TVC Tracking for New Construction Projects
A Path Forward
MERCER TECHNICAL SERVICES
Historical Perspective
• 1935, The "American Tentative Standard Code for Pressure Piping”,
ASA B31.1 was issued
• 1955, Section 8, designated B31.1.8, represented a significant
technical advancement in requirements for natural gas transmission
and distribution piping systems
• 1970, DOT issues original versions of 49 CFR Parts 191 & 192
• 2011, PHMSA issues Advisory Bulletin requiring material to be
“Traceable, Verifiable and Complete”
• 2016, PHMSA NPRM: Safety of Gas Transmission & Gathering Pipelines
MERCER TECHNICAL SERVICES
Steel Pipe (proposed rule)
§ 192.67 Records: Materials.
Each operator of transmission pipelines must acquire
and retain for the life of the pipeline the original
steel pipe manufacturing records that document
tests, inspections, and attributes required by the
manufacturing specification in effect at the time the
pipe was manufactured, including, but not limited to,
yield strength, ultimate tensile strength, and
chemical composition of materials for pipe in
accordance with § 192.55.
MERCER TECHNICAL SERVICES
Pipeline Components (proposed rule)
§ 192.205 Records: Pipeline components.
Each operator of transmission pipelines must acquire and
retain records documenting the manufacturing standard
and pressure rating to which each valve was
manufactured and tested in accordance with this
subpart. Flanges, fittings, branch connections, extruded
outlets, anchor forgings, and other components with
material yield strength grades of 42,000 psi or greater
must have records documenting the manufacturing
specification in effect at the time of manufacture,
including, but not limited to, yield strength, ultimate
tensile strength, and chemical composition of materials.
MERCER TECHNICAL SERVICES
Welders (proposed rule)
§ 192.227 Qualification of welders.
* * * * *
(c) Records for transmission pipelines demonstrating
each individual welder qualification in accordance
with this section must be retained for the life of the
pipeline.
MERCER TECHNICAL SERVICES
We Have Come a Long Way…..
MERCER TECHNICAL SERVICES
Typical Work Flow
Receive
Material at Pipe
Yard and Create
a Pipe Tally with
HN and JN
MTR’s
Pipe Mill
String Pipe
and Document
Check HN and
JN to Pipe Tally
Load Out Pipe
At Pipe Yard and
Track Inventory
Check HN and
JN to Pipe Tally
As-Build Survey
Collects GPS
Shots in Ditch
and Check HN
and JN to Pipe
Tally
As-Build Survey
Off Line
Features
As-Build
Drawings, Check
HN and JN to
Pipe Tally
Data to Client
X-Check to Pipe Tally
MTR’s to Client
MERCER TECHNICAL SERVICES
Typical Records
MERCER TECHNICAL SERVICES
Risk
Risk = Probability of Failure x Consequence
(Missing Records) (Financial Impact)
MERCER TECHNICAL SERVICES
Material Identification
0
100
200
300
400
500
600
700
800
900
1,000
1930 1940 1950 1960 1970 1980 1990 2000 2010 2020
Probability of Not Meeting Code ???
MERCER TECHNICAL SERVICES
Time Dependent
0
100
200
300
400
500
600
700
800
900
1,000
Pipe Mill Coating Mill Transport Staging
Yard
Stringing Welded Hydro In-Service Audit Failure
Consequence
MERCER TECHNICAL SERVICES
Mitigate Risk
Ensure material is RTVC when consequence is low
Receive
Material at Pipe
Yard and Scan
Material
Pipe Mill
Receive MTR’s
and Enter into
Database
String Pipe
and Scan to
Track Material
Load Out Pipe
At Pipe Yard and
Scan to Track
Inventory
As-Build Survey
Collects GPS
Shots in Ditch
and Scan
As-Build Survey
Off Line
Features
As-Build
Drawings, Use
Information
From Database
Data to Client
Interactive Database
MERCER TECHNICAL SERVICES
Material Tracking Systems
• Tagging system have been in the pipeline industry
since 19XX
• Various types of tags can be used
• RFD
• Bar Codes
• Wide range of quality
• One tag does not fit all needs
• Material Database
• What is tracked in the database
• Is the database real time
MERCER TECHNICAL SERVICES
Lessons Learned - Tags
• Tags places on the inside of pipe
• Comes off the pipe and flows with the product
• Tags prevents pipe coating from being jeeped
• Tags destroyed during handling
• Pipe is cut at the firing line and pup moved ahead
• Tags deteriorated on pipe being stored due to UV
The type and style of the tags you use on your
project is a critical desicion point
MERCER TECHNICAL SERVICES
Material Database Requirements
• What data will be stored and the method of storage
• Remote access to the database
• Office
• Field
• Operator
• Database security
• Levels of access to database
• Cyber security
• Storage requirements
• Data transfer to operator at end of project
MERCER TECHNICAL SERVICES
Database
Material database can evolve into a project database
• Tracking of X-Rays
• Welder Qualifications
• Hydrostatic test
• Maintenance tickets for defective material
• Tracking location of material
• Inventory control
MERCER TECHNICAL SERVICES
Mapping
• You must be able to tie your material information
to the physical location of the material
• Fencing will not be excepted
• Survey must be integrated with the database
• Survey accuracy will be key
• Mapping material on a liner pipeline is no problem
• Mapping material for fabrication is challenging
MERCER TECHNICAL SERVICES
Planning
• As with any project, planning is key in
implementing a material tracking system
• Review the process with all stake holders
• The material tracking starts with the ordering of the
material to the final as-built into the operators
records system
• Work with the affected service providers
• Combined traditional tasks with new tasks needed
for material tracking
MERCER TECHNICAL SERVICES
Value Added
• Transparency for the project team
• Streamline communications through real time
reporting (dashboards)
• Reduce the time from physical completion of
project to completion of the project
MERCER TECHNICAL SERVICES
Contact Information
Mark E. Anderson
Vice President
Mercer Technical Services
8826 Santa Fe Drive, Suite 150
Overland Park, KS 66212
mark.anderson@mertechserv.com
P: 913.433.4099

More Related Content

What's hot

Rocky Nash Resume A
Rocky Nash Resume ARocky Nash Resume A
Rocky Nash Resume A
Rocky Nash
 
Automation of the Drilling System: What has been done, what is being done, an...
Automation of the Drilling System: What has been done, what is being done, an...Automation of the Drilling System: What has been done, what is being done, an...
Automation of the Drilling System: What has been done, what is being done, an...
Society of Petroleum Engineers
 
Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer Resume 29012015
Iain Palmer Resume 29012015
Iain Palmer
 

What's hot (20)

Brij mohan cv
Brij mohan  cvBrij mohan  cv
Brij mohan cv
 
New Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary KrichauNew Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary Krichau
 
Pipeline integrity documentation
Pipeline integrity documentationPipeline integrity documentation
Pipeline integrity documentation
 
AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion  AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion
 
Milestone checklist
Milestone checklist   Milestone checklist
Milestone checklist
 
SCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionSCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity Solution
 
Rocky Nash Resume A
Rocky Nash Resume ARocky Nash Resume A
Rocky Nash Resume A
 
Advancements cathodic protection for on grade storage tanks
Advancements cathodic protection for on grade storage tanksAdvancements cathodic protection for on grade storage tanks
Advancements cathodic protection for on grade storage tanks
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
 
National Oilwell Varco Drilling Automation and Optimization 2017 03 03
National Oilwell Varco Drilling Automation and Optimization 2017 03 03National Oilwell Varco Drilling Automation and Optimization 2017 03 03
National Oilwell Varco Drilling Automation and Optimization 2017 03 03
 
ptsresume[1]
ptsresume[1]ptsresume[1]
ptsresume[1]
 
Brian Norton
Brian NortonBrian Norton
Brian Norton
 
Design checklist instrumentation_17.01.15 (1)
Design checklist instrumentation_17.01.15 (1)Design checklist instrumentation_17.01.15 (1)
Design checklist instrumentation_17.01.15 (1)
 
Advances in Phased Array Inspection of API 620 LNG Tanks
Advances in Phased Array Inspection of API 620 LNG TanksAdvances in Phased Array Inspection of API 620 LNG Tanks
Advances in Phased Array Inspection of API 620 LNG Tanks
 
Design Checklist_Electrical
Design Checklist_Electrical Design Checklist_Electrical
Design Checklist_Electrical
 
KOM 15082014 HUC
KOM 15082014 HUCKOM 15082014 HUC
KOM 15082014 HUC
 
Automation of the Drilling System: What has been done, what is being done, an...
Automation of the Drilling System: What has been done, what is being done, an...Automation of the Drilling System: What has been done, what is being done, an...
Automation of the Drilling System: What has been done, what is being done, an...
 
Ldar Audits - Cutting Through the Fog
Ldar Audits - Cutting Through the FogLdar Audits - Cutting Through the Fog
Ldar Audits - Cutting Through the Fog
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer Resume 29012015
Iain Palmer Resume 29012015
 

Similar to INGAA TVC Presentation

Cgc general profile
Cgc general profileCgc general profile
Cgc general profile
Paul Timola
 
Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15
Bill Rogers
 
Mauli Engineering Services Presentation
Mauli Engineering Services PresentationMauli Engineering Services Presentation
Mauli Engineering Services Presentation
Mauli Engineering
 
WILLIAM MICHAEL BROWN R-1
WILLIAM MICHAEL BROWN R-1WILLIAM MICHAEL BROWN R-1
WILLIAM MICHAEL BROWN R-1
William Brown
 
Everett Nichols_Resume_Dec_2015
Everett Nichols_Resume_Dec_2015Everett Nichols_Resume_Dec_2015
Everett Nichols_Resume_Dec_2015
Everett Nichols
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
ParmeshworVetwal1
 

Similar to INGAA TVC Presentation (20)

QA QC Engineer Mechanical
QA QC Engineer MechanicalQA QC Engineer Mechanical
QA QC Engineer Mechanical
 
Engineering
EngineeringEngineering
Engineering
 
Engineering
EngineeringEngineering
Engineering
 
Engineering
EngineeringEngineering
Engineering
 
Adco presentation june 4 2013
Adco presentation june 4 2013Adco presentation june 4 2013
Adco presentation june 4 2013
 
Cgc general profile
Cgc general profileCgc general profile
Cgc general profile
 
QA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorQA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding Inspector
 
RHI Capability Summary
RHI Capability SummaryRHI Capability Summary
RHI Capability Summary
 
Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15
 
Mauli Engineering Services Presentation
Mauli Engineering Services PresentationMauli Engineering Services Presentation
Mauli Engineering Services Presentation
 
CV of Tahir Mahmood
CV of Tahir MahmoodCV of Tahir Mahmood
CV of Tahir Mahmood
 
WILLIAM MICHAEL BROWN R-1
WILLIAM MICHAEL BROWN R-1WILLIAM MICHAEL BROWN R-1
WILLIAM MICHAEL BROWN R-1
 
Process & power plants
Process & power plantsProcess & power plants
Process & power plants
 
Lory Francis Navor - CV
Lory Francis Navor - CVLory Francis Navor - CV
Lory Francis Navor - CV
 
CV
CVCV
CV
 
Everett Nichols_Resume_Dec_2015
Everett Nichols_Resume_Dec_2015Everett Nichols_Resume_Dec_2015
Everett Nichols_Resume_Dec_2015
 
2.-Introduction-to-Process-Plant-Layout-and-Piping-Design.pptx
2.-Introduction-to-Process-Plant-Layout-and-Piping-Design.pptx2.-Introduction-to-Process-Plant-Layout-and-Piping-Design.pptx
2.-Introduction-to-Process-Plant-Layout-and-Piping-Design.pptx
 
Wire arc additive manufacturing
Wire arc additive manufacturingWire arc additive manufacturing
Wire arc additive manufacturing
 
MTCcorp - Aerospace Capabilities
MTCcorp - Aerospace Capabilities MTCcorp - Aerospace Capabilities
MTCcorp - Aerospace Capabilities
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
 

Recently uploaded

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 

Recently uploaded (20)

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

INGAA TVC Presentation

  • 1. TVC Tracking for New Construction Projects A Path Forward
  • 2. MERCER TECHNICAL SERVICES Historical Perspective • 1935, The "American Tentative Standard Code for Pressure Piping”, ASA B31.1 was issued • 1955, Section 8, designated B31.1.8, represented a significant technical advancement in requirements for natural gas transmission and distribution piping systems • 1970, DOT issues original versions of 49 CFR Parts 191 & 192 • 2011, PHMSA issues Advisory Bulletin requiring material to be “Traceable, Verifiable and Complete” • 2016, PHMSA NPRM: Safety of Gas Transmission & Gathering Pipelines
  • 3. MERCER TECHNICAL SERVICES Steel Pipe (proposed rule) § 192.67 Records: Materials. Each operator of transmission pipelines must acquire and retain for the life of the pipeline the original steel pipe manufacturing records that document tests, inspections, and attributes required by the manufacturing specification in effect at the time the pipe was manufactured, including, but not limited to, yield strength, ultimate tensile strength, and chemical composition of materials for pipe in accordance with § 192.55.
  • 4. MERCER TECHNICAL SERVICES Pipeline Components (proposed rule) § 192.205 Records: Pipeline components. Each operator of transmission pipelines must acquire and retain records documenting the manufacturing standard and pressure rating to which each valve was manufactured and tested in accordance with this subpart. Flanges, fittings, branch connections, extruded outlets, anchor forgings, and other components with material yield strength grades of 42,000 psi or greater must have records documenting the manufacturing specification in effect at the time of manufacture, including, but not limited to, yield strength, ultimate tensile strength, and chemical composition of materials.
  • 5. MERCER TECHNICAL SERVICES Welders (proposed rule) § 192.227 Qualification of welders. * * * * * (c) Records for transmission pipelines demonstrating each individual welder qualification in accordance with this section must be retained for the life of the pipeline.
  • 6. MERCER TECHNICAL SERVICES We Have Come a Long Way…..
  • 7. MERCER TECHNICAL SERVICES Typical Work Flow Receive Material at Pipe Yard and Create a Pipe Tally with HN and JN MTR’s Pipe Mill String Pipe and Document Check HN and JN to Pipe Tally Load Out Pipe At Pipe Yard and Track Inventory Check HN and JN to Pipe Tally As-Build Survey Collects GPS Shots in Ditch and Check HN and JN to Pipe Tally As-Build Survey Off Line Features As-Build Drawings, Check HN and JN to Pipe Tally Data to Client X-Check to Pipe Tally MTR’s to Client
  • 9. MERCER TECHNICAL SERVICES Risk Risk = Probability of Failure x Consequence (Missing Records) (Financial Impact)
  • 10. MERCER TECHNICAL SERVICES Material Identification 0 100 200 300 400 500 600 700 800 900 1,000 1930 1940 1950 1960 1970 1980 1990 2000 2010 2020 Probability of Not Meeting Code ???
  • 11. MERCER TECHNICAL SERVICES Time Dependent 0 100 200 300 400 500 600 700 800 900 1,000 Pipe Mill Coating Mill Transport Staging Yard Stringing Welded Hydro In-Service Audit Failure Consequence
  • 12. MERCER TECHNICAL SERVICES Mitigate Risk Ensure material is RTVC when consequence is low Receive Material at Pipe Yard and Scan Material Pipe Mill Receive MTR’s and Enter into Database String Pipe and Scan to Track Material Load Out Pipe At Pipe Yard and Scan to Track Inventory As-Build Survey Collects GPS Shots in Ditch and Scan As-Build Survey Off Line Features As-Build Drawings, Use Information From Database Data to Client Interactive Database
  • 13. MERCER TECHNICAL SERVICES Material Tracking Systems • Tagging system have been in the pipeline industry since 19XX • Various types of tags can be used • RFD • Bar Codes • Wide range of quality • One tag does not fit all needs • Material Database • What is tracked in the database • Is the database real time
  • 14. MERCER TECHNICAL SERVICES Lessons Learned - Tags • Tags places on the inside of pipe • Comes off the pipe and flows with the product • Tags prevents pipe coating from being jeeped • Tags destroyed during handling • Pipe is cut at the firing line and pup moved ahead • Tags deteriorated on pipe being stored due to UV The type and style of the tags you use on your project is a critical desicion point
  • 15. MERCER TECHNICAL SERVICES Material Database Requirements • What data will be stored and the method of storage • Remote access to the database • Office • Field • Operator • Database security • Levels of access to database • Cyber security • Storage requirements • Data transfer to operator at end of project
  • 16. MERCER TECHNICAL SERVICES Database Material database can evolve into a project database • Tracking of X-Rays • Welder Qualifications • Hydrostatic test • Maintenance tickets for defective material • Tracking location of material • Inventory control
  • 17. MERCER TECHNICAL SERVICES Mapping • You must be able to tie your material information to the physical location of the material • Fencing will not be excepted • Survey must be integrated with the database • Survey accuracy will be key • Mapping material on a liner pipeline is no problem • Mapping material for fabrication is challenging
  • 18. MERCER TECHNICAL SERVICES Planning • As with any project, planning is key in implementing a material tracking system • Review the process with all stake holders • The material tracking starts with the ordering of the material to the final as-built into the operators records system • Work with the affected service providers • Combined traditional tasks with new tasks needed for material tracking
  • 19. MERCER TECHNICAL SERVICES Value Added • Transparency for the project team • Streamline communications through real time reporting (dashboards) • Reduce the time from physical completion of project to completion of the project
  • 20. MERCER TECHNICAL SERVICES Contact Information Mark E. Anderson Vice President Mercer Technical Services 8826 Santa Fe Drive, Suite 150 Overland Park, KS 66212 mark.anderson@mertechserv.com P: 913.433.4099