SlideShare a Scribd company logo
Hoover dam bypass bridge
Table of contents
❖ introduction
❖ Pre-feasibility
❖ Project conception
❖ Project need & objective
❖ Project preparation
❖ Environmental impact assessment
❖ Technical assessment
❖ Financial information
❖ Construction
❖ Operation & maintenance
❖ Transfer of the project
Introduction
❖ Hoover dam bypass is a part of 4 miles long
highway connecting Arizona and Nevada
interstates.
❖ The new 1900 ft. (571 m) Hoover dam bypass
bridge spans the black canyon at about 1500 ft.
(457.2m) south of the Hoover Dam, connecting
the Arizona and Nevada approach highways
nearly 900 ft.
❖ The bridge carries four lanes of traffic and
sidewalk.
❖ It is a composite steel concrete deck arch bridge
with main span of 1060 ft. (323m). The arch rib is
made of reinforce concrete.
❖ It is the second largest concrete arch bridge span
in the world. The bride is owned by Arizona DOT
and Nevada DOT.
Pre-feasibility stage
❖ Project conception
❖ “Colorado river bridge project management team” came into place by joint decision of
Navida and Arizona state department of transportation.
Project Need and objective
Potential problems identified
❖ Accidents
❖ Sharp turns
❖ Limited sight distances
❖ No adequate room for
disabled cars
❖ Speed was as low as 15MPH
against initial speed of 50MPH
❖ inadequate road capacity
❖ Less travel times
Objective of the project
• To minimise the potential for traffic accidents
• To remove the bottlenecks to interstate and international commerce to reduce traffic
congested
• To reduce travel time
• To protect Hoover dam employees, visitors, equipment, power generations capabilities
• To provide safe and improved conditions for the maintenance and operation of Hoover
dam
Project Preparation activities
After initial surveys at this point it was decided to carryout two important studies in detail
❖ Engineering & technical aspect
❖ Environmental impact assessment
Environmental impact assessment
studies
• Air quality analysis
• Noise analysis
• Visual resources analysis
• Biological assessments
• Archaeological resources survey
Project Design
The requirement for the design of the bridge was both
technical and aesthetics of the bridge, the most important
requirement in the design would be design load which in
this case was 180 metric tons. Various designs were
studied some of them were as follows.
After considering the design criteria for the bridge the
team selected composite steel and concrete type of
bridge that met all the design criteria.
Financial information
Contract contractor value
Arizona Approach
Mont/VASTCO $22M
Navida Approach
Edward Kraemer & sons $30M
River bridge
Obayashi/Mitsubishi $114M
Paving
Freshener & Las Vegas paving $15M
Total $181M
Construction
❖ Phase 1. Building connection between
Colorado Bridge and U.S 93 this included 4
lanes of roadway
❖ Phase2. This was from Navida side, The
Roadway from the project start to the
Colorado Bridge, started in 2003 and finished
in 2005 ahead of time by 2 months.
❖ Phase3. The contractor constructed 2.11 miles of new four-lane highway
alignment including six new bridges, a new traffic interchange at US 93 near the
Hacienda Casino, retaining walls, wildlife crossing.
❖ Phase4. Asphalt paving of the entire 4 miles from Arizona to Nevada side to the
project. This was complete in 2010.
Operation & maintenance
The operation and maintenance is either side of
the bypass bridge done by Arizona state DOT
and Nevada State DOT. The aim of the
maintenance is to insure safety, carryout visual
and technical inspection of the bridge, to
maintain smooth traffic flow, repairs to the
bridges, road pavements. The funding for the
same comes from the Nevada and Arizona
state departments of transportations.
Achievement
❖ The project completion on budget was a great success story although it went slightly
away from the schedule. The project primary purpose and objective of reduction in
traffic congestion was achieved and this facilitated smooth traffic.
❖ The travel time of the existing road was 16.5minutes while this newly construction
facility reduced it to 6 minutes, a total of 10 minutes were saved. This also increased
speed. The environmental impact assessment helped reduce and mitigate the problems
of environment and also wild life crossing between different points.
Project Schedule
Project Transfer
The twin-rib arch of the Colorado River
Bridge was completed in August 2009 and
the bridge columns were constructed in
November 2009. Construction of the entire
bypass was completed in September 2010. It
was celebrated by making grand ceremony.
The bypass opened to traffic a month later in
October 2010.
Learning
This project helped me a lot in understanding the complexity of the infrastructural project
development, in this exercise I learned various surveys required in each stage of the project,
the project coordination, construction and impact analysis on the environment. Every project
before comes into existence must go through a logical process, I learned practically what
process were involved in this project.
Conclusion
The Hoover Dam, Bypass Colorado River Bridge was an extreme challenge, due to the
structure itself, advanced construction schemes, and the surrounding environment. The
effort of all personnel involved made the incredible graceful bridge into reality. The Hoover
dam bypass Colorado River Bridge was completed in 2010, The Bridge was opened to
traffic on October 2010. The Project resulted iconic landmark structure set in the Colorado
River’s black canyon with a view to historic Hoover Dam. Ten minutes reduction time was
another achievement followed by reduction in traffic congestion and accidents.
References
1. http://energy.gov/sites/prod/files/nepapub/nepa_documents/RedDont/EA-1478-FEA-2003.pdf
2. http://www.roadtraffic-technology.com/projects/hoover-bypass/
3. https://books.google.co.in/books?id=jJ3MBQAAQBAJ&pg=PA1282&dq=hoover+dam+bridge&hl=en&sa=X&ved=0CCIQ6AEwAmoVChMI4
4. http://www.roadtraffic-technology.com/projects/hoover-bypass/hoover-bypass6.html
5. http://www.jpci.or.jp/NR/pdf/40.pdf
6. http://design.transportation.org/Documents/SCOD,Hammontree,FHWA,HooverDamBypass.pdf
7. http://www.klbconstruction.com/pdf/making_history_near_hoover_dam.pdf
8. http://www.crma.ac.th/histdept/journal/jour-49/49-jour-12.pdf
9. http://transportation.ky.gov/SASHTO/The%20Mike%20OCallaghan%20Pat%20Tillman%20Memorial%20Bridge.pdf
10. http://mcedc.colorado.edu/sites/default/files/FinalHooverDamBypass.pdf
11. http://www.hpcbridgeviews.com/i63/Printable.pdf
12. http://www.atkinsglobal.com/en-gb/projects/hoover-dam-bypass
13. http://nepis.epa.gov/Exe/ZyNET.exe/20005FMQ.TXT?ZyActionD=ZyDocument&Client=EPA&Index=2000+Thru+2005&Docs=&Query=&T

More Related Content

What's hot

Konsep Nazam
Konsep NazamKonsep Nazam
Konsep Nazam
ArifahAzlanShah2
 
Modul penuh hidrologi
Modul penuh   hidrologiModul penuh   hidrologi
Modul penuh hidrologi
Asmawi Abdullah
 
Menterjemah fungsi ayat
Menterjemah fungsi ayatMenterjemah fungsi ayat
Menterjemah fungsi ayatMaheram Ahmad
 
Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)
Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)
Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)
Thanushah Soniyasee
 
Minggu 14 (sastera) menjelaskan rangka novel
Minggu 14 (sastera) menjelaskan rangka novelMinggu 14 (sastera) menjelaskan rangka novel
Minggu 14 (sastera) menjelaskan rangka novelShamimi Jamudin
 
Ko kurikulum dan rekreasi
Ko kurikulum dan rekreasiKo kurikulum dan rekreasi
Ko kurikulum dan rekreasiZarina Arz
 
Nota psikoanalitik
Nota psikoanalitikNota psikoanalitik
Nota psikoanalitikJohn Tan
 
Hanyutan benua
Hanyutan benuaHanyutan benua
Hanyutan benua
Dhaarshini1129
 

What's hot (12)

Konsep Nazam
Konsep NazamKonsep Nazam
Konsep Nazam
 
Modul penuh hidrologi
Modul penuh   hidrologiModul penuh   hidrologi
Modul penuh hidrologi
 
Menterjemah fungsi ayat
Menterjemah fungsi ayatMenterjemah fungsi ayat
Menterjemah fungsi ayat
 
Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)
Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)
Bab 12 Bahasa Melayu Penggal 2 Tingkatan 6 (thanushah)
 
Minggu 14 (sastera) menjelaskan rangka novel
Minggu 14 (sastera) menjelaskan rangka novelMinggu 14 (sastera) menjelaskan rangka novel
Minggu 14 (sastera) menjelaskan rangka novel
 
Ko kurikulum dan rekreasi
Ko kurikulum dan rekreasiKo kurikulum dan rekreasi
Ko kurikulum dan rekreasi
 
Contoh soalan fonetik pgsr
Contoh soalan fonetik pgsrContoh soalan fonetik pgsr
Contoh soalan fonetik pgsr
 
Nota psikoanalitik
Nota psikoanalitikNota psikoanalitik
Nota psikoanalitik
 
Ayat
AyatAyat
Ayat
 
Hanyutan benua
Hanyutan benuaHanyutan benua
Hanyutan benua
 
Morfologi
MorfologiMorfologi
Morfologi
 
Penyediaan larutan
Penyediaan larutanPenyediaan larutan
Penyediaan larutan
 

Viewers also liked

Hoover dam bypass_bridge2
Hoover dam bypass_bridge2Hoover dam bypass_bridge2
Hoover dam bypass_bridge2George Martin
 
Note for Hoover Dam
Note for Hoover DamNote for Hoover Dam
Note for Hoover Dam
Lengkengs
 
The hoover dam 3
The hoover dam 3The hoover dam 3
The hoover dam 3l yingling
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover damJasmine Tung
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
Lengkengs
 
Hoover Dam by John Howard
Hoover Dam by John HowardHoover Dam by John Howard
Hoover Dam by John Howard
geographystudents
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homeworkmrzislion
 
Herbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumHerbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumAidan Brady
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vic
mrs_murphy_ncssm
 
HOOVER DAM DOC
HOOVER DAM DOCHOOVER DAM DOC
HOOVER DAM DOC
Karan Kaushal
 
Grace Cathedral - San Francisco California
Grace Cathedral  - San Francisco CaliforniaGrace Cathedral  - San Francisco California
Grace Cathedral - San Francisco California
Steven Cantler
 
Hoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaHoover Dam - Arizona & Nevada
Hoover Dam - Arizona & Nevada
Steven Cantler
 
Hoover Dam
Hoover DamHoover Dam
Hoover Dam
Hussain Fahmy
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vicmrs_murphy_ncssm
 
4M Presentation - E-learning platform
4M Presentation - E-learning platform4M Presentation - E-learning platform
4M Presentation - E-learning platform
Proxicon Ltd
 
Herbert Hoover
Herbert HooverHerbert Hoover
Herbert Hoover
guestaf6098
 
Hoover Dam
Hoover DamHoover Dam
Hoover Dam
Naushad Meedin
 

Viewers also liked (20)

Hoover dam bypass_bridge2
Hoover dam bypass_bridge2Hoover dam bypass_bridge2
Hoover dam bypass_bridge2
 
Note for Hoover Dam
Note for Hoover DamNote for Hoover Dam
Note for Hoover Dam
 
The hoover dam 3
The hoover dam 3The hoover dam 3
The hoover dam 3
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover dam
 
Hoover dam
Hoover damHoover dam
Hoover dam
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
 
Hoover
HooverHoover
Hoover
 
Hoover Dam by John Howard
Hoover Dam by John HowardHoover Dam by John Howard
Hoover Dam by John Howard
 
Women
WomenWomen
Women
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homework
 
Herbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumHerbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-Museum
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vic
 
HOOVER DAM DOC
HOOVER DAM DOCHOOVER DAM DOC
HOOVER DAM DOC
 
Grace Cathedral - San Francisco California
Grace Cathedral  - San Francisco CaliforniaGrace Cathedral  - San Francisco California
Grace Cathedral - San Francisco California
 
Hoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaHoover Dam - Arizona & Nevada
Hoover Dam - Arizona & Nevada
 
Hoover Dam
Hoover DamHoover Dam
Hoover Dam
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vic
 
4M Presentation - E-learning platform
4M Presentation - E-learning platform4M Presentation - E-learning platform
4M Presentation - E-learning platform
 
Herbert Hoover
Herbert HooverHerbert Hoover
Herbert Hoover
 
Hoover Dam
Hoover DamHoover Dam
Hoover Dam
 

Similar to Hoover dam bypass bridge

Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
Soumalya Bag
 
APWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann ArborAPWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann Arbor
OHM Advisors
 
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the Year
OHM Advisors
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
Devore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalDevore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalvvchamber123
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro PE
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017
Eric Boothman
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
Lars Forslöf
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Fairfax County
 
India's preparedness for IWT
India's preparedness for IWTIndia's preparedness for IWT
India's preparedness for IWT
cmmindia2017
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream Restoration
Fairfax County
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
Fairfax County
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Timothy Nikolai
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration Project
Fairfax County
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Fairfax County
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACECSDES
 

Similar to Hoover dam bypass bridge (20)

Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
APWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann ArborAPWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann Arbor
 
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the Year
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
Devore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalDevore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 final
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
Canal City - Poster-
Canal City - Poster-Canal City - Poster-
Canal City - Poster-
 
Virginia
VirginiaVirginia
Virginia
 
India's preparedness for IWT
India's preparedness for IWTIndia's preparedness for IWT
India's preparedness for IWT
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream Restoration
 
Theodor Nicolas Master
Theodor Nicolas MasterTheodor Nicolas Master
Theodor Nicolas Master
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration Project
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence Awards
 

Recently uploaded

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

Hoover dam bypass bridge

  • 2. Table of contents ❖ introduction ❖ Pre-feasibility ❖ Project conception ❖ Project need & objective ❖ Project preparation ❖ Environmental impact assessment ❖ Technical assessment ❖ Financial information ❖ Construction ❖ Operation & maintenance ❖ Transfer of the project
  • 3. Introduction ❖ Hoover dam bypass is a part of 4 miles long highway connecting Arizona and Nevada interstates. ❖ The new 1900 ft. (571 m) Hoover dam bypass bridge spans the black canyon at about 1500 ft. (457.2m) south of the Hoover Dam, connecting the Arizona and Nevada approach highways nearly 900 ft. ❖ The bridge carries four lanes of traffic and sidewalk. ❖ It is a composite steel concrete deck arch bridge with main span of 1060 ft. (323m). The arch rib is made of reinforce concrete. ❖ It is the second largest concrete arch bridge span in the world. The bride is owned by Arizona DOT and Nevada DOT.
  • 4. Pre-feasibility stage ❖ Project conception ❖ “Colorado river bridge project management team” came into place by joint decision of Navida and Arizona state department of transportation.
  • 5. Project Need and objective Potential problems identified ❖ Accidents ❖ Sharp turns ❖ Limited sight distances ❖ No adequate room for disabled cars ❖ Speed was as low as 15MPH against initial speed of 50MPH ❖ inadequate road capacity ❖ Less travel times
  • 6. Objective of the project • To minimise the potential for traffic accidents • To remove the bottlenecks to interstate and international commerce to reduce traffic congested • To reduce travel time • To protect Hoover dam employees, visitors, equipment, power generations capabilities • To provide safe and improved conditions for the maintenance and operation of Hoover dam Project Preparation activities After initial surveys at this point it was decided to carryout two important studies in detail ❖ Engineering & technical aspect ❖ Environmental impact assessment
  • 7. Environmental impact assessment studies • Air quality analysis • Noise analysis • Visual resources analysis • Biological assessments • Archaeological resources survey Project Design The requirement for the design of the bridge was both technical and aesthetics of the bridge, the most important requirement in the design would be design load which in this case was 180 metric tons. Various designs were studied some of them were as follows. After considering the design criteria for the bridge the team selected composite steel and concrete type of bridge that met all the design criteria.
  • 8. Financial information Contract contractor value Arizona Approach Mont/VASTCO $22M Navida Approach Edward Kraemer & sons $30M River bridge Obayashi/Mitsubishi $114M Paving Freshener & Las Vegas paving $15M Total $181M
  • 9. Construction ❖ Phase 1. Building connection between Colorado Bridge and U.S 93 this included 4 lanes of roadway ❖ Phase2. This was from Navida side, The Roadway from the project start to the Colorado Bridge, started in 2003 and finished in 2005 ahead of time by 2 months. ❖ Phase3. The contractor constructed 2.11 miles of new four-lane highway alignment including six new bridges, a new traffic interchange at US 93 near the Hacienda Casino, retaining walls, wildlife crossing. ❖ Phase4. Asphalt paving of the entire 4 miles from Arizona to Nevada side to the project. This was complete in 2010.
  • 10. Operation & maintenance The operation and maintenance is either side of the bypass bridge done by Arizona state DOT and Nevada State DOT. The aim of the maintenance is to insure safety, carryout visual and technical inspection of the bridge, to maintain smooth traffic flow, repairs to the bridges, road pavements. The funding for the same comes from the Nevada and Arizona state departments of transportations.
  • 11. Achievement ❖ The project completion on budget was a great success story although it went slightly away from the schedule. The project primary purpose and objective of reduction in traffic congestion was achieved and this facilitated smooth traffic. ❖ The travel time of the existing road was 16.5minutes while this newly construction facility reduced it to 6 minutes, a total of 10 minutes were saved. This also increased speed. The environmental impact assessment helped reduce and mitigate the problems of environment and also wild life crossing between different points.
  • 13. Project Transfer The twin-rib arch of the Colorado River Bridge was completed in August 2009 and the bridge columns were constructed in November 2009. Construction of the entire bypass was completed in September 2010. It was celebrated by making grand ceremony. The bypass opened to traffic a month later in October 2010.
  • 14. Learning This project helped me a lot in understanding the complexity of the infrastructural project development, in this exercise I learned various surveys required in each stage of the project, the project coordination, construction and impact analysis on the environment. Every project before comes into existence must go through a logical process, I learned practically what process were involved in this project. Conclusion The Hoover Dam, Bypass Colorado River Bridge was an extreme challenge, due to the structure itself, advanced construction schemes, and the surrounding environment. The effort of all personnel involved made the incredible graceful bridge into reality. The Hoover dam bypass Colorado River Bridge was completed in 2010, The Bridge was opened to traffic on October 2010. The Project resulted iconic landmark structure set in the Colorado River’s black canyon with a view to historic Hoover Dam. Ten minutes reduction time was another achievement followed by reduction in traffic congestion and accidents.
  • 15. References 1. http://energy.gov/sites/prod/files/nepapub/nepa_documents/RedDont/EA-1478-FEA-2003.pdf 2. http://www.roadtraffic-technology.com/projects/hoover-bypass/ 3. https://books.google.co.in/books?id=jJ3MBQAAQBAJ&pg=PA1282&dq=hoover+dam+bridge&hl=en&sa=X&ved=0CCIQ6AEwAmoVChMI4 4. http://www.roadtraffic-technology.com/projects/hoover-bypass/hoover-bypass6.html 5. http://www.jpci.or.jp/NR/pdf/40.pdf 6. http://design.transportation.org/Documents/SCOD,Hammontree,FHWA,HooverDamBypass.pdf 7. http://www.klbconstruction.com/pdf/making_history_near_hoover_dam.pdf 8. http://www.crma.ac.th/histdept/journal/jour-49/49-jour-12.pdf 9. http://transportation.ky.gov/SASHTO/The%20Mike%20OCallaghan%20Pat%20Tillman%20Memorial%20Bridge.pdf 10. http://mcedc.colorado.edu/sites/default/files/FinalHooverDamBypass.pdf 11. http://www.hpcbridgeviews.com/i63/Printable.pdf 12. http://www.atkinsglobal.com/en-gb/projects/hoover-dam-bypass 13. http://nepis.epa.gov/Exe/ZyNET.exe/20005FMQ.TXT?ZyActionD=ZyDocument&Client=EPA&Index=2000+Thru+2005&Docs=&Query=&T