, Issues, Dependencies Key Milestones (4 week view) Risks: None Reported Issues: None Reported Dependencies: None Reported Milestone Forecast Date RAG Commentary Review of contract and cost model completed 27/11/201 5 B All billing types mapped 04/12/201 5 B Finance reporting requirements established 31/12/201 5 G
  • 24. IT Systems RAG Overall Progress Vs Plan Information Costs Risks & Issues Reports Current G G G G G G Previous G G G G G G Summary Exceptions to plan (Reasons for Reds/Ambers and Path to Green) • None Reported Achievements & Highlights Planned Achievements for next reporting period  EXAMPLE • EXAMPLE Risks, Issues, Dependencies Key Milestones (4 week view) Risks: None Reported Issues: None Reported Dependencies: None Reported Milestone Forecast Date RAG Commentary Security Information check completed 27/11/2015 B Confirm all Workstream IT requirements 27/11/2015 B Helpdesk Go-Live UAT and testing complete 14/12/2015 A Revised date submitted 18/12/2015 as testing underway
  • 25. QHSE RAG Overall Progress vs. Plan Costs Risks & Issues Information Resources Current G G G G G G Previous G G G G G G Summary Exceptions to plan (Reasons for Reds/Ambers and Path to Green) • None Reported Achievements & Highlights Planned Achievements for next reporting period  EXAMPLE • EXAMPLE Risks, Issues, Dependencies Key Milestones (4 week view) Risks: None Reported Issues: None reported Dependencies: None Reported Milestone Forecast Date RAG Commentary Core future QHSE training identified 11/12/2015 B Draft Business Continuity Plan produced 15/12/2015 B Draft Contract Quality Management Plan produced 15/12/2015 B
  • 26. Copyright © 2018 by Baachu 26 Copyright © 2018 by Baachu, Baskar Sundaram All rights reserved. No part of this publication may be reproduced, distributed, or transmitted in any form or by any means, including photocopying, recording, or other electronic or mechanical methods, without the prior written permission of the publisher, except in the case of certain other noncommercial uses permitted by copyright law. For permission requests, write to the publisher, addressed “Attention: Legal,” at the address below. Baachu Sussex Innovation, No.1 Croydon, 12-16 Addiscombe Rd, Croydon CR0 0XT www.mybidbuddy.com Disclaimer While an effort is made to use the most accurate available information, Baachu does not guarantee that the information shared is always current. Baachu does not warrant or make any representations as to the content, accuracy or completeness of the information, text, graphics, links and other items contained on its printed material and web pages.