SlideShare a Scribd company logo
1 of 40
Integrated Performance Management 2014
Using Technical Progress to Inform
Earned Value Performance
Glen B. Alleman
Niwot Ridge, L.L.C.
+1 303 241 9633
glen.alleman@niwotridge.com
Thomas J. Coonce
Institute for Defense Analyses
+1 703 362 2568
tom.coonce@ida.org
Rick A. Price
Lockheed Martin
+1 303 971 1826
rick.a.price@lmco.com
1
2
EAI-748-C Tells Us To …
 Objectively assess accomplishments at the
work performance level.
And at the same time, says in §3.8
 Earned Value is a direct measurement of the
quantity of work accomplished.
 The quality and technical content of the work
performed is controlled by other processes.
GA
3
It’s Going To Be Hard to Tell When
We’ll Arrive at our Destination …
 If we only measure our progress by CPI and
SPI, whose units of measure are dollars.
 We need to connect technical and quality
measures with these EV measures.
GA
4
4
Technical Performance Informs
Earned Value
DI-MGMT-81861 §1.2.1 says …
Integrate cost and schedule performance with objective technical measures of performance
Objective Technical Measures
Cost Performance Schedule Performance
Conventional Earned Value
+
=
Basis of Estimate developed from
scope of work and historical
performance, and risk adjusted
for all classes of cost, to produce
a resource loaded PMB with MR
established in the EVMS.
The ETC and EAC updated as the
program progresses using
objective technical measures of
performance.
Cost
Measures of Effectiveness
(MOE), Measures of
Performance (MOP), Technical
Performance Measures (TPM),
Key Performance Parameters
(KPP), and, other …ilities of the
technical aspects of the program
performance inform the Physical
Percent Complete used to Inform
BCWP.
Objective Technical Measures
Deterministic IMS derived from
the IMP / Statement of Work
(SOW), showing how all
deliverables defined in the WBS
will be produced and reducible
risks mitigated with Retirement
Plans, and Irreducible risks
mitigated with schedule marring
and Management Reserve, to
establish the Credible PMB.
Schedule
GA
5
5
What Sources Can Be Used To For
Objective Technical Measures of
Performance?
Risk
SOW
Cost
WBS
IMP/IMS
TPM
PMB
GA
6
6
How Are These Sources Connected?
Risk
Management
SOW
SOO
ConOps
WBS
Techncial and Operational
Requirements
CWBS &
CWBS Dictionary
Integrated Master Plan
(IMP)
Integrated Master Schedule
(IMS)
Earned Value Management
System (EVMS)
Performance Measurement Baseline (PBM)
Measures of
Effectiveness (MOE)
Measures of
Performance (MOP)
Measures of Progress
(Physical % Complete)
JROC
Key Performance Parameters
(KPP)
Program Specific
Key Performance Parameters
(KPP)
Technical Performance
Measures (TPM)
CWBS
6
Objective Technical Measures of Performance provide information for proactive
management processes needed to keep the program GREENTC
7
7
6 Steps To These Connections
Step Outcome
❶
Define
WBS
 With SOW, SOO, ConOps, WBS, and other program documents, develop
CWBS of system deliverables and work processes to produce the program
outcomes.
 Develop CWBS Dictionary describing scope of work and Criteria for the
successful delivery of these outcomes.
❷
Build IMP
 Develop Integrated Master Plan (IMP), showing how each system element in
the CWBS moves through the maturation process at each Program Event.
 Define Measures of Effectiveness (MOE) for each Accomplishment.
 Define Measures of Performance (MOP) for each Criteria.
❸
Identify
Reducible
Risk
 For each key system element in the CWBS, identify reducible risks,
probability of occurrence, mitigation plan, and residual risk in the Risk
Register.
 Risk mitigation activities placed in IMS and PMB to assure probability of
occurrence and probability of impact reduced.
 For risks without mitigation plans, place budget for risk in Management
Reserve (MR) to be used to handle risk when it becomes an Issue.TC
8
8
Step Outcome
❹
Build the
IMS
 Arrange Work Packages and Tasks in a logical network of increasing maturity
of the deliverables.
 Define exit criteria for each Work Package to assess planned Physical
Percent Complete to inform BCWP using TPM, MOP, MOE, and Risk
Reduction activities in support of Accomplishments in the IMS.
❺
Adjust for
Irreducible
Risks
 For irreducible risks in the IMS, use Reference Classes for Monte Carlo
Simulation anchored with Most Likely duration to calculate needed schedule
margin.
 Assign schedule margin tasks in the IMS, to protect the key system
elements, per DI-MGMT-81861 guidance.
❻
Establish
PMB
 Using risk adjusted IMS, calculate needed Management Reserve (MR) to
account for the latent risks in the Risk Register.
 With deterministic IMS and its embedded Schedule Margin and
Management Reserve for latent risk, determine the resulting confidence
level of the PMB.
6 Steps To These Connections
TC
9
9
A Reminder of our Starting Point
1.2.1 Integrate cost and schedule
performance data with
objective technical measures
of performance
DI-MGMT-81861†
†Integrated Program Management Report (IPMR), DI-MGMT-81861, OUSD
(AT&L) PARCA, 20 Jun 2012
TC
10
10
❶ DEFINE WORK BREAKDOWN
STRUCTURE
WORK BREAKDOWN STRUCTURE IS PARAMOUNT
The Work Breakdown Structure is the starting point for
developing all other elements needed for the
Performance Measurement Baseline.
With the WBS Dictionary, technical measures are
developed to provide assessment of Physical Percent
Complete of each deliverable.
GA
11
Work Breakdown Structure
 Mutually Exclusive – no subcategory should represent
any other subcategory ("no overlaps"). In the WBS this
means the deliverables are unique so we can assign
cost to them and determine who is going to develop
them.
 Collectively Exhaustive - the set of all subcategories,
taken together, should fully characterize the larger
category of which the data are part ("no gaps"). The
WBS represents the "all in” work. If it's not in the WBS,
it's going to get done.
Mutually Exclusive and Collectively Exhaustive
GA
12
Building a Good WBS
 Know the components of the system that are ME
(Mutually Exclusive).
 Children of these components are CE (Collectively
Exhaustive).
– Parts can be shared in the WBS, only if the work for
those parts can be shared
– But they need different WBS numbers
– So they are ME, while being CE
 WBS collects costs and answers, "what does this
part, sub-assembly, assembly, system cost?”
GA
13
The Work Breakdown Structure is
Start of Risk Management
 Terminal nodes of the WBS are where the
Deliverables live.
 Each must be assessed for the possible risk
that will imped their success in meeting:
– Measures of Effectiveness,
– Measures of Performance,
– Technical Performance Measures,
– Key Performance Parameters,
– All their …ilities.
GA
14
14
❷ BUILD INTEGRATED MASTER PLAN
BUILDING THE IMP IS A SYSTEMS
ENGINEERING ACTIVITY
The IMP represents the Programmatic Architecture.
Poor, weak, or unstructured Programmatic Architecture
reduces visibility to the product’s cost and schedule
performance connected with Technical Performance
Measures.
RP
15
15
The Integrated Master Plan describes where the program is going, the various
paths taken to reach destination, and the progress or performance
assessment points along the way to assure it is on the right path.
These assessment points measures the “maturity” of the product or service
against the planned maturity. This is the only real measure of progress – not
the passage of time or consumption of money.
The Integrated Master Plan (IMP) Is The Strategy For
The Successful Completion Of The Project
RP
16
Structure of the Integrated Master
Plan (IMP)
 Vertical and Horizontal traceability assures each deliverable
is assessed for increasing maturity against its planned
maturity
IMS
IMP
Describes how program
capabilities will be
delivered and
how these
capabilities will
be recognized
as ready for
delivery
Supplemental Schedules (CAM Notebook)
Work Packages and Tasks
Criteria
Accomplishment
Events
or
Milestones
RP
17
17
Wright Flyer
Objective Technical
Measures
The Army Contract No. 486 Says
Program
Performance
Measure
The flying machine must be designed to carry two people having a combined weight of no more than 350
pounds,
MOP
Also sufficient fuel for a flight of 125 miles MOP
The flying machine should be designed to have a speed of at least 40 miles per hour in still air for at least
125 miles
MOP
The flying machine should be designed so that it may be quickly and easily assembled and taken apart
and packed into an Army wagon.
KPP
It should be capable of being assembled and put in operating condition within one hour KPP
Before acceptance, a trial endurance flight will be required of at least one hour during which time, MOP
The flying machine must remain continuously in the air without landing. MOE
It shall return to the starting point and land without any damage that would prevent it immediately
starting upon another flight.
MOE
During this flight of one hour, it must be steered in all directions without difficulty and at all times under
perfect control and equilibrium.
MOE
It should be sufficiently simple in its construction and operation to permit an intelligent man to become
proficient in its use within a reasonable length of time.
KPP
TC
18
18
❸ IDENTIFY REDUCIBLE RISKS
REDUCIBLE RISKS IDENTIFIED AND PLACED IN THE
RISK REGISTER
The Risk Register contains the probability of occurrence,
the probabilistic impact of the risk on cost, schedule, and
technical performance, cost of mitigating the risk, residual
probability of the risk after mitigation, and impact of the
risks after mitigation.
GA
19
19
Reducible Risk Is Created By
Lack of Knowledge (Epistemology)
Uncertainty
Reducible Irreducible
Natural
Variability
Ambiguity
Known but
un-mitigateable
Probabilistic
Events
Probabilistic
Impacts
Periods of
Exposure
The probability of an
event that we can do
something about,
reducing this
probability through
explicit actions.
Statistical range of
natural randomness
characterized by a
historical data, and
therefore irreducible
Epistemic Aleatory
GA/TC
20
Identifying Reducible Risks
 Identify pre-mitigation
– Probability of
occurrence
– Probability of impact
– Cost of mitigation
 Identify post-mitigation
– Probability of occurrence
– Probability of impact
– Residual risk after
mitigation
TC
21
Reducible Risks Must Have
Retirement Plans in the IMS
 Buying down reducible risk is a measure of
performance for the program
RP
Risk ID# 12 If the Power Distribution Unit fails vibration test, redesign will be necessary
22
22
❹ BUILD INTEGRATED MASTER
SCHEDULE
INTEGRATED MASTER SCHEDULE (IMS)
DERIVED FROM
INTEGRATED MASTER PLAN (IMP) CRITERIA
IMS Shows The Order In Which The Work Packages Must
Be Performed To Assure The Criteria Are Completed Within
The Define Measures Of Performance, Key Performance
Parameters, And The Technical Performance Measures.
GA
23
The Integrated Master Schedule
 Is a horizontal sequence of work activities that
produce products with increasing maturity of
technical performance
GA
24
24
Assess the maturity
of a Capability at a point in
time.
Requirements that
enable planned Capabilities.
Exit Criteria for Work Packages
That deliver the Requirements.
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
package
 Integrated Master Plan (IMP) is the strategy for the successful
completion of the program, measured as “increasing maturity” of
the Performance Measures (MOE, MOP, TPM, KPP).
 Without a plan we cannot say what “done” looks like.
 Integrated Master Schedule (IMS) defines the Work Packages and
Planning Packages needed to implement the Plan, retire risks,
manage resources, and sequence the detailed work activities.
 Both the Plan and the Schedule are essential for success.
The structure of a
Performance-Based
Program
CRITERIA
ACCOMPLISHMENTS
EVENTS
MOP
MOE
Subsystem
System
GA
25
25
❺ ADJUST FOR IRREDUCIBLE RISKS
IRREDUCIBLE UNCERTAINTY
CREATES
IRREDUCIBLE TECHNICAL AND PROGRAMMATIC
RISK
This Naturally Occurring Uncertainty Impacts Schedule
And Cost In Irreducible Ways. It Can’t Be Bought Down.
Irreducible Risks Can Only Be Mitigated With Margin.
GA
26
26
Irreducible Risk Driven By
Natural Variability
Uncertainty
Reducible Irreducible
Natural
Variability
Ambiguity
Known but
un-mitigateable
Probabilistic
Events
Probabilistic
Impacts
Periods of
Exposure
The probability of an
event that we can do
something about
reducing this
probability through
explicit actions.
Statistical range of
natural randomness
characterized by a
historical data and
therefore irreducible
Epistemic Aleatory
GA
27
27
Identifying Irreducible Risks
Starts With Reference Class Forecasting
GA
28
Applying Reference Classes to Work Activities
to Construct Network of Random Processes
 The independence or
dependency of each task
with others in the network,
greatly influences the
outcome of the total project
duration.
 Understanding these
dependencies is critical to
assessing the credibility of
the IMS as well as the total
completion time.
 Any path could be critical depending on the probability distributions
of the underlying task completion probability functions.
We must know something about the
probability distributions of the work efforts
GA
29
29
Irreducible Risks Are Mitigated With
Margin For Both Cost and Schedule
 The contract delivery date is 8/31/08
 The IMS without schedule margin has
a confidence of 80% on or before
8/14/08
 The deterministic date is 8/4/08
 10 days of margin protect contractual
schedule with 80% confidence
8/4/1908
Deterministic
Date
GA/RP
8/14/1908
80% On or
Before
8/31/1908
Deterministic
Date
30
30
Schedule Margin Burn Down is a
Measure of Program Performance
RP
31
31
But, Beware the Black Swan
There is no Plan B for Black Swans – Must Replan 31
Natalie Portman, as Nina Sayers, The Swan Queen
Black Swan – An event or occurrence that
deviates beyond what is normally expected of a
situation and that would be extremely difficult
to predict. This term was popularized by Nassim
Nicholas Taleb, a finance professor and former
Wall Street trader.
32
32
❻ ESTABLISH THE PMB
EACH ELEMENT OF THE IMP AND IMS ARE
NEEDED FOR A CREDIBLE PERFORMANCE
MEASUREMENT BASELINE
The Credible PMB Requires That Each Element Itself Be
Credible With The Relationships Properly Established,
Maintained, And Updated.
3333
Connecting the Dots in the PMB
WBS KPPs TPMs
EVM
ETC
EAC
Irreducible
uncertainty
in reference
classes Reducible
uncertainty held
in Risk Register
Schedule Margin in
DI-MGMT-81861
Cost Contingency †
Risk retirement in PMB
Management Reserve
covers unmitigated risk
MOE
MOP
Physical %
Complete
PE
SA
AC
JROC KPP
IMP
IMS WP
33GA
34
34
EXECUTING THE PERFORMANCE
MEASUREMENT BASELINE
A well known example of integrating the elements of a credible PMB needed to
successfully complete a program can be found in the Wright Brothers, 23
December 1907, Army Contract, No. 486
http://www.wright-brothers.org/History_Wing/Wright_Story/Showing_the_World/Back_in_Air/Signal_Corps_Spec.htm
TC
35
35
Executing the
Performance Measurement Baseline
Take management action for any variances to assure on–time, on–
budget and on–specification of all deliverables produced by the Work
Packages.
Maintain Performance Management Baseline (PMB) throughout project
duration for Earned Value measures in Objective units of measure at the
work performance level, meaningful to the decision makes
Perform the Work described in the network of Work Packages held in the
IMS, in the planned order, with the planned budget with the planned
outcomes, meeting the planned performance measures.
Accumulate and Report Performance Data – BCWP – and other
increasing maturing assessment processes based on Physical Percent
Complete described in the MOEs, MOPs, TPMs, and KPPs.
Analyze Performance Data derived from the Earned Value metrics –
informed by Technical Performance – and make any adjustments to the
network of Work Packages to keep program GREEN.
TC
36
Connecting Technical Performance
(Weight) with EV Performance
 Planned weight reduction of Wright Flyer
connected with Earned Value performance by
planned date is a TPM
Earned Value
Performance
Weight Target
in or out of bounds
Informs
Weight out
of bounds
BCWP should
follow weight
TC
37
37
Summary of Steps To Create The
Credible PMB
6 Steps To Success
❶ Define WBS ❹ Build the IMS
❷ Build IMP ❺ Adjust for Irreducible Risks
❸ Identify Reducible Risk ❻ Establish the PMB
1.2.1 Integrate cost and schedule performance
data with objective technical measures of
performance
DI-MGMT-81861†
† Integrated Program Management Report (IPMR), DI-MGMT-81861, OUSD (AT&L) PARCA, 20 Jun 2012
And One Last Reminder
TC
38
References
 IMP/IMS Preparation and Use Guide,
http://www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf
 GAO Cost Estimating and Assessment Guide,
http://www.gao.gov/new.items/d093sp.pdf
 GAO Schedule Assessment Guide,
http://www.gao.gov/assets/600/591240.pdf
 Air Force Integrated Master Schedule Assessment Guide,
http://afacpo.com/AQDocs/AF_IMS_%20Assessment_%20Process_%20V3.0.p
df
 The Integrated Project Management Handbook, Dayton Aerospace, Inc.
 Scheduling Guide for Program Managers
https://www.acquisition.gov/sevensteps/library/DAUschedulinguide.pdf
 Integrated Master Plan Analysis, The PMAG Approach, Col. Mun H. Kwon,
USAF, http://www.dau.mil/pubscats/ATL%20Docs/Jan-Feb/kwon_jan-
feb10.pdf
39
References
 AFMC Pamphlet 63-5, Integrated Master Plan and Schedule Guide, (11
Nov 2004), http://www.everyspec.com/USAF/USAF-
AFMC/AFMC_PAM_63-5_4210/
 MSFC-HDBK-3173, Project Management and System Engineering
Handbook, https://standards.nasa.gov/documents/detail/3315842
 Project Planning and Control Handbook, MSFC-HDBK-3684,
https://standards.nasa.gov/documents/viewdoc/3315842/3315842
 NASA Scheduling Management Handbook,
http://www.nasa.gov/pdf/420297main_NASA-SP-2010-3403.pdf
4040
The End
40

More Related Content

What's hot

Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Reliability Program Approval Presentation_
Reliability Program Approval Presentation_
Chad Broussard
 
Al Lahdan 2011
Al Lahdan 2011Al Lahdan 2011
Al Lahdan 2011
lahddan
 
Project Completion Details
Project Completion DetailsProject Completion Details
Project Completion Details
Faisal Saeed
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project Controls
David Mathews
 
Workshop Presentation_Final
Workshop Presentation_FinalWorkshop Presentation_Final
Workshop Presentation_Final
MICHAEL BLUMBERG
 

What's hot (20)

Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Pramod Chand Chaturvedi
Pramod Chand ChaturvediPramod Chand Chaturvedi
Pramod Chand Chaturvedi
 
Analyze Tollgate
Analyze TollgateAnalyze Tollgate
Analyze Tollgate
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
 
Improve Tollgate
Improve TollgateImprove Tollgate
Improve Tollgate
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Reliability Program Approval Presentation_
Reliability Program Approval Presentation_
 
Viresh Jugali CV
Viresh Jugali CVViresh Jugali CV
Viresh Jugali CV
 
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
 
Al Lahdan 2011
Al Lahdan 2011Al Lahdan 2011
Al Lahdan 2011
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Core Competence Framework for CAMO Personnel
Core Competence Framework for CAMO PersonnelCore Competence Framework for CAMO Personnel
Core Competence Framework for CAMO Personnel
 
Product overview- FlyPal
Product overview- FlyPalProduct overview- FlyPal
Product overview- FlyPal
 
Project Completion Details
Project Completion DetailsProject Completion Details
Project Completion Details
 
Ils management overview
Ils management overviewIls management overview
Ils management overview
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project Controls
 
FlyPal Brochure
FlyPal BrochureFlyPal Brochure
FlyPal Brochure
 
Agile EVMS
Agile EVMSAgile EVMS
Agile EVMS
 
Workshop Presentation_Final
Workshop Presentation_FinalWorkshop Presentation_Final
Workshop Presentation_Final
 
Maintenance Benchmarking (3)
Maintenance Benchmarking (3)Maintenance Benchmarking (3)
Maintenance Benchmarking (3)
 

Similar to Using Technical Performance Progress

Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
Glen Alleman
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
Glen Alleman
 

Similar to Using Technical Performance Progress (20)

Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Technical Performance Measures
Technical Performance MeasuresTechnical Performance Measures
Technical Performance Measures
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPI
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)
 
Integrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program successIntegrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program success
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
Earned Value Managed Services
Earned Value Managed ServicesEarned Value Managed Services
Earned Value Managed Services
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 

More from Glen Alleman

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 

Recently uploaded

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Recently uploaded (20)

Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation Strategies
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 

Using Technical Performance Progress

  • 1. Integrated Performance Management 2014 Using Technical Progress to Inform Earned Value Performance Glen B. Alleman Niwot Ridge, L.L.C. +1 303 241 9633 glen.alleman@niwotridge.com Thomas J. Coonce Institute for Defense Analyses +1 703 362 2568 tom.coonce@ida.org Rick A. Price Lockheed Martin +1 303 971 1826 rick.a.price@lmco.com 1
  • 2. 2 EAI-748-C Tells Us To …  Objectively assess accomplishments at the work performance level. And at the same time, says in §3.8  Earned Value is a direct measurement of the quantity of work accomplished.  The quality and technical content of the work performed is controlled by other processes. GA
  • 3. 3 It’s Going To Be Hard to Tell When We’ll Arrive at our Destination …  If we only measure our progress by CPI and SPI, whose units of measure are dollars.  We need to connect technical and quality measures with these EV measures. GA
  • 4. 4 4 Technical Performance Informs Earned Value DI-MGMT-81861 §1.2.1 says … Integrate cost and schedule performance with objective technical measures of performance Objective Technical Measures Cost Performance Schedule Performance Conventional Earned Value + = Basis of Estimate developed from scope of work and historical performance, and risk adjusted for all classes of cost, to produce a resource loaded PMB with MR established in the EVMS. The ETC and EAC updated as the program progresses using objective technical measures of performance. Cost Measures of Effectiveness (MOE), Measures of Performance (MOP), Technical Performance Measures (TPM), Key Performance Parameters (KPP), and, other …ilities of the technical aspects of the program performance inform the Physical Percent Complete used to Inform BCWP. Objective Technical Measures Deterministic IMS derived from the IMP / Statement of Work (SOW), showing how all deliverables defined in the WBS will be produced and reducible risks mitigated with Retirement Plans, and Irreducible risks mitigated with schedule marring and Management Reserve, to establish the Credible PMB. Schedule GA
  • 5. 5 5 What Sources Can Be Used To For Objective Technical Measures of Performance? Risk SOW Cost WBS IMP/IMS TPM PMB GA
  • 6. 6 6 How Are These Sources Connected? Risk Management SOW SOO ConOps WBS Techncial and Operational Requirements CWBS & CWBS Dictionary Integrated Master Plan (IMP) Integrated Master Schedule (IMS) Earned Value Management System (EVMS) Performance Measurement Baseline (PBM) Measures of Effectiveness (MOE) Measures of Performance (MOP) Measures of Progress (Physical % Complete) JROC Key Performance Parameters (KPP) Program Specific Key Performance Parameters (KPP) Technical Performance Measures (TPM) CWBS 6 Objective Technical Measures of Performance provide information for proactive management processes needed to keep the program GREENTC
  • 7. 7 7 6 Steps To These Connections Step Outcome ❶ Define WBS  With SOW, SOO, ConOps, WBS, and other program documents, develop CWBS of system deliverables and work processes to produce the program outcomes.  Develop CWBS Dictionary describing scope of work and Criteria for the successful delivery of these outcomes. ❷ Build IMP  Develop Integrated Master Plan (IMP), showing how each system element in the CWBS moves through the maturation process at each Program Event.  Define Measures of Effectiveness (MOE) for each Accomplishment.  Define Measures of Performance (MOP) for each Criteria. ❸ Identify Reducible Risk  For each key system element in the CWBS, identify reducible risks, probability of occurrence, mitigation plan, and residual risk in the Risk Register.  Risk mitigation activities placed in IMS and PMB to assure probability of occurrence and probability of impact reduced.  For risks without mitigation plans, place budget for risk in Management Reserve (MR) to be used to handle risk when it becomes an Issue.TC
  • 8. 8 8 Step Outcome ❹ Build the IMS  Arrange Work Packages and Tasks in a logical network of increasing maturity of the deliverables.  Define exit criteria for each Work Package to assess planned Physical Percent Complete to inform BCWP using TPM, MOP, MOE, and Risk Reduction activities in support of Accomplishments in the IMS. ❺ Adjust for Irreducible Risks  For irreducible risks in the IMS, use Reference Classes for Monte Carlo Simulation anchored with Most Likely duration to calculate needed schedule margin.  Assign schedule margin tasks in the IMS, to protect the key system elements, per DI-MGMT-81861 guidance. ❻ Establish PMB  Using risk adjusted IMS, calculate needed Management Reserve (MR) to account for the latent risks in the Risk Register.  With deterministic IMS and its embedded Schedule Margin and Management Reserve for latent risk, determine the resulting confidence level of the PMB. 6 Steps To These Connections TC
  • 9. 9 9 A Reminder of our Starting Point 1.2.1 Integrate cost and schedule performance data with objective technical measures of performance DI-MGMT-81861† †Integrated Program Management Report (IPMR), DI-MGMT-81861, OUSD (AT&L) PARCA, 20 Jun 2012 TC
  • 10. 10 10 ❶ DEFINE WORK BREAKDOWN STRUCTURE WORK BREAKDOWN STRUCTURE IS PARAMOUNT The Work Breakdown Structure is the starting point for developing all other elements needed for the Performance Measurement Baseline. With the WBS Dictionary, technical measures are developed to provide assessment of Physical Percent Complete of each deliverable. GA
  • 11. 11 Work Breakdown Structure  Mutually Exclusive – no subcategory should represent any other subcategory ("no overlaps"). In the WBS this means the deliverables are unique so we can assign cost to them and determine who is going to develop them.  Collectively Exhaustive - the set of all subcategories, taken together, should fully characterize the larger category of which the data are part ("no gaps"). The WBS represents the "all in” work. If it's not in the WBS, it's going to get done. Mutually Exclusive and Collectively Exhaustive GA
  • 12. 12 Building a Good WBS  Know the components of the system that are ME (Mutually Exclusive).  Children of these components are CE (Collectively Exhaustive). – Parts can be shared in the WBS, only if the work for those parts can be shared – But they need different WBS numbers – So they are ME, while being CE  WBS collects costs and answers, "what does this part, sub-assembly, assembly, system cost?” GA
  • 13. 13 The Work Breakdown Structure is Start of Risk Management  Terminal nodes of the WBS are where the Deliverables live.  Each must be assessed for the possible risk that will imped their success in meeting: – Measures of Effectiveness, – Measures of Performance, – Technical Performance Measures, – Key Performance Parameters, – All their …ilities. GA
  • 14. 14 14 ❷ BUILD INTEGRATED MASTER PLAN BUILDING THE IMP IS A SYSTEMS ENGINEERING ACTIVITY The IMP represents the Programmatic Architecture. Poor, weak, or unstructured Programmatic Architecture reduces visibility to the product’s cost and schedule performance connected with Technical Performance Measures. RP
  • 15. 15 15 The Integrated Master Plan describes where the program is going, the various paths taken to reach destination, and the progress or performance assessment points along the way to assure it is on the right path. These assessment points measures the “maturity” of the product or service against the planned maturity. This is the only real measure of progress – not the passage of time or consumption of money. The Integrated Master Plan (IMP) Is The Strategy For The Successful Completion Of The Project RP
  • 16. 16 Structure of the Integrated Master Plan (IMP)  Vertical and Horizontal traceability assures each deliverable is assessed for increasing maturity against its planned maturity IMS IMP Describes how program capabilities will be delivered and how these capabilities will be recognized as ready for delivery Supplemental Schedules (CAM Notebook) Work Packages and Tasks Criteria Accomplishment Events or Milestones RP
  • 17. 17 17 Wright Flyer Objective Technical Measures The Army Contract No. 486 Says Program Performance Measure The flying machine must be designed to carry two people having a combined weight of no more than 350 pounds, MOP Also sufficient fuel for a flight of 125 miles MOP The flying machine should be designed to have a speed of at least 40 miles per hour in still air for at least 125 miles MOP The flying machine should be designed so that it may be quickly and easily assembled and taken apart and packed into an Army wagon. KPP It should be capable of being assembled and put in operating condition within one hour KPP Before acceptance, a trial endurance flight will be required of at least one hour during which time, MOP The flying machine must remain continuously in the air without landing. MOE It shall return to the starting point and land without any damage that would prevent it immediately starting upon another flight. MOE During this flight of one hour, it must be steered in all directions without difficulty and at all times under perfect control and equilibrium. MOE It should be sufficiently simple in its construction and operation to permit an intelligent man to become proficient in its use within a reasonable length of time. KPP TC
  • 18. 18 18 ❸ IDENTIFY REDUCIBLE RISKS REDUCIBLE RISKS IDENTIFIED AND PLACED IN THE RISK REGISTER The Risk Register contains the probability of occurrence, the probabilistic impact of the risk on cost, schedule, and technical performance, cost of mitigating the risk, residual probability of the risk after mitigation, and impact of the risks after mitigation. GA
  • 19. 19 19 Reducible Risk Is Created By Lack of Knowledge (Epistemology) Uncertainty Reducible Irreducible Natural Variability Ambiguity Known but un-mitigateable Probabilistic Events Probabilistic Impacts Periods of Exposure The probability of an event that we can do something about, reducing this probability through explicit actions. Statistical range of natural randomness characterized by a historical data, and therefore irreducible Epistemic Aleatory GA/TC
  • 20. 20 Identifying Reducible Risks  Identify pre-mitigation – Probability of occurrence – Probability of impact – Cost of mitigation  Identify post-mitigation – Probability of occurrence – Probability of impact – Residual risk after mitigation TC
  • 21. 21 Reducible Risks Must Have Retirement Plans in the IMS  Buying down reducible risk is a measure of performance for the program RP Risk ID# 12 If the Power Distribution Unit fails vibration test, redesign will be necessary
  • 22. 22 22 ❹ BUILD INTEGRATED MASTER SCHEDULE INTEGRATED MASTER SCHEDULE (IMS) DERIVED FROM INTEGRATED MASTER PLAN (IMP) CRITERIA IMS Shows The Order In Which The Work Packages Must Be Performed To Assure The Criteria Are Completed Within The Define Measures Of Performance, Key Performance Parameters, And The Technical Performance Measures. GA
  • 23. 23 The Integrated Master Schedule  Is a horizontal sequence of work activities that produce products with increasing maturity of technical performance GA
  • 24. 24 24 Assess the maturity of a Capability at a point in time. Requirements that enable planned Capabilities. Exit Criteria for Work Packages That deliver the Requirements. Work Package Work Package Work Package Work Package Work Package Work package  Integrated Master Plan (IMP) is the strategy for the successful completion of the program, measured as “increasing maturity” of the Performance Measures (MOE, MOP, TPM, KPP).  Without a plan we cannot say what “done” looks like.  Integrated Master Schedule (IMS) defines the Work Packages and Planning Packages needed to implement the Plan, retire risks, manage resources, and sequence the detailed work activities.  Both the Plan and the Schedule are essential for success. The structure of a Performance-Based Program CRITERIA ACCOMPLISHMENTS EVENTS MOP MOE Subsystem System GA
  • 25. 25 25 ❺ ADJUST FOR IRREDUCIBLE RISKS IRREDUCIBLE UNCERTAINTY CREATES IRREDUCIBLE TECHNICAL AND PROGRAMMATIC RISK This Naturally Occurring Uncertainty Impacts Schedule And Cost In Irreducible Ways. It Can’t Be Bought Down. Irreducible Risks Can Only Be Mitigated With Margin. GA
  • 26. 26 26 Irreducible Risk Driven By Natural Variability Uncertainty Reducible Irreducible Natural Variability Ambiguity Known but un-mitigateable Probabilistic Events Probabilistic Impacts Periods of Exposure The probability of an event that we can do something about reducing this probability through explicit actions. Statistical range of natural randomness characterized by a historical data and therefore irreducible Epistemic Aleatory GA
  • 27. 27 27 Identifying Irreducible Risks Starts With Reference Class Forecasting GA
  • 28. 28 Applying Reference Classes to Work Activities to Construct Network of Random Processes  The independence or dependency of each task with others in the network, greatly influences the outcome of the total project duration.  Understanding these dependencies is critical to assessing the credibility of the IMS as well as the total completion time.  Any path could be critical depending on the probability distributions of the underlying task completion probability functions. We must know something about the probability distributions of the work efforts GA
  • 29. 29 29 Irreducible Risks Are Mitigated With Margin For Both Cost and Schedule  The contract delivery date is 8/31/08  The IMS without schedule margin has a confidence of 80% on or before 8/14/08  The deterministic date is 8/4/08  10 days of margin protect contractual schedule with 80% confidence 8/4/1908 Deterministic Date GA/RP 8/14/1908 80% On or Before 8/31/1908 Deterministic Date
  • 30. 30 30 Schedule Margin Burn Down is a Measure of Program Performance RP
  • 31. 31 31 But, Beware the Black Swan There is no Plan B for Black Swans – Must Replan 31 Natalie Portman, as Nina Sayers, The Swan Queen Black Swan – An event or occurrence that deviates beyond what is normally expected of a situation and that would be extremely difficult to predict. This term was popularized by Nassim Nicholas Taleb, a finance professor and former Wall Street trader.
  • 32. 32 32 ❻ ESTABLISH THE PMB EACH ELEMENT OF THE IMP AND IMS ARE NEEDED FOR A CREDIBLE PERFORMANCE MEASUREMENT BASELINE The Credible PMB Requires That Each Element Itself Be Credible With The Relationships Properly Established, Maintained, And Updated.
  • 33. 3333 Connecting the Dots in the PMB WBS KPPs TPMs EVM ETC EAC Irreducible uncertainty in reference classes Reducible uncertainty held in Risk Register Schedule Margin in DI-MGMT-81861 Cost Contingency † Risk retirement in PMB Management Reserve covers unmitigated risk MOE MOP Physical % Complete PE SA AC JROC KPP IMP IMS WP 33GA
  • 34. 34 34 EXECUTING THE PERFORMANCE MEASUREMENT BASELINE A well known example of integrating the elements of a credible PMB needed to successfully complete a program can be found in the Wright Brothers, 23 December 1907, Army Contract, No. 486 http://www.wright-brothers.org/History_Wing/Wright_Story/Showing_the_World/Back_in_Air/Signal_Corps_Spec.htm TC
  • 35. 35 35 Executing the Performance Measurement Baseline Take management action for any variances to assure on–time, on– budget and on–specification of all deliverables produced by the Work Packages. Maintain Performance Management Baseline (PMB) throughout project duration for Earned Value measures in Objective units of measure at the work performance level, meaningful to the decision makes Perform the Work described in the network of Work Packages held in the IMS, in the planned order, with the planned budget with the planned outcomes, meeting the planned performance measures. Accumulate and Report Performance Data – BCWP – and other increasing maturing assessment processes based on Physical Percent Complete described in the MOEs, MOPs, TPMs, and KPPs. Analyze Performance Data derived from the Earned Value metrics – informed by Technical Performance – and make any adjustments to the network of Work Packages to keep program GREEN. TC
  • 36. 36 Connecting Technical Performance (Weight) with EV Performance  Planned weight reduction of Wright Flyer connected with Earned Value performance by planned date is a TPM Earned Value Performance Weight Target in or out of bounds Informs Weight out of bounds BCWP should follow weight TC
  • 37. 37 37 Summary of Steps To Create The Credible PMB 6 Steps To Success ❶ Define WBS ❹ Build the IMS ❷ Build IMP ❺ Adjust for Irreducible Risks ❸ Identify Reducible Risk ❻ Establish the PMB 1.2.1 Integrate cost and schedule performance data with objective technical measures of performance DI-MGMT-81861† † Integrated Program Management Report (IPMR), DI-MGMT-81861, OUSD (AT&L) PARCA, 20 Jun 2012 And One Last Reminder TC
  • 38. 38 References  IMP/IMS Preparation and Use Guide, http://www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf  GAO Cost Estimating and Assessment Guide, http://www.gao.gov/new.items/d093sp.pdf  GAO Schedule Assessment Guide, http://www.gao.gov/assets/600/591240.pdf  Air Force Integrated Master Schedule Assessment Guide, http://afacpo.com/AQDocs/AF_IMS_%20Assessment_%20Process_%20V3.0.p df  The Integrated Project Management Handbook, Dayton Aerospace, Inc.  Scheduling Guide for Program Managers https://www.acquisition.gov/sevensteps/library/DAUschedulinguide.pdf  Integrated Master Plan Analysis, The PMAG Approach, Col. Mun H. Kwon, USAF, http://www.dau.mil/pubscats/ATL%20Docs/Jan-Feb/kwon_jan- feb10.pdf
  • 39. 39 References  AFMC Pamphlet 63-5, Integrated Master Plan and Schedule Guide, (11 Nov 2004), http://www.everyspec.com/USAF/USAF- AFMC/AFMC_PAM_63-5_4210/  MSFC-HDBK-3173, Project Management and System Engineering Handbook, https://standards.nasa.gov/documents/detail/3315842  Project Planning and Control Handbook, MSFC-HDBK-3684, https://standards.nasa.gov/documents/viewdoc/3315842/3315842  NASA Scheduling Management Handbook, http://www.nasa.gov/pdf/420297main_NASA-SP-2010-3403.pdf