SlideShare a Scribd company logo
1 of 67
Cycle de conférences LCH 2013
«The Niagara Tunnel Facility Project»
presented by
Helmut Wannenmacher
Cycle de conférences LCH 2013
Cycle de conférences LCH 2013
The Niagara Tunnel Facility Project «NTFP»
 Introduction and Historical Development
 The NTFP: Excavation and Support
 Economical Lining Design – Passive Pre-stressed Concrete Lining
 Constructional Aspects of Passive Pre-stressed Concrete Lining
 Lessons learnt ?
Cycle de conférences LCH 2013
Introduction and Historical Development
Cycle de conférences LCH 2013
112°
R6300
R7220
Final Lining
Waterproofing
Shotcrete
Rock Mass 600
Arch Concrete
Invert Concrete
Introduction _ NTFP Factbox
Tunnel Length: 10’2 km
Diameter external: 14’400 mm
Diameter internal: 12’600 mm
Lining thickness: 600 mm
Flow rate: 500m3/sec
capacity : 1,6 TWh
Water pressure max.: 13 bar
Cycle de conférences LCH 2013
Introduction
Discharge US: 3’087 m3/sec
Discharge CAN: 1’824 m3/sec
2013: 2’324 m3/sec
Residual flow:
¼ of overall energy production of
Ontario (CAN) and New York (US)
2’832 m3/sec
Cycle de conférences LCH 2013
Introduction
Construction of a twin tunnel back in the 1950 ties
Cycle de conférences LCH 2013
Introduction
International
Control Structure
Ice ControlGate
Gate
New
Intake
ABOVE THE
FALLS
Cycle de conférences LCH 2013
Introduction NTFP
Cellular cofferdam with extensive grouting measures to avoid
seepage into the open pit
Cycle de conférences LCH 2013
Sir Adam Beck I / II
and Pump Storage Reservoir
and Generating Station
Introduction NTFP _ Historical Development
1922
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Diameter : 15.5 m
Support : 200 mm flanged, half circular I beams with channel lagging
in between
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Bench Drilling
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Bench
Complete
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Concrete
Forms
Cycle de conférences LCH 2013
Introduction NTFP _ Historical Development
Cycle de conférences LCH 2013
The NTFP: Excavation and Support
Cycle de conférences LCH 2013
The NTFP: Excavation and Support
• Limestone
• Sandstone
• Claystone- Queenston
Shale 60% (swelling)
Cycle de conférences LCH 2013
The NTFP: Excavation and Support
 World’s largest open hard rock TBM
>> Big Becky<<
4 m 10 m 14.40 m
Cycle de conférences LCH 2013
The NTFP: Excavation and Support
Cycle de conférences LCH 2013
The NTFP: Excavation and Support
Cycle de conférences LCH 2013
The NTFP: Excavation and Support
Rock Mass Behaviour
Cycle de conférences LCH 2013
Economical Lining Design –
Passive Pre Stressed Concrete Lining
Cycle de conférences LCH 2013
1. Premises of a watertight lining to avoid seepage
2. Postulation of an uncracked lining
3. Economical and sustainable allocation of lining
type
General limitations of a passive pre- stressed
concrete lining systems are:
 Internal Water pressure up to ~ 25 bar
for fair rock mass
 Good to fair/ (local weak) rock mass conditions
Economical Lining Design
Cycle de conférences LCH 2013
KWEnzingerboden1967
KWKaunertal1963
KWFragnant1968
PSWDrakensberg1981
PSWKühtai1979
NTFP2013
Linthal2015
UWSTB2012
Linthal2015
OWDST2012
0
2
4
6
8
10
12
14
16
18
20
0 2 4 6 8 10 12
SLENDERNESS RATIO "SR" [m/m]
TENSILERINGFORCE"Z"[MN/m]
 Slenderness ratio and internal water pressure define
indirectly the effort of geotechnical measurements for
pre- stressing works
Area with high
effort of monitoring
works
Economical Lining Design _ History
Cycle de conférences LCH 2013
Final Lining
Contact Grouting
Waterproofing
Interface Grouting
Rock mass
Shotcrete
ri
• Rock support (anchors and shotcrete)
Economical Lining Design _ Assembly of layers
• Rock mass grouting
• Installation of membrane PE-VLD
• Installation unreinforced concrete lining
• Pre- stressing final lining – high pressure
(gap membrane and shotcrete/ rock mass)
Workflow unreinforced pre-stressed concrete lining
• Contact grouting - low pressure
(gap final lining and membrane)
Cycle de conférences LCH 2013
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock
m
ass
stress-strain
relationship
1
po.water
+prock
strain
Phase 1: Initial gap of concrete lining and rock mass
E. L. D._Analytical Graphical Design Method
Cycle de conférences LCH 2013
32
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
1
p
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock
m
ass
stress-strain
relationship
2
po.water
+prock
Rock mass stress-strain
relationship
3
po.water
Phase 2: Contact grouting
(Closure of initial gap - bedding of lining )
E. L. D._Analytical Graphical Design Method
Cycle de conférences LCH 2013
33
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
R
relati
2
p
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock mass stress-strain
relationship
3
po.water
+prock
o.watero.water
rain
Phase 3: passive pre-stressing of lining and rock mass
E. L. D._Analytical Graphical Design Method
Cycle de conférences LCH 2013
34
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
4
po.waterpo.water
+prock
ss-strain
pi
Rock
m
ass
stress-strain
relationship
Phase 4: Pre-stress losses
E. L. D._Analytical Graphical Design Method
Cycle de conférences LCH 2013
35
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
+prock
+pliner
+ r(ro)
tensioncompression
- r(ro)
allow. concrete
Lining stress-strain
relationship
Rock
m
ass
stress-strain
relationship
Waterproofing
stress-strain
relationship
pi
5
Rock
relations
Phase 5: Operational phase
E. L. D._Analytical Graphical Design Method
Cycle de conférences LCH 2013
 Constructional Aspects
of Passive Pre-stressed Concrete Lining
Cycle de conférences LCH 2013
Constructional Aspects_Membrane
Specs waterproofing membrane:
 3 layers of a modified VLD PE
 2 additional layers of PP fleece
Detection of voids with high voltage measurements upon installation
Cycle de conférences LCH 2013
Constructional Aspects_Grout Line
Cycle de conférences LCH 2013
Grouting section:
grout barrier
INTAKE
OUTLET
 Total 4 grout lines per section (bay)
 Grout section consists of two grout lines
 Arch: length ~30,8 m
 Invert: length ~14,4 m
Arch
Invert
3,6 to 3,8 m
Constructional Aspects_Grout Line
Cycle de conférences LCH 2013
40
 Direct line for filling of an initial gap
 Improved tube a manchette lines with two rubber sleeves
 Limitation of grout lines length to 15 m
 Procedure for pressure tests
Constructional Aspects_Grout Line (lessons learnt)
Cycle de conférences LCH 2013
Low
Point
Constructional Aspects_Grouting Setup
Cycle de conférences LCH 2013
S1
Interface
Grouting Carrier
Section n+5 Section n+4 Section n+3 Section n+2 Section n+1
Pre-Monitoring
Carrier
S6
Working
Platform
section n
S5S4S3S2
Post-Monitoring
Carrier
• Premises: Monitoring length must cover the area of influence
• Monitoring length NTFP is about 80 -100 m.
Monitoring length = area of influence
Constructional Aspects_comb. Monitoring/ Grouting Concept
Cycle de conférences LCH 2013
Kops-Vallüla,
AUT
1948
internal 2.7m
Drakensberg,
S.A.
1979-81
internal 6.5
Amlach, AUT
1989
internal
3.3m
NTFP, CAN
2012
internal 12.6m
Constructional Aspects_Development of Monitoring Systems
Cycle de conférences LCH 2013
Boundaries Conditions for
Development of a Laser System
Accuracy:
 Accuracy real time < 1 mm
 Accuracy static 3/10 mm
Traffic:
 no influence of ongoing traffic
(strict order)
Grout Control System:
 Interactive control of grout works
on basis of deformation measurement
Constructional Aspects_Specifications Monitoring System
Cycle de conférences LCH 2013
FILLING
PHASE
PRESTRESSING
PHASE
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
IGS 35, radial deformation over time
-2.4
-4.0
-3.5
-3.0
-2.5
-2.0
-1.5
-1.0
-0.5
0.0
0.5
1.0
08.09.201100:00
10.09.201100:00
12.09.201100:00
14.09.201100:00
16.09.201100:00
18.09.201100:00
20.09.201100:00
22.09.201100:00
24.09.201100:00
26.09.201100:00
28.09.201100:00
30.09.201100:00
time / date
radialdeformation[mm]
radial strain due to IG: - 3.8 10-4
radial deformation due to IG: - 2.4 mm
point of time: 27.09.2011
result of strain gauges
result of strain gaugesFILLING
PHASE
PRE-
STRESSING
PHASE
S2 S1
IGS 32 IGS 33 IGS 34 IGS 35 IGS 36 IGS 37 IGS 38
S4S1 S3
Development of radial deformation due neighboring grouting works
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 02.04.2012 20:40
Ovalisation: 4.00 mm
m. rad. Deformation -1.38 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 02.04.2012 23:39
Ovalisation: 5.10 mm
m. rad. Deformation -2.24 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 00:40
Ovalisation: 4.60 mm
m. rad. Deformation -2.33 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 01:10
Ovalisation: 4.80 mm
m. rad. Deformation -2.46 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 01:45
Ovalisation: 5.00 mm
m. rad. Deformation -2.48 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 02:15
Ovalisation: 5.10 mm
m. rad. Deformation -2.49 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 02:46
Ovalisation: 5.50 mm
m. rad. Deformation -2.49 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 03:12
Ovalisation: 5.10 mm
m. rad. Deformation -2.65 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 03:40
Ovalisation: 5.30 mm
m. rad. Deformation -2.70 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 04:24
Ovalisation: 6.80 mm
m. rad. Deformation -2.78 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 04:57
Ovalisation: 7.10 mm
m. rad. Deformation -2.91 mm
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Section140, differential deformation (developed view)
Date/Time: 03.04.2012 05:30
Ovalisation: 8.80 mm
m. rad. Deformation -3.60 mm
Deformation of the lining due to IG:
Results Pre - Stressing
2
4
6
8 7
5
3
1
Lining 03.04.2012 05:34
interpolation of splines is based on
cubic spline interpolation method
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
-5.0
-4.5
-4.0
-3.5
-3.0
-2.5
-2.0
-1.5
-1.0
-0.5
0.0
0 5 10 15 20 25
radialdeformation[mm]
pre-stress pressure [bar]
data
behaviour of final lining - average
behaviour of final lining - boundary range
behaviour of final lining - boundary range +/- 25%
0%
20%
40%
60%
80%
100%
0%
20%
40%
60%
80%
100%
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
0.0
5.0
10.0
15.0
20.0
25.0
30.0
09.09.1215:15:00
09.09.1215:30:00
09.09.1215:45:00
09.09.1216:00:00
09.09.1216:15:00
09.09.1216:30:00
09.09.1216:45:00
09.09.1217:00:00
09.09.1217:15:00
09.09.1217:30:00
09.09.1217:45:00
09.09.1218:00:00
09.09.1218:15:00
09.09.1218:30:00
09.09.1218:45:00
09.09.1219:00:00
09.09.1219:15:00
09.09.1219:30:00
09.09.1219:45:00
09.09.1220:00:00
09.09.1220:15:00
09.09.1220:30:00
09.09.1220:45:00
09.09.1221:00:00
Pressure[bar]
Flowrate[l/min]
date / time
Pressure
Pressure Test
flow rate
strain gauge
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
-2.5
-2.0
-1.5
-1.0
-0.5
0.0
08.09.201206.00
08.09.201209.00
08.09.201212.00
08.09.201215.00
08.09.201218.00
08.09.201221.00
09.09.201200.00
09.09.201203.00
09.09.201206.00
09.09.201209.00
09.09.201212.00
09.09.201215.00
09.09.201218.00
09.09.201221.00
10.09.201200.00
radialdeformation[mm]
date /time
Mobile Deformation Monitoring
Strain Gauge
09.09.2012 20:46
-2.2
8
mm
mm
Date / Time
Ovalisation
Radial deformation
Mobile Monitoring Results due to IG
Start Value due to
Contact Grouting
and Filling Phase
Constructional Aspects_ Monitoring and Interpretation
Cycle de conférences LCH 2013
Constructional Aspects_ Monitoring and Interpretation
Observation of pre-stressing losses before watering up
 Antithesis of doctrine , to be investigated by a phd study !!!!!!!!
Cycle de conférences LCH 2013
 Lessons learnt ?
Cycle de conférences LCH 2013
• Effective und risk minized operation of pre-stressing works due to dection in
time (spalling and overstressing may lead to damage of structure and personal)
• Full scale documentation and detection of area with insufficient pre-stressing
(Intervention)
• Amortisation of initial cost due to shortage of time for pre-stressing works.
• System is now fully developed (after 10 km) and can be rented !!!!!!!!!
ContraPro
 (Higher initial investment for
monitoring system)
 Qualified und experienced personal
necessary for set up and monitoring
 Intense work preparation
 Pre-stressed pressure tunnels work!
 Combined grouting / deformation (full
face) is the key to success
 Full face monitoring is valuable for
geotechnical monitoring and data
interpretation and documentation for
owner
 In time decision making , no delays
(costs)
Conclusion
Lessons learnt
Cycle de conférences LCH 2013
Operation
Supervisor
Shift Engineer
Foreman
Technicans Pumps
Operator Pumps
Design & Monitoring
P.P-S.C.L.
Experienced design team
Geotechnical Eng. on site
Mechatronics
Mechatronics
Electricians
Software Engineers
Lessons learnt
further contact :
hwannenmacher@amberg.ch
Thanks for your audience.

More Related Content

What's hot

Lean & Green Project Management - PMI Conference
Lean & Green Project Management - PMI ConferenceLean & Green Project Management - PMI Conference
Lean & Green Project Management - PMI ConferenceNicos Kourounakis
 
lean construction and integrated project delivery
lean construction and integrated project delivery lean construction and integrated project delivery
lean construction and integrated project delivery Mahendra Bhuva
 
PMBOK 6 Summary: Module 3 (Executing Processes)
PMBOK 6 Summary: Module 3 (Executing Processes)PMBOK 6 Summary: Module 3 (Executing Processes)
PMBOK 6 Summary: Module 3 (Executing Processes)Awaludin Zakaria
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurementMalcolm Peart
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
PMBOK 6 Summary: Module 5 (Closing Processes)
PMBOK 6 Summary: Module 5 (Closing Processes)PMBOK 6 Summary: Module 5 (Closing Processes)
PMBOK 6 Summary: Module 5 (Closing Processes)Awaludin Zakaria
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP) Ahmad Maharma, PMP,RMP
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagramriosabel
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionDavid H Moloney
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration ManagementMartin Sillaots
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Murali Naidu
 

What's hot (20)

Lean & Green Project Management - PMI Conference
Lean & Green Project Management - PMI ConferenceLean & Green Project Management - PMI Conference
Lean & Green Project Management - PMI Conference
 
lean construction and integrated project delivery
lean construction and integrated project delivery lean construction and integrated project delivery
lean construction and integrated project delivery
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
PMBOK 6 Summary: Module 3 (Executing Processes)
PMBOK 6 Summary: Module 3 (Executing Processes)PMBOK 6 Summary: Module 3 (Executing Processes)
PMBOK 6 Summary: Module 3 (Executing Processes)
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
 
EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
PMBOK 6 Summary: Module 5 (Closing Processes)
PMBOK 6 Summary: Module 5 (Closing Processes)PMBOK 6 Summary: Module 5 (Closing Processes)
PMBOK 6 Summary: Module 5 (Closing Processes)
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagram
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Pmbok 5 ed diagram
Pmbok 5 ed diagramPmbok 5 ed diagram
Pmbok 5 ed diagram
 
Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016
 

Similar to The Niagara Tunnel Facility Project

“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”IRJET Journal
 
Feasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationFeasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationAwais Marwat
 
Thesis Powerpoint
Thesis PowerpointThesis Powerpoint
Thesis Powerpointneha47
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Sirris
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESCarlo Avanzini
 
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...Global CCS Institute
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
14 aneu applications of technological &amp; engineering solutions edit
14 aneu applications of technological &amp; engineering solutions edit 14 aneu applications of technological &amp; engineering solutions edit
14 aneu applications of technological &amp; engineering solutions edit Juan Carlos Bonapace
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technologyAbhishek Paul
 
Kelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboKelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboAnton Ricalovskis
 
SELF COMPSCTING CONCRETE BY USING FLYASH
SELF COMPSCTING CONCRETE BY USING FLYASHSELF COMPSCTING CONCRETE BY USING FLYASH
SELF COMPSCTING CONCRETE BY USING FLYASHSiddhu Siddarth
 
Impact driving of large piles/monopiles - contributions from pile driving mon...
Impact driving of large piles/monopiles - contributions from pile driving mon...Impact driving of large piles/monopiles - contributions from pile driving mon...
Impact driving of large piles/monopiles - contributions from pile driving mon...Cathie Associates
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16Leo Youngman
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Pratik Rao - Thesis Presentation FINAL
Pratik Rao - Thesis Presentation FINALPratik Rao - Thesis Presentation FINAL
Pratik Rao - Thesis Presentation FINALPratik Rao
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wallvikas Meena
 

Similar to The Niagara Tunnel Facility Project (20)

“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
 
Feasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationFeasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower Station
 
Thesis Powerpoint
Thesis PowerpointThesis Powerpoint
Thesis Powerpoint
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCES
 
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
Modeling CO2 injection into saline aquifers, Gonzalo Zambrano, University of ...
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
14 aneu applications of technological &amp; engineering solutions edit
14 aneu applications of technological &amp; engineering solutions edit 14 aneu applications of technological &amp; engineering solutions edit
14 aneu applications of technological &amp; engineering solutions edit
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
Kelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboKelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in Colombo
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
SELF COMPSCTING CONCRETE BY USING FLYASH
SELF COMPSCTING CONCRETE BY USING FLYASHSELF COMPSCTING CONCRETE BY USING FLYASH
SELF COMPSCTING CONCRETE BY USING FLYASH
 
Impact driving of large piles/monopiles - contributions from pile driving mon...
Impact driving of large piles/monopiles - contributions from pile driving mon...Impact driving of large piles/monopiles - contributions from pile driving mon...
Impact driving of large piles/monopiles - contributions from pile driving mon...
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Pratik Rao - Thesis Presentation FINAL
Pratik Rao - Thesis Presentation FINALPratik Rao - Thesis Presentation FINAL
Pratik Rao - Thesis Presentation FINAL
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wall
 

More from Helmut Wannenmacher

Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2Helmut Wannenmacher
 
Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...Helmut Wannenmacher
 
Operational analyses of pressure tunnel and shaft grouting operations
Operational analyses of pressure tunnel  and shaft grouting operationsOperational analyses of pressure tunnel  and shaft grouting operations
Operational analyses of pressure tunnel and shaft grouting operationsHelmut Wannenmacher
 
LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART
LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ARTLARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART
LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ARTHelmut Wannenmacher
 
Underground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston FormationUnderground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston FormationHelmut Wannenmacher
 
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...Helmut Wannenmacher
 
Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration Helmut Wannenmacher
 
Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Helmut Wannenmacher
 
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...Helmut Wannenmacher
 

More from Helmut Wannenmacher (11)

Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
Baulos SBT3.1: Bohr- und Injektionsarbeiten für den Schacht Sommerau 2
 
Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...Control of operational and technical aspects of grouting works in tunnelling ...
Control of operational and technical aspects of grouting works in tunnelling ...
 
Hydro 2016 wannenmacher
Hydro 2016  wannenmacherHydro 2016  wannenmacher
Hydro 2016 wannenmacher
 
Operational analyses of pressure tunnel and shaft grouting operations
Operational analyses of pressure tunnel  and shaft grouting operationsOperational analyses of pressure tunnel  and shaft grouting operations
Operational analyses of pressure tunnel and shaft grouting operations
 
LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART
LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ARTLARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART
LARGE TBM PROJECTS IN SWITZERLAND – EXPERIENCE AND STATE OF THE ART
 
Tum vortragfinal
Tum vortragfinal Tum vortragfinal
Tum vortragfinal
 
Underground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston FormationUnderground Excavation Behavior of the Queenston Formation
Underground Excavation Behavior of the Queenston Formation
 
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
Aspects of pressure tunnel lining with special focus on pre-stressed pressure...
 
Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration Der Einfluss von Gebirgsparametern auf die Penetration
Der Einfluss von Gebirgsparametern auf die Penetration
 
Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...
 
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
Unexpected performance and cost factors for hard rock TBM. Analyses of specif...
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

The Niagara Tunnel Facility Project

  • 1. Cycle de conférences LCH 2013 «The Niagara Tunnel Facility Project» presented by Helmut Wannenmacher
  • 3. Cycle de conférences LCH 2013 The Niagara Tunnel Facility Project «NTFP»  Introduction and Historical Development  The NTFP: Excavation and Support  Economical Lining Design – Passive Pre-stressed Concrete Lining  Constructional Aspects of Passive Pre-stressed Concrete Lining  Lessons learnt ?
  • 4. Cycle de conférences LCH 2013 Introduction and Historical Development
  • 5. Cycle de conférences LCH 2013 112° R6300 R7220 Final Lining Waterproofing Shotcrete Rock Mass 600 Arch Concrete Invert Concrete Introduction _ NTFP Factbox Tunnel Length: 10’2 km Diameter external: 14’400 mm Diameter internal: 12’600 mm Lining thickness: 600 mm Flow rate: 500m3/sec capacity : 1,6 TWh Water pressure max.: 13 bar
  • 6. Cycle de conférences LCH 2013 Introduction Discharge US: 3’087 m3/sec Discharge CAN: 1’824 m3/sec 2013: 2’324 m3/sec Residual flow: ¼ of overall energy production of Ontario (CAN) and New York (US) 2’832 m3/sec
  • 7. Cycle de conférences LCH 2013 Introduction Construction of a twin tunnel back in the 1950 ties
  • 8. Cycle de conférences LCH 2013 Introduction International Control Structure Ice ControlGate Gate New Intake ABOVE THE FALLS
  • 9. Cycle de conférences LCH 2013 Introduction NTFP Cellular cofferdam with extensive grouting measures to avoid seepage into the open pit
  • 10. Cycle de conférences LCH 2013 Sir Adam Beck I / II and Pump Storage Reservoir and Generating Station Introduction NTFP _ Historical Development 1922
  • 11. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development
  • 12. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development
  • 13. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development Diameter : 15.5 m Support : 200 mm flanged, half circular I beams with channel lagging in between
  • 14. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development
  • 15. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development
  • 16. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development Bench Drilling
  • 17. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development Bench Complete
  • 18. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development
  • 19. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development Concrete Forms
  • 20. Cycle de conférences LCH 2013 Introduction NTFP _ Historical Development
  • 21. Cycle de conférences LCH 2013 The NTFP: Excavation and Support
  • 22. Cycle de conférences LCH 2013 The NTFP: Excavation and Support • Limestone • Sandstone • Claystone- Queenston Shale 60% (swelling)
  • 23. Cycle de conférences LCH 2013 The NTFP: Excavation and Support  World’s largest open hard rock TBM >> Big Becky<< 4 m 10 m 14.40 m
  • 24. Cycle de conférences LCH 2013 The NTFP: Excavation and Support
  • 25. Cycle de conférences LCH 2013 The NTFP: Excavation and Support
  • 26. Cycle de conférences LCH 2013 The NTFP: Excavation and Support Rock Mass Behaviour
  • 27. Cycle de conférences LCH 2013 Economical Lining Design – Passive Pre Stressed Concrete Lining
  • 28. Cycle de conférences LCH 2013 1. Premises of a watertight lining to avoid seepage 2. Postulation of an uncracked lining 3. Economical and sustainable allocation of lining type General limitations of a passive pre- stressed concrete lining systems are:  Internal Water pressure up to ~ 25 bar for fair rock mass  Good to fair/ (local weak) rock mass conditions Economical Lining Design
  • 29. Cycle de conférences LCH 2013 KWEnzingerboden1967 KWKaunertal1963 KWFragnant1968 PSWDrakensberg1981 PSWKühtai1979 NTFP2013 Linthal2015 UWSTB2012 Linthal2015 OWDST2012 0 2 4 6 8 10 12 14 16 18 20 0 2 4 6 8 10 12 SLENDERNESS RATIO "SR" [m/m] TENSILERINGFORCE"Z"[MN/m]  Slenderness ratio and internal water pressure define indirectly the effort of geotechnical measurements for pre- stressing works Area with high effort of monitoring works Economical Lining Design _ History
  • 30. Cycle de conférences LCH 2013 Final Lining Contact Grouting Waterproofing Interface Grouting Rock mass Shotcrete ri • Rock support (anchors and shotcrete) Economical Lining Design _ Assembly of layers • Rock mass grouting • Installation of membrane PE-VLD • Installation unreinforced concrete lining • Pre- stressing final lining – high pressure (gap membrane and shotcrete/ rock mass) Workflow unreinforced pre-stressed concrete lining • Contact grouting - low pressure (gap final lining and membrane)
  • 31. Cycle de conférences LCH 2013 +prock +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship Rock m ass stress-strain relationship 1 po.water +prock strain Phase 1: Initial gap of concrete lining and rock mass E. L. D._Analytical Graphical Design Method
  • 32. Cycle de conférences LCH 2013 32 +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship 1 p +prock +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship Rock m ass stress-strain relationship 2 po.water +prock Rock mass stress-strain relationship 3 po.water Phase 2: Contact grouting (Closure of initial gap - bedding of lining ) E. L. D._Analytical Graphical Design Method
  • 33. Cycle de conférences LCH 2013 33 +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship R relati 2 p +prock +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship Rock mass stress-strain relationship 3 po.water +prock o.watero.water rain Phase 3: passive pre-stressing of lining and rock mass E. L. D._Analytical Graphical Design Method
  • 34. Cycle de conférences LCH 2013 34 +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship +prock +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship 4 po.waterpo.water +prock ss-strain pi Rock m ass stress-strain relationship Phase 4: Pre-stress losses E. L. D._Analytical Graphical Design Method
  • 35. Cycle de conférences LCH 2013 35 +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship +prock +pliner + r(ro) tensioncompression - r(ro) allow. concrete Lining stress-strain relationship Rock m ass stress-strain relationship Waterproofing stress-strain relationship pi 5 Rock relations Phase 5: Operational phase E. L. D._Analytical Graphical Design Method
  • 36. Cycle de conférences LCH 2013  Constructional Aspects of Passive Pre-stressed Concrete Lining
  • 37. Cycle de conférences LCH 2013 Constructional Aspects_Membrane Specs waterproofing membrane:  3 layers of a modified VLD PE  2 additional layers of PP fleece Detection of voids with high voltage measurements upon installation
  • 38. Cycle de conférences LCH 2013 Constructional Aspects_Grout Line
  • 39. Cycle de conférences LCH 2013 Grouting section: grout barrier INTAKE OUTLET  Total 4 grout lines per section (bay)  Grout section consists of two grout lines  Arch: length ~30,8 m  Invert: length ~14,4 m Arch Invert 3,6 to 3,8 m Constructional Aspects_Grout Line
  • 40. Cycle de conférences LCH 2013 40  Direct line for filling of an initial gap  Improved tube a manchette lines with two rubber sleeves  Limitation of grout lines length to 15 m  Procedure for pressure tests Constructional Aspects_Grout Line (lessons learnt)
  • 41. Cycle de conférences LCH 2013 Low Point Constructional Aspects_Grouting Setup
  • 42. Cycle de conférences LCH 2013 S1 Interface Grouting Carrier Section n+5 Section n+4 Section n+3 Section n+2 Section n+1 Pre-Monitoring Carrier S6 Working Platform section n S5S4S3S2 Post-Monitoring Carrier • Premises: Monitoring length must cover the area of influence • Monitoring length NTFP is about 80 -100 m. Monitoring length = area of influence Constructional Aspects_comb. Monitoring/ Grouting Concept
  • 43. Cycle de conférences LCH 2013 Kops-Vallüla, AUT 1948 internal 2.7m Drakensberg, S.A. 1979-81 internal 6.5 Amlach, AUT 1989 internal 3.3m NTFP, CAN 2012 internal 12.6m Constructional Aspects_Development of Monitoring Systems
  • 44. Cycle de conférences LCH 2013 Boundaries Conditions for Development of a Laser System Accuracy:  Accuracy real time < 1 mm  Accuracy static 3/10 mm Traffic:  no influence of ongoing traffic (strict order) Grout Control System:  Interactive control of grout works on basis of deformation measurement Constructional Aspects_Specifications Monitoring System
  • 45. Cycle de conférences LCH 2013 FILLING PHASE PRESTRESSING PHASE Constructional Aspects_ Monitoring and Interpretation
  • 46. Cycle de conférences LCH 2013 IGS 35, radial deformation over time -2.4 -4.0 -3.5 -3.0 -2.5 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 08.09.201100:00 10.09.201100:00 12.09.201100:00 14.09.201100:00 16.09.201100:00 18.09.201100:00 20.09.201100:00 22.09.201100:00 24.09.201100:00 26.09.201100:00 28.09.201100:00 30.09.201100:00 time / date radialdeformation[mm] radial strain due to IG: - 3.8 10-4 radial deformation due to IG: - 2.4 mm point of time: 27.09.2011 result of strain gauges result of strain gaugesFILLING PHASE PRE- STRESSING PHASE S2 S1 IGS 32 IGS 33 IGS 34 IGS 35 IGS 36 IGS 37 IGS 38 S4S1 S3 Development of radial deformation due neighboring grouting works Constructional Aspects_ Monitoring and Interpretation
  • 47. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 02.04.2012 20:40 Ovalisation: 4.00 mm m. rad. Deformation -1.38 mm Constructional Aspects_ Monitoring and Interpretation
  • 48. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 02.04.2012 23:39 Ovalisation: 5.10 mm m. rad. Deformation -2.24 mm Constructional Aspects_ Monitoring and Interpretation
  • 49. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 00:40 Ovalisation: 4.60 mm m. rad. Deformation -2.33 mm Constructional Aspects_ Monitoring and Interpretation
  • 50. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 01:10 Ovalisation: 4.80 mm m. rad. Deformation -2.46 mm Constructional Aspects_ Monitoring and Interpretation
  • 51. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 01:45 Ovalisation: 5.00 mm m. rad. Deformation -2.48 mm Constructional Aspects_ Monitoring and Interpretation
  • 52. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 02:15 Ovalisation: 5.10 mm m. rad. Deformation -2.49 mm Constructional Aspects_ Monitoring and Interpretation
  • 53. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 02:46 Ovalisation: 5.50 mm m. rad. Deformation -2.49 mm Constructional Aspects_ Monitoring and Interpretation
  • 54. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 03:12 Ovalisation: 5.10 mm m. rad. Deformation -2.65 mm Constructional Aspects_ Monitoring and Interpretation
  • 55. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 03:40 Ovalisation: 5.30 mm m. rad. Deformation -2.70 mm Constructional Aspects_ Monitoring and Interpretation
  • 56. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 04:24 Ovalisation: 6.80 mm m. rad. Deformation -2.78 mm Constructional Aspects_ Monitoring and Interpretation
  • 57. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 04:57 Ovalisation: 7.10 mm m. rad. Deformation -2.91 mm Constructional Aspects_ Monitoring and Interpretation
  • 58. Cycle de conférences LCH 2013 Section140, differential deformation (developed view) Date/Time: 03.04.2012 05:30 Ovalisation: 8.80 mm m. rad. Deformation -3.60 mm Deformation of the lining due to IG: Results Pre - Stressing 2 4 6 8 7 5 3 1 Lining 03.04.2012 05:34 interpolation of splines is based on cubic spline interpolation method Constructional Aspects_ Monitoring and Interpretation
  • 59. Cycle de conférences LCH 2013 Constructional Aspects_ Monitoring and Interpretation
  • 60. Cycle de conférences LCH 2013 -5.0 -4.5 -4.0 -3.5 -3.0 -2.5 -2.0 -1.5 -1.0 -0.5 0.0 0 5 10 15 20 25 radialdeformation[mm] pre-stress pressure [bar] data behaviour of final lining - average behaviour of final lining - boundary range behaviour of final lining - boundary range +/- 25% 0% 20% 40% 60% 80% 100% 0% 20% 40% 60% 80% 100% Constructional Aspects_ Monitoring and Interpretation
  • 61. Cycle de conférences LCH 2013 0.0 5.0 10.0 15.0 20.0 25.0 30.0 09.09.1215:15:00 09.09.1215:30:00 09.09.1215:45:00 09.09.1216:00:00 09.09.1216:15:00 09.09.1216:30:00 09.09.1216:45:00 09.09.1217:00:00 09.09.1217:15:00 09.09.1217:30:00 09.09.1217:45:00 09.09.1218:00:00 09.09.1218:15:00 09.09.1218:30:00 09.09.1218:45:00 09.09.1219:00:00 09.09.1219:15:00 09.09.1219:30:00 09.09.1219:45:00 09.09.1220:00:00 09.09.1220:15:00 09.09.1220:30:00 09.09.1220:45:00 09.09.1221:00:00 Pressure[bar] Flowrate[l/min] date / time Pressure Pressure Test flow rate strain gauge Constructional Aspects_ Monitoring and Interpretation
  • 62. Cycle de conférences LCH 2013 -2.5 -2.0 -1.5 -1.0 -0.5 0.0 08.09.201206.00 08.09.201209.00 08.09.201212.00 08.09.201215.00 08.09.201218.00 08.09.201221.00 09.09.201200.00 09.09.201203.00 09.09.201206.00 09.09.201209.00 09.09.201212.00 09.09.201215.00 09.09.201218.00 09.09.201221.00 10.09.201200.00 radialdeformation[mm] date /time Mobile Deformation Monitoring Strain Gauge 09.09.2012 20:46 -2.2 8 mm mm Date / Time Ovalisation Radial deformation Mobile Monitoring Results due to IG Start Value due to Contact Grouting and Filling Phase Constructional Aspects_ Monitoring and Interpretation
  • 63. Cycle de conférences LCH 2013 Constructional Aspects_ Monitoring and Interpretation Observation of pre-stressing losses before watering up  Antithesis of doctrine , to be investigated by a phd study !!!!!!!!
  • 64. Cycle de conférences LCH 2013  Lessons learnt ?
  • 65. Cycle de conférences LCH 2013 • Effective und risk minized operation of pre-stressing works due to dection in time (spalling and overstressing may lead to damage of structure and personal) • Full scale documentation and detection of area with insufficient pre-stressing (Intervention) • Amortisation of initial cost due to shortage of time for pre-stressing works. • System is now fully developed (after 10 km) and can be rented !!!!!!!!! ContraPro  (Higher initial investment for monitoring system)  Qualified und experienced personal necessary for set up and monitoring  Intense work preparation  Pre-stressed pressure tunnels work!  Combined grouting / deformation (full face) is the key to success  Full face monitoring is valuable for geotechnical monitoring and data interpretation and documentation for owner  In time decision making , no delays (costs) Conclusion Lessons learnt
  • 66. Cycle de conférences LCH 2013 Operation Supervisor Shift Engineer Foreman Technicans Pumps Operator Pumps Design & Monitoring P.P-S.C.L. Experienced design team Geotechnical Eng. on site Mechatronics Mechatronics Electricians Software Engineers Lessons learnt