This document discusses the inspection and maintenance of steel bridges. It outlines the various components that should be inspected such as bearings, rivets, camber, and superstructure. Critical locations prone to issues like corrosion, fatigue cracks, and loose rivets are identified. The schedule and process for inspections by different roles is provided. Recommendations for maintenance activities like painting, epoxy coating, and metallizing of steel components are described.
The document discusses inspection and maintenance of reinforced concrete and steel bridges. It describes the importance of regular bridge inspection using various instrumentation to detect cracks, corrosion, and other issues. Bridges require maintenance to address damage over time from factors like weather, traffic loads, and corrosion. Common repairs include replacing expansion joints, repairing cracks, and addressing structural issues. Proper inspection and maintenance are needed to preserve bridge integrity and safety.
This document provides an overview of bridges, including:
1) It defines what a bridge is, its main components, and classifications based on various factors such as material, location, purpose, and structural design.
2) The key components of a bridge are described as the superstructure, which is above the bearings, and the substructure, which is below the bearings.
3) Bridges are investigated and designed based on considerations like span length, site conditions, and cost. Maintaining bridges requires regular inspections to identify deterioration and prevent structural failures.
Rails, Types, Joints, Creep, Failure of Rails and Welding of Railssrinivas2036
The document discusses rails used in railway tracks. It defines different types of rails including double headed, bull headed, and flat footed rails. Flat footed rails, also called Vignoles rails, are now most commonly used. Standard rail sections used in Indian railways, such as 52kg and 60kg, are presented. Requirements of an ideal rail and factors affecting rail wear and failure are explained. Methods to reduce rail wear include use of special alloys, track maintenance, reducing expansion gaps, and lubricating rails.
A concise presentation on bridge construction. Related to civil engineering courses. can be helpful for undergraduate students.
Its a Part of my class presentation.
A RCC bridge is a monolithic structure that is poured in place. Forms are placed, the reinforcing steel is placed into the forms and a concrete mix is poured into the forms. The rebar extends beyond the form to allow connection to the next section to be poured. In a PSC structure the elements are precast either in a yard or onsite. They are cast with longitudinal holes to allow the prestressing strands to be extended between them. These strands use their tension to pull the units together and to act as reinforcement by prestreeing the entirety of the structure to make it stronger.
The document describes a topographic survey conducted for the construction of a new railway bridge. It discusses using a topographic map to identify potential alignment options for the railway track. A field survey was then carried out using a total station to determine the central line alignment and elevation levels at different points. Soil exploration work, including lab testing, was also performed. Following this, the land acquisition process began by contacting local authorities to purchase the necessary land from owners. Foundation excavation work then commenced based on the ground conditions. Piers were constructed using a total station to ensure proper alignment. Bed blocks were then marked for placing precast girders. Sleepers were later laid to allow for track alignment along the central line.
Railway secondary part of the transportation . Railway use of maximum materials transport of one place to other place. Particular time of number of trains are move of particular junction so these part are used of points and crossing.
Best helpful of these ppt of railway track and design purposes.
The document discusses the components and requirements of an ideal permanent way for railways. It describes that the permanent way consists of rails fitted on sleepers which rest on ballast and a subgrade. The key requirements for an ideal permanent way are proper gauge, alignment, gradient, drainage and minimal resistance. It also discusses different types of rails, sleepers and fastenings used in railway track construction.
The document discusses inspection and maintenance of reinforced concrete and steel bridges. It describes the importance of regular bridge inspection using various instrumentation to detect cracks, corrosion, and other issues. Bridges require maintenance to address damage over time from factors like weather, traffic loads, and corrosion. Common repairs include replacing expansion joints, repairing cracks, and addressing structural issues. Proper inspection and maintenance are needed to preserve bridge integrity and safety.
This document provides an overview of bridges, including:
1) It defines what a bridge is, its main components, and classifications based on various factors such as material, location, purpose, and structural design.
2) The key components of a bridge are described as the superstructure, which is above the bearings, and the substructure, which is below the bearings.
3) Bridges are investigated and designed based on considerations like span length, site conditions, and cost. Maintaining bridges requires regular inspections to identify deterioration and prevent structural failures.
Rails, Types, Joints, Creep, Failure of Rails and Welding of Railssrinivas2036
The document discusses rails used in railway tracks. It defines different types of rails including double headed, bull headed, and flat footed rails. Flat footed rails, also called Vignoles rails, are now most commonly used. Standard rail sections used in Indian railways, such as 52kg and 60kg, are presented. Requirements of an ideal rail and factors affecting rail wear and failure are explained. Methods to reduce rail wear include use of special alloys, track maintenance, reducing expansion gaps, and lubricating rails.
A concise presentation on bridge construction. Related to civil engineering courses. can be helpful for undergraduate students.
Its a Part of my class presentation.
A RCC bridge is a monolithic structure that is poured in place. Forms are placed, the reinforcing steel is placed into the forms and a concrete mix is poured into the forms. The rebar extends beyond the form to allow connection to the next section to be poured. In a PSC structure the elements are precast either in a yard or onsite. They are cast with longitudinal holes to allow the prestressing strands to be extended between them. These strands use their tension to pull the units together and to act as reinforcement by prestreeing the entirety of the structure to make it stronger.
The document describes a topographic survey conducted for the construction of a new railway bridge. It discusses using a topographic map to identify potential alignment options for the railway track. A field survey was then carried out using a total station to determine the central line alignment and elevation levels at different points. Soil exploration work, including lab testing, was also performed. Following this, the land acquisition process began by contacting local authorities to purchase the necessary land from owners. Foundation excavation work then commenced based on the ground conditions. Piers were constructed using a total station to ensure proper alignment. Bed blocks were then marked for placing precast girders. Sleepers were later laid to allow for track alignment along the central line.
Railway secondary part of the transportation . Railway use of maximum materials transport of one place to other place. Particular time of number of trains are move of particular junction so these part are used of points and crossing.
Best helpful of these ppt of railway track and design purposes.
The document discusses the components and requirements of an ideal permanent way for railways. It describes that the permanent way consists of rails fitted on sleepers which rest on ballast and a subgrade. The key requirements for an ideal permanent way are proper gauge, alignment, gradient, drainage and minimal resistance. It also discusses different types of rails, sleepers and fastenings used in railway track construction.
The document discusses bridge types, components, selection criteria, and design considerations. It begins by defining what a bridge is and its purpose in transportation systems. It then covers typical bridge components and various structural forms for bridges based on material, span length, and other factors. Key criteria for selecting bridge types include span length, site conditions, cost, and aesthetics. The document emphasizes that aesthetic design requires considering function, proportion, harmony, order/rhythm, and contrast/texture to create pleasing structures that blend with their environments.
Bridge Bearings has been considered as of huge importance in civil engineering. It plays a significant role in the structure of bridges. This presentation covers the complete study of Bridge Bearings.
Internship Report on Bridge Construction & Dam ConstructionKhaliqur Rahman
Its about Bridge Component and Dam technique.
Full information about Bridge Construction.
Full information about construction of dam.
Training report. in pdf file
The document discusses concrete mix design, including:
- Concrete is made from cement, aggregates, water, and sometimes admixtures.
- ACI and BIS methods are described for determining mix proportions based on factors like strength, workability, durability, and materials.
- A step-by-step example is provided to design a mix using the ACI method for a specified 30MPa strength, including determining water-cement ratio, volumes, and final proportions.
Sleepers, also called ties, are transverse members laid beneath rails to distribute load from trains to the track bed. They come in various materials including wood, steel, concrete, and plastic. Wooden sleepers are most common but have short lifespans while concrete and steel last longer. All sleepers must firmly support rails, maintain proper gauge, and evenly distribute heavy train loads over a wide area of ballast for track stability.
Bridges provide passage over obstacles without blocking the way below. They carry traffic and loads over channels, roads, or railways. Bridges are classified based on their function, materials, form, position, construction method, and more. Common types include girder, truss, arch, cable-stayed, and suspension bridges, which vary in their typical spans and forces. Joints are often included to allow for movement from temperature changes and material shrinkage/expansion without compromising the bridge's integrity.
This document discusses railway turnouts. It begins by defining a turnout as the combination of points and crossings that allows a train to move from one track to another, either parallel or diverging. It then describes the key components of a turnout, including tongue rails, stock rails, lead rails, and a vee crossing. It also explains the classification of turnouts as left-hand or right-hand depending on the direction of diversion. Diagrams are included to illustrate the components and working principle of a turnout. The document concludes by stating that turnouts are essential for diverting traffic but can cause issues if not designed and maintained properly.
Bridges and its Types & Components by Chetan BishtChetanBisht16
This is very Useful for Fresher Civil engineers and also for Student of Civil Engineering . This Slide show almost cover the Basic Knowledge about Bridges
This document discusses quality control of concrete through various tests on fresh and hardened concrete. It begins with an introduction to concrete and quality, then discusses where quality control begins in the production of materials and continues through handling, batching, mixing, transporting and placing concrete. Key tests on fresh concrete include slump and compacting factor tests, while tests on hardened concrete include compression, tensile strength, and flexural strength tests to evaluate the quality and strength of the concrete. The document also reviews materials used in concrete such as cement, water, aggregates, and admixtures.
Cement is a binding agent that undergoes hydration when mixed with water. There are various types of cement including ordinary Portland cement (OPC), rapid hardening cement, and sulphate resisting cement. Cement provides early strength through C3S and later strength through C2S. Heat is generated during cement hydration through an exothermic reaction. Proper storing, grading of aggregates, minimizing segregation, and adding admixtures can improve the properties of concrete.
The document provides instructions for conducting pull-out tests to determine the compressive strength of concrete. It states that pull-out tests should be confirmed to BS 1881 Part 207 and give a direct tensile strength value. It describes how inserts can be cast into wet concrete or positioned in hardened concrete using an under-reamed groove. When testing, at least four pull-out tests should be performed at each location and a loading rate of 0.5 ± 0.2 kN/s should be used for 25mm diameter inserts. The compressive strength can then be calculated from the direct tensile strength value obtained during testing.
Rajkiya Engineering College, Bijnor presented information on bridge engineering. Bridges are key infrastructure that allow crossing of obstacles like rivers and canals. A bridge consists of substructure elements like foundations, piers, and abutments, and superstructure elements like the deck. Bridges are classified by span length, material used, and the type of superstructure. Bridges improve transportation, emergency response times, and reduce traffic congestion. Selection of a bridge type depends on site conditions, traffic needs, structural requirements, and material availability.
modern methods of railway track maintanencekrishnacp
The document discusses modern methods of track maintenance including mechanized maintenance using tamping machines, measured shovel packing, and directed track maintenance. Mechanized maintenance uses tamping machines to consolidate ballast and maintain tracks more efficiently. Measured shovel packing involves accurately measuring track defects, lifting the track, and placing measured quantities of stone chippings to level the track without blocking traffic. Directed track maintenance identifies track geometry defects using measuring devices and only rectifies defects at indicated locations to maintain tracks to standards.
This document contains instructions for 10 laboratory experiments related to highway engineering materials testing. The experiments include tests on aggregate such as the Los Angeles abrasion test, specific gravity, and water absorption. Tests on bitumen include determining specific gravity, penetration value, softening point, and ductility. The introduction provides background on concrete materials including cement, water, and aggregates. It describes properties and roles of each material in concrete. Definitions and properties of soils and aggregates used in highways are also given.
This seminar report discusses caisson foundations. Caissons are watertight structures used for deep foundations under water, such as for bridges, piers, and docks. There are three main types - open, box, and pneumatic caissons. Caissons can take various shapes and are used when foundations need to extend below riverbeds or in deep water. Advantages include ability to reach large depths, but difficulties include tilting or sinking during construction. Caisson diseases can affect workers if decompressed too quickly from pressurized conditions.
Bridges allow crossing over obstacles and come in different types. A basic beam or plank bridge will sag under its own weight if too long. Proper design must account for the bridge's dead load (its own weight), live load (weight of users), and wind load. Common modern bridge types include beam, arch, truss, suspension, and cable-stayed bridges. Each type has distinct structural properties and advantages/disadvantages for different uses and spans. Bridges have evolved significantly over history as materials and engineering have advanced.
Concrete permeability is a key factor in its durability. Permeability is affected by water-cement ratio, with lower ratios producing less permeable concrete. Curing also impacts permeability. Proper curing, including moist curing, produces less permeable concrete. Permeability testing involves measuring water flow through a sample over time under pressure. Sulfate attack can occur when sulfates penetrate permeable concrete and form expansive compounds that crack the material. Resistance to sulfates is improved with lower permeability concrete.
Suspension bridges can span long distances using cables and vertical suspenders to hang the deck below. They are lightweight yet strong structures using cables anchored at each end and resting on towers. The Golden Gate Bridge is an iconic suspension bridge that connects San Francisco to Marin County, built between 1933-1937. At over 1 mile long, it was the longest in the world until 1964 and demonstrates the advantages of suspension bridges to cross long spans over water.
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Shanmugasundaram N
1. The document discusses the philosophy, purpose, and requirements of estimation as well as load bearing and framed structures. Estimation involves approximating the cost of an engineering project before execution and requires thorough knowledge of construction procedures, materials, labor costs, and experience.
2. The purpose of estimation is for successful project implementation, determining material needs, knowing costs beforehand, and maintaining proper project reports.
3. Load bearing structures transfer weight directly to their foundations, while framed structures use beams and columns to distribute loads. Foundations and sections of each type are described.
Presentation on steel, fabrication & erection Munger Ganga BridgeAshish Kumar Yadav
Presentation on Steel Fabrication work and Erection of girder by Cantilever erection method.
One of the largest bridge in India (Bridge Length 3.690 Km)
Similar Bridge 1. Patna- Sonpur (Digha Bridge) across the river Ganga, Bihar
2. Bogibeel across river Brahmaputra in Assam
This document discusses bridge expansion joints. It begins by explaining that expansion joints accommodate movements in bridges due to thermal effects, loading, and structural deformation. It then categorizes joints based on their range of motion and provides examples of common joint types for small, medium, and large movements. Details are given on the construction, advantages, and disadvantages of sliding plate, compression seal, asphaltic plug, poured sealant, strip seal, finger plate, bolt-down, and modular joints. The document concludes with information on installing finger joints and maintaining expansion joints.
The document discusses bridge types, components, selection criteria, and design considerations. It begins by defining what a bridge is and its purpose in transportation systems. It then covers typical bridge components and various structural forms for bridges based on material, span length, and other factors. Key criteria for selecting bridge types include span length, site conditions, cost, and aesthetics. The document emphasizes that aesthetic design requires considering function, proportion, harmony, order/rhythm, and contrast/texture to create pleasing structures that blend with their environments.
Bridge Bearings has been considered as of huge importance in civil engineering. It plays a significant role in the structure of bridges. This presentation covers the complete study of Bridge Bearings.
Internship Report on Bridge Construction & Dam ConstructionKhaliqur Rahman
Its about Bridge Component and Dam technique.
Full information about Bridge Construction.
Full information about construction of dam.
Training report. in pdf file
The document discusses concrete mix design, including:
- Concrete is made from cement, aggregates, water, and sometimes admixtures.
- ACI and BIS methods are described for determining mix proportions based on factors like strength, workability, durability, and materials.
- A step-by-step example is provided to design a mix using the ACI method for a specified 30MPa strength, including determining water-cement ratio, volumes, and final proportions.
Sleepers, also called ties, are transverse members laid beneath rails to distribute load from trains to the track bed. They come in various materials including wood, steel, concrete, and plastic. Wooden sleepers are most common but have short lifespans while concrete and steel last longer. All sleepers must firmly support rails, maintain proper gauge, and evenly distribute heavy train loads over a wide area of ballast for track stability.
Bridges provide passage over obstacles without blocking the way below. They carry traffic and loads over channels, roads, or railways. Bridges are classified based on their function, materials, form, position, construction method, and more. Common types include girder, truss, arch, cable-stayed, and suspension bridges, which vary in their typical spans and forces. Joints are often included to allow for movement from temperature changes and material shrinkage/expansion without compromising the bridge's integrity.
This document discusses railway turnouts. It begins by defining a turnout as the combination of points and crossings that allows a train to move from one track to another, either parallel or diverging. It then describes the key components of a turnout, including tongue rails, stock rails, lead rails, and a vee crossing. It also explains the classification of turnouts as left-hand or right-hand depending on the direction of diversion. Diagrams are included to illustrate the components and working principle of a turnout. The document concludes by stating that turnouts are essential for diverting traffic but can cause issues if not designed and maintained properly.
Bridges and its Types & Components by Chetan BishtChetanBisht16
This is very Useful for Fresher Civil engineers and also for Student of Civil Engineering . This Slide show almost cover the Basic Knowledge about Bridges
This document discusses quality control of concrete through various tests on fresh and hardened concrete. It begins with an introduction to concrete and quality, then discusses where quality control begins in the production of materials and continues through handling, batching, mixing, transporting and placing concrete. Key tests on fresh concrete include slump and compacting factor tests, while tests on hardened concrete include compression, tensile strength, and flexural strength tests to evaluate the quality and strength of the concrete. The document also reviews materials used in concrete such as cement, water, aggregates, and admixtures.
Cement is a binding agent that undergoes hydration when mixed with water. There are various types of cement including ordinary Portland cement (OPC), rapid hardening cement, and sulphate resisting cement. Cement provides early strength through C3S and later strength through C2S. Heat is generated during cement hydration through an exothermic reaction. Proper storing, grading of aggregates, minimizing segregation, and adding admixtures can improve the properties of concrete.
The document provides instructions for conducting pull-out tests to determine the compressive strength of concrete. It states that pull-out tests should be confirmed to BS 1881 Part 207 and give a direct tensile strength value. It describes how inserts can be cast into wet concrete or positioned in hardened concrete using an under-reamed groove. When testing, at least four pull-out tests should be performed at each location and a loading rate of 0.5 ± 0.2 kN/s should be used for 25mm diameter inserts. The compressive strength can then be calculated from the direct tensile strength value obtained during testing.
Rajkiya Engineering College, Bijnor presented information on bridge engineering. Bridges are key infrastructure that allow crossing of obstacles like rivers and canals. A bridge consists of substructure elements like foundations, piers, and abutments, and superstructure elements like the deck. Bridges are classified by span length, material used, and the type of superstructure. Bridges improve transportation, emergency response times, and reduce traffic congestion. Selection of a bridge type depends on site conditions, traffic needs, structural requirements, and material availability.
modern methods of railway track maintanencekrishnacp
The document discusses modern methods of track maintenance including mechanized maintenance using tamping machines, measured shovel packing, and directed track maintenance. Mechanized maintenance uses tamping machines to consolidate ballast and maintain tracks more efficiently. Measured shovel packing involves accurately measuring track defects, lifting the track, and placing measured quantities of stone chippings to level the track without blocking traffic. Directed track maintenance identifies track geometry defects using measuring devices and only rectifies defects at indicated locations to maintain tracks to standards.
This document contains instructions for 10 laboratory experiments related to highway engineering materials testing. The experiments include tests on aggregate such as the Los Angeles abrasion test, specific gravity, and water absorption. Tests on bitumen include determining specific gravity, penetration value, softening point, and ductility. The introduction provides background on concrete materials including cement, water, and aggregates. It describes properties and roles of each material in concrete. Definitions and properties of soils and aggregates used in highways are also given.
This seminar report discusses caisson foundations. Caissons are watertight structures used for deep foundations under water, such as for bridges, piers, and docks. There are three main types - open, box, and pneumatic caissons. Caissons can take various shapes and are used when foundations need to extend below riverbeds or in deep water. Advantages include ability to reach large depths, but difficulties include tilting or sinking during construction. Caisson diseases can affect workers if decompressed too quickly from pressurized conditions.
Bridges allow crossing over obstacles and come in different types. A basic beam or plank bridge will sag under its own weight if too long. Proper design must account for the bridge's dead load (its own weight), live load (weight of users), and wind load. Common modern bridge types include beam, arch, truss, suspension, and cable-stayed bridges. Each type has distinct structural properties and advantages/disadvantages for different uses and spans. Bridges have evolved significantly over history as materials and engineering have advanced.
Concrete permeability is a key factor in its durability. Permeability is affected by water-cement ratio, with lower ratios producing less permeable concrete. Curing also impacts permeability. Proper curing, including moist curing, produces less permeable concrete. Permeability testing involves measuring water flow through a sample over time under pressure. Sulfate attack can occur when sulfates penetrate permeable concrete and form expansive compounds that crack the material. Resistance to sulfates is improved with lower permeability concrete.
Suspension bridges can span long distances using cables and vertical suspenders to hang the deck below. They are lightweight yet strong structures using cables anchored at each end and resting on towers. The Golden Gate Bridge is an iconic suspension bridge that connects San Francisco to Marin County, built between 1933-1937. At over 1 mile long, it was the longest in the world until 1964 and demonstrates the advantages of suspension bridges to cross long spans over water.
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Shanmugasundaram N
1. The document discusses the philosophy, purpose, and requirements of estimation as well as load bearing and framed structures. Estimation involves approximating the cost of an engineering project before execution and requires thorough knowledge of construction procedures, materials, labor costs, and experience.
2. The purpose of estimation is for successful project implementation, determining material needs, knowing costs beforehand, and maintaining proper project reports.
3. Load bearing structures transfer weight directly to their foundations, while framed structures use beams and columns to distribute loads. Foundations and sections of each type are described.
Presentation on steel, fabrication & erection Munger Ganga BridgeAshish Kumar Yadav
Presentation on Steel Fabrication work and Erection of girder by Cantilever erection method.
One of the largest bridge in India (Bridge Length 3.690 Km)
Similar Bridge 1. Patna- Sonpur (Digha Bridge) across the river Ganga, Bihar
2. Bogibeel across river Brahmaputra in Assam
This document discusses bridge expansion joints. It begins by explaining that expansion joints accommodate movements in bridges due to thermal effects, loading, and structural deformation. It then categorizes joints based on their range of motion and provides examples of common joint types for small, medium, and large movements. Details are given on the construction, advantages, and disadvantages of sliding plate, compression seal, asphaltic plug, poured sealant, strip seal, finger plate, bolt-down, and modular joints. The document concludes with information on installing finger joints and maintaining expansion joints.
This document discusses bridge expansion joints. It begins by defining expansion joints and their purpose of accommodating movement in bridges. It then categorizes expansion joints based on the magnitude of movement they can handle: small (under 45mm), medium (45-130mm), and large (over 130mm). Examples of joint types for each category are given along with their advantages and disadvantages. Small movement joints discussed include sliding plate, compression seal, asphaltic plug, and poured sealant joints. Medium movement joints include strip seal and finger plate joints. Large movement joints include bolt-down panels and modular elastomeric seals. The document also discusses the installation process and maintenance of finger plate joints.
Inspection,Repair and Strengthening of PSC Bridge.Mohammad Furqan
The document provides information on inspection, repair, and strengthening of pre-stressed concrete (PSC) bridges. It discusses common types of deterioration in concrete bridges such as carbonation, chloride attack, alkali-silica reaction, and corrosion of steel reinforcement. It outlines the inspection process including planning, objectives, equipment used, and what elements to inspect such as cracks, bearings, and prestressing components. Non-destructive testing methods like rebound hammer, ultrasonic pulse velocity, and cover meter tests are described. Finally, common repair methods for concrete like mortar filling, grouting, shotcrete, and fiber reinforced polymer wrapping are presented.
The document discusses storage tank inspections and provides details on:
- Inspection techniques used to evaluate tank floors, shells, roofs, and structures. Inspections include engineering calculations per industry standards.
- Common materials used in tank construction like carbon steel, low-chrome alloys, and stainless steel. Corrosion allowances are also discussed.
- Types of inspections like routine in-service, external, and internal inspections. Factors that determine inspection intervals are outlined.
The document discusses principles and concepts related to reinforced cement concrete (RCC). It describes RCC as concrete in which steel reinforcement is embedded to take tensile stresses. The steel is generally round bars of diameters between 6mm to 32mm. RCC is equally strong in tension, compression, and shear. It also discusses RCC mix proportions, uses of RCC in foundations, beams, slabs etc., load transfer, mixing of concrete, formwork, curing and stripping times.
Formwork is a temporary mold into which concrete is poured and shaped. It must be strong enough to support the weight of wet concrete and construction loads. Common materials for formwork include timber, steel, plastic, and aluminum. Proper construction and removal of formwork is important for quality, safety, and economy of concrete structures. Failure to properly brace, support, or remove formwork can lead to collapse during construction.
This document summarizes the description and condition of a bridge located at Chemin Côte-des-Neiges and Chemin Remembrance in Montreal. The bridge is made of concrete and steel and is owned by the city. It shows signs of deterioration from corrosion, cracking, and efflorescence. Testing and evaluations indicate repairs are needed for corrosion, alkali-silica reaction, and cracks. Recommendations include repairs to the concrete and application of protective coatings or overlays. The bridge is rated as deficient but repairs are not urgent unless the planned elimination is delayed.
Composite construction by Er. SURESH RAOAjit Sabnis
Presentation is a part of Structural Engg. series by ACCE(I) Institutes. Deals with details of Composite Structures-Design and Construction with case studies
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxChristopherThomas578171
This document provides an overview of structural construction materials and processes. It discusses aggregates, cement, water, reinforcement, admixtures, workability testing, water-cement ratios, concrete curing, embedded pipes, and cement and rebar storage. Formwork and scaffolding requirements are also outlined. Test procedures like slump tests and concrete cylinder tests are described. Typical reinforced concrete details are shown regarding clear cover, beam-column joints, splices and more.
This document defines formwork and its requirements, categories, types of materials used, and construction process. Formwork is a temporary mold into which concrete is poured and shaped. It must be strong enough to support the weight of wet concrete and loads. There are traditional, engineered, and modern modular types. Common materials are timber, steel, plastic, and aluminum. Proper construction and removal of formwork is important for quality, safety, and economy of concrete structures.
The document discusses different types of reinforcement used in concrete construction including hot rolled deformed bars, mild steel plain bars, cold worked steel reinforcement, and prestressing steel. It also discusses ready mixed concrete (RMX), the working process of RMX, advantages and disadvantages compared to site mixed concrete. The document provides information on major RMX companies. It also discusses insulating concrete formwork (ICF), crosswall construction formwork, and photos of ICF site installation.
This document discusses the advantages of monopole structures over traditional lattice structures for overhead power transmission lines. Monopoles require less land area since they have smaller foundations. They also have lower installation and maintenance costs than lattice structures. Monopole structures are more flexible, reliable under extreme weather, and have a smaller visual impact. The document provides details on the design, manufacturing, testing and specifications of monopole structures and compares their performance to lattice structures.
The document provides information about open web girder and soil testing projects. It discusses the key steps in fabricating an open web girder, including templating, manufacturing masters and jigs, cutting materials, jig filling, assembly, inspection, metalizing, and welding. It also summarizes various soil testing procedures like sieve analysis, compaction testing, shear testing, and Atterberg limits testing to classify soil types. The document appears to be a project report submitted by a student detailing their study of open web girder fabrication and common soil testing methods used in civil engineering projects.
Types of pavement construction procedureBhavik A Shah
The document discusses different types of pavement construction procedures, including continuously reinforced concrete pavement (CRCP), prestressed pavement, steel fibre reinforced concrete pavement, and specifications from organizations like the Indian Road Congress (IRC) and American Concrete Institute (ACI). It provides details on the characteristics, advantages, and construction issues of CRCP and prestressed pavement. It also outlines properties and specifications for steel fibre reinforced concrete and various IRC specifications for pavement construction.
Experimental Investigation on Steel Concrete Composite Floor SlabIRJET Journal
This document summarizes an experimental investigation on steel-concrete composite floor slabs. Cold-formed steel decking with trapezoidal profiles was used to construct composite floor slabs with concrete. Shear connectors in the form of stud bolts connected the steel decking to the concrete. Three specimens were tested - an RCC slab, a composite slab, and a composite truss. The composite truss was fabricated from steel and connected to the decking and concrete with shear connectors. All specimens were tested for load carrying capacity. The composite truss performed comparably to the RCC slab and was found to effectively transfer loads through composite action between the steel and concrete components.
This document provides an overview of piping systems and components. It discusses that piping is used to convey liquids, gases, or materials through a tubular system. Key piping components include pipes, fittings, flanges, valves, and strainers. Common piping materials include carbon steel, alloy steels, and stainless steels. The document also discusses piping design considerations like material selection, insulation, supports, flexibility analysis, and piping and instrumentation diagrams (P&IDs). Piping stress analysis is conducted to ensure stresses from pressures, temperatures, and other loads do not exceed design limits.
WALKSON are International Strategic Sourcing Company for casting,forging,fabrication components. We are committed to the manufacture of castings, forgings, fabrications to your design and specification with Max. weight for casting up to 150tons/pc, for forging up to 200ton/pc,for fabrication according customer requirement. Acting as your reliable partner, our goal is to deliver every competetive product to meet your satisfaction! With more than 10 years international strategic sourcing experience, we will ensure to give metal fields risk free access to our International supply chain
The document discusses the components and functions of a railway track system. It describes the key elements including rails, sleepers, ballast, and fastenings. It explains how the rails transfer load to the sleepers, which then distribute the load to the ballast and subgrade. The ballast provides stability, drainage, and holds the sleepers in proper position. Various types of rails, sleepers, and ballasting materials are also discussed. Maintaining proper gauge, gradient, drainage and joints is important for track performance.
Similar to Maintenance & repair of steel bridges (20)
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
Comparative analysis between traditional aquaponics and reconstructed aquapon...bijceesjournal
The aquaponic system of planting is a method that does not require soil usage. It is a method that only needs water, fish, lava rocks (a substitute for soil), and plants. Aquaponic systems are sustainable and environmentally friendly. Its use not only helps to plant in small spaces but also helps reduce artificial chemical use and minimizes excess water use, as aquaponics consumes 90% less water than soil-based gardening. The study applied a descriptive and experimental design to assess and compare conventional and reconstructed aquaponic methods for reproducing tomatoes. The researchers created an observation checklist to determine the significant factors of the study. The study aims to determine the significant difference between traditional aquaponics and reconstructed aquaponics systems propagating tomatoes in terms of height, weight, girth, and number of fruits. The reconstructed aquaponics system’s higher growth yield results in a much more nourished crop than the traditional aquaponics system. It is superior in its number of fruits, height, weight, and girth measurement. Moreover, the reconstructed aquaponics system is proven to eliminate all the hindrances present in the traditional aquaponics system, which are overcrowding of fish, algae growth, pest problems, contaminated water, and dead fish.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...IJECEIAES
Climate change's impact on the planet forced the United Nations and governments to promote green energies and electric transportation. The deployments of photovoltaic (PV) and electric vehicle (EV) systems gained stronger momentum due to their numerous advantages over fossil fuel types. The advantages go beyond sustainability to reach financial support and stability. The work in this paper introduces the hybrid system between PV and EV to support industrial and commercial plants. This paper covers the theoretical framework of the proposed hybrid system including the required equation to complete the cost analysis when PV and EV are present. In addition, the proposed design diagram which sets the priorities and requirements of the system is presented. The proposed approach allows setup to advance their power stability, especially during power outages. The presented information supports researchers and plant owners to complete the necessary analysis while promoting the deployment of clean energy. The result of a case study that represents a dairy milk farmer supports the theoretical works and highlights its advanced benefits to existing plants. The short return on investment of the proposed approach supports the paper's novelty approach for the sustainable electrical system. In addition, the proposed system allows for an isolated power setup without the need for a transmission line which enhances the safety of the electrical network
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Sinan KOZAK
Sinan from the Delivery Hero mobile infrastructure engineering team shares a deep dive into performance acceleration with Gradle build cache optimizations. Sinan shares their journey into solving complex build-cache problems that affect Gradle builds. By understanding the challenges and solutions found in our journey, we aim to demonstrate the possibilities for faster builds. The case study reveals how overlapping outputs and cache misconfigurations led to significant increases in build times, especially as the project scaled up with numerous modules using Paparazzi tests. The journey from diagnosing to defeating cache issues offers invaluable lessons on maintaining cache integrity without sacrificing functionality.
Advanced control scheme of doubly fed induction generator for wind turbine us...IJECEIAES
This paper describes a speed control device for generating electrical energy on an electricity network based on the doubly fed induction generator (DFIG) used for wind power conversion systems. At first, a double-fed induction generator model was constructed. A control law is formulated to govern the flow of energy between the stator of a DFIG and the energy network using three types of controllers: proportional integral (PI), sliding mode controller (SMC) and second order sliding mode controller (SOSMC). Their different results in terms of power reference tracking, reaction to unexpected speed fluctuations, sensitivity to perturbations, and resilience against machine parameter alterations are compared. MATLAB/Simulink was used to conduct the simulations for the preceding study. Multiple simulations have shown very satisfying results, and the investigations demonstrate the efficacy and power-enhancing capabilities of the suggested control system.
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
2. BRIDGE INSPECTION
SYSTEMATIC OBSERVATION OF
CONDITION AND BEHAVIOUR OF
VARIOUS COMPONENETS/ PARTS
OF A BRIDGE IS CALLED BRIDGE
INSPECTION
3. AIMS OF BRIDGE
INSPECTION
To assess structural soundness and
fitness for use
To identify trouble at the earliest stage
To keep a systematic record of
condition and behaviour (data bank)
To plan repair and rehabilitation
strategy and programme
4. SCHEDULE OF INSPECTION
BRIDGE INSPECTOR
Steel girders including bearings of girders >
12.2m – once in 5 years
Welded girder – initial inspection after 1 year of
installation, than once in 3 years
Composite girder – 1 year and subsequently 5
years
Overstressed girders – at least once in a year
Early steel girder – Floor System– once in a year
: rest-once in 5 years.
Steel work, rivet testing, weld test etc.
5. Schedule Of Inspection
AEN/DEN (Bridge)
Scrutinize – register sent by BRI
Inspect Bridges referred to him
Bridges call for inspection
All overstressed bridges – camber loss
10% test check of BRIs work
Dy. CE/Bridges
Scrutinize bridge inspection register
Inspect Bridges referred to him or call for
inspection
6. BEARINGS
ROLE OF BEARINGS
Transmission of Forces from
superstructure to substructure
Vertical
Horizontal
To permit movement
Translation
Rotation
9. INSPECTION OF BEARINGS
The longitudinal alignment - straight
and central to base plates.
The girders - symmetrically placed
No cavity/ gap between base plate and
bed block
Bearings are free to move in the
designed manner
10. INSPECTION OF BEARINGS
contd.
Check the condition of location strip and
guide strip or shearing of rivets
The anchor bolts - in proper position
and intact. Look for any bend or
shearing of bolt
Uniform seating of rollers & bearing
strip check with feeler gauge
14. INSPECTION OF BEARINGS
contd.
All fittings of rocker and roller- Sound
and proper
Free movement of bearings and
condition of grease
check both ends of girder are in same
level.
15. CAMBER
Camber in steel truss girder is provided
upward amount being equal to
deflection of girder under design load
during fabrication and erection so that
girder under full load, truss shall be in
horizontal plane (nominal shape).
Steel plate girders of span 12.2m,
18.3m & 24.4m span (either welded
construction or rivetted construction)
are not provided with camber
16. PRESTRESSING
Prestressing of open web steel girder of
track bridge is predeforming of
members during fabrication and
erection of girder to ensure girder
under full design load shall be in
nominal shape to minimise
deformation stresses.
17. MEASURE CAMBER
During technical inspection, camber is
checked at every panel point of bottom
chords of both truss with the help of dumpy
level or precision level, which will facilitate
the inspection officials to understand the
structural condition.
As far as possible camber observations are
required to be taken at the ambient
temperature mentioned in the stress sheet.
Graph in different colour.- Dead Load Camber
18. INSPECTION OF STEEL
SUPERSTRUCTURE
Check the Camber
Loss of camber/Sagging due to
Heavy overstressing
Loss of cross section
Increased load/fatigue
Overstressing of joint
Play between holes and rivets
19. LOSS OF CAMBER
IF loss of Camber observed –
Impose SR of 30 KMPH
Investigate in detail-loose rivets,
corrosion, distortion
Measure stress in critical members by
Faraday Palmer Stress Recorder or
Strain Gauges
Check for frozen bearings
20. INSPECTION OF STEEL
SUPERSTRUCTURE contd.
DISTORTION
Plate girder
Top flange- comp member
Web plate near bearings-stress
concentration
Top lateral bracing – excessive
vibration
21. INSPECTION OF STEEL
SUPERSTRUCTURE contd.
DISTORTION
Open web girder
Top chord – insufficient restraints
Diagonal web member – made of flat in
mid span
Bottom chord member – if not braced
properly
Top lateral/ portal bracing - If not braced
properly
Frozen bearings
22. DISTORTION -CHECK
Distortion can be checked visually as
well as by a piano wire stretched
between panel points over the
members
Sometimes web member i.e. diagonal,
vertical and end rakers in through
girder bridges are hit by moving loads
due to shifting of load in wagons,
particularly ODC. Hence, these
members should be checked at 1.2
meters above rail level for any damage.
23. RIVETS
3 groups:
stitch rivets are driven to form a member.
These rivets are driven in workshop and
mostly do not become loose in service life
of girder upto 80 to 100 years
rivets at joints connecting members. These
rivets transfer the load from member to
joint. Tend to become loose after 40 to 50
years.
rivets connecting top and bottom lateral
bracings including sway and portal
bracings tend to become loose on account
of vibrations.
24. TESTING FOR LOOSE
RIVETS
Testing of rivets by rivet hammer chips
off the paint film, making rivet head
steel exposed to environment leading to
corrosion of rivet heads
During technical inspection rivets should
be tested at the critical locations
Inspect Rivets for loose rivets
rivet testing once in 5 years
25. LOOSE RIVET–CRITICAL LOCATION
PLATE/COMPOSITE GIRDER
Web plate to flange angle at end of
girders
Bearing stiffener
Splice rivets of flanges
Bracing and cross frame connection
26. LOOSE RIVET –CRITICAL LOCATION
OPEN WEB GIRDERS
Rail bearer – cross girder connections
Cross girder – panel point gussets
Panel point main gussets
Top/bottom lateral bracings
27. CORROSION
Inspect for corrosion/loss of section
Critical locations
Under wooden sleepers
Formation of water pocket due to
construction
Places where dust accumulate
In vicinity of drainage system
Area directly affected by diesel loco fumes
28. CORROSION- PAINTING
The inspecting officials should clearly
indicate the following during inspection:
i) Major portion of steel work require
only cover coat painting and at some
locations patch painting.
ii) Steel girder requires complete
painting.
iii) Only patch painting.
iv) Paint in good condition, hence no
painting is required.
29. FATIGUE
Fatigue Cracks
Fatigue is the tendency of metal to fail
at lower stress level when subjected to
cyclic loading
Fatigue is becoming important because
of growing volume of traffic at greater
speeds and higher axle loads.
30. LOCATION-FATIGUE CRACK
Critical locations of cracking;
i) Ends of diagonal members near middle of
the span due to reversal of stresses.
ii) Sharp edges at cut notch in stringer
flanges at connections with cross girders.
iii) Top flange plates or flange angles of plate
girders or rail bearers especially below the
sleepers.
31. LOCATION-FATIGUE CRACK
iv) Roots of channel and angles on
account of rolling defects.
v) Corrosion pits at any location in
tension member. Joints where heavy
shear is transmitted.
To arrest the crack propagation, a hole
should be drilled at the end of the crack
in plate and cover material is provided
with rivets.
42. Maintenance of Steel superstructures
Inspection and recording
Cleaning and greasing of bearings
Protective painting system for steel
structures
Replacement of loose rivets or repair to
weld joint
Strengthening of steel superstructure
Replacement of corroded rivets
43. Painting
Steel girders are prone for corrosion
Where humidity > 60%
In coastal areas
Bridge across creek
Bridge surrounded by chemical industry.
Type of traffic
Public nuisance
44. Painting
Surface preperation
Use emery paper , wire brush, scrappers
With power tools
Blast cleaning – sand or grit
Flame cleaning – oxy-acetylene flame
(not to be done on plates with
thickness<10mm)
Luke warm water – 2% detergent
45. Painting
No severe corrosion
Priming coat
Heavy coat of ready mixed paint red lead
priming to IS 102 or
One coat of Zink cromate priming to IS 104
followed by red oxide zink crome priming to IS
2074 or
Two coat of Zink cromate red oxide primer to
IRS P31
Finishing coat
Two cover coats of red oxide paint to IS 123
46. Painting
Severe corrosion
Priming coat
Two coats of red lead priming to IS 102
Finishing
Two coats of aluminium paint to IS 2339
Above also recommended for open web girders in
all cases due to better and longer life.
All floor and top bracing system in electrified
areas with epoxy painting
47. Paint life
Paint red lead - 4 months
Paint red oxide – 1 year
Aluminium
When paste & oil not mixed – 1 year
When mixed – 4 months
Red lead dry paint – No time limit
48. Time lag between paints
Surface prep and Primer – 24 hours
Primer coat and first finishing coat – 7
days
First fininshing coat and 2nd fininshing
coat –7 days
49. Epoxy painting
Should be done for
Flooring system ( cross girder and rail bearer) in
open web girders
Top flange plate of plate girder and underslung
girder
Top bracing system in open web girders in
electrified areas
Steel girders subjected to salt spray
50. Epoxy painting
Remove oil/grease using petrolium hydrocarbon
solvent ( IS 1745)
Prepare the surface by sand blasting
Primer coat – Epoxy zinc phosphate primer
to 60 micron min. ( RDSO M&C/PCN-102/ 86)
Intermediate coat – One coat of micaceous iron
oxide to 100 micron . ( RDSO M&C/PCN-103/ 86)
Finishing coat - two coats of polyurethane
aluminium to 40 micron. ( RDSO M&C/PCN-110/
88)
51. Metallising
Should be done for
Flooring system ( cross girder and rail bearer) in
open web girders
Top flange plate of plate girder and underslung
girder
Top bracing system in open web girders in
electrified areas
Steel girders subjected to salt spray
52. Metallising
Zinc chrome primer to IS 104
Two coat of aluminium paint to IS2339
Min thickness of metal coating 115 micron
Surface preparation crucial
Final cleaning by chilled iron grit G24.
Final surface roughness as per IS 5909.
Aluminium to be sprayed as per BS1475
53. Renewal of loose rivets
Slight slackness does not cause loss of
strength
Renewal should be done only when in groups
All hand loose rivets which have lost 50% of
head
All hammer loose rivets where corrosion has
set in bet head and plate
In end stiffeners where hammer loose rivets
> 30%
54. Renewal of loose rivets
Use only pneumatic rivetting
Not > 10% rivets should be cut at a joint at a
time
Preferably drill a rivet out than use a rivet
buster
Rivet to be heated to white hot
Rivet to be driven and snap removed within
20 sec. After leaving fire
Length
Snap head – L= G +1.5 D +1 mm for every 4mm of grip
Counter sunk – L= G + 0.5 D +1 mm for every 4mm of grip
59. 2 3 4 5 6 7 8
HORIZONTAL LEG OF ANGLE MISSING
DUE TO ACUTE CORROSSION
3' 4' 5' 6' 7'
OHE OHE
VIEW A-A
ADDITIONAL
COVER PLATE
60. CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA