SlideShare a Scribd company logo
1 of 41
ANALYSIS OF EXISTING DISTRIBUTION LINE AND
FEASIBILITY STUDY ON UNDERGROUND CABLE SYSTEM,
LAKESIDE POKHARA
Bishal Rimal(BEL-070-213)
Himal Chaulagain(BEL-070-218)
Manoj Sah(BEL-070-224)
Paras Subedi(BEL-070-228)
Project Supervisor: Er.Rajendra Dhakal
Electric power distribution is the final stage in the delivery of
electric power; it carries electricity from the transmission system to
individual consumers.
Radial Distribution System
Ring Main Distribution System
Network Distribution System
Load flow study is numerical analysis of the flow of electric power
in an any system. Load flow studies basically comprises of the
determination of
Voltage and power angle
Active Power
Reactive Power
losses
INTRODUCTION
An Overhead power line is a structure used in electric power
transmission and distribution to transmit electrical energy along
large distances. It consists of one or more conductors
suspended by towers or poles
Underground cables transmit power across densely populated
or areas where land is costly or environmentally sensitive
load forecasting Load forecasting is a technique used by
energy providing companies to predict the energy needed to
meet the demand and supply equilibrium
ETAP
Platform which gives the solution for Generation,
Transmission, Distribution, Industrial,
Transportation, and Low-Voltage Power Systems
Google Earth
Geobrowser that accesses satellite and aerial
imagery, ocean bathymetry, and other geographic
data over the internet to represent the Earth as a
three-dimensional globe
Software used
 OSMTracker for Android
This application allows us to record our
track, save waypoints(geotagging).
The output of our recording can be export
into GPX file format and we can open it
through Google Earth.
To analyse the peak power demand ,losses and voltage drop on
the feeder.
To analyse the reliability of the feeder.
OBJECTIVE
To forecast the load demand for 15 years.
To analyse the feasibility in replacing the overhead
distribution line by underground cable
Economic estimation of underground system
 Data collection
NEA
Private transformer load record
No. of transformer
Single line diagram of Baidam feeder
Collection of Peak load data of past 8 fiscal years
METHODOLOGY
BAIDAM FEEDER Private NEA
Number of transformer 35 42
 Daily load log sheet of Baidam feeder 28April
2017
0
500
1000
1500
2000
2500
3000
3500
4000
4500 1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
22:00
23:00
24:00:00
Daily load curve
Kw
Field Survey
 With the help of OSMTracker for Android (for obtaining GPS
coordinate of transformer location) and Google Earth (for plotting
the transformer and its line route distance measurement)
OSMTRACKER
GPX GOOGLE EARTH Plot the location on map
Transmission lengthETAP
ETAP Simulation
Following assumption are made for the simplicity of analysis.
All peak load occurs at the same time for all transformer.
All three phase are balanced.
Power factor: 0.85
All transformers are solidly grounded.
No private consumer use reactive power compensator.
We simulate the existing distribution system on ETAP
under three conditions:
Simulation of existing system using data of 28 April
2017
Simulation of existing system using annual peak load
of fiscal year 73-74.
Simulation of existing system replacing overhead line
by underground cable beyond Jarebar using annual
peak load of fiscal year 73-74
Load Forecasting
Available Data: 66/67 to 72/73- During Load Shedding
73-74-During No Load Shedding
Trend analysis method.
From that peak load with load shedding data we forecast
the peak load of fiscal year 73/74 assuming load shedding
Relative percentage peak load variation between load
shedding period and without load shedding period is
13.95% using peak load of fiscal year 73/74
1. Simulation of existing system using data of 28 April
2017
Peak load: 3848KW @power factor 0.85
Peak KVA: 4528KVA
Demand factor: 0.47
Average Private Transformer loading: 18%
Average NEA transformer loading: 71%
Total Active power loss: 294.5KW
Percentage active power loss: 7.65%
Total reactive power loss: 383.5 KVAR
Percentage voltage drop: 11.46%
End terminal voltage: 9.74KV
RESULT AND ANALYSIS
2.Simulation of existing system using annual peak
load of fiscal year 73-74
Peak load: 6397KW @power factor 0.85
Peak KVA: 7526KVA
Demand factor: 0.78
Average Private Transformer loading: 50%
Average NEA transformer loading: 100%
Total Active power loss: 860.2KW
Percentage active power loss: 13.45%
Total reactive power loss: 1073.9 KVar
Percentage voltage drop: 20.75%
End terminal voltage: 8.8KV
3.Simulation using underground cable beyond
Jarebar
Peak load: 6397KW @power factor 0.85
Peak KVA: 7526KVA
Demand factor: 0.78
Average Private Transformer loading: 50%
Average NEA transformer loading: 100%
Total Active power loss: 788.6KW
Percentage active power loss: 12.32%
Total reactive power loss: 1005.4 KVAR
Percentage voltage drop: 17.96%
End terminal voltage: 9.0244KV
Losses
 Transformers and power lines are major source of Technical losses
in power distribution system.
 Unbalanced loading is another factor which results to losses in
electric distribution line
0
200
400
600
800
1000
1200
Active power loss Reactive power
loss
Chart Title
Existing system
using annual peak
load of fiscal year 73-
74
Underground cable
beyond Jarebar
Figure: Comparison of losses
Reduction of peak loss=71.6KW
LF=0.441
LLF=0.3LF+0.7LF2 = 0.268
Reduction on Average power loss=LLF*peak power loss
=19.18 KW
Average annual energy saving= 19.18*365*24
=168094 KWhr
Less spacing between the conductors the cables have much
capacitance, so draw higher charging current. Thus the line
capacitance compensates the reactive power demand and hence
reactive power demand decreases.
Reduction in total reactive power loss = 1073.9-1005.4
=68.23KVAR.
Voltage Drop
Lower voltage drop in underground system than overhead
system due to lower inductance because of smaller spacing
between conductor cable in underground distribution system
20.75
17.96
Existing system using annual peak load
of fiscal year 73-74
Underground cable beyond Jrebar
Percentage voltage drop
Also the surge voltage on the
underground system is
smoothed down as surge energy
is absorbed by the sheath
Voltage drop O/H = 20.75%
Voltage drop U/G = 17.96%
Reliability indices
Reliability
Indices
Overhead Distribution
System
Underground
Distribution System
SAIFI 4.9039 f /customer. yr 4.4499 f / customer.yr
SAIDI 320.82 hr/customer. yr 322.31 hr/customer.yr
CAIDI 65.423 hr / customer
interruption
72.429 hr / customer
interruption
ASAI 0.9634 pu 0.9632 pu
Load forecast
Using exponential model , MAPE= 3.32%
Load at (n) number of year = 4.136*exp(0.0526*number of year)
(considering 66/67 as base year)
0
2
4
6
8
10
12
14
16
KW
Peak load MW
during load
shedding
forecasted Peak
load without
Loadshedding MW
Figure: Forecasted load vs fiscal year
S.N. Year
Peak load MW during load
shedding(MW)
Peak load without Load shedding(
MW)
1 66-67 5.263 4.528
2 67-68 5.393 4.640
3 68-69 5.441 4.681
4 69-70 5.62 4.836
5 70-71 6.138 5.281
6 71-72 6.964 5.992
7 72-73 7.012 6.033
8 73-74 7.289 6.397
9 74-75 - 6.640
10 75-76 - 6.998
11 76-77 - 7.376
12 77-78 - 7.775
13 78-79 - 8.195
14 79-80 - 8.6376
15 80-81 - 9.1041
16 81-82 - 9.5958
17 82-83 - 10.114
18 83-84 - 10.660
19 84-85 - 11.236
20 86-87 - 11.842
21 87-88 - 12.482
22 88-89 - 13.156
Load Forecast
The peak demand after 15 years will be 13.867 MW.
Generally as according to various research papers it has been
concluded that 11KV system can economically carry sufficient
current to handle about 10MVA load at reasonable distance
probably 15 Km from primary substation.
Thus, the present lines couldn’t supply the power reliably and
efficiently in near future
Thus if peak load continues to increases in this similar trend, our
present system can’t handle its load reliably after 2079-80.
 Selection of cable
 After 2079-80 the current feeder is unable for a reliable power
supply in the service area
So, for FY 2079-80
Annual peak load=8.5MW
System voltage=11KV
Peak value of current through the cable =
8500
3∗11∗0.85
=
524.86A
 From cable selection table, For 525A current for duct bank, 630mm2
single core AL XLPE 11KV cable with ampacity 550A is selected
for straight run of feeder beyond Jarebar i.e. 4.29km
FEASIBILITY STUDY ON UNDER GROUND
CABLE SYSTEM
 For long and heavily loaded braches we select the 3 core XLPE
cable of size 185mm2 with ampacity 290A for the approximate
distance of 6.65km
 For smaller branching, 3 core XLPE cable of size 70mm2 with
ampacity 165A is selected for approximate distance of 2.61km
 Cable laying method
 Direct laying
 Draw-in system
 Solid system
According to our requirement in the service area considering the
reliability and economy, draw in system is preferred
 Duct Specification
 Type
i. Stone ware pipes
ii. GI pipes
iii. Cast Iron Pipe
iv. Spun Reinforced Concrete Pipe
v. HDPP or PVC pipe
Among these HDPP pipes are selected for undergrounding due to its
low initial cost, lighter weight, longer lifespan, low maintenance cost
and faster assembly
Size and Configuration
i. For a single cable duct diameter shouldn’t less than 10cm
ii. For a more than one cable duct diameter shouldn’t less than
15cm
Following configuration can be used for our project
Figure: Cross-sectional view of duct configuration
 Manholes and Joint
 For clear working space for performing necessary maintenance
manhole size be 6ft * 3ft
 Joint should provide the required electrical connection as well as the
mechanical support
Figure: Manhole Figure: Typical cable joint
 Protection against Fault
 Pad-mounted fused switches
 Pad-mounted vacuum fault interrupter
 Pad-mounted breakers or reclosure
 Cable end capping
 Cold shrink cap
 Heat shrink cap
 Denso seal
Cable Installation
Winch pulling
Laying cable from a moving drum trailer
Pulling in by hand
Bond pulling
Winch pulling or laying of
cable direct from a moving
cable drum trailer is to be
preferred because it is less
arduous with fewer people
 Economic Calculation
 Approximate cost for undergrounding the portion of service region
of Baidam feeder (beyond Jarebar) is summarized below:
S.N Parameter Cost (Rs.)
1 Cable Cost 5,72,82,400
2 Duct Cost 4,82,00,000
3 Manhole Construction
Cost
27,20,000
4 Excavation Cost 9,45,520
5 Installation Cost 3,54,570
6 Jointing Accessories Cost 4,40,630
7 Protection System Cost 23,68,800
Total 11,23,11,920
The excavation of cable route in already settled area is
difficult, resulting in more expense of economy
The problem for traffic during the excavation of cable route is
very significant. So, we might have to compromise our
working schedule and local sound pollution during working
hours
Dusts produced after excavation, can cause the air pollution in
the city. Thus, the project must be completed within short
period of time
Water pipes and drainage system are the vital components of
city thus must be considered throughout the excavation period
The routing of the cable during crossing of the main road
Possible Obstacles
After simulating the present system under two condition, we
conclude that in underground system the active power loss is
reduced thereby reducing annual energy lost cost
The present value of peak load is 6.397MW. If this trend
normally continues to increase, the present system is not capable
to carry the power economically, after fiscal year 2079-80 due to
economic limitation of 11kv line
Though the initial cost of installation of underground cable
distribution system is higher than that for overhead system, the
operating cost and the maintenance cost for underground
distribution is much lower than that for the overhead system
CONCLUSION
In terms of rate of interruption of supply, we can conclude that
underground system is more reliable than overhead system
because there is very less chance of affecting the system by
lightning, wind, storm and ice
Since all the cables and other accessories are buried under the
ground level, so, the underground cable system provides an
adequate level of safety to the public and tourists, and helps in
maintaining the natural beauty
Summarizing, we concluded that underground distribution
system provides a higher level of managerial and safety
benefits than the overhead distribution system
Following recommendation can be made to reduce losses in present
context
 Loading on each phase should be balanced as far as possible
 Most of the private transformers in the feeder run at low loading
condition causing high No load loss .So transformer of proper size
should be provided to the private consumer considering the future
possible load growth
 Installation of shunt capacitors for improvement of power factor in
the proper places.
 Good workmanship during the repair and maintenance is also a
includable factor to reduce the minor non technical losses
 For reliable performance after fiscal year 2079-80, the feeder must
be divided into two parts
RECOMMENDATION
[1] (Nagrath, 2014)D.P Kothari and I.J Nagrath “Power System
Engineering”, second edition
[2 (Gupta, 2012)] J.B Gupta “Electrical Installation Estimating and
Costing”, ninth edition
[3]http://www.theiet.org/forums/forum/messageview.cfm?catid=205&th
readid=62888
[4] Navaraj Poudel, Sumit Adhikari, Bhupendra Shaud, and Manoj
Kumar Yadav, “Comparative study of different feeders in Kudhar
substation” BE final year Project, IOE Paschimanchal, Campus.
[5] http://ieeexplore.ieee.org/abstract/document/667402/
[6] http://www.thestate.com/opinion/letters-to-the-
editor/article41203599.html
[7] http://www.jainvidyut.com/pdf/raychem-pricelist-2013.pdf
References
THANK YOU!!!

More Related Content

What's hot

Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!PRABHAHARAN429
 
Fundamentals of power system
Fundamentals of power systemFundamentals of power system
Fundamentals of power systemBalaram Das
 
Ee423 fault analysis_notes
Ee423  fault analysis_notesEe423  fault analysis_notes
Ee423 fault analysis_notesAcot Benard
 
Instantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its ApplicationsInstantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its Applicationsarunj89
 
power quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcompower quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcom7867867869
 
Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...Kinnera Kin
 
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) Mathankumar S
 
Topic1_Castiglianos Theorem.pptx
Topic1_Castiglianos Theorem.pptxTopic1_Castiglianos Theorem.pptx
Topic1_Castiglianos Theorem.pptxMary Joanne Aniñon
 
Power electronics-lab-manual
Power electronics-lab-manualPower electronics-lab-manual
Power electronics-lab-manualponarun
 
Digital Electronics Lab
Digital Electronics LabDigital Electronics Lab
Digital Electronics LabCyber4Tech
 
Bipolar Junction Transistor (BJT) DC and AC Analysis
Bipolar Junction Transistor (BJT) DC and AC AnalysisBipolar Junction Transistor (BJT) DC and AC Analysis
Bipolar Junction Transistor (BJT) DC and AC AnalysisJess Rangcasajo
 
Example: Modal analysis using DIgSILENT PowerFactory.
Example: Modal analysis using DIgSILENT PowerFactory. Example: Modal analysis using DIgSILENT PowerFactory.
Example: Modal analysis using DIgSILENT PowerFactory. Francisco Gonzalez-Longatt
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch centerddxdharmesh
 
Facts static voltage & phase angle regulators
Facts   static voltage & phase angle regulatorsFacts   static voltage & phase angle regulators
Facts static voltage & phase angle regulatorsSITCOE, Yadrav
 

What's hot (20)

Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!
 
Fundamentals of power system
Fundamentals of power systemFundamentals of power system
Fundamentals of power system
 
Ee423 fault analysis_notes
Ee423  fault analysis_notesEe423  fault analysis_notes
Ee423 fault analysis_notes
 
Instantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its ApplicationsInstantaneous Reactive Power Theory And Its Applications
Instantaneous Reactive Power Theory And Its Applications
 
power quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcompower quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcom
 
Load flow study
Load flow studyLoad flow study
Load flow study
 
Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...
 
Load flow studies 19
Load flow studies 19Load flow studies 19
Load flow studies 19
 
EE6501 - Power System Analysis
EE6501 - Power System AnalysisEE6501 - Power System Analysis
EE6501 - Power System Analysis
 
Static relay
Static relayStatic relay
Static relay
 
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
 
Topic1_Castiglianos Theorem.pptx
Topic1_Castiglianos Theorem.pptxTopic1_Castiglianos Theorem.pptx
Topic1_Castiglianos Theorem.pptx
 
Power electronics-lab-manual
Power electronics-lab-manualPower electronics-lab-manual
Power electronics-lab-manual
 
Power flow through transmission line.
Power flow through transmission line.Power flow through transmission line.
Power flow through transmission line.
 
Heffron phillips model
Heffron phillips modelHeffron phillips model
Heffron phillips model
 
Digital Electronics Lab
Digital Electronics LabDigital Electronics Lab
Digital Electronics Lab
 
Bipolar Junction Transistor (BJT) DC and AC Analysis
Bipolar Junction Transistor (BJT) DC and AC AnalysisBipolar Junction Transistor (BJT) DC and AC Analysis
Bipolar Junction Transistor (BJT) DC and AC Analysis
 
Example: Modal analysis using DIgSILENT PowerFactory.
Example: Modal analysis using DIgSILENT PowerFactory. Example: Modal analysis using DIgSILENT PowerFactory.
Example: Modal analysis using DIgSILENT PowerFactory.
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
 
Facts static voltage & phase angle regulators
Facts   static voltage & phase angle regulatorsFacts   static voltage & phase angle regulators
Facts static voltage & phase angle regulators
 

Similar to Analysis for underground cable system, lakeside pokhara

Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...IJMERJOURNAL
 
EE456_NWPUD Transmission Reinforcement Planning
EE456_NWPUD Transmission Reinforcement PlanningEE456_NWPUD Transmission Reinforcement Planning
EE456_NWPUD Transmission Reinforcement Planningki hei chan
 
Design And Simulation of Microgrid Control based Wind Power Generation Syst...
Design And Simulation of  Microgrid Control  based Wind Power Generation Syst...Design And Simulation of  Microgrid Control  based Wind Power Generation Syst...
Design And Simulation of Microgrid Control based Wind Power Generation Syst...IRJET Journal
 
Major Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaMajor Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaSaurabh Saxena
 
ELECTRICAL POWER TRANSMISSION-3.pptx
ELECTRICAL POWER TRANSMISSION-3.pptxELECTRICAL POWER TRANSMISSION-3.pptx
ELECTRICAL POWER TRANSMISSION-3.pptxamitpandey509058
 
Solar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysSolar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysIRJET Journal
 
Autonomous microgrid based parallel inverters using droop controller for impr...
Autonomous microgrid based parallel inverters using droop controller for impr...Autonomous microgrid based parallel inverters using droop controller for impr...
Autonomous microgrid based parallel inverters using droop controller for impr...journalBEEI
 
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...IJERA Editor
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointslmnsvn
 
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipurramesh kumawat
 
Flexible ac transmission FACTs
Flexible ac transmission FACTsFlexible ac transmission FACTs
Flexible ac transmission FACTsMOHAN RAKIB
 
FACTs_Final_Presensation
FACTs_Final_PresensationFACTs_Final_Presensation
FACTs_Final_PresensationMOHAN RAKIB
 
Laboratory Setup for Long Transmission Line
Laboratory Setup for Long Transmission LineLaboratory Setup for Long Transmission Line
Laboratory Setup for Long Transmission LineIRJET Journal
 
PERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEM
PERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEMPERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEM
PERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEMJournal For Research
 
Frequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable loadFrequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable loadIAEME Publication
 
Design aspects of high voltage transmission line
Design aspects of high voltage transmission lineDesign aspects of high voltage transmission line
Design aspects of high voltage transmission linejournalBEEI
 
Uttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training ReportUttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training ReportAmitKumar6931
 
PERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUIT
PERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUITPERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUIT
PERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUITVLSICS Design
 

Similar to Analysis for underground cable system, lakeside pokhara (20)

Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
 
EE456_NWPUD Transmission Reinforcement Planning
EE456_NWPUD Transmission Reinforcement PlanningEE456_NWPUD Transmission Reinforcement Planning
EE456_NWPUD Transmission Reinforcement Planning
 
Design And Simulation of Microgrid Control based Wind Power Generation Syst...
Design And Simulation of  Microgrid Control  based Wind Power Generation Syst...Design And Simulation of  Microgrid Control  based Wind Power Generation Syst...
Design And Simulation of Microgrid Control based Wind Power Generation Syst...
 
Substation
Substation Substation
Substation
 
Major Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaMajor Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh Saxena
 
ELECTRICAL POWER TRANSMISSION-3.pptx
ELECTRICAL POWER TRANSMISSION-3.pptxELECTRICAL POWER TRANSMISSION-3.pptx
ELECTRICAL POWER TRANSMISSION-3.pptx
 
Solar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysSolar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National Highways
 
Autonomous microgrid based parallel inverters using droop controller for impr...
Autonomous microgrid based parallel inverters using droop controller for impr...Autonomous microgrid based parallel inverters using droop controller for impr...
Autonomous microgrid based parallel inverters using droop controller for impr...
 
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection point
 
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
 
Flexible ac transmission FACTs
Flexible ac transmission FACTsFlexible ac transmission FACTs
Flexible ac transmission FACTs
 
FACTs_Final_Presensation
FACTs_Final_PresensationFACTs_Final_Presensation
FACTs_Final_Presensation
 
Irjet v4 i6288
Irjet v4 i6288Irjet v4 i6288
Irjet v4 i6288
 
Laboratory Setup for Long Transmission Line
Laboratory Setup for Long Transmission LineLaboratory Setup for Long Transmission Line
Laboratory Setup for Long Transmission Line
 
PERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEM
PERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEMPERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEM
PERFORMANCE OF MVDC AND MVAC OFFSHORE WIND FARM DISTRIBUTION SYSTEM
 
Frequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable loadFrequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable load
 
Design aspects of high voltage transmission line
Design aspects of high voltage transmission lineDesign aspects of high voltage transmission line
Design aspects of high voltage transmission line
 
Uttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training ReportUttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training Report
 
PERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUIT
PERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUITPERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUIT
PERFORMANCE ANALYSIS OF MODIFIED QSERL CIRCUIT
 

More from Bishal Rimal

Energy and COVID 19
Energy and COVID 19Energy and COVID 19
Energy and COVID 19Bishal Rimal
 
Digial instrumentation fnal
Digial instrumentation fnalDigial instrumentation fnal
Digial instrumentation fnalBishal Rimal
 
Electrical signal processing and transmission
Electrical signal processing and transmissionElectrical signal processing and transmission
Electrical signal processing and transmissionBishal Rimal
 
Switchgear, protection and measurement
Switchgear, protection and measurementSwitchgear, protection and measurement
Switchgear, protection and measurementBishal Rimal
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepalBishal Rimal
 
Kulekhani I hydropower ,Nepal
Kulekhani I hydropower ,NepalKulekhani I hydropower ,Nepal
Kulekhani I hydropower ,NepalBishal Rimal
 
Artifical intelligence
Artifical intelligenceArtifical intelligence
Artifical intelligenceBishal Rimal
 
Electric traction system final upload
Electric traction system final uploadElectric traction system final upload
Electric traction system final uploadBishal Rimal
 

More from Bishal Rimal (9)

Energy and COVID 19
Energy and COVID 19Energy and COVID 19
Energy and COVID 19
 
Mini grid
Mini gridMini grid
Mini grid
 
Digial instrumentation fnal
Digial instrumentation fnalDigial instrumentation fnal
Digial instrumentation fnal
 
Electrical signal processing and transmission
Electrical signal processing and transmissionElectrical signal processing and transmission
Electrical signal processing and transmission
 
Switchgear, protection and measurement
Switchgear, protection and measurementSwitchgear, protection and measurement
Switchgear, protection and measurement
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepal
 
Kulekhani I hydropower ,Nepal
Kulekhani I hydropower ,NepalKulekhani I hydropower ,Nepal
Kulekhani I hydropower ,Nepal
 
Artifical intelligence
Artifical intelligenceArtifical intelligence
Artifical intelligence
 
Electric traction system final upload
Electric traction system final uploadElectric traction system final upload
Electric traction system final upload
 

Recently uploaded

call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 

Recently uploaded (20)

call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 

Analysis for underground cable system, lakeside pokhara

  • 1. ANALYSIS OF EXISTING DISTRIBUTION LINE AND FEASIBILITY STUDY ON UNDERGROUND CABLE SYSTEM, LAKESIDE POKHARA Bishal Rimal(BEL-070-213) Himal Chaulagain(BEL-070-218) Manoj Sah(BEL-070-224) Paras Subedi(BEL-070-228) Project Supervisor: Er.Rajendra Dhakal
  • 2. Electric power distribution is the final stage in the delivery of electric power; it carries electricity from the transmission system to individual consumers. Radial Distribution System Ring Main Distribution System Network Distribution System Load flow study is numerical analysis of the flow of electric power in an any system. Load flow studies basically comprises of the determination of Voltage and power angle Active Power Reactive Power losses INTRODUCTION
  • 3. An Overhead power line is a structure used in electric power transmission and distribution to transmit electrical energy along large distances. It consists of one or more conductors suspended by towers or poles Underground cables transmit power across densely populated or areas where land is costly or environmentally sensitive load forecasting Load forecasting is a technique used by energy providing companies to predict the energy needed to meet the demand and supply equilibrium
  • 4. ETAP Platform which gives the solution for Generation, Transmission, Distribution, Industrial, Transportation, and Low-Voltage Power Systems Google Earth Geobrowser that accesses satellite and aerial imagery, ocean bathymetry, and other geographic data over the internet to represent the Earth as a three-dimensional globe Software used
  • 5.  OSMTracker for Android This application allows us to record our track, save waypoints(geotagging). The output of our recording can be export into GPX file format and we can open it through Google Earth.
  • 6. To analyse the peak power demand ,losses and voltage drop on the feeder. To analyse the reliability of the feeder. OBJECTIVE
  • 7. To forecast the load demand for 15 years. To analyse the feasibility in replacing the overhead distribution line by underground cable Economic estimation of underground system
  • 8.
  • 9.  Data collection NEA Private transformer load record No. of transformer Single line diagram of Baidam feeder Collection of Peak load data of past 8 fiscal years METHODOLOGY BAIDAM FEEDER Private NEA Number of transformer 35 42
  • 10.
  • 11.  Daily load log sheet of Baidam feeder 28April 2017 0 500 1000 1500 2000 2500 3000 3500 4000 4500 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 17:30 18:00 18:30 19:00 19:30 20:00 20:30 21:00 22:00 23:00 24:00:00 Daily load curve Kw
  • 12. Field Survey  With the help of OSMTracker for Android (for obtaining GPS coordinate of transformer location) and Google Earth (for plotting the transformer and its line route distance measurement) OSMTRACKER GPX GOOGLE EARTH Plot the location on map Transmission lengthETAP
  • 13.
  • 14. ETAP Simulation Following assumption are made for the simplicity of analysis. All peak load occurs at the same time for all transformer. All three phase are balanced. Power factor: 0.85 All transformers are solidly grounded. No private consumer use reactive power compensator.
  • 15. We simulate the existing distribution system on ETAP under three conditions: Simulation of existing system using data of 28 April 2017 Simulation of existing system using annual peak load of fiscal year 73-74. Simulation of existing system replacing overhead line by underground cable beyond Jarebar using annual peak load of fiscal year 73-74
  • 16. Load Forecasting Available Data: 66/67 to 72/73- During Load Shedding 73-74-During No Load Shedding Trend analysis method. From that peak load with load shedding data we forecast the peak load of fiscal year 73/74 assuming load shedding Relative percentage peak load variation between load shedding period and without load shedding period is 13.95% using peak load of fiscal year 73/74
  • 17.
  • 18. 1. Simulation of existing system using data of 28 April 2017 Peak load: 3848KW @power factor 0.85 Peak KVA: 4528KVA Demand factor: 0.47 Average Private Transformer loading: 18% Average NEA transformer loading: 71% Total Active power loss: 294.5KW Percentage active power loss: 7.65% Total reactive power loss: 383.5 KVAR Percentage voltage drop: 11.46% End terminal voltage: 9.74KV RESULT AND ANALYSIS
  • 19. 2.Simulation of existing system using annual peak load of fiscal year 73-74 Peak load: 6397KW @power factor 0.85 Peak KVA: 7526KVA Demand factor: 0.78 Average Private Transformer loading: 50% Average NEA transformer loading: 100% Total Active power loss: 860.2KW Percentage active power loss: 13.45% Total reactive power loss: 1073.9 KVar Percentage voltage drop: 20.75% End terminal voltage: 8.8KV
  • 20. 3.Simulation using underground cable beyond Jarebar Peak load: 6397KW @power factor 0.85 Peak KVA: 7526KVA Demand factor: 0.78 Average Private Transformer loading: 50% Average NEA transformer loading: 100% Total Active power loss: 788.6KW Percentage active power loss: 12.32% Total reactive power loss: 1005.4 KVAR Percentage voltage drop: 17.96% End terminal voltage: 9.0244KV
  • 21. Losses  Transformers and power lines are major source of Technical losses in power distribution system.  Unbalanced loading is another factor which results to losses in electric distribution line 0 200 400 600 800 1000 1200 Active power loss Reactive power loss Chart Title Existing system using annual peak load of fiscal year 73- 74 Underground cable beyond Jarebar Figure: Comparison of losses
  • 22. Reduction of peak loss=71.6KW LF=0.441 LLF=0.3LF+0.7LF2 = 0.268 Reduction on Average power loss=LLF*peak power loss =19.18 KW Average annual energy saving= 19.18*365*24 =168094 KWhr Less spacing between the conductors the cables have much capacitance, so draw higher charging current. Thus the line capacitance compensates the reactive power demand and hence reactive power demand decreases. Reduction in total reactive power loss = 1073.9-1005.4 =68.23KVAR.
  • 23. Voltage Drop Lower voltage drop in underground system than overhead system due to lower inductance because of smaller spacing between conductor cable in underground distribution system 20.75 17.96 Existing system using annual peak load of fiscal year 73-74 Underground cable beyond Jrebar Percentage voltage drop Also the surge voltage on the underground system is smoothed down as surge energy is absorbed by the sheath Voltage drop O/H = 20.75% Voltage drop U/G = 17.96%
  • 24. Reliability indices Reliability Indices Overhead Distribution System Underground Distribution System SAIFI 4.9039 f /customer. yr 4.4499 f / customer.yr SAIDI 320.82 hr/customer. yr 322.31 hr/customer.yr CAIDI 65.423 hr / customer interruption 72.429 hr / customer interruption ASAI 0.9634 pu 0.9632 pu
  • 25. Load forecast Using exponential model , MAPE= 3.32% Load at (n) number of year = 4.136*exp(0.0526*number of year) (considering 66/67 as base year) 0 2 4 6 8 10 12 14 16 KW Peak load MW during load shedding forecasted Peak load without Loadshedding MW Figure: Forecasted load vs fiscal year
  • 26. S.N. Year Peak load MW during load shedding(MW) Peak load without Load shedding( MW) 1 66-67 5.263 4.528 2 67-68 5.393 4.640 3 68-69 5.441 4.681 4 69-70 5.62 4.836 5 70-71 6.138 5.281 6 71-72 6.964 5.992 7 72-73 7.012 6.033 8 73-74 7.289 6.397 9 74-75 - 6.640 10 75-76 - 6.998 11 76-77 - 7.376 12 77-78 - 7.775 13 78-79 - 8.195 14 79-80 - 8.6376 15 80-81 - 9.1041 16 81-82 - 9.5958 17 82-83 - 10.114 18 83-84 - 10.660 19 84-85 - 11.236 20 86-87 - 11.842 21 87-88 - 12.482 22 88-89 - 13.156
  • 27. Load Forecast The peak demand after 15 years will be 13.867 MW. Generally as according to various research papers it has been concluded that 11KV system can economically carry sufficient current to handle about 10MVA load at reasonable distance probably 15 Km from primary substation. Thus, the present lines couldn’t supply the power reliably and efficiently in near future Thus if peak load continues to increases in this similar trend, our present system can’t handle its load reliably after 2079-80.
  • 28.  Selection of cable  After 2079-80 the current feeder is unable for a reliable power supply in the service area So, for FY 2079-80 Annual peak load=8.5MW System voltage=11KV Peak value of current through the cable = 8500 3∗11∗0.85 = 524.86A  From cable selection table, For 525A current for duct bank, 630mm2 single core AL XLPE 11KV cable with ampacity 550A is selected for straight run of feeder beyond Jarebar i.e. 4.29km FEASIBILITY STUDY ON UNDER GROUND CABLE SYSTEM
  • 29.  For long and heavily loaded braches we select the 3 core XLPE cable of size 185mm2 with ampacity 290A for the approximate distance of 6.65km  For smaller branching, 3 core XLPE cable of size 70mm2 with ampacity 165A is selected for approximate distance of 2.61km  Cable laying method  Direct laying  Draw-in system  Solid system According to our requirement in the service area considering the reliability and economy, draw in system is preferred
  • 30.  Duct Specification  Type i. Stone ware pipes ii. GI pipes iii. Cast Iron Pipe iv. Spun Reinforced Concrete Pipe v. HDPP or PVC pipe Among these HDPP pipes are selected for undergrounding due to its low initial cost, lighter weight, longer lifespan, low maintenance cost and faster assembly Size and Configuration i. For a single cable duct diameter shouldn’t less than 10cm ii. For a more than one cable duct diameter shouldn’t less than 15cm Following configuration can be used for our project
  • 31. Figure: Cross-sectional view of duct configuration
  • 32.  Manholes and Joint  For clear working space for performing necessary maintenance manhole size be 6ft * 3ft  Joint should provide the required electrical connection as well as the mechanical support Figure: Manhole Figure: Typical cable joint
  • 33.  Protection against Fault  Pad-mounted fused switches  Pad-mounted vacuum fault interrupter  Pad-mounted breakers or reclosure  Cable end capping  Cold shrink cap  Heat shrink cap  Denso seal
  • 34. Cable Installation Winch pulling Laying cable from a moving drum trailer Pulling in by hand Bond pulling Winch pulling or laying of cable direct from a moving cable drum trailer is to be preferred because it is less arduous with fewer people
  • 35.  Economic Calculation  Approximate cost for undergrounding the portion of service region of Baidam feeder (beyond Jarebar) is summarized below: S.N Parameter Cost (Rs.) 1 Cable Cost 5,72,82,400 2 Duct Cost 4,82,00,000 3 Manhole Construction Cost 27,20,000 4 Excavation Cost 9,45,520 5 Installation Cost 3,54,570 6 Jointing Accessories Cost 4,40,630 7 Protection System Cost 23,68,800 Total 11,23,11,920
  • 36. The excavation of cable route in already settled area is difficult, resulting in more expense of economy The problem for traffic during the excavation of cable route is very significant. So, we might have to compromise our working schedule and local sound pollution during working hours Dusts produced after excavation, can cause the air pollution in the city. Thus, the project must be completed within short period of time Water pipes and drainage system are the vital components of city thus must be considered throughout the excavation period The routing of the cable during crossing of the main road Possible Obstacles
  • 37. After simulating the present system under two condition, we conclude that in underground system the active power loss is reduced thereby reducing annual energy lost cost The present value of peak load is 6.397MW. If this trend normally continues to increase, the present system is not capable to carry the power economically, after fiscal year 2079-80 due to economic limitation of 11kv line Though the initial cost of installation of underground cable distribution system is higher than that for overhead system, the operating cost and the maintenance cost for underground distribution is much lower than that for the overhead system CONCLUSION
  • 38. In terms of rate of interruption of supply, we can conclude that underground system is more reliable than overhead system because there is very less chance of affecting the system by lightning, wind, storm and ice Since all the cables and other accessories are buried under the ground level, so, the underground cable system provides an adequate level of safety to the public and tourists, and helps in maintaining the natural beauty Summarizing, we concluded that underground distribution system provides a higher level of managerial and safety benefits than the overhead distribution system
  • 39. Following recommendation can be made to reduce losses in present context  Loading on each phase should be balanced as far as possible  Most of the private transformers in the feeder run at low loading condition causing high No load loss .So transformer of proper size should be provided to the private consumer considering the future possible load growth  Installation of shunt capacitors for improvement of power factor in the proper places.  Good workmanship during the repair and maintenance is also a includable factor to reduce the minor non technical losses  For reliable performance after fiscal year 2079-80, the feeder must be divided into two parts RECOMMENDATION
  • 40. [1] (Nagrath, 2014)D.P Kothari and I.J Nagrath “Power System Engineering”, second edition [2 (Gupta, 2012)] J.B Gupta “Electrical Installation Estimating and Costing”, ninth edition [3]http://www.theiet.org/forums/forum/messageview.cfm?catid=205&th readid=62888 [4] Navaraj Poudel, Sumit Adhikari, Bhupendra Shaud, and Manoj Kumar Yadav, “Comparative study of different feeders in Kudhar substation” BE final year Project, IOE Paschimanchal, Campus. [5] http://ieeexplore.ieee.org/abstract/document/667402/ [6] http://www.thestate.com/opinion/letters-to-the- editor/article41203599.html [7] http://www.jainvidyut.com/pdf/raychem-pricelist-2013.pdf References

Editor's Notes

  1. Lakeside is the most Popular tourist destination in Pokhara-Lekhnath Metropolitan city. Among various factor to degrade the beauty of Lakeside, the unmanaged overhead Power cables and communication line, is one of the major factor.
  2. Heart of Nepal, Pokhara is a famous Paradise for its Natural Beauty. Lakeside (Area is Baidam Feeder) is the most Popular tourist destination in Pokhara-Lekhnath Metropolitan city. Among various factor to degrade the beauty of Lakeside, the unmanaged overhead Power cables and communication line, is one of the major factor. The reliability of distributed power cable is also significant factor for the reliable service and facilities on the tourist area. Prevention of failure of line due to high wind, lightning, falling of tree etc. could be reduced to very low level, if undergrounding cabling could be implemented. The matter of Public safety from power cable is another vital necessity of the urban area. The minimization of the accidents that might be happens due to distribution power cables has become a challenge in urban area. Road accidents due to presence overhead distribution pole on main road side is also a considering matter in urban area.
  3. The length of transmission line obtained from google earth is used.
  4. PEAK LOAD at magh
  5. ????
  6. Analysing we found, SAIFI is less for underground system than for overhead system i.e the rate of interruption of supply in underground system is less But SAIDI is greater for underground system because if any fault occur, it is difficult to locate and hence takes more time to repair.
  7. If the consumption increases with present rate we found that the peak load after 15 years will be 13.867 MW At present contest, during annual peak hour most of the NEA transformers are overloaded So, the transformer and lines couldn’t able to supply the power reliably and efficiently in near future Generally as according to various research papers it has been concluded that 11KV system can economically carry sufficient current to handle about 10MVA load at reasonable distance probably 15 Km from primary substation. Thus if peak load continues to increases in this similar trend, our present system can’t handle its load reliably after 2079-80. If the consumption increases with present rate we found that the peak load after 15 years will be 13.867 MW At present contest, during annual peak hour most of the NEA transformers are overloaded So, the transformer and lines couldn’t able to supply the power reliably and efficiently in near future Generally as according to various research papers it has been concluded that 11KV system can economically carry sufficient current to handle about 10MVA load at reasonable distance probably 15 Km from primary substation. Thus if peak load continues to increases in this similar trend, our present system can’t handle its load reliably after 2079-80. If the consumption increases with present rate we found that the peak load after 15 years will be 13.867 MW At present contest, during annual peak hour most of the NEA transformers are overloaded So, the transformer and lines couldn’t able to supply the power reliably and efficiently in near future Generally as according to various research papers it has been concluded that 11KV system can economically carry sufficient current to handle about 10MVA load at reasonable distance probably 15 Km from primary substation. Thus if peak load continues to increases in this similar trend, our present system can’t handle its load reliably after 2079-80.