SlideShare a Scribd company logo
1 of 8
WorkMethodology
1.0 Scope of the work
2.0 Definitions
3.0 References
4.0 Tools and equipment
5.0 Safety
6.0 Prioractivities
7.0 Procedure
8.0 Topographical Survey
9.0 Horizontal Control Survey
10.0 The WholeSite Survey, Cross / Longitudinal
survey
11.0 Responsibilities
12.0 Attachment
1.0 Scope of the work
1.1 This method statement details how surveying for the work will be carried out in both
activities involved in this project. Level surveys along the centerlines of the pipes
setting outs points and finally generate longitudinal profile for all length of the pipe.
This work also involves Installation of Benchmarks
2.0 Definitions
2.1 Hj
2.2 Fg
2.3 Ddd
2.4 Erer
3.0 References
3.1 Contract drawings
3.2 Particulars Technical Specifications- Earthworks, Pipe works and ground improvement
4.0 Tools an Equipments
4.1 Total station
4.2 Dump level
4.3 Tripod stand
4.4 Surveying Tape
4.5 Measuring Tape
4.6 Alidade
4.7 Surveyor's chain
4.8 Surveying Rods
4.9 Surveying Poles
4.10 Hubs & Nails
4.11 Pegs
4.12 Hummer
4.13 Axe
4.14 Elevating Tripods
4.15 Surveying Tripods
4.16 Marking Paint
4.17 Surveyors Umbrellas
5.0 Safety
1.1 General Technical Specifications
1.2 Construction health and safety Plan
1.3 dddd
1.4 Hazards Identified
a) The hazards to working in the environment are to be set out in the risk
assessment, these are briefly (but not limited to):
 Underfoot Conditions: Slip/Trip Hazards;
 Moving Vehicles/Machinery.
 Overhead Services.
 Stockpiles.
 Open Water Bodies Adjacent to site.
 Vegetation.
 Public Vehicles.
b) PPE such as safety helmet, safety harness, safety Boots, goggles will be always
provided. Staff will take necessary precautions and utilize them when potential
hazards are identified.
c) An emergency telephone list will be provided for the Team Leader, to make
sure that the Contractor, Police Department and any emergency service provider
can be contacted should the need arise.
6.0 Prior Activities
6.1 Calibration and Testing of Survey Equipment; Prior to commencement of survey
works, the Surveyor shall ensure that all survey equipment such as Total Stations and
Automatic Levels deployed in the project are within the calibration period or duly
registered.
6.2 Automatic Levels shall undergo peg tests every two weeks to ensure that readings are
within allowable errors. Peg test records shall be compiled by the Chief surveyor.
The Chief Surveyor shall ensure that all survey equipment will be recalibrated on or
before the expiration of calibration certificates.
6.3 Reconnaissance; Together with the Engineer, the survey group shall schedule a joint
inspection or reconnaissance for familiarization of the project site and to check if the
survey control points are still undisturbed. All disturbed control points shall be recorded
and reported accordingly.
6.4 Coordination Meeting of Survey Teams; The Surveyor shall conduct daily coordination
meeting (preferably before or after the daily toolbox meeting) to orient the survey teams
on their assignments/work area to eliminate confusion and double handling of work
items when the field survey has commenced.
7.0 Procedure
7.1 Elevation of Benchmarks; Elevation of benchmarks will be decided by direct leveling
survey. A leveling route for measuring benchmarks will be selected in such a way that
the route starts from existing benchmark, and return either to the original benchmark or
another existing benchmark in the area
a) Observation; Two way observations by level using a pair of staff will be carried
out. Lengths of foresights and back sights will be kept very nearly equal. As a
rule, the length will be not exceeding 70 m.
Reading of observation values will be made in millimeters.
b) Limits In Observation Value; Limits in observation value in leveling will be as
follows:
Error of two way observation 20 mm or less for each 1 km.
Error of closure 15 S mm or less
Where S is one way distance in kilometer.
c) When the error of closure falls within the specified limits, it will be distributed
equally over the survey points in proportion to the distance between survey
points.
d) When the error of closure has exceeded the specified limits investigate the causes
thereof and carry out re surveying.
7.2 Construction of Station and Benchmarks;
a) The stations and benchmarks will be carefully constructed after approved by the
Engineer.
b) The Stations and benchmarks will be provided with adequate protective fences to
preserve them during construction terms.
c) The stations and benchmarks will be clearly marked with item number, elevation
and / or coordinate
7.3 Control Point Survey; Control point survey will be carried out to produce fixed
coordinates of each control point referred to the reference point subjected by the
Engineer.
8.0 TOPOGRAPHICAL SURVEY
The survey group shall ensure that a topographic survey shall be done before the start of
earthwork activities
8.1 Topographical survey will be include of horizontal control survey, vertical control survey
and survey the whole site using cross section in every 10 meters.
8.2 Topographical map will show horizontal detail and elevation of the ground.
1.0 Horizontal Control Survey
1.1 Sufficient number of control benchmarks for detail will be installed.
1.2 Location of the control benchmarks will be decided by site reconnaissance
1.3 All coordinates of control benchmarks will be decided according to the existing
benchmark by means or traverse survey.
1.4 Accuracy of coordinate of existing benchmark will be confirmed by traverse survey.
2.0 Vertical Control Survey
2.1 Sufficient number of temporary benchmarks will be installed for the whole site survey of
areas.
2.2 All elevation of the temporary benchmarks will be decided according to the existing
benchmark by means of direct leveling survey.
3.0 The Whole Site Survey, Cross / Longitudinal survey
(1) Horizontal and vertical detail of areas will be surveyed based on the control benchmarks.
(2) Cross section will be surveyed by direct levelling at 25 m interval.
(3) Total Station or Combination of T-2 Theodolite and EDM will be used to collect data of
cross section.
(4) Beginning Point (BP), Intersection Point (IP) and Ending Point (EP) will be set out of
each cross section line from the nearby control point.
(5) Wooden peg or concrete marker will be established for each marking BP, IP and EP.
(6) Traversing and levelling work will be carried out to preserve coordinates and elevation of
BP, IP and EP referred to existing BM.
(7) The measuring intervals of cross section will be 5 to 10 m and all remarkable changes of
topography will be measured.
(8) All fields will be carefully recorded for further processing.
Establishment of Horizontal and Vertical Controls
All survey works shall be reference to the existing survey control points within the project site.
In cases where additional control points are needed, traverse and leveling surveys shall be done.
The surveyor shall ensure that errors accumulated within the surveys are within the allowable
tolerances as stated in the DENR Administrative Order 2007 – 29 or the Revised Regulations on
Land Surveys (Article 7 Section 28.b Project Primary Control).
Survey control monuments shall have a standard dimension of L20cmxW20cmxH50cm with 30-
40cm embedded on the ground. In cases of hard ground, monuments shall be cement putty type
with standard dimension of L20cmxW20cm.
Topographic Survey
The survey group shall ensure that a topographic survey shall be done before the start of
earthwork activities.
All visible features will be measured using ground measurement points for every feature that
needs to be shot. These points will be spread throughout the project area in sufficient number to
fully cover all features and the entire ground, and to ensure accurate computation of the contour
lines and elevations. Also, the gathered data shall be the basis for the earthworks (cut and fill)
computations.
All man-made structures such as buildings, roads, culverts, drainages, bridges, walkways, etc.,
within the project, site will also be measured in order to get their ground footprint. All other
elements on the ground, such as plantations, trees (with a minimum diameter), rivers, streams,
etc. will also be included the measurements.
Road Layout
Horizontal road layouts shall be done at 10 meter interval (straight) and 5 meter interval (curves).
Toe and embankment limit shall also be marked at the same interval.
Survey stakes shall be in the form of woods or rebars (preferably 10mm diameter). Elevations
shall be marked with the use of masking tapes to determine the required elevations.
Excavations
Excavations shall be initially marked in the ground using wood stakes. Batter boards shall also
be placed (1 to 2 meters offset) if needed to serve as permanent guides for the excavation team.
Benching at required slope ratio shall be done.
Methodology and execution Plan of Topographical Survey
Posted on July 27, 2012 by robbysatria
This Methodology and execution Plan of Topographical Survey, covers the following works
(1) Installation of Benchmarks
(2) Topographical survey at with scale 1 : 500 and grid every 10 m interval.
(4) Topographical surveys for Pipeline route, with scale 1 : 500 and grid every 100 m interval.
Installation of Benchmark
The purposed of Benchmark establishment is intended to be used as a permanent point over the
field, that point
in future particularly during the construction stage can be used as reference point within stake
out stage.
The Benchmark will be installed on the stable area, easily identified and reachable. Shape and
size of
benchmark are planned to have dimensions or 30 cm x 30 cm x 120 cm for temporary Bench
Mark, and shall
founded on piles or shall based on geotechnical calculation.
.

More Related Content

What's hot

Leveling final-report
Leveling final-reportLeveling final-report
Leveling final-reportFelix Vong
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveyingMujeeb Muji
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - TraversingXinYee Khoo
 
Input of Surveying in Civil Engineering.pdf
Input of Surveying in Civil Engineering.pdfInput of Surveying in Civil Engineering.pdf
Input of Surveying in Civil Engineering.pdfMANISHKUMAR863071
 
Site surveying-Leveling
Site surveying-LevelingSite surveying-Leveling
Site surveying-LevelingShane Ah
 
SITE SURVEYING LEVELING
SITE SURVEYING LEVELINGSITE SURVEYING LEVELING
SITE SURVEYING LEVELINGFarah Sham
 
Total Station Topographic Survey
Total Station Topographic Survey Total Station Topographic Survey
Total Station Topographic Survey haroldtaylor1113
 
Introduction to Setting Out a Building
Introduction to Setting Out a BuildingIntroduction to Setting Out a Building
Introduction to Setting Out a BuildingSteve Jarvis
 
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptxSaddoAjmal
 
Site surveying-report-2
Site surveying-report-2Site surveying-report-2
Site surveying-report-2Shane Ah
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levellingYASMINE HASLAN
 
Setting Out Works in Surveying
Setting Out Works in SurveyingSetting Out Works in Surveying
Setting Out Works in SurveyingATUL DONGRE
 
Site surveying report i
Site surveying   report iSite surveying   report i
Site surveying report i마 이환
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Haziq1511
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01Rajesh Rajguru
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingDolat Ram
 
LAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiuiLAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiuicivilengineerf14
 

What's hot (20)

Leveling final-report
Leveling final-reportLeveling final-report
Leveling final-report
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveying
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
 
Input of Surveying in Civil Engineering.pdf
Input of Surveying in Civil Engineering.pdfInput of Surveying in Civil Engineering.pdf
Input of Surveying in Civil Engineering.pdf
 
Setting out work
Setting out workSetting out work
Setting out work
 
Bridge survey
Bridge surveyBridge survey
Bridge survey
 
Site surveying-Leveling
Site surveying-LevelingSite surveying-Leveling
Site surveying-Leveling
 
SITE SURVEYING LEVELING
SITE SURVEYING LEVELINGSITE SURVEYING LEVELING
SITE SURVEYING LEVELING
 
Total Station Topographic Survey
Total Station Topographic Survey Total Station Topographic Survey
Total Station Topographic Survey
 
Introduction to Setting Out a Building
Introduction to Setting Out a BuildingIntroduction to Setting Out a Building
Introduction to Setting Out a Building
 
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptx
 
Levelling
LevellingLevelling
Levelling
 
Site surveying-report-2
Site surveying-report-2Site surveying-report-2
Site surveying-report-2
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levelling
 
Setting Out Works in Surveying
Setting Out Works in SurveyingSetting Out Works in Surveying
Setting Out Works in Surveying
 
Site surveying report i
Site surveying   report iSite surveying   report i
Site surveying report i
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 
LAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiuiLAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiui
 

Similar to surveying Work methodology

Canal Surveying.pdf
Canal Surveying.pdfCanal Surveying.pdf
Canal Surveying.pdfBivaYadav3
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.pptMuhammed Sulfeek
 
samseer husain CV 15-4-2015
samseer husain CV  15-4-2015samseer husain CV  15-4-2015
samseer husain CV 15-4-2015Samseer Husain
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfNkosiAnsari
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveysbrett_grocock
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Sunilkumar Mandal
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveyingstooty s
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-iiMarvin Ken
 
Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.Prudhvi Thota
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportJoshua Yu
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
S2 1 introduction of basic surveying
S2 1 introduction of basic surveyingS2 1 introduction of basic surveying
S2 1 introduction of basic surveyingEst
 
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfAPTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfssuser1fc1f0
 

Similar to surveying Work methodology (20)

Unit 5
Unit 5Unit 5
Unit 5
 
Canal Surveying.pdf
Canal Surveying.pdfCanal Surveying.pdf
Canal Surveying.pdf
 
Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
 
samseer husain CV 15-4-2015
samseer husain CV  15-4-2015samseer husain CV  15-4-2015
samseer husain CV 15-4-2015
 
Control Surveying.ppt
Control Surveying.pptControl Surveying.ppt
Control Surveying.ppt
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdf
 
Basics of surveying
Basics of surveyingBasics of surveying
Basics of surveying
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-ii
 
Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering Report
 
Unit 1
Unit 1Unit 1
Unit 1
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
S2 1 introduction of basic surveying
S2 1 introduction of basic surveyingS2 1 introduction of basic surveying
S2 1 introduction of basic surveying
 
361
361361
361
 
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfAPTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
 
G03-Topografia-de-Obras.pdf
G03-Topografia-de-Obras.pdfG03-Topografia-de-Obras.pdf
G03-Topografia-de-Obras.pdf
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

surveying Work methodology

  • 1. WorkMethodology 1.0 Scope of the work 2.0 Definitions 3.0 References 4.0 Tools and equipment 5.0 Safety 6.0 Prioractivities 7.0 Procedure 8.0 Topographical Survey 9.0 Horizontal Control Survey 10.0 The WholeSite Survey, Cross / Longitudinal survey 11.0 Responsibilities 12.0 Attachment
  • 2. 1.0 Scope of the work 1.1 This method statement details how surveying for the work will be carried out in both activities involved in this project. Level surveys along the centerlines of the pipes setting outs points and finally generate longitudinal profile for all length of the pipe. This work also involves Installation of Benchmarks 2.0 Definitions 2.1 Hj 2.2 Fg 2.3 Ddd 2.4 Erer 3.0 References 3.1 Contract drawings 3.2 Particulars Technical Specifications- Earthworks, Pipe works and ground improvement 4.0 Tools an Equipments 4.1 Total station 4.2 Dump level 4.3 Tripod stand 4.4 Surveying Tape 4.5 Measuring Tape 4.6 Alidade 4.7 Surveyor's chain 4.8 Surveying Rods 4.9 Surveying Poles 4.10 Hubs & Nails 4.11 Pegs 4.12 Hummer 4.13 Axe 4.14 Elevating Tripods 4.15 Surveying Tripods 4.16 Marking Paint 4.17 Surveyors Umbrellas
  • 3. 5.0 Safety 1.1 General Technical Specifications 1.2 Construction health and safety Plan 1.3 dddd 1.4 Hazards Identified a) The hazards to working in the environment are to be set out in the risk assessment, these are briefly (but not limited to):  Underfoot Conditions: Slip/Trip Hazards;  Moving Vehicles/Machinery.  Overhead Services.  Stockpiles.  Open Water Bodies Adjacent to site.  Vegetation.  Public Vehicles. b) PPE such as safety helmet, safety harness, safety Boots, goggles will be always provided. Staff will take necessary precautions and utilize them when potential hazards are identified. c) An emergency telephone list will be provided for the Team Leader, to make sure that the Contractor, Police Department and any emergency service provider can be contacted should the need arise. 6.0 Prior Activities 6.1 Calibration and Testing of Survey Equipment; Prior to commencement of survey works, the Surveyor shall ensure that all survey equipment such as Total Stations and Automatic Levels deployed in the project are within the calibration period or duly registered. 6.2 Automatic Levels shall undergo peg tests every two weeks to ensure that readings are within allowable errors. Peg test records shall be compiled by the Chief surveyor.
  • 4. The Chief Surveyor shall ensure that all survey equipment will be recalibrated on or before the expiration of calibration certificates. 6.3 Reconnaissance; Together with the Engineer, the survey group shall schedule a joint inspection or reconnaissance for familiarization of the project site and to check if the survey control points are still undisturbed. All disturbed control points shall be recorded and reported accordingly. 6.4 Coordination Meeting of Survey Teams; The Surveyor shall conduct daily coordination meeting (preferably before or after the daily toolbox meeting) to orient the survey teams on their assignments/work area to eliminate confusion and double handling of work items when the field survey has commenced. 7.0 Procedure 7.1 Elevation of Benchmarks; Elevation of benchmarks will be decided by direct leveling survey. A leveling route for measuring benchmarks will be selected in such a way that the route starts from existing benchmark, and return either to the original benchmark or another existing benchmark in the area a) Observation; Two way observations by level using a pair of staff will be carried out. Lengths of foresights and back sights will be kept very nearly equal. As a rule, the length will be not exceeding 70 m. Reading of observation values will be made in millimeters. b) Limits In Observation Value; Limits in observation value in leveling will be as follows: Error of two way observation 20 mm or less for each 1 km. Error of closure 15 S mm or less Where S is one way distance in kilometer. c) When the error of closure falls within the specified limits, it will be distributed equally over the survey points in proportion to the distance between survey points. d) When the error of closure has exceeded the specified limits investigate the causes thereof and carry out re surveying. 7.2 Construction of Station and Benchmarks;
  • 5. a) The stations and benchmarks will be carefully constructed after approved by the Engineer. b) The Stations and benchmarks will be provided with adequate protective fences to preserve them during construction terms. c) The stations and benchmarks will be clearly marked with item number, elevation and / or coordinate 7.3 Control Point Survey; Control point survey will be carried out to produce fixed coordinates of each control point referred to the reference point subjected by the Engineer. 8.0 TOPOGRAPHICAL SURVEY The survey group shall ensure that a topographic survey shall be done before the start of earthwork activities 8.1 Topographical survey will be include of horizontal control survey, vertical control survey and survey the whole site using cross section in every 10 meters. 8.2 Topographical map will show horizontal detail and elevation of the ground. 1.0 Horizontal Control Survey 1.1 Sufficient number of control benchmarks for detail will be installed. 1.2 Location of the control benchmarks will be decided by site reconnaissance 1.3 All coordinates of control benchmarks will be decided according to the existing benchmark by means or traverse survey. 1.4 Accuracy of coordinate of existing benchmark will be confirmed by traverse survey. 2.0 Vertical Control Survey 2.1 Sufficient number of temporary benchmarks will be installed for the whole site survey of areas. 2.2 All elevation of the temporary benchmarks will be decided according to the existing benchmark by means of direct leveling survey. 3.0 The Whole Site Survey, Cross / Longitudinal survey (1) Horizontal and vertical detail of areas will be surveyed based on the control benchmarks. (2) Cross section will be surveyed by direct levelling at 25 m interval. (3) Total Station or Combination of T-2 Theodolite and EDM will be used to collect data of cross section.
  • 6. (4) Beginning Point (BP), Intersection Point (IP) and Ending Point (EP) will be set out of each cross section line from the nearby control point. (5) Wooden peg or concrete marker will be established for each marking BP, IP and EP. (6) Traversing and levelling work will be carried out to preserve coordinates and elevation of BP, IP and EP referred to existing BM. (7) The measuring intervals of cross section will be 5 to 10 m and all remarkable changes of topography will be measured. (8) All fields will be carefully recorded for further processing.
  • 7. Establishment of Horizontal and Vertical Controls All survey works shall be reference to the existing survey control points within the project site. In cases where additional control points are needed, traverse and leveling surveys shall be done. The surveyor shall ensure that errors accumulated within the surveys are within the allowable tolerances as stated in the DENR Administrative Order 2007 – 29 or the Revised Regulations on Land Surveys (Article 7 Section 28.b Project Primary Control). Survey control monuments shall have a standard dimension of L20cmxW20cmxH50cm with 30- 40cm embedded on the ground. In cases of hard ground, monuments shall be cement putty type with standard dimension of L20cmxW20cm. Topographic Survey The survey group shall ensure that a topographic survey shall be done before the start of earthwork activities. All visible features will be measured using ground measurement points for every feature that needs to be shot. These points will be spread throughout the project area in sufficient number to fully cover all features and the entire ground, and to ensure accurate computation of the contour lines and elevations. Also, the gathered data shall be the basis for the earthworks (cut and fill) computations. All man-made structures such as buildings, roads, culverts, drainages, bridges, walkways, etc., within the project, site will also be measured in order to get their ground footprint. All other elements on the ground, such as plantations, trees (with a minimum diameter), rivers, streams, etc. will also be included the measurements. Road Layout Horizontal road layouts shall be done at 10 meter interval (straight) and 5 meter interval (curves). Toe and embankment limit shall also be marked at the same interval. Survey stakes shall be in the form of woods or rebars (preferably 10mm diameter). Elevations shall be marked with the use of masking tapes to determine the required elevations. Excavations Excavations shall be initially marked in the ground using wood stakes. Batter boards shall also
  • 8. be placed (1 to 2 meters offset) if needed to serve as permanent guides for the excavation team. Benching at required slope ratio shall be done. Methodology and execution Plan of Topographical Survey Posted on July 27, 2012 by robbysatria This Methodology and execution Plan of Topographical Survey, covers the following works (1) Installation of Benchmarks (2) Topographical survey at with scale 1 : 500 and grid every 10 m interval. (4) Topographical surveys for Pipeline route, with scale 1 : 500 and grid every 100 m interval. Installation of Benchmark The purposed of Benchmark establishment is intended to be used as a permanent point over the field, that point in future particularly during the construction stage can be used as reference point within stake out stage. The Benchmark will be installed on the stable area, easily identified and reachable. Shape and size of benchmark are planned to have dimensions or 30 cm x 30 cm x 120 cm for temporary Bench Mark, and shall founded on piles or shall based on geotechnical calculation. .