SlideShare a Scribd company logo
http://www.iaeme.com/IJMET/index.asp 156 editor@iaeme.com
International Journal of Mechanical Engineering and Technology (IJMET)
Volume 6, Issue 8, Aug 2015, pp. 156-169, Article ID: IJMET_06_08_015
Available online at
http://www.iaeme.com/IJMET/issues.asp?JTypeIJMET&VType=6&IType=8
ISSN Print: 0976-6340 and ISSN Online: 0976-6359
© IAEME Publication
________________________________________________________________________
SCS &GIS ENABLED PROJECT
MANAGEMENT SYSTEM FOR
DEVELOPMENT AND IMPLEMENTATION
PHASE OF GAS DISTRIBUTION PROJECT
G. Dhamodaran
Department of Mechanical Engineering, School of Mechanical Engineering,
AMET University, Chennai
R. J. Golden Ranjith
Assistant Professor, Dept. of Mechanical Engineering,
Bharath University, Chennai, India
ABSTRACT
Background/Objectives: To investigate the usefulness of requirement of
‘Supervisory Control System for Gas Distribution Construction Project
Management’.
Methods/Statistical analysis: Human Video interface model preparation
and updating the live progress of the project to Update on the monitor
installed in Central Project Room thru Arc GIS and other Pipeline modules
interlinking with GPS Technology.
Results/Findings: Can be implemented at construction projects of Gas
Distribution Project where there will be complex Network of pipelines and
were geographically dispersed.
Conclusion/Application: “Supervisory Control System with GIS data for
development and implementation phase for Gas Distribution Construction
Project Management” can be implemented.
Key words:
Human Video Interface Monitor- Large size monitor where the entire
network of the Gas distribution circuit can be seen and required selection can
be made based on the requirement.
GIS -Geographical Information System – Integrated Tool/Application
having Geographical information’s which maps all data related to the pipeline
network.
SCS & GIS Enabled Project Management System for Development and Implementation
Phase of Gas Distribution Project
http://www.iaeme.com/IJMET/index.asp 157 editor@iaeme.com
Central Project Room- The Project Management room installed with the
Monitor from where Progress is analysed and further front generation and
planning activities can be planned
Pipelines modules- The pipeline drawing software’s which produce the
alignment sheets
Pipeline alignment sheets- the drawing to the pipeline will all data like
length, corridor, co-ordinates, fittings, cable details, turning points etc.
GPS Technology- The Radio frequency transfer technology thru which the
progress can be updated.
SCS- Supervisory Control System- System with HMI enables to manage the
Project having the facility of real-time updation of the data thru GPS
technology.
Cite this Article: Dhamodaran, G. and Golden Ranjith, R. J. SCS & GIS
enabled Project Management System for Development and Implementation
phase of Gas Distribution Project. International Journal of Mechanical
Engineering and Technology, 6(8), 2015, pp. 151-164.
http://www.iaeme.com/IJMET/issues.asp?JTypeIJMET&VType=6&IType=8
1. INTRODUCTION
The Pipeline network of the Gas distribution is a more complex network and
construction of these kind of networks is a big task as many activities like Survey,
Land acquisition, Right of way acquiring, Right of Use acquiring, excavation, laying,
testing, padding, cables installation, back filling, restoration etc..
There may be Trunk lines, lateral lines, Branch lines, final flow lines which will
be many numbers according to the distribution network, size of the pipelines will be
varying with respect to the consumers located in one particular line or area. Also there
will be many nodes, turning points to avoid any other facilities, with this kind of
complex networks; Project management becomes cumbersome exercise to have
overall control over the Entire Project.
To overcome that Computer enabled methodology which will be having there
preloaded data like pipeline routing, and other data. will have to be graphically
represented and daily progress in each field are to be updated. Updation is easy in
present days as many internet or GPRS enabled messengers are available in the
market like Whats-app, Telegram etc.. Constructing these complex pipeline facilities
for Gas Distribution Network are challenging tasks and generally this activity drives
the project.
2. PRESENT METHOD AND ITS DIFFICULTIES
2.1. Present method being followedin the industry
In general, Every major portions either in terms of Trunk lines or in terms of
area/Villages are being segregated and contracted with some agencies and based on
the progress reports and rare occasion meetings the progress is measured and there is
no solid method available for front generation other than individuals’ capabilities.
Also conducting regular meeting with all the contractor by Project Manager is a
simple task and the person representing the individual area. Village/Trunk line also
may not have th full knowledge about the happenings and further plans. To overcome
G. Dhamodaran and R. J. Golden Ranjith
http://www.iaeme.com/IJMET/index.asp 158 editor@iaeme.com
this one Project Management Cell with Supervisory Control System may be required
and the updation s to be made simple.
2.2. Difficulties in present methods
As many of the areas were spread over many of the villages and many of the districts,
only best way is to have the regular meetings with each of the one on regular intervals
at any office accessible by every one of the project. Here in this system everyone has
to spend the time may be whole day oe even more than a day. Because to this, the
meeting once in a week cannot be arranged and co-ordination becomes cumbersome
and hence delays the project
3. PROPOSED METHODOLOGY
In the Proposal submitter here, the Central Control Room has to be located with
somewhere at the central location of the Gas distribution area. There in the Central
Control Room, One big size with all required storages, servers, UPS, Work Station,
Preloaded software, Pre-loaded pipeline route/geographical data. HMI Screens etc.
A point to multipoint low band width radio connection will serve the purpose,
where the entire distribution network will get connected to the CCR. Where ever
required some FOC network can also be implemented if required and volume of data
transmission is high in nature. From the work location real-time updation by
respective field engineer will update the master data thru the radio network or GPRS
enabled smart mobile phone where an application will have to be developed to
connect to Servers and HMI monitors. All networks and servers to be made accessible
through LAN/ WAN / WEB / GPRS Network.
3.1. Database creation and Server Management
The following steps to be followed to create the master database. The Pipeline Data
management system based on Engineering and GIS to be developed by experienced
specialist vendor. The entire field facilities and pipeline network to be mapped using
Satellite images procured for the Field development area.
A master database of entire pipeline information will be created using GIS tools.
The master database to include detailed facility layouts, pipeline alignment drawings,
facility location database, support facility information, ROU information, linked
technical specifications, sparing schedule, maintenance schedule, and pigging
schedule.
The Following minimum features will be provided in the Engineering Cum GIS
based pipeline database management system:
 Drawing release status
 ROU application status
 ROW application status
 Revenue Survey details
 Other lands acquisition status
 Land over/ROU Compensation payment Status
 Soil status
 Excavation Status
 Pipeline/Cable /other material arrival Status
 Joints Welding Progress
SCS & GIS Enabled Project Management System for Development and Implementation
Phase of Gas Distribution Project
http://www.iaeme.com/IJMET/index.asp 159 editor@iaeme.com
 Lowering Status
 Testing status and Reports
 Backfilling Status
 Pigging schedules
 Customised report generation.
 Accessibility to all relevant information / documents / drawings etc.
The proposed method is having majorly two parts called 1. Geographical
Information System (GIS) and 2. Supervisory Control System (SCS)
3.1.1. Geographical Information System
This is Software supplied by various companies around the world which helps in
viewing and managing the integrated pipeline network. This Spatially enabled GIS
Model manages the all pipeline attributes in centre line data with ensuring accuracy in
data.
GIS system meets all the general and minimum requirement such as Database set
up, survey data uploading and reference, data exchange between various stakeholders,
Alignment sheet Generations, Crossing drawings, Reference drawings, MTO
Preparation etc. As this stores High Resolution Satellite imagery, data accuracy will
be attained.
The following Steps to be followed
 Taking the High Resolution Satellite Imageries and updating in server
 Verification of the Survey data
o Verification with respect to Spheroid/Ellipsoid Parameters
o Verification with respect to topological and topographical parameters
o Verification by superimposing Survey data with HRSIs
 Uploading and updating the database server
 Carrying out detailed Engineering works
With this the following minimum engineering deliverables can be extracted
 Integrated Alignment Sheets
 Crossing Drawings
 Pipeline, Electrical and FOC standard drawings
 Integrated MTOs for various disciplines
The following are the some of the important survey data which may be required to
update the database
 Land base information
 Feed Data
 Detailed Route Survey information
 Topographical Survey information
 Ground Profile data
 Population Density Index
G. Dhamodaran and R. J. Golden Ranjith
http://www.iaeme.com/IJMET/index.asp 160 editor@iaeme.com
Flowchart for Database Setup and utilizing for Detailed Engineering
Figure 1 Flow Chart for GIS Data base setup, updation and Detailed Engineering
•DataBase Setup
Basic
Data
•HRSI
•AdminPrivilages
•LandBase Information
•FeedData
Survey
•Route Survey Infomation
•Topographicla Survey Information
•Ground Profile Data
•Population Density Index
Update
Data
Process
Integrated Alignment Sheets
Standard / Reference Drawings
MTOs
SCS & GIS Enabled Project Management System for Development and Implementation
Phase of Gas Distribution Project
http://www.iaeme.com/IJMET/index.asp 161 editor@iaeme.com
Some of the major Advantages of using Geographical Information System
 Efforts required to manage records can be minimised
 Efforts require to communicate with increased noumbers of stake holders can be
minimised
 Multiple data editors at one time can be increased with respect to size of the Project
 Ease of Producing the Reports
 Ease of Producing Engineering Deliverables
 Visualisation by viewing the status in Web browser
 Integrated link between Construction Contractor, Owner, Project Manager, Financing
institute, Surveyors, engineers, Inspectors, Detail engineering Contractor, ROU
Agents, Environmental Team, CSR Team etc.
 Ease maintenance of E-log book
 Viewing and Referring Survey shots whenever required
 Permissions Status
 Ease MIS Reporting
 Crossing and legal permission Status
 Accuracy in Data
 Integrity in data
 Efficient Project Management
 Developing various Databases
 Production of various Auto Cad Drawings
 Linking Graphics to tables an d databases
 Editing As built drawings
 Tracing of Joints and status reporting
 Uniqueness in data management
 Aligning all project managers in one approach
 Ease interface with SQL Servers
 Ease in exporting graphics in required format
 Generations of notification and alerts on daily updates and pending works
3.1.2. Supervisory Control System
The Central Control Room will be manned 24/7 and monitors the field parameters and
equipment status & alarms. The Control Room Operators will be responsible for
alerting the Filed Construction team for any Follow up actions and control actions to
be taken at any of the field sites visa viz. Trunk lines, Branch lines, Lateral Lines,
Field Lines or any other Permanent facilities oft the Project
This control Room will be Equipped with the large Video cum HMI Monitor
where the entire Pipeline network will be visually seen and the required portions can
be enlarged and seen. With the help of any suitable application thru the GPS
frequency Signal site construction progress will be updated in the master data which
will be of real-time updation.
Network system required to transmit the data could be either LAN/WIFI/Wireless
technology or any other thing. The follow up actions can be automatically or
manually sent to the required portion or the project manager.
G. Dhamodaran and R. J. Golden Ranjith
http://www.iaeme.com/IJMET/index.asp 162 editor@iaeme.com
Remote Terminal Units(RTU) can be installed and important nodal points thru
which the data can be communicated to the th central control Room. These RTUs will
be collecting data from the Various facilities and pipeline segments and transfer them
to the Central Control Room.
The instrumentation & automation data from the Well will require low bandwidth;
data polling will be on real-time basis. A point to multi point microwave radio
networks will meet the requirement. There may be other low band width requirements
for IT voice network and for Security Automation. These can also be connected
through the same Radio network
3.2. Various WBS and Activities to get covered
With the implementation of this SCS the following WBS may be getting covered
along with applicable Activities
Engineering-
Detail Engineering Status,
MTOs,
Alignment Sheet Revision Status,
Schedule of releasing the other documents related to the particular section or part of
the pipeline or facilities.
Procurement-
MR Status,
RFQ Status,
Material delivery status,
Material shifting status to erection location
Legal-
Permission Status,
Land Acquisition Status,
Crossing Details,
ROU Application Status,
ROW Status,
Compensation Status,
Local agitation details
Construction-
Excavation,
Grading
Bedding,
Stringing,
Joints welding,
Lowering,
Testing,
Back filling,
Restoration
SCS & GIS Enabled Project Management System for Development and Implementation
Phase of Gas Distribution Project
http://www.iaeme.com/IJMET/index.asp 163 editor@iaeme.com
Other these, there are many other options can also be inducted in the Engineering-
Cum-GIS based construction data base.
3.3. Options to be made available in menu
With the implementation of this SCS the following WBS may be getting covered
along with applicable Activities.
The following table shows the list of options that may be required as a minimum
to continue the construction
3.3.1. Engineering Phase
Table 1 Various Menu options required during Engineering Phase
Phase Location Entity Activity Progress
Time
line
Document
Quantity
Status
Level 1 Level 2 Level 3 Level 4 Level 5
Sub
Level-1
Sub level-
2
Sub
level-3
Engineeri
ng
Trunk
Line/
Lateral
line/
Branch
line/ Flow
Line/
From
Chainage/
To
Chainage
Alignment
sheet
Preparat
ion
Started
Target to
Start
View
Procurem
ent
Village/
Survey
Number/
Land
Owner
MTO
Draft
Release
In
progress
Target to
Finish
Download
Legal
other
Engineerin
g
Deliverable
approval
Complete
d
Target to
Release
Retrive
Constructi
on
Release Approved Extract
Final
Release
Sent for
Approval
Upload
Revised Comment
Released
Menu such as status of the all deliverables, their time line data can be fed. Also
the quantity status also can be included either in terms of numbers or in terms of
percentages. In order to track the engineering deliverables the options like comment,
upload etc can now be included.
G. Dhamodaran and R. J. Golden Ranjith
http://www.iaeme.com/IJMET/index.asp 164 editor@iaeme.com
Concern area manager/project engineer can upload the status immediately either
thru eh Android enabled application in smartphone or any other means of system
inclusion.
3.3.2. Procurement Phase
Table 2 Various Menu options required during Procurement Phase
Phase Location Entity Activity Progress
Time
line
Document
Quantity
Stat
us
Level 1 Level 2 Level 3 Level 4 Level 5
Sub
Level-
1
Sub level-
2
Sub
level
-3
Engineering
Trunk
Line/
Lateral
line/
Branch
line/
Flow
Line/
From
Chainage/
To
Chainage
MR Preparation Started
Target
to Start
View
Procurement
Village/
Survey
Number/
Land
Owner
RFQ
Draft
Release
In
progress
Target
to
Finish
Download
Legal Delivery approval Completed
Target
to
Release
Retrieve
Construction Release Approved Extract
Final
Release
Sent for
Approval
Upload
Published Revised Comment
Bids
Received
Released Check
Evaluated
Ordered
Received
SCS & GIS Enabled Project Management System for Development and Implementation
Phase of Gas Distribution Project
http://www.iaeme.com/IJMET/index.asp 165 editor@iaeme.com
Procurement documents like Material Requisition, RFQ, Material Delivery can be
tracked and status can be retrieved by the relevance users. The Procurement team to
update the status as and when happen in real time basis.
The Approval cycle of time and Technical Bid evaluation details and Technical
Recommendation details can also be included if required.
3.3.3. Legal Phase
Table 3 Various Menu options required during Legal Phase
Phase Location Entity Activity Progress
Time
line
Document
Quantit
y Status
Level 1 Level 2 Level 3 Level 4 Level 5
Sub
Level-
1
Sub level-
2
Sub
level-3
Engineering
Trunk Line/
Lateral line/
Branch line/
Flow Line/
From
Chainage/ To
Chainage
Permission
Preparati
on
Started
Target
to
Start
View
Procurement
Village/
Survey
Number/
Land Owner
Crossing
Draft
Release
In
progress
Target
to
Finish
Download
Legal LAQ approval
Complete
d
Target
to
Releas
e
Retrieve
Construction ROU Release Approved Extract
ROW
Final
Release
Sent for
Approval
Upload
Agitation
Submitte
d
Revised Comment
Tracked Released Check
Corrected Paid
Received
DD Sent
Fee
Payment
Various legal issues like permissions from various boards and departments of
Government bodies can be tracked in this SCS System. Right of Use and Right of
Way related progress etc can be traced in this. Also the Team who is co ordination
with Legal departments to update the relevant documents on regular intervels.
G. Dhamodaran and R. J. Golden Ranjith
http://www.iaeme.com/IJMET/index.asp 166 editor@iaeme.com
Payments status to various applications can also be tracked with this and the local
agitations and related FIRS can also be tracked and accordingly further front can be
generated.
3.3.4. Construction Phase
Table 4 Various Menu options required during Construction Phase
Phase Location Entity Activity Progress
Time
line
Document
Quantity
Status
Level 1 Level 2 Level 3 Level 4 Level 5
Sub
Level-
1
Sub level-
2
Sub
level-3
Engineering
Trunk Line/
Lateral line/
Branch line/
Flow Line/
From
Chainage/ To
Chainage
Trench Grading Started
Target
to Start
View
Procurement
Village/
Survey
Number/
Land Owner
Pipeline Excavation
In
progress
Target
to
Finish
Download
Legal Cable Bedding Completed
Target
to
Release
Retrieve
Construction Stringing Extract
Welding Upload
Lowering Comment
Testing Check
Back filling
Restorations
During Construction phases, various construction activities status can be traced
centrally like Excavation, bedding, laying, welding, lowering, testing, back filling etc.
Further front can be generated from the Central Control Room.
4. DATA FEEDING, UPDATING, PROCESSING AND
MANAGEMENT.
Central Construction Control Centre should be manned for all 24x7 days. There will
be a monitor where the entire Gas distribution network will be visible. Wherever
SCS & GIS Enabled Project Management System for Development and Implementation
Phase of Gas Distribution Project
http://www.iaeme.com/IJMET/index.asp 167 editor@iaeme.com
required, the particular portions can be zoomed and edited. GIS images of the Gas
distribution network area have to be preloaded into the system. Individual area
managers/construction heads or the Field engineers will be provided wither with
laptop or Smartphone with application. Accesses have to be provided to the respective
construction man to update the current happenings.
With the real-time updation, the Person monitoring the data at CCCC can easily
generate the front and send to the succeeding persons or to the same person if he is
alone to carry out the succeeding activities.
Example: Operator takes out the locations where all testing completed and
backfilling is balance. His output will be in terms of Line number/Village name/Trunk
line/Feed line / Chainage details etc. This list Operator will be sending to the Civil co-
ordinator to initiate the backfilling works.
Figure 2 Schematic drawing of concept of ‘Central Construction Control Centre’
Central Construction Control Centre
G. Dhamodaran and R. J. Golden Ranjith
http://www.iaeme.com/IJMET/index.asp 168 editor@iaeme.com
5. RESULTS
This kind id system is used in operation phase for many projects as “Supervisory
Control System and Data Acquisition”. Our Aim is to extend that kind of Central
project Control Concepts which will increase the efficiency of the Project
management.
6. DISCUSSION
6.1. Advantages of using this system
This system has more advantages like,
a. Efficient Project management
b. Better revision management in drawings and documents
c. Complete reliability on the work progress and front
d. Accurate reports
e. Provides clear guidelines for planning, and forecasting
f. Provides access to multiple users so that many people can work in same time
g. Tracing facility of materials, reports, documents history etc.
h. Helps in generating many data bases.
i. Controls Duplication works
j. Continues expedition from the Site team
k. Single Point Co-ordination system which minimise the error.
l. Completely provides real time tracking of the progress
m. Generates Front for almost all disciplines included in the scope
n. Minimal investment and no major operational cost
o. Less Manpower requirement
7. CONCLUSION
As this reduces lot of man-hour wastages and time this method can be encouraged for
many of the Pipeline projects like Gas Distribution Projects.
ACKNOWLEDGEMENTS
Informally many other forms the same concept is being used partially in many of the
Gas distribution Projects. With little improvement and value addition will yield good
results in terms of the efficient Project Management.
REFERENCES
[1] Al-Momani, A. H. Construction delay: A quantitative analysis. International
Journal of ProjectManagement, 18(1), 2000.
[2] Ammar, M. A. and Mohieldin, Y. A. Resource constrained project scheduling
using simulation. Construction Management and Economics, 2002.
[3] Assaf, S. A. and Al-Hejji, S. Causes of delay in large construction projects.
International Journal of Project Management, 2006.
[4] Chan, A. P. C., Scott, D. and Chan, A. P. L. Factors affecting the success of a
construction project. Journal of Construction Engineering and Management,
2004.
[5] Graham, G. E., Maxwell, D. A. and Vallone, A. How to Optimize Gas Pipeline
Networks. Pipeline Industry, June, 1971. 41–43.
[6] Martch, H. B. and N. J. McCall. Optimization of the Design and Operation of
Natural Gas Pipeline Systems. Paper No. SPE 4006, Society of Petroleum
Engineers of AIME, 1972.
SCS & GIS Enabled Project Management System for Development and Implementation
Phase of Gas Distribution Project
http://www.iaeme.com/IJMET/index.asp 169 editor@iaeme.com
[7] Flanigan, O. Constrained Derivatives in Natural Gas Pipeline System
Optimization. Journal of Petroleum Technology, May, 1972, pp. 549.
[8] Mah, R. S. H. and Schacham, M. Pipeline Network Design and Synthesis.
Advances in Chemical Engineering, 10, 1978.
[9] Cheesman, A. P. How to Optimize Gas Pipeline Design by Computer. Oil and
Gas Journal, 69(51), December 20, 1971, pp. 64.
[10] Cheesman, A. P. Understanding Origin of Pressure is a Key to Better Well
Planning. Oil and Gas Journal, 69(46), November 15, 1971, pp. 146.
[11] Edgar, T. F., Himmelblau, D. M. and Bickel, T. C. Optimal Design of Gas
Transmission Network. Society of Petroleum Engineering Journal, 30, 1978, pp.
96.
[12] Hasan, H. S. and Dr. Ramesh Babu, P. SCS Analysis and Control of Mobile
Robot for Pipe Line Inspection. International Journal of Mechanical Engineering
and Technology, 4(5), 2013, pp. 01–09.
[13] Olorunniwo, F. O. A Methodology for Optimal Design and Capacity Expansion
planning of Natural Gas Transmission Networks. Ph.D Dissertation, The
University of Texas Austin, May, 1981
[14] Wong, P. J. and Larson, R. E. Optimization of natural gas pipeline systems via
dynamic programming. IEEE Trans. Auto. Control, AC-13(5), October 1968, pp.
475–481.
[15] Harris, R. B. and Ioannou, P. G. Scheduling projects with repeating activities.
Journal of Construction Engineering and Management, 1998.

More Related Content

What's hot

Csi 2130 machinery health analyzer
Csi 2130 machinery health analyzerCsi 2130 machinery health analyzer
Csi 2130 machinery health analyzer
Ahmed Gamal
 
Case Study - Monitoring and Evaluating the working of Telenor and ZTE
Case Study - Monitoring and Evaluating the working of Telenor and ZTECase Study - Monitoring and Evaluating the working of Telenor and ZTE
Case Study - Monitoring and Evaluating the working of Telenor and ZTE
Asim Ranjha
 
IRJET- Strategical Management of Image Processing based Real Time Traffic Con...
IRJET- Strategical Management of Image Processing based Real Time Traffic Con...IRJET- Strategical Management of Image Processing based Real Time Traffic Con...
IRJET- Strategical Management of Image Processing based Real Time Traffic Con...
IRJET Journal
 
KA6423 P57600 Assignment 4
KA6423 P57600 Assignment 4KA6423 P57600 Assignment 4
KA6423 P57600 Assignment 4armada7000
 
Design of intelligent traffic light controller using gsm & embedded system
Design of intelligent traffic light controller using gsm & embedded systemDesign of intelligent traffic light controller using gsm & embedded system
Design of intelligent traffic light controller using gsm & embedded system
Yakkali Kiran
 
A highway variable speed limit control system based on internet of things
A highway variable speed limit control system based on internet of thingsA highway variable speed limit control system based on internet of things
A highway variable speed limit control system based on internet of things
ijmnct
 

What's hot (6)

Csi 2130 machinery health analyzer
Csi 2130 machinery health analyzerCsi 2130 machinery health analyzer
Csi 2130 machinery health analyzer
 
Case Study - Monitoring and Evaluating the working of Telenor and ZTE
Case Study - Monitoring and Evaluating the working of Telenor and ZTECase Study - Monitoring and Evaluating the working of Telenor and ZTE
Case Study - Monitoring and Evaluating the working of Telenor and ZTE
 
IRJET- Strategical Management of Image Processing based Real Time Traffic Con...
IRJET- Strategical Management of Image Processing based Real Time Traffic Con...IRJET- Strategical Management of Image Processing based Real Time Traffic Con...
IRJET- Strategical Management of Image Processing based Real Time Traffic Con...
 
KA6423 P57600 Assignment 4
KA6423 P57600 Assignment 4KA6423 P57600 Assignment 4
KA6423 P57600 Assignment 4
 
Design of intelligent traffic light controller using gsm & embedded system
Design of intelligent traffic light controller using gsm & embedded systemDesign of intelligent traffic light controller using gsm & embedded system
Design of intelligent traffic light controller using gsm & embedded system
 
A highway variable speed limit control system based on internet of things
A highway variable speed limit control system based on internet of thingsA highway variable speed limit control system based on internet of things
A highway variable speed limit control system based on internet of things
 

Viewers also liked

INTTEC Diploma Fashion Design
INTTEC Diploma Fashion DesignINTTEC Diploma Fashion Design
INTTEC Diploma Fashion DesignRoxann Ristow
 
Post-Event-Report-Delegate
Post-Event-Report-DelegatePost-Event-Report-Delegate
Post-Event-Report-DelegateAlan Royal
 
Chris Bradford New Resume_v3_9-26-16
Chris Bradford New Resume_v3_9-26-16Chris Bradford New Resume_v3_9-26-16
Chris Bradford New Resume_v3_9-26-16Chris Bradford
 

Viewers also liked (7)

vishal document
vishal documentvishal document
vishal document
 
INTTEC Diploma Fashion Design
INTTEC Diploma Fashion DesignINTTEC Diploma Fashion Design
INTTEC Diploma Fashion Design
 
Post-Event-Report-Delegate
Post-Event-Report-DelegatePost-Event-Report-Delegate
Post-Event-Report-Delegate
 
evans c.v
evans c.vevans c.v
evans c.v
 
all games flier
all games flierall games flier
all games flier
 
RiseFox
RiseFoxRiseFox
RiseFox
 
Chris Bradford New Resume_v3_9-26-16
Chris Bradford New Resume_v3_9-26-16Chris Bradford New Resume_v3_9-26-16
Chris Bradford New Resume_v3_9-26-16
 

Similar to Ijmet 06 08_015

Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...
Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...
Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...
IRJET Journal
 
BUS TRACKING SYSTEM
BUS TRACKING SYSTEMBUS TRACKING SYSTEM
BUS TRACKING SYSTEM
IRJET Journal
 
Capgemini ses - smart grid operational services - gis pov (gr)
Capgemini   ses - smart grid operational services - gis pov (gr)Capgemini   ses - smart grid operational services - gis pov (gr)
Capgemini ses - smart grid operational services - gis pov (gr)
Gord Reynolds
 
Smart vehicle tracking using GPS
Smart vehicle tracking using GPSSmart vehicle tracking using GPS
Smart vehicle tracking using GPS
IRJET Journal
 
IRJET- IoT based Vehicle Tracking using GPS
IRJET-  	  IoT based Vehicle Tracking using GPSIRJET-  	  IoT based Vehicle Tracking using GPS
IRJET- IoT based Vehicle Tracking using GPS
IRJET Journal
 
IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...
IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...
IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...
IRJET Journal
 
A Survey on Smart DRIP Irrigation System
A Survey on Smart DRIP Irrigation SystemA Survey on Smart DRIP Irrigation System
A Survey on Smart DRIP Irrigation System
IRJET Journal
 
Vehicle tracking Using GPS,GSM & ARM7
Vehicle tracking Using GPS,GSM & ARM7Vehicle tracking Using GPS,GSM & ARM7
Vehicle tracking Using GPS,GSM & ARM7
Ashutosh Upadhayay
 
111ei0254ppt8thsem
111ei0254ppt8thsem111ei0254ppt8thsem
111ei0254ppt8thsem
Himansu Pradhan
 
SMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOT
SMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOTSMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOT
SMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOT
IRJET Journal
 
Serving GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution AnalysisServing GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution Analysis
pdituri
 
IRJET- R-Pi based Real-Time Weather Monitoring System
IRJET-  	  R-Pi based Real-Time Weather Monitoring SystemIRJET-  	  R-Pi based Real-Time Weather Monitoring System
IRJET- R-Pi based Real-Time Weather Monitoring System
IRJET Journal
 
IRJET- Intelligent Traffic Management System
IRJET- Intelligent Traffic Management SystemIRJET- Intelligent Traffic Management System
IRJET- Intelligent Traffic Management System
IRJET Journal
 
Review on IoT Based Bus Scheduling System using Wireless Sensor Network
Review on IoT Based Bus Scheduling System using Wireless Sensor NetworkReview on IoT Based Bus Scheduling System using Wireless Sensor Network
Review on IoT Based Bus Scheduling System using Wireless Sensor Network
IRJET Journal
 
Discernment Pothole with Autonomous Metropolitan Vehicle
	 Discernment Pothole with Autonomous Metropolitan  Vehicle	 Discernment Pothole with Autonomous Metropolitan  Vehicle
Discernment Pothole with Autonomous Metropolitan Vehicle
IRJET Journal
 
Embedded system for traffic light control
Embedded system for traffic light controlEmbedded system for traffic light control
Embedded system for traffic light control
Madhu Prasad
 
IRJET - A Design Thinking based Smart Parking System for Vehicle Parking ...
IRJET -  	  A Design Thinking based Smart Parking System for Vehicle Parking ...IRJET -  	  A Design Thinking based Smart Parking System for Vehicle Parking ...
IRJET - A Design Thinking based Smart Parking System for Vehicle Parking ...
IRJET Journal
 
Smart Car
Smart CarSmart Car
Smart Car
IRJET Journal
 
CAN BASE VOLVO AUTOMATION
CAN BASE VOLVO AUTOMATIONCAN BASE VOLVO AUTOMATION
CAN BASE VOLVO AUTOMATION
IAEME Publication
 

Similar to Ijmet 06 08_015 (20)

Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...
Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...
Study of Estimation of Road Roughness Condition and Ghat Complexity Analysis ...
 
BUS TRACKING SYSTEM
BUS TRACKING SYSTEMBUS TRACKING SYSTEM
BUS TRACKING SYSTEM
 
Capgemini ses - smart grid operational services - gis pov (gr)
Capgemini   ses - smart grid operational services - gis pov (gr)Capgemini   ses - smart grid operational services - gis pov (gr)
Capgemini ses - smart grid operational services - gis pov (gr)
 
Smart vehicle tracking using GPS
Smart vehicle tracking using GPSSmart vehicle tracking using GPS
Smart vehicle tracking using GPS
 
IRJET- IoT based Vehicle Tracking using GPS
IRJET-  	  IoT based Vehicle Tracking using GPSIRJET-  	  IoT based Vehicle Tracking using GPS
IRJET- IoT based Vehicle Tracking using GPS
 
IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...
IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...
IRJET - A Real-Time Pothole Detection Approach for a Safety Transportation Sy...
 
A Survey on Smart DRIP Irrigation System
A Survey on Smart DRIP Irrigation SystemA Survey on Smart DRIP Irrigation System
A Survey on Smart DRIP Irrigation System
 
29
2929
29
 
Vehicle tracking Using GPS,GSM & ARM7
Vehicle tracking Using GPS,GSM & ARM7Vehicle tracking Using GPS,GSM & ARM7
Vehicle tracking Using GPS,GSM & ARM7
 
111ei0254ppt8thsem
111ei0254ppt8thsem111ei0254ppt8thsem
111ei0254ppt8thsem
 
SMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOT
SMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOTSMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOT
SMART SOLUTION FOR RESOLVING HEAVY TRAFFIC USING IOT
 
Serving GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution AnalysisServing GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution Analysis
 
IRJET- R-Pi based Real-Time Weather Monitoring System
IRJET-  	  R-Pi based Real-Time Weather Monitoring SystemIRJET-  	  R-Pi based Real-Time Weather Monitoring System
IRJET- R-Pi based Real-Time Weather Monitoring System
 
IRJET- Intelligent Traffic Management System
IRJET- Intelligent Traffic Management SystemIRJET- Intelligent Traffic Management System
IRJET- Intelligent Traffic Management System
 
Review on IoT Based Bus Scheduling System using Wireless Sensor Network
Review on IoT Based Bus Scheduling System using Wireless Sensor NetworkReview on IoT Based Bus Scheduling System using Wireless Sensor Network
Review on IoT Based Bus Scheduling System using Wireless Sensor Network
 
Discernment Pothole with Autonomous Metropolitan Vehicle
	 Discernment Pothole with Autonomous Metropolitan  Vehicle	 Discernment Pothole with Autonomous Metropolitan  Vehicle
Discernment Pothole with Autonomous Metropolitan Vehicle
 
Embedded system for traffic light control
Embedded system for traffic light controlEmbedded system for traffic light control
Embedded system for traffic light control
 
IRJET - A Design Thinking based Smart Parking System for Vehicle Parking ...
IRJET -  	  A Design Thinking based Smart Parking System for Vehicle Parking ...IRJET -  	  A Design Thinking based Smart Parking System for Vehicle Parking ...
IRJET - A Design Thinking based Smart Parking System for Vehicle Parking ...
 
Smart Car
Smart CarSmart Car
Smart Car
 
CAN BASE VOLVO AUTOMATION
CAN BASE VOLVO AUTOMATIONCAN BASE VOLVO AUTOMATION
CAN BASE VOLVO AUTOMATION
 

More from IAEME Publication

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME Publication
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
IAEME Publication
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
IAEME Publication
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
IAEME Publication
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
IAEME Publication
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
IAEME Publication
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
IAEME Publication
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IAEME Publication
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
IAEME Publication
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
IAEME Publication
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
IAEME Publication
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
IAEME Publication
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
IAEME Publication
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
IAEME Publication
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
IAEME Publication
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
IAEME Publication
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
IAEME Publication
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
IAEME Publication
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
IAEME Publication
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
IAEME Publication
 

More from IAEME Publication (20)

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
 

Recently uploaded

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 

Recently uploaded (20)

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 

Ijmet 06 08_015

  • 1. http://www.iaeme.com/IJMET/index.asp 156 editor@iaeme.com International Journal of Mechanical Engineering and Technology (IJMET) Volume 6, Issue 8, Aug 2015, pp. 156-169, Article ID: IJMET_06_08_015 Available online at http://www.iaeme.com/IJMET/issues.asp?JTypeIJMET&VType=6&IType=8 ISSN Print: 0976-6340 and ISSN Online: 0976-6359 © IAEME Publication ________________________________________________________________________ SCS &GIS ENABLED PROJECT MANAGEMENT SYSTEM FOR DEVELOPMENT AND IMPLEMENTATION PHASE OF GAS DISTRIBUTION PROJECT G. Dhamodaran Department of Mechanical Engineering, School of Mechanical Engineering, AMET University, Chennai R. J. Golden Ranjith Assistant Professor, Dept. of Mechanical Engineering, Bharath University, Chennai, India ABSTRACT Background/Objectives: To investigate the usefulness of requirement of ‘Supervisory Control System for Gas Distribution Construction Project Management’. Methods/Statistical analysis: Human Video interface model preparation and updating the live progress of the project to Update on the monitor installed in Central Project Room thru Arc GIS and other Pipeline modules interlinking with GPS Technology. Results/Findings: Can be implemented at construction projects of Gas Distribution Project where there will be complex Network of pipelines and were geographically dispersed. Conclusion/Application: “Supervisory Control System with GIS data for development and implementation phase for Gas Distribution Construction Project Management” can be implemented. Key words: Human Video Interface Monitor- Large size monitor where the entire network of the Gas distribution circuit can be seen and required selection can be made based on the requirement. GIS -Geographical Information System – Integrated Tool/Application having Geographical information’s which maps all data related to the pipeline network.
  • 2. SCS & GIS Enabled Project Management System for Development and Implementation Phase of Gas Distribution Project http://www.iaeme.com/IJMET/index.asp 157 editor@iaeme.com Central Project Room- The Project Management room installed with the Monitor from where Progress is analysed and further front generation and planning activities can be planned Pipelines modules- The pipeline drawing software’s which produce the alignment sheets Pipeline alignment sheets- the drawing to the pipeline will all data like length, corridor, co-ordinates, fittings, cable details, turning points etc. GPS Technology- The Radio frequency transfer technology thru which the progress can be updated. SCS- Supervisory Control System- System with HMI enables to manage the Project having the facility of real-time updation of the data thru GPS technology. Cite this Article: Dhamodaran, G. and Golden Ranjith, R. J. SCS & GIS enabled Project Management System for Development and Implementation phase of Gas Distribution Project. International Journal of Mechanical Engineering and Technology, 6(8), 2015, pp. 151-164. http://www.iaeme.com/IJMET/issues.asp?JTypeIJMET&VType=6&IType=8 1. INTRODUCTION The Pipeline network of the Gas distribution is a more complex network and construction of these kind of networks is a big task as many activities like Survey, Land acquisition, Right of way acquiring, Right of Use acquiring, excavation, laying, testing, padding, cables installation, back filling, restoration etc.. There may be Trunk lines, lateral lines, Branch lines, final flow lines which will be many numbers according to the distribution network, size of the pipelines will be varying with respect to the consumers located in one particular line or area. Also there will be many nodes, turning points to avoid any other facilities, with this kind of complex networks; Project management becomes cumbersome exercise to have overall control over the Entire Project. To overcome that Computer enabled methodology which will be having there preloaded data like pipeline routing, and other data. will have to be graphically represented and daily progress in each field are to be updated. Updation is easy in present days as many internet or GPRS enabled messengers are available in the market like Whats-app, Telegram etc.. Constructing these complex pipeline facilities for Gas Distribution Network are challenging tasks and generally this activity drives the project. 2. PRESENT METHOD AND ITS DIFFICULTIES 2.1. Present method being followedin the industry In general, Every major portions either in terms of Trunk lines or in terms of area/Villages are being segregated and contracted with some agencies and based on the progress reports and rare occasion meetings the progress is measured and there is no solid method available for front generation other than individuals’ capabilities. Also conducting regular meeting with all the contractor by Project Manager is a simple task and the person representing the individual area. Village/Trunk line also may not have th full knowledge about the happenings and further plans. To overcome
  • 3. G. Dhamodaran and R. J. Golden Ranjith http://www.iaeme.com/IJMET/index.asp 158 editor@iaeme.com this one Project Management Cell with Supervisory Control System may be required and the updation s to be made simple. 2.2. Difficulties in present methods As many of the areas were spread over many of the villages and many of the districts, only best way is to have the regular meetings with each of the one on regular intervals at any office accessible by every one of the project. Here in this system everyone has to spend the time may be whole day oe even more than a day. Because to this, the meeting once in a week cannot be arranged and co-ordination becomes cumbersome and hence delays the project 3. PROPOSED METHODOLOGY In the Proposal submitter here, the Central Control Room has to be located with somewhere at the central location of the Gas distribution area. There in the Central Control Room, One big size with all required storages, servers, UPS, Work Station, Preloaded software, Pre-loaded pipeline route/geographical data. HMI Screens etc. A point to multipoint low band width radio connection will serve the purpose, where the entire distribution network will get connected to the CCR. Where ever required some FOC network can also be implemented if required and volume of data transmission is high in nature. From the work location real-time updation by respective field engineer will update the master data thru the radio network or GPRS enabled smart mobile phone where an application will have to be developed to connect to Servers and HMI monitors. All networks and servers to be made accessible through LAN/ WAN / WEB / GPRS Network. 3.1. Database creation and Server Management The following steps to be followed to create the master database. The Pipeline Data management system based on Engineering and GIS to be developed by experienced specialist vendor. The entire field facilities and pipeline network to be mapped using Satellite images procured for the Field development area. A master database of entire pipeline information will be created using GIS tools. The master database to include detailed facility layouts, pipeline alignment drawings, facility location database, support facility information, ROU information, linked technical specifications, sparing schedule, maintenance schedule, and pigging schedule. The Following minimum features will be provided in the Engineering Cum GIS based pipeline database management system:  Drawing release status  ROU application status  ROW application status  Revenue Survey details  Other lands acquisition status  Land over/ROU Compensation payment Status  Soil status  Excavation Status  Pipeline/Cable /other material arrival Status  Joints Welding Progress
  • 4. SCS & GIS Enabled Project Management System for Development and Implementation Phase of Gas Distribution Project http://www.iaeme.com/IJMET/index.asp 159 editor@iaeme.com  Lowering Status  Testing status and Reports  Backfilling Status  Pigging schedules  Customised report generation.  Accessibility to all relevant information / documents / drawings etc. The proposed method is having majorly two parts called 1. Geographical Information System (GIS) and 2. Supervisory Control System (SCS) 3.1.1. Geographical Information System This is Software supplied by various companies around the world which helps in viewing and managing the integrated pipeline network. This Spatially enabled GIS Model manages the all pipeline attributes in centre line data with ensuring accuracy in data. GIS system meets all the general and minimum requirement such as Database set up, survey data uploading and reference, data exchange between various stakeholders, Alignment sheet Generations, Crossing drawings, Reference drawings, MTO Preparation etc. As this stores High Resolution Satellite imagery, data accuracy will be attained. The following Steps to be followed  Taking the High Resolution Satellite Imageries and updating in server  Verification of the Survey data o Verification with respect to Spheroid/Ellipsoid Parameters o Verification with respect to topological and topographical parameters o Verification by superimposing Survey data with HRSIs  Uploading and updating the database server  Carrying out detailed Engineering works With this the following minimum engineering deliverables can be extracted  Integrated Alignment Sheets  Crossing Drawings  Pipeline, Electrical and FOC standard drawings  Integrated MTOs for various disciplines The following are the some of the important survey data which may be required to update the database  Land base information  Feed Data  Detailed Route Survey information  Topographical Survey information  Ground Profile data  Population Density Index
  • 5. G. Dhamodaran and R. J. Golden Ranjith http://www.iaeme.com/IJMET/index.asp 160 editor@iaeme.com Flowchart for Database Setup and utilizing for Detailed Engineering Figure 1 Flow Chart for GIS Data base setup, updation and Detailed Engineering •DataBase Setup Basic Data •HRSI •AdminPrivilages •LandBase Information •FeedData Survey •Route Survey Infomation •Topographicla Survey Information •Ground Profile Data •Population Density Index Update Data Process Integrated Alignment Sheets Standard / Reference Drawings MTOs
  • 6. SCS & GIS Enabled Project Management System for Development and Implementation Phase of Gas Distribution Project http://www.iaeme.com/IJMET/index.asp 161 editor@iaeme.com Some of the major Advantages of using Geographical Information System  Efforts required to manage records can be minimised  Efforts require to communicate with increased noumbers of stake holders can be minimised  Multiple data editors at one time can be increased with respect to size of the Project  Ease of Producing the Reports  Ease of Producing Engineering Deliverables  Visualisation by viewing the status in Web browser  Integrated link between Construction Contractor, Owner, Project Manager, Financing institute, Surveyors, engineers, Inspectors, Detail engineering Contractor, ROU Agents, Environmental Team, CSR Team etc.  Ease maintenance of E-log book  Viewing and Referring Survey shots whenever required  Permissions Status  Ease MIS Reporting  Crossing and legal permission Status  Accuracy in Data  Integrity in data  Efficient Project Management  Developing various Databases  Production of various Auto Cad Drawings  Linking Graphics to tables an d databases  Editing As built drawings  Tracing of Joints and status reporting  Uniqueness in data management  Aligning all project managers in one approach  Ease interface with SQL Servers  Ease in exporting graphics in required format  Generations of notification and alerts on daily updates and pending works 3.1.2. Supervisory Control System The Central Control Room will be manned 24/7 and monitors the field parameters and equipment status & alarms. The Control Room Operators will be responsible for alerting the Filed Construction team for any Follow up actions and control actions to be taken at any of the field sites visa viz. Trunk lines, Branch lines, Lateral Lines, Field Lines or any other Permanent facilities oft the Project This control Room will be Equipped with the large Video cum HMI Monitor where the entire Pipeline network will be visually seen and the required portions can be enlarged and seen. With the help of any suitable application thru the GPS frequency Signal site construction progress will be updated in the master data which will be of real-time updation. Network system required to transmit the data could be either LAN/WIFI/Wireless technology or any other thing. The follow up actions can be automatically or manually sent to the required portion or the project manager.
  • 7. G. Dhamodaran and R. J. Golden Ranjith http://www.iaeme.com/IJMET/index.asp 162 editor@iaeme.com Remote Terminal Units(RTU) can be installed and important nodal points thru which the data can be communicated to the th central control Room. These RTUs will be collecting data from the Various facilities and pipeline segments and transfer them to the Central Control Room. The instrumentation & automation data from the Well will require low bandwidth; data polling will be on real-time basis. A point to multi point microwave radio networks will meet the requirement. There may be other low band width requirements for IT voice network and for Security Automation. These can also be connected through the same Radio network 3.2. Various WBS and Activities to get covered With the implementation of this SCS the following WBS may be getting covered along with applicable Activities Engineering- Detail Engineering Status, MTOs, Alignment Sheet Revision Status, Schedule of releasing the other documents related to the particular section or part of the pipeline or facilities. Procurement- MR Status, RFQ Status, Material delivery status, Material shifting status to erection location Legal- Permission Status, Land Acquisition Status, Crossing Details, ROU Application Status, ROW Status, Compensation Status, Local agitation details Construction- Excavation, Grading Bedding, Stringing, Joints welding, Lowering, Testing, Back filling, Restoration
  • 8. SCS & GIS Enabled Project Management System for Development and Implementation Phase of Gas Distribution Project http://www.iaeme.com/IJMET/index.asp 163 editor@iaeme.com Other these, there are many other options can also be inducted in the Engineering- Cum-GIS based construction data base. 3.3. Options to be made available in menu With the implementation of this SCS the following WBS may be getting covered along with applicable Activities. The following table shows the list of options that may be required as a minimum to continue the construction 3.3.1. Engineering Phase Table 1 Various Menu options required during Engineering Phase Phase Location Entity Activity Progress Time line Document Quantity Status Level 1 Level 2 Level 3 Level 4 Level 5 Sub Level-1 Sub level- 2 Sub level-3 Engineeri ng Trunk Line/ Lateral line/ Branch line/ Flow Line/ From Chainage/ To Chainage Alignment sheet Preparat ion Started Target to Start View Procurem ent Village/ Survey Number/ Land Owner MTO Draft Release In progress Target to Finish Download Legal other Engineerin g Deliverable approval Complete d Target to Release Retrive Constructi on Release Approved Extract Final Release Sent for Approval Upload Revised Comment Released Menu such as status of the all deliverables, their time line data can be fed. Also the quantity status also can be included either in terms of numbers or in terms of percentages. In order to track the engineering deliverables the options like comment, upload etc can now be included.
  • 9. G. Dhamodaran and R. J. Golden Ranjith http://www.iaeme.com/IJMET/index.asp 164 editor@iaeme.com Concern area manager/project engineer can upload the status immediately either thru eh Android enabled application in smartphone or any other means of system inclusion. 3.3.2. Procurement Phase Table 2 Various Menu options required during Procurement Phase Phase Location Entity Activity Progress Time line Document Quantity Stat us Level 1 Level 2 Level 3 Level 4 Level 5 Sub Level- 1 Sub level- 2 Sub level -3 Engineering Trunk Line/ Lateral line/ Branch line/ Flow Line/ From Chainage/ To Chainage MR Preparation Started Target to Start View Procurement Village/ Survey Number/ Land Owner RFQ Draft Release In progress Target to Finish Download Legal Delivery approval Completed Target to Release Retrieve Construction Release Approved Extract Final Release Sent for Approval Upload Published Revised Comment Bids Received Released Check Evaluated Ordered Received
  • 10. SCS & GIS Enabled Project Management System for Development and Implementation Phase of Gas Distribution Project http://www.iaeme.com/IJMET/index.asp 165 editor@iaeme.com Procurement documents like Material Requisition, RFQ, Material Delivery can be tracked and status can be retrieved by the relevance users. The Procurement team to update the status as and when happen in real time basis. The Approval cycle of time and Technical Bid evaluation details and Technical Recommendation details can also be included if required. 3.3.3. Legal Phase Table 3 Various Menu options required during Legal Phase Phase Location Entity Activity Progress Time line Document Quantit y Status Level 1 Level 2 Level 3 Level 4 Level 5 Sub Level- 1 Sub level- 2 Sub level-3 Engineering Trunk Line/ Lateral line/ Branch line/ Flow Line/ From Chainage/ To Chainage Permission Preparati on Started Target to Start View Procurement Village/ Survey Number/ Land Owner Crossing Draft Release In progress Target to Finish Download Legal LAQ approval Complete d Target to Releas e Retrieve Construction ROU Release Approved Extract ROW Final Release Sent for Approval Upload Agitation Submitte d Revised Comment Tracked Released Check Corrected Paid Received DD Sent Fee Payment Various legal issues like permissions from various boards and departments of Government bodies can be tracked in this SCS System. Right of Use and Right of Way related progress etc can be traced in this. Also the Team who is co ordination with Legal departments to update the relevant documents on regular intervels.
  • 11. G. Dhamodaran and R. J. Golden Ranjith http://www.iaeme.com/IJMET/index.asp 166 editor@iaeme.com Payments status to various applications can also be tracked with this and the local agitations and related FIRS can also be tracked and accordingly further front can be generated. 3.3.4. Construction Phase Table 4 Various Menu options required during Construction Phase Phase Location Entity Activity Progress Time line Document Quantity Status Level 1 Level 2 Level 3 Level 4 Level 5 Sub Level- 1 Sub level- 2 Sub level-3 Engineering Trunk Line/ Lateral line/ Branch line/ Flow Line/ From Chainage/ To Chainage Trench Grading Started Target to Start View Procurement Village/ Survey Number/ Land Owner Pipeline Excavation In progress Target to Finish Download Legal Cable Bedding Completed Target to Release Retrieve Construction Stringing Extract Welding Upload Lowering Comment Testing Check Back filling Restorations During Construction phases, various construction activities status can be traced centrally like Excavation, bedding, laying, welding, lowering, testing, back filling etc. Further front can be generated from the Central Control Room. 4. DATA FEEDING, UPDATING, PROCESSING AND MANAGEMENT. Central Construction Control Centre should be manned for all 24x7 days. There will be a monitor where the entire Gas distribution network will be visible. Wherever
  • 12. SCS & GIS Enabled Project Management System for Development and Implementation Phase of Gas Distribution Project http://www.iaeme.com/IJMET/index.asp 167 editor@iaeme.com required, the particular portions can be zoomed and edited. GIS images of the Gas distribution network area have to be preloaded into the system. Individual area managers/construction heads or the Field engineers will be provided wither with laptop or Smartphone with application. Accesses have to be provided to the respective construction man to update the current happenings. With the real-time updation, the Person monitoring the data at CCCC can easily generate the front and send to the succeeding persons or to the same person if he is alone to carry out the succeeding activities. Example: Operator takes out the locations where all testing completed and backfilling is balance. His output will be in terms of Line number/Village name/Trunk line/Feed line / Chainage details etc. This list Operator will be sending to the Civil co- ordinator to initiate the backfilling works. Figure 2 Schematic drawing of concept of ‘Central Construction Control Centre’ Central Construction Control Centre
  • 13. G. Dhamodaran and R. J. Golden Ranjith http://www.iaeme.com/IJMET/index.asp 168 editor@iaeme.com 5. RESULTS This kind id system is used in operation phase for many projects as “Supervisory Control System and Data Acquisition”. Our Aim is to extend that kind of Central project Control Concepts which will increase the efficiency of the Project management. 6. DISCUSSION 6.1. Advantages of using this system This system has more advantages like, a. Efficient Project management b. Better revision management in drawings and documents c. Complete reliability on the work progress and front d. Accurate reports e. Provides clear guidelines for planning, and forecasting f. Provides access to multiple users so that many people can work in same time g. Tracing facility of materials, reports, documents history etc. h. Helps in generating many data bases. i. Controls Duplication works j. Continues expedition from the Site team k. Single Point Co-ordination system which minimise the error. l. Completely provides real time tracking of the progress m. Generates Front for almost all disciplines included in the scope n. Minimal investment and no major operational cost o. Less Manpower requirement 7. CONCLUSION As this reduces lot of man-hour wastages and time this method can be encouraged for many of the Pipeline projects like Gas Distribution Projects. ACKNOWLEDGEMENTS Informally many other forms the same concept is being used partially in many of the Gas distribution Projects. With little improvement and value addition will yield good results in terms of the efficient Project Management. REFERENCES [1] Al-Momani, A. H. Construction delay: A quantitative analysis. International Journal of ProjectManagement, 18(1), 2000. [2] Ammar, M. A. and Mohieldin, Y. A. Resource constrained project scheduling using simulation. Construction Management and Economics, 2002. [3] Assaf, S. A. and Al-Hejji, S. Causes of delay in large construction projects. International Journal of Project Management, 2006. [4] Chan, A. P. C., Scott, D. and Chan, A. P. L. Factors affecting the success of a construction project. Journal of Construction Engineering and Management, 2004. [5] Graham, G. E., Maxwell, D. A. and Vallone, A. How to Optimize Gas Pipeline Networks. Pipeline Industry, June, 1971. 41–43. [6] Martch, H. B. and N. J. McCall. Optimization of the Design and Operation of Natural Gas Pipeline Systems. Paper No. SPE 4006, Society of Petroleum Engineers of AIME, 1972.
  • 14. SCS & GIS Enabled Project Management System for Development and Implementation Phase of Gas Distribution Project http://www.iaeme.com/IJMET/index.asp 169 editor@iaeme.com [7] Flanigan, O. Constrained Derivatives in Natural Gas Pipeline System Optimization. Journal of Petroleum Technology, May, 1972, pp. 549. [8] Mah, R. S. H. and Schacham, M. Pipeline Network Design and Synthesis. Advances in Chemical Engineering, 10, 1978. [9] Cheesman, A. P. How to Optimize Gas Pipeline Design by Computer. Oil and Gas Journal, 69(51), December 20, 1971, pp. 64. [10] Cheesman, A. P. Understanding Origin of Pressure is a Key to Better Well Planning. Oil and Gas Journal, 69(46), November 15, 1971, pp. 146. [11] Edgar, T. F., Himmelblau, D. M. and Bickel, T. C. Optimal Design of Gas Transmission Network. Society of Petroleum Engineering Journal, 30, 1978, pp. 96. [12] Hasan, H. S. and Dr. Ramesh Babu, P. SCS Analysis and Control of Mobile Robot for Pipe Line Inspection. International Journal of Mechanical Engineering and Technology, 4(5), 2013, pp. 01–09. [13] Olorunniwo, F. O. A Methodology for Optimal Design and Capacity Expansion planning of Natural Gas Transmission Networks. Ph.D Dissertation, The University of Texas Austin, May, 1981 [14] Wong, P. J. and Larson, R. E. Optimization of natural gas pipeline systems via dynamic programming. IEEE Trans. Auto. Control, AC-13(5), October 1968, pp. 475–481. [15] Harris, R. B. and Ioannou, P. G. Scheduling projects with repeating activities. Journal of Construction Engineering and Management, 1998.