IMP/IMS Overview
Glen B Alleman
glen.alleman@Niwotridge.com
IMP/IMS - 2/19
Integrated Management Framework
Statement of Work (SOW)
User requirements decomposed from RFP
• Event-driven plan for entire program
• Product and Process Sections
Determined by
performance
• Guidance usually in RFP
• Tailored to contractor’s program / products
• Provides single numbering system for entire program
• Contractor generated. Based on SOW
• Guidance provided in RFP
IMS • Expands IMP, Provides timing
Links cost to
IMS thru WBS
PLACED
ON
CONTRACT
USED TO
TRACK
PERFORMANCE
USED TO REPORT
PERFORMANCE
Technical Requirements
WBS
CPARS
Technical Performance Measures
Process Metrics
• Process quality measures
Earned Value Management System (EVMS)
Integrated Master Plan (IMP)
IMP/IMS - 3/19
What’s the objective of all this formality?
Objective è Implementation
Event driven plan versus a
schedule driven plan based on
completion of tasks
è Separate plan (IMP) from schedule
(IMS) but link elements with
numbering system
Condensed, easy to read “plan”
showing “events” rather than
effort
è Indentured, outline format (not
text)
Pre-defined entry and exit
conditions for major program
events
è Significant accomplishments (SA)
for each key event (submitted in
proposal)
Objective measure of progress/
completion for each
accomplishment
è Pre–defined accomplishment
criteria (AC) for each SA
Stable, contractual plan flexible
enough to portray program status
è IMP is part of contract, IMS is data
item
Capture essence of functional
processes without mandating a
particular process
è Split IMP into Product and Process
sections
IMP/IMS - 4/19
Integrated Master Plan / Integrated Master Schedule
l Integrated Master Plan (IMP) – provides a single plan
describing the fundamental structure of the program
l Focuses the integrated product team (IPT) team on the
customer requirements through deliverables rather than
through tasks
l Establishes an agreement between all members of the IPT
on these deliverables
l Defines the program in terms of events, accomplishments,
and criteria for these accomplishments
l Establishes the criteria and objectives for program success
l Integrated Master Schedule (IMS) – provides a task and
calendar based schedule at a level necessary for day–to–
execution of the program
IMP/IMS - 5/19
IMP / IMS Assembled From RFP
Requirement WBS Element SOW Task
System Specification
1000 Spacecraft
1100 Avionics
Ground Link
§3.1 Structure (WBS1000)
Design, develop, produce
and verify a complete
spacecraft containing
avionics, propulsion and
other installed equipment.
Integrated Master Plan (IMP)
2004 2005 2006
Program Events PDR CDR
1. Preliminary Design Complete
2. Duty Cycle Defined
Integrated Master Schedule (IMS)
Management Plan Events Accomplishment Criteria
1. Preliminary Design Review PDR 1. a. Duty cycle defined
b. Preliminary analysis complete
1000 Spacecraft
1100 Avionics
1110 Ground Link
.
.
11n0 Avionics
IMP/IMS - 6/19
Simple Overview of the IMP/IMS Relationship
-
-
-
-
SYSTEM XX
Integrated Master Plan
(IMP)
Integrated Master Schedule
(IMS)
ID Task Name Duration Start
1 A01a Needs Analysis
Complete
56h 6/1/94
2 A.01a01 Assign Project
Leader
1d 6/1/94
3 A. 01a02 Perform Needs
Analysis
3d 6/2/94
4 A.01a03 Develop Functional Reqmts1d 6/7/94
5 A.01a04 Present Functional
Requirements
1d 6/8/94
6 A.01a05 Functional Requirements
Approval
1d 6/9/94
7 A01b Plan/Organization Complete32h 6/10/94
8 A01b01 Or ganize Project Team 1d 6/10/94
9 A01b02 Complete Team Contacts
Worksheet
1d 6/13/94
10 A01b03 Develop Project Timeline 1d 6/14/94
11 A01b04 Obtain Authorization for
Resources
1d 6/15/94
12 A01c Project Plan Complete 16h 6/16/94
13 A 01c01 Develop Project Plan
Document
1d 6/16/94
14 A01c02 Signoff Plan by Proj ect
Team
1d 6/17/94
15 A01d Project Plan Approved 16h 6/20/94
16 A.01d01 Present Plan Management1d 6/20/94
17 A01d02 Approve the
Plan
1d 6/21/94
18 A01e Project Start-up Announcement8h 6/22/94
19 A01e01 Distribute Approved
Plan
1d 6/22/94
20 A01e02 Issue Site Communication
Memo
1d 6/22/94
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
May 22, '9 4 May 29, '94 Jun 5, '94 Jun 12, '94 Ju
• Event based Plan
• Contractual document
• Relatively top level
• Task & calendar based Schedule
• Level of detail necessary for
day-to-day execution
SYSTEM XX
Integrated Master Plan (IMP)
ProcessesEvent
Accomplishments Reference
( Criteria
PDR
Integration planning completed
F 16 ACA completed
B 52 ACA completed
B 2 ACA completed
B 1 ACA compl eted
Integrated Master Plan (IMP)
1.0 Introduction
2.0 Event Definitions
IMP/IMS - 7/19
Example IMP
Activity # Event
Ê Significant Accomplishment (SA)
Ê Accomplishment Criteria (AC)
WBS
Reference
E Event E – GN&C Flight Units Complete
E01
ÊRelease 1 Flight Production Complete
—
E01a
Ê Release 1 Subassemblies Complete
1.1.2.2
E01b
Ê Release 1 Assembly/Integration/Test
1.1.2.2
E02
Ê Release 1a Flight Production Complete
—
E02a
Ê Release 1a Subassembly complete
1.1.2.4
E02B
Ê Release 1a ATLO
1.1.2.4
IMP/IMS - 8/19
Program Events
l Program Events are assessment points which occur at the
conclusion of significant program activities
l Events are key transition points in the program
– Key points of maturation
– Major product deliveries
– Test and integration points
– Key decision points
l Events are points on the program schedule where the
“entire” program team – customer included – reach
agreement on the status of the program.
– They represent either the beginning or end of integrated program
team activities
– Key tasks or accomplishments yield evidence that the work is
moving forward at an acceptable pace
IMP/IMS - 9/19
Components of an Event
l Events defined in an “event dictionary”
– Name of the event
– Purpose of the event
– What review the event includes
– Expectations at this point in time
Event 1 – Systems Requirements Review (SRR)
Purpose: Ascertain the technical direction of Delivery Order to ensure technical
compliance to user needs. Ensure risk and other management programs and plans are
effectively in place and the organization is functioning as an IPPD team
Includes: review of Pre-contract risk reduction effort; Post Award Conference and
initial working group meetings; program requirements; program management controls;
initial HWCI/CSCIs; functional baseline; risk assessment; and cost, schedule, technical,
and unit cost performance.
Expectations: Common understanding of all key contract elements (CLINs, schedules,
etc.) and a clear well defined requirements baseline for subsequent system development
IMP/IMS - 10/19
Event / Accomplishment Evaluation Criteria
l Do the Events and Accomplishments reflect the logical
evolution and progress of the Program?
– Do the events demonstrate the maturity of the program over its life?
– Do the Accomplishments and Criteria identify meaningful and
measurable progress toward key goals?
l Do the Accomplishments of each Event demonstrate an
understanding of the requirements or are they simply
generic tasks?
– Do these accomplishments reflect the Statement of Work?
l Does the IMP structure map to the IPT structure so each IPT
member knows their scope of responsibility?
l Is visibility provided to track risk and risk mitigation steps?
l After award, can the Accomplishments be used as activity
cost accounts for the EVMS system?
IMP/IMS - 11/19
Significant Accomplishments (SA)
l Significant Accomplishments are the desired results prior
to or at the completion of an event that indicate a level of
the program's progress.
l Shows completion or result of a discrete step in the work
process
l Is relevant and logically linked to an “event”
l Uses consistent language, style and format
– This is a critical issue and a standard dictionary of verbs is needed
IMP/IMS - 12/19
Accomplishment Criteria (AC)
l Accomplishment Criteria provide the definitive evidence
that a specific accomplishment has been completed
l Accomplishment Criteria must:
– Measure success or product maturity over time
– Provide objective, explicit proof of completion
– Highlight specific areas of effort for tracking, monitoring risk, or
incrementally verifying a process of product
– Relate directly to accomplishments
– Answer “how do I know when a accomplishment has been
completed”
– Focus of exit criteria
– Express entrance criteria as predecessors in the IMS
IMP/IMS - 13/19
Tasks
l Tasks are time phased, detailed activities (where work is
accomplished and funds are expended) required to support
the IMP criteria and accomplishments
l Tasks are broken down from the Event Criteria
– Tasks broken down into sub–tasks
– The sum of all the tasks covers all the Contractor WBS Dictionary,
Statement of Work and other contractual requirements
– ONLY durations, predecessors and lags – no dates
l For each Task
– Lag or % – SS+50%
– Rationale for duration and predecessors in dependency link
described in the notes field
– Resources for each task used for Basis of Estimate
IMP/IMS - 14/19
IMS Development within the IPT
IMS Critical Path Analysis, Baseline, Monitor, Update
Define IMS tasks/activities, durations and dependencies
Combine, consolidate, refine across program
IMP Key Events (RFP + unique)
“Product Tree” Systems Engineering IPT & other AITs
IPT Structure WBS Structure
Each IPT defines SAs & ACs for their WBS elements
May Need
Multiple
Iterations
IMP/IMS - 15/19
Integrated Master Schedule (IMS)
l Integrated, networked, multi–layer schedule of activities
needed to achieve the contractual objectives
l Detailed tasks to be completed
l Networked schedule will all dependent tasks linked
– Task numbering correlates IMS with Project IMP
– Both Gantt and Network provided
l Critical path identified and analysis of schedule slack
– Used during execution to track progress to plan
l Layering allows different levels of detail to be shown
l Resource loading should match EVMS
IMP/IMS - 16/19
Constructing an IMS
l The IMS is built as a iterative process between the IPT
members
– Detailed task identification takes place through an IMP/IMS Point of
Contact (POC) using the WBS dictionary
– PM-100 requires “activities in the detailed networks should be
generally be no longer than twenty (20) working days in duration”
– Level of Effort tasks should avoid “grabbing” the critical path, by
keeping the completion dates of LOE short of the program end date
l Task constraints must be “well formed”
– “Must Finish On,” “Finish No Later Than,” and “Start No Later Than”
constraints should be avoided since they do not support credible
risk assessment and given unreliable results in a statistical risk
assessment
– Hard constraints from the government should not be carried as
hard constraints in the IMS
IMP/IMS - 17/19
Task Relationships
l Finish-to-Start (FS) – the standard “one task must finish
before another starts” link:
– A test cannot begin until test procedures are written.
l Start-to-Start (SS) - this is used when one task cannot start
until another starts (often involves some lag time)
– A test is scheduled for four weeks, but gathering test results begins
1 week after the start of the tests
l Finish-to-Finish (FF) - appropriate where only task
completion (but not the start) is driven by another task
– The design could start anytime, but can’t complete until 1 month
after environmental results are available
l Start-to-Finish (SF) - used for administrative-type tasks you
want driven by another task
– Preparing the agenda two weeks prior to a review
IMP/IMS - 18/19
Maintaining the IMS Post–Award
l For the IMS
– Criteria for IMS changes should be clerarly satted
– Coordination process for changes documented
– Key contract dates may be impacted
– Ensure changes are monitored and distributed to IPT members
– Monitor linkage to IMP and other management tools (EVMS)
l For IMP
– IMP requires contract modification to implement changes
– Minor changes to IMP may not impact contract
IMP/IMS - 19/19
Summary
l IMP/IMS approach is a disciplined approach for planning,
organizing and managing a program
l IMP is a contractual roadmap for the entire program
l IMS is a key tool for monitoring program progress
l These are complex, expensive documents, that force the
contractor to plan essentials of program
l In order to maximize their usefulness after award they need
to be developed and maintained with care
l The “trick” is balancing detail with ease-of-use with
contract compliance

More Related Content

What's hot

The Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System DeploymentThe Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System DeploymentGlen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darksideGlen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPKevin West
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGlen Alleman
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccessGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Glen Alleman
 
Risk Management Processes (v2)
Risk Management Processes (v2)Risk Management Processes (v2)
Risk Management Processes (v2)Glen Alleman
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11tony1234
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated masterGlen Alleman
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contractsGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsGlen Alleman
 

What's hot (20)

The Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System DeploymentThe Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System Deployment
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
WBS is Paramount
WBS is ParamountWBS is Paramount
WBS is Paramount
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
CMMI and Agile
CMMI and AgileCMMI and Agile
CMMI and Agile
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
 
Risk Management Processes (v2)
Risk Management Processes (v2)Risk Management Processes (v2)
Risk Management Processes (v2)
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 

Similar to IMP IMS overview

How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance ProgressGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
Technical Performance Measures
Technical Performance MeasuresTechnical Performance Measures
Technical Performance MeasuresGlen Alleman
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)Glen Alleman
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountGlen Alleman
 
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsSe 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsbabak danyal
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Software Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer ScienceSoftware Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer ScienceArti Parab Academics
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanGlen Alleman
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelPrakash Poudel
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinhNASAPMC
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
PS Module Overview
PS Module OverviewPS Module Overview
PS Module Overviewitplant
 
CGZ52qF5TAueGeExyhhO_PPT_VILT.pptx
CGZ52qF5TAueGeExyhhO_PPT_VILT.pptxCGZ52qF5TAueGeExyhhO_PPT_VILT.pptx
CGZ52qF5TAueGeExyhhO_PPT_VILT.pptxSreekanthMylavarapu1
 

Similar to IMP IMS overview (20)

How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Technical Performance Measures
Technical Performance MeasuresTechnical Performance Measures
Technical Performance Measures
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsSe 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
 
Earned value
Earned valueEarned value
Earned value
 
Software Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer ScienceSoftware Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer Science
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity model
 
SW_Cost_Estimation.ppt
SW_Cost_Estimation.pptSW_Cost_Estimation.ppt
SW_Cost_Estimation.ppt
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinh
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
PS Module Overview
PS Module OverviewPS Module Overview
PS Module Overview
 
CGZ52qF5TAueGeExyhhO_PPT_VILT.pptx
CGZ52qF5TAueGeExyhhO_PPT_VILT.pptxCGZ52qF5TAueGeExyhhO_PPT_VILT.pptx
CGZ52qF5TAueGeExyhhO_PPT_VILT.pptx
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)Glen Alleman
 
Writing Proposal Text
Writing Proposal TextWriting Proposal Text
Writing Proposal TextGlen Alleman
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project RiskGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 
Writing Proposal Text
Writing Proposal TextWriting Proposal Text
Writing Proposal Text
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 

Recently uploaded

Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 

Recently uploaded (20)

Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 

IMP IMS overview

  • 1. 1 IMP/IMS Overview Glen B Alleman glen.alleman@Niwotridge.com
  • 2. IMP/IMS - 2/19 Integrated Management Framework Statement of Work (SOW) User requirements decomposed from RFP • Event-driven plan for entire program • Product and Process Sections Determined by performance • Guidance usually in RFP • Tailored to contractor’s program / products • Provides single numbering system for entire program • Contractor generated. Based on SOW • Guidance provided in RFP IMS • Expands IMP, Provides timing Links cost to IMS thru WBS PLACED ON CONTRACT USED TO TRACK PERFORMANCE USED TO REPORT PERFORMANCE Technical Requirements WBS CPARS Technical Performance Measures Process Metrics • Process quality measures Earned Value Management System (EVMS) Integrated Master Plan (IMP)
  • 3. IMP/IMS - 3/19 What’s the objective of all this formality? Objective è Implementation Event driven plan versus a schedule driven plan based on completion of tasks è Separate plan (IMP) from schedule (IMS) but link elements with numbering system Condensed, easy to read “plan” showing “events” rather than effort è Indentured, outline format (not text) Pre-defined entry and exit conditions for major program events è Significant accomplishments (SA) for each key event (submitted in proposal) Objective measure of progress/ completion for each accomplishment è Pre–defined accomplishment criteria (AC) for each SA Stable, contractual plan flexible enough to portray program status è IMP is part of contract, IMS is data item Capture essence of functional processes without mandating a particular process è Split IMP into Product and Process sections
  • 4. IMP/IMS - 4/19 Integrated Master Plan / Integrated Master Schedule l Integrated Master Plan (IMP) – provides a single plan describing the fundamental structure of the program l Focuses the integrated product team (IPT) team on the customer requirements through deliverables rather than through tasks l Establishes an agreement between all members of the IPT on these deliverables l Defines the program in terms of events, accomplishments, and criteria for these accomplishments l Establishes the criteria and objectives for program success l Integrated Master Schedule (IMS) – provides a task and calendar based schedule at a level necessary for day–to– execution of the program
  • 5. IMP/IMS - 5/19 IMP / IMS Assembled From RFP Requirement WBS Element SOW Task System Specification 1000 Spacecraft 1100 Avionics Ground Link §3.1 Structure (WBS1000) Design, develop, produce and verify a complete spacecraft containing avionics, propulsion and other installed equipment. Integrated Master Plan (IMP) 2004 2005 2006 Program Events PDR CDR 1. Preliminary Design Complete 2. Duty Cycle Defined Integrated Master Schedule (IMS) Management Plan Events Accomplishment Criteria 1. Preliminary Design Review PDR 1. a. Duty cycle defined b. Preliminary analysis complete 1000 Spacecraft 1100 Avionics 1110 Ground Link . . 11n0 Avionics
  • 6. IMP/IMS - 6/19 Simple Overview of the IMP/IMS Relationship - - - - SYSTEM XX Integrated Master Plan (IMP) Integrated Master Schedule (IMS) ID Task Name Duration Start 1 A01a Needs Analysis Complete 56h 6/1/94 2 A.01a01 Assign Project Leader 1d 6/1/94 3 A. 01a02 Perform Needs Analysis 3d 6/2/94 4 A.01a03 Develop Functional Reqmts1d 6/7/94 5 A.01a04 Present Functional Requirements 1d 6/8/94 6 A.01a05 Functional Requirements Approval 1d 6/9/94 7 A01b Plan/Organization Complete32h 6/10/94 8 A01b01 Or ganize Project Team 1d 6/10/94 9 A01b02 Complete Team Contacts Worksheet 1d 6/13/94 10 A01b03 Develop Project Timeline 1d 6/14/94 11 A01b04 Obtain Authorization for Resources 1d 6/15/94 12 A01c Project Plan Complete 16h 6/16/94 13 A 01c01 Develop Project Plan Document 1d 6/16/94 14 A01c02 Signoff Plan by Proj ect Team 1d 6/17/94 15 A01d Project Plan Approved 16h 6/20/94 16 A.01d01 Present Plan Management1d 6/20/94 17 A01d02 Approve the Plan 1d 6/21/94 18 A01e Project Start-up Announcement8h 6/22/94 19 A01e01 Distribute Approved Plan 1d 6/22/94 20 A01e02 Issue Site Communication Memo 1d 6/22/94 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T May 22, '9 4 May 29, '94 Jun 5, '94 Jun 12, '94 Ju • Event based Plan • Contractual document • Relatively top level • Task & calendar based Schedule • Level of detail necessary for day-to-day execution SYSTEM XX Integrated Master Plan (IMP) ProcessesEvent Accomplishments Reference ( Criteria PDR Integration planning completed F 16 ACA completed B 52 ACA completed B 2 ACA completed B 1 ACA compl eted Integrated Master Plan (IMP) 1.0 Introduction 2.0 Event Definitions
  • 7. IMP/IMS - 7/19 Example IMP Activity # Event Ê Significant Accomplishment (SA) Ê Accomplishment Criteria (AC) WBS Reference E Event E – GN&C Flight Units Complete E01 ÊRelease 1 Flight Production Complete — E01a Ê Release 1 Subassemblies Complete 1.1.2.2 E01b Ê Release 1 Assembly/Integration/Test 1.1.2.2 E02 Ê Release 1a Flight Production Complete — E02a Ê Release 1a Subassembly complete 1.1.2.4 E02B Ê Release 1a ATLO 1.1.2.4
  • 8. IMP/IMS - 8/19 Program Events l Program Events are assessment points which occur at the conclusion of significant program activities l Events are key transition points in the program – Key points of maturation – Major product deliveries – Test and integration points – Key decision points l Events are points on the program schedule where the “entire” program team – customer included – reach agreement on the status of the program. – They represent either the beginning or end of integrated program team activities – Key tasks or accomplishments yield evidence that the work is moving forward at an acceptable pace
  • 9. IMP/IMS - 9/19 Components of an Event l Events defined in an “event dictionary” – Name of the event – Purpose of the event – What review the event includes – Expectations at this point in time Event 1 – Systems Requirements Review (SRR) Purpose: Ascertain the technical direction of Delivery Order to ensure technical compliance to user needs. Ensure risk and other management programs and plans are effectively in place and the organization is functioning as an IPPD team Includes: review of Pre-contract risk reduction effort; Post Award Conference and initial working group meetings; program requirements; program management controls; initial HWCI/CSCIs; functional baseline; risk assessment; and cost, schedule, technical, and unit cost performance. Expectations: Common understanding of all key contract elements (CLINs, schedules, etc.) and a clear well defined requirements baseline for subsequent system development
  • 10. IMP/IMS - 10/19 Event / Accomplishment Evaluation Criteria l Do the Events and Accomplishments reflect the logical evolution and progress of the Program? – Do the events demonstrate the maturity of the program over its life? – Do the Accomplishments and Criteria identify meaningful and measurable progress toward key goals? l Do the Accomplishments of each Event demonstrate an understanding of the requirements or are they simply generic tasks? – Do these accomplishments reflect the Statement of Work? l Does the IMP structure map to the IPT structure so each IPT member knows their scope of responsibility? l Is visibility provided to track risk and risk mitigation steps? l After award, can the Accomplishments be used as activity cost accounts for the EVMS system?
  • 11. IMP/IMS - 11/19 Significant Accomplishments (SA) l Significant Accomplishments are the desired results prior to or at the completion of an event that indicate a level of the program's progress. l Shows completion or result of a discrete step in the work process l Is relevant and logically linked to an “event” l Uses consistent language, style and format – This is a critical issue and a standard dictionary of verbs is needed
  • 12. IMP/IMS - 12/19 Accomplishment Criteria (AC) l Accomplishment Criteria provide the definitive evidence that a specific accomplishment has been completed l Accomplishment Criteria must: – Measure success or product maturity over time – Provide objective, explicit proof of completion – Highlight specific areas of effort for tracking, monitoring risk, or incrementally verifying a process of product – Relate directly to accomplishments – Answer “how do I know when a accomplishment has been completed” – Focus of exit criteria – Express entrance criteria as predecessors in the IMS
  • 13. IMP/IMS - 13/19 Tasks l Tasks are time phased, detailed activities (where work is accomplished and funds are expended) required to support the IMP criteria and accomplishments l Tasks are broken down from the Event Criteria – Tasks broken down into sub–tasks – The sum of all the tasks covers all the Contractor WBS Dictionary, Statement of Work and other contractual requirements – ONLY durations, predecessors and lags – no dates l For each Task – Lag or % – SS+50% – Rationale for duration and predecessors in dependency link described in the notes field – Resources for each task used for Basis of Estimate
  • 14. IMP/IMS - 14/19 IMS Development within the IPT IMS Critical Path Analysis, Baseline, Monitor, Update Define IMS tasks/activities, durations and dependencies Combine, consolidate, refine across program IMP Key Events (RFP + unique) “Product Tree” Systems Engineering IPT & other AITs IPT Structure WBS Structure Each IPT defines SAs & ACs for their WBS elements May Need Multiple Iterations
  • 15. IMP/IMS - 15/19 Integrated Master Schedule (IMS) l Integrated, networked, multi–layer schedule of activities needed to achieve the contractual objectives l Detailed tasks to be completed l Networked schedule will all dependent tasks linked – Task numbering correlates IMS with Project IMP – Both Gantt and Network provided l Critical path identified and analysis of schedule slack – Used during execution to track progress to plan l Layering allows different levels of detail to be shown l Resource loading should match EVMS
  • 16. IMP/IMS - 16/19 Constructing an IMS l The IMS is built as a iterative process between the IPT members – Detailed task identification takes place through an IMP/IMS Point of Contact (POC) using the WBS dictionary – PM-100 requires “activities in the detailed networks should be generally be no longer than twenty (20) working days in duration” – Level of Effort tasks should avoid “grabbing” the critical path, by keeping the completion dates of LOE short of the program end date l Task constraints must be “well formed” – “Must Finish On,” “Finish No Later Than,” and “Start No Later Than” constraints should be avoided since they do not support credible risk assessment and given unreliable results in a statistical risk assessment – Hard constraints from the government should not be carried as hard constraints in the IMS
  • 17. IMP/IMS - 17/19 Task Relationships l Finish-to-Start (FS) – the standard “one task must finish before another starts” link: – A test cannot begin until test procedures are written. l Start-to-Start (SS) - this is used when one task cannot start until another starts (often involves some lag time) – A test is scheduled for four weeks, but gathering test results begins 1 week after the start of the tests l Finish-to-Finish (FF) - appropriate where only task completion (but not the start) is driven by another task – The design could start anytime, but can’t complete until 1 month after environmental results are available l Start-to-Finish (SF) - used for administrative-type tasks you want driven by another task – Preparing the agenda two weeks prior to a review
  • 18. IMP/IMS - 18/19 Maintaining the IMS Post–Award l For the IMS – Criteria for IMS changes should be clerarly satted – Coordination process for changes documented – Key contract dates may be impacted – Ensure changes are monitored and distributed to IPT members – Monitor linkage to IMP and other management tools (EVMS) l For IMP – IMP requires contract modification to implement changes – Minor changes to IMP may not impact contract
  • 19. IMP/IMS - 19/19 Summary l IMP/IMS approach is a disciplined approach for planning, organizing and managing a program l IMP is a contractual roadmap for the entire program l IMS is a key tool for monitoring program progress l These are complex, expensive documents, that force the contractor to plan essentials of program l In order to maximize their usefulness after award they need to be developed and maintained with care l The “trick” is balancing detail with ease-of-use with contract compliance