Oracle Primavera Cloud
Lean Scheduling
Nihat YILDIRIM
nihat@prmyazilim.com
Agenda
Industry Challenges
Our Solution
Solution Presentation
Value & Benefits
Q&A
1
2
3
4
2
5
Problem
• Ten times the number of activities today compared to 25 years ago
• Correctly managing the additional activities and relationships requires
technical expertise, discipline, and time
• Commercial construction can not afford full-time project schedulers
• Resequencing activities is tedious, laborious, and costly
• Never intended to micro-manage a project
• Intended to manage the big picture
Critical Path Method Schedules…
3
Impact
• Large schedules do not effectively communicate the plan
• Incorrectly managing schedule can be risky from a legal perspective
• Construction productivity has decreased
• Projects taking longer
Critical Path Method Schedules…
4
Coordination
Engineering & Construction
projects are continually
challenged with
coordination complexities.
How to assemble Owners,
Contractors,
Subcontractors, Suppliers
and Specialty Service Firms
around shared knowledge
and common goals to
create an environment of
mutual benefit.
Commitment
5
Community
Top challenges
Coordination
Engineering & Construction
projects are continually
challenged with
coordination complexities.
How to assemble Owners,
Contractors,
Subcontractors, Suppliers
and Specialty Service Firms
around shared knowledge
and common goals to
create an environment of
mutual benefit.
Commitment
Scheduling discipline has
always worked to reflect
the closest image of reality
it could, with logical ties
between activities. Yet even
the best well laid plans can
fail to capture the
commitments that must be
made between field
disciplines at the physical
workface.
6
Community
Top challenges
Coordination
Engineering & Construction
projects are continually
challenged with
coordination complexities.
How to assemble Owners,
Contractors,
Subcontractors, Suppliers
and Specialty Service Firms
around shared knowledge
and common goals to
create an environment of
mutual benefit.
Commitment
Scheduling discipline has
always worked to reflect
the closest image of reality
it could, with logical ties
between activities. Yet even
the best well laid plans can
fail to capture the
commitments that must be
made between field
disciplines at the physical
workface.
7
Community
Engineering & Construction
projects will always have
multiple stakeholders and
this makes the industry
historically litigious to
operate in. Building a sense
of community around what
is to be built can be difficult
given the agendas, legal
ramifications and potential
monetary losses that
accompany project failure.
Top challenges
İş programı detay seviyeleri
Özet
Detay
Yöneticiler
Saha
İş programı detay seviyeleri
Level-1 (Mastır program) projenin süresini ve çıktılarını kabaca gösteren detay seviyesi en az
özet iş programıdır. İhale, yatırım onayı vb amaçlar için kullanılır. Feasibility, design,
procurement, construction, installation, commissioning gibi seviyeleri içerir.
Level-2 (Özet program)her iş paketinin teslimatını net olarak gösterir ve Level-1 programa göre
daha detaylıdır ancak özet iş program sayılır. Sözleşme öncesi veya hemen sonrası hazırlanır.
Level-3 (Detay program)koordinasyon iş programıdır ve Level-2 programın detaylandırılması ile
ortaya çıkar. Kritik yol analizinin uygulanmasına elverişli bir detayı içermelidir ve disiplinlerin/iş
paketlerinin arayüzünü/etkileşimlerini göstermelidir. Yapım öncesi hazırlanır ve sunulur.
Level-4 (Yapım programı) çok detaylı, kaynak ve ekiplere atanabilecek aktivitelerden oluşur ve
ilerleme takibinin bazını oluşturur. Sorgulanabilir adam-saat veya ağırlık girilen aktivitelerden
oluşur ve verim konusunda fikir verir. İlerlemeler sonrası kısa vadeli look-ahead raporlamalar
yapmaya elverişlidir.
Level-5 (Kısa vadeli program) saha sorumlularının ve formenlerin işlerini takip etmek için
hazırladıkları 1-2 haftalık geçici programlardır.
Agenda
Industry Challenges
Our Solution
Solution Presentation
Value & Benefits
Q&A
1
2
3
4
10
5
Our Solution
• Schedule Module
– Manage the big picture, CPM schedule network
– Use Activities for rigid, physically dependent sequences
– Reduce activities, relationships, and effort to correctly maintain them
• Lean Module (Work Plan & Task List)
– Manage the short interval, weekly work plan
– Use Tasks for coordinated, flexible sequences
– Engage the project team in defining & sequencing Tasks to support Activities
– Utilize Lean Construction Institute methodologies (PPC, Reasons, Pull-Planning)
Oracle Primavera Cloud Schedule, Work Plan & Tasks
• Non-profit founded in 1997
• Intention is to find a better way to
schedule
• Vision to increase satisfaction with
design & construction delivery
• Includes local communities in
different countries
12
Lean Construction Institute
13
How it is done now?
14
Alternative=Digital Planning Board
Confidential – Oracle
Digital Planning Board
Touch Screen Enabled!
Integrated CPM & Lean Scheduling Process
16
Define
Phases
with
WBS
Monitor
Performance
LastPlanners®
breakdown
Activities
into smaller
Tasks
Define
Activities,
Durations,
Relationships
LastPlanners®
Commit to
Due Dates,
Complete
Tasks
Lean Scheduling Concepts
• Planning Period: In lean scheduling, a meeting facilitator leads a group of
project collaborators (superintendents, subcontractors, tradespeople, and
other stakeholders) from various companies in adding tasks to a planning
board. These meetings may occur daily or weekly and are focused on the
work to be performed over a short-term period, typically the current week
and the following week.
• Tasks:Tasks are identified during planning as the physical work to be
performed by the tradespeople on the project. Each task has a name,
duration, and associated company responsible for performing the work on
the task. There are two task types: Task and Task Milestone.
17
Lean Scheduling Concepts
• Commitments:Commitments are optional submitted agreements to
assume responsibility for the work to be performed on a public task. The
assigned company and user commit to perform the work by a specific date.
If the commitment due date is not met, then the task is overdue.
• Hand-offs:A hand-off is a connection between two tasks that indicates the
sequence in which the task work should be performed. Work is "handed
off" to the next task to be performed after its preceding task has been
completed.
18
Lean Scheduling Concepts
• Push Planning: In traditional or push planning, work is planned in sequence
from the start of a project or task milestone. Planners "push" work through
the sequence according to an established schedule.
• Pull Planning: In pull planning, the sequence of work is determined by
responsible parties planning backward from a task milestone or goal.
Performers request or "pull" work from their dependencies based on
demand for subsequent work to begin and after all prerequisite tasks have
been completed.
19
Work Breakdown Structure
Create the “Big Picture” schedule by organizing project into manageable
phases using the WBS (Work Breakdown Structure)
Easily model the project
schedule. The WBS defines
project phases and creates a
framework that effectively
represents the overall plan.
 Simple to Create
 Leverage Templates
 Indent/Outdent
 Cut/Copy/Paste
 Grid or Gantt
20
Activities, Durations, Relationships
Create logical relationships between Activities in the CPM network
Traditional CPM scheduling
defines activities, durations
and relationships. This
determines the critical path,
project duration, and project
completion date.
 Add Activities
 Define Durations
 Sequence Activities using
Relationships
 Connect Activities between
WBS elements to reflect
transitions between phases
 Calculate the schedule
21
LastPlanners® Breakdown Activities
LastPlanners® breakdown Activities, identify Tasks durations, sequences &
due dates in facilitated production meetings
LastPlanners® breakdown
Activities into smaller Tasks,
collaboratively plan their due
dates, and commit to complete
them as planned.
 The Hopper
- Unplanned Tasks
- Activity Optional
- Collapse/Expand
 Tasks get durations,
sequences, and due dates
22
Activity and Tasks
23
Activity’s Tasks
24
Process
25
Create
Task
Plan Task
(Set Due Date)
Commit
Finish Date
Recommit
(When missed the
committed date)
Complete
Task
LastPlanners® Commit & Complete
The LastPlanners® commit to Due Dates on the Planning Board, complete
when done, and re-commit if not completed
The planning board is where
field disciplines commit to
Task due dates. Each field
discipline has a different Task
color assignment on the
Planning Board.
 Digital Planning Board vs.
Trailer Wall
 Planned Tasks
 Committed Tasks
 Completed Tasks
 Overdue Tasks
 Reference Activities
 Collapse/Expand
26
Monitor Performance
Monitor Planned Percent Complete (PPC) & Reasons for missed
commitments per Lean Construction Institute’s best practices
With the field executing, it’s
now about capturing
completions. If commitments
are missed, reason codes are
assigned, and new
commitments are made. Tasks
alert the CPM network for
incompatible dates or status.
 Project PPC
 Company PPC
(Inherited Colors)
 Reasons for Missed
Commitments
 One Time Frame, All Charts
27
Agenda
Industry Challenges
Our Solution
Solution Presentation
Value & Benefits
Q&A
1
2
3
4
28
5
Oracle Primavera Cloud Work Plan
Introduction
29
Hopper
• Unplanned Tasks
• Group/Ungroup
• Activity Optional
• Collapse/Expand
Work Plan
30
Planning Board
• Smart Board
• Planned Tasks
• Committed Tasks
• Completed Tasks
• Overdue Tasks
• Reference Activities
• Collapse/Expand
Work Plan
31
Buckets
• Navigation
• Future Planning
Periods
Work Plan
32
View Options
• Saved Views
• Planning Window
• Smart Quick Filters
• Group by Activity
• Navigation
• Search
Work Plan
33
Oracle Primavera Cloud Task List
Introduction
34
Grid
• Discussions
• Flags
• Configurable Columns
• Calendar Exceptions
• Public/Private Tasks
• Cut/Copy/Paste
Task List
35
Gantt
• Activity Bars
• Task Bars
• Inherited Colors
• Horizontal Scrolling
Task List
36
View Options
• Bulk Complete
• Saved Views
• List/Gantt
• Planning Window
• Group/Sort
• Search
• Smart Quick Filters
Task List
37
View Options
• 6 weeks planning
• Saved Views
• Hand off Window
• Group By Act, Comp
• Search
• Smart Quick Filters
Hand offs
38
Task Editing
39
Edit in tables
or task forms
40
Mobile: Work Management
Oracle Primavera
Cloud Mobile
• Introduction
Work Management > Tasks
2. View Due, Pending, Flagged
and Completed Tasks.
2
3
1 1. View & Create project Tasks
or private tasks on the fly.
3. Recommit the tasks with
right reasons.
41
Work Plan on iPad
42
Performance Mgmt
Introduction
43
Monitor Performance
Monitor Planned Percent Complete (PPC) & Reasons for missed
commitments per Lean Construction Institute’s best practices
44
PPC - Project
PPC - Company Reasons
Oracle Primavera Cloud Tasks in Schedule
Introduction
45
Grid & Gantt
• P6 Schedule data via
- P6/Prime Sync, or
- Gateway
• Task Status Indicator:
• - Incompatible Dates
- Incompatible Status
Schedule
46
47
Integrate With P6
2 Options
1. Automatic
2. On Demand
48
Auto Sync
49
On Demand
MOBILE DEMO
50
51
Agenda
Industry Challenges
Our Solution
Solution Presentation
Value & Benefits
Q&A
1
2
3
4
52
5
Coordination
Reduce the need for larger,
complex master schedules
which were never intended
to micro-manage the level
of detail required for field
execution teams. Placing
the right coordination tool
in the hands of the right
stakeholder eliminates
costly re-work, drives
accountability and reduces
risk.
Commitment
53
Community
The benefits of our solution
Coordination
Reduce the need for larger,
complex master schedules
which were never intended
to micro-manage the level
of detail required for field
execution teams. Placing
the right coordination tool
in the hands of the right
stakeholder eliminates
costly re-work, drives
accountability and reduces
risk.
Commitment
Blending CPM and Lean
methods drives
performance right down to
the workface based on
commitments of field
disciplines. Flexible Task
sequences focus on short
interval timelines that
inform the master schedule
activity network, giving a
comprehensive view of
overall performance.
54
Community
The benefits of our solution
Coordination
Reduce the need for larger,
complex master schedules
which were never intended
to micro-manage the level
of detail required for field
execution teams. Placing
the right coordination tool
in the hands of the right
stakeholder eliminates
costly re-work, drives
accountability and reduces
risk.
Commitment
Blending CPM and Lean
methods drives
performance right down to
the workface based on
commitments of field
disciplines. Flexible Task
sequences focus on short
interval timelines that
inform the master schedule
activity network, giving a
comprehensive view of
overall performance.
55
Community
Aligning stakeholder
incentives with shared
knowledge and common
goals creates a unique and
differentiated offering in
the market where the best
of CPM and Lean means
and methods are truly
blended to drive
community engagement
and successful business
outcomes.
The benefits of our solution
56
Questions?
57
Homeworks
ENR | Oracle Webinar - How Lean & Critical Path Methods Enhance One Another
ENR | Oracle Webinar - Blending Lean & CPM: Going to the Next Level
Lean Construction Institute - Getting Started with Lean

More Related Content

What's hot

Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jIIT delhi
 
Project cost management a simplified approach ppt - Oracle Primavera Collab...
Project cost management   a simplified approach ppt - Oracle Primavera Collab...Project cost management   a simplified approach ppt - Oracle Primavera Collab...
Project cost management a simplified approach ppt - Oracle Primavera Collab...p6academy
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptxZiyad Zaidi
 
Construction scheduling
Construction schedulingConstruction scheduling
Construction schedulingZTE Nepal
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown StructureNicola2903
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationMubashir Ali
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14p6academy
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceM. Tuna
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear projectThanh Hoang Lam
 

What's hot (20)

Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
Project cost management a simplified approach ppt - Oracle Primavera Collab...
Project cost management   a simplified approach ppt - Oracle Primavera Collab...Project cost management   a simplified approach ppt - Oracle Primavera Collab...
Project cost management a simplified approach ppt - Oracle Primavera Collab...
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptx
 
Construction scheduling
Construction schedulingConstruction scheduling
Construction scheduling
 
Advanced Work Packaging
Advanced Work Packaging Advanced Work Packaging
Advanced Work Packaging
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENTPROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
Pmp basics you need to know
Pmp basics you need to knowPmp basics you need to know
Pmp basics you need to know
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with Confidence
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear project
 

Similar to Lean planning with Oracle Primavera Cloud

Better release planning for Feature Teams
Better release planning for Feature TeamsBetter release planning for Feature Teams
Better release planning for Feature TeamsAmit Singh
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
PM Training Slides
PM Training SlidesPM Training Slides
PM Training SlidesAhmed303
 
Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)love7love
 
Project Management: Choosing the Right Tools and Approach
Project Management: Choosing the Right Tools and ApproachProject Management: Choosing the Right Tools and Approach
Project Management: Choosing the Right Tools and ApproachPeter Campbell
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleAnnsstand
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptxBahredinAbdella1
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMPAndy Pham, PMP
 
Work plan and Scope creep
Work plan and Scope creepWork plan and Scope creep
Work plan and Scope creepOnkar Tendulkar
 
04. Project planning and management.pptx
04. Project planning and management.pptx04. Project planning and management.pptx
04. Project planning and management.pptxALI2H
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
1. into. to project and project management (1)
1. into. to project and project management (1)1. into. to project and project management (1)
1. into. to project and project management (1)tehreem fatima
 
Agile Business Rhythm
Agile Business RhythmAgile Business Rhythm
Agile Business RhythmGlen Alleman
 

Similar to Lean planning with Oracle Primavera Cloud (20)

Better release planning for Feature Teams
Better release planning for Feature TeamsBetter release planning for Feature Teams
Better release planning for Feature Teams
 
Project
Project Project
Project
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
PM Training Slides
PM Training SlidesPM Training Slides
PM Training Slides
 
Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)
 
Project Management: Choosing the Right Tools and Approach
Project Management: Choosing the Right Tools and ApproachProject Management: Choosing the Right Tools and Approach
Project Management: Choosing the Right Tools and Approach
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMP
 
Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
Work plan and Scope creep
Work plan and Scope creepWork plan and Scope creep
Work plan and Scope creep
 
04. Project planning and management.pptx
04. Project planning and management.pptx04. Project planning and management.pptx
04. Project planning and management.pptx
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
1. into. to project and project management (1)
1. into. to project and project management (1)1. into. to project and project management (1)
1. into. to project and project management (1)
 
Project management.pptx
Project management.pptxProject management.pptx
Project management.pptx
 
Agile Business Rhythm
Agile Business RhythmAgile Business Rhythm
Agile Business Rhythm
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 

Recently uploaded

RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-IVigneshvaranMech
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...Amil baba
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
AI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfAI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfmahaffeycheryld
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxwendy cai
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdfKamal Acharya
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectRased Khan
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptxfaamieahmd
 

Recently uploaded (20)

RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
AI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfAI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptx
 

Lean planning with Oracle Primavera Cloud

  • 1. Oracle Primavera Cloud Lean Scheduling Nihat YILDIRIM nihat@prmyazilim.com
  • 2. Agenda Industry Challenges Our Solution Solution Presentation Value & Benefits Q&A 1 2 3 4 2 5
  • 3. Problem • Ten times the number of activities today compared to 25 years ago • Correctly managing the additional activities and relationships requires technical expertise, discipline, and time • Commercial construction can not afford full-time project schedulers • Resequencing activities is tedious, laborious, and costly • Never intended to micro-manage a project • Intended to manage the big picture Critical Path Method Schedules… 3
  • 4. Impact • Large schedules do not effectively communicate the plan • Incorrectly managing schedule can be risky from a legal perspective • Construction productivity has decreased • Projects taking longer Critical Path Method Schedules… 4
  • 5. Coordination Engineering & Construction projects are continually challenged with coordination complexities. How to assemble Owners, Contractors, Subcontractors, Suppliers and Specialty Service Firms around shared knowledge and common goals to create an environment of mutual benefit. Commitment 5 Community Top challenges
  • 6. Coordination Engineering & Construction projects are continually challenged with coordination complexities. How to assemble Owners, Contractors, Subcontractors, Suppliers and Specialty Service Firms around shared knowledge and common goals to create an environment of mutual benefit. Commitment Scheduling discipline has always worked to reflect the closest image of reality it could, with logical ties between activities. Yet even the best well laid plans can fail to capture the commitments that must be made between field disciplines at the physical workface. 6 Community Top challenges
  • 7. Coordination Engineering & Construction projects are continually challenged with coordination complexities. How to assemble Owners, Contractors, Subcontractors, Suppliers and Specialty Service Firms around shared knowledge and common goals to create an environment of mutual benefit. Commitment Scheduling discipline has always worked to reflect the closest image of reality it could, with logical ties between activities. Yet even the best well laid plans can fail to capture the commitments that must be made between field disciplines at the physical workface. 7 Community Engineering & Construction projects will always have multiple stakeholders and this makes the industry historically litigious to operate in. Building a sense of community around what is to be built can be difficult given the agendas, legal ramifications and potential monetary losses that accompany project failure. Top challenges
  • 8. İş programı detay seviyeleri Özet Detay Yöneticiler Saha
  • 9. İş programı detay seviyeleri Level-1 (Mastır program) projenin süresini ve çıktılarını kabaca gösteren detay seviyesi en az özet iş programıdır. İhale, yatırım onayı vb amaçlar için kullanılır. Feasibility, design, procurement, construction, installation, commissioning gibi seviyeleri içerir. Level-2 (Özet program)her iş paketinin teslimatını net olarak gösterir ve Level-1 programa göre daha detaylıdır ancak özet iş program sayılır. Sözleşme öncesi veya hemen sonrası hazırlanır. Level-3 (Detay program)koordinasyon iş programıdır ve Level-2 programın detaylandırılması ile ortaya çıkar. Kritik yol analizinin uygulanmasına elverişli bir detayı içermelidir ve disiplinlerin/iş paketlerinin arayüzünü/etkileşimlerini göstermelidir. Yapım öncesi hazırlanır ve sunulur. Level-4 (Yapım programı) çok detaylı, kaynak ve ekiplere atanabilecek aktivitelerden oluşur ve ilerleme takibinin bazını oluşturur. Sorgulanabilir adam-saat veya ağırlık girilen aktivitelerden oluşur ve verim konusunda fikir verir. İlerlemeler sonrası kısa vadeli look-ahead raporlamalar yapmaya elverişlidir. Level-5 (Kısa vadeli program) saha sorumlularının ve formenlerin işlerini takip etmek için hazırladıkları 1-2 haftalık geçici programlardır.
  • 10. Agenda Industry Challenges Our Solution Solution Presentation Value & Benefits Q&A 1 2 3 4 10 5
  • 11. Our Solution • Schedule Module – Manage the big picture, CPM schedule network – Use Activities for rigid, physically dependent sequences – Reduce activities, relationships, and effort to correctly maintain them • Lean Module (Work Plan & Task List) – Manage the short interval, weekly work plan – Use Tasks for coordinated, flexible sequences – Engage the project team in defining & sequencing Tasks to support Activities – Utilize Lean Construction Institute methodologies (PPC, Reasons, Pull-Planning) Oracle Primavera Cloud Schedule, Work Plan & Tasks
  • 12. • Non-profit founded in 1997 • Intention is to find a better way to schedule • Vision to increase satisfaction with design & construction delivery • Includes local communities in different countries 12 Lean Construction Institute
  • 13. 13 How it is done now?
  • 15. Confidential – Oracle Digital Planning Board Touch Screen Enabled!
  • 16. Integrated CPM & Lean Scheduling Process 16 Define Phases with WBS Monitor Performance LastPlanners® breakdown Activities into smaller Tasks Define Activities, Durations, Relationships LastPlanners® Commit to Due Dates, Complete Tasks
  • 17. Lean Scheduling Concepts • Planning Period: In lean scheduling, a meeting facilitator leads a group of project collaborators (superintendents, subcontractors, tradespeople, and other stakeholders) from various companies in adding tasks to a planning board. These meetings may occur daily or weekly and are focused on the work to be performed over a short-term period, typically the current week and the following week. • Tasks:Tasks are identified during planning as the physical work to be performed by the tradespeople on the project. Each task has a name, duration, and associated company responsible for performing the work on the task. There are two task types: Task and Task Milestone. 17
  • 18. Lean Scheduling Concepts • Commitments:Commitments are optional submitted agreements to assume responsibility for the work to be performed on a public task. The assigned company and user commit to perform the work by a specific date. If the commitment due date is not met, then the task is overdue. • Hand-offs:A hand-off is a connection between two tasks that indicates the sequence in which the task work should be performed. Work is "handed off" to the next task to be performed after its preceding task has been completed. 18
  • 19. Lean Scheduling Concepts • Push Planning: In traditional or push planning, work is planned in sequence from the start of a project or task milestone. Planners "push" work through the sequence according to an established schedule. • Pull Planning: In pull planning, the sequence of work is determined by responsible parties planning backward from a task milestone or goal. Performers request or "pull" work from their dependencies based on demand for subsequent work to begin and after all prerequisite tasks have been completed. 19
  • 20. Work Breakdown Structure Create the “Big Picture” schedule by organizing project into manageable phases using the WBS (Work Breakdown Structure) Easily model the project schedule. The WBS defines project phases and creates a framework that effectively represents the overall plan.  Simple to Create  Leverage Templates  Indent/Outdent  Cut/Copy/Paste  Grid or Gantt 20
  • 21. Activities, Durations, Relationships Create logical relationships between Activities in the CPM network Traditional CPM scheduling defines activities, durations and relationships. This determines the critical path, project duration, and project completion date.  Add Activities  Define Durations  Sequence Activities using Relationships  Connect Activities between WBS elements to reflect transitions between phases  Calculate the schedule 21
  • 22. LastPlanners® Breakdown Activities LastPlanners® breakdown Activities, identify Tasks durations, sequences & due dates in facilitated production meetings LastPlanners® breakdown Activities into smaller Tasks, collaboratively plan their due dates, and commit to complete them as planned.  The Hopper - Unplanned Tasks - Activity Optional - Collapse/Expand  Tasks get durations, sequences, and due dates 22
  • 25. Process 25 Create Task Plan Task (Set Due Date) Commit Finish Date Recommit (When missed the committed date) Complete Task
  • 26. LastPlanners® Commit & Complete The LastPlanners® commit to Due Dates on the Planning Board, complete when done, and re-commit if not completed The planning board is where field disciplines commit to Task due dates. Each field discipline has a different Task color assignment on the Planning Board.  Digital Planning Board vs. Trailer Wall  Planned Tasks  Committed Tasks  Completed Tasks  Overdue Tasks  Reference Activities  Collapse/Expand 26
  • 27. Monitor Performance Monitor Planned Percent Complete (PPC) & Reasons for missed commitments per Lean Construction Institute’s best practices With the field executing, it’s now about capturing completions. If commitments are missed, reason codes are assigned, and new commitments are made. Tasks alert the CPM network for incompatible dates or status.  Project PPC  Company PPC (Inherited Colors)  Reasons for Missed Commitments  One Time Frame, All Charts 27
  • 28. Agenda Industry Challenges Our Solution Solution Presentation Value & Benefits Q&A 1 2 3 4 28 5
  • 29. Oracle Primavera Cloud Work Plan Introduction 29
  • 30. Hopper • Unplanned Tasks • Group/Ungroup • Activity Optional • Collapse/Expand Work Plan 30
  • 31. Planning Board • Smart Board • Planned Tasks • Committed Tasks • Completed Tasks • Overdue Tasks • Reference Activities • Collapse/Expand Work Plan 31
  • 32. Buckets • Navigation • Future Planning Periods Work Plan 32
  • 33. View Options • Saved Views • Planning Window • Smart Quick Filters • Group by Activity • Navigation • Search Work Plan 33
  • 34. Oracle Primavera Cloud Task List Introduction 34
  • 35. Grid • Discussions • Flags • Configurable Columns • Calendar Exceptions • Public/Private Tasks • Cut/Copy/Paste Task List 35
  • 36. Gantt • Activity Bars • Task Bars • Inherited Colors • Horizontal Scrolling Task List 36
  • 37. View Options • Bulk Complete • Saved Views • List/Gantt • Planning Window • Group/Sort • Search • Smart Quick Filters Task List 37
  • 38. View Options • 6 weeks planning • Saved Views • Hand off Window • Group By Act, Comp • Search • Smart Quick Filters Hand offs 38
  • 39. Task Editing 39 Edit in tables or task forms
  • 40. 40 Mobile: Work Management Oracle Primavera Cloud Mobile • Introduction
  • 41. Work Management > Tasks 2. View Due, Pending, Flagged and Completed Tasks. 2 3 1 1. View & Create project Tasks or private tasks on the fly. 3. Recommit the tasks with right reasons. 41
  • 42. Work Plan on iPad 42
  • 44. Monitor Performance Monitor Planned Percent Complete (PPC) & Reasons for missed commitments per Lean Construction Institute’s best practices 44 PPC - Project PPC - Company Reasons
  • 45. Oracle Primavera Cloud Tasks in Schedule Introduction 45
  • 46. Grid & Gantt • P6 Schedule data via - P6/Prime Sync, or - Gateway • Task Status Indicator: • - Incompatible Dates - Incompatible Status Schedule 46
  • 47. 47 Integrate With P6 2 Options 1. Automatic 2. On Demand
  • 51. 51
  • 52. Agenda Industry Challenges Our Solution Solution Presentation Value & Benefits Q&A 1 2 3 4 52 5
  • 53. Coordination Reduce the need for larger, complex master schedules which were never intended to micro-manage the level of detail required for field execution teams. Placing the right coordination tool in the hands of the right stakeholder eliminates costly re-work, drives accountability and reduces risk. Commitment 53 Community The benefits of our solution
  • 54. Coordination Reduce the need for larger, complex master schedules which were never intended to micro-manage the level of detail required for field execution teams. Placing the right coordination tool in the hands of the right stakeholder eliminates costly re-work, drives accountability and reduces risk. Commitment Blending CPM and Lean methods drives performance right down to the workface based on commitments of field disciplines. Flexible Task sequences focus on short interval timelines that inform the master schedule activity network, giving a comprehensive view of overall performance. 54 Community The benefits of our solution
  • 55. Coordination Reduce the need for larger, complex master schedules which were never intended to micro-manage the level of detail required for field execution teams. Placing the right coordination tool in the hands of the right stakeholder eliminates costly re-work, drives accountability and reduces risk. Commitment Blending CPM and Lean methods drives performance right down to the workface based on commitments of field disciplines. Flexible Task sequences focus on short interval timelines that inform the master schedule activity network, giving a comprehensive view of overall performance. 55 Community Aligning stakeholder incentives with shared knowledge and common goals creates a unique and differentiated offering in the market where the best of CPM and Lean means and methods are truly blended to drive community engagement and successful business outcomes. The benefits of our solution
  • 57. 57 Homeworks ENR | Oracle Webinar - How Lean & Critical Path Methods Enhance One Another ENR | Oracle Webinar - Blending Lean & CPM: Going to the Next Level Lean Construction Institute - Getting Started with Lean

Editor's Notes

  1. The solution here in Oracle Primavera Cloud is with Schedule and Tasks working together Distinction between activities and tasks In P6 Often these were used interchangeably (client vs mobile) In Prime there is a clear distinction In Prime Schedule we have activities with the usual logic (SS, FS etc) and CPM Tasks have no logic Tasks are for flexible sequencing where the project team determine how things will be done Note the picture in the background where this is being done. Pre-populated post it notes for the work in hand are laid out and agreement made between all parties
  2. Not our idea!
  3. Here are a couple of photographs of Lean Scheduling in action on a job site. This is a daily exercise carried out each morning before work begins that day. Here we can see a Planning Board with a bunch of coloured post it notes Across the top are days when work will be performed There is a leader, usually the superintendent, who is trying to coordinate all the work All the post it notes are created by what are called ‘The Last Planners’ typically the Foremen who are responsible for the work and know the details of what needs doing. Each of the Foremen writes his tasks on a post it adds it to the board – note the different colours represent the different foreman/contractors. Then as a team they interactively work on sequencing those things within the workplan. They then take simple metrics to track the progress: How many things did you agree to do How many things did you get done That is the fundamental metric of Lean Scheduling: Planned Percent Complete (Did/Said I’d Do)
  4. Here are a couple of photographs of Lean Scheduling in action on a job site. This is a daily exercise carried out each morning before work begins that day. Here we can see a Planning Board with a bunch of coloured post it notes Across the top are days when work will be performed There is a leader, usually the superintendent, who is trying to coordinate all the work All the post it notes are created by what are called ‘The Last Planners’ typically the Foremen who are responsible for the work and know the details of what needs doing. Each of the Foremen writes his tasks on a post it adds it to the board – note the different colours represent the different foreman/contractors. Then as a team they interactively work on sequencing those things within the workplan. They then take simple metrics to track the progress: How many things did you agree to do How many things did you get done That is the fundamental metric of Lean Scheduling: Planned Percent Complete (Did/Said I’d Do)
  5. Users can manage the work and assign tasks to the users who then can progress via mobile interface. Ability to add project level or personal tasks. Users can see their company’s assigned tasks, complete or recommit them.
  6. With the field executing, it’s now about capturing completions. If commitments are missed, reason codes are assigned, and new commitments are made. Tasks alert the CPM network for incompatible dates or status. Project PPC Company PPC (Inherited Colors) Reasons for Missed Commitments One Time Frame, All Charts
  7. Organization with P6 EPPM deployment would like to take advantage of additional features that Prime Cloud Service can offer with a seamless integration. Database level sync up between Prime and P6 to import project and schedule related data. Near-real time data synchronization. Flexibility to synchronize between multiple P6 instances into single Prime instance. Option to support both cloud and on premise deployment of P6 EPPM.
  8. Organization with P6 EPPM deployment would like to take advantage of additional features that Prime Cloud Service can offer with a seamless integration. Database level sync up between Prime and P6 to import project and schedule related data. Near-real time data synchronization. Flexibility to synchronize between multiple P6 instances into single Prime instance. Option to support both cloud and on premise deployment of P6 EPPM.