BEST IN CLASS PERFORMANCE
KCS ACADEMY
CAPM / PMP EXAM PREP COURSE
TRANSFORMING ORGANIZATIONS FROM WITHIN
KCS ACADEMY CAPM / PMP EXAM PREP COURSE
COURSE ADMINISTRATION
 COURSE OBJECTIVES
 CAPM & PMP TEST
PREPARATION
 LEARNING THE:
 INPUTS,
 TOOLS & TECHNIQUES,
 OUTPUTS
 THAT ARE FOUND IN A
GUIDE TO THE PROJECT
MANAGEMENT BODY OF
KNOWLEDGE, (PMBOK)
5TH EDITION, PROJECT
MANAGEMENT
INSTITUTE, Inc., 2013
 C
 COURSE ATTENDEES
 THIS COURSE IS
INTENDED FOR
EXPERIENCED AND
PRACTICING
CANDIDATES
 2 YEARS OF PROJECT
MANAGEMENT
EXPERIENCE
 PMP CANDIDATES
SHOULD HAVE 3 YEARS
OF DOCUMENTED WORK
EXPERIENCE
 CANDIDATES MUST BE
PREPARED TO RECEIVE
35 HOURS OF DETAILED
INSTRUCTION
 ABOUT THE
CURRICULUM
 THIS CURRICULUM IS
INTENDED FOR USE
WITH THE PMBOK 5TH
EDITION
 THE WORKBOOK AND
TRAINER SLIDE DECK
ARE INTEGRATED WITH
QUIZZES, EXERCISES,
HOMEWORK AND MOCK
EXAMS
 EACH CANDIDATE WILL
RECEIVE A COPY OF THE
WORKBOOK, CHAPTER
QUIZZES, FLASH CARDS,
AND 2 PRACTICE EXAMS
KCS ACADEMY CAPM / PMP EXAM PREP COURSE
DAY 1
FUNDAMENTALS
DAY 2
MATH SKILLS
DAY 3
SOFT SKILLS
COURSE AGENDA
 INTRODUCTIONS
 COURSE AGENDA
 CHAPTER 1
 CHAPTER 2
 CHAPTER 3
 LUNCH
 CHAPTER 4
 CHAPTER 5
 QUIZ #1
 QUIZ REVIEW
 CHAPTER 6
 CRITICAL PATH
 CHAPTER 7
 LUNCH
 EVM EXERCISES
 CHAPTER 8
 HW OVERVIEW
 QUIZ #2
 QUIZ REVIEW
 HW REVIEW
 CHAPTER 9
 CHAPTER 10
 LUNCH
 CHAPTER 12
 CHAPTER 13
 HW OVERVIEW
 HW REVIEW
 CHAPTER 11
 MOCK EXAM
 LUNCH
 MOCK EXAM
REVIEW
 PMI AND
PROMETRIC Q & A
 COURSE CRITIQUE
DAY 4
RISK & MOCK EXAM
KCS ACADEMY CAPM / PMP EXAM PREP COURSE
1.0 WHAT DO THESE (5) SUCCESS FACTORS SAY ABOUT THE KCS REQUIREMENTS FOR CLASS
PARTICIPATION?
2.0 WHAT DO THESE CLASSROOM REQUIREMENTS MEAN TO YOU?
3.0 WHY ARE THESE CLASSROOM REQUIREMENTS NECESSARY TO CREATE AN AWESOME TRAINING
EXPERIENCE?
THE PMP WHISPERER’S 5 POINTS OF LIGHT
PARTICIPATE SUPPORT COLLABORATE EXCHANGE CREATE
KCS ACADEMY CAPM / PMP EXAM PREP COURSE
TELL US A LITTLE ABOUT YOU
NAME
ROLE
COMPANY
LOCATION
INDUSTRY
KCS ACADEMY CAPM / PMP EXAM PREP COURSE
A LITTLE ABOUT YOUR INSTRUCTOR
KCS ACADEMY CAPM / PMP EXAM PREP COURSE
KCS ACADEMY CAPM / PMP EXAM PREP COURSE
1.0 THE INTRODUCTION
2.0 ORGANIZATIONAL
INFLUENCES AND PROJECT
LIFE CYCLE
3.0 PROJECT
MANAGEMENT PROCESSES
PROJECT MANAGEMENT – THE FRAMEWORK
INTRODUCTION OVERVIEW
1.1
PURPOSE OF THE
PMBOK
1.5
RELATIONSHIP
BETWEEN PROJECT
MANAGEMENT,
OPERATIONS
MANAGEMENT AND
ORGANIZATIONAL
STRATEGY
1.6
BUSINESS VALUE
1.2
WHAT IS A
PROJECT?
1.7
ROLE OF THE
PROJECT MANAGER
1.3
WHAT IS PROJECT
MANAGEMEMENT?
1.4
RELATIONSHIPS
AMONG
PORTFOLIO,
PROGRAM,
PROJECT, AND
ORGANIZATIONAL
PROJECT
MANAGEMENT
1.8
PROJECT
MANAGEMENT
BODY OF
KNOWLEDGE
 IT IDENTIFIES THE KNOWLEDGE, SKILLS, TOOLS
AND TECHNIQUES THAT IMPROVE THE
LIKELIHOOD OF ACHIEVING PROJECT SUCCESS
 IT IS A GLOBAL STANDARD FOR PROJECT
MANAGAMENT, THAT IS APPLICABLE TO MOST
PROJECTS, MOST OF THE TIME
 THE PMBOK PROMOTES A COMMON
VOCABULARY AMONGST ITS GLOBAL
PRACTICIONERS ALLOWING PROJECT MANAGERS
TO COMMUNICATE ACROSS BORDERS
 IT CONTAINS ANNEX A1 – THE LIVING
FOUNDATIONAL REFERENCE FOR PMP
DEVELOPMENT PROGRAMS
 ESTABLISHED THE PROJECT MANAGEMENT CODE
OF ETHICS AND PROFESSIONAL CONDUCT TO
ENSURE THE PROFESSION REMAINS ETHICALLY
AND MORALLY SOUND WITHIN IT’S 4 PILLARS OF:
 RESPONSIBILITY
 FAIRNESS
 RESPECT
 HONESTY
1.1 PURPOSE OF THE PMBOK GUIDE
1.1 PURPOSE OF THE PMBOK GUIDE
 WHAT IS THE PMBOK REFERENCE FOR THE
PROFESSIONAL DEVELOPMENT OF PROJECT
MANAGERS?
 WHAT IS THE VALUE OFA COMMON VOCABULARY
IN PROJECT MANAGEMENT?
 WHY DOES THE PROJECT MANAGEMENT
PROFESSION NEED A CODE OF ETHICS AND
PROFESSIONAL CONDUCT?
 WHAT ARE THE FOUR CENTRAL PILLARS OF THE
CODE OF ETHICS?
 WHAT IS THE DIFFERENCE BETWEEN GOOD
PRACTICE AND BEST PRACTICE?
1.1 PURPOSE OF THE PMBOK GUIDE
 NOTES
 PROJECTS ARE:
 TEMPORARY
 PROJECTS END WHEN:
 PROJECT OBJECTIVES ARE MET
 THE PROJECT IS TERMINANTED
 THE CUSTOMER’S NEEDS ARE FULFILLED
 UNIQUE
 PRODUCT
 SERVICE
 RESULT – RESEARCH & DEVELOPMENT /
PROTOTYPE / CONCEPT / CAN BE
CONDUCTED TO GENERATE A
DELIVERABLE THAT ELICITS AN EMOTION
 TWO TYPES OF PROGRESSIVE
ELABORATION
 ROLLING WAVE PLANNING
 WATERFALL
1.2 WHAT IS A PROJECT?
1.2 WHAT IS A PROJECT?
 WHAT DOES TEMPORARY MEAN?
 WHY ARE ALL PROJECTS CONSIDERED
UNIQUE UNDERTAKINGS?
 WHAT IS THE DIFFERENCE BETWEEN THE
TWO PROGRESSIVE ELABORATION
TECHNIQUES OF WATERFALL METHOD AND
ROLLING WAVE PLANNING?
 WHO HAS THE AUTHORITY TO TERMINATE
A PROJECT?
 NOTES
1.2 WHAT IS A PROJECT?
 STRATEGIC PLAN
 THE COMPILATION OFAN ORGANIZATION’S
MISSION, VISION, VALUES & PURPOSE
 THE STRATEGIC PLAN INCLUDES
ORGANIZATIONAL
 GOALS
 OBJECTIVES WHICH SUPPORT REACHING THE
GOALS
 STEPS REQUIRED TO MEET THE OBJECTIVES
 PORTFOLIO(S)
 THE LINK BETWEEN THE WORK OF THE
ORGANIZATION AND THE ORGANIZATIONS
STRATEGIC PLAN
 THE PORTFOLIO(S) EQUAL(S) THE TOTAL
BUSINESS VALUE OF THE ORGANIZATION
 OPERATIONS, SUPPORT, AND OVERHEAD
 ASSETS AND LIABILITIES
 PROGRAMS, SUB-PROGRAMS
 PROJECTS, SUB-PROJECTS
1.2.1 THE RELATIONSHIPS AMONG PORTFOLIOS, PROGRAMS, AND PROJECTS
1.2.1 THE RELATIONSHIPS AMONGST PORTFOLIOS, PROGRAMS, AND PROJECTS
 WHY IS THE STRATEGIC PLAN CONSIDERED THE
FORECAST OFAN ORGANIZATIONS FOCUS OF
EFFORT FOR A GIVEN TIME PERIOD?
 ARE PORTFOLIOS REQUIRED TO BE
INTERDEPENDENT AND/OR INTERRELATED? IF SO
WHY?
 WHO IS RESPONSBILE FOR THE PERFORMANCE
OF THE STRATEGIC PLAN?
 DESCRIBE THE BUSINESS RELATIONSHIPS
BETWEEN AN ORGANIZATIONS, PORTFOLIO(S),
PROGRAMS, AND PROJECTS?
 NOTES
1.2.1 THE RELATIONSHIPS AMONG, PORTFOLIOS, PROGRAMS, AND PROJECTS
 THE APPLICATION OF THE PMBOK’S KNOWLEDGE,
SKILLS, TOOLS, & TECHNIQUES TO PRODUCE
DELIVERABLES THAT MEET THE PROJECT
REQUIREMENTS
 THE ROLE OF INTEGRATION
 UTILIZING THE PMBOK’S (5) PROCESS GROUPS,
(10) KNOWLEDGE AREAS, & (47) TAILORABLE
PROCESSES TO EFFECTIVELY MANAGE PROJECTS
 PROJECT MANAGEMENT INCLUDES:
 IDENTIFYING REQUIREMENTS
 DETERMINING STAKEHOLDER NEEDS,
CONCERNS, EXPECTATIONS, AND PERSONALITIES
 EXERCISING EFFECTIVE COMMUNICATIONS
MANAGEMENT
 RESPONSIVE AND EFFECTIVE STAKEHOLDER
ENGAGEMENT AND MANAGEMENT
 BALANCING THE ENHANCED CONSTRAINTS OF
SCOPE, SCHEDULE, COST, RISK, RESOURCES, AND
QUALITY
 ACHIEVING EFFECTIVE CHANGE MANAGEMENT
1.3 WHAT IS PROJECT MANAGEMENT?
1.3 WHAT IS PROJECT MANAGEMENT?
 WHY IS IT IMPORTANT FOR THE PROJECT
MANAGER TO UNDERSTAND THE PMBOK
METHODOLOGY, HOW TO EMPLOY THE
METHODOLOGY, AND HOW TO USE IT TO GUIDE A
TEAM AND AN ORGANIZATION TO AN
APPROPRIATE PROJECT ENDING?
 ARE PROJECT CONSTRAINTS LIMITERS OR
BARRIERS?
 WHY DOES PMI PERMIT TAILORING OF THE 47
PMBOK PROCESSES?
 IN WHAT WAYS DOES A PROJECT MANAGER
INTEGRATE WITHIN HIS/HER PROJECT?
 NOTES
1.3 WHAT IS PROJECT MANAGEMENT?
1.4 RELATIONSHIPS AMONG PORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT,
PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT
 THE SIMILARITIES AMONG THE DISCIPLINES
 THE (3) DISCIPLINES ARE ALIGNED WITH OR
DRIVEN BY ORGANIZATIONAL STRATEGIES
 THE DIFFERENCES AMONG THE DISCIPLINES
 THE WAY EACH DISCIPLINE CONTRIBUTES TO THE
ACHIEVEMENT OF STRATEGIC GOALS
 PORTFOLIO MANAGEMENT ALIGNS TO
ORGANIZATIONAL STRATEGY BY:
 SELECTING THE RIGHT PROGRAMS OR PROJECTS
 PRIORITIZING THE WORK
 PROVIDING THE NECESSARY RESOURCES
 PROGRAM MANAGEMENT ALIGNS WITH
ORGANIZATIONAL STRATEGY BY:
 HARMONIZING IT’S PROJECT AND PROGRAM
COMPONENTS
 CONTROLLING INTERDEPENDENCIES IN ORDER
TO REALIZE SPECIFIC BENEFITS
1.4 RELATIOSHIPS AMONG PORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT,
PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT
 PROJECT MANAGEMENT ALIGNS WITH
ORGANIZATIONAL STRATEGY BY:
 DEVELOPING AND IMPLEMENTING PROJECT
MANAGEMENT PLANS THAT ACHIEVE A SPECIFIC
SCOPE
 UNDERSTANDING THAT PROJECT SCOPE IS
DRIVEN BY THE PROGRAM OR PORTFOLIO
OBJECTIVES
 THE RELATIONSHIP IT SHARES WITH PROGRAMS
AND/OR PORTFOLIOS
 OPM ADVANCES ORGANIZATIONAL CAPABILITIES
BY:
 LINKING PORTFOLIO, PROGRAM, AND PROJECT
MANAGEMENT PRINCIPLES AND PRACTICES WITH
ORGANIZATIONAL GOVERNANCE AND STRATEGY
 UTILIZES CONTINUOUS IMPROVEMENT TO DRIVE
THE ORGANIZATION TOWARDS THE
ACHIEVEMENT OF BEST IN INDUSTRY STATUS
1.4 RELATIONSHIPS AMONGST PORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT,
PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT
 WHAT ARE SOME OF THE SIMILARITIES AMONG
THE THREE DISCIPLINES?
 WHAT ARE SOME OF THE DIFFERENCES AMONG
THE THREE DISCIPLINES?
 HOW DO THE DISCIPLINES RELATE TO OPM?
 WHAT IS OPM?
 WHAT IS THE GOAL OF OPM?
 NOTES
1.4 RELATIONSHIPS AMONGST PORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT,
PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT
1.4.1 PROGRAM MANAGEMENT
 PROGRAM MANAGEMENT IS:
 REALIZING THE BENEFITS AND LEVEL OF
CONTROL THAT IS FOUND IN THE
SIMULTANEOUS MANAGEMENT OF SIMILAR
PROJECTS
 PROGRAM MANAGEMENT:
 THE PROJECTS WITHIN A PROGRAM ARE
RELATED THROUGH A COMMON OUTCOME OR
COLLECTIVE CAPABILITY
 PROGRAM MANAGEMENT LEADS TO THE TIMELY
RESOLUTION OF RESOURCE CONSTRAINTS
AND/OR CONFLICT
 ALIGNS PROGRAM GOALS AND OBJECTIVES WITH
THE ORGANIZATIONAL STRATEGIC DIRECTION
 RESOLVES ISSUES AND CHANGE MANAGEMENT
DISAGREEMENTS WITHIN A SHARED
GOVERNANCE STRUCTURE
1.4.1 PROGRAM MANAGEMENT
 WHAT IS THE DEFINITION OFA PROGRAM?
 WHAT MUST A PROGRAM ALWAYS HAVE?
 PROGRAM MANAGEMENT IS THE APPLICATION
OF?
 PROJECTS IN A PROGRAM ARE RELATED
THROUGH?
 WHAT ARE SOME OF THE ACTIONS OF PROGRAM
MANAGEMENT REGARDING PROJECT
INTERDEPENDENCIES?
 NOTES
1.4.1 PROGRAM MANAGEMENT
 PORTFOLIO MANAGEMENT REFERS TO:
 THE CENTRALIZED MANAGEMENT OF ONE OR
MORE PORTFOLIOS TO ACHIEVE AN
ORGANIZATIONS STRATEGIC OBJECTIVES
 REVIEWING ALL PROJECTS AND PROGRAMS IN
ORDER TO PRIORITIZE RESOURCE ALLOCATIONS
FOR THE GREATEST OPTIMIZATION
 MAINTAINING ALIGNMENT BETWEEN THE
PORTFOLIO(S) AND ORGANIZATIONAL
STRATEGIES
 INCLUDES PROJECTS, PROGRAMS, SUB-
PROJECTS, SUB-PROGRAMS, OPERATIONS,
SUPPORT, INVESTMENTS, CASH FLOW, AND
OVERHEAD
 THE FACT IS THERE ARE NO REQUIREMENTS FOR
PORTFOLIOS TO BE INTERRELATED OR
INTERDEPENDENT
 THE INTEGRATION OF MULTIPLE PORTFOLIOS
UNDER A SINGLE CORPORATE GOVERNANCE
STRUCTURE IS DEFINED AS THE ORGANIZATIONS
ENTERPRISE PORTFOLIO
1.4.2 PORTFOLIO MANAGEMENT
1.4.2 PORTFOLIO MANAGEMENT
 WHAT IS THE DEFINITION OF PORTFOLIO
MANAGEMENT?
 WHAT ARE THE BENEFITS OF HAVING A
DIVERSIFIED PORTFOLIO?
 WHAT DOES THE ENTERPRISE PORTFOLIO
CONSIST OF?
 WHAT DOES PORTFOLIO MANAGEMENT FOCUS
ON?
 NOTES
1.4.2 PORTFOLIO MANAGEMENT
 PROJECTS ARE UTILIZED TO DIRECTLY OR
INDIRECTLY ACHIEVE STRATEGIC OBJECTIVES
AND CONTRIBUTE TO:
 THE BENEFITS OFA PROGRAM
 OBJECTIVES OF THE PORTFOLIO
 THE STRATEGIC PLAN
 THE MOST COMMON STRATEGIC CONSIDERATION
FOR THE EXISTENCE OFA PROJECT IS:
 A CUSTOMER REQUEST
 PROJECTS PROVIDE FEEDBACK TO PROGRAMS
AND PORTFOLIOS THROUGH:
 PERFORMANCE, CHANGES, AND LESSONS
LEARNED
 THE STRATGIC PLAN IS THE PRIMARY DRIVER OF
ORGANIZATIONAL INVESTMENTS
1.4.3 PROJECTS AND STRATEGIC PLANNING
1.4.3 PROJECTS AND STRATEGIC PLANNING
 WHAT ARE PROJECTS USED TO ACHIEVE?
 WHAT ARE SOME OF THE REASONS WHY
PROJECTS ARE AUTHORIZED?
 PROJECTS WITHIN PROGRAMS CAN CONTRIBUTE
TO?
 PORTFOLIOS SHOULD PRIORITIZE WHAT TYPES
OF PROJECTS?
 THE ORGANIZATIONS STRATEGIC PLAN BECOMES
THE PRIMARY DRIVER OF?
 NOTES
1.4.3 PROJECTS AND STRATEGIC PLANNING
THE PMO:
 ESTABLISHES PROGRAM AND PROJECT
MANAGEMENT POLICIES & PROCEDURES
 STANDARDIZES THE PROJECT GOVERNANCE
PROCESSES
 FACILITATES THE SHARING OF:
 RESOURCES
 MULTIPLE METHODOLOGIES
 TOOLS & TECHNIQUES
 PMI IDENTIFIES (3) TYPES OF PMO STRUCTURES:
 DIRECTIVE
 CONTROLLING
 SUPPORTIVE
 THE PMO IS OFTEN A NATURAL LIASION FOR
PROJECTS AND PROGRAMS
 THE PMO LEADERSHIP IS A KEY STAKEHOLDER &
DECISION MAKER
1.4.4 PROJECT MANAGEMENT OFFICE
1.4.4 PROJECT MANAGEMENT OFFICE
 WHAT DOES THE PMO STANDARDIZE?
 WHAT ARE THE THREE TYPES OF PMO’S?
 THE PMO IS THE LIASION BETWEEN THE
ORGANIZATIONS ________________________?
 DOES THE PMO REQUIRE PROJECTS TO BE
INTERRELATED AND INTERDEPENDENT IN ORDER
FOR IT TO SUPPORT THEM?
 DOES THE PMO HAVE THE AUTHORITY TO ACT AS
A STAKEHOLDER OR DECISION MAKER DURING
THE PROJECTS LIFE CYCLE?
 NOTES
1.4.4 PROJECT MANAGEMENT OFFICE
 OPERATIONS MANAGEMENT IS RESPONSIBLE
FOR:
 OVERSEEING BUSINESS OPERATIONS
 DIRECTING BUSINESS OPERATIONS
 CONTROLLING BUSINESS OPERATIONS
 OPERATIONS:
 SUPPORT THE DAY-TO-DAY BUSINESS NEEDS
 ARE NECESSARY TO ACHIEVE STRATEGIC AND
TACTICAL BUSINESS OBJECTIVES
 SUPPORT PROJECTS IN ACHIEVING
ORGANIZATIONAL GOALS:
 MAINTAINS ALIGNMENT WITH ORGANIZATIONAL
STRATEGY
 INTEGRAL COMPONENT FOR ACHIEVING
STRATEGIC BUSINESS INITIATIVES
1.5 RELATIOSHIP BETWEEN PROJECT MANAGEMENT, OPERATIONS MANAGEMENT,
AND ORGANIZATIONAL STRATEGY
1.5 RELATIOSHIP BETWEEN PROJECT MANAGEMENT, OPERATIONS MANAGEMENT,
AND ORGANIZATIONAL STRATEGY
 WHAT ARE THE OBJECTIVES OF OPERATIONS
MANAGEMENT?
 WHAT ARE SOME EXAMPLES OF OPERATIONS
MANAGEMENT?
 DESCRIBE A WAY IN WHICH OPERATIONS
MANAGEMENT AND PROJECTS INTERSECT?
 WHAT ARE SOME OF THE ELEMENTS OF
OPERATIONS?
 NOTES
1.5 RELATIONSHIP BETWEEN PROJECT MANAGEMENT, OPERATIONS MANAGEMENT,
AND ORGANIZATIONAL STRATEGY
 PROJECTS ARE OFTEN CONDUCTED WHEN
SUBSTANTIAL CHANGES ARE BEING MADE TO
BUSINESS OPERATIONS AND:
 INTRODUCING NEW PRODUCTS
 INTRODUCING NEW SERVICES
 KEY POINTS OF INTERSECTIONS BETWEEN
PROJECTS AND OPERATIONS OCCUR WHEN:
 SIGNIFICANT IMPROVEMENTS ARE MADE TO
OPERATIONS
 DELIVERABLES ARE TRANSFERRED TO
OPERATIONAL CONTROL
 CUSTOMERS PURCHASE BACK-END DELIVERABLE
SUPPORT
 DEVELOPING A NEW PRODUCT
 UPGRADING AN EXISTING PRODUCT
 EXPANDING OUTPUT VELOCITY OR CAPACITY
1.5.1 OPERATIONS AND PROJECT MANAGEMENT
1.5.1 OPERATIONS AND PROJECT MANAGEMENT
 HOW DO PROJECTS AID IN MAKING CHANGES TO
BUSINESS OPERATIONS?
 DOES OPERATIONS MANAGEMENT FALL WITHIN
THE SCOPE OF PROJECT MANAGEMENT?
 WHAT ARE SOME COMMON POINTS OF
INTERSECTION BETWEEN PROJECTS AND
OPERATIONS?
 WHAT COULD BE TRANSFERRED TO OPERATIONS
AS A PROJECT NEARS THE CLOSURE PHASE?
 NOTES
1.5.1 OPERATIONS AND PROJECT MANAGEMENT
 OPERATIONS MANAGEMENT AND OPERATIONS:
 OPERATIONS MANAGEMENT FALLS OUTSIDE THE
GOVERNANCE OF PROJECT MANAGEMENT
 OPERATIONS ARE PROCESS DRIVEN AND FOCUSED
ON THE PRODUCTION OR MANUFACTURING OF
GOODS AND SERVICES AND/OR THE DAY-TO-DAY
NEEDS OF THE ORGANIZATION
 OPERATIONS ARE CONCERNED WITH
CONTINUOUS IMPROVEMENT, RESOURCE
OPTIMIZATION, AND MEETING CUSTOMER
DEMANDS:
 SIPOC
 SUPPLIES
 INPUTS
 PROCESSES
 OUTPUTS
 CUSTOMERS
1.5.1.1 OPERATIONS MANAGEMENT
1.5.1.1 OPERATIONS MANAGEMENT
 WHY DOES OPERATIONS MANAGEMENT FALL
OUTSIDE THE SCOPE OF PROJECT MANAGEMENT?
 WHAT IS OPERATIONS MANAGEMENT PRIMARILY
CONCERNED WITH?
 OPERATIONS MANAGEMENT INVOLVES?
 NOTES
1.5.1.1 OPERATIONS MANAGEMENT
 OPERATIONAL STAKEHOLDERS SHOULD BE
INCLUDED IN EVERY PHASE OF THE PROJECT
LIFECYCLE. THIS WILL:
 LEAD TO GAINS IN INSIGHT
 HELP PREVENT UNNECESSARY ISSUES
 OPERATIONAL MANAGERS ARE KEY
STAKEHOLDERS AND SHOULD BE CONSIDERED
WHEN:
 IDENTIFYING STAKEHOLDERS
 IDENTIFYING PROJECT RISKS
 ASSESSING IMPORTANT PROJECT
CONSIDERATIONS
 ASSESSING THE AFFECTS OF FUTURE WORK AND
ENDEAVORS
1.5.1.2 OPERATIONAL STAKEHOLDERS IN PROJECT MANAGEMENT
1.5.1.2 OPERATIONALSTAKEHOLDERS IN PROJECT MANAGEMENT
 ARE THE NEEDS OF OPERATIONS MANAGEMENT
STAKEHOLDERS IMPORTANT TO CONSIDER WHEN
THE PROJECT HAS A DIRECT IMPACT ON THEIR
FUTURE WORK OR ENDEAVORS? WHY?
 DOES INCLUDING APPROPRIATE OPERATIONS
MANAGEMENT STAKEHOLDERS IN ALL PHASES OF
THE PROJECT YIELD ANY NOTICABLE PROJECT
BENEFITS?
 WHEN ARE UNNECESSARY ISSUES CREATED
BETWEEN OPERATIONS AND PROJECT
MANAGEMENT?
 WHY IS IT MORE DIFFICULT TO BASH A PLAN YOU
PLAYED A ROLE IN DEVELOPING?
 NOTES
1.5.1.2 OPERATIONALSTAKEHOLDERS IN PROJECT MANAGEMENT
 ORGANIZATIONAL GOVERNANCE
 GOVERNANCE PROVIDES STRATEGIC DIRECTION
AND PERFORMANCE PARAMETERS
 STRATEGIC DIRECTION PROVIDES PURPOSE,
GOALS, AND ACTIONS
 GOVERNANCE ESTABLISHES ALIGNMENT
BETWEEN PROJECT MANAGEMENT ACTIVITIES
AND BUSINESS DIRECTION
 ACKNOWLEDGING THAT CHANGES IN
OBJECTIVES AFFECT PROJECT EFFICIENCY AND
SUCCESS
 CONSTANT ALIGNMENT INCREASES THE
PROBABILITY OF PROJECT SUCCESS
1.5.2 ORGANIZATIONS AND PROJECT MANAGEMENT
1.5.2 ORGANIZATIONS AND PROJECT MANAGEMENT
 WHY DO ORGANIZATIONS USE GOVERNANCE?
 WHAT DOES STRATEGIC DIRECTION PROVIDE TO
THE ORGANIZATION?
 WHY IS IT IMPORTANT FOR THE PROJECT TO
REMAIN IN ALIGNMENT WITH TOP-LEVEL
BUSINESS DIRECTION?
 IN WHAT WAY DOES A CHANGE IN PROJECT
OBJECTIVES AFFECT EFFICIENCY AND SUCCESS?
 DOES STRATEGIC ALIGNMENT INCREASE OR
DECREASE THE ODDS OF SUCCESS?
 NOTES
1.5.2 ORGANIZATIONS AND PROJECT MANAGEMENT
 PBO’S:
 UTILIZE TEMPORARY ORGANIZATIONAL
SYSTEMS TO EXECUTE THE PROJECT WORK OF
THE ORGANIZATION
 DIMINISH THE IMPACT OF ORGANIZATIONAL
POLITICS BECAUSE THE DELIVERABLE IS THE
ONLY MEASUREMENT OF SUCCESS
 UTILIZE PROJECTS AND/OR PROJECT
MANAGEMENT FUNDAMENTALS TO CONDUCT
THE MAJORITY OF IT’S BUSINESS
 CAN TAKE THE FORM OFA FIRM, COLLECTION
OF FIRMS, OR NETWORKS
1.5.2.1 PROJECT-BASED ORGANIZATIONS (PBO’S)
1.5.2.1 PROJECT-BASED ORGANIZATIONS
 PBO’S REFER TO TEMPORARY ORGANIZATIONAL
STRUCTURES THAT CREATE?
 IN THE PBO THE SUCCESS OF THE PROJECT IS
MEASURED BY?
 WHAT TYPES OF ORGANIZATIONS MIGHT EMPLOY
THE USE OFA PBO?
 NOTES
1.5.2.1 PROJECT-BASED ORGANIZATIONS
 GOVERNANCE:
 PROGRAMS AND PROJECTS ARE UTILIZED TO
ACHIEVE STRATEGIC BUSINESS GOALS
 FORMAL ORGANIZATIONAL GOVERNANCE
CAN IMPOSE CONSTRAINTS ON PROJECTS
 PROJECT SUCCESS IS PARTLY MEASURED BY
THE SUCCESS OF THE PROJECT IN IT’S
RESPONSE TO ORGANIZATIONAL
GOVERNANCE
 THE PROJECT MANAGER MUST BE AWARE OF
THE IMPACT OF CORPORATE OR
ORGANIZATIONAL POLICIES AND
PROCEDURES ON THEIR PROJECTS
1.5.2.2 THE LINK BETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL
GOVERNANCE
1.5.2.2 THE LINK BETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL
GOVERNANCE
 SHOULD ORGANIZATIONS THAT UTILIZE
PROJECTS TO DRIVE STRATEGIC OUTCOMES
ALSO ESTABLISH ORGANIZATIONAL
GOVERNANCE PROCESSES AND PROCEDURES?
 GIVE AN EXAMPLE WHERE ORGANIZATIONAL
GOVERNANCE MIGHT IMPOSE CONSTRAINTS ON
THE PROJECT?
 WHY IS IT IMPORTANT FOR PROJECT MANAGERS
TO BE AWARE OF CORPORATE AND/OR
ORGANIZATIONAL GOVERNANCE POLICIES AND
PROCEDURES?
 NOTES
1.5.2.2 THE LINK BETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL
GOVERNANCE
 ORGANIZATIONAL STRATEGY
 ORGANIZATIONAL STRATEGY PROVIDES
GUIDANCE AND DIRECTION TO PROJECT
MANAGEMENT
 PROJECTS EXIST TO SUPPORT ORGANIZATIONAL
STRATEGY
 THE SPONSOR, PORTFOLIO MANAGER, OR
PROGRAM MANAGER ARE RESPONSIBLE FOR
IDENTIFYING ALIGMENT AS WELLAS POTENTIAL
CONFLICTS BETWEEN THE STRATEGIC PLAN AND
PROJECTS
 IT IS THE RESPONSIBILITY OF THE PROJECT
MANAGER TO IDENTIFY AND DOCUMENT
CONFLICTS WITH ESTABLISHED
ORGANIZATIONAL STRATEGIES
 DEVELOPMENT OFAN ORGANIZATIONAL
STRATEGY COULD BE THE OUTPUT OFA PROJECT
(SUSTAINABILITY)
1.5.2.3 THE RELATIONSHIP BETWEEN PROJECT MANAGEMENT AND
ORGANIZATIONAL STRATEGY
1.5.2.3 THE RELATIONSHIP BETWEEN PROJECT MANAGEMENT AND
ORGANIZATIONAL STRATEGY
 ARE GUIDANCE AND DIRECTION THE ONLY
OBJECTIVES OF ORGANIZATIONAL STRATEGY?
 WHO IS RESPONSIBLE FOR IDENTIFYING PROJECT
ALIGNMENT WITH ORGANIZATIONAL STRATEGY?
 WHO IS REAPONSBILE FOR IDENTIFYING
CONFLICTS WITH ORGANIZATIONAL STRATEGY?
 CAN DEVELOPMENT OF ORGANIZATIONAL
STRATEGY BE THE GOAL OFA PROJECT?
 NOTES
1.5.2.3 THE RELATIONSHIP BETWEEN PROJECT MANAGEMENT AND
ORGANIZATONAL STRATEGY
 BUSINESS VALUE
 BUSINESS VALUE IS UNIQUE TO EVERY
ORGANIZATION
 IT IS THE TOTAL VALUE OF THE ORGANIZATION
 THE SUM OFALL TANGIBLE AND INTANGIBLE
ELEMENTS
 BUSINESS VALUE SCOPE CAN BE ASSESSED SHORT,
MEDIUM OR LONG TERM
 BUSINESS VALUE FOCUSES ON THE EMPLOYMENT
OF EFFICIENT PROCESSES TO MEET STRATEGIC
OBJECTIVES
 BUSINESS VALUE IS DERIVED FROM THE
COLLECTIVE USE OF STRATEGIC PLANNING,
PORTFOLIO, PROGRAM, PROJECT, AND
OPERATIONS MANAGEMENT, ALONG WITH
SUPPORT ACTVITIES, OVERHEAD, INVESTMENTS,
AND REVENUE MANAGEMENT ACTIVITIES
1.6 BUSINESS VALUE
1.6 BUSINESS VALUE
 WHAT IS THE DEFINITION OF BUSINESS VALUE?
 WHAT ARE EXAMPLES OF TANGIBLE ASSETS?
 WHAT ARE SOME EXAMPLES OF INTANGIBLE
ASSETS?
 CAN BUSINESS VALUE SCOPE FALL INTO SHORT,
MEDIUM, OR LONG-TERM TIME FRAMES?
 CAN BUSINESS VALUE BE CREATED THROUGH
EFFICIENT MANAGEMENT?
 DOES THE EFFECTIVE USE OF PROJECT,
PROGRAM, AND PORTFOLIO MANAGEMENT LEAD
TO INCREASED VALUE FROM PROJECT
INVESTMENTS?
 ALL FORMAL ORGANIZATIONS THAT CONDUCT
BUSINESS-RELATED ACTIVITIES FOCUS ON
ATTAINING GREATER BUSINESS VALUE
 NOTES
1.6 BUSINESS VALUE
 THE PROJECT MANAGER ROLE
 THE INDIVIDUAL ASSIGNED BY THE
ORGANIZATION TO LEAD A TEAM IN CREATING A
DELIVERABLE THAT MEETS PROJECT
REQUIREMENTS
 A PROJECT MANAGER MAY REPORT TO A
FUNCTIONAL MANAGER, PROGRAM MANAGER,
PMO, OR PORTFOLIO MANAGER
 THE PROJECT MANAGER IS RESPONSIBLE FOR
MAINTAINING ALIGNMENT WITH
ORGANIZATIONAL STRATEGIES
 THE PROJECT MANAGER ALSO COLLABORATES,
COORDINATES, AND COMMUNICATES WITH
OPERATIONAL, SUPPORT, EXPERT, AND
CONSULTANT PERSONNEL
1.7 ROLE OF THE PROJECT MANAGER
1.7 ROLE OF THE PROJECT MANAGER
 HOW DO PROJECT MANAGERS DIFFER FROM
OPERATIONS OR FUNCTIONAL MANAGERS?
 IN WHICH ORGANIZATIONAL STRUCTURES MIGHT
A PROJECT MANAGER REPORT TO A FUNCTIONAL
MANAGER?
 IN WHAT BUSINESS STRUCTURE MIGHT A
PROJECT MANAGER REPORT TO A PROGRAM OR
PORTFOLIO MANAGER?
 NAME OTHER BUSINESS ROLES THE PROJECT
MANAGER MIGHT NEED TO COLLABORATE WITH?
 NOTES
1.7 ROLE OF THE PROJECT MANAGER
 THE GENERAL RESPONSIILITY OF THE PROJECT
MANAGER IS
 TO SATISFY THE NEEDS OF THE TEAM, CUSTOMER,
SPONSOR, AND KEY STAKEHOLDERS NEEDS:
 TASK RELATED
 INDIVIDUAL NEEDS
 TASK NEEDS
 TEAM NEEDS
 PROJECT MANAGERS MUST POSSESS:
 INDUSTRY AND PROJECT MANAGEMENT
KNOWLEDGE
 A HISTORY OF SUSTAINED EXCEPTIONAL
PERFORMANCE
 EXEMPLARY PROFESSIONAL CONDUCT THAT IS
FUELED BY ETHICALAND SOUND DECISION
MAKING
 THE RIGHT INTERPERSONAL SKILLS (THE ART)
 THE APPROPRIATE MANAGEMENT SKILLS (THE
SCIENCE)
1.7.1 RESPONSIBILITIES AND COMPETENCIES OF THE PROJECT MANAGER
1.7.1 RESPONSIBILITIES AND COMPETENCIES OF THE PROJECT MANAGER
 WHAT ARE SOME OF THE GENERAL
RESPONSIBLITIES OFA PROJECT MANAGER?
 IS THE PROJECT MANAGER THE LINK BETWEEN
THE PROJECT TEAM AND THE PROJECT
MANAGEMENT METHODOLOGY?
 IN ADDITION TO THE APPLICATION OF
KNOWLEDGE, TOOLS, AND TECHNIQUES, PROJECT
MANAGERS MUST ALSO POSSESS THE FOLLOWING
COMPETENCIES?
 -----------------------------------------------------------------------
 -----------------------------------------------------------------------
 -----------------------------------------------------------------------
 NOTES
1.7.1 RESPONSIBILITIES AND COMPETENCIES OF THE PROJECT MANAGER
 PROJECT MANAGERS ACCOMPLISH TASKS
THROUGH:
 THE WORK OF TEAM MEMBERS AND OTHER KEY
STAKEHOLDERS
 THIS REQUIRES THE PROJECT MANAGER TO:
 BUILD TRUST
 UTILIZE INFLUENCE
 DEMONSTRATE INDUSTRY KNOWLEDGE
 DEMONSTRATE PROJECT MANAGEMENT
EXPERTISE
 UTILIZE EFFECTIVE INTERPERSONAL SKILLS
 UTILIZE EFFECTIVE MANAGEMENT SKILLS
 PROACTIVELY RESPOND TO CONFLICT
 COMMUNICATE EFFECTIVELY
 NEGOTIATE WIN-WIN SOLUTIONS
 INFUSE AND SUATAIN TEAM MOTIVATION
 UTILIZE EFFECTIVE SITUATIONAL LEADERSHIP
1.7.2 INTERPERSONAL SKILLS OF A PROJECT MANAGER
1.7.2 INTERPERSONAL SKILLS OF A PROJECT MANAGER
 EFFECTIVE PROJECT MANAGERS REQUIRE A
BALANCE OF TECHNICAL, INTERPERSONAL, AND
____________________ SKILLS?
 THE PRESENCE OF THESE SKILLS HELP THEM
___________________ SITUATIONS AND
______________ APPROPRIATELY?
 WHAT SECTION OF THE PMBOK SPECIFICALLY
ADDRESSES INTERPERSONAL SKILLS?
 NOTES
1.7.2 INTERPERSONAL SKILLS OF A PROJECT MANAGER
 THE PMBOK CONTAINS:
 PROJECT MANAGEMENT GOOD PRACTICES
 A BODY OF KNOWLEDGE (IT IS NOT A
METHODOLOGY)
 A COMMON VOCABULARY
 PROJECT MANAGEMENT PROCESSES
 THE PROPER INTEGRATION OF PROJECT
MANAGEMENT TO OTHER MANAGEMENT
DISCIPLINES
 ANNEX A1 – THE STANDARD FOR PROJECT
MANAGEMENT OFA PROJECT
 APPENDIX X1 – 5TH EDITION VERSION CHANGES TO
THE PMBOK
 APPENDIX X2 – CONTRIBUTORS AND REVIEWERS
OF THE PMBOK’S CURRENT GUIDE
 APPENDIX X3 – INTERPERSONAL SKILLS
 REFERENCES
 GLOSSARY
 INDEX
1.8 PROJECT MANAGEMENT BODY OF KNOWLEDGE
1.8 PROJECT MANAGEMENT BODY OF KNOWLEDGE
 THE PMBOK CONTAINS THE STANDARD FOR?
MANAGING _________ PROJECTS _________ OF THE
TIME, ACROSS __________ INDUSTRIES
 ANNEX A1 DESCRIBES THE ___________ , AND
TO MANAGE A PROJECT TOWARDS A ____________
_____________ ?
 THE STANDARD IS INTERRELATED TO WHAT
OTHER PROJECT MANAGEMENT DISCIPLINES?
 THE STANDARD IS LIMITED TO __________
PROJECTS?
 NOTES
1.8 PROJECT MANAGEMENT BODY OF KNOWLEDGE
CHAPTER 1 SUMMARY
What are the
components of a
PMBOK Process?
Identify the ten
Knowledge Areas
and their purpose.
Identify the
Process Groups
and define their
purpose.
What is the
purpose of Project
Management?
What is the
purpose of a
Program?
What are
characteristics of a
Portfolio?
What are the
intersecting points
for projects and
operations?
What is a
Strategic Plan?
KCS ACADEMY
Time!!

KCS Academy PMP Exam Prep Course Chapter 1 - Introduction

  • 1.
    BEST IN CLASSPERFORMANCE KCS ACADEMY CAPM / PMP EXAM PREP COURSE TRANSFORMING ORGANIZATIONS FROM WITHIN
  • 2.
    KCS ACADEMY CAPM/ PMP EXAM PREP COURSE COURSE ADMINISTRATION  COURSE OBJECTIVES  CAPM & PMP TEST PREPARATION  LEARNING THE:  INPUTS,  TOOLS & TECHNIQUES,  OUTPUTS  THAT ARE FOUND IN A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE, (PMBOK) 5TH EDITION, PROJECT MANAGEMENT INSTITUTE, Inc., 2013  C  COURSE ATTENDEES  THIS COURSE IS INTENDED FOR EXPERIENCED AND PRACTICING CANDIDATES  2 YEARS OF PROJECT MANAGEMENT EXPERIENCE  PMP CANDIDATES SHOULD HAVE 3 YEARS OF DOCUMENTED WORK EXPERIENCE  CANDIDATES MUST BE PREPARED TO RECEIVE 35 HOURS OF DETAILED INSTRUCTION  ABOUT THE CURRICULUM  THIS CURRICULUM IS INTENDED FOR USE WITH THE PMBOK 5TH EDITION  THE WORKBOOK AND TRAINER SLIDE DECK ARE INTEGRATED WITH QUIZZES, EXERCISES, HOMEWORK AND MOCK EXAMS  EACH CANDIDATE WILL RECEIVE A COPY OF THE WORKBOOK, CHAPTER QUIZZES, FLASH CARDS, AND 2 PRACTICE EXAMS
  • 3.
    KCS ACADEMY CAPM/ PMP EXAM PREP COURSE DAY 1 FUNDAMENTALS DAY 2 MATH SKILLS DAY 3 SOFT SKILLS COURSE AGENDA  INTRODUCTIONS  COURSE AGENDA  CHAPTER 1  CHAPTER 2  CHAPTER 3  LUNCH  CHAPTER 4  CHAPTER 5  QUIZ #1  QUIZ REVIEW  CHAPTER 6  CRITICAL PATH  CHAPTER 7  LUNCH  EVM EXERCISES  CHAPTER 8  HW OVERVIEW  QUIZ #2  QUIZ REVIEW  HW REVIEW  CHAPTER 9  CHAPTER 10  LUNCH  CHAPTER 12  CHAPTER 13  HW OVERVIEW  HW REVIEW  CHAPTER 11  MOCK EXAM  LUNCH  MOCK EXAM REVIEW  PMI AND PROMETRIC Q & A  COURSE CRITIQUE DAY 4 RISK & MOCK EXAM
  • 4.
    KCS ACADEMY CAPM/ PMP EXAM PREP COURSE 1.0 WHAT DO THESE (5) SUCCESS FACTORS SAY ABOUT THE KCS REQUIREMENTS FOR CLASS PARTICIPATION? 2.0 WHAT DO THESE CLASSROOM REQUIREMENTS MEAN TO YOU? 3.0 WHY ARE THESE CLASSROOM REQUIREMENTS NECESSARY TO CREATE AN AWESOME TRAINING EXPERIENCE? THE PMP WHISPERER’S 5 POINTS OF LIGHT PARTICIPATE SUPPORT COLLABORATE EXCHANGE CREATE
  • 5.
    KCS ACADEMY CAPM/ PMP EXAM PREP COURSE TELL US A LITTLE ABOUT YOU NAME ROLE COMPANY LOCATION INDUSTRY
  • 6.
    KCS ACADEMY CAPM/ PMP EXAM PREP COURSE A LITTLE ABOUT YOUR INSTRUCTOR
  • 7.
    KCS ACADEMY CAPM/ PMP EXAM PREP COURSE
  • 8.
    KCS ACADEMY CAPM/ PMP EXAM PREP COURSE 1.0 THE INTRODUCTION 2.0 ORGANIZATIONAL INFLUENCES AND PROJECT LIFE CYCLE 3.0 PROJECT MANAGEMENT PROCESSES PROJECT MANAGEMENT – THE FRAMEWORK
  • 10.
    INTRODUCTION OVERVIEW 1.1 PURPOSE OFTHE PMBOK 1.5 RELATIONSHIP BETWEEN PROJECT MANAGEMENT, OPERATIONS MANAGEMENT AND ORGANIZATIONAL STRATEGY 1.6 BUSINESS VALUE 1.2 WHAT IS A PROJECT? 1.7 ROLE OF THE PROJECT MANAGER 1.3 WHAT IS PROJECT MANAGEMEMENT? 1.4 RELATIONSHIPS AMONG PORTFOLIO, PROGRAM, PROJECT, AND ORGANIZATIONAL PROJECT MANAGEMENT 1.8 PROJECT MANAGEMENT BODY OF KNOWLEDGE
  • 11.
     IT IDENTIFIESTHE KNOWLEDGE, SKILLS, TOOLS AND TECHNIQUES THAT IMPROVE THE LIKELIHOOD OF ACHIEVING PROJECT SUCCESS  IT IS A GLOBAL STANDARD FOR PROJECT MANAGAMENT, THAT IS APPLICABLE TO MOST PROJECTS, MOST OF THE TIME  THE PMBOK PROMOTES A COMMON VOCABULARY AMONGST ITS GLOBAL PRACTICIONERS ALLOWING PROJECT MANAGERS TO COMMUNICATE ACROSS BORDERS  IT CONTAINS ANNEX A1 – THE LIVING FOUNDATIONAL REFERENCE FOR PMP DEVELOPMENT PROGRAMS  ESTABLISHED THE PROJECT MANAGEMENT CODE OF ETHICS AND PROFESSIONAL CONDUCT TO ENSURE THE PROFESSION REMAINS ETHICALLY AND MORALLY SOUND WITHIN IT’S 4 PILLARS OF:  RESPONSIBILITY  FAIRNESS  RESPECT  HONESTY 1.1 PURPOSE OF THE PMBOK GUIDE
  • 12.
    1.1 PURPOSE OFTHE PMBOK GUIDE
  • 13.
     WHAT ISTHE PMBOK REFERENCE FOR THE PROFESSIONAL DEVELOPMENT OF PROJECT MANAGERS?  WHAT IS THE VALUE OFA COMMON VOCABULARY IN PROJECT MANAGEMENT?  WHY DOES THE PROJECT MANAGEMENT PROFESSION NEED A CODE OF ETHICS AND PROFESSIONAL CONDUCT?  WHAT ARE THE FOUR CENTRAL PILLARS OF THE CODE OF ETHICS?  WHAT IS THE DIFFERENCE BETWEEN GOOD PRACTICE AND BEST PRACTICE? 1.1 PURPOSE OF THE PMBOK GUIDE  NOTES
  • 14.
     PROJECTS ARE: TEMPORARY  PROJECTS END WHEN:  PROJECT OBJECTIVES ARE MET  THE PROJECT IS TERMINANTED  THE CUSTOMER’S NEEDS ARE FULFILLED  UNIQUE  PRODUCT  SERVICE  RESULT – RESEARCH & DEVELOPMENT / PROTOTYPE / CONCEPT / CAN BE CONDUCTED TO GENERATE A DELIVERABLE THAT ELICITS AN EMOTION  TWO TYPES OF PROGRESSIVE ELABORATION  ROLLING WAVE PLANNING  WATERFALL 1.2 WHAT IS A PROJECT?
  • 15.
    1.2 WHAT ISA PROJECT?
  • 16.
     WHAT DOESTEMPORARY MEAN?  WHY ARE ALL PROJECTS CONSIDERED UNIQUE UNDERTAKINGS?  WHAT IS THE DIFFERENCE BETWEEN THE TWO PROGRESSIVE ELABORATION TECHNIQUES OF WATERFALL METHOD AND ROLLING WAVE PLANNING?  WHO HAS THE AUTHORITY TO TERMINATE A PROJECT?  NOTES 1.2 WHAT IS A PROJECT?
  • 17.
     STRATEGIC PLAN THE COMPILATION OFAN ORGANIZATION’S MISSION, VISION, VALUES & PURPOSE  THE STRATEGIC PLAN INCLUDES ORGANIZATIONAL  GOALS  OBJECTIVES WHICH SUPPORT REACHING THE GOALS  STEPS REQUIRED TO MEET THE OBJECTIVES  PORTFOLIO(S)  THE LINK BETWEEN THE WORK OF THE ORGANIZATION AND THE ORGANIZATIONS STRATEGIC PLAN  THE PORTFOLIO(S) EQUAL(S) THE TOTAL BUSINESS VALUE OF THE ORGANIZATION  OPERATIONS, SUPPORT, AND OVERHEAD  ASSETS AND LIABILITIES  PROGRAMS, SUB-PROGRAMS  PROJECTS, SUB-PROJECTS 1.2.1 THE RELATIONSHIPS AMONG PORTFOLIOS, PROGRAMS, AND PROJECTS
  • 18.
    1.2.1 THE RELATIONSHIPSAMONGST PORTFOLIOS, PROGRAMS, AND PROJECTS
  • 19.
     WHY ISTHE STRATEGIC PLAN CONSIDERED THE FORECAST OFAN ORGANIZATIONS FOCUS OF EFFORT FOR A GIVEN TIME PERIOD?  ARE PORTFOLIOS REQUIRED TO BE INTERDEPENDENT AND/OR INTERRELATED? IF SO WHY?  WHO IS RESPONSBILE FOR THE PERFORMANCE OF THE STRATEGIC PLAN?  DESCRIBE THE BUSINESS RELATIONSHIPS BETWEEN AN ORGANIZATIONS, PORTFOLIO(S), PROGRAMS, AND PROJECTS?  NOTES 1.2.1 THE RELATIONSHIPS AMONG, PORTFOLIOS, PROGRAMS, AND PROJECTS
  • 20.
     THE APPLICATIONOF THE PMBOK’S KNOWLEDGE, SKILLS, TOOLS, & TECHNIQUES TO PRODUCE DELIVERABLES THAT MEET THE PROJECT REQUIREMENTS  THE ROLE OF INTEGRATION  UTILIZING THE PMBOK’S (5) PROCESS GROUPS, (10) KNOWLEDGE AREAS, & (47) TAILORABLE PROCESSES TO EFFECTIVELY MANAGE PROJECTS  PROJECT MANAGEMENT INCLUDES:  IDENTIFYING REQUIREMENTS  DETERMINING STAKEHOLDER NEEDS, CONCERNS, EXPECTATIONS, AND PERSONALITIES  EXERCISING EFFECTIVE COMMUNICATIONS MANAGEMENT  RESPONSIVE AND EFFECTIVE STAKEHOLDER ENGAGEMENT AND MANAGEMENT  BALANCING THE ENHANCED CONSTRAINTS OF SCOPE, SCHEDULE, COST, RISK, RESOURCES, AND QUALITY  ACHIEVING EFFECTIVE CHANGE MANAGEMENT 1.3 WHAT IS PROJECT MANAGEMENT?
  • 21.
    1.3 WHAT ISPROJECT MANAGEMENT?
  • 22.
     WHY ISIT IMPORTANT FOR THE PROJECT MANAGER TO UNDERSTAND THE PMBOK METHODOLOGY, HOW TO EMPLOY THE METHODOLOGY, AND HOW TO USE IT TO GUIDE A TEAM AND AN ORGANIZATION TO AN APPROPRIATE PROJECT ENDING?  ARE PROJECT CONSTRAINTS LIMITERS OR BARRIERS?  WHY DOES PMI PERMIT TAILORING OF THE 47 PMBOK PROCESSES?  IN WHAT WAYS DOES A PROJECT MANAGER INTEGRATE WITHIN HIS/HER PROJECT?  NOTES 1.3 WHAT IS PROJECT MANAGEMENT?
  • 23.
    1.4 RELATIONSHIPS AMONGPORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT, PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT  THE SIMILARITIES AMONG THE DISCIPLINES  THE (3) DISCIPLINES ARE ALIGNED WITH OR DRIVEN BY ORGANIZATIONAL STRATEGIES  THE DIFFERENCES AMONG THE DISCIPLINES  THE WAY EACH DISCIPLINE CONTRIBUTES TO THE ACHIEVEMENT OF STRATEGIC GOALS  PORTFOLIO MANAGEMENT ALIGNS TO ORGANIZATIONAL STRATEGY BY:  SELECTING THE RIGHT PROGRAMS OR PROJECTS  PRIORITIZING THE WORK  PROVIDING THE NECESSARY RESOURCES  PROGRAM MANAGEMENT ALIGNS WITH ORGANIZATIONAL STRATEGY BY:  HARMONIZING IT’S PROJECT AND PROGRAM COMPONENTS  CONTROLLING INTERDEPENDENCIES IN ORDER TO REALIZE SPECIFIC BENEFITS
  • 24.
    1.4 RELATIOSHIPS AMONGPORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT, PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT  PROJECT MANAGEMENT ALIGNS WITH ORGANIZATIONAL STRATEGY BY:  DEVELOPING AND IMPLEMENTING PROJECT MANAGEMENT PLANS THAT ACHIEVE A SPECIFIC SCOPE  UNDERSTANDING THAT PROJECT SCOPE IS DRIVEN BY THE PROGRAM OR PORTFOLIO OBJECTIVES  THE RELATIONSHIP IT SHARES WITH PROGRAMS AND/OR PORTFOLIOS  OPM ADVANCES ORGANIZATIONAL CAPABILITIES BY:  LINKING PORTFOLIO, PROGRAM, AND PROJECT MANAGEMENT PRINCIPLES AND PRACTICES WITH ORGANIZATIONAL GOVERNANCE AND STRATEGY  UTILIZES CONTINUOUS IMPROVEMENT TO DRIVE THE ORGANIZATION TOWARDS THE ACHIEVEMENT OF BEST IN INDUSTRY STATUS
  • 25.
    1.4 RELATIONSHIPS AMONGSTPORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT, PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT
  • 26.
     WHAT ARESOME OF THE SIMILARITIES AMONG THE THREE DISCIPLINES?  WHAT ARE SOME OF THE DIFFERENCES AMONG THE THREE DISCIPLINES?  HOW DO THE DISCIPLINES RELATE TO OPM?  WHAT IS OPM?  WHAT IS THE GOAL OF OPM?  NOTES 1.4 RELATIONSHIPS AMONGST PORTFOLIO MANAGEMENT, PROGRAM MANAGEMENT, PROJECT MANAGEMENT, AND ORGANIZATIONAL PROJECT MANAGEMENT
  • 27.
    1.4.1 PROGRAM MANAGEMENT PROGRAM MANAGEMENT IS:  REALIZING THE BENEFITS AND LEVEL OF CONTROL THAT IS FOUND IN THE SIMULTANEOUS MANAGEMENT OF SIMILAR PROJECTS  PROGRAM MANAGEMENT:  THE PROJECTS WITHIN A PROGRAM ARE RELATED THROUGH A COMMON OUTCOME OR COLLECTIVE CAPABILITY  PROGRAM MANAGEMENT LEADS TO THE TIMELY RESOLUTION OF RESOURCE CONSTRAINTS AND/OR CONFLICT  ALIGNS PROGRAM GOALS AND OBJECTIVES WITH THE ORGANIZATIONAL STRATEGIC DIRECTION  RESOLVES ISSUES AND CHANGE MANAGEMENT DISAGREEMENTS WITHIN A SHARED GOVERNANCE STRUCTURE
  • 28.
  • 29.
     WHAT ISTHE DEFINITION OFA PROGRAM?  WHAT MUST A PROGRAM ALWAYS HAVE?  PROGRAM MANAGEMENT IS THE APPLICATION OF?  PROJECTS IN A PROGRAM ARE RELATED THROUGH?  WHAT ARE SOME OF THE ACTIONS OF PROGRAM MANAGEMENT REGARDING PROJECT INTERDEPENDENCIES?  NOTES 1.4.1 PROGRAM MANAGEMENT
  • 30.
     PORTFOLIO MANAGEMENTREFERS TO:  THE CENTRALIZED MANAGEMENT OF ONE OR MORE PORTFOLIOS TO ACHIEVE AN ORGANIZATIONS STRATEGIC OBJECTIVES  REVIEWING ALL PROJECTS AND PROGRAMS IN ORDER TO PRIORITIZE RESOURCE ALLOCATIONS FOR THE GREATEST OPTIMIZATION  MAINTAINING ALIGNMENT BETWEEN THE PORTFOLIO(S) AND ORGANIZATIONAL STRATEGIES  INCLUDES PROJECTS, PROGRAMS, SUB- PROJECTS, SUB-PROGRAMS, OPERATIONS, SUPPORT, INVESTMENTS, CASH FLOW, AND OVERHEAD  THE FACT IS THERE ARE NO REQUIREMENTS FOR PORTFOLIOS TO BE INTERRELATED OR INTERDEPENDENT  THE INTEGRATION OF MULTIPLE PORTFOLIOS UNDER A SINGLE CORPORATE GOVERNANCE STRUCTURE IS DEFINED AS THE ORGANIZATIONS ENTERPRISE PORTFOLIO 1.4.2 PORTFOLIO MANAGEMENT
  • 31.
  • 32.
     WHAT ISTHE DEFINITION OF PORTFOLIO MANAGEMENT?  WHAT ARE THE BENEFITS OF HAVING A DIVERSIFIED PORTFOLIO?  WHAT DOES THE ENTERPRISE PORTFOLIO CONSIST OF?  WHAT DOES PORTFOLIO MANAGEMENT FOCUS ON?  NOTES 1.4.2 PORTFOLIO MANAGEMENT
  • 33.
     PROJECTS AREUTILIZED TO DIRECTLY OR INDIRECTLY ACHIEVE STRATEGIC OBJECTIVES AND CONTRIBUTE TO:  THE BENEFITS OFA PROGRAM  OBJECTIVES OF THE PORTFOLIO  THE STRATEGIC PLAN  THE MOST COMMON STRATEGIC CONSIDERATION FOR THE EXISTENCE OFA PROJECT IS:  A CUSTOMER REQUEST  PROJECTS PROVIDE FEEDBACK TO PROGRAMS AND PORTFOLIOS THROUGH:  PERFORMANCE, CHANGES, AND LESSONS LEARNED  THE STRATGIC PLAN IS THE PRIMARY DRIVER OF ORGANIZATIONAL INVESTMENTS 1.4.3 PROJECTS AND STRATEGIC PLANNING
  • 34.
    1.4.3 PROJECTS ANDSTRATEGIC PLANNING
  • 35.
     WHAT AREPROJECTS USED TO ACHIEVE?  WHAT ARE SOME OF THE REASONS WHY PROJECTS ARE AUTHORIZED?  PROJECTS WITHIN PROGRAMS CAN CONTRIBUTE TO?  PORTFOLIOS SHOULD PRIORITIZE WHAT TYPES OF PROJECTS?  THE ORGANIZATIONS STRATEGIC PLAN BECOMES THE PRIMARY DRIVER OF?  NOTES 1.4.3 PROJECTS AND STRATEGIC PLANNING
  • 36.
    THE PMO:  ESTABLISHESPROGRAM AND PROJECT MANAGEMENT POLICIES & PROCEDURES  STANDARDIZES THE PROJECT GOVERNANCE PROCESSES  FACILITATES THE SHARING OF:  RESOURCES  MULTIPLE METHODOLOGIES  TOOLS & TECHNIQUES  PMI IDENTIFIES (3) TYPES OF PMO STRUCTURES:  DIRECTIVE  CONTROLLING  SUPPORTIVE  THE PMO IS OFTEN A NATURAL LIASION FOR PROJECTS AND PROGRAMS  THE PMO LEADERSHIP IS A KEY STAKEHOLDER & DECISION MAKER 1.4.4 PROJECT MANAGEMENT OFFICE
  • 37.
  • 38.
     WHAT DOESTHE PMO STANDARDIZE?  WHAT ARE THE THREE TYPES OF PMO’S?  THE PMO IS THE LIASION BETWEEN THE ORGANIZATIONS ________________________?  DOES THE PMO REQUIRE PROJECTS TO BE INTERRELATED AND INTERDEPENDENT IN ORDER FOR IT TO SUPPORT THEM?  DOES THE PMO HAVE THE AUTHORITY TO ACT AS A STAKEHOLDER OR DECISION MAKER DURING THE PROJECTS LIFE CYCLE?  NOTES 1.4.4 PROJECT MANAGEMENT OFFICE
  • 39.
     OPERATIONS MANAGEMENTIS RESPONSIBLE FOR:  OVERSEEING BUSINESS OPERATIONS  DIRECTING BUSINESS OPERATIONS  CONTROLLING BUSINESS OPERATIONS  OPERATIONS:  SUPPORT THE DAY-TO-DAY BUSINESS NEEDS  ARE NECESSARY TO ACHIEVE STRATEGIC AND TACTICAL BUSINESS OBJECTIVES  SUPPORT PROJECTS IN ACHIEVING ORGANIZATIONAL GOALS:  MAINTAINS ALIGNMENT WITH ORGANIZATIONAL STRATEGY  INTEGRAL COMPONENT FOR ACHIEVING STRATEGIC BUSINESS INITIATIVES 1.5 RELATIOSHIP BETWEEN PROJECT MANAGEMENT, OPERATIONS MANAGEMENT, AND ORGANIZATIONAL STRATEGY
  • 40.
    1.5 RELATIOSHIP BETWEENPROJECT MANAGEMENT, OPERATIONS MANAGEMENT, AND ORGANIZATIONAL STRATEGY
  • 41.
     WHAT ARETHE OBJECTIVES OF OPERATIONS MANAGEMENT?  WHAT ARE SOME EXAMPLES OF OPERATIONS MANAGEMENT?  DESCRIBE A WAY IN WHICH OPERATIONS MANAGEMENT AND PROJECTS INTERSECT?  WHAT ARE SOME OF THE ELEMENTS OF OPERATIONS?  NOTES 1.5 RELATIONSHIP BETWEEN PROJECT MANAGEMENT, OPERATIONS MANAGEMENT, AND ORGANIZATIONAL STRATEGY
  • 42.
     PROJECTS AREOFTEN CONDUCTED WHEN SUBSTANTIAL CHANGES ARE BEING MADE TO BUSINESS OPERATIONS AND:  INTRODUCING NEW PRODUCTS  INTRODUCING NEW SERVICES  KEY POINTS OF INTERSECTIONS BETWEEN PROJECTS AND OPERATIONS OCCUR WHEN:  SIGNIFICANT IMPROVEMENTS ARE MADE TO OPERATIONS  DELIVERABLES ARE TRANSFERRED TO OPERATIONAL CONTROL  CUSTOMERS PURCHASE BACK-END DELIVERABLE SUPPORT  DEVELOPING A NEW PRODUCT  UPGRADING AN EXISTING PRODUCT  EXPANDING OUTPUT VELOCITY OR CAPACITY 1.5.1 OPERATIONS AND PROJECT MANAGEMENT
  • 43.
    1.5.1 OPERATIONS ANDPROJECT MANAGEMENT
  • 44.
     HOW DOPROJECTS AID IN MAKING CHANGES TO BUSINESS OPERATIONS?  DOES OPERATIONS MANAGEMENT FALL WITHIN THE SCOPE OF PROJECT MANAGEMENT?  WHAT ARE SOME COMMON POINTS OF INTERSECTION BETWEEN PROJECTS AND OPERATIONS?  WHAT COULD BE TRANSFERRED TO OPERATIONS AS A PROJECT NEARS THE CLOSURE PHASE?  NOTES 1.5.1 OPERATIONS AND PROJECT MANAGEMENT
  • 45.
     OPERATIONS MANAGEMENTAND OPERATIONS:  OPERATIONS MANAGEMENT FALLS OUTSIDE THE GOVERNANCE OF PROJECT MANAGEMENT  OPERATIONS ARE PROCESS DRIVEN AND FOCUSED ON THE PRODUCTION OR MANUFACTURING OF GOODS AND SERVICES AND/OR THE DAY-TO-DAY NEEDS OF THE ORGANIZATION  OPERATIONS ARE CONCERNED WITH CONTINUOUS IMPROVEMENT, RESOURCE OPTIMIZATION, AND MEETING CUSTOMER DEMANDS:  SIPOC  SUPPLIES  INPUTS  PROCESSES  OUTPUTS  CUSTOMERS 1.5.1.1 OPERATIONS MANAGEMENT
  • 46.
  • 47.
     WHY DOESOPERATIONS MANAGEMENT FALL OUTSIDE THE SCOPE OF PROJECT MANAGEMENT?  WHAT IS OPERATIONS MANAGEMENT PRIMARILY CONCERNED WITH?  OPERATIONS MANAGEMENT INVOLVES?  NOTES 1.5.1.1 OPERATIONS MANAGEMENT
  • 48.
     OPERATIONAL STAKEHOLDERSSHOULD BE INCLUDED IN EVERY PHASE OF THE PROJECT LIFECYCLE. THIS WILL:  LEAD TO GAINS IN INSIGHT  HELP PREVENT UNNECESSARY ISSUES  OPERATIONAL MANAGERS ARE KEY STAKEHOLDERS AND SHOULD BE CONSIDERED WHEN:  IDENTIFYING STAKEHOLDERS  IDENTIFYING PROJECT RISKS  ASSESSING IMPORTANT PROJECT CONSIDERATIONS  ASSESSING THE AFFECTS OF FUTURE WORK AND ENDEAVORS 1.5.1.2 OPERATIONAL STAKEHOLDERS IN PROJECT MANAGEMENT
  • 49.
  • 50.
     ARE THENEEDS OF OPERATIONS MANAGEMENT STAKEHOLDERS IMPORTANT TO CONSIDER WHEN THE PROJECT HAS A DIRECT IMPACT ON THEIR FUTURE WORK OR ENDEAVORS? WHY?  DOES INCLUDING APPROPRIATE OPERATIONS MANAGEMENT STAKEHOLDERS IN ALL PHASES OF THE PROJECT YIELD ANY NOTICABLE PROJECT BENEFITS?  WHEN ARE UNNECESSARY ISSUES CREATED BETWEEN OPERATIONS AND PROJECT MANAGEMENT?  WHY IS IT MORE DIFFICULT TO BASH A PLAN YOU PLAYED A ROLE IN DEVELOPING?  NOTES 1.5.1.2 OPERATIONALSTAKEHOLDERS IN PROJECT MANAGEMENT
  • 51.
     ORGANIZATIONAL GOVERNANCE GOVERNANCE PROVIDES STRATEGIC DIRECTION AND PERFORMANCE PARAMETERS  STRATEGIC DIRECTION PROVIDES PURPOSE, GOALS, AND ACTIONS  GOVERNANCE ESTABLISHES ALIGNMENT BETWEEN PROJECT MANAGEMENT ACTIVITIES AND BUSINESS DIRECTION  ACKNOWLEDGING THAT CHANGES IN OBJECTIVES AFFECT PROJECT EFFICIENCY AND SUCCESS  CONSTANT ALIGNMENT INCREASES THE PROBABILITY OF PROJECT SUCCESS 1.5.2 ORGANIZATIONS AND PROJECT MANAGEMENT
  • 52.
    1.5.2 ORGANIZATIONS ANDPROJECT MANAGEMENT
  • 53.
     WHY DOORGANIZATIONS USE GOVERNANCE?  WHAT DOES STRATEGIC DIRECTION PROVIDE TO THE ORGANIZATION?  WHY IS IT IMPORTANT FOR THE PROJECT TO REMAIN IN ALIGNMENT WITH TOP-LEVEL BUSINESS DIRECTION?  IN WHAT WAY DOES A CHANGE IN PROJECT OBJECTIVES AFFECT EFFICIENCY AND SUCCESS?  DOES STRATEGIC ALIGNMENT INCREASE OR DECREASE THE ODDS OF SUCCESS?  NOTES 1.5.2 ORGANIZATIONS AND PROJECT MANAGEMENT
  • 54.
     PBO’S:  UTILIZETEMPORARY ORGANIZATIONAL SYSTEMS TO EXECUTE THE PROJECT WORK OF THE ORGANIZATION  DIMINISH THE IMPACT OF ORGANIZATIONAL POLITICS BECAUSE THE DELIVERABLE IS THE ONLY MEASUREMENT OF SUCCESS  UTILIZE PROJECTS AND/OR PROJECT MANAGEMENT FUNDAMENTALS TO CONDUCT THE MAJORITY OF IT’S BUSINESS  CAN TAKE THE FORM OFA FIRM, COLLECTION OF FIRMS, OR NETWORKS 1.5.2.1 PROJECT-BASED ORGANIZATIONS (PBO’S)
  • 55.
  • 56.
     PBO’S REFERTO TEMPORARY ORGANIZATIONAL STRUCTURES THAT CREATE?  IN THE PBO THE SUCCESS OF THE PROJECT IS MEASURED BY?  WHAT TYPES OF ORGANIZATIONS MIGHT EMPLOY THE USE OFA PBO?  NOTES 1.5.2.1 PROJECT-BASED ORGANIZATIONS
  • 57.
     GOVERNANCE:  PROGRAMSAND PROJECTS ARE UTILIZED TO ACHIEVE STRATEGIC BUSINESS GOALS  FORMAL ORGANIZATIONAL GOVERNANCE CAN IMPOSE CONSTRAINTS ON PROJECTS  PROJECT SUCCESS IS PARTLY MEASURED BY THE SUCCESS OF THE PROJECT IN IT’S RESPONSE TO ORGANIZATIONAL GOVERNANCE  THE PROJECT MANAGER MUST BE AWARE OF THE IMPACT OF CORPORATE OR ORGANIZATIONAL POLICIES AND PROCEDURES ON THEIR PROJECTS 1.5.2.2 THE LINK BETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL GOVERNANCE
  • 58.
    1.5.2.2 THE LINKBETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL GOVERNANCE
  • 59.
     SHOULD ORGANIZATIONSTHAT UTILIZE PROJECTS TO DRIVE STRATEGIC OUTCOMES ALSO ESTABLISH ORGANIZATIONAL GOVERNANCE PROCESSES AND PROCEDURES?  GIVE AN EXAMPLE WHERE ORGANIZATIONAL GOVERNANCE MIGHT IMPOSE CONSTRAINTS ON THE PROJECT?  WHY IS IT IMPORTANT FOR PROJECT MANAGERS TO BE AWARE OF CORPORATE AND/OR ORGANIZATIONAL GOVERNANCE POLICIES AND PROCEDURES?  NOTES 1.5.2.2 THE LINK BETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL GOVERNANCE
  • 60.
     ORGANIZATIONAL STRATEGY ORGANIZATIONAL STRATEGY PROVIDES GUIDANCE AND DIRECTION TO PROJECT MANAGEMENT  PROJECTS EXIST TO SUPPORT ORGANIZATIONAL STRATEGY  THE SPONSOR, PORTFOLIO MANAGER, OR PROGRAM MANAGER ARE RESPONSIBLE FOR IDENTIFYING ALIGMENT AS WELLAS POTENTIAL CONFLICTS BETWEEN THE STRATEGIC PLAN AND PROJECTS  IT IS THE RESPONSIBILITY OF THE PROJECT MANAGER TO IDENTIFY AND DOCUMENT CONFLICTS WITH ESTABLISHED ORGANIZATIONAL STRATEGIES  DEVELOPMENT OFAN ORGANIZATIONAL STRATEGY COULD BE THE OUTPUT OFA PROJECT (SUSTAINABILITY) 1.5.2.3 THE RELATIONSHIP BETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL STRATEGY
  • 61.
    1.5.2.3 THE RELATIONSHIPBETWEEN PROJECT MANAGEMENT AND ORGANIZATIONAL STRATEGY
  • 62.
     ARE GUIDANCEAND DIRECTION THE ONLY OBJECTIVES OF ORGANIZATIONAL STRATEGY?  WHO IS RESPONSIBLE FOR IDENTIFYING PROJECT ALIGNMENT WITH ORGANIZATIONAL STRATEGY?  WHO IS REAPONSBILE FOR IDENTIFYING CONFLICTS WITH ORGANIZATIONAL STRATEGY?  CAN DEVELOPMENT OF ORGANIZATIONAL STRATEGY BE THE GOAL OFA PROJECT?  NOTES 1.5.2.3 THE RELATIONSHIP BETWEEN PROJECT MANAGEMENT AND ORGANIZATONAL STRATEGY
  • 63.
     BUSINESS VALUE BUSINESS VALUE IS UNIQUE TO EVERY ORGANIZATION  IT IS THE TOTAL VALUE OF THE ORGANIZATION  THE SUM OFALL TANGIBLE AND INTANGIBLE ELEMENTS  BUSINESS VALUE SCOPE CAN BE ASSESSED SHORT, MEDIUM OR LONG TERM  BUSINESS VALUE FOCUSES ON THE EMPLOYMENT OF EFFICIENT PROCESSES TO MEET STRATEGIC OBJECTIVES  BUSINESS VALUE IS DERIVED FROM THE COLLECTIVE USE OF STRATEGIC PLANNING, PORTFOLIO, PROGRAM, PROJECT, AND OPERATIONS MANAGEMENT, ALONG WITH SUPPORT ACTVITIES, OVERHEAD, INVESTMENTS, AND REVENUE MANAGEMENT ACTIVITIES 1.6 BUSINESS VALUE
  • 64.
  • 65.
     WHAT ISTHE DEFINITION OF BUSINESS VALUE?  WHAT ARE EXAMPLES OF TANGIBLE ASSETS?  WHAT ARE SOME EXAMPLES OF INTANGIBLE ASSETS?  CAN BUSINESS VALUE SCOPE FALL INTO SHORT, MEDIUM, OR LONG-TERM TIME FRAMES?  CAN BUSINESS VALUE BE CREATED THROUGH EFFICIENT MANAGEMENT?  DOES THE EFFECTIVE USE OF PROJECT, PROGRAM, AND PORTFOLIO MANAGEMENT LEAD TO INCREASED VALUE FROM PROJECT INVESTMENTS?  ALL FORMAL ORGANIZATIONS THAT CONDUCT BUSINESS-RELATED ACTIVITIES FOCUS ON ATTAINING GREATER BUSINESS VALUE  NOTES 1.6 BUSINESS VALUE
  • 66.
     THE PROJECTMANAGER ROLE  THE INDIVIDUAL ASSIGNED BY THE ORGANIZATION TO LEAD A TEAM IN CREATING A DELIVERABLE THAT MEETS PROJECT REQUIREMENTS  A PROJECT MANAGER MAY REPORT TO A FUNCTIONAL MANAGER, PROGRAM MANAGER, PMO, OR PORTFOLIO MANAGER  THE PROJECT MANAGER IS RESPONSIBLE FOR MAINTAINING ALIGNMENT WITH ORGANIZATIONAL STRATEGIES  THE PROJECT MANAGER ALSO COLLABORATES, COORDINATES, AND COMMUNICATES WITH OPERATIONAL, SUPPORT, EXPERT, AND CONSULTANT PERSONNEL 1.7 ROLE OF THE PROJECT MANAGER
  • 67.
    1.7 ROLE OFTHE PROJECT MANAGER
  • 68.
     HOW DOPROJECT MANAGERS DIFFER FROM OPERATIONS OR FUNCTIONAL MANAGERS?  IN WHICH ORGANIZATIONAL STRUCTURES MIGHT A PROJECT MANAGER REPORT TO A FUNCTIONAL MANAGER?  IN WHAT BUSINESS STRUCTURE MIGHT A PROJECT MANAGER REPORT TO A PROGRAM OR PORTFOLIO MANAGER?  NAME OTHER BUSINESS ROLES THE PROJECT MANAGER MIGHT NEED TO COLLABORATE WITH?  NOTES 1.7 ROLE OF THE PROJECT MANAGER
  • 69.
     THE GENERALRESPONSIILITY OF THE PROJECT MANAGER IS  TO SATISFY THE NEEDS OF THE TEAM, CUSTOMER, SPONSOR, AND KEY STAKEHOLDERS NEEDS:  TASK RELATED  INDIVIDUAL NEEDS  TASK NEEDS  TEAM NEEDS  PROJECT MANAGERS MUST POSSESS:  INDUSTRY AND PROJECT MANAGEMENT KNOWLEDGE  A HISTORY OF SUSTAINED EXCEPTIONAL PERFORMANCE  EXEMPLARY PROFESSIONAL CONDUCT THAT IS FUELED BY ETHICALAND SOUND DECISION MAKING  THE RIGHT INTERPERSONAL SKILLS (THE ART)  THE APPROPRIATE MANAGEMENT SKILLS (THE SCIENCE) 1.7.1 RESPONSIBILITIES AND COMPETENCIES OF THE PROJECT MANAGER
  • 70.
    1.7.1 RESPONSIBILITIES ANDCOMPETENCIES OF THE PROJECT MANAGER
  • 71.
     WHAT ARESOME OF THE GENERAL RESPONSIBLITIES OFA PROJECT MANAGER?  IS THE PROJECT MANAGER THE LINK BETWEEN THE PROJECT TEAM AND THE PROJECT MANAGEMENT METHODOLOGY?  IN ADDITION TO THE APPLICATION OF KNOWLEDGE, TOOLS, AND TECHNIQUES, PROJECT MANAGERS MUST ALSO POSSESS THE FOLLOWING COMPETENCIES?  -----------------------------------------------------------------------  -----------------------------------------------------------------------  -----------------------------------------------------------------------  NOTES 1.7.1 RESPONSIBILITIES AND COMPETENCIES OF THE PROJECT MANAGER
  • 72.
     PROJECT MANAGERSACCOMPLISH TASKS THROUGH:  THE WORK OF TEAM MEMBERS AND OTHER KEY STAKEHOLDERS  THIS REQUIRES THE PROJECT MANAGER TO:  BUILD TRUST  UTILIZE INFLUENCE  DEMONSTRATE INDUSTRY KNOWLEDGE  DEMONSTRATE PROJECT MANAGEMENT EXPERTISE  UTILIZE EFFECTIVE INTERPERSONAL SKILLS  UTILIZE EFFECTIVE MANAGEMENT SKILLS  PROACTIVELY RESPOND TO CONFLICT  COMMUNICATE EFFECTIVELY  NEGOTIATE WIN-WIN SOLUTIONS  INFUSE AND SUATAIN TEAM MOTIVATION  UTILIZE EFFECTIVE SITUATIONAL LEADERSHIP 1.7.2 INTERPERSONAL SKILLS OF A PROJECT MANAGER
  • 73.
    1.7.2 INTERPERSONAL SKILLSOF A PROJECT MANAGER
  • 74.
     EFFECTIVE PROJECTMANAGERS REQUIRE A BALANCE OF TECHNICAL, INTERPERSONAL, AND ____________________ SKILLS?  THE PRESENCE OF THESE SKILLS HELP THEM ___________________ SITUATIONS AND ______________ APPROPRIATELY?  WHAT SECTION OF THE PMBOK SPECIFICALLY ADDRESSES INTERPERSONAL SKILLS?  NOTES 1.7.2 INTERPERSONAL SKILLS OF A PROJECT MANAGER
  • 75.
     THE PMBOKCONTAINS:  PROJECT MANAGEMENT GOOD PRACTICES  A BODY OF KNOWLEDGE (IT IS NOT A METHODOLOGY)  A COMMON VOCABULARY  PROJECT MANAGEMENT PROCESSES  THE PROPER INTEGRATION OF PROJECT MANAGEMENT TO OTHER MANAGEMENT DISCIPLINES  ANNEX A1 – THE STANDARD FOR PROJECT MANAGEMENT OFA PROJECT  APPENDIX X1 – 5TH EDITION VERSION CHANGES TO THE PMBOK  APPENDIX X2 – CONTRIBUTORS AND REVIEWERS OF THE PMBOK’S CURRENT GUIDE  APPENDIX X3 – INTERPERSONAL SKILLS  REFERENCES  GLOSSARY  INDEX 1.8 PROJECT MANAGEMENT BODY OF KNOWLEDGE
  • 76.
    1.8 PROJECT MANAGEMENTBODY OF KNOWLEDGE
  • 77.
     THE PMBOKCONTAINS THE STANDARD FOR? MANAGING _________ PROJECTS _________ OF THE TIME, ACROSS __________ INDUSTRIES  ANNEX A1 DESCRIBES THE ___________ , AND TO MANAGE A PROJECT TOWARDS A ____________ _____________ ?  THE STANDARD IS INTERRELATED TO WHAT OTHER PROJECT MANAGEMENT DISCIPLINES?  THE STANDARD IS LIMITED TO __________ PROJECTS?  NOTES 1.8 PROJECT MANAGEMENT BODY OF KNOWLEDGE
  • 78.
    CHAPTER 1 SUMMARY Whatare the components of a PMBOK Process? Identify the ten Knowledge Areas and their purpose. Identify the Process Groups and define their purpose. What is the purpose of Project Management? What is the purpose of a Program? What are characteristics of a Portfolio? What are the intersecting points for projects and operations? What is a Strategic Plan?
  • 79.