INTERNAL ATTACHMENT
Group 4
Fieldwork 4 Report
ROAD PROFILING, CROSS SECTION & SETTING OUT
SEWER LINE
Student Name Registration Nº
Gavin Kendo ENC221-0330/2016
Stildon Kimani ENC222-0337/2016
Tarri Halakhe ENC221-0159/2016
Calvin Kiplimo ENC222-0168/2016
Ivy Njeri ENC221-0157/2016
Raymond Rawlings ENC222-0362/2016
Sharon Mwanza ENC221-0098/2016
Barasa Samuel ENC222-0351/2016
Faith Mwende ENC221-0311/2016
Kosgei Antoney ENC222-0354/2016
Paul Akelo ENC222-0331/2016
Group 4 ǀ Fieldwork 4
2
Introduction
In profile leveling, you determine the elevations of a series of
points lengthwise along a road. Profile are plotted such that the
vertical scale is exaggerated in relation to the horizontal scale so
that the difference in the elevation are accentuated. The line along
which the profile is to be taken may be marked prior to the survey.
This is normally done in 100-foot stations. A rod reading is taken at
each full station and at each major break in the ground slope. This
procedure differs from the running of a circuit level in that more
foresights are taken from each set-up. The stations of the breaks in
slope are taped and referenced from the full stations established
along the profile line
In cross-section leveling, you determine the elevations of
points on a succession of lines running at right angles to the
lengthwise line of the highway. Cross sections are necessary for
measurement of earthwork volumes in roadway construction. They
are profile views of the ground, perpendicular to the centerline or
base line, and indicate ground elevations at points of change in the
ground slope. Original cross sections indicate the profile of the
original ground before the ground is disturbed. These
measurements may be used for primary design, estimating
volumes, etc. Borrow pit original cross sections are taken after
stripping has occurred.
Cross sectioning is a method of leveling to know the nature of
ground on either side of the centerline of the proposed route and
leveling is carried out along this cross section. During location and
construction of highways, Rail tracks sewers and canals mark are
placed at various aligned points.
Cross sections are the sections run at right angles to the
centerline and on the either side of it they are taken at each 5,10m
station on the centerline. The length of cross section depends upon
the nature of the work.
Manhole is a small covered opening in a paved area allowing
access beneath, especially one leading to a sewer.
Drainage set-out surveys generally provide the set-out
required for the designed horizontal and vertical alignment of a road
Group 4 ǀ Fieldwork 4
3
or drain. Survey can consist of a peg or mark placed indicating an
offset and level at incremental distances along the designed
alignment. This information will determine the required cut/fill
required, to meet the design criteria. Both road and drainage set-out
generally will require as-built surveys to be carried out. This
information can be used to calculate how close the road has been
built to design, and if it meets the design tolerances and standards.
Volumes of material used and required can also be determined from
these surveys and are useful in accounting for materials used and
also forecast what cut or fill volumes remains.
Objectives:
 To determine the elevations of the ground surface.
 To set out sewer line and Manholes.
 Carry out accurate setting out.
 Carry out all the necessary calculations to establish
the setting-out points.
 Work as a team in order to execute a large-scale
surveying work.
 Produce and present an engineering report on an
engineering survey work.
 To find elevation of longitudinal and transverse
stations for making profile and cross sections.
Instruments to be used:
1. Level.
2. Staff.
3. Tripod.
4. Measuring Tape.
5. Ranging Rod.
Group 4 ǀ Fieldwork 4
4
Fig1.0 Area of work
Procedure
1. Fix the stations for the centerline 20m each from 0+00 to
0+400 by measuring tape.
2. Then for each station mark 5R, 10R, 5L and 10L
perpendicular to the longitudinal line.
3. Instrument level is setup at convenient positions near bench
mark.
4. First sight of B.M (point of known elevation) is taken and
reading is entered in back Sight column.
5. If distance is large instrument is shifted, the instrument
becomes turning point (or) changing point.
6. After setting up instrument at new position,
performing temporary adjustment and Take back sight as
turning point.
7. Thus, turning point will have both back sight and fore sight
readings.
8. Take readings for near stations and enter the readings in
intermediate column.
9. Then take another turning point and shift to new location for
other stations.
Group 4 ǀ Fieldwork 4
5
10. Lock the leveling operation by returning to the first point
(BM).
11. Readings are entered in a tabular form given below and
Reduced levels are calculated by height of instrument method.
Sources of Error
 They are staff readings and tilt of the pole or staff. Observer
tends to make wrong observation when observing the staff
reading, they might misread the staff marking scales and this
brought to the crucial error along the booking process.
Besides, the tilting of the staff rod can influence the accuracy
of the height readings taken from the staff. When the staff is
not truly vertical (90º) or almost to it, the reading taken is
incorrect and lead to the failure of tachometry process.
 Errors in conducting tachometry survey also caused by
natural causes. These include errors due to high winds.
During high winds, it is difficult to keep the staff vertical and
read it accurately. Works should be undertaken during hot
mid-day period. In very hot conditions, the instrument should
be protected with an umbrella to avoid errors due to the
unequal expansion of different parts of instruments. Work
may also be hampered by bad visibility due to strong sunlight
and glare.
 Error due to manipulation and sighting are inaccurate leveling
of the instrument, inaccurate reading of horizontal line and
vertical angles, poor focusing errors, inaccurate bisection of
the target, inaccurate reading of the staff intercept and lastly
due to errors in holding the staff.
 Instrumental errors. They are those caused by the adjustment
of the instruments used or faults in them. Any errors in these
measurements have serious implications in the heights and
distances measured with the instruments. To avoid such
errors, the following points should be taken care of:
Group 4 ǀ Fieldwork 4
6
a) The level should be in perfect adjustment for taking
observation.
b) The altitude bubble should be at the centre of its run
while reading the vertical circle for angles. Any index
error should be detected and eliminated or accounted for.
c) The multiplying and additive constants of the instrument
should be periodically checked to see that they indeed
have the values that are being used.
d) The stadia rod (staff) should be accurately divided into
parts. The graduations should be uniform and free of
errors. They should be marked bold for greater visibility
from a large distance.
Conclusion
In this experiment we worked in field and we obtained desired
data. From the profile run, we know the center-line elevation at
each station. And we take cross-section elevations at (0+20 m) for
center line and both sides of the center line.
On the plot of the profile we note that the road line is slope, it
decreases when we move from left to right.
From the field sheet we see the cross-section of the road and
we note that the center line is higher than both sides (right and
left).

More Related Content

What's hot

tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveyingMujeeb Muji
 
LAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiuiLAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiuicivilengineerf14
 
Total Station Topographic Survey
Total Station Topographic Survey Total Station Topographic Survey
Total Station Topographic Survey haroldtaylor1113
 
Electronic distance measurement (EDM)
Electronic distance measurement (EDM)Electronic distance measurement (EDM)
Electronic distance measurement (EDM)Bathla Tuition Centre
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in SurveyingRAHUL SINHA
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveyingPhurba Tamang
 
Tacheometric survey
Tacheometric surveyTacheometric survey
Tacheometric surveyStudent
 
Setting out of curve (Survey)
Setting out of curve (Survey)Setting out of curve (Survey)
Setting out of curve (Survey)Bhavik Patel
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-iiMarvin Ken
 
Surveying by using Digital Theodolite
Surveying by using Digital TheodoliteSurveying by using Digital Theodolite
Surveying by using Digital TheodoliteEhab AL-Timimi
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying neharajpl
 
Theodolite angle measurement
Theodolite angle measurementTheodolite angle measurement
Theodolite angle measurementMujeeb Muji
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying Krish Bhavsar
 

What's hot (20)

Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveying
 
LAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiuiLAB MANUAL contouring by indirect method . dce: fet: iiui
LAB MANUAL contouring by indirect method . dce: fet: iiui
 
Unit 4
Unit 4Unit 4
Unit 4
 
Total Station Topographic Survey
Total Station Topographic Survey Total Station Topographic Survey
Total Station Topographic Survey
 
Electronic distance measurement (EDM)
Electronic distance measurement (EDM)Electronic distance measurement (EDM)
Electronic distance measurement (EDM)
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveying
 
Triangulation
Triangulation Triangulation
Triangulation
 
Tacheometric survey
Tacheometric surveyTacheometric survey
Tacheometric survey
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
 
Setting out of curve (Survey)
Setting out of curve (Survey)Setting out of curve (Survey)
Setting out of curve (Survey)
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-ii
 
Trigonometric levelling
Trigonometric levellingTrigonometric levelling
Trigonometric levelling
 
Surveying by using Digital Theodolite
Surveying by using Digital TheodoliteSurveying by using Digital Theodolite
Surveying by using Digital Theodolite
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying
 
Theodolite angle measurement
Theodolite angle measurementTheodolite angle measurement
Theodolite angle measurement
 
Construction surveys
Construction surveysConstruction surveys
Construction surveys
 
Two Peg Test - Report
Two Peg Test - ReportTwo Peg Test - Report
Two Peg Test - Report
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying
 

Similar to ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE

Tacheometry @surveyingreport
Tacheometry @surveyingreportTacheometry @surveyingreport
Tacheometry @surveyingreportKiplimoCalvin
 
Traverse @surveyingreport
Traverse @surveyingreportTraverse @surveyingreport
Traverse @surveyingreportKiplimoCalvin
 
Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Enoch Wong
 
Ss report 2
Ss report 2Ss report 2
Ss report 2Shen Sin
 
Sem 2 Site surveying report 2
Sem 2 Site surveying report 2Sem 2 Site surveying report 2
Sem 2 Site surveying report 2Est
 
ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)Jing Chuang
 
Site Surveying Traversing
Site Surveying TraversingSite Surveying Traversing
Site Surveying Traversingashleyyeap
 
Tacheometry survey of detailing
Tacheometry survey of detailingTacheometry survey of detailing
Tacheometry survey of detailingSuman Jyoti
 
Abijit sharma 201818510 survey report
Abijit sharma 201818510 survey reportAbijit sharma 201818510 survey report
Abijit sharma 201818510 survey reportSingayWangchuk2
 
Fpt 3163 water_science_chapter_4_level_survey
Fpt 3163 water_science_chapter_4_level_surveyFpt 3163 water_science_chapter_4_level_survey
Fpt 3163 water_science_chapter_4_level_surveyRione Drevale
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2Doreen Yeo
 
Profile and Cross-Section - Report
Profile and Cross-Section - ReportProfile and Cross-Section - Report
Profile and Cross-Section - ReportSarchia Khursheed
 
Site surveying assignment
Site surveying assignmentSite surveying assignment
Site surveying assignmentSze Ting Kuek
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfNkosiAnsari
 

Similar to ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE (20)

Tacheometry @surveyingreport
Tacheometry @surveyingreportTacheometry @surveyingreport
Tacheometry @surveyingreport
 
Traverse @surveyingreport
Traverse @surveyingreportTraverse @surveyingreport
Traverse @surveyingreport
 
Traversing
TraversingTraversing
Traversing
 
Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)
 
Ss report 2
Ss report 2Ss report 2
Ss report 2
 
Sem 2 Site surveying report 2
Sem 2 Site surveying report 2Sem 2 Site surveying report 2
Sem 2 Site surveying report 2
 
ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)ABC Report - 123 (gathered with reference)
ABC Report - 123 (gathered with reference)
 
Site Surveying Traversing
Site Surveying TraversingSite Surveying Traversing
Site Surveying Traversing
 
Tacheometry survey of detailing
Tacheometry survey of detailingTacheometry survey of detailing
Tacheometry survey of detailing
 
Unit 5
Unit 5Unit 5
Unit 5
 
Leveling report
Leveling reportLeveling report
Leveling report
 
Abijit sharma 201818510 survey report
Abijit sharma 201818510 survey reportAbijit sharma 201818510 survey report
Abijit sharma 201818510 survey report
 
ASU MP.docx
ASU MP.docxASU MP.docx
ASU MP.docx
 
Fpt 3163 water_science_chapter_4_level_survey
Fpt 3163 water_science_chapter_4_level_surveyFpt 3163 water_science_chapter_4_level_survey
Fpt 3163 water_science_chapter_4_level_survey
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2
 
Profile and Cross-Section - Report
Profile and Cross-Section - ReportProfile and Cross-Section - Report
Profile and Cross-Section - Report
 
Site surveying assignment
Site surveying assignmentSite surveying assignment
Site surveying assignment
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdf
 
Fw2
Fw2Fw2
Fw2
 
Plane table survey
Plane table survey Plane table survey
Plane table survey
 

Recently uploaded

Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 

Recently uploaded (20)

Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 

ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE

  • 1. JJOOMMOO KKEENNYYAATTTTAA UUNNIIVVEERRSSIITTYY OOFF AAGGRRIICCUULLTTUURREE AANNDD TTEECCHHNNOOLLOOGGYY Setting Trends in Higher Education, Research and Innovation School of Civil Engineering and Geospatial Engineering Bachelor of Geomatics Engineering and Geospatial Systems Bachelor of Geospatial Information Science INTERNAL ATTACHMENT Group 4 Fieldwork 4 Report ROAD PROFILING, CROSS SECTION & SETTING OUT SEWER LINE Student Name Registration Nº Gavin Kendo ENC221-0330/2016 Stildon Kimani ENC222-0337/2016 Tarri Halakhe ENC221-0159/2016 Calvin Kiplimo ENC222-0168/2016 Ivy Njeri ENC221-0157/2016 Raymond Rawlings ENC222-0362/2016 Sharon Mwanza ENC221-0098/2016 Barasa Samuel ENC222-0351/2016 Faith Mwende ENC221-0311/2016 Kosgei Antoney ENC222-0354/2016 Paul Akelo ENC222-0331/2016
  • 2. Group 4 ǀ Fieldwork 4 2 Introduction In profile leveling, you determine the elevations of a series of points lengthwise along a road. Profile are plotted such that the vertical scale is exaggerated in relation to the horizontal scale so that the difference in the elevation are accentuated. The line along which the profile is to be taken may be marked prior to the survey. This is normally done in 100-foot stations. A rod reading is taken at each full station and at each major break in the ground slope. This procedure differs from the running of a circuit level in that more foresights are taken from each set-up. The stations of the breaks in slope are taped and referenced from the full stations established along the profile line In cross-section leveling, you determine the elevations of points on a succession of lines running at right angles to the lengthwise line of the highway. Cross sections are necessary for measurement of earthwork volumes in roadway construction. They are profile views of the ground, perpendicular to the centerline or base line, and indicate ground elevations at points of change in the ground slope. Original cross sections indicate the profile of the original ground before the ground is disturbed. These measurements may be used for primary design, estimating volumes, etc. Borrow pit original cross sections are taken after stripping has occurred. Cross sectioning is a method of leveling to know the nature of ground on either side of the centerline of the proposed route and leveling is carried out along this cross section. During location and construction of highways, Rail tracks sewers and canals mark are placed at various aligned points. Cross sections are the sections run at right angles to the centerline and on the either side of it they are taken at each 5,10m station on the centerline. The length of cross section depends upon the nature of the work. Manhole is a small covered opening in a paved area allowing access beneath, especially one leading to a sewer. Drainage set-out surveys generally provide the set-out required for the designed horizontal and vertical alignment of a road
  • 3. Group 4 ǀ Fieldwork 4 3 or drain. Survey can consist of a peg or mark placed indicating an offset and level at incremental distances along the designed alignment. This information will determine the required cut/fill required, to meet the design criteria. Both road and drainage set-out generally will require as-built surveys to be carried out. This information can be used to calculate how close the road has been built to design, and if it meets the design tolerances and standards. Volumes of material used and required can also be determined from these surveys and are useful in accounting for materials used and also forecast what cut or fill volumes remains. Objectives:  To determine the elevations of the ground surface.  To set out sewer line and Manholes.  Carry out accurate setting out.  Carry out all the necessary calculations to establish the setting-out points.  Work as a team in order to execute a large-scale surveying work.  Produce and present an engineering report on an engineering survey work.  To find elevation of longitudinal and transverse stations for making profile and cross sections. Instruments to be used: 1. Level. 2. Staff. 3. Tripod. 4. Measuring Tape. 5. Ranging Rod.
  • 4. Group 4 ǀ Fieldwork 4 4 Fig1.0 Area of work Procedure 1. Fix the stations for the centerline 20m each from 0+00 to 0+400 by measuring tape. 2. Then for each station mark 5R, 10R, 5L and 10L perpendicular to the longitudinal line. 3. Instrument level is setup at convenient positions near bench mark. 4. First sight of B.M (point of known elevation) is taken and reading is entered in back Sight column. 5. If distance is large instrument is shifted, the instrument becomes turning point (or) changing point. 6. After setting up instrument at new position, performing temporary adjustment and Take back sight as turning point. 7. Thus, turning point will have both back sight and fore sight readings. 8. Take readings for near stations and enter the readings in intermediate column. 9. Then take another turning point and shift to new location for other stations.
  • 5. Group 4 ǀ Fieldwork 4 5 10. Lock the leveling operation by returning to the first point (BM). 11. Readings are entered in a tabular form given below and Reduced levels are calculated by height of instrument method. Sources of Error  They are staff readings and tilt of the pole or staff. Observer tends to make wrong observation when observing the staff reading, they might misread the staff marking scales and this brought to the crucial error along the booking process. Besides, the tilting of the staff rod can influence the accuracy of the height readings taken from the staff. When the staff is not truly vertical (90º) or almost to it, the reading taken is incorrect and lead to the failure of tachometry process.  Errors in conducting tachometry survey also caused by natural causes. These include errors due to high winds. During high winds, it is difficult to keep the staff vertical and read it accurately. Works should be undertaken during hot mid-day period. In very hot conditions, the instrument should be protected with an umbrella to avoid errors due to the unequal expansion of different parts of instruments. Work may also be hampered by bad visibility due to strong sunlight and glare.  Error due to manipulation and sighting are inaccurate leveling of the instrument, inaccurate reading of horizontal line and vertical angles, poor focusing errors, inaccurate bisection of the target, inaccurate reading of the staff intercept and lastly due to errors in holding the staff.  Instrumental errors. They are those caused by the adjustment of the instruments used or faults in them. Any errors in these measurements have serious implications in the heights and distances measured with the instruments. To avoid such errors, the following points should be taken care of:
  • 6. Group 4 ǀ Fieldwork 4 6 a) The level should be in perfect adjustment for taking observation. b) The altitude bubble should be at the centre of its run while reading the vertical circle for angles. Any index error should be detected and eliminated or accounted for. c) The multiplying and additive constants of the instrument should be periodically checked to see that they indeed have the values that are being used. d) The stadia rod (staff) should be accurately divided into parts. The graduations should be uniform and free of errors. They should be marked bold for greater visibility from a large distance. Conclusion In this experiment we worked in field and we obtained desired data. From the profile run, we know the center-line elevation at each station. And we take cross-section elevations at (0+20 m) for center line and both sides of the center line. On the plot of the profile we note that the road line is slope, it decreases when we move from left to right. From the field sheet we see the cross-section of the road and we note that the center line is higher than both sides (right and left).