Layout/Grade Specialist Duties
GPS Level/Philadelphia Rod
1. Layout stations and property lines with
spray paint
2. Use a line to show pipe layers/ trench
excavator where pipe will be going and
approximate elevation of bottom of gravel
3. Locate sidewalk and edge of pavement
4. Use locator to make gas lines and other
services
5. Locate MH and catch basin locations and
mark it out
6. Find road grade Left EP, Crown, Right EP
(sub base, Gran B, top of road).
7. Setting of fire hydrants.
1. Check sub grade, B grade etc
2. Check top of pipe to ensure pipe is on
proper grade
3. Use to set man hole and catch basins
4. When checking road grade, give operator
an indication with spray paint the
approximate elevation required.
 Keep daily progress recorded and have inspector sign off on daily basis if possible.
 Record any rock excavation or tree stump removal for each day
 Record services (City & Private) for each address under which date it was done. Need
pipe type and pipe size for all services for the address. Approximate locations (station)
recorded.
 Record Manhole and Catch basin information and approximate locations after being set
 Record length of mainlines from centre of one manhole to the next. Type of pipe and size
of pipe need to be recorded as well.
 Ensure construction site is walk able for pedestrians.
 Ensure temporary sidewalk is set.
 No garbage is left in trenches.
Finding HI:
Use known benchmark (can get this from drawings or Owner), set up equipment and take shot to find
back sight. To get Height of Instrument = Benchmark + Backsight (Need to find this every time
instrument is set up and moved.
*Need this for daily elevation calculations and checks.
Distance from MH:
Use GPS to find the distance from middle of manhole to current location or use stationing to find length
for top of pipe calculations.
Top of Pipe Readings:
*Try to do at every station (within 10 metres apart generally).
Calculate what elevation should be before using level and rod to find what it is at. Have your station
“zero” information handy at all times. This is the information from the reference man hole. Need exact
station, top of pipe and length from location to manhole.
Station “Zero” – Man Hole #1 Location
 Top of pipe – 3.674
 STN 3+684.1
 L=19.52 m
 Invert of pipe: 0.41m
EX. HI 98.746 Grade of Pipe 0.98%  0.0098
STN LENGTH GRADE TP (THEO) TP(ACTUAL) ELEV. INVERT
ELEV.
0
3+684.1 0.0098 3.674 95.072 94.662
3+703.62 19.52 0.0098 3.482 *TAKE
SHOT*
95.264 95.674
Theoretical Top of Pipe = (TP Actual @ STN Zero) – (Length * Grade)
*Take shot with rod and level to see if close to grade*
*Find elevations from actual top of pipe reading*
Finding Grade for Roadway:
Proposed Elevation - HI– depth down in road (from drawing)
*dependent on drawing elevations*
Used to find Granular “B” and sub base elevations
Left EP: ____________
Crown: _____________ @ STN ________
Right EP: ____________
*Do for even stations*
Catch basins
Left: Top of Grade (elevation), Bottom of bed (# on rod), Bottom of Gravel (# on rod)
Right: Top of Grade (elevation), Bottom of bed (# on rod), Bottom of Gravel (# on rod)
Manhole Information: (Typical for payment and Owner)
Sump = 0.221
MH ex = 95.084
TR = 95.359
Cut 0.275
1.24 m3 Root
STM MH #4598
*Get catch basin and man hole information from manufacture label on them.
 Bottom of bed elev.
 Bottom of gravel elev.
 Find elev. Based on local and measurements to find bottom of bed, add approx. 15 cm to bottom
of gravel.

More Related Content

What's hot

Algortimos del area y volumen de figuras plana
Algortimos del area y volumen de figuras planaAlgortimos del area y volumen de figuras plana
Algortimos del area y volumen de figuras plana
RamiroDelahoz1
 
Setting out of Tunnel
Setting out of TunnelSetting out of Tunnel
Setting out of Tunnel
SachinGunjal7
 
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALCRail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Institution of Lighting Professionals
 
Bezier curve computer graphics
Bezier curve computer graphics Bezier curve computer graphics
Bezier curve computer graphics
University of Potsdam
 
True angle between lines and planes
True angle between lines and planesTrue angle between lines and planes
True angle between lines and planes
Sinokia Lee
 
Earth work
Earth workEarth work
Earth work
Atiqa khan
 
Earthwork notes
Earthwork notesEarthwork notes
Earthwork notes
Adilen Del
 
Geom 5point5
Geom 5point5Geom 5point5
Geom 5point5
herbison
 
Internal loadings
Internal loadingsInternal loadings
Internal loadings
KingJyeWong
 
Lecture 04 angle corrections
Lecture 04 angle correctionsLecture 04 angle corrections
Lecture 04 angle corrections
Rehan Hanif
 

What's hot (10)

Algortimos del area y volumen de figuras plana
Algortimos del area y volumen de figuras planaAlgortimos del area y volumen de figuras plana
Algortimos del area y volumen de figuras plana
 
Setting out of Tunnel
Setting out of TunnelSetting out of Tunnel
Setting out of Tunnel
 
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALCRail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALC
 
Bezier curve computer graphics
Bezier curve computer graphics Bezier curve computer graphics
Bezier curve computer graphics
 
True angle between lines and planes
True angle between lines and planesTrue angle between lines and planes
True angle between lines and planes
 
Earth work
Earth workEarth work
Earth work
 
Earthwork notes
Earthwork notesEarthwork notes
Earthwork notes
 
Geom 5point5
Geom 5point5Geom 5point5
Geom 5point5
 
Internal loadings
Internal loadingsInternal loadings
Internal loadings
 
Lecture 04 angle corrections
Lecture 04 angle correctionsLecture 04 angle corrections
Lecture 04 angle corrections
 

Similar to Layout and Grade task sheet

Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
brett_grocock
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveys
Est
 
levelling and contouring
levelling and contouringlevelling and contouring
levelling and contouring
ANAND JIBHKATE
 
lecture_1a.ppt
lecture_1a.pptlecture_1a.ppt
lecture_1a.ppt
ArisamTom
 
ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE
ROAD  PROFILING, CROSS SECTION & SETTING OUT SEWER LINEROAD  PROFILING, CROSS SECTION & SETTING OUT SEWER LINE
ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE
KiplimoCalvin
 
Profile and Cross-Section - Report
Profile and Cross-Section - ReportProfile and Cross-Section - Report
Profile and Cross-Section - Report
Sarchia Khursheed
 
sunil.pptx
sunil.pptxsunil.pptx
sunil.pptx
ShravanKumar124460
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
Luke D'Arcy
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
Luke D'Arcy
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
Luke D'Arcy
 
Unit 1
Unit 1Unit 1
Abijit sharma 201818510 survey report
Abijit sharma 201818510 survey reportAbijit sharma 201818510 survey report
Abijit sharma 201818510 survey report
SingayWangchuk2
 
Survey camp report main (2nd) Part
Survey camp report main (2nd) PartSurvey camp report main (2nd) Part
Survey camp report main (2nd) Part
BishnuBhandari12
 
Unit 5
Unit 5Unit 5
Chain Surveying 2020.ppt
 Chain Surveying 2020.ppt Chain Surveying 2020.ppt
Chain Surveying 2020.ppt
AsadKhan606012
 
handbook of civil engineering
handbook of civil engineeringhandbook of civil engineering
handbook of civil engineering
Ashok Narisetti
 
Location survey for the Rural and urban areas
Location survey for the Rural and urban areasLocation survey for the Rural and urban areas
Location survey for the Rural and urban areas
Rana Ibrahim
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
ANAND JIBHKATE
 
surveying Work methodology
surveying Work methodologysurveying Work methodology
surveying Work methodology
simon mhando
 
ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)
Jing Chuang
 

Similar to Layout and Grade task sheet (20)

Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveys
 
levelling and contouring
levelling and contouringlevelling and contouring
levelling and contouring
 
lecture_1a.ppt
lecture_1a.pptlecture_1a.ppt
lecture_1a.ppt
 
ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE
ROAD  PROFILING, CROSS SECTION & SETTING OUT SEWER LINEROAD  PROFILING, CROSS SECTION & SETTING OUT SEWER LINE
ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE
 
Profile and Cross-Section - Report
Profile and Cross-Section - ReportProfile and Cross-Section - Report
Profile and Cross-Section - Report
 
sunil.pptx
sunil.pptxsunil.pptx
sunil.pptx
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Unit 1
Unit 1Unit 1
Unit 1
 
Abijit sharma 201818510 survey report
Abijit sharma 201818510 survey reportAbijit sharma 201818510 survey report
Abijit sharma 201818510 survey report
 
Survey camp report main (2nd) Part
Survey camp report main (2nd) PartSurvey camp report main (2nd) Part
Survey camp report main (2nd) Part
 
Unit 5
Unit 5Unit 5
Unit 5
 
Chain Surveying 2020.ppt
 Chain Surveying 2020.ppt Chain Surveying 2020.ppt
Chain Surveying 2020.ppt
 
handbook of civil engineering
handbook of civil engineeringhandbook of civil engineering
handbook of civil engineering
 
Location survey for the Rural and urban areas
Location survey for the Rural and urban areasLocation survey for the Rural and urban areas
Location survey for the Rural and urban areas
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
 
surveying Work methodology
surveying Work methodologysurveying Work methodology
surveying Work methodology
 
ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)
 

Layout and Grade task sheet

  • 1. Layout/Grade Specialist Duties GPS Level/Philadelphia Rod 1. Layout stations and property lines with spray paint 2. Use a line to show pipe layers/ trench excavator where pipe will be going and approximate elevation of bottom of gravel 3. Locate sidewalk and edge of pavement 4. Use locator to make gas lines and other services 5. Locate MH and catch basin locations and mark it out 6. Find road grade Left EP, Crown, Right EP (sub base, Gran B, top of road). 7. Setting of fire hydrants. 1. Check sub grade, B grade etc 2. Check top of pipe to ensure pipe is on proper grade 3. Use to set man hole and catch basins 4. When checking road grade, give operator an indication with spray paint the approximate elevation required.  Keep daily progress recorded and have inspector sign off on daily basis if possible.  Record any rock excavation or tree stump removal for each day  Record services (City & Private) for each address under which date it was done. Need pipe type and pipe size for all services for the address. Approximate locations (station) recorded.  Record Manhole and Catch basin information and approximate locations after being set  Record length of mainlines from centre of one manhole to the next. Type of pipe and size of pipe need to be recorded as well.  Ensure construction site is walk able for pedestrians.  Ensure temporary sidewalk is set.  No garbage is left in trenches. Finding HI: Use known benchmark (can get this from drawings or Owner), set up equipment and take shot to find back sight. To get Height of Instrument = Benchmark + Backsight (Need to find this every time instrument is set up and moved. *Need this for daily elevation calculations and checks. Distance from MH: Use GPS to find the distance from middle of manhole to current location or use stationing to find length for top of pipe calculations. Top of Pipe Readings: *Try to do at every station (within 10 metres apart generally). Calculate what elevation should be before using level and rod to find what it is at. Have your station “zero” information handy at all times. This is the information from the reference man hole. Need exact station, top of pipe and length from location to manhole.
  • 2. Station “Zero” – Man Hole #1 Location  Top of pipe – 3.674  STN 3+684.1  L=19.52 m  Invert of pipe: 0.41m EX. HI 98.746 Grade of Pipe 0.98%  0.0098 STN LENGTH GRADE TP (THEO) TP(ACTUAL) ELEV. INVERT ELEV. 0 3+684.1 0.0098 3.674 95.072 94.662 3+703.62 19.52 0.0098 3.482 *TAKE SHOT* 95.264 95.674 Theoretical Top of Pipe = (TP Actual @ STN Zero) – (Length * Grade) *Take shot with rod and level to see if close to grade* *Find elevations from actual top of pipe reading* Finding Grade for Roadway: Proposed Elevation - HI– depth down in road (from drawing) *dependent on drawing elevations* Used to find Granular “B” and sub base elevations Left EP: ____________ Crown: _____________ @ STN ________ Right EP: ____________ *Do for even stations* Catch basins Left: Top of Grade (elevation), Bottom of bed (# on rod), Bottom of Gravel (# on rod) Right: Top of Grade (elevation), Bottom of bed (# on rod), Bottom of Gravel (# on rod)
  • 3. Manhole Information: (Typical for payment and Owner) Sump = 0.221 MH ex = 95.084 TR = 95.359 Cut 0.275 1.24 m3 Root STM MH #4598 *Get catch basin and man hole information from manufacture label on them.  Bottom of bed elev.  Bottom of gravel elev.  Find elev. Based on local and measurements to find bottom of bed, add approx. 15 cm to bottom of gravel.