SlideShare a Scribd company logo
TASK RISK ASSESSMENT
ENTER COMPANY NAME
TASK TITLE: Tail Lifting of Equipments Date:
Activity: Lifting & Rigging TRA.
Location:
Description: Lifting & placement of Equipments using Tail Lift method
S/
No
.
HAZARD HAZARD EFFECT
RISK
EVALUATION
(Refer to
Evaluation form) CONTROLS
ACTION TO BE TAKEN
RESIDUAL
RISK
AL
AR
P
Y/
N
S P R DESCRIBE ACTION MANPOWER S P R
1.
Unskilled Workers
1. Personal
injury,
2. accident
F 6 8
1. Skilled workforce
deployed.
1. Ensure the workers involved in the
lifting activity are trained, qualified and
competent to carry out the work safely.
SPA: Lifting &
Rigging
Supervisor,
Safety
Watchman
F 3 5 Yes
2
Improper Crane
setup in
Personnel
injury. /
damage to
other tank
F 6 8
Never stand between
the load and a barrier.
Place Crane on leveled &
compacted ground with
fully extended out
riggers on wooden
sleepers.
1. Position of the crane will be controlled
by sup. Do a 360 deg swing, disengage
swing brake at 0, 90, 270, 360, to check
crane leveling.
2. Follow controls for exclusion zone as
marked on lifting plan.
3.Inspect/ checklist the equipment
(crane/ gears) before the lift, Tool box to
share movement arrangement with crane
driver/ operator/lookout/ supervisor
Certified
Riggers.
Competent
Rigging & Lifting
Supervisor.
F 3 5 Y
2. Struck with crane
during movement
Personal injury,
Damage to the
Equipment
G 6 7
1. Look outs deployment
2. Slow reverse
movement.
3. Reverse alarm
functional.
4. Defensive driving
certified operator
1. Look out to be deployed for safe
reverse movement.
2. Look out should use reflective vest.
2. Reverse alarm should be used during
reverse movement.
3. Boom should be closed during any
movement of the crane.
4. Follow the speed limits (5 Km/Hr) as
per UEPL standard for cranes.
SPA: Lifting &
Rigging
Supervisor,
Safety
Watchman
Lookouts.
G 2 3 Yes
3.
Crane collapse due
to poor ground
condition
Property
damage,
personal injury
F 5 7
1. Assess the ground
condition prior to lift.
1. Place crane on leveled/compacted
ground with fully extended outriggers.
2. Provide wooden pads underneath the
float pads of outriggers with area at least
2 times larger than that of float pad area.
4. If the poor ground conditions
encountered change the location.
5. In case of soggy conditions do not
perform the lift.
6. Don’t setup crane outrigger directly
above underground facility.
7. Always provide concrete slabs /ramps
for crossing over surface tubing/pipeline.
The should be designed so that
tubing/pipeline never takes the load
upon crane/trailer crossover
SPA: Lifting &
Rigging
Supervisor,
Safety
Watchman
F 3 5 Yes
4.
Damaged lifting
gears
Lifting Collapse,
Serious
personal
injury/Fatality
E 4 7
1. Pre Use inspection of
lifting accessories &
equipments.
2. Check the valid 3rd
party certification.
1. Ensure all lifting gears should be third
party certified.
2. Inspect all Lifting equipment and
accessories before any lifting activity
3. For choking of pipe spools with wire
rope sling, ensure proper anchorage with
the help of bulldog clamps
Check sling angles (with horizontal) are
equal to or greater then 45 deg.
De-rate WLL of shackles, slings for
different angles/configurations/modes
For single/double choker reduce the sling
SWL by 20%.
SPA: Lifting &
Rigging
Supervisor,
Safety
Watchman
E 2 5 Yes
5.
Falling / Slipping of
load
Physical Injury,
Load Hit with
Existing Piping.
G 6 7
Lifting plan, Weight of
load should be known,
Trail Lift
Slowly raise / lower the load, Lifting plan
should be available at site Lifting gear
certification, trial lift.
2.Rigging study should be available at job
site
Safety
Supervisor,
Rigger,
Banks man,
Supervisor
G 2 3
Yes
6.
Unnecessary
movement of
personnel
Personal Injury G 6 7
1.Area cordon off
2.No parallel activities
1. Area to be cordoned off with full time
supervision.
2. Stop other activities in that working
area.
Safety
Supervisor,
Banks man
G 2 3 Yes
7.
Weather
conditions
Equipment
stuck in muddy
area due to
rain, High Wind
speed
F 5 7
1.Site/area/location
survey before moving
equipment at site i.e.
Soil condition
1. Rigger/signal/outlook man visit site
before moving equipment at site.
2. HSE supervisor will ensure wind speed
limit before starting lifting operation if
wind speed exceeds from 25 knots TRA
should be revised.
Rigging
Sup,(SPA)
Crane Opt, HSE
Sup
F 3 5 Yes
2.Wait till clear visibility
achieved (in case of wind
storm)
3. Observe plant wind
speed limit before any
lifting operations.
3. No lifting if wind speed cross 30 knots
4. Wind speed Reading should be from
radio room or look out for wind sock.
Wind sock generally gets horizontal if
wind speeds are equal to or above 15
knots.
8. SIMPOS
Injuries,
Fatalities
E 7 10
Cross reference this task
with all relevant PTW's,
plans certificates one
day before job execution
subject to SIMPOS
operation
Conduct a permit planning meeting with
stakeholders one day before job
execution
Stop all SIMOP activities that fall within
the barricaded area of crane
Rigging Sup,
Crane
Operator,
Safety Watch
E 2 5 Yes
9 Crane Overload
Crane Toppling,
Structural
Failure,
Damage to
other tank,
Personnel
injury/fatality
F 6 8
Tool box talk sharing the
sequence of lift as
mentioned in lifting plan,
load chart,
Check the calibration of
SLI prior to lift.
Define exclusion zone
Check work radius prior to lift see if they
tally with the lifting plan, in case of any
variation reposition the crane.
Perform trial lift (inch the load to check
stability and verify the weight of the load
with SLI) in accordance with the lift plan.
Keep everyone out of the exclusion zone.
Competent
Lifting
Supervisor,
Certified riggers
Safety watch
(spotters)
F 4 6 Y
10
Inadequate or
inoperative safety
devices
Equipment
damage due to
overload,
Plant/facility
damage
G 6 8
Perform functional test
of mobile crane, verify
SLI readouts with proper
tools
Check whether ATB is working (audible
alarm and cut-off)
Verify SLI boom angle readout with angle
finder, Radius readout with measuring
tape, boom length with load chart (main
boom), actual load with crane hook load
or if possible test load prior to lift.
Check whether correct falls are selected
on SLI display.
Crane operator,
Rigging and
Lifting
Supervisor
G 4 5 Y
GENERAL COMMENTS: Abbreviations
1. TBT will be conducted prior to job start. SPA: Single Person Accountable
2. Unauthorized entry of the person not allowed in work premises. ATB: Anti-Block
3. PPE’s should be use (safety helmet, goggle, gloves, safety shoes ,safety harness, Face shield, welding helmet, SWL: Safe Working Load
Welding gloves,) SLI: Safe Load Indicator
4. Stand by vehicle must be present at the site in case of emergency. SIMOPS: Simultaneous Operation
5. Adequate cold drinking water readily is available at the site to prevent dehydration.
6. Housekeeping of the area should be done on prior basis before and after completion of job.
NAME OF TEAM MEMBERS
( Manager)
(Rigging & Lifting Supervisor)
(Hse Engineer/officer)
Signature RISK ASSISMENT APPROVAL
I’m satisfied that the safeguard put in place will reduce the level of Risk to an acceptable level
and the Task/Action is permitted to proceed.
Reviewed by: ____________
Date: ________________________ Time: ____________________
S = Severity; P = Probability, R = Risk
Authorizing
Signatory: _______________ DATE: ________________

More Related Content

Similar to TRA%20of%20Lifting.Tail.docx

11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docxDwarika Bhushan Sharma
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction siteNMRD Ltd
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekRoseGaming1
 
JHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdfJHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdfHaroon AbdulRahim
 
S ky jack_scissorlift_manlift
S ky jack_scissorlift_manliftS ky jack_scissorlift_manlift
S ky jack_scissorlift_manliftPunya Benja
 
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfHaroon AbdulRahim
 
Lifting plan
Lifting planLifting plan
Lifting plantnsv22
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction siteNMRD Ltd
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputGaurav Singh Rajput
 

Similar to TRA%20of%20Lifting.Tail.docx (20)

11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
Aerial Lift Safety Training by ANSV
Aerial Lift Safety Training by ANSVAerial Lift Safety Training by ANSV
Aerial Lift Safety Training by ANSV
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction site
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
 
JHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdfJHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdf
 
Job safety analysis
Job safety analysisJob safety analysis
Job safety analysis
 
S ky jack_scissorlift_manlift
S ky jack_scissorlift_manliftS ky jack_scissorlift_manlift
S ky jack_scissorlift_manlift
 
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdfJHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
JHA LIFTING ERECTION OF VESSEL EQUIPMENT.pdf
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction site
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 

Recently uploaded

2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturingssuser0811ec
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdfKamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfNurvisNavarroSanchez
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxwendy cai
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxVishalDeshpande27
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-IVigneshvaranMech
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectRased Khan
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptssuser9bd3ba
 

Recently uploaded (20)

2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturing
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 

TRA%20of%20Lifting.Tail.docx

  • 1. TASK RISK ASSESSMENT ENTER COMPANY NAME TASK TITLE: Tail Lifting of Equipments Date: Activity: Lifting & Rigging TRA. Location: Description: Lifting & placement of Equipments using Tail Lift method S/ No . HAZARD HAZARD EFFECT RISK EVALUATION (Refer to Evaluation form) CONTROLS ACTION TO BE TAKEN RESIDUAL RISK AL AR P Y/ N S P R DESCRIBE ACTION MANPOWER S P R 1. Unskilled Workers 1. Personal injury, 2. accident F 6 8 1. Skilled workforce deployed. 1. Ensure the workers involved in the lifting activity are trained, qualified and competent to carry out the work safely. SPA: Lifting & Rigging Supervisor, Safety Watchman F 3 5 Yes 2 Improper Crane setup in Personnel injury. / damage to other tank F 6 8 Never stand between the load and a barrier. Place Crane on leveled & compacted ground with fully extended out riggers on wooden sleepers. 1. Position of the crane will be controlled by sup. Do a 360 deg swing, disengage swing brake at 0, 90, 270, 360, to check crane leveling. 2. Follow controls for exclusion zone as marked on lifting plan. 3.Inspect/ checklist the equipment (crane/ gears) before the lift, Tool box to share movement arrangement with crane driver/ operator/lookout/ supervisor Certified Riggers. Competent Rigging & Lifting Supervisor. F 3 5 Y 2. Struck with crane during movement Personal injury, Damage to the Equipment G 6 7 1. Look outs deployment 2. Slow reverse movement. 3. Reverse alarm functional. 4. Defensive driving certified operator 1. Look out to be deployed for safe reverse movement. 2. Look out should use reflective vest. 2. Reverse alarm should be used during reverse movement. 3. Boom should be closed during any movement of the crane. 4. Follow the speed limits (5 Km/Hr) as per UEPL standard for cranes. SPA: Lifting & Rigging Supervisor, Safety Watchman Lookouts. G 2 3 Yes
  • 2. 3. Crane collapse due to poor ground condition Property damage, personal injury F 5 7 1. Assess the ground condition prior to lift. 1. Place crane on leveled/compacted ground with fully extended outriggers. 2. Provide wooden pads underneath the float pads of outriggers with area at least 2 times larger than that of float pad area. 4. If the poor ground conditions encountered change the location. 5. In case of soggy conditions do not perform the lift. 6. Don’t setup crane outrigger directly above underground facility. 7. Always provide concrete slabs /ramps for crossing over surface tubing/pipeline. The should be designed so that tubing/pipeline never takes the load upon crane/trailer crossover SPA: Lifting & Rigging Supervisor, Safety Watchman F 3 5 Yes 4. Damaged lifting gears Lifting Collapse, Serious personal injury/Fatality E 4 7 1. Pre Use inspection of lifting accessories & equipments. 2. Check the valid 3rd party certification. 1. Ensure all lifting gears should be third party certified. 2. Inspect all Lifting equipment and accessories before any lifting activity 3. For choking of pipe spools with wire rope sling, ensure proper anchorage with the help of bulldog clamps Check sling angles (with horizontal) are equal to or greater then 45 deg. De-rate WLL of shackles, slings for different angles/configurations/modes For single/double choker reduce the sling SWL by 20%. SPA: Lifting & Rigging Supervisor, Safety Watchman E 2 5 Yes 5. Falling / Slipping of load Physical Injury, Load Hit with Existing Piping. G 6 7 Lifting plan, Weight of load should be known, Trail Lift Slowly raise / lower the load, Lifting plan should be available at site Lifting gear certification, trial lift. 2.Rigging study should be available at job site Safety Supervisor, Rigger, Banks man, Supervisor G 2 3 Yes 6. Unnecessary movement of personnel Personal Injury G 6 7 1.Area cordon off 2.No parallel activities 1. Area to be cordoned off with full time supervision. 2. Stop other activities in that working area. Safety Supervisor, Banks man G 2 3 Yes 7. Weather conditions Equipment stuck in muddy area due to rain, High Wind speed F 5 7 1.Site/area/location survey before moving equipment at site i.e. Soil condition 1. Rigger/signal/outlook man visit site before moving equipment at site. 2. HSE supervisor will ensure wind speed limit before starting lifting operation if wind speed exceeds from 25 knots TRA should be revised. Rigging Sup,(SPA) Crane Opt, HSE Sup F 3 5 Yes
  • 3. 2.Wait till clear visibility achieved (in case of wind storm) 3. Observe plant wind speed limit before any lifting operations. 3. No lifting if wind speed cross 30 knots 4. Wind speed Reading should be from radio room or look out for wind sock. Wind sock generally gets horizontal if wind speeds are equal to or above 15 knots. 8. SIMPOS Injuries, Fatalities E 7 10 Cross reference this task with all relevant PTW's, plans certificates one day before job execution subject to SIMPOS operation Conduct a permit planning meeting with stakeholders one day before job execution Stop all SIMOP activities that fall within the barricaded area of crane Rigging Sup, Crane Operator, Safety Watch E 2 5 Yes 9 Crane Overload Crane Toppling, Structural Failure, Damage to other tank, Personnel injury/fatality F 6 8 Tool box talk sharing the sequence of lift as mentioned in lifting plan, load chart, Check the calibration of SLI prior to lift. Define exclusion zone Check work radius prior to lift see if they tally with the lifting plan, in case of any variation reposition the crane. Perform trial lift (inch the load to check stability and verify the weight of the load with SLI) in accordance with the lift plan. Keep everyone out of the exclusion zone. Competent Lifting Supervisor, Certified riggers Safety watch (spotters) F 4 6 Y 10 Inadequate or inoperative safety devices Equipment damage due to overload, Plant/facility damage G 6 8 Perform functional test of mobile crane, verify SLI readouts with proper tools Check whether ATB is working (audible alarm and cut-off) Verify SLI boom angle readout with angle finder, Radius readout with measuring tape, boom length with load chart (main boom), actual load with crane hook load or if possible test load prior to lift. Check whether correct falls are selected on SLI display. Crane operator, Rigging and Lifting Supervisor G 4 5 Y GENERAL COMMENTS: Abbreviations 1. TBT will be conducted prior to job start. SPA: Single Person Accountable 2. Unauthorized entry of the person not allowed in work premises. ATB: Anti-Block 3. PPE’s should be use (safety helmet, goggle, gloves, safety shoes ,safety harness, Face shield, welding helmet, SWL: Safe Working Load Welding gloves,) SLI: Safe Load Indicator 4. Stand by vehicle must be present at the site in case of emergency. SIMOPS: Simultaneous Operation 5. Adequate cold drinking water readily is available at the site to prevent dehydration. 6. Housekeeping of the area should be done on prior basis before and after completion of job. NAME OF TEAM MEMBERS ( Manager) (Rigging & Lifting Supervisor) (Hse Engineer/officer) Signature RISK ASSISMENT APPROVAL I’m satisfied that the safeguard put in place will reduce the level of Risk to an acceptable level and the Task/Action is permitted to proceed. Reviewed by: ____________ Date: ________________________ Time: ____________________
  • 4. S = Severity; P = Probability, R = Risk Authorizing Signatory: _______________ DATE: ________________