5. Cycle de conférences LCH 2013
112°
R6300
R7220
Final Lining
Waterproofing
Shotcrete
Rock Mass 600
Arch Concrete
Invert Concrete
Introduction _ NTFP Factbox
Tunnel Length: 10’2 km
Diameter external: 14’400 mm
Diameter internal: 12’600 mm
Lining thickness: 600 mm
Flow rate: 500m3/sec
capacity : 1,6 TWh
Water pressure max.: 13 bar
6. Cycle de conférences LCH 2013
Introduction
Discharge US: 3’087 m3/sec
Discharge CAN: 1’824 m3/sec
2013: 2’324 m3/sec
Residual flow:
¼ of overall energy production of
Ontario (CAN) and New York (US)
2’832 m3/sec
7. Cycle de conférences LCH 2013
Introduction
Construction of a twin tunnel back in the 1950 ties
8. Cycle de conférences LCH 2013
Introduction
International
Control Structure
Ice ControlGate
Gate
New
Intake
ABOVE THE
FALLS
9. Cycle de conférences LCH 2013
Introduction NTFP
Cellular cofferdam with extensive grouting measures to avoid
seepage into the open pit
10. Cycle de conférences LCH 2013
Sir Adam Beck I / II
and Pump Storage Reservoir
and Generating Station
Introduction NTFP _ Historical Development
1922
13. Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Diameter : 15.5 m
Support : 200 mm flanged, half circular I beams with channel lagging
in between
26. Cycle de conférences LCH 2013
The NTFP: Excavation and Support
Rock Mass Behaviour
27. Cycle de conférences LCH 2013
Economical Lining Design –
Passive Pre Stressed Concrete Lining
28. Cycle de conférences LCH 2013
1. Premises of a watertight lining to avoid seepage
2. Postulation of an uncracked lining
3. Economical and sustainable allocation of lining
type
General limitations of a passive pre- stressed
concrete lining systems are:
Internal Water pressure up to ~ 25 bar
for fair rock mass
Good to fair/ (local weak) rock mass conditions
Economical Lining Design
29. Cycle de conférences LCH 2013
KWEnzingerboden1967
KWKaunertal1963
KWFragnant1968
PSWDrakensberg1981
PSWKühtai1979
NTFP2013
Linthal2015
UWSTB2012
Linthal2015
OWDST2012
0
2
4
6
8
10
12
14
16
18
20
0 2 4 6 8 10 12
SLENDERNESS RATIO "SR" [m/m]
TENSILERINGFORCE"Z"[MN/m]
Slenderness ratio and internal water pressure define
indirectly the effort of geotechnical measurements for
pre- stressing works
Area with high
effort of monitoring
works
Economical Lining Design _ History
30. Cycle de conférences LCH 2013
Final Lining
Contact Grouting
Waterproofing
Interface Grouting
Rock mass
Shotcrete
ri
• Rock support (anchors and shotcrete)
Economical Lining Design _ Assembly of layers
• Rock mass grouting
• Installation of membrane PE-VLD
• Installation unreinforced concrete lining
• Pre- stressing final lining – high pressure
(gap membrane and shotcrete/ rock mass)
Workflow unreinforced pre-stressed concrete lining
• Contact grouting - low pressure
(gap final lining and membrane)
31. Cycle de conférences LCH 2013
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock
m
ass
stress-strain
relationship
1
po.water
+prock
strain
Phase 1: Initial gap of concrete lining and rock mass
E. L. D._Analytical Graphical Design Method
32. Cycle de conférences LCH 2013
32
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
1
p
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock
m
ass
stress-strain
relationship
2
po.water
+prock
Rock mass stress-strain
relationship
3
po.water
Phase 2: Contact grouting
(Closure of initial gap - bedding of lining )
E. L. D._Analytical Graphical Design Method
33. Cycle de conférences LCH 2013
33
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
R
relati
2
p
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock mass stress-strain
relationship
3
po.water
+prock
o.watero.water
rain
Phase 3: passive pre-stressing of lining and rock mass
E. L. D._Analytical Graphical Design Method
34. Cycle de conférences LCH 2013
34
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
4
po.waterpo.water
+prock
ss-strain
pi
Rock
m
ass
stress-strain
relationship
Phase 4: Pre-stress losses
E. L. D._Analytical Graphical Design Method
35. Cycle de conférences LCH 2013
35
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock
m
ass
stress-strain
relationship
Waterproofing
stress-strain
relationship
pi
5
Rock
relations
Phase 5: Operational phase
E. L. D._Analytical Graphical Design Method
36. Cycle de conférences LCH 2013
Constructional Aspects
of Passive Pre-stressed Concrete Lining
37. Cycle de conférences LCH 2013
Constructional Aspects_Membrane
Specs waterproofing membrane:
3 layers of a modified VLD PE
2 additional layers of PP fleece
Detection of voids with high voltage measurements upon installation
39. Cycle de conférences LCH 2013
Grouting section:
grout barrier
INTAKE
OUTLET
Total 4 grout lines per section (bay)
Grout section consists of two grout lines
Arch: length ~30,8 m
Invert: length ~14,4 m
Arch
Invert
3,6 to 3,8 m
Constructional Aspects_Grout Line
40. Cycle de conférences LCH 2013
40
Direct line for filling of an initial gap
Improved tube a manchette lines with two rubber sleeves
Limitation of grout lines length to 15 m
Procedure for pressure tests
Constructional Aspects_Grout Line (lessons learnt)
42. Cycle de conférences LCH 2013
S1
Interface
Grouting Carrier
Section n+5 Section n+4 Section n+3 Section n+2 Section n+1
Pre-Monitoring
Carrier
S6
Working
Platform
section n
S5S4S3S2
Post-Monitoring
Carrier
• Premises: Monitoring length must cover the area of influence
• Monitoring length NTFP is about 80 -100 m.
Monitoring length = area of influence
Constructional Aspects_comb. Monitoring/ Grouting Concept
43. Cycle de conférences LCH 2013
Kops-Vallüla,
AUT
1948
internal 2.7m
Drakensberg,
S.A.
1979-81
internal 6.5
Amlach, AUT
1989
internal
3.3m
NTFP, CAN
2012
internal 12.6m
Constructional Aspects_Development of Monitoring Systems
44. Cycle de conférences LCH 2013
Boundaries Conditions for
Development of a Laser System
Accuracy:
Accuracy real time < 1 mm
Accuracy static 3/10 mm
Traffic:
no influence of ongoing traffic
(strict order)
Grout Control System:
Interactive control of grout works
on basis of deformation measurement
Constructional Aspects_Specifications Monitoring System
45. Cycle de conférences LCH 2013
FILLING
PHASE
PRESTRESSING
PHASE
Constructional Aspects_ Monitoring and Interpretation
46. Cycle de conférences LCH 2013
IGS 35, radial deformation over time
-2.4
-4.0
-3.5
-3.0
-2.5
-2.0
-1.5
-1.0
-0.5
0.0
0.5
1.0
08.09.201100:00
10.09.201100:00
12.09.201100:00
14.09.201100:00
16.09.201100:00
18.09.201100:00
20.09.201100:00
22.09.201100:00
24.09.201100:00
26.09.201100:00
28.09.201100:00
30.09.201100:00
time / date
radialdeformation[mm]
radial strain due to IG: - 3.8 10-4
radial deformation due to IG: - 2.4 mm
point of time: 27.09.2011
result of strain gauges
result of strain gaugesFILLING
PHASE
PRE-
STRESSING
PHASE
S2 S1
IGS 32 IGS 33 IGS 34 IGS 35 IGS 36 IGS 37 IGS 38
S4S1 S3
Development of radial deformation due neighboring grouting works
Constructional Aspects_ Monitoring and Interpretation
47. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 02.04.2012 20:40
Ovalisation: 4.00 mm
m. rad. Deformation -1.38 mm
Constructional Aspects_ Monitoring and Interpretation
48. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 02.04.2012 23:39
Ovalisation: 5.10 mm
m. rad. Deformation -2.24 mm
Constructional Aspects_ Monitoring and Interpretation
49. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 00:40
Ovalisation: 4.60 mm
m. rad. Deformation -2.33 mm
Constructional Aspects_ Monitoring and Interpretation
50. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 01:10
Ovalisation: 4.80 mm
m. rad. Deformation -2.46 mm
Constructional Aspects_ Monitoring and Interpretation
51. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 01:45
Ovalisation: 5.00 mm
m. rad. Deformation -2.48 mm
Constructional Aspects_ Monitoring and Interpretation
52. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 02:15
Ovalisation: 5.10 mm
m. rad. Deformation -2.49 mm
Constructional Aspects_ Monitoring and Interpretation
53. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 02:46
Ovalisation: 5.50 mm
m. rad. Deformation -2.49 mm
Constructional Aspects_ Monitoring and Interpretation
54. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 03:12
Ovalisation: 5.10 mm
m. rad. Deformation -2.65 mm
Constructional Aspects_ Monitoring and Interpretation
55. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 03:40
Ovalisation: 5.30 mm
m. rad. Deformation -2.70 mm
Constructional Aspects_ Monitoring and Interpretation
56. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 04:24
Ovalisation: 6.80 mm
m. rad. Deformation -2.78 mm
Constructional Aspects_ Monitoring and Interpretation
57. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 04:57
Ovalisation: 7.10 mm
m. rad. Deformation -2.91 mm
Constructional Aspects_ Monitoring and Interpretation
58. Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 05:30
Ovalisation: 8.80 mm
m. rad. Deformation -3.60 mm
Deformation of the lining due to IG:
Results Pre - Stressing
2
4
6
8 7
5
3
1
Lining 03.04.2012 05:34
interpolation of splines is based on
cubic spline interpolation method
Constructional Aspects_ Monitoring and Interpretation
59. Cycle de conférences LCH 2013
Constructional Aspects_ Monitoring and Interpretation
60. Cycle de conférences LCH 2013
-5.0
-4.5
-4.0
-3.5
-3.0
-2.5
-2.0
-1.5
-1.0
-0.5
0.0
0 5 10 15 20 25
radialdeformation[mm]
pre-stress pressure [bar]
data
behaviour of final lining - average
behaviour of final lining - boundary range
behaviour of final lining - boundary range +/- 25%
0%
20%
40%
60%
80%
100%
0%
20%
40%
60%
80%
100%
Constructional Aspects_ Monitoring and Interpretation
62. Cycle de conférences LCH 2013
-2.5
-2.0
-1.5
-1.0
-0.5
0.0
08.09.201206.00
08.09.201209.00
08.09.201212.00
08.09.201215.00
08.09.201218.00
08.09.201221.00
09.09.201200.00
09.09.201203.00
09.09.201206.00
09.09.201209.00
09.09.201212.00
09.09.201215.00
09.09.201218.00
09.09.201221.00
10.09.201200.00
radialdeformation[mm]
date /time
Mobile Deformation Monitoring
Strain Gauge
09.09.2012 20:46
-2.2
8
mm
mm
Date / Time
Ovalisation
Radial deformation
Mobile Monitoring Results due to IG
Start Value due to
Contact Grouting
and Filling Phase
Constructional Aspects_ Monitoring and Interpretation
63. Cycle de conférences LCH 2013
Constructional Aspects_ Monitoring and Interpretation
Observation of pre-stressing losses before watering up
Antithesis of doctrine , to be investigated by a phd study !!!!!!!!
65. Cycle de conférences LCH 2013
• Effective und risk minized operation of pre-stressing works due to dection in
time (spalling and overstressing may lead to damage of structure and personal)
• Full scale documentation and detection of area with insufficient pre-stressing
(Intervention)
• Amortisation of initial cost due to shortage of time for pre-stressing works.
• System is now fully developed (after 10 km) and can be rented !!!!!!!!!
ContraPro
(Higher initial investment for
monitoring system)
Qualified und experienced personal
necessary for set up and monitoring
Intense work preparation
Pre-stressed pressure tunnels work!
Combined grouting / deformation (full
face) is the key to success
Full face monitoring is valuable for
geotechnical monitoring and data
interpretation and documentation for
owner
In time decision making , no delays
(costs)
Conclusion
Lessons learnt
66. Cycle de conférences LCH 2013
Operation
Supervisor
Shift Engineer
Foreman
Technicans Pumps
Operator Pumps
Design & Monitoring
P.P-S.C.L.
Experienced design team
Geotechnical Eng. on site
Mechatronics
Mechatronics
Electricians
Software Engineers
Lessons learnt