Importance of Microsoft Project and
Primavera In Construction Industry
November 03, 2015
Questions ?
CEPT
UNIVERSITY
Why Microsoft Project and Primavera ?
Why PMS ?
Planners only make schedules
Microsoft Project or Primavera ?
Microsoft Project cannot handle Complex Projects
Potential Used ?
Contents… CEPT
UNIVERSITY
 Project Management Challenges
 Market Penetration
 Project planning:
 PDM network
 Assign Resources and Cost
 Baseline the plan
 Project review:
 Identify resource over-allocations
 Level if necessary
 Project Execution:
 Generate Reports
 Project Monitoring and Tracking:
 Update Baseline plan
 Compare Actual against Baseline
 Re-plan and Re-Baseline
 Earned Value Concept
 Difference between MSP and
Primavera
 Microsoft Project or Primavera?
Work Performance Data/Info/Reports
CEPT
UNIVERSITY
PM Plan
The document which
describes how the
project will be
documented, monitored
and controlled
WPD
Physical work
completion, start and
finish dates, change
requests, actual costs,
actual duration etc.
WPI
Status of deliverables,
status for change requests,
forecasted estimates to
complete
WPR
Status
reports,memos,justifications,
recommendations
Project Management Challenges CEPT
UNIVERSITY
Geographic dispersion
Overbooked or
Unutilized
Resources
Project Scope Changes
Unnecessary Paperwork
Market Penetration CEPT
UNIVERSITY
Middle East United States
Source: The use of project management software in construction industry of Southeast Europe
Mladen Vukomanović, Mladen Radujković, Zlata Dolaček Alduk
Project Planning CEPT
UNIVERSITY
Schedule
Baseline is
established to
control actual
project
performance
Project Planning: PDM Network CEPT
UNIVERSITY
Project Planning : PDM Network CEPT
UNIVERSITY
Project Review: Assigning resources and Cost
CEPT
UNIVERSITY
Project Review: Levelling Resources CEPT
UNIVERSITY
Managing Floats in MS-Project and Primavera
CEPT
UNIVERSITY
Managing Floats in MS-Project and Primavera
CEPT
UNIVERSITY
Managing Floats in MS-Project and Primavera
CEPT
UNIVERSITY
Managing Floats in MS-Project and Primavera
CEPT
UNIVERSITY
Project Tracking: Setup Baseline CEPT
UNIVERSITY
Go to: Project/Set baseline to set a
baseline for your project
A Baseline is essentially a snapshot of your
project schedule, it should be captured once
your schedule is complete.
So that you can compare your original plan
with the current progress.
Project Monitoring & Tracking: Tracking Gantt
CEPT
UNIVERSITY
CEPT
UNIVERSITYEarned Value Analysis
55000
49000
56000
0
20000
40000
60000
80000
100000
120000 Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Oct-03
Nov-03
Dec-03
BCWS
BCWP
ACWP
Cost Variance: 55,000-56,0000 = -1000 INR (Cost-Overrun)
Schedule Variance: 49,000 – 55,000 = -6000 INR (Behind Schedule)
Project Monitoring & Tracking: EVA CEPT
UNIVERSITY
Project Execution: Reports CEPT
UNIVERSITY
Microsoft Project-2013 Primavera-P6
Primavera P6 Dashboard
CEPT
UNIVERSIT
Y
MS-Project or Primavera? Decision Matrix
CEPT
UNIVERSITY
Source: https://precisionschedulingconsultants.co
Factor MS-Project Primavera
Small & medium building project (<200 activities)
Program-level analysis or simultaneous multiple project analysis
Multiple user interface (more than one person updating/tracking the
schedule)
Construction schedule oversight and detailed analysis
Non-construction projects / simple schedules
Basic bar charts or timelines for display in MS PowerPoint™ presentation
System Integration (BIM,ERP)
Licensing Cost
User friendly , Beginner use, planning and scheduling
Recommended
Note: These decisions are based on professional opinion that were derived from years
and $billions worth of construction scheduling experience.
Not-Recommended
MICROSOFT PROJECT PRIMAVERA
Simple and user friendly Detailed and complex
Allows user to make Macros and Switches
with the help of VBA language
Macros , complex formulas cannot be made
in Primavera
Limited Baselines (Only 11) Unlimited baselines
Project Tracking with multiple projects at
same time is not possible.
Project Tracking with multiple projects at
same time is possible.
Multiple activity relationship not possible It is possible to have a FF as well as SS
relationship between two activities.
Relatively low cost of installation and
maintenance.
High installation and maintenance cost
Appealing appearance Needs configuration to make it appealing.
Difference a decade makes (MS-Project) CEPT
UNIVERSITY
Difference a decade makes….
1994 2000 2003 2006 2010
P3-V1 for
Windows
P3 (V-02)
incorporated
EPS
P6- PrimaVision
web based
platform is
released
Incorporates
Risk
management
Enterprise
Project
Portfolio is
released
CEPT
UNIVERSITY
The Competition—Endless……
Thank You For Your Attention….
Questions?

Importance of Microsoft Project and Primavera

  • 1.
    Importance of MicrosoftProject and Primavera In Construction Industry November 03, 2015
  • 2.
    Questions ? CEPT UNIVERSITY Why MicrosoftProject and Primavera ? Why PMS ? Planners only make schedules Microsoft Project or Primavera ? Microsoft Project cannot handle Complex Projects Potential Used ?
  • 3.
    Contents… CEPT UNIVERSITY  ProjectManagement Challenges  Market Penetration  Project planning:  PDM network  Assign Resources and Cost  Baseline the plan  Project review:  Identify resource over-allocations  Level if necessary  Project Execution:  Generate Reports  Project Monitoring and Tracking:  Update Baseline plan  Compare Actual against Baseline  Re-plan and Re-Baseline  Earned Value Concept  Difference between MSP and Primavera  Microsoft Project or Primavera?
  • 4.
    Work Performance Data/Info/Reports CEPT UNIVERSITY PMPlan The document which describes how the project will be documented, monitored and controlled WPD Physical work completion, start and finish dates, change requests, actual costs, actual duration etc. WPI Status of deliverables, status for change requests, forecasted estimates to complete WPR Status reports,memos,justifications, recommendations
  • 5.
    Project Management ChallengesCEPT UNIVERSITY Geographic dispersion Overbooked or Unutilized Resources Project Scope Changes Unnecessary Paperwork
  • 6.
    Market Penetration CEPT UNIVERSITY MiddleEast United States Source: The use of project management software in construction industry of Southeast Europe Mladen Vukomanović, Mladen Radujković, Zlata Dolaček Alduk
  • 7.
    Project Planning CEPT UNIVERSITY Schedule Baselineis established to control actual project performance
  • 8.
    Project Planning: PDMNetwork CEPT UNIVERSITY
  • 9.
    Project Planning :PDM Network CEPT UNIVERSITY
  • 10.
    Project Review: Assigningresources and Cost CEPT UNIVERSITY
  • 11.
    Project Review: LevellingResources CEPT UNIVERSITY
  • 12.
    Managing Floats inMS-Project and Primavera CEPT UNIVERSITY
  • 13.
    Managing Floats inMS-Project and Primavera CEPT UNIVERSITY
  • 14.
    Managing Floats inMS-Project and Primavera CEPT UNIVERSITY
  • 15.
    Managing Floats inMS-Project and Primavera CEPT UNIVERSITY
  • 16.
    Project Tracking: SetupBaseline CEPT UNIVERSITY Go to: Project/Set baseline to set a baseline for your project A Baseline is essentially a snapshot of your project schedule, it should be captured once your schedule is complete. So that you can compare your original plan with the current progress.
  • 17.
    Project Monitoring &Tracking: Tracking Gantt CEPT UNIVERSITY
  • 18.
    CEPT UNIVERSITYEarned Value Analysis 55000 49000 56000 0 20000 40000 60000 80000 100000 120000Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03 BCWS BCWP ACWP Cost Variance: 55,000-56,0000 = -1000 INR (Cost-Overrun) Schedule Variance: 49,000 – 55,000 = -6000 INR (Behind Schedule)
  • 19.
    Project Monitoring &Tracking: EVA CEPT UNIVERSITY
  • 20.
    Project Execution: ReportsCEPT UNIVERSITY Microsoft Project-2013 Primavera-P6
  • 21.
  • 23.
    MS-Project or Primavera?Decision Matrix CEPT UNIVERSITY Source: https://precisionschedulingconsultants.co Factor MS-Project Primavera Small & medium building project (<200 activities) Program-level analysis or simultaneous multiple project analysis Multiple user interface (more than one person updating/tracking the schedule) Construction schedule oversight and detailed analysis Non-construction projects / simple schedules Basic bar charts or timelines for display in MS PowerPoint™ presentation System Integration (BIM,ERP) Licensing Cost User friendly , Beginner use, planning and scheduling Recommended Note: These decisions are based on professional opinion that were derived from years and $billions worth of construction scheduling experience. Not-Recommended
  • 24.
    MICROSOFT PROJECT PRIMAVERA Simpleand user friendly Detailed and complex Allows user to make Macros and Switches with the help of VBA language Macros , complex formulas cannot be made in Primavera Limited Baselines (Only 11) Unlimited baselines Project Tracking with multiple projects at same time is not possible. Project Tracking with multiple projects at same time is possible. Multiple activity relationship not possible It is possible to have a FF as well as SS relationship between two activities. Relatively low cost of installation and maintenance. High installation and maintenance cost Appealing appearance Needs configuration to make it appealing.
  • 25.
    Difference a decademakes (MS-Project) CEPT UNIVERSITY
  • 26.
    Difference a decademakes…. 1994 2000 2003 2006 2010 P3-V1 for Windows P3 (V-02) incorporated EPS P6- PrimaVision web based platform is released Incorporates Risk management Enterprise Project Portfolio is released CEPT UNIVERSITY
  • 27.
    The Competition—Endless…… Thank YouFor Your Attention…. Questions?

Editor's Notes

  • #2 Introduce Feel honored No fancy stuff Overview of slides I would like it to be a discussion Disclaimer Misconceptions Why MSP and Primavera ? Why not Excel?
  • #5 Project Charter
  • #7 Ask audience why is it so? Marketting Show off to get projects
  • #12 Difference in levelling in Msp and Primavera (Levelling Priorities) Case of contradiction Difference in using Calendars : alternate Saturdays work/nonwork Customise Ribbon option in msp Total Float: ES-LS or EF-LF Free Float: ES(succ) – EF(current)
  • #13 Difference in levelling in Msp and Primavera (Levelling Priorities) Case of contradiction Difference in using Calendars : alternate Saturdays work/nonwork Customise Ribbon option in msp Total Float: ES-LS or EF-LF Free Float: ES(succ) – EF(current)
  • #14 Difference in levelling in Msp and Primavera (Levelling Priorities) Case of contradiction Difference in using Calendars : alternate Saturdays work/nonwork Customise Ribbon option in msp Total Float: ES-LS or EF-LF Free Float: ES(succ) – EF(current)
  • #15 Difference in levelling in Msp and Primavera (Levelling Priorities) Case of contradiction Difference in using Calendars : alternate Saturdays work/nonwork Customise Ribbon option in msp Total Float: ES-LS or EF-LF Free Float: ES(succ) – EF(current)
  • #16 Difference in levelling in Msp and Primavera (Levelling Priorities) Case of contradiction Difference in using Calendars : alternate Saturdays work/nonwork Customise Ribbon option in msp Total Float: ES-LS or EF-LF Free Float: ES(succ) – EF(current)
  • #17 MSP allows 11 baselines. 10 Interim Plans Unusual feature for allowing to change details of summary task.
  • #18 Recurring Task Activity steps in Primavera
  • #19 What is Earned Value? Explain with Example Difference between MSP and Primavera Performance factor