SlideShare a Scribd company logo
FJELLSPRENGNINGSDAGEN,
BERGMEKANIKKDAGEN, GEOTEKNIKKDAGEN
2012
LARGE TBM PROJECTS IN
SWITZERLAND –
EXPERIENCE AND STATE OF THE ART
Part 2
Johannes Gollegger & Helmut Wannenmacher
Amberg Engineering Ltd., Switzerland
Content
2
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
1. Introduction
3. Risk-based geotechnical design
4. Case study Lago Bianco Hydropower
6. Remaining risks of TBM tunnelling
2. Lessons learned from recent projects
5. Uncertainties in the prediction of penetration rates
Introduction
3
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
 Switzerland 40 years of experience
 Development of TBM
 Improved well established technique
 Lessons learned
 Remaining risks
Content
4
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
1. Introduction
3. Risk-based geotechnical design
4. Case study Lago Bianco Hydropower
6. Remaining risks of TBM tunnelling
2. Lessons learned from recent projects
5. Uncertainties in the prediction of penetration rates
2.1 Vereina Tunnel
2.2 Gotthard Base Tunnel
Vereina Railway Line
5
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Geology of the Vereina Tunnel
 Crystalline rock mass, gneisses and amphibolites
 Foliation is flatly bedded, fissures show narrow spacing
Experience Gained at the Vereina Tunnel
6
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Crown failure some sections excavated by TBM
1st causal factor
 Existing geology, flatly bedded foliation
2nd causal factor
 Thrust force, bracing of TBM against the tunnel wall
→Gripper force can lead to opening of existing fissures
→Opening of fissures in existing geology led to crown failure
Experience Gained at the Vereina Tunnel
7
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
→Increased supporting measures
→Drop down of advance rate
Excavation rates
Content
8
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
1. Introduction
3. Risk-based geotechnical design
4. Case study Lago Bianco Hydropower
6. Remaining risks of TBM tunnelling
2. Lessons learned from recent projects
5. Uncertainties in the prediction of penetration rates
2.1 Vereina Tunnel
2.2 Gotthard Base Tunnel
Experience Gained at the Faido Single-Track Tubes
9
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Damages at Following Excavation of West Tube
Invert heaves behind
cutter head including
heave of invert concrete
Contact between
back-up constructions
and rock support
Experience Gained at the Faido Single-Track Tubes
10
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Stress redistribution process
Development of
arch
subhorizontal
rock foliation
Primary stress
EST-
East
EST-
West
Stress redistribution due
to excavation of West tube
Deformations
of invert and
crown
Stress redistribution due
to excavation East tube
11
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Radial deformation [cm]
0 5 10 15 20 25 30
0.5
0
1
1.5
2
3
2.5
Pressure[MPa]
Ground reaction curve after
excavation of the first tube
Ground reaction curve after
excavation of the second tube
Flexible lining
Stiff lining
Failure of rock support
Residual resistance
Failure of rock support
Required rock support
Required rock support
Experience Gained at the Faido Single-Track Tubes
Ground reaction curve
Experience Gained at the Faido Single-Track Tubes
12
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Encountered geological conditions
Experience Gained at the Faido Single-Track Tubes
13
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Crown collapse West tube, blocking of TBM,
first countermeasures
 6 m long weak zone of kakiritic and cataclastic material
> TBM was blocked
 Installation of 4 pipe umbrellas
 Filling of space above cutter head with concrete
 Countermeasures failed
Experience Gained at the Faido Single-Track Tubes
14
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Crown collapse West tube, blocking of TBM,
additional countermeasures
 Gel grouting above TBM in order to protect cutter head
from cement grouting
 Cement grouting in order to stabilize collapsed zone
 Adit from east tube
> TBM freed after
20 weeks
Experience Gained at the Faido Single-Track Tubes
15
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Lessons learned
 Largest possible overcut
 Robust shield and cutter head
 Shield with variable diameter
 Shortest possible shield
 Sufficiently large thrust force
 The capability of installing flexible support
 The capability of installing support simultaneously with tunnel
driving
Content
16
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
1. Introduction
3. Risk-based geotechnical design
4. Case study Lago Bianco Hydropower
6. Remaining risks of TBM tunnelling
2. Lessons learned from recent projects
5. Uncertainties in the prediction of penetration rates
Risk Based Geotechnical Design
17
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
TBM
excavation
resonable
Conventional
excavation
Evaluation of excavation
method
Definition of rock mass behaviour
Relevant geotechnical parameters
Primary stress
conditions
Size, shape, location of structure
Orientation of
ground structure
Ground water
Definition of ground types
no
yes
Risk Based Geotechnical Design
18
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Risks
acceptable
Evaluation of remaining
risks
Choice of TBM concept including
rock support
Behaviour at
shield
Behaviour fulfils the requirements
Behaviour at
back-up
Behaviour at
cutter head
Definition of system behaviour
no
yes
no
yes
Content
19
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
1. Introduction
3. Risk-based geotechnical design
4. Case study Lago Bianco Hydropower
6. Remaining risks of TBM tunnelling
2. Lessons learned from recent projects
5. Uncertainties in the prediction of penetration rates
20
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Lago Bianco Hydropower
Geological, longitudinal profile
2000
3000
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
11000
12000
13000
14000
15000
16000
17000
18000
19000
20000
21000
Lago Bianco
1000
Lago di Poschiavo
2000
3000
Stretta and Bernina
crystalline with Alv zone
Bernina
thrust zone
Musella
granite
Margna
nappe
Malenco
nappe
Margna
nappe
Marinelli
formation
Sella
nappe
Sella
nappe
Musella
granite
© Bild Repower
Source: www.repower.com
Experience gained at the Lago Bianco Hydropower
21
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Homogeneous zone A, chainage 1+090 to 6+820
 Massive to blocky gneisses and shists
 Overburden up to 850 m
 Stable rock mass behaviour
 Potential of gravitational overbreaks
 Inhomogeneous face conditions → higher wear rates
Experience gained at the Lago Bianco Hydropower
22
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Homogeneous zone A, chainage 1+090 to 6+820
 Massive to blocky gneisses and shists
 Overburden up to 850 m
 Stable rock mass behaviour
 Potential of gravitational overbreaks
 Inhomogeneous face conditions → higher wear rates
Experience gained at the Lago Bianco Hydropower
23
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Homogeneous zone B, chainage 6+820 to 7+020
 Overburden approx. 950 m , large deformations, shear failure in crown
 Risk of jamming of TBM
 Shield lubrication, shifting of gauge cutters, grouting
 Local water ingress und limited flowing ground conditions
 Measures: Segmental lining, pipe umbrella, drainage borehole
 Risk acceptable
Experience gained at the Lago Bianco Hydropower
24
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Homogeneous zone B, chainage 6+820 to 7+020
 Overburden approx. 950 m , large deformations, shear failure in crown
 Risk of jamming of TBM
 Shield lubrication, shifting of gauge cutters, grouting
 Local water ingress und limited flowing ground conditions
 Measures: Segmental lining, pipe umbrella, drainage borehole
 Risk acceptable
Experience gained at the Lago Bianco Hydropower
25
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Homogeneous zone C, chainage 14+760 to 16+050
 Non-cohesive fault zone, stress induced shear- failure
 Major water inflow (up to 210l/s) > risk of flowing ground conditions
 High load on TBM shield and on segments > high risk of jamming
 Risk not acceptable
Experience gained at the Lago Bianco Hydropower
26
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Homogeneous zone C, chainage 14+760 to 16+050
 Non-cohesive fault zone, stress induced shear failure
 Major water inflow (up to 210l/s) > risk of flowing ground conditions
 High load on TBM shield and on segments > high risk of jamming
 Risk not acceptable
Experience gained at the Lago Bianco Hydropower
27
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Tunnelling concept
 Double shield TBM
 Trapezoidal segments
 Pea gravel and grouting of annular gap
 Flat cutter head
 Anti-wear plates and wedges
 Equipment for exploration drilling
 Umbrella pipe
 Lubrication of shield
 Pumping devices of up to 250 l/s,
 Possibility of probe drillings
 Segments with higher reinforcement and load capacity, with
drainage tubes
Content
28
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
1. Introduction
3. Risk-based geotechnical design
4. Case study Lago Bianco Hydropower
6. Remaining risks of TBM tunnelling
2. Lessons learned from recent projects
5. Uncertainties in the prediction of penetration rates
Uncertainties in the Prediction of Penetration Rates
29
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Geological and geotechnical influencing factors for penetration
prediction models
Uncertainties in the Prediction of Penetration Rates
30
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Influences on penetration rate
 Clogging of mucking buckets (left)
 Cutter failure due to dynamic loads (right)
Uncertainties in the Prediction of Penetration Rates
31
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Influences on penetration rate
 Unaxial compressive strength
 Normally oriented angle of fabric towards tunnel axis > maximum penetration
 Parallel oriented angle > minimum penetration
 Stress conditions at the tunnel face
 Failure mode
Content
32
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
1. Introduction
3. Risk-based geotechnical design
4. Case study Lago Bianco Hydropower
6. Remaining risks of TBM tunnelling
2. Lessons learned from recent projects
5. Uncertainties in the prediction of penetration rates
Risk Based Geotechnical Design
33
Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012
Remaining uncertainties of TBM tunnelling are related
 To false prediction of system behaviour
>> Ground investigation with a risk based geotechnical
design
>> Action plan with countermeasures
 To false prediction of penetration rate
>> Reliable failure modes for the determination of
the advance rate
A design for the “Worst Case” is certainly technically
desirable, but cannot always be implemented with
economically justifiable means!!!
Thank You Very Much
For Your Attention!

More Related Content

Viewers also liked

MAIN BEARING GREASES AND TAIL SEALANTS
MAIN BEARING GREASES AND TAIL SEALANTSMAIN BEARING GREASES AND TAIL SEALANTS
MAIN BEARING GREASES AND TAIL SEALANTS
FONDAZIONE INT.LE CENTRO STUDI E RICERCHE-ONLUS (NGO)
 
Zemin Araştırması nasıl yapılır?
Zemin Araştırması nasıl yapılır?Zemin Araştırması nasıl yapılır?
Zemin Araştırması nasıl yapılır?
Tolga GÖZÜTOK
 
ŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEME
ŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEMEŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEME
ŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEME
Tolga GÖZÜTOK
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machine
VISHAL KUMAR SINGH
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
Naquiakhter
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
rutuldave
 
Makro süreksizliklerin tbm performansına etkisi
Makro süreksizliklerin tbm performansına etkisiMakro süreksizliklerin tbm performansına etkisi
Makro süreksizliklerin tbm performansına etkisi
aliyuksel2000
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experience
gifanta
 
21 Hidden LinkedIn Hacks Revealed
21 Hidden LinkedIn Hacks Revealed21 Hidden LinkedIn Hacks Revealed
21 Hidden LinkedIn Hacks Revealed
Emma Brudner
 
Top 10 Procurement KPI\'s
Top 10 Procurement KPI\'sTop 10 Procurement KPI\'s
Top 10 Procurement KPI\'samberkar
 

Viewers also liked (10)

MAIN BEARING GREASES AND TAIL SEALANTS
MAIN BEARING GREASES AND TAIL SEALANTSMAIN BEARING GREASES AND TAIL SEALANTS
MAIN BEARING GREASES AND TAIL SEALANTS
 
Zemin Araştırması nasıl yapılır?
Zemin Araştırması nasıl yapılır?Zemin Araştırması nasıl yapılır?
Zemin Araştırması nasıl yapılır?
 
ŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEME
ŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEMEŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEME
ŞEV STABİLİTE ANALİZLERİNDE KULLANILAN YÖNTEMLER VE ANALİZLERE ESAS MODELLEME
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machine
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Makro süreksizliklerin tbm performansına etkisi
Makro süreksizliklerin tbm performansına etkisiMakro süreksizliklerin tbm performansına etkisi
Makro süreksizliklerin tbm performansına etkisi
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experience
 
21 Hidden LinkedIn Hacks Revealed
21 Hidden LinkedIn Hacks Revealed21 Hidden LinkedIn Hacks Revealed
21 Hidden LinkedIn Hacks Revealed
 
Top 10 Procurement KPI\'s
Top 10 Procurement KPI\'sTop 10 Procurement KPI\'s
Top 10 Procurement KPI\'s
 

Similar to LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART

Comacchio Drilling Equipment
Comacchio Drilling EquipmentComacchio Drilling Equipment
Comacchio Drilling Equipment
MECandPMV
 
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Helmut Wannenmacher
 
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
Svenska Betongföreningen
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
BPA-GmbH, Waterproofing is our Passion!
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eJens Classen
 
CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016Tomasz Najder
 
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide showTomasz Najder
 
High Resolution Multibeam Survey and Mobile Laser Scanning
High Resolution Multibeam Survey and Mobile Laser ScanningHigh Resolution Multibeam Survey and Mobile Laser Scanning
High Resolution Multibeam Survey and Mobile Laser Scanning
Havnetekniskgruppe
 
Immersed Tunnels Recent developments
Immersed Tunnels Recent developmentsImmersed Tunnels Recent developments
Immersed Tunnels Recent developments
Statybos Akademija
 
11 jan otcenas
11 jan otcenas11 jan otcenas
11 jan otcenaspvsinbloom
 
17 if g popp teutschenthal v4
17 if g popp teutschenthal v417 if g popp teutschenthal v4
17 if g popp teutschenthal v4
leann_mays
 
Présentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest Québec
Présentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest QuébecPrésentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest Québec
Présentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest Québec
Alain Plaisant
 
PRO INDUSTRY LTD. - portfolio
PRO INDUSTRY LTD. - portfolioPRO INDUSTRY LTD. - portfolio
PRO INDUSTRY LTD. - portfolioLazar Gavric
 
The Gjøa project
The Gjøa projectThe Gjøa project
The Gjøa projectStatoil
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010
Tonyamis
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
AmirShafiq25
 
Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17Tomasz Najder
 

Similar to LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART (20)

Comacchio Drilling Equipment
Comacchio Drilling EquipmentComacchio Drilling Equipment
Comacchio Drilling Equipment
 
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
 
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_e
 
CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016
 
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
 
High Resolution Multibeam Survey and Mobile Laser Scanning
High Resolution Multibeam Survey and Mobile Laser ScanningHigh Resolution Multibeam Survey and Mobile Laser Scanning
High Resolution Multibeam Survey and Mobile Laser Scanning
 
Immersed Tunnels Recent developments
Immersed Tunnels Recent developmentsImmersed Tunnels Recent developments
Immersed Tunnels Recent developments
 
11 jan otcenas
11 jan otcenas11 jan otcenas
11 jan otcenas
 
17 if g popp teutschenthal v4
17 if g popp teutschenthal v417 if g popp teutschenthal v4
17 if g popp teutschenthal v4
 
Présentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest Québec
Présentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest QuébecPrésentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest Québec
Présentation Dr Suzane Lacasse (Directrice Technique NGI) - SCG Ouest Québec
 
PRO INDUSTRY LTD. - portfolio
PRO INDUSTRY LTD. - portfolioPRO INDUSTRY LTD. - portfolio
PRO INDUSTRY LTD. - portfolio
 
Oresund
OresundOresund
Oresund
 
The Gjøa project
The Gjøa projectThe Gjøa project
The Gjøa project
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17
 

More from Helmut Wannenmacher

Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Helmut Wannenmacher
 
Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...
Helmut Wannenmacher
 
Hydro 2016 wannenmacher
Hydro 2016  wannenmacherHydro 2016  wannenmacher
Hydro 2016 wannenmacher
Helmut Wannenmacher
 
Operational analyses of pressure tunnel and shaft grouting operations
Operational analyses of pressure tunnel  and shaft grouting operationsOperational analyses of pressure tunnel  and shaft grouting operations
Operational analyses of pressure tunnel and shaft grouting operations
Helmut Wannenmacher
 
Tum vortragfinal
Tum vortragfinal Tum vortragfinal
Tum vortragfinal
Helmut Wannenmacher
 
Underground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston FormationUnderground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston Formation
Helmut Wannenmacher
 
Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration
Helmut Wannenmacher
 
Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...
Helmut Wannenmacher
 
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Helmut Wannenmacher
 
The Niagara Tunnel Facility Project
The Niagara Tunnel Facility ProjectThe Niagara Tunnel Facility Project
The Niagara Tunnel Facility Project
Helmut Wannenmacher
 

More from Helmut Wannenmacher (10)

Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
 
Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...
 
Hydro 2016 wannenmacher
Hydro 2016  wannenmacherHydro 2016  wannenmacher
Hydro 2016 wannenmacher
 
Operational analyses of pressure tunnel and shaft grouting operations
Operational analyses of pressure tunnel  and shaft grouting operationsOperational analyses of pressure tunnel  and shaft grouting operations
Operational analyses of pressure tunnel and shaft grouting operations
 
Tum vortragfinal
Tum vortragfinal Tum vortragfinal
Tum vortragfinal
 
Underground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston FormationUnderground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston Formation
 
Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration
 
Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...
 
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
 
The Niagara Tunnel Facility Project
The Niagara Tunnel Facility ProjectThe Niagara Tunnel Facility Project
The Niagara Tunnel Facility Project
 

Recently uploaded

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 

Recently uploaded (20)

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 

LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART

  • 1. FJELLSPRENGNINGSDAGEN, BERGMEKANIKKDAGEN, GEOTEKNIKKDAGEN 2012 LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART Part 2 Johannes Gollegger & Helmut Wannenmacher Amberg Engineering Ltd., Switzerland
  • 2. Content 2 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 1. Introduction 3. Risk-based geotechnical design 4. Case study Lago Bianco Hydropower 6. Remaining risks of TBM tunnelling 2. Lessons learned from recent projects 5. Uncertainties in the prediction of penetration rates
  • 3. Introduction 3 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012  Switzerland 40 years of experience  Development of TBM  Improved well established technique  Lessons learned  Remaining risks
  • 4. Content 4 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 1. Introduction 3. Risk-based geotechnical design 4. Case study Lago Bianco Hydropower 6. Remaining risks of TBM tunnelling 2. Lessons learned from recent projects 5. Uncertainties in the prediction of penetration rates 2.1 Vereina Tunnel 2.2 Gotthard Base Tunnel
  • 5. Vereina Railway Line 5 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Geology of the Vereina Tunnel  Crystalline rock mass, gneisses and amphibolites  Foliation is flatly bedded, fissures show narrow spacing
  • 6. Experience Gained at the Vereina Tunnel 6 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Crown failure some sections excavated by TBM 1st causal factor  Existing geology, flatly bedded foliation 2nd causal factor  Thrust force, bracing of TBM against the tunnel wall →Gripper force can lead to opening of existing fissures →Opening of fissures in existing geology led to crown failure
  • 7. Experience Gained at the Vereina Tunnel 7 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 →Increased supporting measures →Drop down of advance rate Excavation rates
  • 8. Content 8 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 1. Introduction 3. Risk-based geotechnical design 4. Case study Lago Bianco Hydropower 6. Remaining risks of TBM tunnelling 2. Lessons learned from recent projects 5. Uncertainties in the prediction of penetration rates 2.1 Vereina Tunnel 2.2 Gotthard Base Tunnel
  • 9. Experience Gained at the Faido Single-Track Tubes 9 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Damages at Following Excavation of West Tube Invert heaves behind cutter head including heave of invert concrete Contact between back-up constructions and rock support
  • 10. Experience Gained at the Faido Single-Track Tubes 10 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Stress redistribution process Development of arch subhorizontal rock foliation Primary stress EST- East EST- West Stress redistribution due to excavation of West tube Deformations of invert and crown Stress redistribution due to excavation East tube
  • 11. 11 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Radial deformation [cm] 0 5 10 15 20 25 30 0.5 0 1 1.5 2 3 2.5 Pressure[MPa] Ground reaction curve after excavation of the first tube Ground reaction curve after excavation of the second tube Flexible lining Stiff lining Failure of rock support Residual resistance Failure of rock support Required rock support Required rock support Experience Gained at the Faido Single-Track Tubes Ground reaction curve
  • 12. Experience Gained at the Faido Single-Track Tubes 12 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Encountered geological conditions
  • 13. Experience Gained at the Faido Single-Track Tubes 13 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Crown collapse West tube, blocking of TBM, first countermeasures  6 m long weak zone of kakiritic and cataclastic material > TBM was blocked  Installation of 4 pipe umbrellas  Filling of space above cutter head with concrete  Countermeasures failed
  • 14. Experience Gained at the Faido Single-Track Tubes 14 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Crown collapse West tube, blocking of TBM, additional countermeasures  Gel grouting above TBM in order to protect cutter head from cement grouting  Cement grouting in order to stabilize collapsed zone  Adit from east tube > TBM freed after 20 weeks
  • 15. Experience Gained at the Faido Single-Track Tubes 15 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Lessons learned  Largest possible overcut  Robust shield and cutter head  Shield with variable diameter  Shortest possible shield  Sufficiently large thrust force  The capability of installing flexible support  The capability of installing support simultaneously with tunnel driving
  • 16. Content 16 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 1. Introduction 3. Risk-based geotechnical design 4. Case study Lago Bianco Hydropower 6. Remaining risks of TBM tunnelling 2. Lessons learned from recent projects 5. Uncertainties in the prediction of penetration rates
  • 17. Risk Based Geotechnical Design 17 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 TBM excavation resonable Conventional excavation Evaluation of excavation method Definition of rock mass behaviour Relevant geotechnical parameters Primary stress conditions Size, shape, location of structure Orientation of ground structure Ground water Definition of ground types no yes
  • 18. Risk Based Geotechnical Design 18 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Risks acceptable Evaluation of remaining risks Choice of TBM concept including rock support Behaviour at shield Behaviour fulfils the requirements Behaviour at back-up Behaviour at cutter head Definition of system behaviour no yes no yes
  • 19. Content 19 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 1. Introduction 3. Risk-based geotechnical design 4. Case study Lago Bianco Hydropower 6. Remaining risks of TBM tunnelling 2. Lessons learned from recent projects 5. Uncertainties in the prediction of penetration rates
  • 20. 20 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Lago Bianco Hydropower Geological, longitudinal profile 2000 3000 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000 13000 14000 15000 16000 17000 18000 19000 20000 21000 Lago Bianco 1000 Lago di Poschiavo 2000 3000 Stretta and Bernina crystalline with Alv zone Bernina thrust zone Musella granite Margna nappe Malenco nappe Margna nappe Marinelli formation Sella nappe Sella nappe Musella granite © Bild Repower Source: www.repower.com
  • 21. Experience gained at the Lago Bianco Hydropower 21 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Homogeneous zone A, chainage 1+090 to 6+820  Massive to blocky gneisses and shists  Overburden up to 850 m  Stable rock mass behaviour  Potential of gravitational overbreaks  Inhomogeneous face conditions → higher wear rates
  • 22. Experience gained at the Lago Bianco Hydropower 22 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Homogeneous zone A, chainage 1+090 to 6+820  Massive to blocky gneisses and shists  Overburden up to 850 m  Stable rock mass behaviour  Potential of gravitational overbreaks  Inhomogeneous face conditions → higher wear rates
  • 23. Experience gained at the Lago Bianco Hydropower 23 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Homogeneous zone B, chainage 6+820 to 7+020  Overburden approx. 950 m , large deformations, shear failure in crown  Risk of jamming of TBM  Shield lubrication, shifting of gauge cutters, grouting  Local water ingress und limited flowing ground conditions  Measures: Segmental lining, pipe umbrella, drainage borehole  Risk acceptable
  • 24. Experience gained at the Lago Bianco Hydropower 24 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Homogeneous zone B, chainage 6+820 to 7+020  Overburden approx. 950 m , large deformations, shear failure in crown  Risk of jamming of TBM  Shield lubrication, shifting of gauge cutters, grouting  Local water ingress und limited flowing ground conditions  Measures: Segmental lining, pipe umbrella, drainage borehole  Risk acceptable
  • 25. Experience gained at the Lago Bianco Hydropower 25 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Homogeneous zone C, chainage 14+760 to 16+050  Non-cohesive fault zone, stress induced shear- failure  Major water inflow (up to 210l/s) > risk of flowing ground conditions  High load on TBM shield and on segments > high risk of jamming  Risk not acceptable
  • 26. Experience gained at the Lago Bianco Hydropower 26 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Homogeneous zone C, chainage 14+760 to 16+050  Non-cohesive fault zone, stress induced shear failure  Major water inflow (up to 210l/s) > risk of flowing ground conditions  High load on TBM shield and on segments > high risk of jamming  Risk not acceptable
  • 27. Experience gained at the Lago Bianco Hydropower 27 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Tunnelling concept  Double shield TBM  Trapezoidal segments  Pea gravel and grouting of annular gap  Flat cutter head  Anti-wear plates and wedges  Equipment for exploration drilling  Umbrella pipe  Lubrication of shield  Pumping devices of up to 250 l/s,  Possibility of probe drillings  Segments with higher reinforcement and load capacity, with drainage tubes
  • 28. Content 28 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 1. Introduction 3. Risk-based geotechnical design 4. Case study Lago Bianco Hydropower 6. Remaining risks of TBM tunnelling 2. Lessons learned from recent projects 5. Uncertainties in the prediction of penetration rates
  • 29. Uncertainties in the Prediction of Penetration Rates 29 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Geological and geotechnical influencing factors for penetration prediction models
  • 30. Uncertainties in the Prediction of Penetration Rates 30 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Influences on penetration rate  Clogging of mucking buckets (left)  Cutter failure due to dynamic loads (right)
  • 31. Uncertainties in the Prediction of Penetration Rates 31 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Influences on penetration rate  Unaxial compressive strength  Normally oriented angle of fabric towards tunnel axis > maximum penetration  Parallel oriented angle > minimum penetration  Stress conditions at the tunnel face  Failure mode
  • 32. Content 32 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 1. Introduction 3. Risk-based geotechnical design 4. Case study Lago Bianco Hydropower 6. Remaining risks of TBM tunnelling 2. Lessons learned from recent projects 5. Uncertainties in the prediction of penetration rates
  • 33. Risk Based Geotechnical Design 33 Fjellsprengningsdagen, Bergmekanikkdagen, Geoteknikkdagen Oslo, November 22 -23, 2012 Remaining uncertainties of TBM tunnelling are related  To false prediction of system behaviour >> Ground investigation with a risk based geotechnical design >> Action plan with countermeasures  To false prediction of penetration rate >> Reliable failure modes for the determination of the advance rate A design for the “Worst Case” is certainly technically desirable, but cannot always be implemented with economically justifiable means!!!
  • 34. Thank You Very Much For Your Attention!