SlideShare a Scribd company logo
REPAIR &
MAINTENANCE OF
STEEL BRIDGES
VINEET GUPTA
SPB-I
BRIDGE INSPECTION
 SYSTEMATIC OBSERVATION OF
CONDITION AND BEHAVIOUR OF
VARIOUS COMPONENETS/ PARTS
OF A BRIDGE IS CALLED BRIDGE
INSPECTION
AIMS OF BRIDGE
INSPECTION
 To assess structural soundness and
fitness for use
 To identify trouble at the earliest stage
 To keep a systematic record of
condition and behaviour (data bank)
 To plan repair and rehabilitation
strategy and programme
SCHEDULE OF INSPECTION
BRIDGE INSPECTOR
 Steel girders including bearings of girders >
12.2m – once in 5 years
 Welded girder – initial inspection after 1 year of
installation, than once in 3 years
 Composite girder – 1 year and subsequently 5
years
 Overstressed girders – at least once in a year
 Early steel girder – Floor System– once in a year
: rest-once in 5 years.
 Steel work, rivet testing, weld test etc.
Schedule Of Inspection
AEN/DEN (Bridge)
 Scrutinize – register sent by BRI
 Inspect Bridges referred to him
 Bridges call for inspection
 All overstressed bridges – camber loss
 10% test check of BRIs work
Dy. CE/Bridges
 Scrutinize bridge inspection register
 Inspect Bridges referred to him or call for
inspection
BEARINGS
ROLE OF BEARINGS
 Transmission of Forces from
superstructure to substructure
 Vertical
 Horizontal
 To permit movement
 Translation
 Rotation
SHIFTING OF ROLLER
BEARING
TRANSVINGERSE SHIFT
INSPECTION OF BEARINGS
 The longitudinal alignment - straight
and central to base plates.
 The girders - symmetrically placed
 No cavity/ gap between base plate and
bed block
 Bearings are free to move in the
designed manner
INSPECTION OF BEARINGS
contd.
 Check the condition of location strip and
guide strip or shearing of rivets
 The anchor bolts - in proper position
and intact. Look for any bend or
shearing of bolt
 Uniform seating of rollers & bearing
strip check with feeler gauge
INSPECTION OF BEARINGS
contd.
INSPECTION OF BEARINGS
contd.
INSPECTION OF BEARINGS
contd.
INSPECTION OF BEARINGS
contd.
 All fittings of rocker and roller- Sound
and proper
 Free movement of bearings and
condition of grease
 check both ends of girder are in same
level.
CAMBER
 Camber in steel truss girder is provided
upward amount being equal to
deflection of girder under design load
during fabrication and erection so that
girder under full load, truss shall be in
horizontal plane (nominal shape).
 Steel plate girders of span 12.2m,
18.3m & 24.4m span (either welded
construction or rivetted construction)
are not provided with camber
PRESTRESSING
 Prestressing of open web steel girder of
track bridge is predeforming of
members during fabrication and
erection of girder to ensure girder
under full design load shall be in
nominal shape to minimise
deformation stresses.
MEASURE CAMBER
 During technical inspection, camber is
checked at every panel point of bottom
chords of both truss with the help of dumpy
level or precision level, which will facilitate
the inspection officials to understand the
structural condition.
 As far as possible camber observations are
required to be taken at the ambient
temperature mentioned in the stress sheet.
 Graph in different colour.- Dead Load Camber
INSPECTION OF STEEL
SUPERSTRUCTURE
Check the Camber
 Loss of camber/Sagging due to
 Heavy overstressing
 Loss of cross section
 Increased load/fatigue
 Overstressing of joint
 Play between holes and rivets
LOSS OF CAMBER
 IF loss of Camber observed –
 Impose SR of 30 KMPH
 Investigate in detail-loose rivets,
corrosion, distortion
 Measure stress in critical members by
Faraday Palmer Stress Recorder or
Strain Gauges
 Check for frozen bearings
INSPECTION OF STEEL
SUPERSTRUCTURE contd.
DISTORTION
Plate girder
Top flange- comp member
Web plate near bearings-stress
concentration
Top lateral bracing – excessive
vibration
INSPECTION OF STEEL
SUPERSTRUCTURE contd.
DISTORTION
Open web girder
 Top chord – insufficient restraints
 Diagonal web member – made of flat in
mid span
 Bottom chord member – if not braced
properly
 Top lateral/ portal bracing - If not braced
properly
 Frozen bearings
DISTORTION -CHECK
 Distortion can be checked visually as
well as by a piano wire stretched
between panel points over the
members
 Sometimes web member i.e. diagonal,
vertical and end rakers in through
girder bridges are hit by moving loads
due to shifting of load in wagons,
particularly ODC. Hence, these
members should be checked at 1.2
meters above rail level for any damage.
RIVETS
 3 groups:
 stitch rivets are driven to form a member.
These rivets are driven in workshop and
mostly do not become loose in service life
of girder upto 80 to 100 years
 rivets at joints connecting members. These
rivets transfer the load from member to
joint. Tend to become loose after 40 to 50
years.
 rivets connecting top and bottom lateral
bracings including sway and portal
bracings tend to become loose on account
of vibrations.
TESTING FOR LOOSE
RIVETS
 Testing of rivets by rivet hammer chips
off the paint film, making rivet head
steel exposed to environment leading to
corrosion of rivet heads
 During technical inspection rivets should
be tested at the critical locations
 Inspect Rivets for loose rivets
 rivet testing once in 5 years
LOOSE RIVET–CRITICAL LOCATION
PLATE/COMPOSITE GIRDER
 Web plate to flange angle at end of
girders
 Bearing stiffener
 Splice rivets of flanges
 Bracing and cross frame connection
LOOSE RIVET –CRITICAL LOCATION
OPEN WEB GIRDERS
 Rail bearer – cross girder connections
 Cross girder – panel point gussets
 Panel point main gussets
 Top/bottom lateral bracings
CORROSION
Inspect for corrosion/loss of section
Critical locations
 Under wooden sleepers
 Formation of water pocket due to
construction
 Places where dust accumulate
 In vicinity of drainage system
 Area directly affected by diesel loco fumes
CORROSION- PAINTING
 The inspecting officials should clearly
indicate the following during inspection:
 i) Major portion of steel work require
only cover coat painting and at some
locations patch painting.
 ii) Steel girder requires complete
painting.
 iii) Only patch painting.
 iv) Paint in good condition, hence no
painting is required.
FATIGUE
 Fatigue Cracks
 Fatigue is the tendency of metal to fail
at lower stress level when subjected to
cyclic loading
 Fatigue is becoming important because
of growing volume of traffic at greater
speeds and higher axle loads.
LOCATION-FATIGUE CRACK
 Critical locations of cracking;
 i) Ends of diagonal members near middle of
the span due to reversal of stresses.
 ii) Sharp edges at cut notch in stringer
flanges at connections with cross girders.
 iii) Top flange plates or flange angles of plate
girders or rail bearers especially below the
sleepers.
LOCATION-FATIGUE CRACK
 iv) Roots of channel and angles on
account of rolling defects.
 v) Corrosion pits at any location in
tension member. Joints where heavy
shear is transmitted.
 To arrest the crack propagation, a hole
should be drilled at the end of the crack
in plate and cover material is provided
with rivets.
CANTI LEVER BRACKET CORROSION LOSS
TILTED ROCKER BEARING
TILTED MULTIPLE ROCKER BEARING
GIRDER BOTTOM FLANGE CORROSION LOSS
TOP CHORD CORROSION AT JOINT
BRACING MEMBER CORROSION LOSS
BOTTOM TRUSS CHORD CORROSION
BOTTOM CHORD CORROSION AT JOINT
CORROSION OF PIN & CRACKING OF HANGER
PLATE
GIRDER BOTTOM FLANGE VEHICLE IMPACT
DAMAGE
Maintenance of Steel superstructures
 Inspection and recording
 Cleaning and greasing of bearings
 Protective painting system for steel
structures
 Replacement of loose rivets or repair to
weld joint
 Strengthening of steel superstructure
 Replacement of corroded rivets
Painting
 Steel girders are prone for corrosion
 Where humidity > 60%
 In coastal areas
 Bridge across creek
 Bridge surrounded by chemical industry.
 Type of traffic
 Public nuisance
Painting
Surface preperation
 Use emery paper , wire brush, scrappers
 With power tools
 Blast cleaning – sand or grit
 Flame cleaning – oxy-acetylene flame
(not to be done on plates with
thickness<10mm)
 Luke warm water – 2% detergent
Painting
No severe corrosion
 Priming coat
 Heavy coat of ready mixed paint red lead
priming to IS 102 or
 One coat of Zink cromate priming to IS 104
followed by red oxide zink crome priming to IS
2074 or
 Two coat of Zink cromate red oxide primer to
IRS P31
 Finishing coat
 Two cover coats of red oxide paint to IS 123
Painting
Severe corrosion
 Priming coat
 Two coats of red lead priming to IS 102
 Finishing
 Two coats of aluminium paint to IS 2339
 Above also recommended for open web girders in
all cases due to better and longer life.
 All floor and top bracing system in electrified
areas with epoxy painting
Paint life
 Paint red lead - 4 months
 Paint red oxide – 1 year
 Aluminium
 When paste & oil not mixed – 1 year
 When mixed – 4 months
 Red lead dry paint – No time limit
Time lag between paints
 Surface prep and Primer – 24 hours
 Primer coat and first finishing coat – 7
days
 First fininshing coat and 2nd fininshing
coat –7 days
Epoxy painting
Should be done for
 Flooring system ( cross girder and rail bearer) in
open web girders
 Top flange plate of plate girder and underslung
girder
 Top bracing system in open web girders in
electrified areas
 Steel girders subjected to salt spray
Epoxy painting
 Remove oil/grease using petrolium hydrocarbon
solvent ( IS 1745)
 Prepare the surface by sand blasting
 Primer coat – Epoxy zinc phosphate primer
to 60 micron min. ( RDSO M&C/PCN-102/ 86)
 Intermediate coat – One coat of micaceous iron
oxide to 100 micron . ( RDSO M&C/PCN-103/ 86)
 Finishing coat - two coats of polyurethane
aluminium to 40 micron. ( RDSO M&C/PCN-110/
88)
Metallising
Should be done for
 Flooring system ( cross girder and rail bearer) in
open web girders
 Top flange plate of plate girder and underslung
girder
 Top bracing system in open web girders in
electrified areas
 Steel girders subjected to salt spray
Metallising
 Zinc chrome primer to IS 104
 Two coat of aluminium paint to IS2339
 Min thickness of metal coating 115 micron
 Surface preparation crucial
 Final cleaning by chilled iron grit G24.
 Final surface roughness as per IS 5909.
 Aluminium to be sprayed as per BS1475
Renewal of loose rivets
 Slight slackness does not cause loss of
strength
 Renewal should be done only when in groups
 All hand loose rivets which have lost 50% of
head
 All hammer loose rivets where corrosion has
set in bet head and plate
 In end stiffeners where hammer loose rivets
> 30%
Renewal of loose rivets
 Use only pneumatic rivetting
 Not > 10% rivets should be cut at a joint at a
time
 Preferably drill a rivet out than use a rivet
buster
 Rivet to be heated to white hot
 Rivet to be driven and snap removed within
20 sec. After leaving fire
 Length
 Snap head – L= G +1.5 D +1 mm for every 4mm of grip
 Counter sunk – L= G + 0.5 D +1 mm for every 4mm of grip
Strengthening
CRACKED GIRDER REPAIR
Vertical
Member
Diagonal
Member
Flooring
Detail at 'A'
Member broken at node No.1
due to excess corrosion
NEW
GUSSET
PLATE
2 3 4 5 6 7 8
HORIZONTAL LEG OF ANGLE MISSING
DUE TO ACUTE CORROSSION
3' 4' 5' 6' 7'
OHE OHE
VIEW A-A
ADDITIONAL
COVER PLATE
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
CORRODED BOTTOM
FLANGE ANGLE WITH
MISSING LEG BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
BOTTOM SPLICE PLATE
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
INTACT BOTTOM FLANGE
ANGLE
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
NEW ANGLES WELDED
TO PROVIDE BOTTOM
FLANGE AREA
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges
Maintenance &amp; repair of steel bridges

More Related Content

What's hot

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Halcrow
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge Bearings
AyushHajare
 
Internship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam ConstructionInternship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam Construction
Khaliqur Rahman
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In India
Khyati Saggu
 
Mix design-ppt
Mix design-pptMix design-ppt
Mix design-ppt
narasimha reddy
 
Sleepers and Their types
Sleepers and Their typesSleepers and Their types
Sleepers and Their types
17CE67
 
Bridge
BridgeBridge
Bridge
Vamshi Krish
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
Ana Debbarma
 
Bridges and its Types & Components by Chetan Bisht
Bridges and its Types & Components by  Chetan BishtBridges and its Types & Components by  Chetan Bisht
Bridges and its Types & Components by Chetan Bisht
ChetanBisht16
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
Gaurang Kakadiya
 
Concrete Technology Study Notes
Concrete Technology Study NotesConcrete Technology Study Notes
Concrete Technology Study Notes
SHAMJITH KM
 
Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concrete
Ayaz khan
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
MohitkumarBharti
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
krishnacp
 
Ce8611 Highway Engineering Laboratory Manual
Ce8611 Highway Engineering Laboratory ManualCe8611 Highway Engineering Laboratory Manual
Ce8611 Highway Engineering Laboratory Manual
Lokesh Kalliz
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
Tarique048
 
Introduction to bridges
Introduction to bridgesIntroduction to bridges
Introduction to bridges
Dheerendra Prasad
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
Selva Prakash
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
Parikshit Hurukadli
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Shanmugasundaram N
 

What's hot (20)

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge Bearings
 
Internship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam ConstructionInternship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam Construction
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In India
 
Mix design-ppt
Mix design-pptMix design-ppt
Mix design-ppt
 
Sleepers and Their types
Sleepers and Their typesSleepers and Their types
Sleepers and Their types
 
Bridge
BridgeBridge
Bridge
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
Bridges and its Types & Components by Chetan Bisht
Bridges and its Types & Components by  Chetan BishtBridges and its Types & Components by  Chetan Bisht
Bridges and its Types & Components by Chetan Bisht
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
Concrete Technology Study Notes
Concrete Technology Study NotesConcrete Technology Study Notes
Concrete Technology Study Notes
 
Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concrete
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
 
Ce8611 Highway Engineering Laboratory Manual
Ce8611 Highway Engineering Laboratory ManualCe8611 Highway Engineering Laboratory Manual
Ce8611 Highway Engineering Laboratory Manual
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
 
Introduction to bridges
Introduction to bridgesIntroduction to bridges
Introduction to bridges
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
 

Similar to Maintenance &amp; repair of steel bridges

Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
Ashish Kumar Yadav
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
Rais Uddin
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
Divya Vishnoi
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.
Mohammad Furqan
 
TANK 13042023.pptx
TANK 13042023.pptxTANK 13042023.pptx
TANK 13042023.pptx
Mohamedazam39
 
RCC-.pdf
RCC-.pdfRCC-.pdf
RCC-.pdf
NehaPaliwal31
 
Formwork
FormworkFormwork
Formwork
natesh0142
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
Monique F M
 
Composite construction by Er. SURESH RAO
Composite construction by Er. SURESH RAOComposite construction by Er. SURESH RAO
Composite construction by Er. SURESH RAO
Ajit Sabnis
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
ChristopherThomas578171
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
Kishor Ade
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
somitra bhardwaj
 
Pole type structures
Pole type structuresPole type structures
Pole type structures
Harish Agarwal
 
Presentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.pptPresentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.ppt
ashadiamir1
 
report of open web girder (railway)
report of open web girder (railway)report of open web girder (railway)
report of open web girder (railway)
Alankar jaiswal
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
Bhavik A Shah
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
IRJET Journal
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
Md Gaffar Beag
 
walkson-presentation-r1.pdf
walkson-presentation-r1.pdfwalkson-presentation-r1.pdf
walkson-presentation-r1.pdf
walkson1
 
3rd unit
3rd unit3rd unit
3rd unit
jagadish108
 

Similar to Maintenance &amp; repair of steel bridges (20)

Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.
 
TANK 13042023.pptx
TANK 13042023.pptxTANK 13042023.pptx
TANK 13042023.pptx
 
RCC-.pdf
RCC-.pdfRCC-.pdf
RCC-.pdf
 
Formwork
FormworkFormwork
Formwork
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
Composite construction by Er. SURESH RAO
Composite construction by Er. SURESH RAOComposite construction by Er. SURESH RAO
Composite construction by Er. SURESH RAO
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
 
Pole type structures
Pole type structuresPole type structures
Pole type structures
 
Presentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.pptPresentation on Piping Familiarization.ppt
Presentation on Piping Familiarization.ppt
 
report of open web girder (railway)
report of open web girder (railway)report of open web girder (railway)
report of open web girder (railway)
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
walkson-presentation-r1.pdf
walkson-presentation-r1.pdfwalkson-presentation-r1.pdf
walkson-presentation-r1.pdf
 
3rd unit
3rd unit3rd unit
3rd unit
 

Recently uploaded

ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
shivani5543
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 

Recently uploaded (20)

ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 

Maintenance &amp; repair of steel bridges

  • 1. REPAIR & MAINTENANCE OF STEEL BRIDGES VINEET GUPTA SPB-I
  • 2. BRIDGE INSPECTION  SYSTEMATIC OBSERVATION OF CONDITION AND BEHAVIOUR OF VARIOUS COMPONENETS/ PARTS OF A BRIDGE IS CALLED BRIDGE INSPECTION
  • 3. AIMS OF BRIDGE INSPECTION  To assess structural soundness and fitness for use  To identify trouble at the earliest stage  To keep a systematic record of condition and behaviour (data bank)  To plan repair and rehabilitation strategy and programme
  • 4. SCHEDULE OF INSPECTION BRIDGE INSPECTOR  Steel girders including bearings of girders > 12.2m – once in 5 years  Welded girder – initial inspection after 1 year of installation, than once in 3 years  Composite girder – 1 year and subsequently 5 years  Overstressed girders – at least once in a year  Early steel girder – Floor System– once in a year : rest-once in 5 years.  Steel work, rivet testing, weld test etc.
  • 5. Schedule Of Inspection AEN/DEN (Bridge)  Scrutinize – register sent by BRI  Inspect Bridges referred to him  Bridges call for inspection  All overstressed bridges – camber loss  10% test check of BRIs work Dy. CE/Bridges  Scrutinize bridge inspection register  Inspect Bridges referred to him or call for inspection
  • 6. BEARINGS ROLE OF BEARINGS  Transmission of Forces from superstructure to substructure  Vertical  Horizontal  To permit movement  Translation  Rotation
  • 9. INSPECTION OF BEARINGS  The longitudinal alignment - straight and central to base plates.  The girders - symmetrically placed  No cavity/ gap between base plate and bed block  Bearings are free to move in the designed manner
  • 10. INSPECTION OF BEARINGS contd.  Check the condition of location strip and guide strip or shearing of rivets  The anchor bolts - in proper position and intact. Look for any bend or shearing of bolt  Uniform seating of rollers & bearing strip check with feeler gauge
  • 14. INSPECTION OF BEARINGS contd.  All fittings of rocker and roller- Sound and proper  Free movement of bearings and condition of grease  check both ends of girder are in same level.
  • 15. CAMBER  Camber in steel truss girder is provided upward amount being equal to deflection of girder under design load during fabrication and erection so that girder under full load, truss shall be in horizontal plane (nominal shape).  Steel plate girders of span 12.2m, 18.3m & 24.4m span (either welded construction or rivetted construction) are not provided with camber
  • 16. PRESTRESSING  Prestressing of open web steel girder of track bridge is predeforming of members during fabrication and erection of girder to ensure girder under full design load shall be in nominal shape to minimise deformation stresses.
  • 17. MEASURE CAMBER  During technical inspection, camber is checked at every panel point of bottom chords of both truss with the help of dumpy level or precision level, which will facilitate the inspection officials to understand the structural condition.  As far as possible camber observations are required to be taken at the ambient temperature mentioned in the stress sheet.  Graph in different colour.- Dead Load Camber
  • 18. INSPECTION OF STEEL SUPERSTRUCTURE Check the Camber  Loss of camber/Sagging due to  Heavy overstressing  Loss of cross section  Increased load/fatigue  Overstressing of joint  Play between holes and rivets
  • 19. LOSS OF CAMBER  IF loss of Camber observed –  Impose SR of 30 KMPH  Investigate in detail-loose rivets, corrosion, distortion  Measure stress in critical members by Faraday Palmer Stress Recorder or Strain Gauges  Check for frozen bearings
  • 20. INSPECTION OF STEEL SUPERSTRUCTURE contd. DISTORTION Plate girder Top flange- comp member Web plate near bearings-stress concentration Top lateral bracing – excessive vibration
  • 21. INSPECTION OF STEEL SUPERSTRUCTURE contd. DISTORTION Open web girder  Top chord – insufficient restraints  Diagonal web member – made of flat in mid span  Bottom chord member – if not braced properly  Top lateral/ portal bracing - If not braced properly  Frozen bearings
  • 22. DISTORTION -CHECK  Distortion can be checked visually as well as by a piano wire stretched between panel points over the members  Sometimes web member i.e. diagonal, vertical and end rakers in through girder bridges are hit by moving loads due to shifting of load in wagons, particularly ODC. Hence, these members should be checked at 1.2 meters above rail level for any damage.
  • 23. RIVETS  3 groups:  stitch rivets are driven to form a member. These rivets are driven in workshop and mostly do not become loose in service life of girder upto 80 to 100 years  rivets at joints connecting members. These rivets transfer the load from member to joint. Tend to become loose after 40 to 50 years.  rivets connecting top and bottom lateral bracings including sway and portal bracings tend to become loose on account of vibrations.
  • 24. TESTING FOR LOOSE RIVETS  Testing of rivets by rivet hammer chips off the paint film, making rivet head steel exposed to environment leading to corrosion of rivet heads  During technical inspection rivets should be tested at the critical locations  Inspect Rivets for loose rivets  rivet testing once in 5 years
  • 25. LOOSE RIVET–CRITICAL LOCATION PLATE/COMPOSITE GIRDER  Web plate to flange angle at end of girders  Bearing stiffener  Splice rivets of flanges  Bracing and cross frame connection
  • 26. LOOSE RIVET –CRITICAL LOCATION OPEN WEB GIRDERS  Rail bearer – cross girder connections  Cross girder – panel point gussets  Panel point main gussets  Top/bottom lateral bracings
  • 27. CORROSION Inspect for corrosion/loss of section Critical locations  Under wooden sleepers  Formation of water pocket due to construction  Places where dust accumulate  In vicinity of drainage system  Area directly affected by diesel loco fumes
  • 28. CORROSION- PAINTING  The inspecting officials should clearly indicate the following during inspection:  i) Major portion of steel work require only cover coat painting and at some locations patch painting.  ii) Steel girder requires complete painting.  iii) Only patch painting.  iv) Paint in good condition, hence no painting is required.
  • 29. FATIGUE  Fatigue Cracks  Fatigue is the tendency of metal to fail at lower stress level when subjected to cyclic loading  Fatigue is becoming important because of growing volume of traffic at greater speeds and higher axle loads.
  • 30. LOCATION-FATIGUE CRACK  Critical locations of cracking;  i) Ends of diagonal members near middle of the span due to reversal of stresses.  ii) Sharp edges at cut notch in stringer flanges at connections with cross girders.  iii) Top flange plates or flange angles of plate girders or rail bearers especially below the sleepers.
  • 31. LOCATION-FATIGUE CRACK  iv) Roots of channel and angles on account of rolling defects.  v) Corrosion pits at any location in tension member. Joints where heavy shear is transmitted.  To arrest the crack propagation, a hole should be drilled at the end of the crack in plate and cover material is provided with rivets.
  • 32. CANTI LEVER BRACKET CORROSION LOSS
  • 35. GIRDER BOTTOM FLANGE CORROSION LOSS
  • 38. BOTTOM TRUSS CHORD CORROSION
  • 40. CORROSION OF PIN & CRACKING OF HANGER PLATE
  • 41. GIRDER BOTTOM FLANGE VEHICLE IMPACT DAMAGE
  • 42. Maintenance of Steel superstructures  Inspection and recording  Cleaning and greasing of bearings  Protective painting system for steel structures  Replacement of loose rivets or repair to weld joint  Strengthening of steel superstructure  Replacement of corroded rivets
  • 43. Painting  Steel girders are prone for corrosion  Where humidity > 60%  In coastal areas  Bridge across creek  Bridge surrounded by chemical industry.  Type of traffic  Public nuisance
  • 44. Painting Surface preperation  Use emery paper , wire brush, scrappers  With power tools  Blast cleaning – sand or grit  Flame cleaning – oxy-acetylene flame (not to be done on plates with thickness<10mm)  Luke warm water – 2% detergent
  • 45. Painting No severe corrosion  Priming coat  Heavy coat of ready mixed paint red lead priming to IS 102 or  One coat of Zink cromate priming to IS 104 followed by red oxide zink crome priming to IS 2074 or  Two coat of Zink cromate red oxide primer to IRS P31  Finishing coat  Two cover coats of red oxide paint to IS 123
  • 46. Painting Severe corrosion  Priming coat  Two coats of red lead priming to IS 102  Finishing  Two coats of aluminium paint to IS 2339  Above also recommended for open web girders in all cases due to better and longer life.  All floor and top bracing system in electrified areas with epoxy painting
  • 47. Paint life  Paint red lead - 4 months  Paint red oxide – 1 year  Aluminium  When paste & oil not mixed – 1 year  When mixed – 4 months  Red lead dry paint – No time limit
  • 48. Time lag between paints  Surface prep and Primer – 24 hours  Primer coat and first finishing coat – 7 days  First fininshing coat and 2nd fininshing coat –7 days
  • 49. Epoxy painting Should be done for  Flooring system ( cross girder and rail bearer) in open web girders  Top flange plate of plate girder and underslung girder  Top bracing system in open web girders in electrified areas  Steel girders subjected to salt spray
  • 50. Epoxy painting  Remove oil/grease using petrolium hydrocarbon solvent ( IS 1745)  Prepare the surface by sand blasting  Primer coat – Epoxy zinc phosphate primer to 60 micron min. ( RDSO M&C/PCN-102/ 86)  Intermediate coat – One coat of micaceous iron oxide to 100 micron . ( RDSO M&C/PCN-103/ 86)  Finishing coat - two coats of polyurethane aluminium to 40 micron. ( RDSO M&C/PCN-110/ 88)
  • 51. Metallising Should be done for  Flooring system ( cross girder and rail bearer) in open web girders  Top flange plate of plate girder and underslung girder  Top bracing system in open web girders in electrified areas  Steel girders subjected to salt spray
  • 52. Metallising  Zinc chrome primer to IS 104  Two coat of aluminium paint to IS2339  Min thickness of metal coating 115 micron  Surface preparation crucial  Final cleaning by chilled iron grit G24.  Final surface roughness as per IS 5909.  Aluminium to be sprayed as per BS1475
  • 53. Renewal of loose rivets  Slight slackness does not cause loss of strength  Renewal should be done only when in groups  All hand loose rivets which have lost 50% of head  All hammer loose rivets where corrosion has set in bet head and plate  In end stiffeners where hammer loose rivets > 30%
  • 54. Renewal of loose rivets  Use only pneumatic rivetting  Not > 10% rivets should be cut at a joint at a time  Preferably drill a rivet out than use a rivet buster  Rivet to be heated to white hot  Rivet to be driven and snap removed within 20 sec. After leaving fire  Length  Snap head – L= G +1.5 D +1 mm for every 4mm of grip  Counter sunk – L= G + 0.5 D +1 mm for every 4mm of grip
  • 57.
  • 58. Vertical Member Diagonal Member Flooring Detail at 'A' Member broken at node No.1 due to excess corrosion NEW GUSSET PLATE
  • 59. 2 3 4 5 6 7 8 HORIZONTAL LEG OF ANGLE MISSING DUE TO ACUTE CORROSSION 3' 4' 5' 6' 7' OHE OHE VIEW A-A ADDITIONAL COVER PLATE
  • 60. CORRODED BOTTOM FLANGE ANGLE WITH MISSING LEG BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA CORRODED BOTTOM FLANGE ANGLE WITH MISSING LEG BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA CORRODED BOTTOM FLANGE ANGLE WITH MISSING LEG BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA BOTTOM SPLICE PLATE INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA INTACT BOTTOM FLANGE ANGLE NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA NEW ANGLES WELDED TO PROVIDE BOTTOM FLANGE AREA