SlideShare a Scribd company logo
1 of 262
PMP Exam
Preparation
Eng. Shamil Habet; MSc; PMP; JPE
Based on PMBOK 6th
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 1
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Planning Project
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 2
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP PROJECT MANAGEMENT PLAN
Develop Project Management Plan is the process of defining, preparing, and coordinating
all plan components and consolidating them into an integrated project management plan.
The key benefit of this process is the production of a comprehensive document that
defines the basis of all project work and how the work will be performed. This process
is performed once or at predefined points in the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 3
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 The project management plan defines how the project is executed,
monitored and controlled, and closed.
 The project management plan may be either summary level or detailed.
Each component plan is described to the extent required by the specific
project.
 The project management plan should be robust enough to respond to an
ever-changing project environment. This agility may result in more
accurate information as the project progresses.
 The project management plan should be baselined; that is, it is necessary
to define at least the project references for scope, time, and cost,
DEVELOP PROJECT MANAGEMENT PLAN
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 4
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Meetings
For this process, meetings are used to discuss the project approach,
determine how work will be executed to accomplish the project objectives,
and establish the way the project will be monitored and controlled.
The project kick-off meeting is usually associated with the end of
planning and the start of executing. Its purpose is to communicate the
objectives of the project, gain the commitment of the team for the project,
and explain the roles and responsibilities of each stakeholder.
 In small projects, there is usually only one team that performs the
planning and the execution. In this case, the kick-off occurs shortly after
initiation, in the Planning Process Group, because the team is involved in
planning.
 In large projects: the kick-off meeting takes place with processes in
the Executing Process Group.
 Multiphase projects will typically include a kick-off meeting at the
beginning of each phase.
DEVELOP PROJECT MANAGEMENT PLAN (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 5
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Types of meetings
kick-off Technical
Sprint or Iteration
Planning
Scrum Daily
Standups
Problem Solving
Progress
Update
Steering Group Retrospective
Typical Sprint Retrospective Model
DEVELOP PROJECT MANAGEMENT PLAN (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 6
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Scrum Daily Standups:
- (15 minutes) Time box;
- Same Place;
- SameTime;
- Facilitated by Scrum Master
- FullTeam Presence;
- THREE main Questions
DEVELOP PROJECT MANAGEMENT PLAN (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 7
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Sprint Planning MeetingBacklog Sprint Backlog
Sprint or Iteration Planning
DEVELOP PROJECT MANAGEMENT PLAN (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 8
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP PROJECT MANAGEMENT PLAN (Outputs)
 Project Management Plan
The project management plan is the document that describes how the
project will be executed, monitored and controlled, and closed. It
integrates and consolidates all of the subsidiary management plans and
baselines, and other information necessary to manage the project. The
needs of the project determine which components of the project
management plan are needed.
 Additional Components: Most components of the project management
plan are produced as outputs from other processes, though some are
produced during this process. Those components developed as part of this
process will be dependent on the project; however, they often include but
are not limited to:
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 9
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Change Management Plan: Describes how the change requests
throughout the project will be formally authorized and incorporated.
 Configuration Management Plan: Describes how the information about
the items of the project (and which items) will be recorded and updated so
that the product, service, or result of the project remains consistent and/or
operative.
 Performance Measurement Baseline: Integrated Scope-Schedule-Cost
plan (Baselines) for the project work against which project execution is
compared to measure and manage performance.
 Project Life Cycle: Describes the series of phases that a project passes
through from its initiation to its closure.
 Development Approach: Describes the product, service, or result
development approach, such as predictive, iterative, agile, or a hybrid model.
 Management Reviews: Identifies the points in the project when the
project manager and relevant stakeholders will review the project progress
to determine if performance is as expected, or if preventive or corrective
actions are necessary.
DEVELOP PROJECT MANAGEMENT PLAN (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 10
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Project Management Plan and Project Documents
DEVELOP PROJECT MANAGEMENT PLAN (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 11
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN SCOPE MANAGEMENT
Plan Scope Management is the process of creating a scope management plan
that documents how the project and product scope will be defined, validated,
and controlled.
The key benefit of this process is that it provides guidance and direction on
how scope will be managed throughout the project. This process is
performed once or at predefined points in the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 12
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN SCOPE MANAGEMENT (Outputs)
 Scope Management Plan
The scope management plan is a component of the project management
plan that describes how the scope will be defined, developed, monitored,
controlled, and validated. This plan helps reduce the risk of project scope
creep. The components of a scope management plan include:
 Process for preparing a project scope statement;
 Process that enables the creation of the WBS from the detailed project
scope statement;
 Process that establishes how the scope baseline will be approved and
maintained;
 Process that specifies how formal acceptance of the completed project
deliverables will be obtained.
The Scope Management Plan can be formal or informal, broadly
framed or highly detailed, based on the needs of the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 13
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Scope Creep: The uncontrolled expansion to product or project scope
without adjustments to time, cost, and resources.
Gold Plating: Adding extra features or functions to the products which
were not included in the scope statement.
PLAN SCOPE MANAGEMENT (Outputs)
Important Notes:
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 14
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN SCOPE MANAGEMENT (Outputs)
 Requirements Management Plan
The requirements management plan is a component of the project
management plan that describes how Project and Product requirements will
be analyzed, documented, and managed. Components of the requirements
management plan can include but are not limited to:
 How requirements activities will be planned, tracked, and reported;
 Configuration management activities such as: how changes will be initiated;
how impacts will be analyzed; how they will be traced, tracked, and reported;
as well as the authorization levels required to approve these changes;
 Requirements prioritization process;
 Metrics that will be used and the rationale for using them;
 Traceability structure that reflects the requirement attributes captured on
the traceability matrix.
Product scope: The features and functions that characterize a product, service, or result.
Project scope: The work performed to deliver a product, service, or result with the
specified features and functions. The term “project scope” is
sometimes viewed as including product scope.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 15
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
COLLECT REQUIREMENTS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 16
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
COLLECT REQUIREMENTS
Collect Requirements is the process of determining, documenting, and
managing stakeholder needs and requirements to meet objectives.
The key benefit of this process is that it provides the basis for defining the
product scope and project scope. This process is performed once or at
predefined points in the project.
Requirements include:
- Conditions or capabilities that are required to be present in a product, service,
or result to satisfy an agreement or other formally imposed specification.
- The quantified and documented needs and expectations of the sponsor,
customer, and other stakeholders.
These requirements need to be elicited, analyzed, and recorded in enough
detail to be included in the scope baseline and to be measured once project
execution begins.
Requirements become the foundation of theWBS.
Cost, schedule, quality planning, and procurement are all based on
these requirements.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 17
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
COLLECT REQUIREMENTS (T & T)
 Data Gathering
 Brainstorming: This technique is used to identify a list of ideas in a
short period of time. It is conducted in a group environment and is led
by a facilitator. Brainstorming comprises two parts: idea generation and
analysis. Brainstorming can be used to gather data and solutions or ideas
from stakeholders, subject matter experts, and team members.
Can include both:
1- Brainstorming: A general data-gathering and creativity technique that
elicits input from groups such as team members or subject matter
experts.
2- Brain Writing: A refinement of brainstorming that allows individual
participants time to consider the question(s) individually before the
group creativity session is held. The information can be gathered in face-
to-face groups or using virtual environments supported by technology.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 18
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Data Gathering (Cont.)
 Interviews: An interview is a formal or informal approach to elicit
information from stakeholders by talking to them directly. It is typically
performed by asking prepared and spontaneous questions and recording
the responses.
- Interviews can aid in identifying and defining the features and
functions of the desired product deliverables.
- Interviews are useful for obtaining confidential information
 Focus Groups: Focus groups bring together prequalified stakeholders
and subject matter experts to learn about their expectations and
attitudes about a proposed product, service, or result. A trained
moderator guides the group through an interactive discussion designed
to be more conversational than a one-on-one interview.
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 19
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Data Gathering (Cont.)
 Questionnaires and Surveys: Questionnaires and surveys are written
sets of questions designed to quickly accumulate information from a
large number of respondents. Questionnaires and/or surveys are most
appropriate with varied audiences, when a quick turnaround is needed,
when respondents are geographically dispersed, and where statistical
analysis could be appropriate.
- DelphiTechnique: Questionnaire for Experts
 Benchmarking: Benchmarking involves comparing actual or planned
project practices or the project’s quality standards to those of
comparable projects to identify best practices, generate ideas for
improvement, and provide a basis for measuring performance.
Benchmarked projects may exist within the performing organization or
outside of it, or can be within the same application area or other
application area. Benchmarking allows for analogies from projects in a
different application area or different industries to be made.
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 20
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Decision Making
 Voting: Voting is a collective decision-making technique and an
assessment process having multiple alternatives with an expected
outcome in the form of future actions. These techniques can be used to
generate, classify, and prioritize product requirements. Examples of
voting techniques include:
- Unanimity: A decision that is reached whereby everyone agrees on
a single course of action.
- Majority: A decision that is reached with support obtained from
more than 50% of the members of the group. Having a group size
with an uneven number of participants can ensure that a decision will
be reached, rather than resulting in a tie.
- Plurality: A decision that is reached whereby the largest block in a
group decides, even if a majority is not achieved. This method is
generally used when the number of options nominated is more than
two.
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 21
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Decision Making (Cont.)
 Autocratic Decision Making: In this method, one individual takes
responsibility for making the decision for the group.
 Multi-criteria Decision Analysis: A technique that uses a decision
matrix to provide a systematic analytical approach for establishing
criteria, such as risk levels, uncertainty, and valuation, to evaluate and
rank many ideas.
 Data Representation
 Affinity Diagrams: Allow large numbers of ideas to be classified into
groups for review and analysis.
 Mind Mapping: Consolidates ideas created through individual
brainstorming sessions into a single map to reflect commonality and
differences in understanding and to generate new ideas.
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 22
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Affinity Diagram
Mind Mapping
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 23
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Interpersonal andTeam Skills
 Nominal Group Technique: The nominal group technique enhances
brainstorming with a voting process used to rank the most useful ideas
for further brainstorming or for prioritization. The nominal group
technique is a structured form of brainstorming consisting of four steps:
1. A question or problem is posed to the group. Each person silently
generates and writes down their ideas.
2. The moderator writes down the ideas on a flip chart until all ideas
are recorded.
3. Each recorded idea is discussed until all group members have a clear
understanding.
4. Individuals vote privately to prioritize the ideas, usually using a scale
of 1 – 5, with 1 being the lowest and 5 being the highest. Voting may
take place in many rounds to reduce and focus in on ideas. After
each round, the votes are tallied and the highest scoring ideas are
selected.
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 24
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Interpersonal andTeam Skills (Cont.)
 Facilitation: Facilitation is used with focused sessions that bring key
stakeholders together to define product requirements. Workshops can
be used to quickly define cross-functional requirements and reconcile
stakeholder differences. Because of their interactive group nature, well-
facilitated sessions can build trust, foster relationships, and improve
communication among the participants, which can lead to increased
stakeholder consensus. In addition, issues can be discovered earlier and
resolved more quickly than in individual sessions.
Facilitation skills are used in the following situations, but are not limited to:
- Joint Application Design/Development (JAD). JAD sessions are used in
the software development industry. These facilitated sessions
focus on bringing business subject matter experts and the
development team together to gather requirements and improve the
software development process.
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 25
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Interpersonal andTeam Skills (Cont.)
 Facilitation: (Cont.)
- Quality Function Deployment (QFD). In the manufacturing industry,
QFD is another facilitation technique that helps determine critical
characteristics for new product development. QFD starts by
collecting customer needs, also known as Voice Of Customer
(VOC). These needs are then objectively sorted and prioritized, and
goals are set for achieving them.
- User Stories. User stories, which are short, textual descriptions of
required functionality, are often developed during a requirements
workshop. User stories describe the stakeholder role, who benefits
from the feature (role), what the stakeholder needs to accomplish
(goal), and the benefit to the stakeholder (motivation).
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 26
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Context Diagram
The context diagram is an example of a scope model. Context diagrams
visually depict the product scope by showing a business system (process,
equipment, computer system, etc.), and how people and other systems
(actors) interact with it.
 Prototypes
Prototyping is a method of obtaining early feedback on requirements by
providing a model of the expected product before actually building it.
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 27
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Context diagram
COLLECT REQUIREMENTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 28
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
COLLECT REQUIREMENTS (Outputs)
 Requirements Documentation
Requirements documentation describes how individual requirements meet the
business need for the project.
- Requirements may start out at a high level and become progressively more
detailed as more information about the requirements is known.
- Before being baselined, requirements need to be unambiguous (measurable and
testable), traceable, complete, consistent, and acceptable to key stakeholders.
Requirements Classifications
1. Business Requirements: These describe the higher-level needs of the
organization as a whole, such as the business issues or opportunities, and
reasons why a project has been undertaken.
2. Stakeholder Requirements: These describe needs of a stakeholder or
stakeholder group.
3. Transition and Readiness Requirements: These describe temporary
capabilities, such as data conversion and training requirements, needed to
transition from the current as-is state to the desired future state.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 29
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
4. Solution Requirements: These describe features, functions, and characteristics
of the product, service, or result that will meet the business and stakeholder
requirements.
- Functional requirements: Functional requirements describe the behaviors of
the product. Examples include actions, processes, data, and interactions that
the product should execute.
- Nonfunctional requirements: Nonfunctional requirements supplement
functional requirements and describe the environmental conditions or qualities
required for the product to be effective. Examples include: reliability, security,
performance, safety, level of service, supportability, retention/purge, etc.
5. Project Requirements: These describe the actions, processes, or other
conditions the project needs to meet. Examples include milestone dates,
contractual obligations, constraints, etc.
6. Quality Requirements: These capture any condition or criteria needed to
validate the successful completion of a project deliverable or fulfillment of other
project requirements. Examples include tests, certifications, validations, etc.
COLLECT REQUIREMENTS (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 30
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
COLLECT REQUIREMENTS (Outputs)
 RequirementsTraceability Matrix
The requirements traceability matrix is a grid that links product requirements from
their origin to the deliverables that satisfy them.
- Helps ensure that each requirement adds business value by linking it to the
business and project objectives.
- Provides a means to track requirements throughout the project life cycle,
helping to ensure that requirements approved in the requirements
documentation are delivered at the end of the project.
- Provides a structure for managing changes to the product scope.
Tracing requirements includes but is not limited to:
- Business needs, opportunities, goals, and objectives;
- Project objectives;
- Project scope andWBS deliverables;
- Product design;
- Product development;
- Test strategy and test scenarios;
- High-level requirements to more detailed requirements.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 31
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
COLLECT REQUIREMENTS (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 32
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEFINE SCOPE
Define Scope is the process of developing a detailed description of the
project and product.
The key benefit of this process is that it describes the product, service, or
result boundaries and acceptance criteria.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 33
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEFINE SCOPE (T & T)
 Product analysis
Product analysis can be used to define products and services. It includes
asking questions about a product or service and forming answers to
describe the use, characteristics, and other relevant aspects of what is going
to be delivered. Each application area has one or more generally accepted
methods for translating high-level product or service descriptions into
meaningful deliverables. Requirements are captured at a high level and
decomposed to the level of detail needed to design the final product.
Examples of product analysis techniques include but are not limited to:
- Product breakdown,
- Requirements analysis,
- Systems analysis,
- Systems engineering,
- Value analysis,
- Value engineering.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 34
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEFINE SCOPE (Outputs)
 Project Scope Statement
The project scope statement is the description of the project scope, major
deliverables, assumptions, and constraints. The project scope statement documents
the entire scope, including project and product scope.
The detailed project scope statement, either directly or by reference to other
documents, includes the following:
- Product Scope Description: Progressively elaborates the characteristics of
the product, service, or result described in the project charter and
requirements documentation.
- Deliverables: Any unique and verifiable product, result, or capability to
perform a service that is required to be produced to complete a process, phase,
or project. Deliverables also include ancillary results, such as project
management reports and documentation. These deliverables may be described
at a summary level or in great detail.
- Acceptance Criteria: A set of conditions that is required to be met before
deliverables are accepted.
- Project Exclusions: Identifies what is excluded from the project. Explicitly
stating what is out of scope for the project helps manage stakeholders’
expectations and can reduce scope creep.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 35
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Elements of the Project
Charter and Project Scope
Statement
DEFINE SCOPE (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 36
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
CREATE WBS
Create WBS is the process of subdividing project deliverables and project
work into smaller, more manageable components.
The key benefit of this process is that it provides a framework of what has
to be delivered. This process is performed once or at predefined points in
the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 37
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
The WBS is a hierarchical decomposition of the total scope of work to be
carried out by the project team to accomplish the project objectives and
create the required deliverables.
The WBS organizes and defines the total scope of the project and represents
the work specified in the current approved project scope statement.
CREATE WBS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 38
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
CREATE WBS (T & T)
 Decomposition
Decomposition is a technique used for dividing and subdividing the project scope
and project deliverables into smaller, more manageable parts.
- The work package is the work defined at the lowest level of the WBS
for which cost and duration can be estimated and managed.
- The level of decomposition is often guided by the degree of control
needed to effectively manage the project.
- The level of detail for work packages will vary with the size and complexity
of the project.
- Decomposition of the total project work into work packages generally
involves the following activities:
 Identifying and analyzing the deliverables and related work,
 Structuring and organizing theWBS,
 Decomposing the upperWBS levels into lower-level detailed components,
 Developing and assigning identification codes to theWBS components,
 Verifying that the degree of decomposition of the deliverables is
appropriate.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 39
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
SampleWBS Decomposed DownThrough Work Packages
CREATE WBS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 40
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
A WBS structure may be created through various approaches.
- top-down approach,
- Use of organization-specific guidelines,
- Use of WBS templates.
- A bottom-up approach can be used to group subcomponents.
The WBS structure can be represented in a number of forms, such as:
- Using Phases of the project life cycle as the second level of decomposition,
with the product and project deliverables inserted at the third level;
- Using Major Deliverables as the second level of decomposition,
- Incorporating Subcomponents that may be developed by organizations
outside the project team, such as contracted work. The seller then develops
the supporting contract WBS as part of the contracted work.
CREATE WBS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 41
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
WBS Organized by Phase
CREATE WBS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 42
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
WBS with Major Deliverables
CREATE WBS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 43
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Important Notes:
- Excessive decomposition can lead to nonproductive management effort,
inefficient use of resources, decreased efficiency in performing the work,
and difficulty aggregating data over different levels of theWBS.
- The WBS represents ALL product and project work, including the project
management work.
- 100% rule: Total of the work at the lowest levels should roll up to the higher
levels so that nothing is left out and no extra work is performed.
- 4/40 rule: NO work package (task) should be shorter than four hours or
longer than 40 hours in duration.
- 8/80 rule: Similar to 4/40 rule; but with bigger limits.
CREATE WBS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 44
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
CREATE WBS (Outputs)
 Scope Baseline
The SCOPE BASELINE is the approved version of a scope statement, WBS,
and its associated WBS dictionary, which can be changed only through formal
change control procedures and is used as a basis for comparison. It is a component of
the project management plan. Components of the scope baseline include:
 Project Scope Statement.
 WBS.
 Work Package: The lowest level of the WBS is a work package with a unique
identifier. These identifiers provide a structure for hierarchical summation of
costs, schedule, and resource information and form a code of accounts. Each
work package is part of a control account. A control account is a management
control point where scope, budget, and schedule are integrated and compared to
the earned value for performance measurement. A control account has two or
more work packages, though each work package is associated with a single
control account.
 Planning Package: A control account may include one or more planning
packages. A planning package is a work breakdown structure component below
the control account and above the work package with known work content but
without detailed schedule activities.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 45
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 WBS Dictionary: The WBS dictionary is a document that provides detailed
deliverable, activity, and scheduling information about each component in the
WBS. The WBS dictionary is a document that supports the WBS. Most of the
information included in the WBS dictionary is created by other processes and
added to this document at a later stage. Information in the WBS dictionary may
include but is not limited to:
- Code of account identifier,
- Description of work,
- Assumptions and constraints,
- Responsible organization,
- Schedule milestones,
- Associated schedule activities,
- Resources required,
- Cost estimates,
- Quality requirements,
- Acceptance criteria,
- Technical references,
- Agreement information.
CREATE WBS (Outputs)
Scope
Baseline
Scope
Statement
WBS
Dictionary
WBS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 46
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
CREATE WBS (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 47
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Plan Schedule Management is the process of establishing the policies,
procedures, and documentation for planning, developing, managing, executing,
and controlling the project schedule.
The key benefit of this process is that it provides guidance and direction on
how the project schedule will be managed throughout the project. This
process is performed once or at predefined points in the project.
PLAN SCHEDULE MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 48
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN SCHEDULE MANAGEMENT
 Project Scheduling Methods:
 Iterative Scheduling with a Backlog:
- Form of Rolling Wave Planning based on adaptive life cycles, such as
the agile approach for product development.
- The requirements are documented in user stories that are then
prioritized and refined just prior to construction, and the product
features are developed using time-boxed periods of work.
- Often used to deliver incremental value to the customer or when
multiple teams can concurrently develop a large number of features
that have few interconnected dependencies.
- Appropriate for many projects as indicated by the widespread and
growing use of adaptive life cycles for product development.
- It welcomes changes throughout the development life cycle.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 49
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Project Scheduling Methods (Cont.)
 On-Demand Scheduling:
- This approach, typically used in a Kanban system, is based on the
theory-of constraints and pull-based scheduling concepts from lean
manufacturing to limit a team’s work in progress in order to
balance demand against the team’s delivery throughput.
- Does not rely on a schedule that was developed previously for the
development of the product or product increments, but rather pulls
work from a backlog or intermediate queue of work to be done
immediately as resources become available.
- Often used for projects that evolve the product incrementally in
operational or sustainment environments, and where tasks may be
made relatively similar in size and scope or can be bundled by size
and scope.
PLAN SCHEDULE MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 50
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Kanban: Simple Real Example
PLAN SCHEDULE MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 51
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN SCHEDULE MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 52
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN SCHEDULE MANAGEMENT (Outputs)
 Schedule Management Plan
The schedule management plan is a component of the project management
plan that establishes the criteria and the activities for developing, monitoring,
and controlling the schedule. The schedule management plan may be formal
or informal, highly detailed, or broadly framed based on the needs of the
project, and includes appropriate control thresholds.
The Schedule Management Plan can establish the following:
 Project Schedule Model Development: The scheduling methodology
and the scheduling tool to be used in the development of the project
schedule model are specified.
 Level of Accuracy: The level of accuracy specifies the acceptable range
used in determining realistic activity duration estimates and may include
an amount for contingencies.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 53
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Schedule Management Plan (Cont.)
The schedule management plan can establish the following (Cont.):
 Release and Iteration Length: When using an adaptive life cycle, the
time-boxed periods for releases, waves, and iterations are specified.
- Time-Boxed periods are durations during which the team works
steadily toward completion of a goal.
- Time-boxing helps to minimize scope creep as it forces the teams
to process essential features first, then other features when time
permits..
 Units of Measure: Each unit of measurement (such as staff hours, staff
days, or weeks for time measures, or meters, liters, tons, kilometers, or
cubic yards for quantity measures) is defined for each of the resources.
PLAN SCHEDULE MANAGEMENT (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 54
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Schedule Management Plan (Cont.)
The schedule management plan can establish the following (Cont.):
 Organizational Procedures Links: The work breakdown structure
(WBS) provides the framework for the schedule management plan,
allowing for consistency with the estimates and resulting schedules.
 Project Schedule Model Maintenance: The process used to update
the status and record progress of the project in the schedule model
during the execution of the project is defined.
 Control Thresholds: Variance thresholds for monitoring schedule
performance may be specified to indicate an agreed-upon amount of
variation to be allowed before some action needs to be taken.
- Thresholds are typically expressed as percentage deviations from
the parameters established in the baseline plan.
PLAN SCHEDULE MANAGEMENT (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 55
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Schedule Management Plan (Cont.)
The schedule management plan can establish the following (Cont.):
 Rules of Performance Measurement: Earned value management
(EVM) rules or other physical measurement rules of performance
measurement are set. For example, the schedule management plan may
specify:
- Rules for establishing percent complete,
- EVM techniques (e.g., baselines, fixed-formula, percent complete, etc.)
to be employed,
- Schedule performance measurements such as schedule variance (SV)
and schedule performance index (SPI) used to assess the magnitude
of variation to the original schedule baseline.
 Reporting Formats: The formats and frequency for the various
schedule reports are defined.
PLAN SCHEDULE MANAGEMENT (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 56
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEFINE ACTIVITIES
Define Activities is the process of identifying and documenting the specific
actions to be performed to produce the project deliverables.
The key benefit of this process is that it decomposes work packages into
schedule activities that provide a basis for estimating, scheduling, executing,
monitoring, and controlling the project work.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 57
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEFINE ACTIVITIES (Outputs)
 Activity List
Activity List includes the schedule activities required on the project.
 For projects that use rolling wave planning or agile techniques, the
activity list will be updated periodically as the project progresses.
 The activity list includes:
- Activity Identifier.
- Scope of work description for each activity in sufficient detail to
ensure that project team members understand what work is required
to be completed.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 58
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEFINE ACTIVITIES (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 59
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEFINE ACTIVITIES (Outputs)
 Activity Attributes
Activity Attributes extend the description of the activity by
identifying multiple components associated with each activity.
Activity attributes are used for schedule development and for selecting,
ordering, and sorting the planned schedule activities in various ways within
reports.
 Milestone List
Milestone is a significant point or event in a project.
Milestones have zero duration because they represent a significant point
or event.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 60
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Milestone List
Project Start Date: Project Manager Project Sponsor
Expected Completion Date:
Milestone Number: Milestone Name: Date:
Mandatory/Optional Completion Date: Verifications
Comments:
DEFINE ACTIVITIES (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 61
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
SEQUENCE ACTIVITIES
Sequence Activities is the process of identifying and documenting relationships
among the project activities.
The key benefit of this process is that it defines the logical sequence of work
to obtain the greatest efficiency given all project constraints. This process is
performed throughout the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 62
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
SEQUENCE ACTIVITIES (T & T)
 Precedence Diagramming Method
The Precedence Diagramming Method (PDM) is a technique used for
constructing a schedule model in which activities are represented by nodes
and are graphically linked by one or more logical relationships to show the
sequence in which the activities are to be performed.
- Finish-to-Start (FS) (most commonly used): installing the operating
system on a PC (successor) cannot start until the PC hardware is
assembled (predecessor).
- Finish-to-Finish (FF): For example, writing a document (predecessor)
is required to finish before editing the document (successor) can finish.
- Start-to-Start (SS): For example, level concrete (successor) cannot
begin until pour foundation (predecessor) begins.
- Start-to-Finish (SF) (very rarely used): For example, a new accounts
payable system (successor) has to start before the old accounts payable
system can be shut down (predecessor).
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 63
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Precedence Diagramming Method (PDM) RelationshipTypes
SEQUENCE ACTIVITIES (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 64
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
SEQUENCE ACTIVITIES (T & T)
 Dependency Determination and Integration
1. Mandatory Dependencies (Hard Logic): Mandatory dependencies are those
that are legally or contractually required or inherent in the nature of the work.
Mandatory dependencies often involve physical limitations, such as on a
construction project, where it is impossible to erect the superstructure until
after the foundation has been built.
2. Discretionary Dependencies (Preferred Logic, Preferential Logic, or Soft
Logic): Discretionary dependencies are established based on knowledge of best
practices within a particular application area or some unusual aspect of the
project where a specific sequence is desired, even though there may be other
acceptable sequences. For example, generally accepted best practices
recommend that during construction, the electrical work should start after
finishing the plumbing work.
Important Note:
Discretionary dependencies should be fully documented since they can
create arbitrary total float values and can limit later scheduling options.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 65
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
3. External Dependencies: External dependencies involve a relationship
between project activities and non-project activities. These dependencies are
usually outside of the project team’s control. For example, the
testing activity in a software project may be dependent on the delivery
of hardware from an external source.
4. Internal Dependencies: Internal dependencies involve a precedence
relationship between project activities and are generally inside the project
team’s control. For example, if the team cannot test a machine until
they assemble it.
SEQUENCE ACTIVITIES (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 66
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Leads and Lags
A LEAD is the amount of time a successor activity can be advanced with respect to
a predecessor activity
A LAG is the amount of time a successor activity will be delayed with respect to a
predecessor activity.
Important Notes:
- Lead is often represented as a negative value for lag.
- The use of leads and lags should not replace schedule logic.
- Duration Estimates do not include any leads or lags.
 Project Schedule Network Diagram
Graphical representation of the logical relationships, also referred to as dependencies,
among the project schedule activities. It can include full project details, or have one
or more summary activities. A summary narrative can accompany the diagram and
describe the basic approach used to sequence the activities. Any unusual activity
sequences within the network should be fully described within the narrative.
SEQUENCE ACTIVITIES (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 67
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
SEQUENCE ACTIVITIES (T & T)
Project Schedule Network Diagram
Lead and Lag
Important Notes:
- Path Convergence: Activities that have multiple predecessor activities.
- Path Divergence:Activities that have multiple successor activities.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 68
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE ACTIVITY DURATIONS
Estimate Activity Durations is the process of
estimating the number of work periods needed to
complete individual activities with estimated resources.
The key benefit of this process is that it provides the
amount of time each activity will take to complete. This
process is performed throughout the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 69
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Factors for consideration when estimating duration include:
 Law of Diminishing Returns: When one factor (e.g., resource) used
to determine the effort required to produce a unit of work is
increased while all other factors remain fixed, a point will eventually be
reached at which additions of that one factor start to yield progressively
smaller or diminishing increases in output.
ESTIMATE ACTIVITY DURATIONS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 70
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Number of Resources: Increasing the number of resources to twice the
original number of the resources does not always reduce the time by half, as
it may increase extra duration due to risk, and at some point adding too many
resources to the activity may increase duration due to knowledge transfer,
learning curve, additional coordination, and other factors involved.
 Advances in Technology: For example, an increase in the output of a
manufacturing plant may be achieved by procuring the latest advances in
technology, which may impact duration and resource needs.
 Motivation of Staff: The project manager needs to be aware of Student
Syndrome -or procrastination- when people start to apply themselves only at
the last possible moment before the deadline, and Parkinson’s Law where
work expands to fill the time available for its completion.
ESTIMATE ACTIVITY DURATIONS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 71
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE ACTIVITY DURATIONS (T & T)
 Analogous Estimating (Top-Bottom)
Analogous estimating is a technique for estimating the duration or cost of an
activity or a project using historical data from a similar activity or
project. Analogous estimating uses parameters from a previous, similar
project, such as duration, budget, size, weight, and complexity, as the basis for
estimating the same parameter or measure for a future project.
 Frequently used to estimate project duration when there is a limited
amount of detailed information about the project.
 Generally less costly and less time-consuming than other techniques,
but it is also less accurate.
 Most reliable when the previous activities are similar in fact and
not just in appearance, and the project team members preparing the
estimates have the needed expertise.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 72
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE ACTIVITY DURATIONS (T & T)
 Parametric Estimating
Parametric estimating is an estimating technique in which an algorithm is
used to calculate cost or duration based on historical data and project
parameters. Parametric estimating uses a statistical relationship between
historical data and other variables (e.g., square footage in construction) to
calculate an estimate for activity parameters, such as cost, budget, and
duration.
For Example: If the assigned resource is capable of installing 25 meters of cable
per hour, the duration required to install 1,000 meters is 40 hours.
 Bottom-Up Estimating
Bottom-up is a method of estimating project duration or cost by aggregating
the estimates of the lower-level components of theWBS.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 73
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE ACTIVITY DURATIONS (T & T)
 Three-Point Estimating
The accuracy of single-point duration estimates may be improved by considering
estimation uncertainty and risk. Using Three-Point estimates helps define an
approximate range for an activity’s duration:
 Most likely (tM): This estimate is based on the duration of the activity, given the
resources likely to be assigned, their productivity, realistic expectations of
availability for the activity, dependencies on other participants, and interruptions.
 Optimistic (tO): The activity duration based on analysis of the best-case
scenario for the activity.
 Pessimistic (tP): The duration based on analysis of the worst-case scenario for
the activity.
One commonly used formula is
Triangular Distribution: tE = (tO + tM + tP) / 3.
Important Note:
- Triangular distribution is used when there is insufficient historical data or
when using judgmental data.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 74
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE ACTIVITY DURATIONS (T & T)
 Data Analysis
Data analysis techniques that can be used for this process include but are not
limited to:
 Alternatives Analysis: Alternatives analysis is used to compare various
levels of resource capability or skills; scheduling compression techniques;
different tools (manual versus automated); and make, rent, or buy
decisions regarding the resources. This allows the team to weigh resource,
cost, and duration variables to determine an optimal approach for
accomplishing project work.
 Reserve Analysis: Reserve analysis is used to determine the amount of
Contingency and Management Reserve needed for the project.
Duration estimates may include contingency reserves, sometimes referred
to as schedule reserves, to account for schedule uncertainty.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 75
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Contingency Reserves Management Reserves
To Address Known Unknowns, Identi able,
Foreseeable Uncertainty Risks
To Address Unknown Unknowns,
Unidentifiable Unforeseeable Uncertainty
Measurable Within Reasonable Limits of
Accuracy
Cannot Be Measured With Any Precision
Based on Risk Register And Risk Plans/Responses
For Potential Events Conditions
Not Associated With Any Speci c Events or
Conditions
Included In The Cost Baseline Not Included In The Cost Baseline
Managed By Project Manager Requires Management Approval To Access
Any Unspent Contingency Converted To
Profit/Fee
Any Unspent Reserve Realized As Pro t/Fee
Can be % or Fixed Number or May Be Developed
By Using Quantitative Analysis Methods.
Simply As A Percentage (5%, 10%, Or 15%, For
Example) of The Cost of The Project
Part of Overall Project Budget Part of Overall Project Budget
ESTIMATE ACTIVITY DURATIONS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 76
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE ACTIVITY DURATIONS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 77
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Decision Making
Decision-making techniques that can be used in this process include but are
not limited to voting. One variation of the voting method that is often used in
Agile-Based Projects is called the fist of five (also called fist to five). In this
technique,
1. The project manager asks the team to show their level of support for a
decision by holding up a closed fist (indicating no support) up to five
fingers (indicating full support).
2. If a team member holds up fewer than three fingers, the team member is
given the opportunity to discuss any objections with the team.
3. The project manager continues the fist-of-five process until the team
achieves consensus (everyone holds up three or more fingers) or agrees
to move on to the next decision.
ESTIMATE ACTIVITY DURATIONS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 78
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Meetings
The project team may hold meetings to estimate activity durations. When
using an agile approach, it is necessary to conduct sprint or iteration
planning meetings to discuss prioritized product backlog items (user
stories) and decide which of these items the team will commit to work on
in the upcoming iteration.
- This meeting is usually held on the first day of the iteration and is attended
by the Product Owner, the Scrum Team, (Cross-functional team
members) and the Project Manager (Team facilitator).
- The outcome of the meeting includes an iteration backlog, as well as
assumptions, concerns, risks, dependencies, decisions, and actions.
ESTIMATE ACTIVITY DURATIONS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 79
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
The AgileTeam and the Backlog.
ESTIMATE ACTIVITY DURATIONS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 80
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE ACTIVITY DURATIONS (Outputs)
 Duration Estimates
Duration estimates are quantitative assessments of the likely number of
time periods that are required to complete an activity, a phase, or a project.
Important Note:
Duration estimates do not include any Leads or Lags.
 Basis of Estimates
The amount and type of additional details supporting the duration estimate
vary by application area. Regardless of the level of detail.
Important Note:
The supporting documentation should provide a clear and complete
understanding of how the duration estimate was derived.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 81
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 82
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Develop Schedule is the process of analyzing activity sequences, durations,
resource requirements, and schedule constraints to create a schedule model
for project execution and monitoring and controlling.
The key benefit of this process is that it generates a schedule model with
planned dates for completing project activities. This process is performed
throughout the project.
Developing an acceptable project schedule is an iterative process. The
schedule model is used to determine the planned start and finish dates for
project activities and milestones based on the best available information.
Schedule development can require the review and revision of duration
estimates, resource estimates, and schedule reserves to establish an approved
project schedule that can serve as a baseline to track progress.
DEVELOP SCHEDULE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 83
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 84
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
 Schedule Network Analysis
Schedule network analysis is the overarching technique used to generate
the project schedule model. It employs several other techniques such as
critical path method, resource optimization techniques, and modeling
techniques. Additional analysis includes but is not limited to:
 Assessing the need to aggregate schedule reserves to reduce the
probability of a schedule slip when multiple paths converge at a single
point in time or when multiple paths diverge from a single point in time,
to reduce the probability of a schedule slip.
 Reviewing the network to see if the critical path has high-risk activities or
long lead items that would necessitate use of schedule reserves or the
implementation of risk responses to reduce the risk on the critical path.
Important Note:
Schedule network analysis is an iterative process that is employed until
a viable schedule model is developed.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 85
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
 Critical Path Method (CPM)
The critical path is the sequence of activities that represents the longest path
through a project, which determines the shortest possible project duration.
- The critical path method is used to calculate the critical path(s) and the amount
of total and free float or schedule flexibility.
- TOTAL FLOAT or schedule flexibility: is the amount of time that a schedule
activity can be delayed or extended from its early start date without delaying
the project finish date.
Total Float = LS – ES = LF – EF
- FREE FLOAT: is the amount of time that a schedule activity can be delayed
without delaying the early start date of any successor.
Free Float =
Earliest ES of Following Activities - ES of Present Activity -Duration of Present Activity.
Important Notes:
- Critical path is normally characterized by Zero total float on the critical
path, and may have positive, or negative total float depending on the
constraints applied.
- Free Float for any activity on the Critical Path is equal to Zero
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 86
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
- Activity Duration = EF - ES + 1= LF – LS +1
- Early Finish (EF) = (ES + duration) – 1
- Early Start (ES) = (EF of predecessor) + 1
- Late Finish (LF) = (LS of successor) – 1
- Late Start (LS) = (LF – duration) + 1
Important Note:
- A project can have
several, parallel, near
critical paths or near
critical paths.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 87
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Example of Critical Path Method
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 88
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 89
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
 Resource Optimization
Resource optimization is used to adjust the start and finish dates of activities to
adjust planned resource use to be equal to or less than resource availability.
Examples include but are not limited to:
 Resource Leveling: A technique in which start and finish dates are adjusted
based on resource constraints with the goal of balancing the demand for
resources with the available supply.
 Resource Smoothing: A technique that adjusts the activities of a schedule
model such that the requirements for resources on the project do not exceed
certain predefined resource limits.
Resource Levelling Resource Smoothing
Adjust Actives Start and Finish to get
balanced resource requirements
Adjust Activities Start and Finish Within
Their Free /Total Float
Used when we have same Resources
for same period
Put fixed limit for resources
Done on Critical Path Not on Critical path
It may extend the project No project extension
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 90
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 91
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
 Data Analysis
Data analysis techniques that can be used for this process include but are
not limited to:
 What-if scenario analysis: What-if scenario analysis is the process of
evaluating scenarios in order to predict their effect, positive or negative,
on project objectives. This is an analysis of the question, “What if the
situation represented by scenario X happens?”
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 92
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Data Analysis (Cont.)
 Simulation: Simulation models the combined effects of individual
project risks and other sources of uncertainty to evaluate their potential
impact on achieving project objectives. The most common simulation
technique is Monte Carlo analysis, in which risks and other sources of
uncertainty are used to calculate possible schedule outcomes for the
total project.
In this example, there is a
10% probability that the
project will finish on or
before the target date of May
13, while there is a 90%
probability of completing the
project by May 28.
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 93
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Schedule Compression
Schedule compression techniques are used to shorten or accelerate the schedule
duration without reducing the project scope in order to meet schedule constraints,
imposed dates, or other schedule objectives. Schedule compression include:
 Crashing: Used to shorten the schedule duration for the least incremental cost
by adding resources. Examples of crashing include approving overtime, bringing in
additional resources, or paying to expedite delivery.
- Works only for activities on the critical path where additional resources will
shorten the activity’s duration.
- Does not always produce a viable alternative and may result in increased risk
and/or cost.
 Fast Tracking: Activities or phases normally done in sequence are performed in
parallel for at least a portion of their duration.
- May result in rework and increased risk.
- Only works when activities can be overlapped to shorten the project duration
on the critical path.
- Using leads in case of schedule acceleration usually increases coordination
efforts between the activities concerned and increases quality risk.
- May also increase project costs.
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 94
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 95
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Agile Release Planning
Agile release planning provides a high-level summary timeline of the release
schedule (typically 3 to 6 months) based on the product roadmap and the
product vision for the product’s evolution.
- Determines the number of iterations or sprints in the release, and allows the
product owner and team to decide how much needs to be developed and how
long it will take to have a releasable product based on business goals,
dependencies, and impediments.
- Since features represent value to the customer, the timeline provides a more
easily understood project schedule as it defines which feature will be available
at the end of each iteration, which is exactly the depth of information the
customer is looking for.
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 96
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Relationship Between ProductVision, Release Planning, and Iteration Planning
DEVELOP SCHEDULE (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 97
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Schedule Baseline
A schedule baseline is the approved version of a schedule model that can be
changed only through formal change control procedures and is used as a basis for
comparison to actual results.
- It is accepted and approved by the appropriate stakeholders as the schedule
baseline with baseline start dates and baseline finish dates.
- During monitoring and controlling, the approved baseline dates are compared to
the actual start and finish dates to determine if variances have occurred.
- A component of the project management plan.
 Project Schedule
The project schedule is an output of a schedule model that presents linked
activities with planned dates, durations, milestones, and resources. t is more often
presented graphically, using one or more of the following formats:
- Bar Charts
- Milestone Charts
- Project Schedule Network Diagrams
DEVELOP SCHEDULE (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 98
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 99
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DEVELOP SCHEDULE (Outputs)
 Schedule Data
The collection of information for describing and controlling the schedule. The
schedule data includes, at a minimum, the schedule milestones, schedule activities,
activity attributes, and documentation of all identified assumptions and constraints.
Information frequently supplied as supporting detail includes but is not limited to:
- Resource requirements by time period,often in the form of a resource histogram;
- Alternative schedules, such as best-case or worst-case, not resource-leveled or
resource-leveled, or with or without imposed dates;
- Applied schedule reserves.
- Schedule data could also include such items as resource histograms, cash-flow
projections, order and delivery schedules, or other relevant information.
 Project Calendars
Identifies working days and shifts that are available for scheduled activities.
- It distinguishes time periods in days or parts of days that are available to
complete scheduled activities from time periods that are not available for work.
- May require more than one project calendar to allow for different work periods
for some activities to calculate the project schedule.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 100
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN COST MANAGEMENT
Plan Cost Management is the process of defining how the project costs will be
estimated, budgeted, managed, monitored, and controlled.
The key benefit of this process is that it provides guidance and direction on
how the project costs will be managed throughout the project. This process is
performed once or at predefined points in the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 101
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN COST MANAGEMENT (Outputs)
 Cost Management Plan
Describes how the project costs will be planned, structured, and controlled.
- Units of Measure.
- Level of Precision: This is the degree to which cost estimates will be rounded
up or down (e.g., US$995.59 to US$1,000), based on the scope of the activities
and magnitude of the project.
- Level of Accuracy: The acceptable range (e.g., ±10%) used in determining
realistic cost estimates is specified, and may include an amount for contingencies.
- Organizational Procedures Links: The WBS component used for the project
cost accounting is called the control account.
- Control Thresholds: Variance thresholds for monitoring cost performance may
be specified to indicate an agreed-upon amount of variation to be allowed before
some action needs to be taken. Thresholds are typically expressed as percentage
deviations from the baseline plan.
- Rules of Performance Measurement: Earned value management (EVM) rules
of performance measurement are set.
- Reporting Formats: The formats and frequency for the various cost reports
are defined.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 102
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN COST MANAGEMENT (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 103
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE COSTS
Estimate Costs is the process of developing an approximation of the cost of
resources needed to complete project work.
The key benefit of this process is that it determines the monetary resources
required for the project. This process is performed periodically throughout
the project as needed.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 104
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE COSTS
 KeyTerms For Estimate Costs
The accuracy of a project estimate will increase as the project progresses
through the project life cycle. For example, a project in the initiation phase
may have a Rough Order of Magnitude (ROM). Later in the project, as
more information is known, project may have Definitive estimates.
Order of Magnitude Estimate -25% to +75%
Preliminary Estimate -15% to + 50%
Budget Estimate -10% to +25%
Definitive Estimate -5% to +10%
Final Estimate 0%
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 105
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 KeyTerms For Estimate Costs (Cont.)
 Depreciation Methods:
1. Straight-line Depreciation:
- Depreciation Expense = Asset Cost / Useful Life
- Depreciation Expense = (Asset Cost – ScrapValue) / Useful Life
- Depreciation Rate = 100% / Useful Life
2. Double Declining Balance
- Depreciation Rate = 2 * (100% / Useful Life)
- Depreciation Expense = Depreciation Rate * BookValue at Beginning ofYear
- BookValue = BookValue at beginning of year - Depreciation Expense
The Depreciation Rate stays the same over the years, but the Depreciation
Expense gets smaller each year because it is calculated from a smaller book value
each year. (Make sure the asset's book value does not fall below its Scrap value)
3. Sum-of-Years' Digits Method
- Sum of the digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
- Depreciation rate = fraction of years left and sum of the digits (i.e. 4/15th)
Both depreciation rate and depreciation fraction get smaller over time.
Example: Sum of the digits: If the useful life is 5, then it is 5 + 4 + 3 + 2 + 1 =15
Depreciation rate: 5/15th for the 1st year, 4/15 for 2nd …; and 1/15th for the 5th year.
ESTIMATE COSTS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 106
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Example (Double Declining Balance)
A machine that cost $400,000 has an estimated residual value of $40,000 and an
estimated useful life of four years. The company uses Double-Declining-Balance
depreciation. Calculate its book value at the end of year 3.
Solution:
Depreciation Rate = 2 * (100% / Useful Life) = 2*(100%/4) = 50%
1st Year Depreciation = 50% * $400,000 = $200,000
2nd Year Depreciation = 50% * ($400,000- $200,000) = $100,000
3rd Year Depreciation = 50% * ($400,000-($200,000+ $100,000)) = $50,000
BookValue at the end of year 3 = ($400,000-($200,000+ $100,000+ $50,000)) = $50,000
Example (Double Declining Balance)
A machine that cost $600,000 has an estimated useful life of five years. The company uses
Sum-of-Years' Digits depreciation. Calculate its book value at the end of year 3.
Solution:
Sum of the digits = 5+4+3+2+1=15
1st Year Depreciation = 5/15 * $600,000 = $200,000
2nd Year Depreciation = 4/15 * $600,000= $160,000
3rd Year Depreciation = 3/15 * $600,000= $120,000
BookValue at the end of year 3 = ($600,000-($200,000+ $160,000+ $120,000)) = $120,000
ESTIMATE COSTS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 107
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Depreciation Methods
ESTIMATE COSTS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 108
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 KeyTerms For Estimate Costs (Cont.)
 Average or Mean:The sum of all the members of the list divided by the number
of items in the list.
 Median: Arrange the values from lowest value to highest value and pick the
middle one. Example: 4 is the median in 2, 4, 6
(If there is an even number of values, calculate the mean of the two middle values.
Example: 5 is the median in 2, 4, 6, 8 because 4 + 6 / 2 = 5)
 Mode: The most frequent value in a given data set.
 Range:The Difference highest the highest and lowest numbers in a set of numbers.
ESTIMATE COSTS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 109
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Types of Cost
 Direct Cost: Directly attributable to project work. Such as: team travel,
recognitions, team wages.
 Indirect Cost: Such as overhead, benefits, and costs incurred for more than one
project. Such as: equipment, rental cost
 Fixed Cost: Costs that are not changed with production such as: setup cost and
rental cost.
 Variable Cost: Costs that are changed with Production/Work such as: material
and labors, supplies.
Important Note:
- Opportunity Cost: Is the value of the project NOT chosen. (Project B was
selected over project A, therefore the opportunity cost is the unrealized profit of project
A. ); Note that NO calculation is required.
- Sunk Cost: Is the cost that has already been incurred, and there is no way to
recover this cost. As the name implies – the money is sunk, gone, down the drain,
history (Should be Ignored in future project Decisions); There is no calculation required
for arriving at the Sunk Cost. It is always equal to the Actual Cost spent to date.
ESTIMATE COSTS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 110
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Question:
The management is reviewing the budget for the year 2018, and is evaluating the projects
ROI, and its usefulness in the market. The management is also going to look at the projects
that were started in the past 5 years, but were put on hold for some reason. In making
future project decisions,which of the following should not be considered?
A. EarnedValue
B. Benefit Cost Ratio
C. Sunk Cost
D. Fixed Cost
Question:
You are part of a project selection team evaluating three proposed projects and you
need to select the project that would bring the best return for the organization. Project
A has an NPV of $25,000 and an IRR of 1.5, Project B has a NPV of $30,000 and an IRR
of 1.25, and Project C has an NPV of $15,000 and an IRR of 1.5. What would be the
opportunity cost of selecting Project B over Project A?
A. $15,000
B. $5,000
C. $25,000
D. $30,000
ESTIMATE COSTS
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 111
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Three-Point Estimating
Two commonly used formula is
Triangular Distribution: cE = (cO + cM + cP) / 3.
Beta Distribution (PERT): cE = (cO + 4cM + cP) / 6
ESTIMATE COSTS (T & T)
Important Notes:
- PERT Standard Deviation (Single Activity) = σ = (Pessimistic - Optimistic) / 6
- PERT Activity Variance =Variance = ((Pessimistic - Optimistic) /6)2
- PERT Standard Deviation (All Activities)= √sum(Variances)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 112
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE COSTS (T & T)
 Data Analysis
 Alternatives Analysis
 Reserve Analysis
 Cost of quality: The cost of quality (COQ) associated with a project
consists of one or more of the following costs
- Prevention Costs: Costs related to the Prevention of poor quality in
the products, deliverables, or services of the specific project.
- Appraisal Costs: Costs related to evaluating, measuring, auditing, and
testing the products, deliverables, or services of the specific project.
- Failure Costs (internal/external): Costs related to Non-
Conformance of the products, deliverables, or services to the
needs or expectations of the stakeholders.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 113
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE COSTS (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 114
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
ESTIMATE COSTS (Outputs)
 Cost Estimates
Cost estimates include quantitative assessments of the probable costs required
to complete project work, as well as contingency amounts to account for
identified risks,and management reserve to cover unplanned work.
 Basis of Estimates
Regardless of the level of detail, the supporting documentation should
provide a clear and complete understanding of how the cost estimate
was derived. Supporting detail for cost estimates may include:
- Documentation of the basis of the estimate (i.e., how it was developed),
- Documentation of all assumptions made,
- Documentation of any known constraints,
- Documentation of identified risks included when estimating costs,
- Indication of the range of possible estimates (e.g., US$10,000 (±10%) to
indicate that the item is expected to cost between a range of values),
- Indication of the confidence level of the final estimate.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 115
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DETERMINE BUDGET
Determine Budget is the process of aggregating the
estimated costs of individual activities or work packages
to establish an authorized cost baseline.
The key benefit of this process is that it determines the
cost baseline against which project performance can be
monitored and controlled. This process is performed
once or at predefined points in the project.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 116
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DETERMINE BUDGET (T & T)
 Cost Aggregation
Cost estimates are aggregated by work packages in accordance with the WBS. The
work package cost estimates are then aggregated for the higher component levels
of the WBS (such as control accounts) and, ultimately, for the entire project.
 Funding Limit Reconciliation
The expenditure of funds should be reconciled with any funding limits on the
commitment of funds for the project. A variance between the funding limits and the
planned expenditures will sometimes necessitate the rescheduling of work to level
out the rate of expenditures. This is accomplished by placing imposed date
constraints for work into the project schedule.
 Financing
Financing entails acquiring funding for projects. It is common for long-term
infrastructure, industrial, and public services projects to seek external sources of
funds. If a project is funded externally, the funding entity may have certain
requirements that are required to be met.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 117
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DETERMINE BUDGET (Outputs)
 Cost Baseline
The cost baseline is the approved version of the time-phased project budget,
excluding any management reserves, which can only be changed through formal
change control procedures. It is used as a basis for comparison to actual results.
- The cost baseline is developed as a summation of the approved budgets for the
different schedule activities.
- As changes warranting the use of management reserves arise, the change control
process is used to obtain approval to move the applicable management reserve
funds into the cost baseline.
- Project Budget = Management Reserves + Cost Baseline.
 Project Funding Requirements
Total funding requirements and periodic funding requirements (e.g., quarterly,
annually) are derived from the cost baseline. The cost baseline will include
projected expenditures plus anticipated liabilities.
- Funding often occurs in incremental amounts (Steps)
- Total Funds Required = Management Reserves + Cost Baseline.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 118
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
DETERMINE BUDGET (Outputs)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 119
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN QUALITY MANAGEMENT
 Key Concepts For Project Quality Management
 Failure to meet the quality requirements can have serious negative
consequences for any or all of the project’s stakeholders. For example:
 Meeting customer requirements by overworking the project team may
result in decreased profits and increased levels of overall project risks,
employee attrition, errors, or rework.
 Meeting project schedule objectives by rushing planned quality inspections
may result in undetected errors, decreased profits, and increased post-
implementation risks.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 120
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Key Concepts For Project Quality Management (Cont.)
 Quality vs. Grade
Quality as a delivered performance or result is “the degree to which a set of
inherent characteristics fulfill requirements.
Grade as a design intent is a category assigned to deliverables having the same
functional use but different technical characteristics.
Important Note:
 Quality level that fails to meet quality requirements is always a problem,
 A low-grade product may not be a problem.
For Example:
- It may not be a problem if a suitable low-grade product (one with a limited
number of features) is of high quality (no obvious defects).
- It may be a problem if a high-grade product (one with numerous features) is of low
quality (many defects). In essence, a high-grade feature set would prove ineffective
and/or inefficient due to low quality
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 121
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Important Notes
 Prevention (keeping errors out of the process) and Inspection (keeping errors
out of the hands of the customer);
Prevention is preferred over inspection. It is better to design quality into
deliverables, rather than to find quality issues during inspection. The cost of
preventing mistakes is generally much less than the cost of correcting mistakes
when they are found by inspection or during usage.
 Attribute Sampling (the result either conforms or does not conform) and
Variable Sampling (the result is rated on a continuous scale that measures the
degree of conformity);
 Tolerances (specified range of acceptable results) and Control Limits (that
identify the boundaries of common variation in a statistically stable process or
process performance).
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 122
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Key Concepts For Project Quality Management (Cont.)
There are FIVE levels of increasingly effective quality management as
follows:
1. Usually, the most expensive approach is to let the customer find the
defects. This approach can lead to warranty issues, recalls, loss of
reputation, and rework costs.
2. Detect and correct the defects before the deliverables are sent to the
customer as part of the quality control process. The control quality
process has related costs, which are mainly the appraisal costs and
internal failure costs.
3. Use quality assurance to examine and correct the process itself and
not just special defects.
4. Incorporate quality into the planning and designing of the project and
product.
5. Create a culture throughout the organization that is aware and
committed to quality in processes and products.
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 123
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 124
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Key Concepts For Project Quality Management (Cont.)
- Crosby Zero Defects: Identify processes to remove defects, quality is built into
the processes
- Joseph Juran Fitness for Use: Does the product/service meet customer’s needs
(1- Grade, 2- Quality conformance, 3- Reliability/maintainability, 4- Safety, 5- Actual
Use). Proposed the application of Pareto’s (80/20 Principle) to Quality; as 80%
of the quality issues are due to the 20% of the causes.
- W.Edwards Deming: PDCA 85% of quality problem is managers’ responsibility,
- Six Sigma: Achieve 3.4/1.0 million defect level (99.999%), refine the process
to get rid of human error and outside influences with precise measurements,
variations are random in nature.
- Just In Time: Just when they are needed or just before they are needed.
Eliminate build up of inventory. (Value of the inventory very close to 0%)
- Total Quality Management (TQM): All members to center on quality to drive
customer satisfaction , refine the process of producing the product.
- Kaizen (Macro-PDCA Cycle): Implement consistent and incremental (small)
improvement, to reduce costs, cycle time, drive customer satisfaction using PDCA
(Plan-Do-Check-Act).
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 125
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Trends And Emerging Practices In Project Quality Management
 Customer Satisfaction: Understand, evaluate, define, and manage requirements
so that customer expectations are met. This requires a combination of
conformance to requirements (to ensure the project produces what it was
created to produce) and fitness for use (the product or service needs to satisfy
the real needs). In agile environments, stakeholder engagement with the team
ensures customer satisfaction is maintained throughout the project.
 Continual Improvement: The Plan-Do-Check-Act (PDCA) cycle is the basis
for quality improvement as defined by Shewhart and modified by Deming. In
addition, quality improvement initiatives such as total quality management
(TQM), Six Sigma, and Lean Six Sigma may improve both the quality of
project management, as well as the quality of the end product, service, or result.
 Management Responsibility: Success requires the participation of all members
of the project team. Management retains, within its responsibility for quality, a
related responsibility to provide suitable resources at adequate capacities.
 Mutually Beneficial Partnership with Suppliers: A mutually beneficial
relationship enhances the ability for both the organization and the suppliers to
create value for each other, enhances the joint responses to customer needs and
expectations, and optimizes costs and resources.
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 126
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN QUALITY MANAGEMENT
PDCA
DMAIC
Lean Six Sigma
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 127
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Considerations For Agile/Adaptive Environments
In order to navigate changes, agile methods call for frequent quality and
review steps built in throughout the project rather than toward the end of
the project.
Recurring retrospectives regularly check on the effectiveness of the quality
processes. They look for the root cause of issues then suggest trials of new
approaches to improve quality. Subsequent retrospectives evaluate any trial
processes to determine if they are working and should be continued or
new adjusting or should be dropped from use.
In order to facilitate frequent, incremental delivery, agile methods focus on
small batches of work, incorporating as many elements of project
deliverables as possible. Small batch systems aim to uncover
inconsistencies and quality issues earlier in the project life cycle when the
overall costs of change are lower.
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 128
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 129
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Plan Quality Management is the process of identifying quality requirements
and/or standards for the project and its deliverables, and documenting how
the project will demonstrate compliance with quality requirements and/or
standards.
The key benefit of this process is that it provides guidance and direction on
how quality will be managed and verified throughout the project. This process
is performed in parallel with the other planning processes once or at
predefined points in the project.
PLAN QUALITY MANAGEMENT
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 130
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Decision Making
Multi-criteria decision analysis tools (e.g., Prioritization Matrix) can be used to
identify the key issues and suitable alternatives to be prioritized as a set of decisions
for implementation. Criteria are prioritized and weighted before being applied to all
available alternatives to obtain a mathematical score for each alternative. The
alternatives are then ranked by score. As used in this process, it can help prioritize
quality metrics.
Prioritization Matrix
PLAN QUALITY MANAGEMENT (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 131
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
 Data Representation
 Flowcharts: display the sequence of steps and the branching possibilities that
exist for a process that transforms one or more inputs into one or more outputs.
Flowcharts show the activities, decision points, branching loops, parallel paths, and
the overall order of processing by mapping the operational details of procedures
that exist within a horizontal value chain. One version of a value chain, known as
a SIPOC (suppliers, inputs, process, outputs, and customers) model.
 Logical Data Model: Visual representation of an organization’s data, described
in business language and independent of any specific technology. The logical data
model can be used to identify where data integrity or other quality issues
can arise.
 Matrix Diagrams: Help find the strength of relationships among different
factors, causes, and objectives that exist between the rows and columns that form
the matrix.
- L,T,Y, X, C, Shaped
- Roof–Shaped.
 Mind mapping.
PLAN QUALITY MANAGEMENT (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 132
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
Flowcharts
Logical Data Model
PLAN QUALITY MANAGEMENT (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 133
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
The SIPOC Model
PLAN QUALITY MANAGEMENT (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 134
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN QUALITY MANAGEMENT (T & T)
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 135
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PLAN QUALITY MANAGEMENT (Outputs)
 Quality Management Plan
Describes how applicable policies, procedures, and guidelines will be implemented
to achieve the quality objectives.
 It describes the activities and resources necessary for the project management
team to achieve the quality objectives set for the project.
 May be formal or informal, detailed, or broadly framed.
 Should be reviewed early in the project to ensure that decisions are based on
accurate information. The benefits of this review can include a sharper focus on
the project’s value proposition, reductions in costs, and less frequent schedule
overruns that are caused by rework.
The quality management plan may include but is not limited to the following:
- Quality standards that will be used by the project;
- Quality objectives of the project;
- Quality roles and responsibilities;
- Project deliverables and processes subject to quality review;
- Quality control and quality management activities planned for the project;
- Quality tools that will be used for the project;
- Major procedures relevant for the project, such as dealing with nonconformance,
corrective actions procedures, and continuous improvement procedures.
PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE
shamilhabet@yahoo.com 136
PMP Exam
Preparation; Shamil Habet; MSc; PMP; JPE
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide
PMP Prep Guide

More Related Content

What's hot

Project Management Playbook
Project Management PlaybookProject Management Playbook
Project Management PlaybookDemand Metric
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...Edureka!
 
Enterprise Project Office
Enterprise Project OfficeEnterprise Project Office
Enterprise Project OfficeImad Almurib
 
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...Edureka!
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP) Ahmad Maharma, PMP,RMP
 
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...Edureka!
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off PresentationEbru Seiwert
 
Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)Hussain Bandukwala
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...
Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...
Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...Sophia Zhou
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOAnthony Natoli
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationOsama Zarzour
 

What's hot (20)

Project Management Playbook
Project Management PlaybookProject Management Playbook
Project Management Playbook
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
 
Enterprise Project Office
Enterprise Project OfficeEnterprise Project Office
Enterprise Project Office
 
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off Presentation
 
Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)
 
PMP MINDMAP
PMP MINDMAPPMP MINDMAP
PMP MINDMAP
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...
Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...
Microsoft PPM tool (Project Online / Project Server) Case Study by epmsolutio...
 
PMP Exam Notes
PMP Exam NotesPMP Exam Notes
PMP Exam Notes
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMO
 
Pmo Why?
Pmo Why?Pmo Why?
Pmo Why?
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint Presentation
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 

Similar to PMP Prep Guide

PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...Shamil Habet
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionJohn Khateeb
 
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...May Wong, PMP
 
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...Shamil Habet
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adbngocjos
 
Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2Becky Flint
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6Amit Gupta
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adbTa Ngoc
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overviewhouserdah
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.pptGoharSaeed6
 
PMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfPMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfDivya Malik
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...PMILebanonChapter
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...Arlene Smith
 
Presentation how a traditional project manager transforms to scrum - final
Presentation   how a traditional project manager transforms to scrum - finalPresentation   how a traditional project manager transforms to scrum - final
Presentation how a traditional project manager transforms to scrum - finalSadaf Saad
 

Similar to PMP Prep Guide (20)

PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
 
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 
Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2Startup Program Management Playbook (v1) - Pls check for v2
Startup Program Management Playbook (v1) - Pls check for v2
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overview
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
 
PMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfPMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdf
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
 
Presentation how a traditional project manager transforms to scrum - final
Presentation   how a traditional project manager transforms to scrum - finalPresentation   how a traditional project manager transforms to scrum - final
Presentation how a traditional project manager transforms to scrum - final
 

Recently uploaded

URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 

Recently uploaded (20)

URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 

PMP Prep Guide

  • 1. PMP Exam Preparation Eng. Shamil Habet; MSc; PMP; JPE Based on PMBOK 6th PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 1 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 2. Planning Project PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 2 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 3. DEVELOP PROJECT MANAGEMENT PLAN Develop Project Management Plan is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan. The key benefit of this process is the production of a comprehensive document that defines the basis of all project work and how the work will be performed. This process is performed once or at predefined points in the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 3 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 4.  The project management plan defines how the project is executed, monitored and controlled, and closed.  The project management plan may be either summary level or detailed. Each component plan is described to the extent required by the specific project.  The project management plan should be robust enough to respond to an ever-changing project environment. This agility may result in more accurate information as the project progresses.  The project management plan should be baselined; that is, it is necessary to define at least the project references for scope, time, and cost, DEVELOP PROJECT MANAGEMENT PLAN PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 4 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 5.  Meetings For this process, meetings are used to discuss the project approach, determine how work will be executed to accomplish the project objectives, and establish the way the project will be monitored and controlled. The project kick-off meeting is usually associated with the end of planning and the start of executing. Its purpose is to communicate the objectives of the project, gain the commitment of the team for the project, and explain the roles and responsibilities of each stakeholder.  In small projects, there is usually only one team that performs the planning and the execution. In this case, the kick-off occurs shortly after initiation, in the Planning Process Group, because the team is involved in planning.  In large projects: the kick-off meeting takes place with processes in the Executing Process Group.  Multiphase projects will typically include a kick-off meeting at the beginning of each phase. DEVELOP PROJECT MANAGEMENT PLAN (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 5 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 6. Types of meetings kick-off Technical Sprint or Iteration Planning Scrum Daily Standups Problem Solving Progress Update Steering Group Retrospective Typical Sprint Retrospective Model DEVELOP PROJECT MANAGEMENT PLAN (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 6 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 7. Scrum Daily Standups: - (15 minutes) Time box; - Same Place; - SameTime; - Facilitated by Scrum Master - FullTeam Presence; - THREE main Questions DEVELOP PROJECT MANAGEMENT PLAN (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 7 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 8. Sprint Planning MeetingBacklog Sprint Backlog Sprint or Iteration Planning DEVELOP PROJECT MANAGEMENT PLAN (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 8 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 9. DEVELOP PROJECT MANAGEMENT PLAN (Outputs)  Project Management Plan The project management plan is the document that describes how the project will be executed, monitored and controlled, and closed. It integrates and consolidates all of the subsidiary management plans and baselines, and other information necessary to manage the project. The needs of the project determine which components of the project management plan are needed.  Additional Components: Most components of the project management plan are produced as outputs from other processes, though some are produced during this process. Those components developed as part of this process will be dependent on the project; however, they often include but are not limited to: PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 9 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 10.  Change Management Plan: Describes how the change requests throughout the project will be formally authorized and incorporated.  Configuration Management Plan: Describes how the information about the items of the project (and which items) will be recorded and updated so that the product, service, or result of the project remains consistent and/or operative.  Performance Measurement Baseline: Integrated Scope-Schedule-Cost plan (Baselines) for the project work against which project execution is compared to measure and manage performance.  Project Life Cycle: Describes the series of phases that a project passes through from its initiation to its closure.  Development Approach: Describes the product, service, or result development approach, such as predictive, iterative, agile, or a hybrid model.  Management Reviews: Identifies the points in the project when the project manager and relevant stakeholders will review the project progress to determine if performance is as expected, or if preventive or corrective actions are necessary. DEVELOP PROJECT MANAGEMENT PLAN (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 10 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 11. Project Management Plan and Project Documents DEVELOP PROJECT MANAGEMENT PLAN (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 11 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 12. PLAN SCOPE MANAGEMENT Plan Scope Management is the process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled. The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project. This process is performed once or at predefined points in the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 12 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 13. PLAN SCOPE MANAGEMENT (Outputs)  Scope Management Plan The scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated. This plan helps reduce the risk of project scope creep. The components of a scope management plan include:  Process for preparing a project scope statement;  Process that enables the creation of the WBS from the detailed project scope statement;  Process that establishes how the scope baseline will be approved and maintained;  Process that specifies how formal acceptance of the completed project deliverables will be obtained. The Scope Management Plan can be formal or informal, broadly framed or highly detailed, based on the needs of the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 13 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 14. Scope Creep: The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources. Gold Plating: Adding extra features or functions to the products which were not included in the scope statement. PLAN SCOPE MANAGEMENT (Outputs) Important Notes: PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 14 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 15. PLAN SCOPE MANAGEMENT (Outputs)  Requirements Management Plan The requirements management plan is a component of the project management plan that describes how Project and Product requirements will be analyzed, documented, and managed. Components of the requirements management plan can include but are not limited to:  How requirements activities will be planned, tracked, and reported;  Configuration management activities such as: how changes will be initiated; how impacts will be analyzed; how they will be traced, tracked, and reported; as well as the authorization levels required to approve these changes;  Requirements prioritization process;  Metrics that will be used and the rationale for using them;  Traceability structure that reflects the requirement attributes captured on the traceability matrix. Product scope: The features and functions that characterize a product, service, or result. Project scope: The work performed to deliver a product, service, or result with the specified features and functions. The term “project scope” is sometimes viewed as including product scope. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 15 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 16. COLLECT REQUIREMENTS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 16 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 17. COLLECT REQUIREMENTS Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet objectives. The key benefit of this process is that it provides the basis for defining the product scope and project scope. This process is performed once or at predefined points in the project. Requirements include: - Conditions or capabilities that are required to be present in a product, service, or result to satisfy an agreement or other formally imposed specification. - The quantified and documented needs and expectations of the sponsor, customer, and other stakeholders. These requirements need to be elicited, analyzed, and recorded in enough detail to be included in the scope baseline and to be measured once project execution begins. Requirements become the foundation of theWBS. Cost, schedule, quality planning, and procurement are all based on these requirements. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 17 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 18. COLLECT REQUIREMENTS (T & T)  Data Gathering  Brainstorming: This technique is used to identify a list of ideas in a short period of time. It is conducted in a group environment and is led by a facilitator. Brainstorming comprises two parts: idea generation and analysis. Brainstorming can be used to gather data and solutions or ideas from stakeholders, subject matter experts, and team members. Can include both: 1- Brainstorming: A general data-gathering and creativity technique that elicits input from groups such as team members or subject matter experts. 2- Brain Writing: A refinement of brainstorming that allows individual participants time to consider the question(s) individually before the group creativity session is held. The information can be gathered in face- to-face groups or using virtual environments supported by technology. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 18 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 19.  Data Gathering (Cont.)  Interviews: An interview is a formal or informal approach to elicit information from stakeholders by talking to them directly. It is typically performed by asking prepared and spontaneous questions and recording the responses. - Interviews can aid in identifying and defining the features and functions of the desired product deliverables. - Interviews are useful for obtaining confidential information  Focus Groups: Focus groups bring together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product, service, or result. A trained moderator guides the group through an interactive discussion designed to be more conversational than a one-on-one interview. COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 19 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 20.  Data Gathering (Cont.)  Questionnaires and Surveys: Questionnaires and surveys are written sets of questions designed to quickly accumulate information from a large number of respondents. Questionnaires and/or surveys are most appropriate with varied audiences, when a quick turnaround is needed, when respondents are geographically dispersed, and where statistical analysis could be appropriate. - DelphiTechnique: Questionnaire for Experts  Benchmarking: Benchmarking involves comparing actual or planned project practices or the project’s quality standards to those of comparable projects to identify best practices, generate ideas for improvement, and provide a basis for measuring performance. Benchmarked projects may exist within the performing organization or outside of it, or can be within the same application area or other application area. Benchmarking allows for analogies from projects in a different application area or different industries to be made. COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 20 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 21.  Decision Making  Voting: Voting is a collective decision-making technique and an assessment process having multiple alternatives with an expected outcome in the form of future actions. These techniques can be used to generate, classify, and prioritize product requirements. Examples of voting techniques include: - Unanimity: A decision that is reached whereby everyone agrees on a single course of action. - Majority: A decision that is reached with support obtained from more than 50% of the members of the group. Having a group size with an uneven number of participants can ensure that a decision will be reached, rather than resulting in a tie. - Plurality: A decision that is reached whereby the largest block in a group decides, even if a majority is not achieved. This method is generally used when the number of options nominated is more than two. COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 21 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 22.  Decision Making (Cont.)  Autocratic Decision Making: In this method, one individual takes responsibility for making the decision for the group.  Multi-criteria Decision Analysis: A technique that uses a decision matrix to provide a systematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.  Data Representation  Affinity Diagrams: Allow large numbers of ideas to be classified into groups for review and analysis.  Mind Mapping: Consolidates ideas created through individual brainstorming sessions into a single map to reflect commonality and differences in understanding and to generate new ideas. COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 22 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 23. Affinity Diagram Mind Mapping COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 23 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 24.  Interpersonal andTeam Skills  Nominal Group Technique: The nominal group technique enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization. The nominal group technique is a structured form of brainstorming consisting of four steps: 1. A question or problem is posed to the group. Each person silently generates and writes down their ideas. 2. The moderator writes down the ideas on a flip chart until all ideas are recorded. 3. Each recorded idea is discussed until all group members have a clear understanding. 4. Individuals vote privately to prioritize the ideas, usually using a scale of 1 – 5, with 1 being the lowest and 5 being the highest. Voting may take place in many rounds to reduce and focus in on ideas. After each round, the votes are tallied and the highest scoring ideas are selected. COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 24 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 25.  Interpersonal andTeam Skills (Cont.)  Facilitation: Facilitation is used with focused sessions that bring key stakeholders together to define product requirements. Workshops can be used to quickly define cross-functional requirements and reconcile stakeholder differences. Because of their interactive group nature, well- facilitated sessions can build trust, foster relationships, and improve communication among the participants, which can lead to increased stakeholder consensus. In addition, issues can be discovered earlier and resolved more quickly than in individual sessions. Facilitation skills are used in the following situations, but are not limited to: - Joint Application Design/Development (JAD). JAD sessions are used in the software development industry. These facilitated sessions focus on bringing business subject matter experts and the development team together to gather requirements and improve the software development process. COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 25 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 26.  Interpersonal andTeam Skills (Cont.)  Facilitation: (Cont.) - Quality Function Deployment (QFD). In the manufacturing industry, QFD is another facilitation technique that helps determine critical characteristics for new product development. QFD starts by collecting customer needs, also known as Voice Of Customer (VOC). These needs are then objectively sorted and prioritized, and goals are set for achieving them. - User Stories. User stories, which are short, textual descriptions of required functionality, are often developed during a requirements workshop. User stories describe the stakeholder role, who benefits from the feature (role), what the stakeholder needs to accomplish (goal), and the benefit to the stakeholder (motivation). COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 26 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 27.  Context Diagram The context diagram is an example of a scope model. Context diagrams visually depict the product scope by showing a business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it.  Prototypes Prototyping is a method of obtaining early feedback on requirements by providing a model of the expected product before actually building it. COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 27 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 28. Context diagram COLLECT REQUIREMENTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 28 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 29. COLLECT REQUIREMENTS (Outputs)  Requirements Documentation Requirements documentation describes how individual requirements meet the business need for the project. - Requirements may start out at a high level and become progressively more detailed as more information about the requirements is known. - Before being baselined, requirements need to be unambiguous (measurable and testable), traceable, complete, consistent, and acceptable to key stakeholders. Requirements Classifications 1. Business Requirements: These describe the higher-level needs of the organization as a whole, such as the business issues or opportunities, and reasons why a project has been undertaken. 2. Stakeholder Requirements: These describe needs of a stakeholder or stakeholder group. 3. Transition and Readiness Requirements: These describe temporary capabilities, such as data conversion and training requirements, needed to transition from the current as-is state to the desired future state. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 29 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 30. 4. Solution Requirements: These describe features, functions, and characteristics of the product, service, or result that will meet the business and stakeholder requirements. - Functional requirements: Functional requirements describe the behaviors of the product. Examples include actions, processes, data, and interactions that the product should execute. - Nonfunctional requirements: Nonfunctional requirements supplement functional requirements and describe the environmental conditions or qualities required for the product to be effective. Examples include: reliability, security, performance, safety, level of service, supportability, retention/purge, etc. 5. Project Requirements: These describe the actions, processes, or other conditions the project needs to meet. Examples include milestone dates, contractual obligations, constraints, etc. 6. Quality Requirements: These capture any condition or criteria needed to validate the successful completion of a project deliverable or fulfillment of other project requirements. Examples include tests, certifications, validations, etc. COLLECT REQUIREMENTS (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 30 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 31. COLLECT REQUIREMENTS (Outputs)  RequirementsTraceability Matrix The requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. - Helps ensure that each requirement adds business value by linking it to the business and project objectives. - Provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. - Provides a structure for managing changes to the product scope. Tracing requirements includes but is not limited to: - Business needs, opportunities, goals, and objectives; - Project objectives; - Project scope andWBS deliverables; - Product design; - Product development; - Test strategy and test scenarios; - High-level requirements to more detailed requirements. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 31 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 32. COLLECT REQUIREMENTS (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 32 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 33. DEFINE SCOPE Define Scope is the process of developing a detailed description of the project and product. The key benefit of this process is that it describes the product, service, or result boundaries and acceptance criteria. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 33 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 34. DEFINE SCOPE (T & T)  Product analysis Product analysis can be used to define products and services. It includes asking questions about a product or service and forming answers to describe the use, characteristics, and other relevant aspects of what is going to be delivered. Each application area has one or more generally accepted methods for translating high-level product or service descriptions into meaningful deliverables. Requirements are captured at a high level and decomposed to the level of detail needed to design the final product. Examples of product analysis techniques include but are not limited to: - Product breakdown, - Requirements analysis, - Systems analysis, - Systems engineering, - Value analysis, - Value engineering. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 34 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 35. DEFINE SCOPE (Outputs)  Project Scope Statement The project scope statement is the description of the project scope, major deliverables, assumptions, and constraints. The project scope statement documents the entire scope, including project and product scope. The detailed project scope statement, either directly or by reference to other documents, includes the following: - Product Scope Description: Progressively elaborates the characteristics of the product, service, or result described in the project charter and requirements documentation. - Deliverables: Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project. Deliverables also include ancillary results, such as project management reports and documentation. These deliverables may be described at a summary level or in great detail. - Acceptance Criteria: A set of conditions that is required to be met before deliverables are accepted. - Project Exclusions: Identifies what is excluded from the project. Explicitly stating what is out of scope for the project helps manage stakeholders’ expectations and can reduce scope creep. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 35 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 36. Elements of the Project Charter and Project Scope Statement DEFINE SCOPE (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 36 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 37. CREATE WBS Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components. The key benefit of this process is that it provides a framework of what has to be delivered. This process is performed once or at predefined points in the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 37 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 38. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. The WBS organizes and defines the total scope of the project and represents the work specified in the current approved project scope statement. CREATE WBS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 38 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 39. CREATE WBS (T & T)  Decomposition Decomposition is a technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts. - The work package is the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed. - The level of decomposition is often guided by the degree of control needed to effectively manage the project. - The level of detail for work packages will vary with the size and complexity of the project. - Decomposition of the total project work into work packages generally involves the following activities:  Identifying and analyzing the deliverables and related work,  Structuring and organizing theWBS,  Decomposing the upperWBS levels into lower-level detailed components,  Developing and assigning identification codes to theWBS components,  Verifying that the degree of decomposition of the deliverables is appropriate. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 39 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 40. SampleWBS Decomposed DownThrough Work Packages CREATE WBS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 40 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 41. A WBS structure may be created through various approaches. - top-down approach, - Use of organization-specific guidelines, - Use of WBS templates. - A bottom-up approach can be used to group subcomponents. The WBS structure can be represented in a number of forms, such as: - Using Phases of the project life cycle as the second level of decomposition, with the product and project deliverables inserted at the third level; - Using Major Deliverables as the second level of decomposition, - Incorporating Subcomponents that may be developed by organizations outside the project team, such as contracted work. The seller then develops the supporting contract WBS as part of the contracted work. CREATE WBS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 41 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 42. WBS Organized by Phase CREATE WBS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 42 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 43. WBS with Major Deliverables CREATE WBS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 43 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 44. Important Notes: - Excessive decomposition can lead to nonproductive management effort, inefficient use of resources, decreased efficiency in performing the work, and difficulty aggregating data over different levels of theWBS. - The WBS represents ALL product and project work, including the project management work. - 100% rule: Total of the work at the lowest levels should roll up to the higher levels so that nothing is left out and no extra work is performed. - 4/40 rule: NO work package (task) should be shorter than four hours or longer than 40 hours in duration. - 8/80 rule: Similar to 4/40 rule; but with bigger limits. CREATE WBS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 44 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 45. CREATE WBS (Outputs)  Scope Baseline The SCOPE BASELINE is the approved version of a scope statement, WBS, and its associated WBS dictionary, which can be changed only through formal change control procedures and is used as a basis for comparison. It is a component of the project management plan. Components of the scope baseline include:  Project Scope Statement.  WBS.  Work Package: The lowest level of the WBS is a work package with a unique identifier. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information and form a code of accounts. Each work package is part of a control account. A control account is a management control point where scope, budget, and schedule are integrated and compared to the earned value for performance measurement. A control account has two or more work packages, though each work package is associated with a single control account.  Planning Package: A control account may include one or more planning packages. A planning package is a work breakdown structure component below the control account and above the work package with known work content but without detailed schedule activities. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 45 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 46.  WBS Dictionary: The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS. Most of the information included in the WBS dictionary is created by other processes and added to this document at a later stage. Information in the WBS dictionary may include but is not limited to: - Code of account identifier, - Description of work, - Assumptions and constraints, - Responsible organization, - Schedule milestones, - Associated schedule activities, - Resources required, - Cost estimates, - Quality requirements, - Acceptance criteria, - Technical references, - Agreement information. CREATE WBS (Outputs) Scope Baseline Scope Statement WBS Dictionary WBS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 46 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 47. CREATE WBS (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 47 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 48. Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project. This process is performed once or at predefined points in the project. PLAN SCHEDULE MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 48 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 49. PLAN SCHEDULE MANAGEMENT  Project Scheduling Methods:  Iterative Scheduling with a Backlog: - Form of Rolling Wave Planning based on adaptive life cycles, such as the agile approach for product development. - The requirements are documented in user stories that are then prioritized and refined just prior to construction, and the product features are developed using time-boxed periods of work. - Often used to deliver incremental value to the customer or when multiple teams can concurrently develop a large number of features that have few interconnected dependencies. - Appropriate for many projects as indicated by the widespread and growing use of adaptive life cycles for product development. - It welcomes changes throughout the development life cycle. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 49 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 50.  Project Scheduling Methods (Cont.)  On-Demand Scheduling: - This approach, typically used in a Kanban system, is based on the theory-of constraints and pull-based scheduling concepts from lean manufacturing to limit a team’s work in progress in order to balance demand against the team’s delivery throughput. - Does not rely on a schedule that was developed previously for the development of the product or product increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately as resources become available. - Often used for projects that evolve the product incrementally in operational or sustainment environments, and where tasks may be made relatively similar in size and scope or can be bundled by size and scope. PLAN SCHEDULE MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 50 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 51. Kanban: Simple Real Example PLAN SCHEDULE MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 51 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 52. PLAN SCHEDULE MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 52 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 53. PLAN SCHEDULE MANAGEMENT (Outputs)  Schedule Management Plan The schedule management plan is a component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule. The schedule management plan may be formal or informal, highly detailed, or broadly framed based on the needs of the project, and includes appropriate control thresholds. The Schedule Management Plan can establish the following:  Project Schedule Model Development: The scheduling methodology and the scheduling tool to be used in the development of the project schedule model are specified.  Level of Accuracy: The level of accuracy specifies the acceptable range used in determining realistic activity duration estimates and may include an amount for contingencies. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 53 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 54.  Schedule Management Plan (Cont.) The schedule management plan can establish the following (Cont.):  Release and Iteration Length: When using an adaptive life cycle, the time-boxed periods for releases, waves, and iterations are specified. - Time-Boxed periods are durations during which the team works steadily toward completion of a goal. - Time-boxing helps to minimize scope creep as it forces the teams to process essential features first, then other features when time permits..  Units of Measure: Each unit of measurement (such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers, or cubic yards for quantity measures) is defined for each of the resources. PLAN SCHEDULE MANAGEMENT (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 54 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 55.  Schedule Management Plan (Cont.) The schedule management plan can establish the following (Cont.):  Organizational Procedures Links: The work breakdown structure (WBS) provides the framework for the schedule management plan, allowing for consistency with the estimates and resulting schedules.  Project Schedule Model Maintenance: The process used to update the status and record progress of the project in the schedule model during the execution of the project is defined.  Control Thresholds: Variance thresholds for monitoring schedule performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. - Thresholds are typically expressed as percentage deviations from the parameters established in the baseline plan. PLAN SCHEDULE MANAGEMENT (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 55 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 56.  Schedule Management Plan (Cont.) The schedule management plan can establish the following (Cont.):  Rules of Performance Measurement: Earned value management (EVM) rules or other physical measurement rules of performance measurement are set. For example, the schedule management plan may specify: - Rules for establishing percent complete, - EVM techniques (e.g., baselines, fixed-formula, percent complete, etc.) to be employed, - Schedule performance measurements such as schedule variance (SV) and schedule performance index (SPI) used to assess the magnitude of variation to the original schedule baseline.  Reporting Formats: The formats and frequency for the various schedule reports are defined. PLAN SCHEDULE MANAGEMENT (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 56 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 57. DEFINE ACTIVITIES Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables. The key benefit of this process is that it decomposes work packages into schedule activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 57 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 58. DEFINE ACTIVITIES (Outputs)  Activity List Activity List includes the schedule activities required on the project.  For projects that use rolling wave planning or agile techniques, the activity list will be updated periodically as the project progresses.  The activity list includes: - Activity Identifier. - Scope of work description for each activity in sufficient detail to ensure that project team members understand what work is required to be completed. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 58 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 59. DEFINE ACTIVITIES (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 59 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 60. DEFINE ACTIVITIES (Outputs)  Activity Attributes Activity Attributes extend the description of the activity by identifying multiple components associated with each activity. Activity attributes are used for schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports.  Milestone List Milestone is a significant point or event in a project. Milestones have zero duration because they represent a significant point or event. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 60 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 61. Milestone List Project Start Date: Project Manager Project Sponsor Expected Completion Date: Milestone Number: Milestone Name: Date: Mandatory/Optional Completion Date: Verifications Comments: DEFINE ACTIVITIES (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 61 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 62. SEQUENCE ACTIVITIES Sequence Activities is the process of identifying and documenting relationships among the project activities. The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints. This process is performed throughout the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 62 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 63. SEQUENCE ACTIVITIES (T & T)  Precedence Diagramming Method The Precedence Diagramming Method (PDM) is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. - Finish-to-Start (FS) (most commonly used): installing the operating system on a PC (successor) cannot start until the PC hardware is assembled (predecessor). - Finish-to-Finish (FF): For example, writing a document (predecessor) is required to finish before editing the document (successor) can finish. - Start-to-Start (SS): For example, level concrete (successor) cannot begin until pour foundation (predecessor) begins. - Start-to-Finish (SF) (very rarely used): For example, a new accounts payable system (successor) has to start before the old accounts payable system can be shut down (predecessor). PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 63 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 64. Precedence Diagramming Method (PDM) RelationshipTypes SEQUENCE ACTIVITIES (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 64 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 65. SEQUENCE ACTIVITIES (T & T)  Dependency Determination and Integration 1. Mandatory Dependencies (Hard Logic): Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work. Mandatory dependencies often involve physical limitations, such as on a construction project, where it is impossible to erect the superstructure until after the foundation has been built. 2. Discretionary Dependencies (Preferred Logic, Preferential Logic, or Soft Logic): Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. For example, generally accepted best practices recommend that during construction, the electrical work should start after finishing the plumbing work. Important Note: Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 65 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 66. 3. External Dependencies: External dependencies involve a relationship between project activities and non-project activities. These dependencies are usually outside of the project team’s control. For example, the testing activity in a software project may be dependent on the delivery of hardware from an external source. 4. Internal Dependencies: Internal dependencies involve a precedence relationship between project activities and are generally inside the project team’s control. For example, if the team cannot test a machine until they assemble it. SEQUENCE ACTIVITIES (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 66 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 67.  Leads and Lags A LEAD is the amount of time a successor activity can be advanced with respect to a predecessor activity A LAG is the amount of time a successor activity will be delayed with respect to a predecessor activity. Important Notes: - Lead is often represented as a negative value for lag. - The use of leads and lags should not replace schedule logic. - Duration Estimates do not include any leads or lags.  Project Schedule Network Diagram Graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities. It can include full project details, or have one or more summary activities. A summary narrative can accompany the diagram and describe the basic approach used to sequence the activities. Any unusual activity sequences within the network should be fully described within the narrative. SEQUENCE ACTIVITIES (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 67 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 68. SEQUENCE ACTIVITIES (T & T) Project Schedule Network Diagram Lead and Lag Important Notes: - Path Convergence: Activities that have multiple predecessor activities. - Path Divergence:Activities that have multiple successor activities. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 68 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 69. ESTIMATE ACTIVITY DURATIONS Estimate Activity Durations is the process of estimating the number of work periods needed to complete individual activities with estimated resources. The key benefit of this process is that it provides the amount of time each activity will take to complete. This process is performed throughout the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 69 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 70.  Factors for consideration when estimating duration include:  Law of Diminishing Returns: When one factor (e.g., resource) used to determine the effort required to produce a unit of work is increased while all other factors remain fixed, a point will eventually be reached at which additions of that one factor start to yield progressively smaller or diminishing increases in output. ESTIMATE ACTIVITY DURATIONS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 70 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 71.  Number of Resources: Increasing the number of resources to twice the original number of the resources does not always reduce the time by half, as it may increase extra duration due to risk, and at some point adding too many resources to the activity may increase duration due to knowledge transfer, learning curve, additional coordination, and other factors involved.  Advances in Technology: For example, an increase in the output of a manufacturing plant may be achieved by procuring the latest advances in technology, which may impact duration and resource needs.  Motivation of Staff: The project manager needs to be aware of Student Syndrome -or procrastination- when people start to apply themselves only at the last possible moment before the deadline, and Parkinson’s Law where work expands to fill the time available for its completion. ESTIMATE ACTIVITY DURATIONS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 71 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 72. ESTIMATE ACTIVITY DURATIONS (T & T)  Analogous Estimating (Top-Bottom) Analogous estimating is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Analogous estimating uses parameters from a previous, similar project, such as duration, budget, size, weight, and complexity, as the basis for estimating the same parameter or measure for a future project.  Frequently used to estimate project duration when there is a limited amount of detailed information about the project.  Generally less costly and less time-consuming than other techniques, but it is also less accurate.  Most reliable when the previous activities are similar in fact and not just in appearance, and the project team members preparing the estimates have the needed expertise. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 72 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 73. ESTIMATE ACTIVITY DURATIONS (T & T)  Parametric Estimating Parametric estimating is an estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters. Parametric estimating uses a statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and duration. For Example: If the assigned resource is capable of installing 25 meters of cable per hour, the duration required to install 1,000 meters is 40 hours.  Bottom-Up Estimating Bottom-up is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of theWBS. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 73 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 74. ESTIMATE ACTIVITY DURATIONS (T & T)  Three-Point Estimating The accuracy of single-point duration estimates may be improved by considering estimation uncertainty and risk. Using Three-Point estimates helps define an approximate range for an activity’s duration:  Most likely (tM): This estimate is based on the duration of the activity, given the resources likely to be assigned, their productivity, realistic expectations of availability for the activity, dependencies on other participants, and interruptions.  Optimistic (tO): The activity duration based on analysis of the best-case scenario for the activity.  Pessimistic (tP): The duration based on analysis of the worst-case scenario for the activity. One commonly used formula is Triangular Distribution: tE = (tO + tM + tP) / 3. Important Note: - Triangular distribution is used when there is insufficient historical data or when using judgmental data. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 74 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 75. ESTIMATE ACTIVITY DURATIONS (T & T)  Data Analysis Data analysis techniques that can be used for this process include but are not limited to:  Alternatives Analysis: Alternatives analysis is used to compare various levels of resource capability or skills; scheduling compression techniques; different tools (manual versus automated); and make, rent, or buy decisions regarding the resources. This allows the team to weigh resource, cost, and duration variables to determine an optimal approach for accomplishing project work.  Reserve Analysis: Reserve analysis is used to determine the amount of Contingency and Management Reserve needed for the project. Duration estimates may include contingency reserves, sometimes referred to as schedule reserves, to account for schedule uncertainty. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 75 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 76. Contingency Reserves Management Reserves To Address Known Unknowns, Identi able, Foreseeable Uncertainty Risks To Address Unknown Unknowns, Unidentifiable Unforeseeable Uncertainty Measurable Within Reasonable Limits of Accuracy Cannot Be Measured With Any Precision Based on Risk Register And Risk Plans/Responses For Potential Events Conditions Not Associated With Any Speci c Events or Conditions Included In The Cost Baseline Not Included In The Cost Baseline Managed By Project Manager Requires Management Approval To Access Any Unspent Contingency Converted To Profit/Fee Any Unspent Reserve Realized As Pro t/Fee Can be % or Fixed Number or May Be Developed By Using Quantitative Analysis Methods. Simply As A Percentage (5%, 10%, Or 15%, For Example) of The Cost of The Project Part of Overall Project Budget Part of Overall Project Budget ESTIMATE ACTIVITY DURATIONS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 76 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 77. ESTIMATE ACTIVITY DURATIONS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 77 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 78.  Decision Making Decision-making techniques that can be used in this process include but are not limited to voting. One variation of the voting method that is often used in Agile-Based Projects is called the fist of five (also called fist to five). In this technique, 1. The project manager asks the team to show their level of support for a decision by holding up a closed fist (indicating no support) up to five fingers (indicating full support). 2. If a team member holds up fewer than three fingers, the team member is given the opportunity to discuss any objections with the team. 3. The project manager continues the fist-of-five process until the team achieves consensus (everyone holds up three or more fingers) or agrees to move on to the next decision. ESTIMATE ACTIVITY DURATIONS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 78 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 79.  Meetings The project team may hold meetings to estimate activity durations. When using an agile approach, it is necessary to conduct sprint or iteration planning meetings to discuss prioritized product backlog items (user stories) and decide which of these items the team will commit to work on in the upcoming iteration. - This meeting is usually held on the first day of the iteration and is attended by the Product Owner, the Scrum Team, (Cross-functional team members) and the Project Manager (Team facilitator). - The outcome of the meeting includes an iteration backlog, as well as assumptions, concerns, risks, dependencies, decisions, and actions. ESTIMATE ACTIVITY DURATIONS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 79 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 80. The AgileTeam and the Backlog. ESTIMATE ACTIVITY DURATIONS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 80 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 81. ESTIMATE ACTIVITY DURATIONS (Outputs)  Duration Estimates Duration estimates are quantitative assessments of the likely number of time periods that are required to complete an activity, a phase, or a project. Important Note: Duration estimates do not include any Leads or Lags.  Basis of Estimates The amount and type of additional details supporting the duration estimate vary by application area. Regardless of the level of detail. Important Note: The supporting documentation should provide a clear and complete understanding of how the duration estimate was derived. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 81 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 82. DEVELOP SCHEDULE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 82 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 83. Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring and controlling. The key benefit of this process is that it generates a schedule model with planned dates for completing project activities. This process is performed throughout the project. Developing an acceptable project schedule is an iterative process. The schedule model is used to determine the planned start and finish dates for project activities and milestones based on the best available information. Schedule development can require the review and revision of duration estimates, resource estimates, and schedule reserves to establish an approved project schedule that can serve as a baseline to track progress. DEVELOP SCHEDULE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 83 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 84. DEVELOP SCHEDULE PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 84 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 85. DEVELOP SCHEDULE (T & T)  Schedule Network Analysis Schedule network analysis is the overarching technique used to generate the project schedule model. It employs several other techniques such as critical path method, resource optimization techniques, and modeling techniques. Additional analysis includes but is not limited to:  Assessing the need to aggregate schedule reserves to reduce the probability of a schedule slip when multiple paths converge at a single point in time or when multiple paths diverge from a single point in time, to reduce the probability of a schedule slip.  Reviewing the network to see if the critical path has high-risk activities or long lead items that would necessitate use of schedule reserves or the implementation of risk responses to reduce the risk on the critical path. Important Note: Schedule network analysis is an iterative process that is employed until a viable schedule model is developed. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 85 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 86. DEVELOP SCHEDULE (T & T)  Critical Path Method (CPM) The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration. - The critical path method is used to calculate the critical path(s) and the amount of total and free float or schedule flexibility. - TOTAL FLOAT or schedule flexibility: is the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date. Total Float = LS – ES = LF – EF - FREE FLOAT: is the amount of time that a schedule activity can be delayed without delaying the early start date of any successor. Free Float = Earliest ES of Following Activities - ES of Present Activity -Duration of Present Activity. Important Notes: - Critical path is normally characterized by Zero total float on the critical path, and may have positive, or negative total float depending on the constraints applied. - Free Float for any activity on the Critical Path is equal to Zero PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 86 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 87. DEVELOP SCHEDULE (T & T) - Activity Duration = EF - ES + 1= LF – LS +1 - Early Finish (EF) = (ES + duration) – 1 - Early Start (ES) = (EF of predecessor) + 1 - Late Finish (LF) = (LS of successor) – 1 - Late Start (LS) = (LF – duration) + 1 Important Note: - A project can have several, parallel, near critical paths or near critical paths. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 87 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 88. Example of Critical Path Method DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 88 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 89. DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 89 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 90. DEVELOP SCHEDULE (T & T)  Resource Optimization Resource optimization is used to adjust the start and finish dates of activities to adjust planned resource use to be equal to or less than resource availability. Examples include but are not limited to:  Resource Leveling: A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing the demand for resources with the available supply.  Resource Smoothing: A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. Resource Levelling Resource Smoothing Adjust Actives Start and Finish to get balanced resource requirements Adjust Activities Start and Finish Within Their Free /Total Float Used when we have same Resources for same period Put fixed limit for resources Done on Critical Path Not on Critical path It may extend the project No project extension PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 90 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 91. DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 91 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 92. DEVELOP SCHEDULE (T & T)  Data Analysis Data analysis techniques that can be used for this process include but are not limited to:  What-if scenario analysis: What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positive or negative, on project objectives. This is an analysis of the question, “What if the situation represented by scenario X happens?” PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 92 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 93.  Data Analysis (Cont.)  Simulation: Simulation models the combined effects of individual project risks and other sources of uncertainty to evaluate their potential impact on achieving project objectives. The most common simulation technique is Monte Carlo analysis, in which risks and other sources of uncertainty are used to calculate possible schedule outcomes for the total project. In this example, there is a 10% probability that the project will finish on or before the target date of May 13, while there is a 90% probability of completing the project by May 28. DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 93 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 94.  Schedule Compression Schedule compression techniques are used to shorten or accelerate the schedule duration without reducing the project scope in order to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression include:  Crashing: Used to shorten the schedule duration for the least incremental cost by adding resources. Examples of crashing include approving overtime, bringing in additional resources, or paying to expedite delivery. - Works only for activities on the critical path where additional resources will shorten the activity’s duration. - Does not always produce a viable alternative and may result in increased risk and/or cost.  Fast Tracking: Activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. - May result in rework and increased risk. - Only works when activities can be overlapped to shorten the project duration on the critical path. - Using leads in case of schedule acceleration usually increases coordination efforts between the activities concerned and increases quality risk. - May also increase project costs. DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 94 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 95. DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 95 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 96.  Agile Release Planning Agile release planning provides a high-level summary timeline of the release schedule (typically 3 to 6 months) based on the product roadmap and the product vision for the product’s evolution. - Determines the number of iterations or sprints in the release, and allows the product owner and team to decide how much needs to be developed and how long it will take to have a releasable product based on business goals, dependencies, and impediments. - Since features represent value to the customer, the timeline provides a more easily understood project schedule as it defines which feature will be available at the end of each iteration, which is exactly the depth of information the customer is looking for. DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 96 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 97. Relationship Between ProductVision, Release Planning, and Iteration Planning DEVELOP SCHEDULE (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 97 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 98.  Schedule Baseline A schedule baseline is the approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results. - It is accepted and approved by the appropriate stakeholders as the schedule baseline with baseline start dates and baseline finish dates. - During monitoring and controlling, the approved baseline dates are compared to the actual start and finish dates to determine if variances have occurred. - A component of the project management plan.  Project Schedule The project schedule is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources. t is more often presented graphically, using one or more of the following formats: - Bar Charts - Milestone Charts - Project Schedule Network Diagrams DEVELOP SCHEDULE (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 98 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 99. DEVELOP SCHEDULE (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 99 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 100. DEVELOP SCHEDULE (Outputs)  Schedule Data The collection of information for describing and controlling the schedule. The schedule data includes, at a minimum, the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints. Information frequently supplied as supporting detail includes but is not limited to: - Resource requirements by time period,often in the form of a resource histogram; - Alternative schedules, such as best-case or worst-case, not resource-leveled or resource-leveled, or with or without imposed dates; - Applied schedule reserves. - Schedule data could also include such items as resource histograms, cash-flow projections, order and delivery schedules, or other relevant information.  Project Calendars Identifies working days and shifts that are available for scheduled activities. - It distinguishes time periods in days or parts of days that are available to complete scheduled activities from time periods that are not available for work. - May require more than one project calendar to allow for different work periods for some activities to calculate the project schedule. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 100 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 101. PLAN COST MANAGEMENT Plan Cost Management is the process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled. The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project. This process is performed once or at predefined points in the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 101 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 102. PLAN COST MANAGEMENT (Outputs)  Cost Management Plan Describes how the project costs will be planned, structured, and controlled. - Units of Measure. - Level of Precision: This is the degree to which cost estimates will be rounded up or down (e.g., US$995.59 to US$1,000), based on the scope of the activities and magnitude of the project. - Level of Accuracy: The acceptable range (e.g., ±10%) used in determining realistic cost estimates is specified, and may include an amount for contingencies. - Organizational Procedures Links: The WBS component used for the project cost accounting is called the control account. - Control Thresholds: Variance thresholds for monitoring cost performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the baseline plan. - Rules of Performance Measurement: Earned value management (EVM) rules of performance measurement are set. - Reporting Formats: The formats and frequency for the various cost reports are defined. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 102 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 103. PLAN COST MANAGEMENT (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 103 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 104. ESTIMATE COSTS Estimate Costs is the process of developing an approximation of the cost of resources needed to complete project work. The key benefit of this process is that it determines the monetary resources required for the project. This process is performed periodically throughout the project as needed. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 104 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 105. ESTIMATE COSTS  KeyTerms For Estimate Costs The accuracy of a project estimate will increase as the project progresses through the project life cycle. For example, a project in the initiation phase may have a Rough Order of Magnitude (ROM). Later in the project, as more information is known, project may have Definitive estimates. Order of Magnitude Estimate -25% to +75% Preliminary Estimate -15% to + 50% Budget Estimate -10% to +25% Definitive Estimate -5% to +10% Final Estimate 0% PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 105 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 106.  KeyTerms For Estimate Costs (Cont.)  Depreciation Methods: 1. Straight-line Depreciation: - Depreciation Expense = Asset Cost / Useful Life - Depreciation Expense = (Asset Cost – ScrapValue) / Useful Life - Depreciation Rate = 100% / Useful Life 2. Double Declining Balance - Depreciation Rate = 2 * (100% / Useful Life) - Depreciation Expense = Depreciation Rate * BookValue at Beginning ofYear - BookValue = BookValue at beginning of year - Depreciation Expense The Depreciation Rate stays the same over the years, but the Depreciation Expense gets smaller each year because it is calculated from a smaller book value each year. (Make sure the asset's book value does not fall below its Scrap value) 3. Sum-of-Years' Digits Method - Sum of the digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. - Depreciation rate = fraction of years left and sum of the digits (i.e. 4/15th) Both depreciation rate and depreciation fraction get smaller over time. Example: Sum of the digits: If the useful life is 5, then it is 5 + 4 + 3 + 2 + 1 =15 Depreciation rate: 5/15th for the 1st year, 4/15 for 2nd …; and 1/15th for the 5th year. ESTIMATE COSTS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 106 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 107. Example (Double Declining Balance) A machine that cost $400,000 has an estimated residual value of $40,000 and an estimated useful life of four years. The company uses Double-Declining-Balance depreciation. Calculate its book value at the end of year 3. Solution: Depreciation Rate = 2 * (100% / Useful Life) = 2*(100%/4) = 50% 1st Year Depreciation = 50% * $400,000 = $200,000 2nd Year Depreciation = 50% * ($400,000- $200,000) = $100,000 3rd Year Depreciation = 50% * ($400,000-($200,000+ $100,000)) = $50,000 BookValue at the end of year 3 = ($400,000-($200,000+ $100,000+ $50,000)) = $50,000 Example (Double Declining Balance) A machine that cost $600,000 has an estimated useful life of five years. The company uses Sum-of-Years' Digits depreciation. Calculate its book value at the end of year 3. Solution: Sum of the digits = 5+4+3+2+1=15 1st Year Depreciation = 5/15 * $600,000 = $200,000 2nd Year Depreciation = 4/15 * $600,000= $160,000 3rd Year Depreciation = 3/15 * $600,000= $120,000 BookValue at the end of year 3 = ($600,000-($200,000+ $160,000+ $120,000)) = $120,000 ESTIMATE COSTS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 107 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 108. Depreciation Methods ESTIMATE COSTS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 108 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 109.  KeyTerms For Estimate Costs (Cont.)  Average or Mean:The sum of all the members of the list divided by the number of items in the list.  Median: Arrange the values from lowest value to highest value and pick the middle one. Example: 4 is the median in 2, 4, 6 (If there is an even number of values, calculate the mean of the two middle values. Example: 5 is the median in 2, 4, 6, 8 because 4 + 6 / 2 = 5)  Mode: The most frequent value in a given data set.  Range:The Difference highest the highest and lowest numbers in a set of numbers. ESTIMATE COSTS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 109 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 110.  Types of Cost  Direct Cost: Directly attributable to project work. Such as: team travel, recognitions, team wages.  Indirect Cost: Such as overhead, benefits, and costs incurred for more than one project. Such as: equipment, rental cost  Fixed Cost: Costs that are not changed with production such as: setup cost and rental cost.  Variable Cost: Costs that are changed with Production/Work such as: material and labors, supplies. Important Note: - Opportunity Cost: Is the value of the project NOT chosen. (Project B was selected over project A, therefore the opportunity cost is the unrealized profit of project A. ); Note that NO calculation is required. - Sunk Cost: Is the cost that has already been incurred, and there is no way to recover this cost. As the name implies – the money is sunk, gone, down the drain, history (Should be Ignored in future project Decisions); There is no calculation required for arriving at the Sunk Cost. It is always equal to the Actual Cost spent to date. ESTIMATE COSTS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 110 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 111. Question: The management is reviewing the budget for the year 2018, and is evaluating the projects ROI, and its usefulness in the market. The management is also going to look at the projects that were started in the past 5 years, but were put on hold for some reason. In making future project decisions,which of the following should not be considered? A. EarnedValue B. Benefit Cost Ratio C. Sunk Cost D. Fixed Cost Question: You are part of a project selection team evaluating three proposed projects and you need to select the project that would bring the best return for the organization. Project A has an NPV of $25,000 and an IRR of 1.5, Project B has a NPV of $30,000 and an IRR of 1.25, and Project C has an NPV of $15,000 and an IRR of 1.5. What would be the opportunity cost of selecting Project B over Project A? A. $15,000 B. $5,000 C. $25,000 D. $30,000 ESTIMATE COSTS PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 111 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 112.  Three-Point Estimating Two commonly used formula is Triangular Distribution: cE = (cO + cM + cP) / 3. Beta Distribution (PERT): cE = (cO + 4cM + cP) / 6 ESTIMATE COSTS (T & T) Important Notes: - PERT Standard Deviation (Single Activity) = σ = (Pessimistic - Optimistic) / 6 - PERT Activity Variance =Variance = ((Pessimistic - Optimistic) /6)2 - PERT Standard Deviation (All Activities)= √sum(Variances) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 112 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 113. ESTIMATE COSTS (T & T)  Data Analysis  Alternatives Analysis  Reserve Analysis  Cost of quality: The cost of quality (COQ) associated with a project consists of one or more of the following costs - Prevention Costs: Costs related to the Prevention of poor quality in the products, deliverables, or services of the specific project. - Appraisal Costs: Costs related to evaluating, measuring, auditing, and testing the products, deliverables, or services of the specific project. - Failure Costs (internal/external): Costs related to Non- Conformance of the products, deliverables, or services to the needs or expectations of the stakeholders. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 113 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 114. ESTIMATE COSTS (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 114 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 115. ESTIMATE COSTS (Outputs)  Cost Estimates Cost estimates include quantitative assessments of the probable costs required to complete project work, as well as contingency amounts to account for identified risks,and management reserve to cover unplanned work.  Basis of Estimates Regardless of the level of detail, the supporting documentation should provide a clear and complete understanding of how the cost estimate was derived. Supporting detail for cost estimates may include: - Documentation of the basis of the estimate (i.e., how it was developed), - Documentation of all assumptions made, - Documentation of any known constraints, - Documentation of identified risks included when estimating costs, - Indication of the range of possible estimates (e.g., US$10,000 (±10%) to indicate that the item is expected to cost between a range of values), - Indication of the confidence level of the final estimate. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 115 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 116. DETERMINE BUDGET Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled. This process is performed once or at predefined points in the project. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 116 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 117. DETERMINE BUDGET (T & T)  Cost Aggregation Cost estimates are aggregated by work packages in accordance with the WBS. The work package cost estimates are then aggregated for the higher component levels of the WBS (such as control accounts) and, ultimately, for the entire project.  Funding Limit Reconciliation The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project. A variance between the funding limits and the planned expenditures will sometimes necessitate the rescheduling of work to level out the rate of expenditures. This is accomplished by placing imposed date constraints for work into the project schedule.  Financing Financing entails acquiring funding for projects. It is common for long-term infrastructure, industrial, and public services projects to seek external sources of funds. If a project is funded externally, the funding entity may have certain requirements that are required to be met. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 117 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 118. DETERMINE BUDGET (Outputs)  Cost Baseline The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures. It is used as a basis for comparison to actual results. - The cost baseline is developed as a summation of the approved budgets for the different schedule activities. - As changes warranting the use of management reserves arise, the change control process is used to obtain approval to move the applicable management reserve funds into the cost baseline. - Project Budget = Management Reserves + Cost Baseline.  Project Funding Requirements Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline. The cost baseline will include projected expenditures plus anticipated liabilities. - Funding often occurs in incremental amounts (Steps) - Total Funds Required = Management Reserves + Cost Baseline. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 118 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 119. DETERMINE BUDGET (Outputs) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 119 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 120. PLAN QUALITY MANAGEMENT  Key Concepts For Project Quality Management  Failure to meet the quality requirements can have serious negative consequences for any or all of the project’s stakeholders. For example:  Meeting customer requirements by overworking the project team may result in decreased profits and increased levels of overall project risks, employee attrition, errors, or rework.  Meeting project schedule objectives by rushing planned quality inspections may result in undetected errors, decreased profits, and increased post- implementation risks. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 120 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 121.  Key Concepts For Project Quality Management (Cont.)  Quality vs. Grade Quality as a delivered performance or result is “the degree to which a set of inherent characteristics fulfill requirements. Grade as a design intent is a category assigned to deliverables having the same functional use but different technical characteristics. Important Note:  Quality level that fails to meet quality requirements is always a problem,  A low-grade product may not be a problem. For Example: - It may not be a problem if a suitable low-grade product (one with a limited number of features) is of high quality (no obvious defects). - It may be a problem if a high-grade product (one with numerous features) is of low quality (many defects). In essence, a high-grade feature set would prove ineffective and/or inefficient due to low quality PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 121 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 122. Important Notes  Prevention (keeping errors out of the process) and Inspection (keeping errors out of the hands of the customer); Prevention is preferred over inspection. It is better to design quality into deliverables, rather than to find quality issues during inspection. The cost of preventing mistakes is generally much less than the cost of correcting mistakes when they are found by inspection or during usage.  Attribute Sampling (the result either conforms or does not conform) and Variable Sampling (the result is rated on a continuous scale that measures the degree of conformity);  Tolerances (specified range of acceptable results) and Control Limits (that identify the boundaries of common variation in a statistically stable process or process performance). PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 122 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 123.  Key Concepts For Project Quality Management (Cont.) There are FIVE levels of increasingly effective quality management as follows: 1. Usually, the most expensive approach is to let the customer find the defects. This approach can lead to warranty issues, recalls, loss of reputation, and rework costs. 2. Detect and correct the defects before the deliverables are sent to the customer as part of the quality control process. The control quality process has related costs, which are mainly the appraisal costs and internal failure costs. 3. Use quality assurance to examine and correct the process itself and not just special defects. 4. Incorporate quality into the planning and designing of the project and product. 5. Create a culture throughout the organization that is aware and committed to quality in processes and products. PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 123 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 124. PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 124 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 125.  Key Concepts For Project Quality Management (Cont.) - Crosby Zero Defects: Identify processes to remove defects, quality is built into the processes - Joseph Juran Fitness for Use: Does the product/service meet customer’s needs (1- Grade, 2- Quality conformance, 3- Reliability/maintainability, 4- Safety, 5- Actual Use). Proposed the application of Pareto’s (80/20 Principle) to Quality; as 80% of the quality issues are due to the 20% of the causes. - W.Edwards Deming: PDCA 85% of quality problem is managers’ responsibility, - Six Sigma: Achieve 3.4/1.0 million defect level (99.999%), refine the process to get rid of human error and outside influences with precise measurements, variations are random in nature. - Just In Time: Just when they are needed or just before they are needed. Eliminate build up of inventory. (Value of the inventory very close to 0%) - Total Quality Management (TQM): All members to center on quality to drive customer satisfaction , refine the process of producing the product. - Kaizen (Macro-PDCA Cycle): Implement consistent and incremental (small) improvement, to reduce costs, cycle time, drive customer satisfaction using PDCA (Plan-Do-Check-Act). PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 125 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 126.  Trends And Emerging Practices In Project Quality Management  Customer Satisfaction: Understand, evaluate, define, and manage requirements so that customer expectations are met. This requires a combination of conformance to requirements (to ensure the project produces what it was created to produce) and fitness for use (the product or service needs to satisfy the real needs). In agile environments, stakeholder engagement with the team ensures customer satisfaction is maintained throughout the project.  Continual Improvement: The Plan-Do-Check-Act (PDCA) cycle is the basis for quality improvement as defined by Shewhart and modified by Deming. In addition, quality improvement initiatives such as total quality management (TQM), Six Sigma, and Lean Six Sigma may improve both the quality of project management, as well as the quality of the end product, service, or result.  Management Responsibility: Success requires the participation of all members of the project team. Management retains, within its responsibility for quality, a related responsibility to provide suitable resources at adequate capacities.  Mutually Beneficial Partnership with Suppliers: A mutually beneficial relationship enhances the ability for both the organization and the suppliers to create value for each other, enhances the joint responses to customer needs and expectations, and optimizes costs and resources. PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 126 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 127. PLAN QUALITY MANAGEMENT PDCA DMAIC Lean Six Sigma PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 127 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 128.  Considerations For Agile/Adaptive Environments In order to navigate changes, agile methods call for frequent quality and review steps built in throughout the project rather than toward the end of the project. Recurring retrospectives regularly check on the effectiveness of the quality processes. They look for the root cause of issues then suggest trials of new approaches to improve quality. Subsequent retrospectives evaluate any trial processes to determine if they are working and should be continued or new adjusting or should be dropped from use. In order to facilitate frequent, incremental delivery, agile methods focus on small batches of work, incorporating as many elements of project deliverables as possible. Small batch systems aim to uncover inconsistencies and quality issues earlier in the project life cycle when the overall costs of change are lower. PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 128 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 129. PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 129 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 130. Plan Quality Management is the process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards. The key benefit of this process is that it provides guidance and direction on how quality will be managed and verified throughout the project. This process is performed in parallel with the other planning processes once or at predefined points in the project. PLAN QUALITY MANAGEMENT PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 130 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 131.  Decision Making Multi-criteria decision analysis tools (e.g., Prioritization Matrix) can be used to identify the key issues and suitable alternatives to be prioritized as a set of decisions for implementation. Criteria are prioritized and weighted before being applied to all available alternatives to obtain a mathematical score for each alternative. The alternatives are then ranked by score. As used in this process, it can help prioritize quality metrics. Prioritization Matrix PLAN QUALITY MANAGEMENT (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 131 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 132.  Data Representation  Flowcharts: display the sequence of steps and the branching possibilities that exist for a process that transforms one or more inputs into one or more outputs. Flowcharts show the activities, decision points, branching loops, parallel paths, and the overall order of processing by mapping the operational details of procedures that exist within a horizontal value chain. One version of a value chain, known as a SIPOC (suppliers, inputs, process, outputs, and customers) model.  Logical Data Model: Visual representation of an organization’s data, described in business language and independent of any specific technology. The logical data model can be used to identify where data integrity or other quality issues can arise.  Matrix Diagrams: Help find the strength of relationships among different factors, causes, and objectives that exist between the rows and columns that form the matrix. - L,T,Y, X, C, Shaped - Roof–Shaped.  Mind mapping. PLAN QUALITY MANAGEMENT (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 132 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 133. Flowcharts Logical Data Model PLAN QUALITY MANAGEMENT (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 133 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 134. The SIPOC Model PLAN QUALITY MANAGEMENT (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 134 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 135. PLAN QUALITY MANAGEMENT (T & T) PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 135 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE
  • 136. PLAN QUALITY MANAGEMENT (Outputs)  Quality Management Plan Describes how applicable policies, procedures, and guidelines will be implemented to achieve the quality objectives.  It describes the activities and resources necessary for the project management team to achieve the quality objectives set for the project.  May be formal or informal, detailed, or broadly framed.  Should be reviewed early in the project to ensure that decisions are based on accurate information. The benefits of this review can include a sharper focus on the project’s value proposition, reductions in costs, and less frequent schedule overruns that are caused by rework. The quality management plan may include but is not limited to the following: - Quality standards that will be used by the project; - Quality objectives of the project; - Quality roles and responsibilities; - Project deliverables and processes subject to quality review; - Quality control and quality management activities planned for the project; - Quality tools that will be used for the project; - Major procedures relevant for the project, such as dealing with nonconformance, corrective actions procedures, and continuous improvement procedures. PMP Exam Preparation; Based on PMBOK 6th Edition Eng. Shamil Habet; MSc; PMP; JPE shamilhabet@yahoo.com 136 PMP Exam Preparation; Shamil Habet; MSc; PMP; JPE